Remote sequence control checking method, system and device based on transformer substation
By adopting the remote sequence control verification method in the substation and utilizing the dual verification method of virtual simulation and actual operation, the potential safety hazards of the sequence control logic function and operation ticket verification in the one-key sequence control of the substation are solved, ensuring the safety of the operation. sex and accuracy.
Patent Information
- Application Number
- CN202410758755.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-06-13
- Publication Date
- 2024-10-01
- Estimated Expiration
- 2044-06-13
AI Technical Summary
In the one-key sequence control project of the power system substation, there is a lack of effective on-site testing and acceptance technology, which leads to the heavy reliance on manual experience for verification of sequence control logic functions and operation tickets, posing great safety risks.
The remote sequence control verification method based on the substation is used to determine the logical correctness of the sequence control instructions through virtual simulation, and the operation ticket is forwarded to the target device through the data gateway for one-click sequence control operation, combined with telemetry signal comparison to ensure the operation ticket The accuracy and equipment status changes are consistent with the preset status to achieve double verification.
It ensures the safety of one-key sequence control of the substation, avoids the frequent risks of manual operations, and improves the accuracy and safety of operations.
Smart Images

Figure CN118739563A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the field of one-button sequential control of a substation, and in particular to a remote sequential control verification method, system and device based on a substation. Background Art
[0002] With the continuous development of intelligent technology, substation one-button sequential control technology has been widely used in practical applications. One-button sequential control is an operation mode of substation switching operation, which can realize the prefabrication of operation project software, modular construction of operation tasks, automatic identification of equipment status, intelligent verification of anti-error interlocking, one-button start of operation steps, and automatic sequential execution of operation process, saving a lot of manpower and material resources. At the same time, it also improves safety accordingly without manual direct operation of primary equipment.
[0003] At present, in the implementation of one-button sequential control projects in new or renovated substations, the power system lacks effective technical support for on-site testing and acceptance of one-button sequential control. The testing and acceptance of one-button sequential control heavily relies on manual experience and frequent operation of primary equipment. There is no effective verification method for sequential control logic functions and operation tickets, which brings great safety hazards. Summary of the invention
[0004] The technical problem to be solved by the present invention is to provide a remote sequential control verification method, system and device based on a substation, which can effectively verify the sequential control logic function and operation ticket verification, and ensure the safety of the one-key sequential control of the substation.
[0005] The technical solution of the present invention to solve the above technical problems is as follows: A remote sequential control verification method based on a substation comprises the following steps:
[0006] S1, in the initial state, obtaining a first telemetry signal of a target device in the substation;
[0007] S2, obtaining the task to be sequentially controlled, parsing the task to be sequentially controlled to obtain a sequential control instruction, and judging whether the sequential control locking logic of the sequential control instruction is correct based on a virtual simulation method, if it is correct, executing S3, if not, executing S7;
[0008] S3, receiving the sequence control instruction and generating an operation ticket through the one-key sequence control host, and performing intelligent error prevention on the one-key sequence control host based on the operation ticket;
[0009] S4, forwarding the operation ticket to the target device through the data gateway machine to perform a one-key sequential control operation on the target device;
[0010] S5, acquiring a second telemetry signal of the target device, and acquiring a state change of the target device by comparing the first telemetry signal with the second telemetry signal;
[0011] S6, determining whether the state change of the target device is consistent with the state change preset in the task to be sequentially controlled, if the state change is consistent, determining that the one-key sequential control operation is successful, if the state change is inconsistent, executing S7;
[0012] S7, modify the task to be sequentially controlled, and return to execute S2-S6 until the one-key sequential control operation is successful.
[0013] Based on the above technical solution, the present invention can also be improved as follows.
[0014] Further, in S1, the first telemetry signal is an electrical parameter signal measured by the target device when the target device does not execute the operation instruction of the operation ticket;
[0015] In said S5, said second telemetry signal is an electrical parameter signal measured by said target device after executing the operation instruction of said operation ticket;
[0016] The electrical parameter signals include current signals, voltage signals and power signals.
[0017] Further, in S2, the process of judging whether the sequential control locking logic of the sequential control instruction is correct is as follows:
[0018] S21, build and train the logic simulation model;
[0019] S22, inputting the sequence control instruction into the logic simulation model, and simulating the sequence control instruction using the logic simulation model to obtain a simulation result;
[0020] S23, judging whether the simulation result matches the preset sequence control result in the sequence control task to be controlled, if so, judging that the sequence control blocking logic of the sequence control instruction is correct, if not, judging that the sequence control blocking logic of the sequence control instruction is incorrect and executing S24;
[0021] S24, analyzing the unmatched simulation results to determine the source of the mismatch; wherein the source includes the logic simulation model and the task to be sequentially controlled;
[0022] S25, when the source of the mismatch is the logic simulation model, return to S21 to retrain the logic simulation model to improve the accuracy of the logic simulation model, and execute S22-S24; when the source of the mismatch is the task to be controlled, execute S7.
[0023] Further, in S3, the one-button sequential control host is intelligently prevented from operating incorrectly based on the operation ticket through the intelligent error prevention host, and the specific process of the intelligent error prevention is:
[0024] The intelligent anti-error host sends a remote control unlocking command to the one-button sequence control host to obtain the sole operating right of the target device. When the operation instructions of the operation ticket are completed, the intelligent anti-error host sends a remote control locking command to the one-button sequence control host to release the sole operating right of the target device.
[0025] Further, in S4, the process of forwarding the operation ticket to the target device through the data gateway machine also includes the following steps:
[0026] According to the telemetry configuration in the data communication gateway scheduling link forwarding table file, a corresponding signal is triggered to perform consistency check on the telemetry forwarding value of the data communication gateway centralized control link and the telemetry forwarding value of the scheduling link.
[0027] Further, in S5, comparing the first telemetry signal and the second telemetry signal to obtain the state change of the target device is specifically as follows:
[0028] Performing a difference process on the current signal in the first telemetry signal and the current signal in the second telemetry signal to obtain a current difference value;
[0029] Performing a difference processing on the voltage signal in the first telemetry signal and the voltage signal in the second telemetry signal to obtain a voltage difference value;
[0030] Performing a difference processing on the power signal in the first telemetry signal and the power signal in the second telemetry signal to obtain a power difference value;
[0031] The current difference, the voltage difference, and the power difference represent the state change.
[0032] Furthermore, the preset state change in the task to be sequentially controlled includes a preset current difference threshold, a preset voltage difference threshold and a preset power difference threshold, then S6 is specifically,
[0033] Determine whether the current difference is within the current difference threshold range, determine whether the voltage difference is within the voltage difference threshold range, and determine whether the power difference is within the power difference threshold range;
[0034] If the current difference is within the current difference threshold range, the voltage difference is within the voltage difference threshold range, and the power difference is within the power difference threshold range, then it is determined that the state change of the target device is consistent with the state change preset in the task to be controlled; otherwise, it is determined that the state change of the target device is inconsistent with the state change preset in the task to be controlled.
[0035] Further, in said S7,
[0036] When the sequence control locking logic of the sequence control instruction is correct, the task to be sequence controlled is modified in S7 according to the sequence control locking logic of the sequence control instruction;
[0037] When the state change of the target device does not match the state change preset in the task to be sequentially controlled, the task to be sequentially controlled is modified according to the state change in S7.
[0038] On the basis of the above-mentioned remote sequential control verification method based on a substation, the present invention also provides a remote sequential control verification system based on a substation.
[0039] A remote sequential control verification system based on a substation includes the following modules:
[0040] A telemetry signal acquisition module, which is used to acquire a first telemetry signal of a target device in the substation in an initial state;
[0041] A logic judgment module, which is used to obtain a task to be sequentially controlled, parse the task to be sequentially controlled to obtain a sequential control instruction, and judge whether the sequential control locking logic of the sequential control instruction is correct based on a virtual simulation method;
[0042] An error prevention module, which is used to receive the sequence control instruction through the one-key sequence control host and generate an operation ticket under the condition that the logic of the sequence control instruction is correct, and to perform intelligent error prevention on the one-key sequence control host based on the operation ticket;
[0043] A one-key sequential control operation module, which is used to forward the operation ticket to the target device through the data gateway machine under the condition that the anti-mischeck is passed, so as to perform a one-key sequential control operation on the target device;
[0044] The telemetry signal acquisition module is further used to acquire a second telemetry signal of the target device;
[0045] a comparison module, configured to obtain a state change of the target device by comparing the first telemetry signal with the second telemetry signal;
[0046] A state judgment module, which is used to judge whether the state change of the target device is consistent with the state change preset in the task to be sequentially controlled;
[0047] The modification module is used to modify the task to be sequentially controlled under the condition that the logic of the sequential control instruction is incorrect or the state change is inconsistent.
[0048] On the basis of the above-mentioned remote sequential control verification method based on a substation, the present invention also provides a remote sequential control verification device based on a substation.
[0049] A remote sequential control verification device based on a substation comprises a processor, a memory and a computer program stored in the memory. When the computer program is executed by the processor, the remote sequential control verification method based on a substation as described above is implemented.
[0050] The beneficial effects of the present invention are as follows: in a remote sequential control verification method, system and device based on a substation of the present invention, the sequential control locking logic of the sequential control instruction is verified by virtual simulation, and the operation ticket in the one-key sequential control process is verified by actual operation; this combination of virtual and on-site actual methods performs double verification of the remote sequential control to ensure the safety of the one-key sequential control of the substation. BRIEF DESCRIPTION OF THE DRAWINGS
[0051] Figure 1 It is a flow chart of a remote sequential control verification method based on a substation of the present invention;
[0052] Figure 2 The present invention is a structural block diagram of a remote sequential control verification system based on a substation. DETAILED DESCRIPTION
[0053] The principles and features of the present invention are described below in conjunction with the accompanying drawings. The examples given are only used to explain the present invention and are not used to limit the scope of the present invention.
[0054] like Figure 1 As shown, a remote sequential control verification method based on a substation includes the following steps:
[0055] S1, in the initial state, obtaining a first telemetry signal of a target device in the substation;
[0056] S2, obtaining the task to be sequentially controlled, parsing the task to be sequentially controlled to obtain a sequential control instruction, and judging whether the sequential control locking logic of the sequential control instruction is correct based on a virtual simulation method, if it is correct, executing S3, if not, executing S7;
[0057] S3, receiving the sequence control instruction and generating an operation ticket through the one-key sequence control host, and performing intelligent error prevention on the one-key sequence control host based on the operation ticket;
[0058] S4, forwarding the operation ticket to the target device through the data gateway machine to perform a one-key sequential control operation on the target device;
[0059] S5, acquiring a second telemetry signal of the target device, and acquiring a state change of the target device by comparing the first telemetry signal with the second telemetry signal;
[0060] S6, determining whether the state change of the target device is consistent with the state change preset in the task to be sequentially controlled, if the state change is consistent, determining that the one-key sequential control operation is successful, if the state change is inconsistent, executing S7;
[0061] S7, modify the task to be sequentially controlled, and return to execute S2-S6 until the one-key sequential control operation is successful.
[0062] In the present invention, the verification of the sequential control locking logic of the sequential control instruction is judged by virtual simulation, and the verification of the operation ticket is carried out by sending the operation ticket to the target device and verifying it according to the actual corresponding changes of the target device. It belongs to the actual on-site verification. This combined verification method is safe and reliable and avoids loopholes.
[0063] In some embodiments, in S1, the first telemetry signal is an electrical parameter signal measured by the target device when the target device does not execute the operation instruction of the operation ticket;
[0064] In said S5, said second telemetry signal is an electrical parameter signal measured by said target device after executing the operation instruction of said operation ticket;
[0065] The electrical parameter signals include current signals, voltage signals and power signals.
[0066] Before the one-key sequence control, the target device is in the initial state, and the initial state signal of the target device at this time is obtained as the first telemetry signal. After the one-key sequence control is performed on the target device, the target device will respond, for example, the knife switch will be closed or opened after the target device responds to the operation ticket, and the state signal of the target device at this time is obtained as the second telemetry signal.
[0067] In some embodiments, in S2, the process of determining whether the sequential control locking logic of the sequential control instruction is correct is as follows:
[0068] S21, build and train the logic simulation model;
[0069] S22, inputting the sequence control instruction into the logic simulation model, and simulating the sequence control instruction using the logic simulation model to obtain a simulation result;
[0070] S23, judging whether the simulation result matches the preset sequence control result in the sequence control task to be controlled, if so, judging that the sequence control blocking logic of the sequence control instruction is correct, if not, judging that the sequence control blocking logic of the sequence control instruction is incorrect and executing S24;
[0071] S24, analyzing the unmatched simulation results to determine the source of the mismatch; wherein the source includes the logic simulation model and the task to be sequentially controlled;
[0072] S25, when the source of the mismatch is the logic simulation model, return to S21 to retrain the logic simulation model to improve the accuracy of the logic simulation model, and execute S22-S24; when the source of the mismatch is the task to be controlled, execute S7.
[0073] The present invention can determine whether the source of the mismatch is the logic simulation model or the task to be controlled by analyzing the mismatched simulation results, and when the source of the mismatch is the logic simulation model, return to S21 to retrain the logic simulation model to improve the accuracy of the logic simulation model; this can avoid the influence of the problems of the logic simulation model itself on the verification results, and at the same time, the logic simulation model can be repeatedly trained to improve the model accuracy, so that virtual simulation can be performed more reliably.
[0074] In some embodiments, in S3, the one-button sequential control host is intelligently prevented from operating incorrectly based on the operation ticket through the intelligent error prevention host, and the specific process of intelligent error prevention is:
[0075] The intelligent anti-error host sends a remote control unlocking command to the one-button sequence control host to obtain the sole operating right of the target device. When the operation instructions of the operation ticket are completed, the intelligent anti-error host sends a remote control locking command to the one-button sequence control host to release the sole operating right of the target device.
[0076] The intelligent error prevention of the present invention can ensure that the target device has the only operating right, and then control the target device accordingly, ensuring that when the target device is controlled, the target device will not be controlled by other instructions, thereby ensuring the correct implementation of the one-key sequential control operation, avoiding the situation where different instructions from different sources control the target device, ensuring the safety of equipment operation, and improving the correctness of the one-key sequential control operation.
[0077] In some embodiments, in S4, the process of forwarding the operation ticket to the target device through the data gateway machine further includes the following steps:
[0078] According to the telemetry configuration in the data communication gateway scheduling link forwarding table file, a corresponding signal is triggered to perform consistency check on the telemetry forwarding value of the data communication gateway centralized control link and the telemetry forwarding value of the scheduling link.
[0079] The present invention also performs consistency check on the telemetry forwarding value of the data communication gateway centralized control link and the telemetry forwarding value of the scheduling link during the one-key sequential control process, which can further verify the one-key sequential control. When the telemetry forwarding value of the data communication gateway centralized control link and the telemetry forwarding value of the scheduling link are inconsistent, it may also indicate that there is a problem with the operation ticket. Therefore, when the consistency check of the telemetry forwarding value of the data communication gateway centralized control link and the telemetry forwarding value of the scheduling link fails, S7 is also executed to modify the task to be sequentially controlled.
[0080] In some embodiments, in S5, comparing the first telemetry signal with the second telemetry signal to obtain the state change of the target device is specifically:
[0081] Performing a difference process on the current signal in the first telemetry signal and the current signal in the second telemetry signal to obtain a current difference value;
[0082] Performing a difference processing on the voltage signal in the first telemetry signal and the voltage signal in the second telemetry signal to obtain a voltage difference value;
[0083] Performing a difference processing on the power signal in the first telemetry signal and the power signal in the second telemetry signal to obtain a power difference value;
[0084] The current difference, the voltage difference and the power difference represent the state change. In some embodiments, the state change preset in the task to be sequentially controlled includes a preset current difference threshold, a preset voltage difference threshold and a preset power difference threshold, then S6 is specifically,
[0085] Determine whether the current difference is within the current difference threshold range, determine whether the voltage difference is within the voltage difference threshold range, and determine whether the power difference is within the power difference threshold range;
[0086] If the current difference is within the current difference threshold range, the voltage difference is within the voltage difference threshold range, and the power difference is within the power difference threshold range, then it is determined that the state change of the target device is consistent with the state change preset in the task to be controlled; otherwise, it is determined that the state change of the target device is inconsistent with the state change preset in the task to be controlled.
[0087] The present invention characterizes the state change through the change of three power parameters: current, voltage and power. If one power parameter change does not meet the requirement, it indicates that the one-key sequential control fails. Such strict judgment conditions can ensure the safety of the one-key sequential control.
[0088] In some embodiments, in said S7,
[0089] When the sequence control locking logic of the sequence control instruction is correct, the task to be sequence controlled is modified in S7 according to the sequence control locking logic of the sequence control instruction;
[0090] When the state change of the target device does not match the state change preset in the task to be sequentially controlled, the task to be sequentially controlled is modified according to the state change in S7.
[0091] On the basis of the above-mentioned remote sequential control verification method based on a substation, the present invention also provides a remote sequential control verification system based on a substation.
[0092] like Figure 2 As shown, a remote sequential control verification system based on a substation includes the following modules:
[0093] A telemetry signal acquisition module, which is used to acquire a first telemetry signal of a target device in the substation in an initial state;
[0094] A logic judgment module, which is used to obtain a task to be sequentially controlled, parse the task to be sequentially controlled to obtain a sequential control instruction, and judge whether the sequential control locking logic of the sequential control instruction is correct based on a virtual simulation method;
[0095] An error prevention module, which is used to receive the sequence control instruction through the one-key sequence control host and generate an operation ticket under the condition that the logic of the sequence control instruction is correct, and to perform intelligent error prevention on the one-key sequence control host based on the operation ticket;
[0096] A one-key sequential control operation module, which is used to forward the operation ticket to the target device through the data gateway machine under the condition that the anti-mischeck is passed, so as to perform a one-key sequential control operation on the target device;
[0097] The telemetry signal acquisition module is further used to acquire a second telemetry signal of the target device;
[0098] a comparison module, configured to obtain a state change of the target device by comparing the first telemetry signal with the second telemetry signal;
[0099] A state judgment module, which is used to judge whether the state change of the target device is consistent with the state change preset in the task to be sequentially controlled;
[0100] The modification module is used to modify the task to be sequentially controlled under the condition that the logic of the sequential control instruction is incorrect or the state change is inconsistent.
[0101] On the basis of the above-mentioned remote sequential control verification method based on a substation, the present invention also provides a remote sequential control verification device based on a substation.
[0102] A remote sequential control verification device based on a substation comprises a processor, a memory and a computer program stored in the memory. When the computer program is executed by the processor, the remote sequential control verification method based on a substation as described above is implemented.
[0103] In a remote sequential control verification method, system and device based on a substation of the present invention, whether the sequential control locking logic of the sequential control instruction is correct is verified by virtual simulation, and the operation ticket in the one-key sequential control process is verified by actual operation; this combination of virtual and on-site actual methods performs double verification of the remote sequential control to ensure the safety of the one-key sequential control of the substation.
[0104] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principle of the present invention should be included in the protection scope of the present invention.
Claims
1. A remote sequential control verification method based on a substation, characterized in that: The following steps are included: S1, in the initial state, obtaining a first telemetry signal of a target device in the substation; S2, obtaining the task to be sequentially controlled, parsing the task to be sequentially controlled to obtain a sequential control instruction, and judging whether the sequential control locking logic of the sequential control instruction is correct based on a virtual simulation method, if it is correct, executing S3, if not, executing S7; S3, receiving the sequence control instruction and generating an operation ticket through the one-key sequence control host, and performing intelligent error prevention on the one-key sequence control host based on the operation ticket; S4, forwarding the operation ticket to the target device through the data gateway machine to perform a one-key sequential control operation on the target device; S5, acquiring a second telemetry signal of the target device, and acquiring a state change of the target device by comparing the first telemetry signal with the second telemetry signal; S6, determining whether the state change of the target device is consistent with the state change preset in the task to be sequentially controlled, if the state change is consistent, determining that the one-key sequential control operation is successful, if the state change is inconsistent, executing S7; S7, modify the task to be sequentially controlled, and return to execute S2-S6 until the one-key sequential control operation is successful.
2. The remote sequential control verification method based on substation according to claim 1 is characterized in that: In S1, the first telemetry signal is an electrical parameter signal measured by the target device when the target device does not execute the operation instruction of the operation ticket; In said S5, said second telemetry signal is an electrical parameter signal measured by said target device after executing the operation instruction of said operation ticket; The electrical parameter signals include current signals, voltage signals and power signals.
3. The remote sequential control verification method based on substation according to claim 1 is characterized in that: In S2, the process of judging whether the sequential control locking logic of the sequential control instruction is correct is as follows: S21, build and train the logic simulation model; S22, inputting the sequence control instruction into the logic simulation model, and simulating the sequence control instruction using the logic simulation model to obtain a simulation result; S23, judging whether the simulation result matches the preset sequence control result in the sequence control task to be controlled, if so, judging that the sequence control blocking logic of the sequence control instruction is correct, if not, judging that the sequence control blocking logic of the sequence control instruction is incorrect and executing S24; S24, analyzing the unmatched simulation results to determine the source of the mismatch; wherein the source includes the logic simulation model and the task to be sequentially controlled; S25, when the source of the mismatch is the logic simulation model, return to S21 to retrain the logic simulation model to improve the accuracy of the logic simulation model, and execute S22-S24; when the source of the mismatch is the task to be controlled, execute S7.
4. The remote sequential control verification method based on substation according to claim 1 is characterized in that: In S3, the one-button sequence control host is intelligently prevented from operating incorrectly based on the operation ticket through the intelligent error prevention host, and the specific process of the intelligent error prevention is as follows: The intelligent anti-error host sends a remote control unlocking command to the one-button sequence control host to obtain the sole operating right of the target device. When the operation instructions of the operation ticket are completed, the intelligent anti-error host sends a remote control locking command to the one-button sequence control host to release the sole operating right of the target device.
5. The remote sequential control verification method based on substation according to claim 1 is characterized in that: In S4, the process of forwarding the operation ticket to the target device through the data gateway machine also includes the following steps: According to the telemetry configuration in the data communication gateway scheduling link forwarding table file, a corresponding signal is triggered to perform consistency check on the telemetry forwarding value of the data communication gateway centralized control link and the telemetry forwarding value of the scheduling link.
6. The remote sequential control verification method based on substation according to claim 2 is characterized in that: In S5, comparing the first telemetry signal with the second telemetry signal to obtain the state change of the target device is specifically as follows: Performing a difference process on the current signal in the first telemetry signal and the current signal in the second telemetry signal to obtain a current difference value; Performing a difference processing on the voltage signal in the first telemetry signal and the voltage signal in the second telemetry signal to obtain a voltage difference value; Performing a difference processing on the power signal in the first telemetry signal and the power signal in the second telemetry signal to obtain a power difference value; The current difference, the voltage difference, and the power difference represent the state change.
7. The remote sequential control verification method based on substation according to claim 6 is characterized in that: The preset state change in the task to be sequentially controlled includes a preset current difference threshold, a preset voltage difference threshold and a preset power difference threshold, then S6 is specifically, Determine whether the current difference is within the current difference threshold range, determine whether the voltage difference is within the voltage difference threshold range, and determine whether the power difference is within the power difference threshold range; If the current difference is within the current difference threshold range, the voltage difference is within the voltage difference threshold range, and the power difference is within the power difference threshold range, then it is determined that the state change of the target device is consistent with the state change preset in the task to be controlled; otherwise, it is determined that the state change of the target device is inconsistent with the state change preset in the task to be controlled.
8. The remote sequential control verification method based on substation according to claim 1 is characterized in that: In said S7, When the sequence control locking logic of the sequence control instruction is correct, the task to be sequence controlled is modified in S7 according to the sequence control locking logic of the sequence control instruction; When the state change of the target device does not match the state change preset in the task to be sequentially controlled, the task to be sequentially controlled is modified according to the state change in S7.
9. A remote sequential control verification system based on a substation, characterized by: Includes the following modules, A telemetry signal acquisition module, which is used to acquire a first telemetry signal of a target device in the substation in an initial state; A logic judgment module, which is used to obtain a task to be sequentially controlled, parse the task to be sequentially controlled to obtain a sequential control instruction, and judge whether the sequential control locking logic of the sequential control instruction is correct based on a virtual simulation method; An error prevention module, which is used to receive the sequence control instruction through the one-key sequence control host and generate an operation ticket under the condition that the logic of the sequence control instruction is correct, and to perform intelligent error prevention on the one-key sequence control host based on the operation ticket; A one-key sequential control operation module, which is used to forward the operation ticket to the target device through the data gateway machine under the condition that the anti-mischeck is passed, so as to perform a one-key sequential control operation on the target device; The telemetry signal acquisition module is further used to acquire a second telemetry signal of the target device; a comparison module, configured to obtain a state change of the target device by comparing the first telemetry signal with the second telemetry signal; A state judgment module, which is used to judge whether the state change of the target device is consistent with the state change preset in the task to be sequentially controlled; The modification module is used to modify the task to be sequentially controlled under the condition that the logic of the sequential control instruction is incorrect or the state change is inconsistent.
10. A remote sequential control verification device based on a substation, characterized in that: The invention comprises a processor, a memory and a computer program stored in the memory, wherein when the computer program is executed by the processor, the remote sequential control verification method based on a substation as described in any one of claims 1 to 8 is implemented.
Citation Information
Patent Citations
Control and protection method for thyristor controlled phase shifter of supergrid
CN104377691A
Sequence control system and method for switching operation of transformer substation
CN111614157A
One-key sequential control operation ticket testing method and device for transformer substation
CN113485214A
Thermal power generating unit automatic start-stop system based on digital simulation and development method thereof
CN113970890A
Sequential control logic checking device and method based on message monitoring
CN116203927A
Cited By
GIS substation one-key sequential control anti-error method, system and device
CN119209935A
A one-button sequential control error prevention method, system and device for GIS substation
CN119209935B