Building operation system, method and equipment based on BIM model and storage medium
By combining PLC controllers, edge computing gateways and smart operation systems in the building operation system, BIM model data is used to achieve building energy consumption management, which solves the problem that the BIM model cannot be applied in the operation and maintenance phase, and improves the intelligence and low-efficiency of the building. Carbonation level.
Patent Information
- Application Number
- CN202410701119.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-05-31
- Publication Date
- 2024-10-01
AI Technical Summary
Existing BIM models cannot be effectively applied during the building operation and maintenance phase, resulting in high building energy consumption and insufficient intelligence.
Adopt a building operation system based on BIM model, integrate it with the smart building operation system through PLC controller and edge computing gateway, use KNX, ModBus, and BACNET protocols to receive sensor data, generate control instructions, control equipment operating status, and use energy consumption prediction algorithms Achieve target control of energy consumption of smart devices.
Extend the application scope of BIM model data to the operation and maintenance stage, and combine digital, informatization, and intelligent technologies to effectively reduce building energy consumption, improve the level of intelligence, and achieve visual, low-carbon, and intelligent operation and maintenance.
Smart Images

Figure CN118732597A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of Internet of Things, and in particular to a building operation system, method, device and storage medium based on a BIM model. Background Art
[0002] At present, the country has proposed digital transformation and "dual carbon" goals, and various types of intelligent equipment and communication technologies are constantly developing. How to achieve the goal of combining digitalization, low-carbonization, and intelligent operations in the building operation and maintenance stage will receive more and more attention. It is a development trend in the construction industry for buildings to have low-carbon and intelligent characteristics throughout their life cycle.
[0003] Building Information Modeling (BIM) is a digital expression of the physical and functional characteristics of a building. The building model created based on BIM technology is a shared knowledge resource that contains all the information about the building and its internal equipment and facilities. It is widely used in the design and construction phase of the building, but is disconnected from the operation and maintenance phase, resulting in a large amount of building and equipment and facility data in the BIM model being unable to be applied to the operation and maintenance phase. Therefore, how to reduce building energy consumption while improving the level of building intelligence has become an urgent problem to be solved.
[0004] The above contents are only used to assist in understanding the technical solution of the present invention and do not constitute an admission that the above contents are prior art. Summary of the invention
[0005] The main purpose of the present invention is to provide a building operation system, method, device and storage medium based on the BIM model, aiming to solve the problem of how to improve the intelligence level of buildings while reducing building energy consumption.
[0006] To achieve the above object, the present invention provides a building operation system based on a BIM model, wherein the building operation system based on a BIM model comprises a PLC controller, an edge computing gateway and a smart building operation system, wherein the PLC controller is connected to the smart building operation system through an API interface, and the edge computing gateway is connected to the smart building operation system through a ModBus protocol;
[0007] The PLC controller is used to receive sensor data collected by sensors built into the building through a preset protocol, and determine control instructions according to the sensor data, wherein the preset protocol includes the KNX protocol and the ModBus protocol;
[0008] The PLC controller is further used to control the operation state of the equipment according to the control instruction, and send the control instruction to the smart building operation system through the API interface, and view the equipment operation data through the visual operation and maintenance platform of the smart operation system;
[0009] The edge computing gateway is used to obtain the water and electricity data corresponding to the smart water and electricity meter equipment through active polling, and send the water and electricity data to the smart building operation system through the ModBus protocol, so that the command and operation service platform of the smart building operation system can realize the energy consumption target control of the smart device according to the water and electricity data.
[0010] Optionally, the BIM model-based building operation system further includes a human presence sensor and an IO switch module;
[0011] The human presence sensor is used to obtain the human activity signal data in the sensing area in real time, and send the human activity signal data to the PLC controller through the KNX protocol;
[0012] The PLC controller is used to determine the IO switch control instruction according to the personnel activity signal data, and send the IO switch control instruction to the IO switch module;
[0013] The IO switch module is used to control the lighting switch of the lighting system according to the IO switch control instruction.
[0014] Optionally, the BIM model-based building operation system further includes an air quality sensor and a fan control panel;
[0015] The air quality sensor is used to collect indoor carbon dioxide concentration data or PM2.5 concentration data in real time, and when the indoor carbon dioxide concentration is greater than the warning upper limit or the PM2.5 concentration is less than the warning lower limit, the indoor carbon dioxide concentration data or the PM2.5 concentration data is sent to the PLC controller through the ModBus protocol;
[0016] The PLC controller is further used to determine a ventilation control instruction according to the indoor carbon dioxide concentration data or the PM2.5 concentration data, and send the ventilation control instruction to the fan control panel through the ModBus protocol;
[0017] The fan control panel is used to control the wind speed mode of the ventilation system according to the ventilation control instruction.
[0018] Optionally, the BIM model-based building operation system further includes a BACNET gateway and a VR V air conditioner;
[0019] The PLC controller is further configured to generate an air conditioning linkage instruction when detecting that the lighting is turned on, and send the air conditioning linkage instruction to the BACNET gateway via the BACNET protocol;
[0020] The BACNET gateway is used to control the operating state of the VRV air conditioner according to the air conditioner linkage instruction.
[0021] Optionally, the edge computing gateway is used to obtain water and electricity data corresponding to the smart water and electricity meter device by active polling, and send the water and electricity data to the smart building operation system through the ModBus protocol;
[0022] The smart building operation system is used to obtain energy consumption prediction values according to the water and electricity data through an energy prediction algorithm based on the command and operation service platform, and to achieve energy consumption target control of the smart device according to the energy consumption prediction values.
[0023] Optionally, the smart building operation system is also used to obtain operation data corresponding to the video surveillance system, access control system and parking management system through an API interface, and view visualization information corresponding to the operation data through the visualization operation and maintenance platform.
[0024] In addition, to achieve the above-mentioned purpose, the present invention also proposes a building operation system based on the BIM model, and the building operation method based on the BIM model comprises the following steps:
[0025] The PLC controller receives sensor data collected by sensors built into the building through a preset protocol, and determines control instructions according to the sensor data, wherein the preset protocol includes a KNX protocol and a ModBus protocol;
[0026] The PLC controller controls the operation state of the equipment according to the control instruction, and sends the control instruction to the smart building operation system through the API interface, and checks the equipment operation data through the visual operation and maintenance platform of the smart operation system;
[0027] The edge computing gateway obtains the water and electricity data corresponding to the smart water and electricity meter device through active polling, and sends the water and electricity data to the smart building operation system through the ModBus protocol, so that the command and operation service platform of the smart building operation system can realize the energy consumption target control of the smart device according to the water and electricity data.
[0028] In addition, to achieve the above-mentioned objectives, the present invention also proposes a building operation device based on the BIM model, the device comprising: a memory, a processor, and a building operation program based on the BIM model stored in the memory and executable on the processor, the building operation program based on the BIM model being configured to implement the steps of the building operation system based on the BIM model as described above.
[0029] In addition, to achieve the above-mentioned objectives, the present invention also proposes a storage medium, on which a building operation program based on the BIM model is stored. When the building operation program based on the BIM model is executed by a processor, the steps of the building operation system based on the BIM model as described above are implemented.
[0030] The building operation system based on the BIM model of the present invention includes a PLC controller, an edge computing gateway and a smart building operation system. The PLC controller is connected to the smart building operation system through an API interface, and the edge computing gateway is connected to the smart building operation system through a ModBus protocol. First, the PLC controller receives sensor data collected by sensors built into the building through a preset protocol, and determines control instructions according to the sensor data. The preset protocol includes a KNX protocol and a ModBus protocol. Then, the PLC controller controls the operation status of the equipment according to the control instruction, and sends the control instruction to the smart building operation system through an API interface. The equipment operation data is viewed through a visual operation and maintenance platform of the smart operation system. Finally, the edge computing gateway obtains the water and electricity data corresponding to the smart water and electricity meter equipment through active polling, and sends the water and electricity data to the smart building operation system through the ModBus protocol, so that the command and operation service platform of the smart building operation system can realize the energy consumption target control of the smart device according to the water and electricity data. Compared with the prior art where the BIM model is disconnected from the operation and maintenance stage, resulting in a large amount of building and equipment facility data in the BIM model being unable to be applied to the operation and maintenance stage, the present invention extends the application scope of BIM model data to the operation and maintenance stage, and combines digital, information and intelligent technologies to effectively reduce building energy consumption, improve the intelligence level of buildings, and realize visual, low-carbon and intelligent operation and maintenance of buildings. BRIEF DESCRIPTION OF THE DRAWINGS
[0031] Figure 1 It is a structural diagram of a building operation device based on a BIM model in a hardware operating environment involved in an embodiment of the present invention;
[0032] Figure 2 It is a structural block diagram of a first embodiment of a building operation system based on a BIM model of the present invention;
[0033] Figure 3 It is an overall system block diagram of the first embodiment of the building operation system based on the BIM model of the present invention;
[0034] Figure 4 A block diagram of a PCL controller connection system of a first embodiment of a building operation system based on a BIM model of the present invention;
[0035] Figure 5 A block diagram of a human presence sensor system of a first embodiment of a building operation system based on a BIM model of the present invention;
[0036] Figure 6 This is a block diagram of an air quality sensor system of a first embodiment of a building operation system based on a BIM model of the present invention;
[0037] Figure 7 A block diagram of a smart water and electricity meter system according to a first embodiment of a building operation system based on a BIM model of the present invention;
[0038] Figure 8 A block diagram of a smart building operation system according to a first embodiment of a building operation system based on a BIM model of the present invention;
[0039] Fig. 9 It is a flowchart of the first embodiment of the building operation method based on the BIM model of the present invention.
[0040] The realization of the purpose, functional features and advantages of the present invention will be further explained in conjunction with embodiments and with reference to the accompanying drawings. DETAILED DESCRIPTION
[0041] It should be understood that the specific embodiments described herein are only used to explain the present invention, and are not used to limit the present invention.
[0042] Reference Figure 1 , Figure 1 The present invention is a schematic diagram of a building operation equipment structure based on a BIM model in a hardware operating environment according to an embodiment of the present invention.
[0043] like Figure 1 As shown, the building operation equipment based on the BIM model may include: a processor 1001, such as a central processing unit (CPU), a communication bus 1002, a user interface 1003, a network interface 1004, and a memory 1005. Among them, the communication bus 1002 is used to realize the connection and communication between these components. The user interface 1003 may include a display screen (Display), an input module such as a keyboard (Keyboard), and the optional user interface 1003 may also include a standard wired interface and a wireless interface. The network interface 1004 may optionally include a standard wired interface and a wireless interface (such as a wireless fidelity (Wireless-Fidelity, Wi-Fi) interface). The memory 1005 may be a high-speed random access memory (Random Access Memory, RAM), or a stable non-volatile memory (Non-Volatile Memory, NVM), such as a disk storage. The memory 1005 may also be a storage system independent of the aforementioned processor 1001.
[0044] Those skilled in the art will understand that Figure 1The structure shown in the figure does not constitute a limitation on the building operation equipment based on the BIM model, and may include more or less components than shown in the figure, or a combination of certain components, or a different arrangement of components.
[0045] like Figure 1 As shown, the memory 1005 as a storage medium may include an operating system, a network communication module, a user interface module, and a building operation program based on a BIM model.
[0046] exist Figure 1 In the BIM model-based building operation equipment shown, the network interface 1004 is mainly used for data communication with the network server; the user interface 1003 is mainly used for data interaction with the user; the processor 1001 and the memory 1005 in the BIM model-based building operation equipment of the present invention can be set in the BIM model-based building operation equipment, and the BIM model-based building operation equipment calls the BIM model-based building operation program stored in the memory 1005 through the processor 1001, and executes the BIM model-based building operation system provided by the embodiment of the present invention.
[0047] The embodiment of the present invention provides a building operation system based on the BIM model, referring to Figure 2 , Figure 2 This is a structural block diagram of the first embodiment of the building operation system based on the BIM model of the present invention.
[0048] In this embodiment, the building operation system based on the BIM model includes a PLC controller 2001, an edge computing gateway 2002 and a smart building operation system 2003. The PLC controller 2001 is connected to the smart building operation system 2003 through an API interface, and the edge computing gateway 2002 is connected to the smart building operation system 2003 through a Mod Bus protocol.
[0049] In the specific implementation, refer to Figure 3 , Figure 3 This is an overall system block diagram of the first embodiment of the building operation system based on the BIM model of the present invention, which includes human presence sensors, air quality sensors, VRV air conditioners, BACNET gateways, PLC controllers, smart water and electricity meters, edge computing gateways, lighting systems, ventilation systems, intelligent subsystems and API interfaces, lightweight BIM workstations, smart building operation systems and servers.
[0050] The smart building operation system includes three platforms: a BIM-based visual operation and maintenance platform, a command and operation service platform, and a mobile comprehensive application platform. It integrates lightweight BIM models and data, key data API interfaces of each subsystem, Internet of Things technology, PLC control system, energy consumption prediction algorithm, and intelligent equipment control.
[0051] It should also be noted that the human presence sensor and air quality sensor are connected to the PLC controller via the communication bus. VRV air conditioner is connected to the PLC via the BACNET gateway. The smart water and electricity meter is connected to the edge computing gateway via the RS485 port. The PLC controller output is connected to the lighting system IO switch module via the communication bus, and the PLC controller output is connected to the ventilation system control panel via the RS485 port. The PLC controller is connected to the switch via the network cable, and the data is transmitted to the top-level application server via the data middle station. Each intelligent subsystem is connected to the top-level application server via the Http network API interface, and the data is sent to the top-level application server via the data middle station. The lightweight BIM workstation is located on the top-level application server, refer to Figure 4 , Figure 4 This is a block diagram of the PCL controller connection system of the first embodiment of the building operation system based on the BIM model of the present invention.
[0052] It should be understood that three-dimensional models of the terminal points of the building, structure, HVAC, water supply and drainage, electrical, and intelligent subsystems are established based on the design drawings of various disciplines. According to operational needs, specific information is filled into the corresponding model to form a model and a corresponding database. The lightweight BIM model workstation is integrated into the smart building operation system, and displays each subsystem model and the corresponding equipment operation data in a three-dimensional visual form. Operators can use the visual operation and maintenance platform of the smart building operation system to realize functions such as equipment operation status viewing, equipment control, and data aggregation, thereby realizing three-dimensional visual operation and maintenance based on BIM.
[0053] After receiving the drawings of architecture, structure, various electromechanical disciplines, and various intelligent subsystems, the lightweight BIM model workstation uses BIM three-dimensional modeling to form a three-dimensional model based on professional classification. The model contains the key data of each discipline. After the digital-analog separation operation, a lightweight BIM model and database are formed.
[0054] Furthermore, after receiving the design drawings of the building, structure, various mechanical and electrical disciplines, and intelligent subsystems, a three-dimensional model of the terminal points of the building, structure, HVAC, water supply and drainage, electrical, and intelligent subsystems is established based on the Revit software. The model contains key data such as various professional building components and equipment. Based on the data export function of the Revit software, the model data is exported by category to form a database corresponding to the component ID. At the same time, the Revit software is used to export the model to a file in fbx format to form a lightweight BIM model.
[0055] The PLC controller 2001 is used to receive sensor data collected by sensors built into the building through a preset protocol, and determine control instructions according to the sensor data. The preset protocol includes the KNX protocol and the ModBus protocol.
[0056] The PLC controller 2001 is also used to control the equipment operation status according to the control instruction, and send the control instruction to the smart building operation system 2003 through the API interface, and view the equipment operation data through the visual operation and maintenance platform of the smart operation system.
[0057] Sensors built into the building include a human presence sensor (model MTN630819) and an air quality sensor (model WL-QV3210AL).
[0058] In a specific implementation, the building operation system based on the BIM model also includes a human presence sensor and an IO switch module; the human presence sensor is used to obtain human activity signal data in the sensing area in real time, and send the human activity signal data to the PLC controller through the KNX protocol; the PLC controller is used to determine the IO switch control instructions based on the human activity signal data, and send the IO switch control instructions to the IO switch module; the IO switch module is used to control the lighting switch of the lighting system according to the IO switch control instructions.
[0059] The personnel activity signal data includes personnel presence signal data and personnel absence signal data, wherein the personnel presence signal data also includes personnel presence area signal data. The IO switch control instruction includes the IO switch control lighting system on instruction and the IO switch control lighting system off instruction.
[0060] Furthermore, the building operation system based on the BIM model also includes an air quality sensor and a fan control panel; the air quality sensor is used to collect indoor carbon dioxide concentration data or PM2.5 concentration data in real time, and when the indoor carbon dioxide concentration is greater than the warning upper limit or the PM2.5 concentration is less than the warning lower limit, the indoor carbon dioxide concentration data or PM2.5 concentration data is sent to the PLC controller through the ModBus protocol; the PLC controller is also used to determine ventilation control instructions based on the indoor carbon dioxide concentration data or PM2.5 concentration data, and send the ventilation control instructions to the fan control panel through the ModBus protocol; the fan control panel is used to control the wind speed mode of the ventilation system according to the ventilation control instructions.
[0061] The warning upper limit value and the warning lower limit value are user-defined settings, and this embodiment does not limit them.
[0062] Furthermore, the building operation system based on the BIM model also includes BACNET gateway and VRV air conditioner;
[0063] The PLC controller is also used to generate an air-conditioning linkage instruction when detecting that the lighting is turned on, and send the air-conditioning linkage instruction to the BACNET gateway through the BACNET protocol; the BACNET gateway is used to control the operating status of the VRV air-conditioner according to the air-conditioning linkage instruction.
[0064] In this embodiment, reference Figure 5 and Figure 6 , Figure 5 This is a block diagram of a human presence sensor system of a first embodiment of a building operation system based on a BIM model of the present invention. Figure 6 This is a block diagram of the air quality sensor system of the first embodiment of the building operation system based on the BIM model of the present invention. When the human presence sensor senses the presence / absence of human activity in the area, it is transmitted to the PLC controller in the form of the KNX protocol, and the PLC internal program outputs the on / off command to the IO switch module, so that the relay in the IO module is energized / disconnected. Since the internal relay of the IO switch module is connected in series to the light control circuit, the lighting switch can be controlled, and the air conditioning control command is linked to the output through the BACNET gateway to the VRV air conditioning control panel to turn on the air conditioning in the corresponding area. At the same time, the data is updated to the smart building operation system, and the operation and maintenance personnel can see the start and stop status of the corresponding equipment on the BIM-based visual operation and maintenance platform. When the air quality sensor detects that the carbon dioxide concentration or PM2.5 concentration in the indoor air exceeds the upper warning limit or is lower than the lower warning limit, the data of the air quality sensor is transmitted to the PLC controller in the form of ModBus protocol. The PLC outputs ventilation control instructions according to the internal program logic. The control instructions are sent to the ventilation system control panel in the ModBus protocol to increase or decrease the wind speed of the ventilation system. Under the premise of meeting the indoor air quality standards, energy consumption can be reduced. At the same time, the PLC will feed back the air quality data and the status of the fan to the command building operation system in real time.
[0065] The edge computing gateway 2002 is used to obtain the water and electricity data corresponding to the smart water and electricity meter equipment through active polling, and send the water and electricity data to the smart building operation system 2003 through the ModBus protocol, so that the command and operation service platform of the smart building operation system 2003 can realize the energy consumption target control of the smart device according to the water and electricity data.
[0066] It should also be understood that smart devices can be understood as air-conditioning equipment, lighting equipment, ventilation equipment, etc. The operating status of air-conditioning equipment, lighting equipment, ventilation equipment, etc. can be controlled according to water and electricity data, thereby achieving energy consumption control.
[0067] Furthermore, the edge computing gateway 2002 is used to obtain the water and electricity data corresponding to the smart water and electricity meter equipment through active polling, and send the water and electricity data to the smart building operation system 2003 through the ModBus protocol; the smart building operation system 2003 is used to obtain the energy consumption prediction value based on the water and electricity data through the energy prediction algorithm based on the command and operation service platform, and realize the energy consumption target control of the smart device according to the energy consumption prediction value.
[0068] The smart building operation system 2003 is also used to obtain the operation data corresponding to the video surveillance system, access control system and parking management system through the API interface, and view the visual information corresponding to the operation data through the visual operation and maintenance platform.
[0069] In this embodiment, reference Figure 7 , Figure 7 This is a block diagram of the smart water and electricity meter system of the first embodiment of the building operation system based on the BIM model of the present invention. The smart water meter is connected to the edge computing gateway via the RS485 port. The edge computing gateway actively polls the data of each water and electricity meter and sends it to the smart building operation system through the data center. The system integrates various sub-modules of energy management and energy prediction algorithms. The energy prediction algorithm is based on the random forest algorithm and the XGBOOST algorithm. It takes all the energy consumption data of the building throughout the year as input, and thus derives the energy consumption forecast value for each month in the next year, assisting the operation and maintenance personnel in formulating an overall operation and maintenance plan; at the same time, it combines the Internet of Things technology and BIM technology to realize automatic equipment control based on energy consumption targets.
[0070] It should also be noted that the key operation data of the three subsystems (video surveillance system, access control system, and parking management system) are obtained through the standard API interface of the http protocol. The smart building operation system obtains real-time monitoring images and video playback from the video surveillance system; obtains information on people entering and leaving the access control system, and obtains parking space occupancy status and in-and-out vehicle information from the parking management system. The data of different systems are concentrated on one platform, thereby improving data integration and operational work efficiency.
[0071] In this embodiment, reference Figure 8 , Figure 8 This is a block diagram of the smart building operation system of the first embodiment of the building operation system based on the BIM model of the present invention. After the lightweight model is processed by the graphics engine, it is integrated into the smart building operation system, and each subsystem model and the corresponding equipment operation data are displayed in a three-dimensional visualization form.
[0072] The smart building operation system includes three platforms: a BIM-based visual operation and maintenance platform, a command and operation service platform, and a mobile terminal comprehensive application platform. It integrates lightweight BIM models and data, key data API interfaces of each subsystem, Internet of Things technology, PLC control system, energy consumption prediction algorithm, and intelligent equipment control algorithm.
[0073] The BIM-based visual operation and maintenance platform includes: data overview, equipment management, smart security, space management, and energy management.
[0074] The command and operation service platform includes: smart IoT, property work orders, workbench, system management, and resource management.
[0075] The comprehensive mobile application platform includes: contactless access, public area reservation, visitor registration, item release, daily repair reporting, smart device management, smart restaurant, and workbench.
[0076] Operators can use the visual operation and maintenance platform of the smart building operation system to view equipment operating status, control equipment, summarize data, and achieve three-dimensional visual operation and maintenance based on BIM.
[0077] In this embodiment, the building operation system based on the BIM model includes a PLC controller, an edge computing gateway and a smart building operation system. The PLC controller is connected to the smart building operation system through an API interface, and the edge computing gateway is connected to the smart building operation system through a ModBus protocol. First, the PLC controller receives sensor data collected by sensors built into the building through a preset protocol, and determines control instructions based on the sensor data. The preset protocols include the KNX protocol and the ModBus protocol. Then, the PLC controller controls the operation status of the equipment according to the control instructions, and sends the control instructions to the smart building operation system through the API interface. The equipment operation data is viewed through the visual operation and maintenance platform of the smart operation system. Finally, the edge computing gateway obtains the water and electricity data corresponding to the smart water and electricity meter equipment through active polling, and sends the water and electricity data to the smart building operation system through the ModBus protocol, so that the command and operation service platform of the smart building operation system can realize the energy consumption target control of the smart equipment according to the water and electricity data. Compared with the prior art where the BIM model is out of touch with the operation and maintenance stage, resulting in a large amount of building and equipment facility data in the BIM model being unable to be applied to the operation and maintenance stage, this embodiment extends the application scope of BIM model data to the operation and maintenance stage, and combines digital, information, and intelligent technologies to effectively reduce building energy consumption, improve the building's intelligence level, and realize building visualization, low-carbon, and intelligent operation and maintenance.
[0078] Reference Fig. 9 , Fig. 9 It is a flowchart of the first embodiment of the building operation method based on the BIM model of the present invention.
[0079] like Fig. 9 As shown, the building operation method based on the BIM model proposed in the embodiment of the present invention includes the following steps:
[0080] Step S10: The PLC controller receives sensor data collected by sensors built into the building through a preset protocol, and determines control instructions according to the sensor data. The preset protocol includes the KNX protocol and the ModBus protocol.
[0081] Step S20: The PLC controller controls the equipment operation status according to the control instruction, and sends the control instruction to the smart building operation system through the API interface, and checks the equipment operation data through the visual operation and maintenance platform of the smart operation system.
[0082] Step S30: The edge computing gateway obtains the water and electricity data corresponding to the smart water and electricity meter device through active polling, and sends the water and electricity data to the smart building operation system through the ModBus protocol, so that the command and operation service platform of the smart building operation system can realize the energy consumption target control of the smart device according to the water and electricity data.
[0083] In this embodiment, the building operation system based on the BIM model includes a PLC controller, an edge computing gateway and a smart building operation system. The PLC controller is connected to the smart building operation system through an API interface, and the edge computing gateway is connected to the smart building operation system through a ModBus protocol. First, the PLC controller receives sensor data collected by sensors built into the building through a preset protocol, and determines control instructions based on the sensor data. The preset protocols include the KNX protocol and the ModBus protocol. Then, the PLC controller controls the operation status of the equipment according to the control instructions, and sends the control instructions to the smart building operation system through the API interface. The equipment operation data is viewed through the visual operation and maintenance platform of the smart operation system. Finally, the edge computing gateway obtains the water and electricity data corresponding to the smart water and electricity meter equipment through active polling, and sends the water and electricity data to the smart building operation system through the ModBus protocol, so that the command and operation service platform of the smart building operation system can realize the energy consumption target control of the smart equipment according to the water and electricity data. Compared with the prior art where the BIM model is out of touch with the operation and maintenance stage, resulting in a large amount of building and equipment facility data in the BIM model being unable to be applied to the operation and maintenance stage, this embodiment extends the application scope of BIM model data to the operation and maintenance stage, and combines digital, information, and intelligent technologies to effectively reduce building energy consumption, improve the building's intelligence level, and realize building visualization, low-carbon, and intelligent operation and maintenance.
[0084] It should be noted that, in this article, the terms "include", "comprises" or any other variations thereof are intended to cover non-exclusive inclusion, so that a process, method, article or system including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or system. In the absence of further restrictions, an element defined by the sentence "comprises a ..." does not exclude the existence of other identical elements in the process, method, article or system including the element.
[0085] The serial numbers of the above embodiments of the present invention are only for description and do not represent the advantages or disadvantages of the embodiments.
[0086] Through the description of the above implementation methods, those skilled in the art can clearly understand that the above-mentioned embodiment methods can be implemented by means of software plus a necessary general hardware platform, and of course by hardware, but in many cases the former is a better implementation method. Based on such an understanding, the technical solution of the present invention, or the part that contributes to the prior art, can be embodied in the form of a software product, which is stored in a storage medium (such as a read-only memory / random access memory, a magnetic disk, or an optical disk), and includes a number of instructions for a terminal device (which can be a mobile phone, a computer, a server, or a network device, etc.) to execute the methods described in each embodiment of the present invention.
[0087] The above are only preferred embodiments of the present invention, and are not intended to limit the patent scope of the present invention. Any equivalent structure or equivalent process transformation made using the contents of the present invention specification and drawings, or directly or indirectly applied in other related technical fields, are also included in the patent protection scope of the present invention.
Claims
1. A building operation system based on BIM model, characterized in that: The building operation system based on the BIM model includes a PLC controller, an edge computing gateway and a smart building operation system, wherein the PLC controller is connected to the smart building operation system through an API interface, and the edge computing gateway is connected to the smart building operation system through a ModBus protocol; The PLC controller is used to receive sensor data collected by sensors built into the building through a preset protocol, and determine control instructions according to the sensor data, wherein the preset protocol includes the KNX protocol and the ModBus protocol; The PLC controller is further used to control the operation state of the equipment according to the control instruction, and send the control instruction to the smart building operation system through the API interface, and view the equipment operation data through the visual operation and maintenance platform of the smart operation system; The edge computing gateway is used to obtain the water and electricity data corresponding to the smart water and electricity meter equipment through active polling, and send the water and electricity data to the smart building operation system through the ModBus protocol, so that the command and operation service platform of the smart building operation system can realize the energy consumption target control of the smart device according to the water and electricity data.
2. The system according to claim 1, characterized in that The BIM model-based building operation system also includes a human presence sensor and an IO switch module; The human presence sensor is used to obtain the human activity signal data in the sensing area in real time, and send the human activity signal data to the PLC controller through the KNX protocol; The PLC controller is used to determine the IO switch control instruction according to the personnel activity signal data, and send the IO switch control instruction to the IO switch module; The IO switch module is used to control the lighting switch of the lighting system according to the IO switch control instruction.
3. The system according to claim 2, characterized in that The BIM model-based building operation system also includes an air quality sensor and a fan control panel; The air quality sensor is used to collect indoor carbon dioxide concentration data or PM2.5 concentration data in real time, and when the indoor carbon dioxide concentration is greater than the warning upper limit or the PM2.5 concentration is less than the warning lower limit, the indoor carbon dioxide concentration data or the PM2.5 concentration data is sent to the PLC controller through the ModBus protocol; The PLC controller is further used to determine a ventilation control instruction according to the indoor carbon dioxide concentration data or the PM2.5 concentration data, and send the ventilation control instruction to the fan control panel through the ModBus protocol; The fan control panel is used to control the wind speed mode of the ventilation system according to the ventilation control instruction.
4. The system according to claim 2, characterized in that The BIM model-based building operation system also includes a BACNET gateway and a VRV air conditioner; The PLC controller is further configured to generate an air conditioning linkage instruction when detecting that the lighting is turned on, and send the air conditioning linkage instruction to the BACNET gateway via the BACNET protocol; The BACNET gateway is used to control the operating state of the VRV air conditioner according to the air conditioner linkage instruction.
5. The system according to any one of claims 1 to 4, characterized in that: The edge computing gateway is used to obtain water and electricity data corresponding to the smart water and electricity meter device through active polling, and send the water and electricity data to the smart building operation system through the ModBus protocol; The smart building operation system is used to obtain energy consumption prediction values according to the water and electricity data through an energy prediction algorithm based on the command and operation service platform, and to achieve energy consumption target control of smart devices according to the energy consumption prediction values.
6. The system according to claim 5, characterized in that The smart building operation system is also used to obtain the operation data corresponding to the video surveillance system, access control system and parking management system through the API interface, and view the visual information corresponding to the operation data through the visual operation and maintenance platform.
7. A building operation method based on BIM model, characterized in that: The building operation method based on the BIM model comprises the following steps: The PLC controller receives sensor data collected by sensors built into the building through a preset protocol, and determines control instructions according to the sensor data, wherein the preset protocol includes a KNX protocol and a ModBus protocol; The PLC controller controls the operation state of the equipment according to the control instruction, and sends the control instruction to the smart building operation system through the API interface, and checks the equipment operation data through the visual operation and maintenance platform of the smart operation system; The edge computing gateway obtains the water and electricity data corresponding to the smart water and electricity meter device through active polling, and sends the water and electricity data to the smart building operation system through the ModBus protocol, so that the command and operation service platform of the smart building operation system can realize the energy consumption target control of the smart device according to the water and electricity data.
8. A building operation equipment based on BIM model, characterized in that: The device includes: a memory, a processor, and a BIM model-based building operation program stored in the memory and executable on the processor, wherein the BIM model-based building operation program is configured to implement the steps of the BIM model-based building operation system as described in any one of claims 1 to 6.
9. A storage medium, characterized in that: The storage medium stores a building operation program based on the BIM model, and when the building operation program based on the BIM model is executed by the processor, the steps of the building operation system based on the BIM model as described in any one of claims 1 to 6 are implemented.
Citation Information
Patent Citations
Intelligent operation and maintenance platform based on BIM and RFID
CN110046718A
Building energy internet intelligent operation cloud operation system
CN110225075A
Building management system with space profiles
CN110709786A
Railway station building construction equipment monitoring and energy management system, program and storage medium
CN112394697A
Intelligent building integrated management platform based on BIM
CN114139950A