Mining flame-proof lighting signal protection test method

By designing a mine explosion-proof lighting signal protection test method, the problem of single test items and insufficient accuracy of existing experimental devices has been solved, and a high-capacity, multi-functional and accurate test device has been realized, which meets the requirements for the detection of large-capacity comprehensive protection devices. requirements, improving inspection efficiency and data accuracy.

CN118731540APending Publication Date: 2024-10-01CHONGQING SAFETY STANDARD TESTING RES INST CO LTD +2
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202410793385.5
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-06-19
Publication Date
2024-10-01

AI Technical Summary

Technical Problem

The development of the existing comprehensive protection performance experimental device for coal electric drill lighting is not yet mature. The test device has a single test item and insufficient accuracy, and the device capacity cannot meet the development needs of comprehensive protection devices.

Method used

A mine explosion-proof lighting signal protection test method is designed. Through the upper computer to issue operating instructions, the PLC cooperates with the rear-stage relays and contactors to realize load cable switching and power output adjustment. The test data is collected and processed in real time, and the temperature is carried out. It uses a 35kVA voltage regulator and a 30kVA main transformer to form an adjustable power supply and integrates multiple test functions.

Benefits of technology

It has achieved large capacity, high precision and high integration of the test device, optimized the detection components of the comprehensive protection device, improved the inspection efficiency and data accuracy, met the power supply needs of the large-capacity comprehensive protection device, and through human-machine dialogue capabilities The powerful, simple-to-operate control system reduces manual data processing.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118731540A_ABST
    Figure CN118731540A_ABST
Patent Text Reader

Abstract

The invention relates to a mining flame-proof lighting signal protection test method, and belongs to the technical field of mining equipment. The method comprises the steps that an upper computer issues an operation instruction to a PLC, the PLC receives the instruction and then cooperates with a rear-stage relay and a contactor to achieve load cable switching, load starting and stopping and power output adjustment, and test data of a tested sample are collected in real time through a voltage measurement module, a current measurement module and a time measurement module and uploaded to the PLC; and after being processed by the PLC, the signals are transmitted to the upper computer to realize real-time monitoring. A clamp-type wire is adopted as a test wire, so that a connecting wire is convenient to replace; a load cable adopts an MVV3 * 4 type mining cable, and 0-1500m segmented selective switching can be realized, so that the protection distance requirement in short-circuit protection performance is met.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of mining equipment and relates to a mining explosion-proof lighting signal protection test method. Background Art

[0002] At present, the development of comprehensive protection performance test equipment for coal drill lighting is not mature, and only a small amount of experimental equipment development literature is publicly available. The test equipment on sale is basically a comprehensive test bench, which can only provide manufacturers with factory inspection of some test items. It has problems such as single inspection items, inspection accuracy that cannot meet the test requirements, and device capacity that cannot meet the development needs of comprehensive protection devices. Summary of the invention

[0003] In view of this, an object of the present invention is to provide a mining explosion-proof lighting signal protection test method.

[0004] In order to achieve the above object, the present invention provides the following technical solutions:

[0005] The test method for protection of explosion-proof lighting signals for mines is as follows:

[0006] The host computer sends operation instructions to the PLC. After receiving the instructions, the PLC cooperates with the subsequent relays and contactors to realize load cable switching, load start and stop, and power output adjustment. The test data of the tested sample is collected in real time through the voltage measurement module, current measurement module, and time measurement module and uploaded to the PLC. After being processed by the PLC, it is transmitted to the host computer for real-time monitoring.

[0007] Information configuration: Set the test sample information, fill in according to the actual situation and save, select the sample category and test items to enter the corresponding test interface;

[0008] Temperature rise test: set the rated voltage, input the given voltage and automatically adjust the voltage, the voltage regulating motor works and adjusts to the required voltage; select the load power according to the sample capacity, set the temperature recording time interval and test duration, start the test, and draw the temperature rise curve through the real-time temperature of the test point; stop the test and save the data at the end of the test, and the test is completed;

[0009] Transformer performance and deviation test: Set the rated voltage and rated capacity and confirm the settings, input the given voltage, and the voltage regulating motor will work and adjust to the required voltage; if the set rated voltage is inconsistent with the voltage selected by the selection switch on the operating table, an inconsistency prompt will pop up and the next operation cannot be performed; if the set rated voltage is consistent with the voltage selected by the selection switch on the operating table, a prompt to close the switch will be displayed, and the sample will be closed; input the no-load and load performance limits and deviation values ​​specified in the standard, start the no-load test, load test or ratio test to enter the corresponding test, perform data sampling, compare the test value with the limit required by the standard and calculate the deviation, and the test will stop;

[0010] Short-circuit protection characteristic test: set the rated voltage, rated load, cable cross-sectional area, cable length and power-on time, input the given voltage, automatically adjust the voltage, and the voltage regulating motor will work and adjust to the required voltage; if the set rated voltage is inconsistent with the voltage selected by the selection switch on the operating table, an inconsistency prompt will pop up, and the next step cannot be performed at this time to ensure safety; if the set rated voltage is consistent with the voltage selected by the selection switch on the operating table, a prompt to close the switch will be displayed, and the sample will be closed; add load and test the corresponding short-circuit point. If the sample is successfully opened, the load will be automatically disconnected. If the sample under test fails to open, the power will be automatically disconnected after the set power-on time is reached; store the test data at the end of the test;

[0011] Leakage protection performance test: set the rated voltage, input the given voltage and automatically adjust the voltage, the voltage regulating motor works and adjusts to the required voltage; during this process, if the set rated voltage is inconsistent with the voltage selected by the selection switch on the operating table, an inconsistency prompt will pop up and the next operation cannot be performed at this time; if the set rated voltage is consistent with the voltage selected by the selection switch on the operating table, a prompt to close the switch will be displayed, and the sample will be closed at this time; start the leakage action test and save the test data.

[0012] The beneficial effects of the present invention are:

[0013] (1) This test device has a large capacity: the test device uses a 35kVA voltage regulator and a 30kVA main transformer to form an adjustable power supply to meet the power supply needs of a large-capacity comprehensive protection device (currently the maximum capacity is 25kVA);

[0014] (2) High integration: This test device integrates temperature rise test, short-circuit protection test, leakage action and leakage lockout protection test, over-voltage and under-voltage protection test, overload protection test, phase loss and phase imbalance test, transformer no-load performance measurement (no-load current, no-load loss, impedance voltage, load loss) and other tests, optimizing and integrating the detection components of the main performance of the comprehensive protection device.

[0015] (3) High precision: The precision of each acquisition module (voltage, current, time) in the test device is not less than 0.2 level, ensuring the accuracy and effectiveness of the test data;

[0016] (4) Strong human-computer dialogue capability: The control system consists of a host computer, configuration software, programmable controller, signal acquisition module, relays and contactors, etc. It can collect and monitor data during the test in real time. The test parameters can be automatically adjusted according to the set values, and the data can be automatically processed, reducing the manual data processing links and improving the inspection efficiency.

[0017] (5) Strong operability: The test bench can be controlled by manual short-range button control and host computer remote control. The test wiring is small and the operation is simple. The test wire adopts clamp-type wire, which is convenient for replacing the connection wire; the load cable adopts MVV3*4 mining cable, which can realize 0~1500m segmented selective switching to meet the protection distance requirements in the short-circuit protection performance (the minimum change distance is 50m); the leakage resistance can realize 0~22kΩ segmented dead zone adjustment, so as to realize the accurate detection of the leakage blocking resistance value.

[0018] Other advantages, objectives and features of the present invention will be described in the following description to some extent, and to some extent, will be obvious to those skilled in the art based on the following examination and study, or can be taught from the practice of the present invention. The objectives and other advantages of the present invention can be realized and obtained through the following description. BRIEF DESCRIPTION OF THE DRAWINGS

[0019] In order to make the purpose, technical solutions and advantages of the present invention more clear, the present invention will be described in detail below in conjunction with the accompanying drawings, wherein:

[0020] Figure 1 It is the principle diagram of the present invention;

[0021] Figure 2 It is a composition diagram of the system of the present invention;

[0022] Figure 3 It is the control circuit diagram;

[0023] Figure 4 Wiring the PLC Figure 1 ;

[0024] Figure 5 Wiring the PLC Figure 2 ;

[0025] Figure 6 Wiring the PLC Figure 3 . DETAILED DESCRIPTION

[0026] The following describes the embodiments of the present invention by specific examples, and those skilled in the art can easily understand other advantages and effects of the present invention from the contents disclosed in this specification. The present invention can also be implemented or applied through other different specific embodiments, and the details in this specification can also be modified or changed in various ways based on different viewpoints and applications without departing from the spirit of the present invention. It should be noted that the illustrations provided in the following embodiments only illustrate the basic concept of the present invention in a schematic manner, and the following embodiments and features in the embodiments can be combined with each other without conflict.

[0027] Among them, the drawings are only used for illustrative explanations, and they only represent schematic diagrams rather than actual pictures, and should not be understood as limitations on the present invention. In order to better illustrate the embodiments of the present invention, some parts of the drawings may be omitted, enlarged or reduced, and do not represent the size of actual products. For those skilled in the art, it is understandable that some well-known structures and their descriptions in the drawings may be omitted.

[0028] The same or similar numbers in the drawings of the embodiments of the present invention correspond to the same or similar parts; in the description of the present invention, it should be understood that if the terms "upper", "lower", "left", "right", "front", "rear", etc. indicate the orientation or position relationship, they are based on the orientation or position relationship shown in the drawings, which is only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operate in a specific orientation. Therefore, the terms describing the position relationship in the drawings are only used for illustrative purposes and cannot be understood as limiting the present invention. For ordinary technicians in this field, the specific meanings of the above terms can be understood according to specific circumstances.

[0029] like Figure 1 As shown in the figure, the lighting (coal drill) comprehensive protection performance experimental device can realize the test operation by two control modes: manual short-range button control and host computer remote control. The host computer can realize real-time monitoring of the whole test process and send operation instructions to the PLC. After receiving the instructions, the PLC can cooperate with the subsequent relays and contactors to realize load cable switching, load start and stop, and power output adjustment. The various test data of the tested samples are collected in real time through the voltage, current and time acquisition modules and uploaded to the PLC. After being processed by the PLC, they are transmitted to the host computer for real-time monitoring.

[0030] like Figure 2 As shown, this is the equipment selection and design.

[0031] See also Figure 3 to Figure 6 , the experimental method of the present invention includes the following test categories:

[0032] Information configuration: After entering the main interface, you can set the test sample information, fill it out according to the actual situation and save it, select the sample category and test item to enter the corresponding test interface.

[0033] Temperature rise test: Set the rated voltage, input the given voltage and click the automatic voltage adjustment button, the voltage adjustment motor will work and adjust to the required voltage. Select the load power according to the sample capacity, set the temperature recording time interval and test duration, confirm the settings and click the start button to enter the test, and the temperature rise curve will be automatically drawn through the real-time temperature of the test point. At the end of the test, click Stop Test and save the data, and the test is completed.

[0034] Transformer performance and deviation test: Set the rated voltage and rated capacity and confirm the settings, input the given voltage, click the automatic voltage adjustment button, and the voltage regulating motor will work and adjust to the required voltage. During this process, if the set rated voltage is inconsistent with the voltage selected by the selection switch on the operating table, an inconsistency prompt will pop up, and the next step cannot be performed at this time to ensure safety. If they are consistent, it will prompt to close the switch, and the sample can be closed at this time. Enter the no-load and load performance limits and deviation values ​​specified in the standard, click the no-load test start button, the load test start button or the ratio test start button to enter the corresponding test, click the data sampling button to compare the test value with the standard limit and calculate the deviation, and click the test stop button to end the test.

[0035] Short-circuit protection characteristic test: Set the rated voltage, rated load, cable cross-sectional area, cable length and power-on time and confirm the settings, input the given voltage, click the automatic voltage regulation button, the voltage regulating motor will work and adjust to the required voltage. During this process, if the set rated voltage is inconsistent with the voltage selected by the selection switch on the operating table, an inconsistency prompt will pop up, and the next step cannot be performed at this time to ensure safety. If they are consistent, it will prompt to close the switch, and the sample can be closed at this time. Click the load addition button and click the corresponding short-circuit point to enter the test. If the sample is successfully disconnected, the load will be automatically disconnected. If the sample under test fails to be disconnected, the power supply will be automatically disconnected after the set power-on time is reached to ensure that the voltage regulating power supply is not damaged. At the end of the test, click to store the test data and click the stop button to end the test.

[0036] Leakage protection performance test: Set the rated voltage, input the given voltage and click the automatic voltage adjustment button, the voltage regulating motor will work and adjust to the required voltage. During this process, if the set rated voltage is inconsistent with the voltage selected by the selection switch on the operating table, an inconsistent prompt will pop up, and the next step cannot be performed at this time to ensure safety. If they are consistent, it will prompt to close the switch, and the sample can be closed at this time. Click the 1k start button to enter the test, and click the save test data button and the stop button to end the test.

[0037] The following is a further refinement of the technical solution:

[0038] System component refinement:

[0039] Host computer:

[0040] It uses high-performance industrial control computers and is equipped with professional monitoring software.

[0041] The software interface can display key data such as voltage, current, and operating time in real time.

[0042] Provides functions such as command issuance, data storage, report generation and alarm prompts.

[0043] PLC (Programmable Logic Controller):

[0044] Choose high-performance PLC from well-known brands, such as Siemens, Allen-Bradley, etc.

[0045] The PLC program adopts a modular design to facilitate subsequent maintenance and upgrades.

[0046] The PLC contains multiple control loops to process various instructions and feedback information.

[0047] Voltage measurement module:

[0048] High-precision voltage transformer is used to ensure measurement accuracy.

[0049] The module has built-in protection circuit to prevent overvoltage damage.

[0050] The measured data is transmitted to the PLC in real time via a digital interface.

[0051] Current measurement module:

[0052] Current measurements are made using Hall effect current sensors or shunts.

[0053] The module has a temperature compensation function to reduce the impact of ambient temperature on the measurement results.

[0054] Provide current overload alarm function.

[0055] Time measurement module:

[0056] Adopt high-precision clock chip to ensure the accuracy of time measurement.

[0057] Records the load's operating time and can trigger maintenance reminders when preset values ​​are reached.

[0058] Workflow refinement:

[0059] Instructions issued:

[0060] The host computer sends specific operation instructions to the PLC according to the operator input or preset program. The instructions include switching on and off the load cable, starting and stopping the load, and adjusting the power output.

[0061] Instruction execution:

[0062] After receiving the instruction, the PLC analyzes and converts it into corresponding control signals.

[0063] Through internal logic judgment, the safe execution of instructions is ensured.

[0064] Control the relays and contactors at the back stage to complete operations such as switching on and off the load cables and starting and stopping the loads. Data collection and upload:

[0065] The voltage, current and time measurement modules continuously collect test data of the tested samples.

[0066] After preliminary processing, the data is uploaded to the PLC in real time through the communication interface.

[0067] Data processing and monitoring:

[0068] The PLC further processes the received data, such as filtering and conversion.

[0069] The processed data is transmitted to the host computer through the communication link.

[0070] The monitoring software of the host computer displays these data in real time and provides alarm, recording and analysis functions. Safety and protection:

[0071] Multiple safety protection mechanisms are set up in the system, such as overload protection, short circuit protection, etc.

[0072] In abnormal situations, the PLC can quickly cut off the power supply to prevent equipment damage and personal injury.

[0073] Maintenance and Upgrades:

[0074] The system design takes into account the needs of easy maintenance and upgrade.

[0075] The PLC program adopts a modular design to facilitate subsequent function addition and modification.

[0076] The host computer software provides remote upgrade function to reduce the complexity of on-site maintenance.

[0077] Finally, it should be noted that the above embodiments are only used to illustrate the technical solution of the present invention rather than to limit it. Although the present invention has been described in detail with reference to the preferred embodiments, those skilled in the art should understand that the technical solution of the present invention can be modified or replaced by equivalents without departing from the purpose and scope of the technical solution, which should be included in the scope of the claims of the present invention.

Claims

1. The test method for protection of explosion-proof lighting signals for mines is characterized by: The method is: The host computer sends operation instructions to the PLC. After receiving the instructions, the PLC cooperates with the subsequent relays and contactors to realize load cable switching, load start and stop, and power output adjustment. The test data of the tested sample is collected in real time through the voltage measurement module, current measurement module, and time measurement module and uploaded to the PLC. After being processed by the PLC, it is transmitted to the host computer for real-time monitoring. Information configuration: Set the test sample information, fill in according to the actual situation and save, select the sample category and test items to enter the corresponding test interface; Temperature rise test: set the rated voltage, input the given voltage and automatically adjust the voltage, the voltage regulating motor works and adjusts to the required voltage; select the load power according to the sample capacity, set the temperature recording time interval and test duration, start the test, and draw the temperature rise curve through the real-time temperature of the test point; stop the test and save the data at the end of the test, and the test is completed; Transformer performance and deviation test: Set the rated voltage and rated capacity and confirm the settings, input the given voltage, and the voltage regulating motor will work and adjust to the required voltage; if the set rated voltage is inconsistent with the voltage selected by the selection switch on the operating table, an inconsistent prompt will pop up and the next operation cannot be performed; If the set rated voltage is consistent with the voltage selected by the selector switch on the operating table, a prompt will be given to close the circuit breaker and close the circuit breaker on the sample; input the no-load and load performance limits and deviation values ​​specified in the standard, start the no-load test, load test or ratio test to enter the corresponding test, perform data sampling, compare the test value with the limit value required by the standard, calculate the deviation, and then stop the test; Short-circuit protection characteristic test: set the rated voltage, rated load, cable cross-sectional area, cable length and power-on time, input the given voltage, automatically adjust the voltage, and the voltage regulating motor will work and adjust to the required voltage; if the set rated voltage is inconsistent with the voltage selected by the selection switch on the operating table, an inconsistency prompt will pop up, and the next step cannot be performed at this time to ensure safety; if the set rated voltage is consistent with the voltage selected by the selection switch on the operating table, a prompt to close the switch will be displayed, and the sample will be closed; add load and test the corresponding short-circuit point. If the sample is successfully opened, the load will be automatically disconnected. If the sample under test fails to open, the power will be automatically disconnected after the set power-on time is reached; store the test data at the end of the test; Leakage protection performance test: Set the rated voltage, input the given voltage and automatically adjust the voltage. The voltage regulating motor works and adjusts to the required voltage. During this process, if the set rated voltage is inconsistent with the voltage selected by the selection switch on the operating table, an inconsistent prompt will pop up and the next step cannot be performed at this time. If the set rated voltage is consistent with the voltage selected by the selection switch on the operating table, a prompt will appear to close the circuit breaker. At this time, close the circuit breaker on the sample; start the leakage action test and save the test data.

Citation Information

Cited By

  • Device and method for testing short-circuit time of mining lighting signal comprehensive protection device

    CN121595987A