Power dispatching management system
By analyzing the historical output power of photovoltaic power stations in various periods in the power dispatch management system, calculating the number of required grid connectors and dynamically controlling their opening, the problem of waste of grid connectors in power dispatch management is solved, and the efficiency of photovoltaic power stations is achieved. operation and energy savings.
Patent Information
- Application Number
- CN202411025784.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Priority Date
- 2023-08-16
- Filing Date
- 2024-07-30
- Publication Date
- 2024-10-01
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
The power dispatch management system cannot obtain the number of grid connectors that need to be deployed in each period by analyzing the historical output power of photovoltaic power stations in different periods, resulting in the opening of redundant grid connectors, resulting in a waste of energy consumption.
A power dispatch management system is designed, including a data acquisition module, a calculation module, a layout module, a data analysis module and a grid connector control module. By calculating the number of photovoltaic panels in the photovoltaic power station, the safety factor and the system capacity of a single photovoltaic panel, Combined with historical output power analysis, the number of grid connectors required in each period is calculated and their opening and closing are dynamically controlled.
It is possible to set the grid connector according to the actual needs of the photovoltaic power station in each period, avoid redundant opening, ensure the normal operation of the photovoltaic power station, reduce energy loss, and ensure the safe operation of the system through the backup quantity.
Smart Images

Figure CN118739433A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of electric power dispatching management, and in particular to an electric power dispatching management system. Background Art
[0002] With the rapid development of renewable energy, photovoltaic power stations have become an important way of power supply. However, the output power of photovoltaic power stations will fluctuate due to factors such as weather, which brings certain challenges to power dispatching management.
[0003] However, in the power dispatching and management system, the system is unable to analyze the historical output power of the photovoltaic power station in different time periods to obtain the number of grid connectors that need to be deployed in each time period, and then control the corresponding number of grid connectors to be opened in each time period according to the number of grid connectors that need to be deployed in each time period, resulting in redundant grid connectors being opened, causing energy waste. Summary of the invention
[0004] The purpose of the present invention is to provide a power dispatching and management system to solve the technical problem that in the power dispatching and management system, the system is unable to analyze the historical output power of the photovoltaic power station in different time periods to obtain the number of grid connectors required to be deployed in each time period, and then determine the number of grid connectors required to be deployed in each time period.
[0005] The purpose of the present invention can be achieved through the following technical solutions:
[0006] A power dispatching management system, comprising:
[0007] A data acquisition module, used to acquire the design capacity of the photovoltaic power station, the number of photovoltaic panels, the system capacity of a single photovoltaic panel and the rated output power of a single grid connector in the photovoltaic power generation system from the storage module and send them to the calculation module;
[0008] The calculation module is used to receive and calculate the number of photovoltaic panels, safety factor, system capacity of a single photovoltaic panel and rated output power of a single grid connector of the photovoltaic power station, and obtain the number of grid connectors required for the photovoltaic power station according to the calculation results, and send them to the layout module. The specific calculation method of the number of grid connectors required for the photovoltaic power station is:
[0009] D=F×S×K
[0010] In the formula, D represents the number of grid connectors required by the photovoltaic power station, F represents the number of photovoltaic panels in the photovoltaic power station, S represents the safety factor of the photovoltaic power station, and K represents the number of grid connectors required for a single photovoltaic panel;
[0011] A layout module is used to calculate and receive the number of grid connectors required for the photovoltaic power station, and to set the grid connectors according to the number of grid connectors required for the photovoltaic power station;
[0012] The data acquisition module is used to obtain the historical output power of the photovoltaic power station within the time range z from the storage module and send it to the data analysis module;
[0013] The data analysis module is used to analyze the historical output power of the photovoltaic power station within the time range z, and analyze and judge it in combination with the rated output power of a single grid connector, and obtain the number of grid connectors required by the photovoltaic power station in different time periods according to the analysis results, and send it to the grid connector control module;
[0014] The grid connector control module is used to control the corresponding number of grid connectors to be turned on according to the required number of grid connectors corresponding to each time period, and to turn off the remaining grid connectors that are not needed.
[0015] As a further solution of the present invention: in the process of calculating the number of grid connectors required for the photovoltaic power station, the specific method of obtaining the number of grid connectors K required for the single photovoltaic panel is:
[0016] S1: Get the system capacity of a single photovoltaic panel and mark it as Z. The system capacity of a single photovoltaic panel refers to the rated power of a single photovoltaic panel.
[0017] S2: Get the rated output power of a single grid connector and mark it as H;
[0018] S3: Calculate the number of grid connectors required for a single photovoltaic panel using the formula Z÷H=K, and mark it as K.
[0019] As a further solution of the present invention: the specific method of obtaining the safety factor S of the photovoltaic power station is:
[0020] The safety factor S of the photovoltaic power station is calculated by the formula S=C×A, where C is the design capacity of the photovoltaic power station, A is the meteorological influence coefficient, and the design capacity of the photovoltaic power station refers to the rated power of the photovoltaic power station;
[0021] Among them, A=W1×β1+W2×β2, W1 is the real-time temperature, W2 is the real-time sunlight irradiance, and β1 and β2 are fixed coefficients.
[0022] As a further solution of the present invention, the specific method for obtaining the number of grid connectors required by the photovoltaic power station at different time periods is as follows:
[0023] Step 1: Divide a day into n equal time periods, where n>1, and select one time period as the designated time period;
[0024] Step 2: Obtain multiple output power values of the photovoltaic power station in a specified period of time, and mark them as E1, E2, ..., Ei, where i refers to the number of power output values corresponding to the photovoltaic power station in the specified period of time, i≥1;
[0025] Step 3: Obtain the maintenance duration corresponding to each power output value of the photovoltaic power station within the specified time period, and mark them as T1, T2, ..., Ti respectively;
[0026] Step 4: Calculate the total output power G1 corresponding to the specified time period through the formula;
[0027] Step 5: Calculate the total grid connector demand J1 corresponding to the specified time period using the formula G1÷H=J1;
[0028] Step 6: Calculate the grid connector demand X1 corresponding to the specified time period by J1÷n=X1;
[0029] When X1 is an integer, no processing is done. When X1 is not an integer, the integer digit of X1 is added by 1 and the remainder digits are deleted. The final value is then used as the final value corresponding to X1.
[0030] Step 7: Repeat steps 1 to 6 to obtain the required number of grid connectors corresponding to each time period, and mark them as X1, X2, ..., Xn.
[0031] As a further solution of the present invention: it also includes a backup quantity generation module;
[0032] The backup quantity generation module is used to obtain the output power values corresponding to each period of the photovoltaic power station within the time range z from the data analysis module, and analyze the power output peak value corresponding to each period, thereby obtaining the backup quantity of the grid connector corresponding to each period, and binding it with the label n of the corresponding period to send it to the backup device control module. The specific method of obtaining the backup quantity of the grid connector corresponding to each period is:
[0033] S01: Mark the maximum value among multiple output power values E1, E2, ..., Ei within a specified period as the power output peak value E imax corresponding to the specified period;
[0034] S02: Calculate the maximum demand J2 of the grid connector corresponding to the specified time period by the formula E i max ÷ H = J2, where H is the rated output power of a single grid connector;
[0035] S03: By J2-J1=V1, the backup quantity V1 of the grid connector corresponding to the specified time period is calculated;
[0036] S04: Repeat steps S01-S03 to obtain the backup quantity of the grid connector corresponding to each time period and mark them as V1, V2, ..., Vn respectively.
[0037] As a further solution of the present invention: it also includes a warning signal generation module and a backup device control module;
[0038] The warning signal generation module is used to monitor the real-time output power of the photovoltaic power station in each period, compare and analyze it with the warning value corresponding to each period, generate a warning signal based on the comparison result, and send the warning signal to the backup device control module;
[0039] The backup device control module is used to obtain the warning signal of each time period and the backup number of the grid connector, and obtain the backup number of the grid connector with the corresponding label n according to the warning signal of each time period, and open the corresponding number of grid connectors according to the backup number of the grid connector.
[0040] As a further solution of the present invention: the specific method of generating the early warning signal is:
[0041] Step 1: Calculate the expected output power corresponding to each time period by the formula Xn×H=Kn, and mark it as Kn;
[0042] Step 2: Calculate the output power warning value Yn corresponding to each time period through Kn×B1=Yn, where B1 is a predetermined fixed coefficient;
[0043] Step 3: Monitor the real-time output power of the photovoltaic power station in each time period and mark it as Ln. When Ln<Yn, no processing is performed. When Ln≥Yn, an early warning signal for the corresponding time period is generated.
[0044] As a further solution of the present invention: a storage module is used to store the design capacity of the photovoltaic power station in the photovoltaic power generation system, the number of photovoltaic panels, the system capacity of a single photovoltaic panel and the rated output power of a single grid connector.
[0045] Beneficial effects of the present invention:
[0046] (1) The present invention obtains the number of grid connectors required for the photovoltaic power station by analyzing the design capacity of the photovoltaic power station, the number of photovoltaic panels, the safety factor, the system capacity of a single photovoltaic panel, and the rated output power of a single grid connector. The grid connectors are arranged in the photovoltaic power station according to the number of grid connectors required for the photovoltaic power station to ensure the normal operation of the photovoltaic power station.
[0047] (2) The present invention analyzes the historical output power of the photovoltaic power station in different time periods, thereby obtaining the number of grid connectors required to be deployed in each time period. According to the number of grid connectors required to be deployed in each time period, the corresponding number of grid connectors are controlled to be turned on in each time period, thereby ensuring the operation requirements of the photovoltaic power station and avoiding the opening of redundant grid connectors, resulting in redundant grid connectors and unnecessary energy loss of the photovoltaic power station;
[0048] (3) The present invention further ensures the safe operation of the photovoltaic power station by setting the backup number of grid connectors corresponding to each time period. On the basis of the required number of grid connectors, a backup number of grid connectors is set to ensure that when the system is running in the time period and the system is overloaded and redundant, the standby grid connector can be quickly started to prepare for emergencies, thereby further ensuring the normal operation of the photovoltaic power station in each time period. BRIEF DESCRIPTION OF THE DRAWINGS
[0049] The present invention will be further described below in conjunction with the accompanying drawings.
[0050] Figure 1 It is a schematic diagram of the system framework structure of the present invention;
[0051] Figure 2 It is a schematic diagram of the framework structure of the method of the present invention. DETAILED DESCRIPTION
[0052] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0053] Embodiment 1
[0054] See also Figure 1-Figure 2 As shown, the present invention is a power dispatching management system, including a storage module, a data acquisition module, a calculation module, a layout module, a data acquisition module, a data analysis module, a power grid connector control module, a backup quantity generation module, an early warning signal generation module and a backup device control module;
[0055] A storage module, used for storing the design capacity of a photovoltaic power station, the number of photovoltaic panels, the system capacity of a single photovoltaic panel and the rated output power of a single grid connector in the photovoltaic power generation system;
[0056] A data acquisition module, used to acquire the design capacity of the photovoltaic power station, the number of photovoltaic panels, the system capacity of a single photovoltaic panel and the rated output power of a single grid connector in the photovoltaic power generation system from the storage module and send them to the calculation module;
[0057] It should be noted that the design capacity of the photovoltaic power station, the number of photovoltaic panels, the system capacity of a single photovoltaic panel and the rated output power of a single grid connector in the photovoltaic power generation system can all be obtained through on-site measurements or the photovoltaic power station design documents;
[0058] The calculation module is used to receive and calculate the number of photovoltaic panels, safety factor, system capacity of a single photovoltaic panel and rated output power of a single grid connector of the photovoltaic power station, and obtain the number of grid connectors required for the photovoltaic power station according to the calculation results, and send them to the layout module. The specific calculation method of the number of grid connectors required for the photovoltaic power station is:
[0059] The number of photovoltaic panels and the safety factor of the photovoltaic power station are quantified and their values are taken. The number of grid connectors D required for the photovoltaic power station is calculated by the calculation formula D=F×S×K, where F represents the number of photovoltaic panels in the photovoltaic power station, S represents the safety factor of the photovoltaic power station, and K represents the number of grid connectors required for a single photovoltaic panel.
[0060] Furthermore, the specific method for obtaining the number K of grid connectors required by the single photovoltaic panel is as follows:
[0061] S1: Get the system capacity of a single photovoltaic panel and mark it as Z. The system capacity of a single photovoltaic panel refers to the rated power of a single photovoltaic panel.
[0062] S2: Get the rated output power of a single grid connector and mark it as H;
[0063] S3: Calculate the number of grid connectors required for a single photovoltaic panel using the formula Z÷H=K, and mark it as K;
[0064] Furthermore, the specific method for obtaining the safety factor S of the photovoltaic power station is as follows.
[0065] The safety factor S of the photovoltaic power station is calculated by the formula S=C×A, where C is the design capacity of the photovoltaic power station, A is the meteorological influence coefficient, and the design capacity of the photovoltaic power station refers to the rated power of the photovoltaic power station;
[0066] Among them, A=W1×β1+W2×β2, W1 is the real-time temperature, W2 is the real-time sunlight irradiance, β1 and β2 are fixed coefficients, and the specific values are determined by relevant staff based on experience.
[0067] The layout module is used to calculate and receive the number D of grid connectors required by the photovoltaic power station, and to set the grid connectors according to the number D of grid connectors required by the photovoltaic power station.
[0068] By analyzing the design capacity of the photovoltaic power station, the number of photovoltaic panels, the safety factor, the system capacity of a single photovoltaic panel and the rated output power of a single grid connector, the number of grid connectors required for the photovoltaic power station is obtained. The grid connectors are set in the photovoltaic power station according to the number of grid connectors required by the photovoltaic power station to ensure the normal operation of the photovoltaic power station.
[0069] Embodiment 2
[0070] As the second embodiment of the present invention, when the present application is implemented, compared with the first embodiment, the technical solution of the present embodiment is different from the first embodiment only in that in the present embodiment, the historical output power of the photovoltaic power station in different time periods is analyzed by the data acquisition module, so as to obtain the number of grid connectors required to be arranged in each time period, and according to the number of grid connectors required to be arranged in each time period, the corresponding number of grid connectors are controlled to be turned on, and the specific steps of obtaining the number of grid connectors required to be arranged in each time period are:
[0071] The data acquisition module is used to obtain the historical output power of the photovoltaic power station within the time range z from the storage module and send it to the data analysis module. The historical output power of the photovoltaic power station within the time range z can be obtained through monitoring equipment or system records;
[0072] Here, the time range z refers to the period of 30 days from the moment the data is obtained, and the moment the data is obtained is not included, that is, z = {1, 2, ..., 30};
[0073] The data analysis module is used to analyze the historical output power of the photovoltaic power station within the time range z, and analyze and judge it in combination with the rated output power of a single grid connector. According to the analysis results, the number of grid connectors required by the photovoltaic power station at different time periods is obtained, and it is sent to the grid connector control module. The specific method for obtaining the number of grid connectors required by the photovoltaic power station at different time periods is as follows:
[0074] Step 1: Divide a day into n equal time periods, where n>1, and select one time period as the designated time period;
[0075] Step 2: Obtain multiple output power values of the photovoltaic power station in a specified period of time, and mark them as E1, E2, ..., Ei, where i refers to the number of power output values corresponding to the photovoltaic power station in the specified period of time, i≥1;
[0076] Step 3: Obtain the maintenance duration corresponding to each power output value of the photovoltaic power station within the specified time period, and mark them as T1, T2, ..., Ti respectively;
[0077] Step 4: Use the formula Calculate and obtain the total output power G1 corresponding to the specified time period;
[0078] Step 5: Calculate the total grid connector demand J1 corresponding to the specified time period using the formula G1÷H=J1;
[0079] Step 6: Calculate the grid connector demand X1 corresponding to the specified time period by J1÷n=X1;
[0080] When X1 is an integer, no processing is done. When X1 is not an integer, the integer digit of X1 is added by 1 and the remainder digits are deleted. The final value is then used as the final value corresponding to X1.
[0081] Step 7: Repeat Step 1 to Step 6 to obtain the required number of grid connectors corresponding to each time period, and mark them as X1, X2, ..., Xn, and input them into the grid connector control module;
[0082] A grid connector control module is used to control the corresponding number of grid connectors to be turned on according to the number of grid connectors required for each time period, and to turn off the remaining grid connectors that are not needed;
[0083] By analyzing the historical output power of the photovoltaic power station in different time periods, the number of grid connectors required to be deployed in each time period is obtained. According to the number of grid connectors required to be deployed in each time period, the corresponding number of grid connectors are controlled to be opened in each time period, ensuring the operation requirements of the photovoltaic power station, while avoiding the opening of redundant grid connectors, resulting in redundant grid connectors and unnecessary energy loss of the photovoltaic power station;
[0084] Embodiment 3
[0085] As the third embodiment of the present invention, when the present application is specifically implemented, compared with the first and second embodiments, the difference from the first and second embodiments is that in the present embodiment, the power output peak value corresponding to each time period is analyzed by the backup quantity generation module, and then the backup quantity of the grid connector corresponding to each time period is obtained, and then the real-time output power of the photovoltaic power station in each time period is monitored to determine the generation of an early warning signal, and the backup equipment model of the corresponding time period is turned on according to the early warning signal;
[0086] The backup quantity generation module is used to obtain the output power values corresponding to each period of the photovoltaic power station within the time range z from the data analysis module, and analyze the power output peak value corresponding to each period, thereby obtaining the backup quantity of the grid connector corresponding to each period, and binding it with the label n of the corresponding period to send it to the backup device control module. The specific method of obtaining the backup quantity of the grid connector corresponding to each period is:
[0087] S01: Mark the maximum value among multiple output power values E1, E2, ..., Ei within the specified time period as the power output peak value Ei corresponding to the specified time period max ;
[0088] S02: By formula E i max ÷H=J2, calculate and obtain the maximum demand J2 of the grid connector corresponding to the specified time period, where H is the rated output power of a single grid connector;
[0089] S03: By J2-J1=V1, the backup quantity V1 of the grid connector corresponding to the specified time period is calculated;
[0090] S04: Repeat steps S01-S03 to obtain the backup quantity of the grid connector corresponding to each time period and mark them as V1, V2, ..., Vn respectively;
[0091] The warning signal generation module is used to monitor the real-time output power of the photovoltaic power station in each period, and compare and analyze it with the warning value corresponding to each period, generate a warning signal based on the comparison result, and send the warning signal to the backup device control module, wherein the specific method of generating the warning signal is:
[0092] Step 1: Calculate the expected output power corresponding to each time period by the formula Xn×H=Kn, and mark it as Kn;
[0093] Step 2: Calculate the output power warning value Yn corresponding to each time period through Kn×B1=Yn, where B1 is a predetermined fixed coefficient, and B1=0.8 here;
[0094] Step 3: Monitor the real-time output power of the photovoltaic power station in each time period and mark it as Ln. When Ln<Yn, no processing is performed. When Ln≥Yn, an early warning signal for the corresponding time period is generated.
[0095] The backup device control module is used to obtain the warning signal of each time period and the backup number of the grid connector, and obtain the backup number of the grid connector with the corresponding label n according to the warning signal of each time period, and open the corresponding number of grid connectors according to the backup number of the grid connector.
[0096] By setting the backup number of grid connectors corresponding to each time period, the safe operation of the photovoltaic power station is further guaranteed. On the basis of the required number of grid connectors, the backup number of grid connectors is set to ensure that when the system is running in this time period, when the system is overloaded and redundant, the standby grid connector can be quickly started to prepare for emergencies, further ensuring the normal operation of the photovoltaic power station in each time period;
[0097] Embodiment 4
[0098] As the fourth embodiment of the present invention, when the present application is specifically implemented, compared with the first, second and third embodiments, the technical solution of this embodiment is to combine and implement the solutions of the first, second and third embodiments.
[0099] The above formulas are all dimensionless and numerical calculations. The formula is a formula for the most recent real situation obtained by collecting a large amount of data and performing software simulation. The preset parameters and thresholds in the formula are set by technicians in this field according to actual conditions.
[0100] The above is only a specific implementation of the present application, but the protection scope of the present application is not limited thereto. Any person skilled in the art who is familiar with the present technical field can easily think of changes or substitutions within the technical scope disclosed in the present application, which should be included in the protection scope of the present application. Therefore, the protection scope of the present application should be based on the protection scope of the claims.
Claims
1. A power dispatching management system, characterized in that: include: A data acquisition module, used to acquire the design capacity of the photovoltaic power station, the number of photovoltaic panels, the system capacity of a single photovoltaic panel and the rated output power of a single grid connector in the photovoltaic power generation system from the storage module and send them to the calculation module; The calculation module is used to receive and calculate the number of photovoltaic panels, safety factor, system capacity of a single photovoltaic panel and rated output power of a single grid connector of the photovoltaic power station, and obtain the number of grid connectors required for the photovoltaic power station according to the calculation results, and send them to the layout module. The specific calculation method of the number of grid connectors required for the photovoltaic power station is: D=F×S×K In the formula, D represents the number of grid connectors required by the photovoltaic power station, F represents the number of photovoltaic panels in the photovoltaic power station, S represents the safety factor of the photovoltaic power station, and K represents the number of grid connectors required for a single photovoltaic panel; A layout module is used to calculate and receive the number of grid connectors required for the photovoltaic power station, and to set the grid connectors according to the number of grid connectors required for the photovoltaic power station; The data acquisition module is used to obtain the historical output power of the photovoltaic power station within the time range z from the storage module and send it to the data analysis module; The data analysis module is used to analyze the historical output power of the photovoltaic power station within the time range z, and analyze and judge it in combination with the rated output power of a single grid connector, and obtain the number of grid connectors required by the photovoltaic power station in different time periods according to the analysis results, and send it to the grid connector control module; The grid connector control module is used to control the corresponding number of grid connectors to be turned on according to the required number of grid connectors corresponding to each time period, and to turn off the remaining grid connectors that are not needed.
2. A power dispatching management system according to claim 1, characterized in that: In the process of calculating the number of grid connectors required for the photovoltaic power station, the specific method of obtaining the number of grid connectors K required for the single photovoltaic panel is as follows: S1: Get the system capacity of a single photovoltaic panel and mark it as Z. The system capacity of a single photovoltaic panel refers to the rated power of a single photovoltaic panel. S2: Get the rated output power of a single grid connector and mark it as H; S3: Calculate the number of grid connectors required for a single photovoltaic panel using the formula Z÷H=K, and mark it as K.
3. A power dispatching management system according to claim 2, characterized in that: The specific method of obtaining the safety factor S of a photovoltaic power station is: The safety factor S of the photovoltaic power station is calculated by the formula S=C×A, where C is the design capacity of the photovoltaic power station, A is the meteorological influence coefficient, and the design capacity of the photovoltaic power station refers to the rated power of the photovoltaic power station; Among them, A=W1×β1+W2×β2, W1 is the real-time temperature, W2 is the real-time sunlight irradiance, and β1 and β2 are fixed coefficients.
4. The power dispatching management system according to claim 3 is characterized in that: The specific method for obtaining the number of grid connectors required by the photovoltaic power station at different times is as follows: Step 1: Divide a day into n equal time periods, where n>1, and select one time period as the designated time period; Step 2: Obtain multiple output power values of the photovoltaic power station in a specified period of time, and mark them as E1, E2, ..., Ei, where i refers to the number of power output values corresponding to the photovoltaic power station in the specified period of time, i ≥ 1; Step 3: Obtain the maintenance duration corresponding to each power output value of the photovoltaic power station within the specified time period, and mark them as T1, T2, ..., Ti respectively; Step 4: Use the formula Calculate and obtain the total output power G1 corresponding to the specified time period; Step 5: Calculate the total grid connector demand J1 corresponding to the specified time period using the formula G1÷H=J1; Step 6: Through J1÷n=X1; Calculate and obtain the grid connector demand X1 corresponding to the specified time period; When X1 is an integer, no processing is done. When X1 is not an integer, the integer digit of X1 is added by 1 and the remainder digits are deleted. The final value is then used as the final value corresponding to X1. Step 7: Repeat steps 1 to 6 to obtain the required number of grid connectors corresponding to each time period, and mark them as X1, X2, ..., Xn.
5. A power dispatching management system according to claim 4, characterized in that: It also includes a backup quantity generation module; The backup quantity generation module is used to obtain the output power values corresponding to each period of the photovoltaic power station within the time range z from the data analysis module, and analyze the power output peak value corresponding to each period, thereby obtaining the backup quantity of the grid connector corresponding to each period, and binding it with the label n of the corresponding period to send it to the backup device control module. The specific method of obtaining the backup quantity of the grid connector corresponding to each period is: S01: Mark the maximum value among multiple output power values E1, E2, ..., Ei within the specified time period as the power output peak value Ei corresponding to the specified time period max ; S02: By formula Ei max ÷H=J2, calculate and obtain the maximum demand J2 of the grid connector corresponding to the specified time period, where H is the rated output power of a single grid connector; S03: By J2-J1=V1, the backup quantity V1 of the grid connector corresponding to the specified time period is calculated; S04: Repeat steps S01-S03 to obtain the backup quantity of the grid connector corresponding to each time period and mark them as V1, V2, ..., Vn respectively.
6. A power dispatching management system according to claim 5, characterized in that: It also includes an early warning signal generation module and a backup equipment control module; The warning signal generation module is used to monitor the real-time output power of the photovoltaic power station in each period, and compare and analyze it with the warning value corresponding to each period, generate a warning signal based on the comparison result, and send the warning signal to the backup device control module, wherein the specific method of generating the warning signal is: Step 1: Calculate the expected output power corresponding to each time period by the formula Xn×H=Kn, and mark it as Kn; Step 2: Calculate the output power warning value Yn corresponding to each time period through Kn×B1=Yn, where B1 is a predetermined fixed coefficient; Step 3: Monitor the real-time output power of the photovoltaic power station in each period and mark it as Ln. When Ln<Yn, no processing is performed. When Ln≥Yn, an early warning signal of the corresponding period is generated. The backup device control module is used to obtain the warning signal of each time period and the backup number of the grid connector, and obtain the backup number of the grid connector with the corresponding label n according to the warning signal of each time period, and open the corresponding number of grid connectors according to the backup number of the grid connector.
7. The power dispatching management system according to claim 1, characterized in that: The storage module is used to store the design capacity of the photovoltaic power station in the photovoltaic power generation system, the number of photovoltaic panels, the system capacity of a single photovoltaic panel and the rated output power of a single grid connector.