Concrete reservoir wall water distribution port non-cut-off trepanning installation construction method

By installing a water-isolating cofferdam and outriggers under the wall of the concrete reservoir, and installing a non-stop water outlet opening, the problem of water interruption in construction in the existing technology is solved, and the water resource utilization rate and construction safety are improved. It ensures the structural stability and waterproof performance of the water outlet.

CN118727787APending Publication Date: 2024-10-01CHINA CONSTR EIGHTH BUREAU DEV & CONSTR CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411036563.6
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-31
Publication Date
2024-10-01

AI Technical Summary

Technical Problem

The existing method of installing a water diverter by opening holes in the wall of a concrete reservoir requires stopping water, resulting in a long construction period, high costs and low water resource utilization, which affects water supply safety.

Method used

Using water-isolating cofferdams and outrigger fixing devices, the water-isolating cofferdams are installed underwater for precise positioning, cutting and concrete filling, ensuring that the pool structure is not damaged, achieving non-stop water construction, and improving construction safety through buffer devices and water-stop strips. resistance and waterproof performance.

Benefits of technology

It achieves non-stop water construction, reduces the impact of construction on water resources, improves water resource utilization, enhances construction safety and structural stability, and ensures the smoothness and waterproof performance of the cutting surface.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118727787A_ABST
    Figure CN118727787A_ABST
Patent Text Reader

Abstract

The invention provides a concrete reservoir wall water distribution port non-water-cut-off trepanning installation construction method, and belongs to the technical field of concrete reservoirs, the concrete reservoir wall water distribution port non-water-cut-off trepanning installation construction method comprises the following steps: processing a waterproof cofferdam, the waterproof cofferdam is a semicircular cylinder with an opening in the side wall; supporting legs are fixed on the bottom wall of the concrete reservoir towards the position of the water distribution port, the waterproof cofferdam is placed underwater, the waterproof cofferdam is fixed to the wall of the concrete reservoir through the supporting legs, and sealed water pumping is conducted; positioning and cutting a to-be-perforated part through an opening of the waterproof cofferdam, treating a cutting surface, and enabling the perforated part to be a water distribution opening part; an embedded part is installed at the water distribution opening, concrete is used for filling, and the embedded part is dismantled after the concrete is solidified; testing whether the water distribution port leaks or not, and if yes, continuing to process; if no leakage exists, the waterproof cofferdam is dismantled; on the premise that the reservoir is not damaged, water supply is not cut off, normal urban water supply is guaranteed, and the water resource utilization rate is increased.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of concrete water storage tanks, and in particular relates to a method for installing a non-water-stopping hole for a water diversion outlet on a concrete water storage tank wall. Background Art

[0002] During the operation of water storage buildings such as industrial plants, water plants, pumping stations, sewage treatment plants, and channels, according to the design requirements of later projects, it is necessary to drill holes in the walls of water storage concrete pools and install water diversion ports (gates, pipes, etc.) without stopping the water supply, so as to achieve the purpose of using the original pool to divert water to the continued construction project. The current method of drilling holes in the walls of water storage concrete pools in the market in my country is to first stop the water supply in sections, protect it with a flat steel cofferdam, then open the concrete, plug the leak, and finally remove the cofferdam to restore the water supply. Water plant pools and water supply channels involve the water supply safety of the people. Temporary water suspension due to construction will cause very large economic losses and social impacts. The current flat water retaining cofferdams not only have high processing, installation and removal costs, but also have a long construction period, which increases the temporary water suspension time. Summary of the invention

[0003] In view of this, the present invention provides a non-stop water-draining hole installation construction method for a water diversion outlet on a concrete water reservoir wall, which can perform water-draining operations without damaging the water reservoir, thereby ensuring normal water supply in the city and improving water resource utilization.

[0004] The present invention is achieved in that:

[0005] The present invention provides a method for installing a water diversion port on a concrete water storage tank wall without water shutoff, which comprises the following steps:

[0006] S01: Processing a water-proof cofferdam, wherein the water-proof cofferdam is a semicircular cylinder with an opening on the side wall, and the opening is located at the chord plate position;

[0007] S02: Fix the supporting legs on the bottom wall of the concrete water storage tank toward the water diversion port, place the water-proof cofferdam underwater, with the opening of the water-proof cofferdam facing the water diversion port where a hole needs to be opened, and fix the water-proof cofferdam on the wall of the concrete water storage tank through the supporting legs to seal and pump out water;

[0008] S03: Positioning and cutting the part to be opened through the water-proof cofferdam opening, and processing the cut surface, wherein the opening part is the water diversion part;

[0009] S04: Install embedded parts at the water diversion port, fill it with concrete, and remove the embedded parts after the concrete solidifies;

[0010] S05: Test whether there is leakage at the water diversion outlet. If there is leakage, continue to deal with it; if there is no leakage, remove the water-proof cofferdam.

[0011] The technical effects of the non-stop water-cutting hole installation construction method for the water diversion outlet on the wall of a concrete reservoir provided by the present invention are as follows: non-stop water-cutting operation, reduced impact: Traditional hole-cutting methods often require complete drainage, which affects the normal operation of the reservoir and the effective use of water resources. However, this method installs a water-proof cofferdam underwater and performs cutting operations under its protection, without draining the reservoir, which greatly reduces the impact of construction on the daily operation of the reservoir, realizes non-stop water-cutting construction, and improves the utilization efficiency of water resources;

[0012] Precise positioning and efficient cutting: The side wall opening of the water-proof cofferdam is located at the chord plate position, which can accurately align with the predetermined position of the water diversion port, facilitating high-precision positioning and cutting. This precise positioning reduces the risk of miscutting, improves construction efficiency, and also ensures the flatness of the cutting surface and the simplicity of subsequent processing;

[0013] Enhance construction safety and environmental protection: Use water-proof cofferdams and outrigger fixtures to effectively isolate the operation area, prevent the spread of debris generated by cutting operations, protect the water quality from pollution, and reduce the impact of construction on the surrounding environment. In addition, the use of water-proof cofferdams also improves the safety of underwater operations and ensures the safety of construction workers;

[0014] Optimize structural reinforcement and waterproofing: By installing embedded parts and filling concrete at the water diversion outlet, not only the structural stability of the new opening is strengthened, but also good waterproofing performance is ensured. This method effectively prevents leakage, extends the service life of the reservoir, and reduces maintenance costs;

[0015] Convenient for quality inspection and timely correction: Finally, a leakage test is carried out. If leakage is found, measures can be taken immediately to ensure the quality of construction. This instant inspection and correction mechanism improves the reliability and success rate of construction.

[0016] On the basis of the above technical solution, the construction method for installing a water diversion hole on the wall of a concrete water storage tank without water stopping of the present invention can also be improved as follows:

[0017] Among them, a support frame is provided on the outside of the water-proof cofferdam, and the support frame is a semicircular cylindrical structure for supporting and fixing the water-proof cofferdam. A waterstop is provided around the opening of the water-proof cofferdam, and the waterstop is used to prevent water from entering the water-proof cofferdam. One curved side of the water-proof cofferdam is two-layered, including an outer water-retaining cofferdam located on the outside and an inner water-retaining cofferdam located on the inside. The interior of the water-proof cofferdam is a sealed and impermeable structure, and is provided with a plurality of buffer devices for alleviating the curved surface of the water-proof cofferdam.

[0018] Furthermore, the buffer device is a steel bar arranged in an S shape inside, the top view of the steel bar is semicircular, and the steel bar is close to the external water-proof cofferdam.

[0019] Furthermore, the buffer device is a buffer component, including a first fixed point and a second slide fixed to the inner water retaining cofferdam, and a second fixed point and a first slide fixed to the outer water retaining cofferdam, the first slide and the second slide are provided with a slide groove, the slide groove is provided with a sliding point that can slide on the slide groove, the first transmission plate is X-shaped, one end of which is movably connected to the first fixed point and the sliding point on the second slide, and the other end is movably connected to one end of the X-shaped second transmission plate, the other end of the second transmission plate is movably connected to the second fixed point and the sliding point on the first slide, the intersection of the first transmission plate is rotatably connected to one end of the transmission cylinder, and the other end of the transmission cylinder is rotatably connected to the inner water retaining cofferdam.

[0020] The beneficial effects of adopting the above-mentioned improvement scheme are: it can more effectively absorb the impact energy generated by the cylinder at the end of the stroke, consume the kinetic energy of the cylinder by compressing the gas or liquid, reduce the movement speed of the cylinder, and finally achieve a smooth stop; this buffering method can significantly reduce the noise of mechanical impact and prevent damage to the cylinder and equipment;

[0021] The buffer device can significantly reduce the vibration generated during the movement of the cylinder through effective buffering measures. This is not only conducive to protecting the stable operation of the cylinder and equipment, but also can improve the stability and reliability of the entire system.

[0022] Furthermore, a plurality of fixing devices are provided at the contact points between the buffer device and the inner water-proof cofferdam and the outer water-proof cofferdam, for fixing the position of the buffer device, the fixing devices being a fixing hook fixed on the water-proof cofferdam and a fixing ring fixed on the buffer device, the fixing hook being a steel needle with an arc-shaped top, the fixing ring being an arched iron wire, and the bending direction of the second transmission plate being toward the opening direction of the first slide plate; the fixing hook comprising a first connecting portion, a first arc-shaped portion and an oblique connecting portion, the first connecting portion being a straight line and perpendicular to the surface of the water-proof cofferdam, the first arc-shaped portion being an arc-shaped and tangent to the first connecting portion and the oblique connecting portion, the oblique connecting portion being a straight line with the top facing the first connecting portion; the fixing ring comprising two second connecting portions and a second arc-shaped portion, the second connecting portion being a straight line and perpendicular to the water-proof cofferdam, the second arc-shaped portion being a semicircle and tangent to the second connecting portion, and the two second connecting portions being parallel to each other.

[0023] Furthermore, the support frame includes a longitudinal support frame and a transverse support frame. The support frame is located on two vertical edges of the water-proof cofferdam and is fixedly connected to the water-proof cofferdam. The transverse support frame is a horizontally placed C-shaped steel frame, located outside the curved side wall of the water-proof cofferdam and is fixedly connected to the water-proof cofferdam.

[0024] Further, the S02 comprises the following steps:

[0025] Fix the legs at the bottom of the concrete water storage tank, the legs are positioned toward one side of the water diversion port, and there are two legs, which are located at both sides of the water diversion port respectively;

[0026] Mark the hole location;

[0027] Put the water-proof cofferdam into the water, with the opening of the chord plate facing the water diversion port, and the water stop strip close to the side wall of the concrete water storage tank;

[0028] Use expansion screws to fix the side walls of the water-proof cofferdam concrete reservoir together, and further fix the water-proof cofferdam through the legs;

[0029] Pump out the water in the cofferdam cavity, let it stand for one hour, and then check the water seepage in the cofferdam cavity. If it is greater than the threshold, use legs to support the cofferdam and inflate the waterstop; if it is less than the threshold, use a suction pump to pump out the water.

[0030] Further, the S03 comprises the following steps:

[0031] Mark and locate the water outlet of the concrete water storage tank, and use a cutting machine to open the water outlet;

[0032] Roughen the cut surface of the water diversion port and make the cut surface rough;

[0033] The steel bars are implanted on the cutting surface, the distance between the top of the steel bars is greater than the radius of the water diversion mold, and the width of the steel bars is equal to the width of the cutting surface;

[0034] A concrete groove is cut in a reverse direction in the middle of the cutting surface, and a second water stop strip is placed in the groove. The second water stop strip is a water stop strip that expands when exposed to water.

[0035] The beneficial effects of adopting the above-mentioned improvement scheme are as follows: the splicing mechanism can ensure that it can maintain a stable structure under the action of water pressure; when the water level in the reservoir rises due to rainfall, workers can quickly splice these units together to form a temporary barrier, effectively blocking the water in the reservoir from flowing to the construction area;

[0036] This design not only improves construction efficiency but also ensures the safety of workers; through simple operations, workers can complete the construction of the barrier in a short time, thus avoiding construction delays and safety risks caused by rising water levels.

[0037] Furthermore, the protrusion is arc-shaped, trapezoidal or triangular.

[0038] Further, the S04 comprises the following steps:

[0039] Place the embedded parts on the cutting surface and fix them;

[0040] Placing round steel bars and embedded wires around the embedded parts to further secure the embedded parts;

[0041] A water stop ring is provided in the middle of the wire drawing;

[0042] Fill concrete between the embedded parts and the cut surface;

[0043] Remove the embedded parts after 12 hours.

[0044] Further, the S05 comprises the following steps:

[0045] Release water into the watertight cofferdam to the water level line and conduct a full water test. If there is leakage, pump out the seepage water in the watertight cofferdam and continue the treatment;

[0046] Retract the legs and remove the expansion bolts on the water-proof cofferdam;

[0047] The water-proof cofferdam is hoisted by a crane.

[0048] Furthermore, a splicing mechanism for extending the height of the water-proof cofferdam is provided above the cofferdam, and the splicing mechanism includes a cofferdam baffle, a first splicing portion is provided on the outer side of the bottom of the cofferdam baffle, and a second splicing portion is provided on the inner side of the top of the water-proof cofferdam. The cofferdam baffle is a semicircular cylinder, which is the same size as the water-proof cofferdam, and the bottom size of the water-proof cofferdam is smaller than the top size of the water-proof cofferdam. The first splicing portion is a plurality of annular protrusions located on the outer side of the bottom of the cofferdam baffle, and the second splicing portion is a plurality of annular protrusions located on the inner side of the top of the cofferdam. The first splicing portion and the second splicing portion are adapted to each other in shape and position after splicing.

[0049] Furthermore, waterproof spacers are provided on the top of the first joint portion and the bottom of the second joint portion.

[0050] Furthermore, the supporting legs are hydraulic equipment, and the interior of the hydraulic equipment is water.

[0051] Furthermore, the top of the supporting leg is fixedly connected to the center of both sides of the water-proof cofferdam opening.

[0052] Furthermore, a positioning cable is provided at the bottom of the supporting leg, and the top of the positioning cable is fixedly connected to the top of the water-proof cofferdam.

[0053] Compared with the prior art, the beneficial effects of the non-water-stopping hole installation construction method for the water diversion outlet on the wall of a concrete water storage tank provided by the present invention are:

[0054] Without the need for an underwater backrest structure, the cofferdam structure can be pressed against the side wall of the water storage structure through a hydraulic expansion device to form a seal, thus getting rid of the dependence on the underwater backrest structure and being suitable for the construction of the side wall of any water storage structure;

[0055] P-shaped rubber waterstop strips are installed around the semicircular arc cofferdam working window (the waterstop strips are annularly closed and connected, and an inflation port is reserved). The air compressor is turned on to inflate the cavity of the P-shaped waterstop strips to expand the P-shaped waterstop strips, thereby improving the sealing degree of the pool wall opening and ensuring that there is no leakage at the contact between the cofferdam and the concrete pool wall;

[0056] The semi-circular steel plate pressure cofferdam is used to install the water diversion port without stopping the water flow. The static cutting technology is used to open the water diversion port quickly without damaging the pool structure, and the water flow is not stopped, which greatly shortens the construction period.

[0057] The concrete static cutting technology is used to open holes, the anchoring technology is used to anchor the second phase concrete, the water-expanding waterstop strips are used to stop water in the construction joints, and the non-shrinkage grouting materials are used to seal the holes, ensuring the quality of concrete opening and sealing, and being more energy-saving and environmentally friendly. BRIEF DESCRIPTION OF THE DRAWINGS

[0058] In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the accompanying drawings required for use in the description of the embodiments of the present invention will be briefly introduced below. Obviously, the accompanying drawings in the following description are only some embodiments of the present invention. For ordinary technicians in this field, other accompanying drawings can be obtained based on these accompanying drawings without paying creative labor.

[0059] Figure 1 It is a flow chart of a method for installing a hole for a water diversion outlet on a concrete water reservoir wall without shutting off water;

[0060] Figure 2 A schematic diagram of the use of a water-isolating cofferdam in a method for installing a water diversion hole on a concrete water storage tank wall without water stopping;

[0061] Figure 3 A schematic diagram of a water-isolating cofferdam in a method for installing a water diversion hole on a concrete water storage tank wall without water shutoff;

[0062] Figure 4 A schematic diagram of a splicing mechanism in a method for installing a water diversion hole on a concrete water storage tank wall without water stopping;

[0063] Figure 5 A schematic diagram of a second embodiment of a buffer device for a non-water-stopping drilling and installation construction method of a water diversion outlet on a concrete water storage tank wall;

[0064] Figure 6 A cross-sectional view of a first embodiment of a water-proof cofferdam for a method of installing a hole for a water diversion outlet on a concrete reservoir wall without water shutoff;

[0065] Figure 7 for Figure 6 A magnified view of part A;

[0066] In the accompanying drawings, the components represented by the reference numerals are listed as follows:

[0067] 1. Water-proof cofferdam; 11. Cofferdam baffle; 111. First joint; 112. Second joint; 12. Support frame; 121. Longitudinal support frame; 122. Transverse support frame; 13. Waterstop; 14. Buffer component; 141. Transmission cylinder; 142. First fixed point; 143. First transmission plate; 144. Second transmission plate; 145. First slide plate; 146. Second slide plate; 147. Second fixed point; 148. Fixing hook; 1481. First connecting part; 1482. First arc-shaped part; 1483. Oblique connecting part; 149. Fixing ring; 1491. Second connecting part; 1492. Second arc-shaped part; 2. Support leg. DETAILED DESCRIPTION

[0068] In order to make the purpose, technical solution and advantages of the embodiments of the present invention more clear, the technical solution in the embodiments of the present invention will be clearly and completely described below in conjunction with the accompanying drawings in the embodiments of the present invention.

[0069] like Figure 1 As shown, it is a first embodiment of a method for installing a water diversion hole on a concrete water storage tank wall without water shutoff provided by the present invention. In this embodiment, the following steps are included:

[0070] S01: Processing water-blocking cofferdam 1, which is a semicircular cylinder with an opening on the side wall, and the opening is located at the chord plate position;

[0071] S02: fix the support leg 2 on the bottom wall of the concrete water storage tank toward the water diversion port, place the water-blocking cofferdam 1 underwater, with the opening of the water-blocking cofferdam 1 facing the water diversion port where a hole needs to be opened, fix the water-blocking cofferdam 1 on the wall of the concrete water storage tank through the support leg 2, and seal and pump out water;

[0072] S03: Position and cut the part where the hole needs to be opened through the opening of the water-proof cofferdam 1, and process the cutting surface. The hole opening part is the water diversion part;

[0073] S04: Install embedded parts at the water diversion port, fill it with concrete, and remove the embedded parts after the concrete solidifies;

[0074] S05: Test whether there is leakage at the water diversion outlet. If there is leakage, continue to deal with it; if there is no leakage, dismantle the water-proof cofferdam 1.

[0075] like Figure 2 , Figure 3As shown, in the above technical scheme, a support frame 12 is provided on the outside of the water-blocking cofferdam 1, and the support frame 12 is a semicircular cylindrical structure for supporting and fixing the water-blocking cofferdam 1. A waterstop 13 is provided around the opening of the water-blocking cofferdam 1, and the waterstop 13 is used to prevent water from entering the water-blocking cofferdam 1. One curved side of the water-blocking cofferdam 1 is two-layered, including an outer water-retaining cofferdam located on the outside and an inner water-retaining cofferdam located on the inside. The interior of the water-blocking cofferdam 1 is a sealed and impermeable structure, and is provided with a plurality of buffer devices for alleviating the curved surface of the water-blocking cofferdam 1.

[0076] Furthermore, in the above technical solution, the buffer device is a steel bar arranged in an S shape inside, the top view of the steel bar is semicircular, and the steel bar is close to the water-proof cofferdam 1 close to the outside.

[0077] like Figure 5 As shown, it is a second embodiment of a method for installing a water diversion port on a concrete water tank wall without water stopping provided by the present invention. In this embodiment, the buffer device is a buffer component 14, including a first fixed point 142 and a second slide plate 146 respectively fixed on the inner water retaining cofferdam, and a second fixed point 147 and a first slide plate 145 fixed on the outer water retaining cofferdam. The first slide plate 145 and the second slide plate 146 are provided with a slide groove, and the slide groove is provided with a sliding point that can slide on the slide groove. The first transmission plate 143 is X-shaped, one end of which is movably connected to the first fixed point 142 and the sliding point on the second slide plate 146, and the other end is movably connected to one end of the X-shaped second transmission plate 144, and the other end of the second transmission plate 144 is movably connected to the second fixed point 147 and the sliding point on the first slide plate 145. The intersection of the first transmission plate 143 is rotatably connected to one end of the transmission cylinder 141, and the other end of the transmission cylinder 141 is rotatably connected to the inner water retaining cofferdam.

[0078] like Figure 6 , Figure 7As shown, further, in the above technical solution, a plurality of fixing devices are provided at the contact between the buffer device and the inner water-proof cofferdam and the outer water-proof cofferdam, which are used to fix the position of the buffer device, and the fixing devices are a fixing hook 148 fixed on the water-proof cofferdam 1 and a fixing ring 149 fixed on the buffer device, the fixing hook 148 is a steel needle with an arc-shaped top, the fixing ring 149 is an arched iron wire, and the bending direction of the second transmission sheet 144 is toward the opening direction of the first slide plate 145; the fixing hook 148 includes a first connecting portion 1481, a first arc-shaped portion 1482 and an oblique connecting portion 148 3. The first connection part 1481 is straight and perpendicular to the surface of the water-proof cofferdam 1. The first arc-shaped part 1482 is arc-shaped and tangent to the first connection part 1481 and the oblique connection part 1483. The oblique connection part 1483 is straight and its top is facing the first connection part 1481. The fixing ring 149 includes two second connection parts 1491 and a second arc-shaped part 1492. The second connection part 1491 is straight and perpendicular to the surface of the water-proof cofferdam 1. The second arc-shaped part 1492 is semicircular and tangent to the second connection part 1491. The two second connection parts 1491 are parallel to each other.

[0079] Furthermore, in the above technical scheme, the support frame 12 includes a longitudinal support frame 121 and a transverse support frame 122. The support frame 12 is located on two vertical edges of the water-proof cofferdam 1 and is fixedly connected to the water-proof cofferdam 1. The transverse support frame 122 is a horizontally placed C-shaped steel frame, located on the outside of the curved side wall of the water-proof cofferdam 1 and is fixedly connected to the water-proof cofferdam 1.

[0080] Furthermore, in the above technical solution, S02 includes the following steps:

[0081] Fix the support leg 2 at the bottom of the concrete water storage tank, with the support leg 2 positioned toward the water diversion port. There are two support legs 2, one on each side of the water diversion port.

[0082] Mark the hole location;

[0083] Put the water-proof cofferdam 1 into the water, with the opening of the chord plate facing the water diversion port, and the water stop 13 close to the side wall of the concrete reservoir;

[0084] Use expansion screws to fix the side walls of the concrete reservoir of the water barrier cofferdam 1 together, and further fix the water barrier cofferdam 1 through the legs 2;

[0085] Pump out the water in the cavity of the waterproof cofferdam 1, and check the water seepage in the cavity of the waterproof cofferdam 1 after standing for one hour. If it is greater than the threshold, use the legs 2 to support the waterproof cofferdam 1 and inflate the waterstop 13; if it is less than the threshold, use a water suction pump to pump out the water.

[0086] Furthermore, in the above technical solution, S03 includes the following steps:

[0087] Mark and locate the water outlet of the concrete water storage tank, and use a cutting machine to open the water outlet;

[0088] Roughen the cut surface of the water diversion port and make the cut surface rough;

[0089] The steel bars are implanted on the cutting surface, the distance between the top of the steel bars is greater than the radius of the water diversion mold, and the width of the steel bars is equal to the width of the cutting surface;

[0090] A concrete groove is cut in a reverse direction in the middle of the cutting surface, and a second water stop strip is placed in the groove. The second water stop strip is a water stop strip that expands when exposed to water.

[0091] Furthermore, in the above technical solution, S04 includes the following steps:

[0092] Place the embedded parts on the cutting surface and fix them;

[0093] Placing round steel bars and embedded wires around the embedded parts to further secure the embedded parts;

[0094] A water stop ring is provided in the middle of the wire drawing;

[0095] Fill concrete between the embedded parts and the cut surface;

[0096] Remove the embedded parts after 12 hours.

[0097] Furthermore, in the above technical solution, S05 includes the following steps:

[0098] Release water into the water-proof cofferdam 1 to the water level line and conduct a full water test. If there is leakage, pump out the seepage water in the water-proof cofferdam 1 and continue to deal with it;

[0099] Retract the outrigger 2 and remove the expansion bolts on the water-proof cofferdam 1;

[0100] The water-proof cofferdam 1 is lifted by a crane.

[0101] like Figure 4 As shown, further, in the above technical scheme, a splicing mechanism for extending the height of the water-proof cofferdam 1 is also provided above the water-proof cofferdam 1, and the splicing mechanism includes a cofferdam baffle 11, a first splicing portion 111 is provided on the outer side of the bottom of the cofferdam baffle 11, and a second splicing portion 112 is provided on the inner side of the top of the water-proof cofferdam 1. The cofferdam baffle 11 is a semicircular cylinder, which is the same size as the water-proof cofferdam 1, and the bottom size of the water-proof cofferdam 1 is smaller than the top size of the water-proof cofferdam 1. The first splicing portion 111 is a plurality of annular protrusions located on the outer side of the bottom of the cofferdam baffle 11, and the second splicing portion 112 is a plurality of annular protrusions on the inner side of the top of the cofferdam water-proof cofferdam 1. The first splicing portion 111 and the second splicing portion 112 are adapted to each other in shape and position after splicing.

[0102] When in use, the water-proof cofferdam 1, the support frame 12 and the waterstop 13 are placed. If the water level is higher than the height of the water-proof cofferdam 1, the cofferdam baffle 11 is placed into the water-proof cofferdam 1. At this time, the first splicing part 111 and the second splicing part 112 are matched to block the water from entering the cofferdam baffle 11. The waterproof strips at the top of the first splicing part 111 and the bottom of the second splicing part 112 further block water from entering the interior of the water-proof cofferdam 1.

[0103] Furthermore, in the above technical solution, waterproof spacers are provided at the top of the first splicing portion 111 and the bottom of the second splicing portion 112 .

[0104] Furthermore, in the above technical solution, the outrigger 2 is a hydraulic device, and the interior of the hydraulic device is water.

[0105] Furthermore, in the above technical solution, the top of the supporting leg 2 is fixedly connected to the center of both sides of the opening of the water-proof cofferdam 1.

[0106] Furthermore, in the above technical solution, a positioning cable is also provided at the bottom of the supporting leg 2 , and the top of the positioning cable is fixedly connected to the top of the water-proof cofferdam 1 .

[0107] Specifically, the principle of the present invention is:

[0108] First, a water-blocking cofferdam is made by processing. This cofferdam is a semicircular cylinder with an opening located at the chord plate position. Next, the legs are fixed to the bottom wall of the concrete water storage tank, and the position of these legs is biased towards the water diversion port. Then, the water-blocking cofferdam is placed underwater, ensuring that its opening is facing the direction of the water diversion port where the hole needs to be opened, and it is fixed to the wall of the water tank by the legs, and the sealing and pumping operation is carried out at the same time;

[0109] Then, the opening of the water-proof cofferdam is used to locate and cut the parts that need to be opened, and the cut surface is processed. After the cut surface is prepared, the embedded parts are installed at the water diversion port and filled with concrete. The embedded parts are removed after the concrete solidifies. Next, a leakage test is carried out at the water diversion port. If there is leakage, further treatment is carried out; if there is no leakage, the water-proof cofferdam is removed;

[0110] In addition, a support frame is provided on the outside of the water-blocking cofferdam to support and fix the water-blocking cofferdam, and a water stop strip is provided around it to prevent water from entering the water-blocking cofferdam. The support frame includes a longitudinal support frame and a transverse support frame, which are located on the two vertical sides of the water-blocking cofferdam and are fixedly connected to the water-blocking cofferdam. The transverse support frame is a horizontally placed C-shaped steel frame, which is located on the outside of the curved side wall of the water-blocking cofferdam and is fixedly connected to the water-blocking cofferdam;

[0111] The outrigger is a hydraulic device filled with water. The top is fixedly connected to the centers of both sides of the opening of the water-proof cofferdam. A positioning cable is provided at the bottom, and the top of the cable is fixedly connected to the top of the water-proof cofferdam.

[0112] The principle of this method is to create a construction space by setting up water-proof cofferdams and support frames, and install the water diversion while the pool remains in operation. Sealing and leakage tests ensure the quality of the water diversion and the normal operation of the pool.

Claims

1. A method for installing a water diversion hole on a concrete water reservoir wall without water shutoff, characterized in that: The following steps are involved: S01: processing a water-proof cofferdam (1), wherein the water-proof cofferdam (1) is a semicircular cylinder with an opening on the side wall, wherein the opening is located at the position of the chord plate; S02: Fix the support leg (2) on the bottom wall of the concrete water storage tank towards the water diversion port, place the water-proof cofferdam (1) underwater, with the opening of the water-proof cofferdam (1) facing the water diversion port where a hole is to be opened, and fix the water-proof cofferdam (1) on the wall of the concrete water storage tank through the support leg (2) to seal and pump out water; S03: Positioning and cutting the part to be opened through the opening of the water-proof cofferdam (1), and processing the cut surface, wherein the opening part is the water diversion part; S04: Install embedded parts at the water diversion port, fill it with concrete, and remove the embedded parts after the concrete solidifies; S05: Test whether there is leakage at the water diversion point. If there is leakage, continue to deal with it; if there is no leakage, remove the water-blocking cofferdam (1).

2. A method for installing a water diversion hole on a concrete water reservoir wall without water shutoff according to claim 1, characterized in that: A support frame (12) is provided on the outside of the water-blocking cofferdam (1). The support frame (12) is a semicircular cylindrical structure for supporting and fixing the water-blocking cofferdam (1). A waterstop (13) is provided around the opening of the water-blocking cofferdam (1). The waterstop (13) is used to prevent water from entering the water-blocking cofferdam (1). One curved side of the water-blocking cofferdam (1) is two-layered, including an outer water-retaining cofferdam located on the outside and an inner water-retaining cofferdam located on the inside. The interior of the water-blocking cofferdam (1) is a sealed and impermeable structure, and is provided with a plurality of buffer devices for alleviating the curved surface of the water-blocking cofferdam (1).

3. A method for installing a water diversion hole on a concrete water reservoir wall without water shutoff according to claim 2, characterized in that: The buffer device is a steel bar arranged in an S shape inside, the top view of the steel bar is semicircular, and the steel bar is closely attached to the water-proof cofferdam (1) close to the outside.

4. A method for installing a water diversion hole on a concrete water reservoir wall without water shutoff according to claim 3, characterized in that: The buffer device is a buffer component (14), comprising a first fixed point (142) and a second slide plate (146) respectively fixed to the inner water retaining cofferdam, and a second fixed point (147) and a first slide plate (145) fixed to the outer water retaining cofferdam, wherein the first slide plate (145) and the second slide plate (146) are provided with a slide groove, and the slide groove is provided with a sliding point that can slide on the slide groove, and the first transmission plate (143) is X-shaped, one end of which is movably connected to the first fixed point (142) and the sliding point on the second slide plate (146), and the other end is movably connected to one end of the X-shaped second transmission plate (144), the other end of the second transmission plate (144) is movably connected to the second fixed point (147) and the sliding point on the first slide plate (145), and the intersection of the first transmission plate (143) is rotatably connected to one end of a transmission cylinder (141), and the other end of the transmission cylinder (141) is rotatably connected to the inner water retaining cofferdam.

5. A method for installing a water diversion hole on a concrete water reservoir wall without water shutoff according to claim 4, characterized in that: A plurality of fixing devices are provided at the contact points between the buffer device and the inner water-proof cofferdam and the outer water-proof cofferdam, for fixing the position of the buffer device. The fixing devices are a fixing hook (148) fixed on the water-proof cofferdam (1) and a fixing ring (149) fixed on the buffer device. The fixing hook (148) is a steel needle with an arc-shaped top, and the fixing ring (149) is an arched iron wire. The bending direction of the second transmission plate (144) is toward the opening direction of the first slide plate (145); the fixing hook (148) includes a first connecting portion (1481), a first arc-shaped portion (1482) and an oblique connecting portion (1483). The first connecting portion (148 1) is straight and perpendicular to the surface of the water-proof cofferdam (1), the first arc-shaped portion (1482) is arc-shaped and tangent to the first connecting portion (1481) and the oblique connecting portion (1483), the oblique connecting portion (1483) is straight and the top is facing the first connecting portion (1481); the fixing ring (149) includes two second connecting portions (1491) and a second arc-shaped portion (1492), the second connecting portion (1491) is straight and perpendicular to the surface of the water-proof cofferdam (1), the second arc-shaped portion (1492) is semicircular and tangent to the second connecting portion (1491), and the two second connecting portions (1491) are parallel to each other.

6. A method for installing a water diversion hole on a concrete water storage tank wall without water shutoff according to claim 5, characterized in that: The support frame (12) includes a longitudinal support frame (121) and a transverse support frame (122). The support frame (12) is located on two vertical sides of the water-proof cofferdam (1) and is fixedly connected to the water-proof cofferdam (1). The transverse support frame (122) is a horizontally placed C-shaped steel frame, located on the outer side of the curved side wall of the water-proof cofferdam (1) and is fixedly connected to the water-proof cofferdam (1).

7. A method for installing a water diversion hole on a concrete water reservoir wall without water shutoff according to claim 6, characterized in that: The S02 comprises the following steps: The support legs (2) are fixed to the bottom of the concrete water storage tank, the position of the support legs (2) is biased towards one side of the water diversion port, and there are two support legs (2), which are respectively located on both sides of the water diversion port; Mark the hole location; The water-proof cofferdam (1) is placed in water, with the opening of the chord plate facing the water diversion outlet, and the water stop strip (13) is closely attached to the side wall of the concrete water storage tank; Using expansion screws to fix the water-blocking cofferdam (1) and the concrete water storage tank side wall together, and further fixing the water-blocking cofferdam (1) by means of the supporting legs (2); The water in the cavity of the waterproof cofferdam (1) is pumped out and the water seepage in the cavity of the waterproof cofferdam (1) is checked after standing for one hour. If the water seepage in the cavity of the waterproof cofferdam (1) is greater than the threshold, the supporting legs (2) are used to support the waterproof cofferdam (1) and the water stop belt (13) is inflated; if the water seepage in the cavity is less than the threshold, the water seepage is pumped out using a water suction pump.

8. A method for installing a water diversion hole on a concrete water reservoir wall without water shutoff according to claim 7, characterized in that: The S03 comprises the following steps: Mark and locate the water outlet of the concrete water storage tank, and use a cutting machine to open the water outlet; Roughen the cut surface of the water diversion port and make the cut surface rough; The steel bars are implanted on the cutting surface, the distance between the top of the steel bars is greater than the radius of the water diversion mold, and the width of the steel bars is equal to the width of the cutting surface; A concrete groove is cut in a reverse direction in the middle of the cutting surface, and a second water stop strip is placed in the groove. The second water stop strip is a water stop strip that expands when exposed to water.

9. A method for installing a water diversion hole on a concrete water reservoir wall without water shutoff according to claim 8, characterized in that: The S04 comprises the following steps: Place the embedded parts on the cutting surface and fix them; Placing round steel bars and embedded wires around the embedded parts to further secure the embedded parts; A water stop ring is provided in the middle of the wire drawing; Fill concrete between the embedded parts and the cut surface; Remove the embedded parts after 12 hours.

10. A method for installing a water diversion hole on a concrete water reservoir wall without water shutoff according to claim 9, characterized in that: The S05 comprises the following steps: Water is released into the water-proof cofferdam (1) to the water level line to carry out a full water test. If leakage is found, the seepage water in the water-proof cofferdam (1) is pumped out for further treatment; Retract the supporting legs (2) and remove the expansion bolts on the water-proof cofferdam (1); The water-proof cofferdam (1) is hoisted by a crane.