Construction engineering project management method

By setting up safety, progress, evaluation and logistics subsystems in the construction project management system, data sharing and online interaction are realized, which solves the problems of poor information transmission and cumbersome approval processes in project management, and improves management efficiency and project construction. security.

CN118735463AInactive Publication Date: 2024-10-01郑秀叶
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202410946196.7
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-15
Publication Date
2024-10-01
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

In modern engineering project management, there are problems such as poor information transmission, cumbersome approval processes, lagging project progress supervision and chaotic construction management order, resulting in low management efficiency.

Method used

Establish a construction project management system, which is divided into safety subsystem, progress subsystem, evaluation subsystem and logistics subsystem, formulate work processes and set up sub-modules, collect project process data, realize data sharing and online interaction in each link, and use online data Transmission and monitoring problem solving.

Benefits of technology

It improves the efficiency of project construction, ensures the accuracy and safety of project execution, responds to potential hazards in a timely manner, solves unexpected problems, and improves work efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118735463A_ABST
    Figure CN118735463A_ABST
Patent Text Reader

Abstract

The invention discloses a construction engineering project management method, and aims to solve the problems of low project management efficiency, such as tedious approval process, lagged project progress supervision and disordered construction management order, in existing project management in the field of project management of construction engineering. The method comprises the following steps: establishing a construction engineering project management system, and setting a safety subsystem, a progress subsystem, an evaluation subsystem and a logistics subsystem on a platform. And formulating a working process, and setting sub-modules under each subsystem according to the working process. Corresponding rules, regulations and working indexes are associated in the sub-modules, and project process data of the sub-modules are collected. An engineering project is developed according to the work plan, generated engineering data are input into the system, and data sharing of all links in the platform is achieved. And efficient management of the engineering project is realized through online updating of each level of data and contrast acceptance with an acceptance standard.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the field of engineering management, and specifically, is a construction engineering project management method. Background Art

[0002] With the development of economy and computer network technology, the demand for information platforms in various industries in the world is also increasing, and the construction industry is no exception. Applying information technology to the field of construction engineering by relying on the Internet of Things, artificial intelligence and other means has become the main development trend of the construction industry. Driven by information technology, my country's construction engineering management industry can quickly build engineering modules, grasp the progress of the project in real time to ensure the quality of the project, thereby improving the quality and efficiency of the overall management work. The construction project management method and system involved in CN202311256169.9 (a construction project management method and system) focuses on the progress management of the project, ignoring the standardized management and real-time communication of safety, personnel and environment. The present invention incorporates the safety, progress, acceptance and logistics support involved in the project into a system platform. While ensuring the progress of the project through online data sharing, it can also respond to possible hidden dangers in a timely manner, improve work efficiency, and solve sudden problems in the project execution process in a timely manner. Summary of the invention

[0003] The purpose of this invention is to solve the problems of low efficiency in engineering management such as poor information transmission, cumbersome approval process, delayed supervision of engineering progress and chaotic construction management order in modern engineering project management. To solve the above problems, the following technical solutions are adopted: A construction project management method is to establish a construction project management system, and set up a safety subsystem, a progress subsystem, an evaluation subsystem and a logistics subsystem on the platform. Workflows are formulated, and submodules are set up under each subsystem according to the workflows. Corresponding rules and regulations and work indicators are associated with the submodules, and the engineering process data of each submodule is collected. The engineering project is carried out according to the work plan, and the generated engineering data is entered into the system to realize data sharing in various links of the platform.

[0004] A construction project management method, wherein the construction project management system is a comprehensive data integration platform that can realize online interaction of various links of the project, online data transmission, acceptance standard entry and online monitoring.

[0005] A construction project management method, wherein the safety subsystem comprises a construction safety module, a personnel safety module and an environmental safety module.

[0006] A construction project management method, wherein the progress subsystem includes a project negotiation and contract signing module, a project decomposition and program formulation module, and a project execution and data aggregation module.

[0007] A construction project management method, wherein the evaluation subsystem comprises a process acceptance evaluation module, an internal acceptance evaluation module and an external acceptance evaluation module.

[0008] A construction project management method, wherein the logistics subsystem includes a logistics team module, a resource guarantee module and a safety guarantee module.

[0009] The construction safety module includes three construction standards and operating specifications: water and electricity safety, mechanical safety, and open fire control. The personnel safety module includes three construction standards and operating specifications: personnel protection, operating procedures, and clear responsibilities. The environmental safety module includes three construction standards and operating specifications: dust monitoring, waste gas and wastewater emissions, and clear responsibilities.

[0010] The project negotiation and contract signing module includes three data sets: customer information, contract text, and contract terms. The engineering decomposition and solution formulation module includes three real-time data sharing and interactive microsystems: project decomposition, customized solution, and clear responsibility. The project execution and data summary module includes three real-time data sharing and interactive microsystems: progress report, problem feedback, and solution summary.

[0011] The process acceptance evaluation module includes three tasks and interactive processes: acceptance standards, acceptance process, and acceptance rectification. The internal acceptance evaluation module includes three tasks and interactive processes: project completion, internal acceptance, and acceptance rectification. The external acceptance evaluation module includes three tasks and interactive processes: external acceptance, acceptance rectification, and implementation of rectification.

[0012] The logistics team module includes three microsystems: logistics team, logistics division of labor and clear responsibilities. The resource guarantee module includes three microsystems: logistics support facilities, communication equipment and material storage and transportation. The security guarantee module includes three microsystems: personnel protection, food and accommodation guarantee and medical guarantee.

[0013] As an optional solution, the present invention also adopts the following technical solution: The project management system involved in the engineering project management method of the present invention divides the management system into four subsystems according to functions, and each subsystem has an independent management and approval process.

[0014] The project management system involved in the engineering project management method of the present invention is provided with a data reporting template to achieve seamless connection between engineering data and acceptance indicators.

[0015] The advantages and positive effects of the present invention are: 1. After the project contract is signed, the present invention can form engineering model information according to the project type and engineering requirements, reasonably arrange the number of workers required for each type of work according to the engineering volume, select the best worker allocation plan, and improve the efficiency of engineering construction.

[0016] 2. The present invention realizes real-time transmission and interaction of multi-level data in the project, which guarantees the correct execution of the project to the greatest extent and avoids problems. BRIEF DESCRIPTION OF THE DRAWINGS

[0017] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on the provided drawings without paying creative work.

[0018] Figure 1 It is a schematic diagram of the construction project management system of the present invention; Figure 2 Schematic diagram of security subsystem management Figure 3 Schematic diagram of progress subsystem management Figure 4 Schematic diagram for evaluating subsystem management Figure 5 Schematic diagram of logistics subsystem management DETAILED DESCRIPTION

[0019] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0020] A construction project management method is to establish a construction project management system, and set up a safety subsystem, a progress subsystem, an evaluation subsystem and a logistics subsystem on the platform. Workflows are formulated, and submodules are set up under each subsystem according to the workflows. Corresponding rules and regulations and work indicators are associated with the submodules, and the engineering process data of each submodule is collected. The engineering project is carried out according to the work plan, and the generated engineering data is entered into the system to realize data sharing in various links of the platform.

[0021] Personnel related to the engineering project have independent accounts, and access rights to the system are set for different personnel based on their responsibilities and management levels. The rights are divided into inaccessible, read-only, interactive and editable.

[0022] The construction safety module includes three construction standards and operating specifications: water and electricity safety, mechanical safety, and open fire control. The personnel safety module includes three construction standards and operating specifications: personnel protection, operating procedures, and clear responsibilities. The environmental safety module includes three construction standards and operating specifications: dust monitoring, waste gas and wastewater emissions, and clear responsibilities.

[0023] The project negotiation and contract signing module includes three data sets: customer information, contract text, and contract terms. The engineering decomposition and solution formulation module includes three real-time data sharing and interactive microsystems: project decomposition, customized solution, and clear responsibility. The project execution and data summary module includes three real-time data sharing and interactive microsystems: progress report, problem feedback, and solution summary.

[0024] The process acceptance evaluation module includes three tasks and interactive processes: acceptance standards, acceptance process, and acceptance rectification. The internal acceptance evaluation module includes three tasks and interactive processes: project completion, internal acceptance, and acceptance rectification. The external acceptance evaluation module includes three tasks and interactive processes: external acceptance, acceptance rectification, and implementation of rectification.

[0025] The logistics team module includes three microsystems: logistics team, logistics division of labor and clear responsibilities. The resource guarantee module includes three microsystems: logistics support facilities, communication equipment and material storage and transportation. The security guarantee module includes three microsystems: personnel protection, food and accommodation guarantee and medical guarantee.

Claims

1. A construction project management method, establishing a construction project management system, setting up a safety subsystem, a progress subsystem, an evaluation subsystem and a logistics subsystem on the platform. Formulate a workflow, and set up submodules under each subsystem according to the workflow. Associate corresponding rules and regulations and work indicators in the submodules, and collect engineering process data of each submodule. Carry out engineering projects according to the work plan, and enter the generated engineering data into the system to realize data sharing in various links of the platform.

2. According to the construction project management method described in claim 1, the construction project management system is a comprehensive data integration platform that can realize online interaction of various links of the project, online data transmission, acceptance standard entry and online monitoring.

3. According to a construction project management method described in claim 1, the safety subsystem includes a construction safety module, a personnel safety module and an environmental safety module.

4. According to a construction project management method described in claim 1, the progress subsystem includes a project negotiation and contract signing module, a project decomposition and plan formulation module, and a project execution and data aggregation module.

5. According to a construction project management method described in claim 1, the evaluation subsystem includes a process acceptance evaluation module, an internal acceptance evaluation module and an external acceptance evaluation module.

6. According to a construction project management method described in claim 1, the logistics subsystem includes a logistics team module, a resource guarantee module and a security guarantee module.

7. A construction project management method according to claim 3: the construction safety module includes three construction standards and operating specifications: water and electricity safety, mechanical safety, and open fire control. The personnel safety module includes three construction standards and operating specifications: personnel protection, operating procedures, and clear responsibilities. The environmental safety module includes three construction standards and operating specifications: dust monitoring, waste gas and wastewater discharge, and clear responsibilities.

8. A construction project management method according to claim 4: the project negotiation and contract signing module includes three data sets: customer information, contract text and contract terms. The project decomposition and solution formulation module includes three real-time data sharing and interactive microsystems: project decomposition, customized solution and clear responsibility. The project execution and data summary module includes three real-time data sharing and interactive microsystems: progress report, problem feedback and solution summary.

9. A construction project management method according to claim 5: the process acceptance evaluation module includes three tasks and interactive processes: acceptance standard, acceptance process and acceptance rectification. The internal acceptance evaluation module includes three tasks and interactive processes: project completion, internal acceptance and acceptance rectification. The external acceptance evaluation module includes three tasks and interactive processes: external acceptance, acceptance rectification and implementation of rectification.

10. A construction project management method according to claim 6: the logistics team module includes three microsystems: logistics team, logistics division of labor and clear responsibilities. The resource guarantee module includes three microsystems: logistics support facilities, communication equipment and material storage and transportation. The safety guarantee module includes three microsystems: personnel protection, food and accommodation guarantee and medical guarantee.