Electric transmission line area flood early warning method and system

Through simulation scenario models and hydrological simulations, combined with architectural and terrain information, hierarchical early warning indicators and discriminant functions are set, which solves the problem of the traditional early warning system's lack of pertinence and accuracy in flood disaster early warning, and achieves high efficiency in the transmission line area. Flood disaster warning and loss reduction.

CN118736770APending Publication Date: 2024-10-01CHINA ELECTRIC POWER RESEARCH INSTITUTE CO LTD +2
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202410670529.8
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-05-28
Publication Date
2024-10-01

AI Technical Summary

Technical Problem

The traditional meteorological early warning system lacks pertinence in flood disaster early warning and is difficult to meet the safe operation needs of the power system. It also lacks comprehensive consideration of equipment protection measures and outage mechanisms, resulting in inaccurate early warning results.

Method used

A simulation scenario model is used to conduct hydrological simulation, determine the simulated water level data in the transmission line area, and set hierarchical early warning indicators based on the simulated water level data. Use the state discriminant function to identify the index values ​​to issue flood early warnings. Eight-level flood warnings are carried out based on the building foundation shape and terrain information. Directional flow modeling and hydrological simulation of the GSSHA model.

Benefits of technology

It has achieved refined prediction and early warning of flood disasters in transmission line areas, reduced losses caused by floods, and improved the disaster resistance of power equipment and facilities.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118736770A_ABST
    Figure CN118736770A_ABST
Patent Text Reader

Abstract

The invention discloses a flood early warning method and system for a power transmission line area, and belongs to the technical field of power system safety. The method comprises the steps of collecting scene information of a target power transmission line area, building a simulation scene model according to the scene information, and performing hydrological simulation based on the simulation scene model to determine simulated water level data of the target power transmission line area; according to the simulated water level data, determining a predicted graded early warning index of flood of the power equipment and facility area in the target power transmission line area, and determining an index value of the graded early warning index according to the simulated water level data; and using a preset state discrimination function to discriminate the index value of the grading early warning index, and if the discrimination result is not 0, sending out flood early warning for the target power transmission line area. According to the method, the flood disaster of the target area can be effectively predicted through hydrological simulation, and the loss caused by flood can be reduced through effective early warning.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the field of power system safety technology, and more specifically, to a method and system for early warning of flood in a transmission line area. Background Art

[0002] Against the backdrop of global climate change, the frequent occurrence of extreme weather events has become an issue that cannot be ignored. Especially for the power system, the threat of flood disasters is particularly prominent. Extreme weather events such as heavy rains and floods may not only cause direct damage to power facilities, but may also trigger a chain reaction, causing power supply interruptions and bringing significant impacts on the social economy.

[0003] Although the traditional meteorological warning system can provide disaster warnings to a certain extent, these warnings are often for a wide area and lack specificity. Flood disaster warnings in power line areas require more refined models and methods to adapt to the particularity and complexity of power equipment. In addition, traditional warning methods often lack comprehensive consideration of equipment protection measures and shutdown mechanisms, resulting in inaccurate warning results and difficulty in meeting the safe operation requirements of the power system. Summary of the invention

[0004] In view of the above problems, the present invention proposes a method for early warning of flood in a transmission line area, comprising:

[0005] Collecting scene information of the target transmission line area, building a simulation scene model based on the scene information, and performing hydrological simulation based on the simulation scene model to determine simulated water level data of the target transmission line area;

[0006] Determine the forecast graded warning index of flooding in the power equipment and facility area in the target transmission line area, and determine the index value of the graded warning index according to the simulated water level data;

[0007] The index value of the graded warning index is judged using a preset state discrimination function, and if the discrimination result is not 0, a flood warning is issued for the target power transmission line area.

[0008] Optionally, scene information includes: building foundation morphology information and topographic information in the target transmission line area.

[0009] Optionally, performing hydrological simulation based on the simulation scenario model includes:

[0010] According to the simulation scenario model, the central axis data, the ridge line data of the surrounding mountains and the elevation data of the target transmission line area are obtained, and the waterway flow direction and confluence path data of the target transmission line area are calculated based on the central axis data, the ridge line data of the surrounding mountains and the elevation data using the eight-direction flow direction modeling technology;

[0011] Generate a river network according to the waterway flow direction and confluence path data, the actual size of the target transmission line area and the process function of the target transmission line area, and determine the watershed outlet of the river network for the river network to generate a digital watershed;

[0012] The digital watershed is gridded according to the terrain and boundary condition data of the digital watershed, and the GSSHA model is used to perform hydrological simulation on the gridded digital watershed.

[0013] Optionally, hydrological simulation, specifically: simulating the hydrological process in the target transmission line area;

[0014] The hydrological processes include rainfall, runoff and evaporation.

[0015] Optional, graded warning indicators, including: Level 4 blue warning indicator for line flooding and suspension risk warning, Level 3 yellow warning indicator for line flooding and suspension risk warning, Level 2 orange warning indicator for line flooding and suspension risk warning, and Level 1 red warning indicator for line flooding and suspension risk warning;

[0016] The calculation formula of the index value of the graded warning index is as follows:

[0017] Hb1=90%hw1

[0018] Hb2=85%hw2

[0019] Hb3=75%hw3

[0020] Hb4=70%hw4

[0021] Among them, Hb1 is the red snake warning indicator of level 1 risk warning of line flooding and suspension of operation, Hb2 is the orange warning indicator of level 2 risk warning of line flooding and suspension of operation, Hb3 is the yellow warning indicator of level 3 risk warning of line flooding and suspension of operation, Hb4 is the blue warning indicator of level 4 risk warning of line flooding and suspension of operation, hw1 is the water level corresponding to the red flood control level, hw2 is the water level corresponding to the orange flood control level, hw3 is the water level corresponding to the yellow flood control level, and hw4 is the water level corresponding to the blue flood control level.

[0022] Optional, preset state discrimination functions, including:

[0023]

[0024] Wherein, hF represents the simulated water level, if Sb=0, no warning is triggered, if Sb=4, a level 4 blue warning is triggered, if Sb=3, a level 3 yellow warning is triggered, if Sb=2, a level 2 orange warning is triggered, and if Sb=1, a level 1 red warning is triggered.

[0025] In another aspect, the present invention further provides a transmission line area flood warning system, comprising:

[0026] A simulation unit, used to collect scene information of a target transmission line area, build a simulation scene model based on the scene information, and perform hydrological simulation based on the simulation scene model to determine simulated water level data of the target transmission line area;

[0027] A calculation unit, used to determine the predicted graded warning index of flooding in the power equipment and facility area in the target transmission line area, and determine the index value of the graded warning index according to the simulated water level data;

[0028] The early warning unit is used to use a preset state discrimination function to discriminate the index value of the graded early warning index, and if the discrimination result is not 0, issue a flood warning for the target transmission line area.

[0029] Optionally, scene information includes: building foundation morphology information and topographic information in the target transmission line area.

[0030] Optionally, performing hydrological simulation based on the simulation scenario model includes:

[0031] According to the simulation scenario model, the central axis data, the ridge line data of the surrounding mountains and the elevation data of the target transmission line area are obtained, and the waterway flow direction and confluence path data of the target transmission line area are calculated based on the central axis data, the ridge line data of the surrounding mountains and the elevation data using the eight-direction flow direction modeling technology;

[0032] Generate a river network according to the waterway flow direction and confluence path data, the actual size of the target transmission line area and the process function of the target transmission line area, and determine the watershed outlet of the river network for the river network to generate a digital watershed;

[0033] The digital watershed is gridded according to the terrain and boundary condition data of the digital watershed, and the GSSHA model is used to perform hydrological simulation on the gridded digital watershed.

[0034] Optionally, hydrological simulation, specifically: simulating the hydrological process in the target transmission line area;

[0035] The hydrological processes include rainfall, runoff and evaporation.

[0036] Optional, graded warning indicators, including: Level 4 blue warning indicator for line flooding and suspension risk warning, Level 3 yellow warning indicator for line flooding and suspension risk warning, Level 2 orange warning indicator for line flooding and suspension risk warning, and Level 1 red warning indicator for line flooding and suspension risk warning;

[0037] The calculation formula of the index value of the graded warning index is as follows:

[0038] Hb1=90%hw1

[0039] Hb2=85%hw2

[0040] Hb3=75%hw3

[0041] Hb4=70%hw4

[0042] Among them, Hb1 is the red snake warning indicator of level 1 risk warning of line flooding and suspension of operation, Hb2 is the orange warning indicator of level 2 risk warning of line flooding and suspension of operation, Hb3 is the yellow warning indicator of level 3 risk warning of line flooding and suspension of operation, Hb4 is the blue warning indicator of level 4 risk warning of line flooding and suspension of operation, hw1 is the water level corresponding to the red flood control level, hw2 is the water level corresponding to the orange flood control level, hw3 is the water level corresponding to the yellow flood control level, and hw4 is the water level corresponding to the blue flood control level.

[0043] Optional, preset state discrimination functions, including:

[0044]

[0045] Wherein, hF represents the simulated water level, if Sb=0, no warning is triggered, if Sb=4, a level 4 blue warning is triggered, if Sb=3, a level 3 yellow warning is triggered, if Sb=2, a level 2 orange warning is triggered, and if Sb=1, a level 1 red warning is triggered.

[0046] In yet another aspect, the present invention further provides a computing device, comprising: one or more processors;

[0047] a processor for executing one or more programs;

[0048] When the one or more programs are executed by the one or more processors, the above-described method is implemented.

[0049] In yet another aspect, the present invention further provides a computer-readable storage medium having a computer program stored thereon, wherein when the computer program is executed, the method described above is implemented.

[0050] Compared with the prior art, the present invention has the following beneficial effects:

[0051] The present invention proposes a method for early warning of floods in a power transmission line area, comprising: collecting scene information of a target power transmission line area, building a simulation scene model with the scene information, and performing hydrological simulation based on the simulation scene model to determine simulated water level data of the target power transmission line area; determining the predicted graded early warning index of floods in the power equipment and facility area in the target power transmission line area, and determining the index value of the graded early warning index based on the simulated water level data; using a preset state discriminant function to discriminate the index value of the graded early warning index, and if the discrimination result is not 0, issuing a flood early warning for the target power transmission line area. The present invention can effectively predict flood disasters in the target area through hydrological simulation, and can reduce losses caused by floods through effective early warning. BRIEF DESCRIPTION OF THE DRAWINGS

[0052] Figure 1 is a flow chart of the method of the present invention;

[0053] Figure 2 A flowchart of an embodiment of the method of the present invention;

[0054] Figure 3 It is a structural diagram of the system of the present invention. DETAILED DESCRIPTION

[0055] Now, exemplary embodiments of the present invention are described with reference to the accompanying drawings. However, the present invention can be implemented in many different forms and is not limited to the embodiments described herein. These embodiments are provided to disclose the present invention in detail and completely and to fully convey the scope of the present invention to those skilled in the art. The terms used in the exemplary embodiments shown in the accompanying drawings are not intended to limit the present invention. In the accompanying drawings, the same units / elements are marked with the same reference numerals.

[0056] Unless otherwise specified, the terms (including technical terms) used herein have the commonly understood meanings to those skilled in the art. In addition, it is understood that the terms defined in commonly used dictionaries should be understood to have the same meanings as those in the context of the relevant fields, and should not be understood as idealized or overly formal meanings.

[0057] Embodiment 1:

[0058] The present invention proposes a method for early warning of flood in a transmission line area, such as Figure 1 As shown, including:

[0059] Step 1: Collect scene information of the target transmission line area, build a simulation scene model based on the scene information, and perform hydrological simulation based on the simulation scene model to determine simulated water level data of the target transmission line area;

[0060] Step 2: determining the predicted graded warning index of flood in the power equipment and facility area in the target transmission line area, and determining the index value of the graded warning index according to the simulated water level data;

[0061] Step 3: Use a preset state discrimination function to discriminate the index value of the graded warning index. If the discrimination result is not 0, issue a flood warning for the target transmission line area.

[0062] The scene information includes: building foundation morphology information and topography information in the target transmission line area.

[0063] The hydrological simulation is performed based on the simulation scenario model, including:

[0064] According to the simulation scenario model, the central axis data, the ridge line data of the surrounding mountains and the elevation data of the target transmission line area are obtained, and the waterway flow direction and confluence path data of the target transmission line area are calculated based on the central axis data, the ridge line data of the surrounding mountains and the elevation data using the eight-direction flow direction modeling technology;

[0065] Generate a river network according to the waterway flow direction and confluence path data, the actual size of the target transmission line area and the process function of the target transmission line area, and determine the watershed outlet of the river network for the river network to generate a digital watershed;

[0066] The digital watershed is gridded according to the terrain and boundary condition data of the digital watershed, and the GSSHA model is used to perform hydrological simulation on the gridded digital watershed.

[0067] Among them, hydrological simulation, specifically: simulating the hydrological process in the target transmission line area;

[0068] The hydrological processes include rainfall, runoff and evaporation.

[0069] Among them, the graded warning indicators include: Level 4 blue warning indicators for line flooding and suspension risk warning, Level 3 yellow warning indicators for line flooding and suspension risk warning, Level 2 orange warning indicators for line flooding and suspension risk warning, and Level 1 red warning indicators for line flooding and suspension risk warning;

[0070] The calculation formula of the index value of the graded warning index is as follows:

[0071] Hb1=90%hw1

[0072] Hb2=85%hw2

[0073] Hb3=75%hw3

[0074] Hb4=70%hw4

[0075] Among them, Hb1 is the red snake warning indicator of level 1 risk warning of line flooding and suspension of operation, Hb2 is the orange warning indicator of level 2 risk warning of line flooding and suspension of operation, Hb3 is the yellow warning indicator of level 3 risk warning of line flooding and suspension of operation, Hb4 is the blue warning indicator of level 4 risk warning of line flooding and suspension of operation, hw1 is the water level corresponding to the red flood control level, hw2 is the water level corresponding to the orange flood control level, hw3 is the water level corresponding to the yellow flood control level, and hw4 is the water level corresponding to the blue flood control level.

[0076] Among them, the preset state discrimination function includes:

[0077]

[0078] Wherein, hF represents the simulated water level, if Sb=0, no warning is triggered, if Sb=4, a level 4 blue warning is triggered, if Sb=3, a level 3 yellow warning is triggered, if Sb=2, a level 2 orange warning is triggered, and if Sb=1, a level 1 red warning is triggered.

[0079] The present invention will be further described below in conjunction with embodiments:

[0080] Implementation steps: Figure 2 As shown, including:

[0081] Step 1: Data collection and model building: Detailed data collection of building foundation morphology, topography, etc. in the target power line area is carried out. Advanced hydrological modeling software, such as WMS, is used to build a high-precision simulation scenario model of the area. This step is the basis of the early warning method and provides accurate geographic and environmental information for subsequent analysis.

[0082] Step 2: Analysis of waterway flow direction and confluence path: By analyzing the central axis of the power line area, the ridgeline of the surrounding mountains, and elevation data (DEM), the eight-direction (D8) flow modeling technology is used to calculate the waterway flow direction and confluence path. This step helps to understand the potential flow pattern of floods in the power line area and provides an important basis for subsequent flood predictions.

[0083] Step 3: Digital watershed generation: Based on the waterway flow direction and confluence path obtained in the previous steps, combined with the actual size and process function of the power line area, the river network is generated, and the watershed outlet is manually determined to construct a digital watershed. The establishment of the digital watershed provides the necessary spatial framework for subsequent hydrological simulation and flood prediction.

[0084] Step 4: Hydrological simulation: Based on the terrain and boundary condition data of the digital watershed, grid division is performed, and the GSSHA model is used for hydrological simulation. This step simulates the hydrological processes such as rainfall, runoff, and evaporation in the area to obtain key hydrological parameters such as water depth, providing a scientific basis for flood prediction.

[0085] Step 5: Establish early warning indicators: Based on the existing flood control standards and early warning regulations in the basin, expand on the existing hydrological early warning indicators and establish graded early warning indicators for flood prediction in power equipment and facility areas;

[0086] Step 6: Set the trigger conditions according to the warning: According to the forecast period and accuracy requirements, set the trigger conditions of different warning indicators. Through the state discrimination function Sb, the simulated water level is compared with the warning indicator. Once the trigger condition is reached, the corresponding level of warning signal can be issued.

[0087] The step 5 comprises the following steps:

[0088] Based on the analysis of the current hydrological warning indicators, the regional warning division of power lines is carried out based on the existing flood warning indicators, and the warning indicators of line flooding and shutdown risk warning are proposed, that is, level 4 is blue, level 3 is yellow, level 2 is orange, and level 1 is red. The calculation of the warning indicators is:

[0089] Hb1=90%hw1

[0090] Hb2=85%hw2

[0091] Hb3=75%hw3

[0092] Hb4=70%hw4

[0093] Hb1 is the level 1 warning indicator for the risk of line flooding and suspension of operation; Hb2 is the level 2 warning indicator for the risk of line flooding and suspension of operation; Hb3 is the level 3 warning indicator for the risk of line flooding and suspension of operation; Hb4 is the level 4 warning indicator for the risk of line flooding and suspension of operation; hw1 is the water level corresponding to the red flood control level; hw2 is the water level corresponding to the orange flood control level; hw3 is the water level corresponding to the yellow flood control level; hw4 is the water level corresponding to the blue flood control level.

[0094] The step 6 comprises the following steps:

[0095] Establish the state discriminant function Sb of the line flooding suspension risk classification warning index:

[0096]

[0097] Wherein, hF represents the simulated water level;

[0098] If Sb = 0, it means that the hydrological warning is not triggered;

[0099] If Sb=4, it means that the super-standard flood hydrological level 4 warning is triggered;

[0100] If Sb=3, it means that the super-standard flood hydrological level 3 warning is triggered;

[0101] If Sb = 2, it means that the super-standard flood hydrological level 2 warning is triggered;

[0102] If Sb = 1, it means that the super-standard flood hydrological level 1 warning is triggered;

[0103] The present invention can effectively predict and warn of flood disasters in power line areas. By comprehensively considering equipment characteristics and meteorological and hydrological data, it realizes the forecast and warning of flood disasters in power transmission and transformation equipment within the next three days.

[0104] In practical applications, the present invention can effectively guide the formulation of equipment protection and emergency response measures, reduce the losses caused by flood disasters, and improve the disaster resistance of power equipment and facilities.

[0105] Embodiment 2:

[0106] The present invention also proposes a transmission line area flood warning system 200, such as Figure 3 As shown, including:

[0107] A simulation unit 201 is used to collect scene information of a target transmission line area, build a simulation scene model based on the scene information, and perform hydrological simulation based on the simulation scene model to determine simulated water level data of the target transmission line area;

[0108] The calculation unit 202 is used to determine the predicted graded warning index of flooding in the power equipment and facility area in the target transmission line area, and determine the index value of the graded warning index according to the simulated water level data;

[0109] The early warning unit 203 is used to use a preset state discrimination function to discriminate the index value of the graded early warning index, and if the discrimination result is not 0, issue a flood warning for the target transmission line area.

[0110] The scene information includes: building foundation morphology information and topography information in the target transmission line area.

[0111] The hydrological simulation is performed based on the simulation scenario model, including:

[0112] According to the simulation scenario model, the central axis data, the ridge line data of the surrounding mountains and the elevation data of the target transmission line area are obtained, and the waterway flow direction and confluence path data of the target transmission line area are calculated based on the central axis data, the ridge line data of the surrounding mountains and the elevation data using the eight-direction flow direction modeling technology;

[0113] Generate a river network according to the waterway flow direction and confluence path data, the actual size of the target transmission line area and the process function of the target transmission line area, and determine the watershed outlet of the river network for the river network to generate a digital watershed;

[0114] The digital watershed is gridded according to the terrain and boundary condition data of the digital watershed, and the GSSHA model is used to perform hydrological simulation on the gridded digital watershed.

[0115] Among them, hydrological simulation, specifically: simulating the hydrological process in the target transmission line area;

[0116] The hydrological processes include rainfall, runoff and evaporation.

[0117] Among them, the graded warning indicators include: Level 4 blue warning indicators for line flooding and suspension risk warning, Level 3 yellow warning indicators for line flooding and suspension risk warning, Level 2 orange warning indicators for line flooding and suspension risk warning, and Level 1 red warning indicators for line flooding and suspension risk warning;

[0118] The calculation formula of the index value of the graded warning index is as follows:

[0119] Hb1=90%hw1

[0120] Hb2=85%hw2

[0121] Hb3=75%hw3

[0122] Hb4=70%hw4

[0123] Among them, Hb1 is the red snake warning indicator of level 1 risk warning of line flooding and suspension of operation, Hb2 is the orange warning indicator of level 2 risk warning of line flooding and suspension of operation, Hb3 is the yellow warning indicator of level 3 risk warning of line flooding and suspension of operation, Hb4 is the blue warning indicator of level 4 risk warning of line flooding and suspension of operation, hw1 is the water level corresponding to the red flood control level, hw2 is the water level corresponding to the orange flood control level, hw3 is the water level corresponding to the yellow flood control level, and hw4 is the water level corresponding to the blue flood control level.

[0124] Among them, the preset state discrimination function includes:

[0125]

[0126] Wherein, hF represents the simulated water level, if Sb=0, no warning is triggered, if Sb=4, a level 4 blue warning is triggered, if Sb=3, a level 3 yellow warning is triggered, if Sb=2, a level 2 orange warning is triggered, and if Sb=1, a level 1 red warning is triggered.

[0127] The present invention can effectively predict flood disasters in a target area through hydrological simulation, and can reduce losses caused by floods through effective early warning.

[0128] Embodiment 3:

[0129] Based on the same inventive concept, the present invention also provides a computer device, which includes a processor and a memory, wherein the memory is used to store a computer program, the computer program includes program instructions, and the processor is used to execute the program instructions stored in the computer storage medium. The processor may be a central processing unit (CPU), or other general-purpose processors, digital signal processors (DSP), application-specific integrated circuits (ASIC), field-programmable gate arrays (FPGA) or other programmable logic devices, discrete gates or transistor logic devices, discrete hardware components, etc. It is the computing core and control core of the terminal, which is suitable for implementing one or more instructions, and is specifically suitable for loading and executing one or more instructions in the computer storage medium to implement the corresponding method flow or corresponding functions, so as to implement the steps of the method in the above embodiment.

[0130] Embodiment 4:

[0131] Based on the same inventive concept, the present invention also provides a storage medium, specifically a computer-readable storage medium (Memory), which is a memory device in a computer device for storing programs and data. It is understandable that the computer-readable storage medium here can include both a built-in storage medium in a computer device and an extended storage medium supported by the computer device. The computer-readable storage medium provides a storage space, which stores the operating system of the terminal. In addition, one or more instructions suitable for being loaded and executed by a processor are also stored in the storage space, and these instructions can be one or more computer programs (including program codes). It should be noted that the computer-readable storage medium here can be a high-speed RAM memory or a non-volatile memory, such as at least one disk memory. The processor can load and execute one or more instructions stored in the computer-readable storage medium to implement the steps of the method in the above embodiment.

[0132] It will be appreciated by those skilled in the art that embodiments of the present invention may be provided as methods, systems, or computer program products. Therefore, the present invention may take the form of a complete hardware embodiment, a complete software embodiment, or an embodiment combining software and hardware. Moreover, the present invention may take the form of a computer program product implemented on one or more computer-usable storage media (including but not limited to disk storage, CD-ROM, optical storage, etc.) containing computer-usable program codes. The schemes in the embodiments of the present invention may be implemented in various computer languages, for example, object-oriented programming language Java and literal scripting language JavaScript, etc.

[0133] The present invention is described with reference to flowcharts and / or block diagrams of methods, devices (systems), and computer program products according to embodiments of the present invention. It should be understood that each process and / or block in the flowchart and / or block diagram, as well as the combination of processes and / or blocks in the flowchart and / or block diagram, can be implemented by computer program instructions. These computer program instructions can be provided to a processor of a general-purpose computer, a special-purpose computer, an embedded processor, or other programmable data processing device to produce a machine, so that the instructions executed by the processor of the computer or other programmable data processing device generate instructions for implementing the processes in the flowchart and / or block diagram. Figure 1 A process or multiple processes and / or boxes Figure 1 A device that provides the functions specified in a block or multiple blocks.

[0134] These computer program instructions may also be stored in a computer-readable memory capable of directing a computer or other programmable data processing device to operate in a specific manner, so that the instructions stored in the computer-readable memory produce an article of manufacture comprising an instruction device, which implements the process Figure 1 A process or multiple processes and / or boxes Figure 1 A function specified in one or more boxes.

[0135] These computer program instructions can also be loaded onto a computer or other programmable data processing device so that a series of operating steps are executed on the computer or other programmable device to produce a computer-implemented process, thereby providing instructions for implementing the process. Figure 1 A process or multiple processes and / or boxes Figure 1 A step that specifies a function in one or more boxes.

[0136] Although the preferred embodiments of the present invention have been described, those skilled in the art may make other changes and modifications to these embodiments once they have learned the basic creative concept. Therefore, the appended claims are intended to be interpreted as including the preferred embodiments and all changes and modifications that fall within the scope of the present invention.

[0137] Obviously, those skilled in the art can make various changes and modifications to the present invention without departing from the spirit and scope of the present invention. Thus, if these modifications and variations of the present invention fall within the scope of the claims of the present invention and their equivalents, the present invention is also intended to include these modifications and variations.

Claims

1. A method for early warning of flood in a transmission line area, characterized in that: include: Collecting scene information of the target transmission line area, building a simulation scene model based on the scene information, and performing hydrological simulation based on the simulation scene model to determine simulated water level data of the target transmission line area; Determine the forecast graded warning index of flooding in the power equipment and facility area in the target transmission line area, and determine the index value of the graded warning index according to the simulated water level data; The index value of the graded warning index is judged using a preset state discrimination function, and if the discrimination result is not 0, a flood warning is issued for the target power transmission line area.

2. The power transmission line area flood warning method according to claim 1, characterized in that: The scene information includes: building foundation morphology information and topographic information in the target transmission line area.

3. The power transmission line area flood warning method according to claim 1, characterized in that: The hydrological simulation based on the simulation scenario model comprises: According to the simulation scenario model, the central axis data, the ridge line data of the surrounding mountains and the elevation data of the target transmission line area are obtained, and the waterway flow direction and confluence path data of the target transmission line area are calculated based on the central axis data, the ridge line data of the surrounding mountains and the elevation data using the eight-direction flow direction modeling technology; Generate a river network according to the waterway flow direction and confluence path data, the actual size of the target transmission line area and the process function of the target transmission line area, and determine the watershed outlet of the river network for the river network to generate a digital watershed; The digital watershed is gridded according to the terrain and boundary condition data of the digital watershed, and the GSSHA model is used to perform hydrological simulation on the gridded digital watershed.

4. The method for early warning of flood in power transmission line area according to claim 3, characterized in that: The hydrological simulation specifically includes: simulating the hydrological process in the target transmission line area; The hydrological processes include rainfall, runoff and evaporation.

5. The power transmission line area flood warning method according to claim 1, characterized in that: The graded warning indicators include: level 4 blue warning indicators for line flooding and suspension risk warning, level 3 yellow warning indicators for line flooding and suspension risk warning, level 2 orange warning indicators for line flooding and suspension risk warning, and level 1 red warning indicators for line flooding and suspension risk warning; The calculation formula of the index value of the graded warning index is as follows: Hb1=90%hw1 Hb2=85%hw2 Hb3=75%hw3 Hb4=70%hw4 Among them, Hb1 is the red snake warning indicator of level 1 risk warning of line flooding and suspension of operation, Hb2 is the orange warning indicator of level 2 risk warning of line flooding and suspension of operation, Hb3 is the yellow warning indicator of level 3 risk warning of line flooding and suspension of operation, Hb4 is the blue warning indicator of level 4 risk warning of line flooding and suspension of operation, hw1 is the water level corresponding to the red flood control level, hw2 is the water level corresponding to the orange flood control level, hw3 is the water level corresponding to the yellow flood control level, and hw4 is the water level corresponding to the blue flood control level.

6. The power transmission line area flood warning method according to claim 1, characterized in that: The preset state discrimination function includes: Wherein, hF represents the simulated water level, if Sb=0, no warning is triggered, if Sb=4, a level 4 blue warning is triggered, if Sb=3, a level 3 yellow warning is triggered, if Sb=2, a level 2 orange warning is triggered, and if Sb=1, a level 1 red warning is triggered.

7. A transmission line area flood warning system, characterized in that: include: A simulation unit, used to collect scene information of a target transmission line area, build a simulation scene model based on the scene information, and perform hydrological simulation based on the simulation scene model to determine simulated water level data of the target transmission line area; A calculation unit, used to determine the predicted graded warning index of flooding in the power equipment and facility area in the target transmission line area, and determine the index value of the graded warning index according to the simulated water level data; The early warning unit is used to use a preset state discrimination function to discriminate the index value of the graded early warning index, and if the discrimination result is not 0, issue a flood warning for the target transmission line area.

8. The power transmission line area flood warning system according to claim 7, characterized in that: The scene information includes: building foundation morphology information and topographic information in the target transmission line area.

9. The power transmission line area flood warning system according to claim 7, characterized in that: The hydrological simulation based on the simulation scenario model comprises: According to the simulation scenario model, the central axis data, the ridge line data of the surrounding mountains and the elevation data of the target transmission line area are obtained, and the waterway flow direction and confluence path data of the target transmission line area are calculated based on the central axis data, the ridge line data of the surrounding mountains and the elevation data using the eight-direction flow direction modeling technology; Generate a river network according to the waterway flow direction and confluence path data, the actual size of the target transmission line area and the process function of the target transmission line area, and determine the watershed outlet of the river network for the river network to generate a digital watershed; The digital watershed is gridded according to the terrain and boundary condition data of the digital watershed, and the GSSHA model is used to perform hydrological simulation on the gridded digital watershed.

10. The power transmission line area flood warning system according to claim 9, characterized in that: The hydrological simulation specifically includes: simulating the hydrological process in the target transmission line area; The hydrological processes include rainfall, runoff and evaporation.

11. The power transmission line area flood warning system according to claim 7, characterized in that: The graded warning indicators include: level 4 blue warning indicators for line flooding and suspension risk warning, level 3 yellow warning indicators for line flooding and suspension risk warning, level 2 orange warning indicators for line flooding and suspension risk warning, and level 1 red warning indicators for line flooding and suspension risk warning; The calculation formula of the index value of the graded warning index is as follows: Hb1=90%hw1 Hb2=85%hw2 Hb3=75%hw3 Hb4=70%hw4 Among them, Hb1 is the red snake warning indicator of level 1 risk warning of line flooding and suspension of operation, Hb2 is the orange warning indicator of level 2 risk warning of line flooding and suspension of operation, Hb3 is the yellow warning indicator of level 3 risk warning of line flooding and suspension of operation, Hb4 is the blue warning indicator of level 4 risk warning of line flooding and suspension of operation, hw1 is the water level corresponding to the red flood control level, hw2 is the water level corresponding to the orange flood control level, hw3 is the water level corresponding to the yellow flood control level, and hw4 is the water level corresponding to the blue flood control level.

12. The power transmission line area flood warning system according to claim 7, characterized in that: The preset state discrimination function includes: Wherein, hF represents the simulated water level, if Sb=0, no warning is triggered, if Sb=4, a level 4 blue warning is triggered, if Sb=3, a level 3 yellow warning is triggered, if Sb=2, a level 2 orange warning is triggered, and if Sb=1, a level 1 red warning is triggered.

13. A computer device, characterized in that: include: one or more processors; a processor for executing one or more programs; When the one or more programs are executed by the one or more processors, the method according to any one of claims 1 to 6 is implemented.

14. A computer-readable storage medium, characterized in that: A computer program is stored thereon, and when the computer program is executed, the method according to any one of claims 1 to 6 is implemented.