Water and electricity pipeline monitoring method, system and equipment based on BIM (Building Information Modeling) and medium

Through the BIM-based water and electricity pipeline line monitoring method, we organize and analyze historical data, determine the location of monitoring points, and use BIM technology to build pipeline models, which solves the problem in the existing technology that manual inspections and local sensors are difficult to monitor hidden pipelines, and achieves Effective monitoring and management of pipeline status.

CN118734024APending Publication Date: 2024-10-01SHANDONG ZHONGBANG CONSTRUCTION ENGINEERING GROUP CO LTD
View PDF 0 Cites 2 Cited by

Patent Information

Application Number
CN202410770475.2
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-06-14
Publication Date
2024-10-01

AI Technical Summary

Technical Problem

Existing water and electricity pipeline line monitoring methods rely on manual inspections and local sensors, which makes it difficult to effectively monitor hidden or hard-to-reach pipeline parts, and local sensors cannot fully reflect the pipeline status.

Method used

The water and electricity pipeline line monitoring method based on BIM is used to obtain pipeline parameters and historical monitoring data, organize them into first-level, second-level, and third-level data matrices, analyze abnormal data, determine the location of monitoring points, and use BIM technology to build pipeline models and receive Sensor data is bound to achieve real-time monitoring of pipeline status.

Benefits of technology

It improves the monitoring efficiency of water and electricity pipelines, can effectively identify pipeline abnormalities, provides detailed pipeline status information, and enhances the reliability of pipeline management.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118734024A_ABST
    Figure CN118734024A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of line monitoring, in particular to a BIM-based water and electricity pipeline monitoring method, system and device and a medium, and the method comprises the steps: obtaining to-be-monitored pipeline parameters, a pipeline application scene and historical monitoring data, carrying out the data arrangement of the historical monitoring data, obtaining a first-stage pipeline data matrix, and obtaining a second-stage pipeline data matrix; determining a historical analysis result based on the first-level pipeline data matrix, determining environmental information of historical monitoring data, binding the environmental information with the second-level pipeline data matrix to obtain a third-level pipeline data matrix, analyzing the third-level pipeline data matrix to obtain the position of a monitoring point, modeling a water and electricity pipeline line by adopting a BIM technology, and obtaining the monitoring point position of the water and electricity pipeline line. The method comprises the steps of obtaining a water and electricity pipeline model, receiving pipeline monitoring data sent by a monitoring sensor located at a monitoring point position, determining a pipeline node corresponding to the monitoring point position in the water and electricity pipeline model, and binding the pipeline monitoring data with the pipeline node. The monitoring efficiency of the water and electricity pipelines is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of line monitoring, and in particular to a BIM-based water and electricity pipe line monitoring method, system, equipment and medium. Background Art

[0002] In the construction industry, monitoring of water and electricity pipelines is a key link to ensure the safe operation of buildings. However, the currently widely used manual inspection and local sensor monitoring methods have obvious shortcomings. Manual inspections are limited by the experience and observation of inspectors, and the inspection effect is often greatly reduced for hidden or difficult-to-reach pipelines. Although local sensors can provide real-time data feedback, the monitoring data of local sensors cannot fully reflect the status of water and electricity pipelines due to the inability to effectively select the location of monitoring points. Summary of the invention

[0003] In order to solve at least one of the above technical problems, the present application provides a BIM-based water and electricity pipeline monitoring method, system, equipment and medium.

[0004] In the first aspect, the present application provides a water and electricity pipeline monitoring method based on BIM, which adopts the following technical solution: Acquire pipeline parameters to be monitored, pipeline application scenarios corresponding to the pipeline parameters to be monitored, and historical monitoring data corresponding to the pipeline application scenarios; The historical monitoring data are sorted according to timestamps, pipeline transportation categories, and pipeline correlation levels to obtain a primary pipeline data matrix; Determine a historical analysis result based on the primary pipeline data matrix, determine whether there is pipeline abnormality data in the primary pipeline data matrix according to the historical analysis result, and if so, determine the pipeline abnormality degree of the pipeline abnormality data according to the historical analysis result; Binding the pipeline abnormality degree to the corresponding data nodes of the primary pipeline data matrix to obtain a secondary pipeline data matrix after binding; Determine the environmental information when the node data of different pipeline positions in the historical monitoring data is generated based on the pipeline application scenario, and bind the environmental information with the corresponding data nodes in the secondary pipeline data matrix to obtain a third-level pipeline data matrix after binding processing; Perform pipeline abnormal position distribution node analysis on the three-level pipeline data matrix to obtain the monitoring point position; Based on the pipeline parameters to be monitored, the water and electricity pipeline line is modeled using BIM technology to obtain a water and electricity pipeline model; Receive pipeline monitoring data sent by a monitoring sensor located at the monitoring point, determine a pipeline node corresponding to the monitoring point in the water and electricity pipeline model, and bind the pipeline monitoring data to the pipeline node.

[0005] In a possible implementation, the performing pipeline abnormal position distribution node analysis on the three-level pipeline data matrix to obtain the monitoring point position includes: Performing a two-dimensional coordinate change on the three-level pipeline data matrix to obtain a two-dimensional data graph corresponding to the three-level pipeline data matrix; Determine the pipeline data map point corresponding to each node data in the historical monitoring data according to the data two-dimensional map, wherein the pipeline data map point includes data coordinates of the node data, data scene characteristics, data environment characteristics, and data abnormality characteristics; Determine a second pipeline data map point according to the timestamp, and use the second pipeline data map point as the starting map point to perform adjacent map point calculations to obtain a data difference set between each pipeline data map point and the pipeline data map point of the adjacent previous node; Matching the difference in the data difference set with the preset difference interval to obtain the data weight corresponding to each pipeline data map point; Determine whether the data weight meets the preset data weight. If so, use the node of the node data corresponding to the data weight as the monitoring point position.

[0006] In a possible implementation, performing a two-dimensional coordinate change on the three-level pipeline data matrix to obtain a two-dimensional data graph corresponding to the three-level pipeline data matrix includes: Establishing a time coordinate system, wherein the X-axis of the time coordinate system represents different unit times, and the Y-axis of the time coordinate system represents pipeline data corresponding to different pipeline position nodes in different unit times; The data in the three-level pipeline data matrix is ​​added to the time coordinate system according to the time nodes to obtain a two-dimensional data graph.

[0007] In a possible implementation, the calculation of adjacent map points is performed with the second pipeline data map point as the starting map point to obtain a data difference set between each pipeline data map point and the pipeline data map point of the adjacent previous node, including: Classify the pipeline data map points into scene categories according to the data scene characteristics to obtain pipeline data map point groups of different scenes; Dividing the pipeline data map point group into environmental categories according to the data environment characteristics to obtain pipeline data map point groups under different environments; Positioning the second pipeline data map point in each pipeline data map point group respectively, performing difference calculation between the data in the second pipeline data map point and the data in the first pipeline data map point in the same pipeline data map point group to obtain a first data difference; After the difference between the data in the second pipeline data map point and the data in the first pipeline data map point is calculated, the difference determination step is executed cyclically until the difference corresponding to all data points in the pipeline data map point group except the first pipeline data map point is obtained, and the difference corresponding to all data points in the pipeline data map point group except the first pipeline data map point is summarized to obtain a data difference set.

[0008] In one possible implementation, the difference determination step includes: Determine the second pipeline data map point as a target pipeline data map point, calculate the difference between data in the target pipeline data map point and data in a previous pipeline data map point of the target pipeline data map point, and obtain a first data difference; After the difference calculation is performed on the data in the second pipeline data map point and the data in the first pipeline data map point, the next pipeline data map point of the target pipeline data map point is used as the new target pipeline data map point and the difference calculation is performed on the data in the previous pipeline data map point of the new target pipeline data map point to obtain the second data difference. The final target pipeline data map point is the Nth pipeline data map point, and N is the number of pipeline data map points in the pipeline data map point group.

[0009] In a possible implementation, the pipeline data map point group is divided into environment categories according to the data environment characteristics to obtain pipeline data map point groups under different environments, and then the method further includes: Determine whether the data anomaly feature exists in the pipeline data map point. If so, update the pipeline data map point grouping based on the position of the pipeline data map point with the data anomaly feature within the pipeline data map point grouping to obtain an updated pipeline data map point grouping.

[0010] In the second aspect, the present application provides a BIM-based water and electricity pipeline monitoring system, which adopts the following technical solutions: A water and electricity pipeline monitoring system based on BIM, comprising: A data acquisition module, used to acquire pipeline parameters to be monitored, pipeline application scenarios corresponding to the pipeline parameters to be monitored, and historical monitoring data corresponding to the pipeline application scenarios; A data sorting module is used to sort the historical monitoring data according to timestamps, pipeline transportation categories and pipeline correlation degrees to obtain a primary pipeline data matrix; an abnormality determination module, used to determine the historical analysis results based on the primary pipeline data matrix, determine whether there is pipeline abnormality data in the primary pipeline data matrix according to the historical analysis results, and if so, determine the pipeline abnormality degree of the pipeline abnormality data according to the historical analysis results; A node binding module is used to bind the pipeline abnormality degree to the corresponding data node of the primary pipeline data matrix to obtain a secondary pipeline data matrix after binding processing; An information determination module, used to determine the environmental information when the data of different pipeline location nodes in the historical monitoring data are generated based on the pipeline application scenario, and bind the environmental information with the corresponding data nodes in the secondary pipeline data matrix to obtain a tertiary pipeline data matrix after binding processing; A point analysis module is used to perform pipeline abnormal position distribution node analysis on the three-level pipeline data matrix to obtain the monitoring point position; A model building module, used to model the water and electricity pipeline line using BIM technology based on the pipeline parameters to be monitored to obtain a water and electricity pipeline model; The data fusion module is used to receive the pipeline monitoring data sent by the monitoring sensor located at the monitoring point, determine the pipeline node corresponding to the monitoring point in the water and electricity pipeline model, and bind the pipeline monitoring data to the pipeline node.

[0011] In a possible implementation, when the point analysis module performs pipeline abnormal position distribution node analysis on the three-level pipeline data matrix to obtain the monitoring point position, it is specifically used to: Performing a two-dimensional coordinate change on the three-level pipeline data matrix to obtain a two-dimensional data graph corresponding to the three-level pipeline data matrix; Determine the pipeline data map point corresponding to each node data in the historical monitoring data according to the data two-dimensional map, wherein the pipeline data map point includes data coordinates of the node data, data scene characteristics, data environment characteristics, and data abnormality characteristics; Determine a second pipeline data map point according to the timestamp, and use the second pipeline data map point as the starting map point to perform adjacent map point calculations to obtain a data difference set between each pipeline data map point and the pipeline data map point of the adjacent previous node; Matching the difference in the data difference set with the preset difference interval to obtain the data weight corresponding to each pipeline data map point; Determine whether the data weight meets the preset data weight. If so, use the node of the node data corresponding to the data weight as the monitoring point position.

[0012] In another possible implementation, when the point analysis module performs a two-dimensional coordinate change on the three-level pipeline data matrix to obtain a two-dimensional data graph corresponding to the three-level pipeline data matrix, it is specifically used to: Establishing a time coordinate system, wherein the X-axis of the time coordinate system represents different unit times, and the Y-axis of the time coordinate system represents pipeline data corresponding to different pipeline position nodes in different unit times; The data in the three-level pipeline data matrix is ​​added to the time coordinate system according to the time nodes to obtain a two-dimensional data graph.

[0013] In another possible implementation, when the point analysis module calculates adjacent map points with the second pipeline data map point as the starting map point to obtain a data difference set between each pipeline data map point and the pipeline data map point of the adjacent previous node, it is specifically used to: Classify the pipeline data map points into scene categories according to the data scene characteristics to obtain pipeline data map point groups of different scenes; Dividing the pipeline data map point group into environmental categories according to the data environment characteristics to obtain pipeline data map point groups under different environments; Positioning the second pipeline data map point in each pipeline data map point group respectively, performing difference calculation between the data in the second pipeline data map point and the data in the first pipeline data map point in the same pipeline data map point group to obtain a first data difference; After the difference between the data in the second pipeline data map point and the data in the first pipeline data map point is calculated, the difference determination step is executed cyclically until the difference corresponding to all data points in the pipeline data map point group except the first pipeline data map point is obtained, and the difference corresponding to all data points in the pipeline data map point group except the first pipeline data map point is summarized to obtain a data difference set.

[0014] In another possible implementation manner, the difference determining step includes: Determine the second pipeline data map point as a target pipeline data map point, calculate the difference between data in the target pipeline data map point and data in a previous pipeline data map point of the target pipeline data map point, and obtain a first data difference; After the difference calculation is performed on the data in the second pipeline data map point and the data in the first pipeline data map point, the next pipeline data map point of the target pipeline data map point is used as the new target pipeline data map point and the difference calculation is performed on the data in the previous pipeline data map point of the new target pipeline data map point to obtain the second data difference. The final target pipeline data map point is the Nth pipeline data map point, and N is the number of pipeline data map points in the pipeline data map point group.

[0015] In another possible implementation, the system further includes: an update module, wherein: The updating module is used to determine whether the pipeline data map point has the data anomaly feature. If so, the pipeline data map point group is updated based on the position of the pipeline data map point with the data anomaly feature in the pipeline data map point group to obtain an updated pipeline data map point group.

[0016] On the third side, the present application provides an electronic device, which adopts the following technical solution: at least one processor; Memory; At least one application, wherein the at least one application is stored in a memory and configured to be executed by at least one processor, and the at least one application is configured to: execute a BIM-based water and electricity pipeline monitoring method as described in any one of the first aspects.

[0017] In a fourth aspect, the present application provides a computer-readable storage medium, which adopts the following technical solution: A computer-readable storage medium having a computer program stored thereon, which, when executed in a computer, causes the computer to execute the BIM-based water and electricity pipeline monitoring method as described in any one of the first aspects.

[0018] In summary, the present application includes at least one of the following beneficial technical effects: When monitoring the water and electricity pipeline, the pipeline parameters to be monitored, the pipeline application scenarios corresponding to the pipeline parameters to be monitored, and the historical monitoring data corresponding to the pipeline application scenarios are obtained, and then the historical monitoring data are sorted according to the timestamp, pipeline transportation category, and pipeline correlation degree to obtain a first-level pipeline data matrix, and then the historical analysis results are determined based on the first-level pipeline data matrix. According to the historical analysis results, it is determined whether there is pipeline abnormal data in the first-level pipeline data matrix. If so, the pipeline abnormality degree of the pipeline abnormal data is determined through the historical analysis results, and then the pipeline abnormality degree is bound to the corresponding data node of the first-level pipeline data matrix to obtain the second-level pipeline data matrix after binding processing, and then different pipeline abnormalities in the historical monitoring data are determined based on the pipeline application scenario. The environmental information when the pipeline location node data is generated is obtained, and the environmental information is bound to the corresponding data nodes in the secondary pipeline data matrix to obtain the tertiary pipeline data matrix after binding processing, and then the pipeline abnormal position distribution node analysis is performed on the tertiary pipeline data matrix to obtain the monitoring point location, and then based on the pipeline parameters to be monitored, the water and electricity pipeline line is modeled using BIM technology to obtain a water and electricity pipeline model, and then the pipeline monitoring data sent by the monitoring sensor located at the monitoring point position is received, and the pipeline node corresponding to the monitoring point position in the water and electricity pipeline model is determined, and the pipeline monitoring data is bound to the pipeline node. The managers of the water and electricity pipeline line can understand whether there is any abnormality in the water and electricity pipeline line through the water and electricity pipeline model, thereby improving the monitoring efficiency of the water and electricity pipeline line. BRIEF DESCRIPTION OF THE DRAWINGS

[0019] Figure 1 A flow chart of a water and electricity pipeline monitoring method based on BIM provided in an embodiment of the present application.

[0020] Figure 2 A schematic structural diagram of a water and electricity pipeline monitoring system based on BIM provided in an embodiment of the present application.

[0021] Figure 3 A schematic diagram of the structure of an electronic device provided in an embodiment of the present application. DETAILED DESCRIPTION

[0022] The following is combined with Figure 1-3 This application is described in further detail.

[0023] This specific embodiment is merely an explanation of the present application and is not a limitation of the present application. After reading this specification, a person skilled in the art may make non-creative modifications to the present embodiment as needed, but such modifications are protected by the patent law as long as they are within the scope of the present application.

[0024] In order to make the purpose, technical solution and advantages of the embodiments of the present application clearer, the technical solution in the embodiments of the present application will be clearly and completely described below in conjunction with the drawings in the embodiments of the present application. Obviously, the described embodiments are part of the embodiments of the present application, not all of the embodiments. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of this application.

[0025] In addition, the term "and / or" in this article is only a description of the association relationship of associated objects, indicating that there can be three relationships. For example, A and / or B can represent: A exists alone, A and B exist at the same time, and B exists alone. In addition, the character " / " in this article, unless otherwise specified, generally means that the associated objects before and after are in an "or" relationship.

[0026] The embodiments of the present application are further described in detail below in conjunction with the drawings in the specification.

[0027] The embodiment of the present application provides a method for monitoring a water and electricity pipeline based on BIM, which is executed by an electronic device, which can be a server or a terminal device, wherein the server can be an independent physical server, or a server cluster or distributed system composed of multiple physical servers, or a cloud server that provides cloud computing services. The terminal device can be a smart phone, a tablet computer, a laptop computer, a desktop computer, etc., but is not limited thereto. The terminal device and the server can be directly or indirectly connected via wired or wireless communication, which is not limited in the embodiment of the present application. Figure 1 As shown, the method includes: Step S10: Acquire pipeline parameters to be monitored, pipeline application scenarios corresponding to the pipeline parameters to be monitored, and historical monitoring data corresponding to the pipeline application scenarios.

[0028] For the embodiments of the present application, the pipeline parameters to be monitored represent various attributes and characteristic data of the pipeline to be monitored, such as the length, diameter, material type of the pipeline, and real-time parameters such as pressure, temperature, flow rate, etc. during operation. The pipeline application scenario refers to the specific use conditions of the pipeline, which includes but is not limited to factors such as the geographical location of the pipeline, the burial depth, the surrounding soil conditions, and the type of medium transported by the pipeline. Historical monitoring data is used to represent the data records obtained from continuous or regular monitoring of the pipeline to be monitored over a period of time in the past. These data can reflect the status and behavior of the pipeline at different time points and are an important basis for analyzing pipeline performance and safety status.

[0029] Specifically, the real-time parameters of the pipeline to be monitored are obtained through professional equipment or systems, such as collecting data such as pressure and temperature of the pipeline through sensors. Then, according to the actual situation of the pipeline, its application scenario is recorded or identified, such as whether the pipeline is located underground in the city or in the wild, whether it is transporting crude oil or natural gas, etc. Finally, the historical monitoring data corresponding to these application scenarios is retrieved from the database or monitoring system.

[0030] Optionally, a sensor network installed on the pipeline is used to collect pipeline operating parameters such as pressure, temperature, flow, etc. in real time, and transmit these data to a central data processing system via a wireless communication network.

[0031] Optionally, the application scenario of the pipeline can be determined by consulting the engineering design drawings and construction records of the pipeline, including key information such as its geographical location, burial depth, and medium type.

[0032] Optionally, a historical database is accessed, which stores historical monitoring data of the pipeline in different application scenarios. By querying, historical data records matching the current pipeline application scenario can be obtained.

[0033] It is understandable that other methods may be used to obtain relevant data, such as through manual inspection records, third-party data service providers, etc., which are not limited here.

[0034] Step S11: sort the historical monitoring data according to timestamp, pipeline transportation category and pipeline correlation degree to obtain a primary pipeline data matrix.

[0035] Specifically, the timestamp refers to the specific time when the recorded data is generated, and the pipeline transportation category refers to the type of medium transported by the pipeline, such as oil, natural gas, water, etc. Different media types have different requirements and monitoring priorities for pipelines. The pipeline correlation degree is used to indicate the degree of mutual influence between different pipelines. For example, when carrying out long-distance transmission, there will be a process of splicing multiple pipelines. Although each pipeline is independent, when working together to complete the transportation task, the pipelines play a synergistic role. Therefore, the pipeline correlation degree between multiple pipelines is 100%. When there is a part of synergy between pipelines, the pipeline correlation degree is determined according to the proportion of synergy.

[0036] Specifically, the original historical monitoring data is collated and organized according to several key dimensions. The data is arranged in chronological order according to the timestamp information in the data record, which helps to observe and analyze the changes in pipeline status over time. Secondly, the data is classified according to the type of medium transported by the pipeline, because different media have different effects on pipeline corrosion, wear, etc. Finally, considering the degree of correlation between pipelines, for highly correlated pipelines, their data may need to be analyzed together to comprehensively evaluate the status of the entire pipeline network. Through such collation, a structured "first-level pipeline data matrix" can be obtained to facilitate subsequent data analysis and mining.

[0037] In some embodiments, historical monitoring data can be sorted according to timestamps, pipeline transportation categories, and pipeline association levels to obtain a primary pipeline data matrix: Optionally, first, extract the original records containing timestamps, pipeline transport categories, and monitoring data from the database. Then, use the data processing library in the programming language (such as Python's Pandas library) to sort the data by timestamp. Next, group the data according to the pipeline transport category. Finally, for each transport category, further subdivide the data according to the degree of pipeline association, thereby constructing a first-level pipeline data matrix.

[0038] Alternatively, another method is to use specialized data processing software or platforms, such as data warehouses or big data analysis platforms. By configuring the corresponding data processing flow, the data sorting work can be automatically completed and a structured first-level pipeline data matrix can be output.

[0039] It is understandable that other methods may be used to implement data organization, such as using SQL query language to directly complete data sorting, grouping and association operations in the database, which is not limited here.

[0040] Step S12: determine the historical analysis results based on the primary pipeline data matrix, and determine whether there is pipeline abnormality data in the primary pipeline data matrix according to the historical analysis results. If there is, determine the pipeline abnormality degree of the pipeline abnormality data according to the historical analysis results.

[0041] Specifically, this step is usually performed during the data analysis phase to identify and process abnormal data in the primary pipeline data matrix. This is critical to ensuring the safe and reliable operation of the pipeline system. First, in-depth data analysis is performed based on the primary pipeline data matrix, using statistical methods, machine learning algorithms, or other analytical tools to discover patterns, trends, and anomalies in the data. These analysis results will serve as an important basis for determining whether the pipeline is operating normally. Then, based on the historical analysis results, carefully check whether there is abnormal data in the data matrix. Abnormal data may appear as sudden data jumps, continuous values ​​higher or lower than expected, or behavior that does not conform to normal patterns. If abnormal data is found, historical analysis results will be further used to determine the extent of these anomalies. This involves a comprehensive evaluation of factors such as the number of abnormal data points, the magnitude of deviation from normal values, the duration, and the correlation with other abnormal points.

[0042] Optionally, use data analysis tools to perform statistical analysis on the primary pipeline data matrix to identify outliers or abnormal patterns in the data. Then, by comparing the differences between historical data and current data, and using preset thresholds or models, determine which data are abnormal. Finally, based on the deviation degree, frequency of occurrence and other characteristics of the abnormal data, quantify the degree of abnormality.

[0043] Alternatively, another approach is to apply machine learning algorithms, such as cluster analysis, anomaly detection algorithms, etc., to automatically identify and classify abnormal data in the data matrix. These algorithms can identify data points that do not conform to the normal pattern as anomalies by learning the normal pattern of the data. Subsequently, specific evaluation indicators or models can be used to determine the degree of abnormality of these abnormal data.

[0044] Step S13: Bind the pipeline abnormality degree to the corresponding data nodes of the primary pipeline data matrix to obtain a secondary pipeline data matrix after binding.

[0045] For the embodiment of the present application, the pipeline abnormality degree information obtained from the previous analysis is bound to the corresponding data points in the primary pipeline data matrix. The purpose is to add the dimension of abnormality degree on the basis of the original data, so that the data matrix not only contains the original data of monitoring, but also reflects the abnormal state of these data points. In this way, it is possible to more clearly understand which data points are abnormal and the severity of these abnormalities. The processed secondary pipeline data matrix will become an important basis for subsequent fault warnings, maintenance decisions, etc.

[0046] Specifically, a unique identifier for each data point in the primary pipeline data matrix is ​​determined, such as a combination of a timestamp and a pipeline number. Then, an abnormality degree value is assigned to each abnormal data point based on the historical analysis results. Next, a new data matrix is ​​created with the same structure as the primary pipeline data matrix, but with an additional column for storing the abnormality degree value. Finally, the primary pipeline data matrix is ​​traversed, and the abnormality degree value of each data point is filled into the corresponding position of the new matrix to form a secondary pipeline data matrix.

[0047] Step S14: determine the environmental information when the node data of different pipeline positions in the historical monitoring data is generated based on the pipeline application scenario, and bind the environmental information with the corresponding data nodes in the secondary pipeline data matrix to obtain a tertiary pipeline data matrix after binding processing.

[0048] Specifically, according to the pipeline application scenario, the environmental information of different pipeline location node data in the historical monitoring data is collected and analyzed. Then, this environmental information is bound to the corresponding data nodes in the secondary pipeline data matrix. This provides a more comprehensive data foundation for subsequent data analysis and decision support. The final third-level pipeline data matrix will contain the original monitoring data, abnormality information, and environmental information, providing strong data support for pipeline management.

[0049] Optionally, the environmental information is fused with the secondary pipeline data matrix using data fusion technology. First, the collected environmental data is preprocessed, such as cleaning, denoising, and standardization. Then, the environmental information is fused with the corresponding nodes in the secondary pipeline data matrix using an appropriate data fusion algorithm, such as timestamp-based fusion or spatial position-based fusion.

[0050] Step S15: Perform pipeline abnormal position distribution node analysis on the three-level pipeline data matrix to obtain the monitoring point location.

[0051] Specifically, the two-dimensional coordinates of the three-level pipeline data matrix are changed to obtain a two-dimensional data map corresponding to the three-level pipeline data matrix, and then the pipeline data map point corresponding to each node data in the historical monitoring data is determined according to the two-dimensional data map, and the pipeline data map point includes the data coordinates, data scene characteristics, data environment characteristics and data abnormal characteristics of the node data, and then the second pipeline data map point is determined according to the timestamp, and the adjacent map points are calculated with the second pipeline data map point as the starting map point to obtain a data difference set between each pipeline data map point and the pipeline data map point of the adjacent previous node, and then the difference in the data difference set is matched with the preset difference interval to obtain the data weight corresponding to each pipeline data map point, and then it is determined whether the data weight meets the preset data weight. If it meets, the node of the node data corresponding to the data weight is used as the monitoring point position.

[0052] In an embodiment of the present application, a two-dimensional coordinate change is performed on the three-level pipeline data matrix to obtain a two-dimensional data graph corresponding to the three-level pipeline data matrix, including: establishing a time coordinate system, the X-axis of the time coordinate system is different unit time, the Y-axis of the time coordinate system is the pipeline data corresponding to different pipeline position nodes in different unit time, and the data in the three-level pipeline data matrix is ​​added to the time coordinate system according to the time node correspondence to obtain a two-dimensional data graph.

[0053] Specifically, the pipeline data map points are divided into scene categories according to data scene characteristics to obtain pipeline data map point groups of different scenes, and then the pipeline data map point groups are divided into environment categories according to data environment characteristics to obtain pipeline data map point groups under different environments, and then the second pipeline data map point in each pipeline data map point group is located respectively, and the data in the second pipeline data map point in the same pipeline data map point group is calculated to obtain a first data difference, and then after the difference calculation is performed between the data in the second pipeline data map point and the data in the first pipeline data map point, the difference determination step is executed cyclically until the difference corresponding to all data points in the pipeline data map point group except the first pipeline data map point is obtained, and the difference corresponding to all data points in the pipeline data map point group except the first pipeline data map point is summarized to obtain a data difference set.

[0054] Among them, the difference determination step includes: determining the second pipeline data map point as the target pipeline data map point, calculating the difference between the data in the target pipeline data map point and the data in the previous pipeline data map point of the target pipeline data map point, and obtaining a first data difference; after the difference between the data in the second pipeline data map point and the data in the first pipeline data map point is calculated, the next pipeline data map point of the target pipeline data map point is used as a new target pipeline data map point and the difference between the data in the previous pipeline data map point of the new target pipeline data map point is calculated to obtain a second data difference, and the final target pipeline data map point is the Nth pipeline data map point, and N is the number of pipeline data map points in the pipeline data map point grouping.

[0055] Step S16: Based on the parameters of the pipeline to be monitored, the water and electricity pipeline line is modeled using BIM technology to obtain a water and electricity pipeline model.

[0056] Specifically, we use professional BIM software (such as Revit, Archicad, etc.) to build a 3D model of the water and electricity pipeline based on the collected parameters of the pipeline to be monitored. During the modeling process, we need to ensure that the position, size and attributes of each component are accurate. Finally, we verify and optimize the established model to ensure that it can meet the subsequent monitoring and analysis needs.

[0057] Step S17: receiving pipeline monitoring data sent by the monitoring sensor located at the monitoring point, determining the pipeline node corresponding to the monitoring point in the water and electricity pipeline model, and binding the pipeline monitoring data to the pipeline node.

[0058] In an embodiment of the present application, when monitoring a water and electricity pipeline, the pipeline parameters to be monitored, the pipeline application scenarios corresponding to the pipeline parameters to be monitored, and the historical monitoring data corresponding to the pipeline application scenarios are obtained, and then the historical monitoring data are sorted according to the timestamp, pipeline transportation category, and pipeline association degree to obtain a primary pipeline data matrix, and then the historical analysis results are determined based on the primary pipeline data matrix, and it is determined whether there is pipeline abnormal data in the primary pipeline data matrix according to the historical analysis results. If so, the pipeline abnormality degree of the pipeline abnormal data is determined according to the historical analysis results, and then the pipeline abnormality degree is bound to the corresponding data node of the primary pipeline data matrix to obtain the secondary pipeline data matrix after binding processing, and then the historical monitoring data is determined based on the pipeline application scenario. The environmental information when the node data of different pipeline positions is generated is obtained, and the environmental information is bound to the corresponding data nodes in the secondary pipeline data matrix to obtain the tertiary pipeline data matrix after binding processing, and then the pipeline abnormal position distribution node analysis is performed on the tertiary pipeline data matrix to obtain the monitoring point position, and then based on the pipeline parameters to be monitored, the water and electricity pipeline line is modeled using BIM technology to obtain a water and electricity pipeline model, and then the pipeline monitoring data sent by the monitoring sensor located at the monitoring point position is received, and the pipeline node corresponding to the monitoring point position in the water and electricity pipeline model is determined, and the pipeline monitoring data is bound to the pipeline node. The management personnel of the water and electricity pipeline line can understand whether there is any abnormality in the water and electricity pipeline line through the water and electricity pipeline model, thereby improving the monitoring efficiency of the water and electricity pipeline line.

[0059] Further, in an embodiment of the present application, the pipeline data map point group is divided into environmental categories according to the data environment characteristics to obtain pipeline data map point groups under different environments, and then it also includes: determining whether there are data abnormality features in the pipeline data map points, and if so, updating the pipeline data map point grouping based on the position of the pipeline data map point with the data abnormality features in the pipeline data map point grouping to obtain an updated pipeline data map point grouping.

[0060] The following is an introduction to a BIM-based water and electricity pipeline monitoring system provided in an embodiment of the present application. The BIM-based water and electricity pipeline monitoring system described below and the BIM-based water and electricity pipeline monitoring method described above can be referred to each other. Please refer to Figure 2 , Figure 2 : is a structural diagram of a BIM-based water and electricity pipeline monitoring system 20 provided in an embodiment of the present application, including: A data acquisition module 21 is used to acquire pipeline parameters to be monitored, pipeline application scenarios corresponding to the pipeline parameters to be monitored, and historical monitoring data corresponding to the pipeline application scenarios; The data sorting module 22 is used to sort the historical monitoring data according to the timestamp, pipeline transportation category and pipeline correlation degree to obtain a primary pipeline data matrix; The abnormality determination module 23 is used to determine the historical analysis results based on the primary pipeline data matrix, and determine whether there is pipeline abnormality data in the primary pipeline data matrix according to the historical analysis results. If there is, the pipeline abnormality degree of the pipeline abnormality data is determined according to the historical analysis results; The node binding module 24 is used to bind the pipeline abnormality degree to the corresponding data node of the primary pipeline data matrix to obtain the secondary pipeline data matrix after binding processing; The information determination module 25 is used to determine the environmental information when the node data of different pipeline positions in the historical monitoring data is generated based on the pipeline application scenario, and bind the environmental information with the corresponding data nodes in the secondary pipeline data matrix to obtain the tertiary pipeline data matrix after binding processing; The point analysis module 26 is used to analyze the pipeline abnormal position distribution nodes on the three-level pipeline data matrix to obtain the monitoring point position; A model building module 27 is used to model the water and electricity pipeline line based on the parameters to be monitored using BIM technology to obtain a water and electricity pipeline model; The data fusion module 28 is used to receive the pipeline monitoring data sent by the monitoring sensor located at the monitoring point, determine the pipeline node corresponding to the monitoring point in the water and electricity pipeline model, and bind the pipeline monitoring data to the pipeline node.

[0061] In a possible implementation of the embodiment of the present application, when the point analysis module 26 performs pipeline abnormal position distribution node analysis on the three-level pipeline data matrix to obtain the monitoring point position, it is specifically used to: Performing a two-dimensional coordinate change on the three-level pipeline data matrix to obtain a two-dimensional data graph corresponding to the three-level pipeline data matrix; Determine the pipeline data map point corresponding to each node data in the historical monitoring data according to the data two-dimensional graph, and the pipeline data map point includes the data coordinates of the node data, data scene characteristics, data environment characteristics and data abnormal characteristics; Determine the second pipeline data map point according to the timestamp, and use the second pipeline data map point as the starting map point to perform adjacent map point calculations to obtain a data difference set between each pipeline data map point and the pipeline data map point of the adjacent previous node; Match the difference in the data difference set with the preset difference interval to obtain the data weight corresponding to each pipeline data map point; Determine whether the data weight meets the preset data weight. If so, use the node of the node data corresponding to the data weight as the monitoring point position.

[0062] In another possible implementation of the embodiment of the present application, when the point analysis module 26 performs a two-dimensional coordinate change on the three-level pipeline data matrix to obtain a two-dimensional data map corresponding to the three-level pipeline data matrix, it is specifically used to: A time coordinate system is established, wherein the X-axis of the time coordinate system represents different unit times, and the Y-axis of the time coordinate system represents the pipeline data corresponding to different pipeline position nodes in different unit times; The data in the three-level pipeline data matrix are added to the time coordinate system according to the time nodes to obtain a two-dimensional graph of the data.

[0063] In another possible implementation of the embodiment of the present application, the point analysis module 26 calculates adjacent map points with the second pipeline data map point as the starting map point to obtain a data difference set between each pipeline data map point and the pipeline data map point of the adjacent previous node, specifically for: According to the data scene characteristics, the pipeline data map points are divided into scene categories to obtain pipeline data map point groups of different scenes; According to the data environment characteristics, the pipeline data map point group is divided into environmental categories to obtain the pipeline data map point groupings under different environments; Positioning the second pipeline data map point in each pipeline data map point group respectively, performing difference calculation between data in the second pipeline data map point and data in the first pipeline data map point in the same pipeline data map point group, and obtaining a first data difference; After the difference between the data in the second pipeline data map point and the data in the first pipeline data map point is calculated, the difference determination step is executed cyclically until the difference corresponding to all data points in the pipeline data map point group except the first pipeline data map point is obtained, and the difference corresponding to all data points in the pipeline data map point group except the first pipeline data map point is summarized to obtain a data difference set.

[0064] In another possible implementation manner of the embodiment of the present application, the difference determination step includes: Determine the second pipeline data map point as the target pipeline data map point, calculate the difference between the data in the target pipeline data map point and the data in the previous pipeline data map point of the target pipeline data map point, and obtain a first data difference; After the difference calculation is performed on the data in the second pipeline data map point and the data in the first pipeline data map point, the next pipeline data map point of the target pipeline data map point is used as the new target pipeline data map point and the difference calculation is performed on the data in the previous pipeline data map point of the new target pipeline data map point to obtain the second data difference. The final target pipeline data map point is the Nth pipeline data map point, and N is the number of pipeline data map points in the pipeline data map point group.

[0065] In another possible implementation of the embodiment of the present application, the system 20 further includes: an update module, wherein: The updating module is used to determine whether there are data anomaly features in the pipeline data map points. If so, the pipeline data map point grouping is updated based on the position of the pipeline data map points with data anomaly features in the pipeline data map point grouping to obtain an updated pipeline data map point grouping.

[0066] An electronic device provided in an embodiment of the present application is introduced below. The electronic device described below and the BIM-based water and electricity pipeline monitoring method described above can be referenced to each other.

[0067] The present application embodiment provides an electronic device, such as Figure 3 As shown, Figure 3 A schematic diagram of the structure of an electronic device provided in an embodiment of the present application, Figure 3 The electronic device 300 shown includes: a processor 301 and a memory 303. The processor 301 and the memory 303 are connected, such as through a bus 302. Optionally, the electronic device 300 may also include a transceiver 304. It should be noted that in actual applications, the transceiver 304 is not limited to one, and the structure of the electronic device 300 does not constitute a limitation on the embodiments of the present application.

[0068] The processor 301 may be a CPU (Central Processing Unit), a general-purpose processor, a DSP (Digital Signal Processor), an ASIC (Application Specific Integrated Circuit), an FPGA (Field Programmable Gate Array), or other programmable logic devices, transistor logic devices, hardware components, or any combination thereof. It may implement or execute various exemplary logic blocks, modules, and circuits described in conjunction with the disclosure of the embodiments of the present application. The processor 301 may also be a combination that implements computing functions, such as a combination of one or more microprocessors, a combination of a DSP and a microprocessor, and the like.

[0069] The bus 302 may include a path to transmit information between the above components. The bus 302 may be a PCI (Peripheral Component Interconnect) bus or an EISA (Extended Industry Standard Architecture) bus. The bus 302 may be divided into an address bus, a data bus, a control bus, etc. For ease of representation, Figure 3 Only one thick line is used in the diagram, but this does not mean that there is only one bus or only one type of bus.

[0070] The memory 303 may be a ROM (Read Only Memory) or other types of static storage devices that can store static information and instructions, a RAM (Random Access Memory) or other types of dynamic storage devices that can store information and instructions, or an EEPROM (Electrically Erasable Programmable Read Only Memory), a CD-ROM (Compact Disc Read Only Memory) or other optical disk storage, optical disk storage (including compressed optical disk, laser disk, optical disk, digital versatile disk, Blu-ray disk, etc.), a magnetic disk storage medium or other magnetic storage device, or any other medium that can be used to carry or store the desired program code in the form of instructions or data structures and can be accessed by a computer, but is not limited thereto.

[0071] The memory 303 is used to store application code for executing the solution of the embodiment of the present application, and the execution is controlled by the processor 301. The processor 301 is used to execute the application code stored in the memory 303 to implement the content shown in the above method embodiment.

[0072] Among them, electronic devices include but are not limited to: mobile terminals such as mobile phones, laptops, digital broadcast receivers, PDAs (personal digital assistants), PADs (tablet computers), PMPs (portable multimedia players), vehicle-mounted terminals (such as vehicle-mounted navigation terminals), etc., and fixed terminals such as digital TVs, desktop computers, etc. Figure 3 The electronic device shown is merely an example and should not bring any limitation to the functions and scope of use of the embodiments of the present application.

[0073] A computer-readable storage medium provided in an embodiment of the present application is introduced below. The computer-readable storage medium described below and the method described above can be referenced to each other.

[0074] An embodiment of the present application provides a computer-readable storage medium, on which a computer program is stored. When the computer program is executed by a processor, the steps of the above-mentioned BIM-based water and electricity pipeline monitoring method are implemented.

[0075] Since the embodiments of the computer-readable storage medium part and the embodiments of the method part correspond to each other, the embodiments of the computer-readable storage medium part refer to the description of the embodiments of the method part.

[0076] It should be understood that, although the steps in the flowchart of the accompanying drawings are displayed in sequence as indicated by the arrows, these steps are not necessarily executed in sequence in the order indicated by the arrows. Unless otherwise specified herein, there is no strict order restriction on the execution of these steps, and they can be executed in other orders. Moreover, at least a part of the steps in the flowchart of the accompanying drawings may include multiple sub-steps or multiple stages, and these sub-steps or stages are not necessarily executed at the same time, but can be executed at different times, and their execution order is not necessarily sequential, but can be executed in turn or alternately with other steps or at least a part of the sub-steps or stages of other steps.

[0077] The above are only some implementation methods of the present application. It should be pointed out that for ordinary technicians in this technical field, several improvements and modifications can be made without departing from the principles of the present application. These improvements and modifications should also be regarded as the scope of protection of the present application.

Claims

1. A water and electricity pipeline monitoring method based on BIM, characterized in that: include: Acquire pipeline parameters to be monitored, pipeline application scenarios corresponding to the pipeline parameters to be monitored, and historical monitoring data corresponding to the pipeline application scenarios; The historical monitoring data are sorted according to timestamps, pipeline transportation categories, and pipeline correlation levels to obtain a primary pipeline data matrix; Determine a historical analysis result based on the primary pipeline data matrix, determine whether there is pipeline abnormality data in the primary pipeline data matrix according to the historical analysis result, and if so, determine the pipeline abnormality degree of the pipeline abnormality data according to the historical analysis result; Binding the pipeline abnormality degree to the corresponding data nodes of the primary pipeline data matrix to obtain a secondary pipeline data matrix after binding; Determine the environmental information when the node data of different pipeline positions in the historical monitoring data is generated based on the pipeline application scenario, and bind the environmental information with the corresponding data nodes in the secondary pipeline data matrix to obtain a third-level pipeline data matrix after binding processing; Perform pipeline abnormal position distribution node analysis on the three-level pipeline data matrix to obtain the monitoring point position; Based on the pipeline parameters to be monitored, the water and electricity pipeline line is modeled using BIM technology to obtain a water and electricity pipeline model; Receive pipeline monitoring data sent by a monitoring sensor located at the monitoring point, determine a pipeline node corresponding to the monitoring point in the water and electricity pipeline model, and bind the pipeline monitoring data to the pipeline node.

2. A BIM-based water and electricity pipeline monitoring method according to claim 1, characterized in that: The performing pipeline abnormal position distribution node analysis on the three-level pipeline data matrix to obtain the monitoring point position includes: Performing a two-dimensional coordinate change on the three-level pipeline data matrix to obtain a two-dimensional data graph corresponding to the three-level pipeline data matrix; Determine the pipeline data map point corresponding to each node data in the historical monitoring data according to the data two-dimensional map, wherein the pipeline data map point includes data coordinates of the node data, data scene characteristics, data environment characteristics, and data abnormality characteristics; Determine a second pipeline data map point according to the timestamp, and use the second pipeline data map point as the starting map point to perform adjacent map point calculations to obtain a data difference set between each pipeline data map point and the pipeline data map point of the adjacent previous node; Matching the difference in the data difference set with the preset difference interval to obtain the data weight corresponding to each pipeline data map point; Determine whether the data weight meets the preset data weight. If so, use the node of the node data corresponding to the data weight as the monitoring point position.

3. The BIM-based water and electricity pipeline monitoring method according to claim 2 is characterized in that: The step of performing a two-dimensional coordinate change on the three-level pipeline data matrix to obtain a two-dimensional data graph corresponding to the three-level pipeline data matrix includes: Establishing a time coordinate system, wherein the X-axis of the time coordinate system represents different unit times, and the Y-axis of the time coordinate system represents pipeline data corresponding to different pipeline position nodes in different unit times; The data in the three-level pipeline data matrix is ​​added to the time coordinate system according to the time nodes to obtain a two-dimensional data graph.

4. The BIM-based water and electricity pipeline monitoring method according to claim 2 is characterized in that: The method of calculating adjacent map points with the second pipeline data map point as the starting map point to obtain a data difference set between each pipeline data map point and the pipeline data map point of the adjacent previous node includes: Classify the pipeline data map points into scene categories according to the data scene characteristics to obtain pipeline data map point groups of different scenes; Dividing the pipeline data map point group into environmental categories according to the data environment characteristics to obtain pipeline data map point groups under different environments; Positioning the second pipeline data map point in each pipeline data map point group respectively, performing difference calculation between the data in the second pipeline data map point and the data in the first pipeline data map point in the same pipeline data map point group to obtain a first data difference; After the difference between the data in the second pipeline data map point and the data in the first pipeline data map point is calculated, the difference determination step is executed cyclically until the difference corresponding to all data points in the pipeline data map point group except the first pipeline data map point is obtained, and the difference corresponding to all data points in the pipeline data map point group except the first pipeline data map point is summarized to obtain a data difference set.

5. The BIM-based water and electricity pipeline monitoring method according to claim 2 is characterized in that: The difference determination step comprises: Determine the second pipeline data map point as a target pipeline data map point, calculate the difference between data in the target pipeline data map point and data in a previous pipeline data map point of the target pipeline data map point, and obtain a first data difference; After the difference calculation is performed on the data in the second pipeline data map point and the data in the first pipeline data map point, the next pipeline data map point of the target pipeline data map point is used as the new target pipeline data map point and the difference calculation is performed on the data in the previous pipeline data map point of the new target pipeline data map point to obtain the second data difference. The final target pipeline data map point is the Nth pipeline data map point, and N is the number of pipeline data map points in the pipeline data map point group.

6. The BIM-based water and electricity pipeline monitoring method according to claim 4 is characterized in that: The pipeline data map point group is divided into environment categories according to the data environment characteristics to obtain pipeline data map point groups under different environments, and then further includes: Determine whether the data anomaly feature exists in the pipeline data map point. If so, update the pipeline data map point grouping based on the position of the pipeline data map point with the data anomaly feature within the pipeline data map point grouping to obtain an updated pipeline data map point grouping.

7. A water and electricity pipeline monitoring system based on BIM, characterized in that: include: A data acquisition module, used to acquire pipeline parameters to be monitored, pipeline application scenarios corresponding to the pipeline parameters to be monitored, and historical monitoring data corresponding to the pipeline application scenarios; A data sorting module is used to sort the historical monitoring data according to timestamps, pipeline transportation categories and pipeline correlation degrees to obtain a primary pipeline data matrix; an abnormality determination module, used to determine the historical analysis results based on the primary pipeline data matrix, determine whether there is pipeline abnormality data in the primary pipeline data matrix according to the historical analysis results, and if so, determine the pipeline abnormality degree of the pipeline abnormality data according to the historical analysis results; A node binding module is used to bind the pipeline abnormality degree to the corresponding data node of the primary pipeline data matrix to obtain a secondary pipeline data matrix after binding processing; An information determination module, used to determine the environmental information when the data of different pipeline location nodes in the historical monitoring data are generated based on the pipeline application scenario, and bind the environmental information with the corresponding data nodes in the secondary pipeline data matrix to obtain a tertiary pipeline data matrix after binding processing; A point analysis module is used to perform pipeline abnormal position distribution node analysis on the three-level pipeline data matrix to obtain the monitoring point position; A model building module, used to model the water and electricity pipeline line using BIM technology based on the pipeline parameters to be monitored to obtain a water and electricity pipeline model; The data fusion module is used to receive the pipeline monitoring data sent by the monitoring sensor located at the monitoring point, determine the pipeline node corresponding to the monitoring point in the hydropower pipeline model, and bind the pipeline monitoring data to the pipeline node.

8. The BIM-based water and electricity pipeline monitoring system according to claim 7 is characterized in that: When the point analysis module performs pipeline abnormal position distribution node analysis on the three-level pipeline data matrix to obtain the monitoring point position, it is specifically used to: Performing a two-dimensional coordinate change on the three-level pipeline data matrix to obtain a two-dimensional data graph corresponding to the three-level pipeline data matrix; Determine the pipeline data map point corresponding to each node data in the historical monitoring data according to the data two-dimensional map, wherein the pipeline data map point includes data coordinates of the node data, data scene characteristics, data environment characteristics, and data abnormality characteristics; Determine a second pipeline data map point according to the timestamp, and use the second pipeline data map point as the starting map point to perform adjacent map point calculations to obtain a data difference set between each pipeline data map point and the pipeline data map point of the adjacent previous node; Matching the difference in the data difference set with the preset difference interval to obtain the data weight corresponding to each pipeline data map point; Determine whether the data weight meets the preset data weight. If so, use the node of the node data corresponding to the data weight as the monitoring point position.

9. An electronic device, characterized in that: include: at least one processor; Memory; At least one application, wherein the at least one application is stored in a memory and configured to be executed by at least one processor, and the at least one application is configured to: execute a BIM-based water and electricity pipeline monitoring method as described in any one of claims 1 to 6.

10. A computer-readable storage medium, characterized in that: A computer program is stored which can be loaded by a processor and execute a water and electricity pipeline monitoring method based on BIM as described in any one of claims 1 to 6.

Citation Information