Modularized installation and construction method for blast furnace frame
Through the modular installation and construction method of the blast furnace frame, the problems of low lifting efficiency of single-piece blast furnace frames and frequent high-altitude operations are solved, and an efficient and safe installation process is achieved. The three-dimensional modeling software is used to assist in calculating the weight and center of gravity, reducing the number of hoisting and Construction period.
Patent Information
- Application Number
- CN202410835383.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-06-26
- Publication Date
- 2024-10-08
AI Technical Summary
The single-piece hoisting method of the blast furnace frame is inefficient, high-altitude operations are frequent, and the use of large machinery is wasteful and uneconomical.
The modular installation and construction method of the blast furnace frame is adopted, including the overall hoisting after the assembly of each part of the frame on the ground, and the use of SOLIDWORKS three-dimensional modeling software to calculate the weight and center of gravity position, reducing high-altitude operations and the use of large machinery.
It greatly improves the construction efficiency, reduces the risks and construction period of high-altitude operations, saves costs, and achieves rapid and safe installation of the blast furnace frame.
Smart Images

Figure CN118745491A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of blast furnace construction, and in particular to a modular installation construction method for a blast furnace frame. Background Art
[0002] The blast furnace frame is a steel structure arranged around the furnace shell to bear the load of the furnace body and furnace top equipment. The structural form of the furnace frame is related to the form of the blast furnace shell. The frame consists of three parts: the lower frame of the furnace body, the upper frame of the furnace body and the furnace top frame. This frame structure has clear force transmission, wide platforms on each floor, and is convenient for equipment operation and maintenance. It is suitable for modern blast furnaces.
[0003] At present, the installation method of the blast furnace frame is to hoist and install the frame one by one, which has many hoisting times, low operation efficiency, many high-altitude operations, large waste of large machinery, labor-consuming and time-consuming, and is extremely uneconomical and unreasonable. Summary of the invention
[0004] In order to overcome the deficiencies of the prior art, the technical problem to be solved by the present invention is: how to improve the efficiency of hoisting the blast furnace frame.
[0005] The technical solution adopted by the present invention to solve its technical problem is:
[0006] The modular installation construction method of the blast furnace frame is characterized by comprising the following steps:
[0007] S1: After the installation of the lower frame is completed on the ground, the lower frame is hoisted into place as a whole;
[0008] S2: After the upper frame is installed on the ground, the upper frame is hoisted into place as a whole;
[0009] S3: After the furnace top frame is installed on the ground, the furnace top frame is hoisted into place as a whole;
[0010] S4: After completing the installation of the furnace top pressure equalizing platform on the ground, hoist the furnace top pressure equalizing platform into place as a whole.
[0011] Furthermore, the specific installation process in step S1 is to assemble two frame columns and a crossbeam on one side of the lower frame into a portal frame, hoist the two independent portal frames into place, temporarily fix them, hoist the connecting crossbeam into place, and then fix the two portal frames together through the connecting crossbeam.
[0012] Furthermore, the specific installation process in step S2 is to assemble two frame columns and three cross beams of the upper frame into a portal frame, hoist two independent portal frames into place, and fix the two portal frames to be connected.
[0013] Furthermore, the specific installation process in step S3 is to first complete the assembly of the lower frame of the furnace roof frame on the ground, and after hoisting it into place, complete the assembly of the upper frame of the furnace roof frame on the ground, and then hoist the upper frame of the furnace roof frame to the upper end of the lower frame of the furnace roof frame.
[0014] Furthermore, step S4 specifically includes: first assembling the platform columns and the supports between the columns, and then assembling the cantilevered corbels; then laying the platforms and platform railings on each floor in turn, and splicing the frame columns; finally erecting the building and stair railings between each floor; after the entire furnace top pressure equalizing platform is assembled, it is hoisted as a whole into place at the furnace top frame position.
[0015] Furthermore, it also includes the use of SOLIDWORKS 3D modeling software to accurately calculate the overall weight of each section of the lifting module frame after assembly. At the same time, it can accurately calculate the position of the center of gravity of each section of the blast furnace frame, which is convenient for the subsequent determination of the lifting eye position and wire rope length.
[0016] The beneficial effects of the present invention are:
[0017] The modular assembly of the blast furnace frame is all carried out on the ground, which reduces the risk of high-altitude operations. Ground assembly does not require the use of large machinery, reducing the use of large machinery shifts. After modular assembly, it is hoisted into place at one time, which greatly reduces the number of single-hook hoisting operations of large cranes, greatly improves construction efficiency, saves installation time, and can achieve the purpose of reducing the risk of high-altitude operations, saving construction time and costs. BRIEF DESCRIPTION OF THE DRAWINGS
[0018] Figure 1 It is a schematic diagram of the lower frame of the present invention;
[0019] Figure 2 It is a schematic diagram of the upper frame of the present invention;
[0020] Figure 3 It is a schematic diagram of the furnace top frame of the present invention;
[0021] Figure 4 This is a schematic diagram of the furnace top pressure equalization platform of the present invention. Figure 1 ;
[0022] Figure 5 This is a schematic diagram of the furnace top pressure equalization platform of the present invention. Figure 2 ;
[0023] Marked in the figure, 1-frame column, 2-crossbeam, 3-diagonal brace, 4-platform, 5-rail, 6-stairs, 7-support between columns, 100-lower frame of furnace roof, 200-upper frame of furnace roof. DETAILED DESCRIPTION
[0024] The present invention is further described below in conjunction with the accompanying drawings.
[0025] The embodiment of the present application proposes a modular installation construction method for a blast furnace frame, comprising the following steps:
[0026] S1: After completing the installation of the lower frame on the ground, hoist the lower frame as a whole into place; the specific installation process is to assemble the two frame columns 1 and a beam 2 on one side of the lower frame into a portal frame, hoist the two independent portal frames into place, and then temporarily fix them. After hoisting the connecting beam 2 into place, the two portal frames are fixedly connected by the connecting beam 2.
[0027] In this embodiment, the weight of the lower frame is 266.7t, which is relatively heavy. The frame column 1 and the crossbeam 2 on one side are assembled and welded on the ground to form a portal frame, and the whole is modularly hoisted. Specifically, Figure 1 As shown, firstly hoist the portal frame. There are two portal frames in total, which are hoisted into place with two hooks. After the portal frame is installed, hoist the two cross beams 2 with two hooks to the designated position, and then install the two cross beams 2 in sequence to assemble the lower frame into a whole.
[0028] S2: After completing the installation of the upper frame on the ground, hoist the upper frame as a whole into place; in this embodiment, the upper frame weighs 287.3t, which is heavy. It is necessary to assemble the two frame columns 1 and three beams 2 of the upper frame into a portal frame, hoist the two independent portal frames into place, and fix the two portal frames to be connected.
[0029] Specifically, Figure 2 As shown, two frame columns 1 are assembled into a portal frame using three cross beams 2, and the three cross beams 2 are assembled in sequence from bottom to top. During the layer-by-layer assembly process, the diagonal braces 3 between the frame columns 1 and the cross beams 2 are synchronously installed layer by layer. Finally, the corbels are installed on the cross beams 2 of the highest layer and the corresponding frame columns 1. The installed portal-type single-sided frame is first hoisted into place to the upper end of the lower frame, and the portal-type single-sided frame on the other side of the upper frame is synchronously completed on the ground and hoisted to the upper end of the lower frame at the same time. The two above-mentioned portal-type single-sided frames are temporarily fixed, and then the two portal-type single-sided frames are fixed by the corresponding installation beams and diagonal braces 3, and installed to form an overall upper frame.
[0030] S3: After the furnace top frame is installed on the ground, the furnace top frame is hoisted in place as a whole; in this embodiment, the furnace top frame weighs 335.6t, and the furnace top frame includes a furnace top lower frame 100 and a furnace top upper frame 200. Specifically, Figure 3As shown, the two frame columns 1 and a cross beam 2 of the furnace roof lower frame 100 are first assembled into a door-shaped frame, and the two door-shaped frames assembled on the ground are successively hoisted to the upper end of the upper frame for fixed assembly; after the hoisting and fixation of the furnace roof lower frame 100 are completed, the two frame columns 1 and a cross beam 2 of the furnace roof upper frame 200 are first assembled into a door-shaped frame, and the two door-shaped frames assembled on the ground are successively hoisted to the upper end of the furnace roof lower frame 100 for fixed splicing and installation, and the hoisting of the entire furnace roof frame is completed by four-hook hoisting.
[0031] S4: After completing the installation of the furnace top pressure equalizing platform on the ground, hoist the furnace top pressure equalizing platform into place as a whole; in this embodiment, the furnace top pressure equalizing platform weighs 40t, which is relatively light. The overall furnace top pressure equalizing platform can be assembled directly on the ground and then hoisted to the designated position.
[0032] Specifically, Figure 4 , Figure 5 As shown, the frame column 1 and the inter-column support 7 are first installed and fixed, and the cantilevered corbel is installed at the specified position of the frame column 1. After the overall positioning and assembly of the frame column 1 are completed, the platform 4, the railing 5 and the frame column 1 are assembled layer by layer from bottom to top. Simultaneously, the staircase 6 between the two adjacent platforms 4 and the railing 5 of the staircase 6 and the frame column 1 are fixedly installed and fixed. In this embodiment, the furnace top pressure equalizing platform is 4 layers. After the positioning and assembly of the frame column 1 are completed first, a large frame is formed. Three groups of stairs 6 are installed between each platform 4 to ensure the interconnection between each layer. After the assembly and fixation of the overall top pressure equalizing platform are completed, the furnace top pressure equalizing platform is hoisted as a whole to the furnace top frame position.
[0033] Moreover, the entire process is assisted by SOLIDWORKS 3D modeling software, which can accurately calculate the overall weight of each section of the lifting module frame after assembly. At the same time, it can accurately calculate the position of the center of gravity of each section of the blast furnace frame, which is convenient for the subsequent determination of the lifting eye position and wire rope length.
[0034] In summary, the present invention proposes a modular installation construction method for a blast furnace frame, which solves the problems of many single-piece hoisting times of the blast furnace frame, low construction efficiency, many high-altitude operations, and large waste of large-scale machinery shifts; through the optimization of the construction process, each component is assembled and welded on the ground, assembled as a whole, and one hook completes the hoisting of a section, greatly reducing the high-altitude operation construction process, reducing the number of hoisting times, improving installation efficiency, and saving installation period. By using SOLIDWORKS three-dimensional modeling software to assist, the weight of the whole after each section of the management framework is accurately calculated, and the position of the center of gravity of each section of the blast furnace frame can be accurately calculated at the same time, which is convenient for the determination of the subsequent lifting lug position, the length of the wire rope is determined, and accurate data support is provided, and the hoisting level of the blast furnace frame can be accurately controlled. By using the modular installation construction method for the blast furnace frame, the construction efficiency can be greatly improved, the time of workers working at high altitudes is greatly reduced, and the construction is safer, more reliable and faster.
Claims
1. A modular installation construction method for a blast furnace frame, characterized in that: The following steps are included: S1: After the installation of the lower frame is completed on the ground, the lower frame is hoisted into place as a whole; S2: After the upper frame is installed on the ground, the upper frame is hoisted into place as a whole; S3: After the furnace top frame is installed on the ground, the furnace top frame is hoisted into place as a whole; S4: After completing the installation of the furnace top pressure equalizing platform on the ground, hoist the furnace top pressure equalizing platform into place as a whole.
2. The modular installation construction method of blast furnace frame according to claim 1, characterized in that: The specific installation process in step S1 is to assemble two frame columns (1) and a crossbeam (2) on one side of the lower frame into a portal frame, hoist the two independent portal frames into place, temporarily fix them, hoist the connecting crossbeam (2) into place, and then fix the two portal frames together by connecting the crossbeam (2).
3. The modular installation construction method of blast furnace frame according to claim 1, characterized in that: The specific installation process in step S2 is to assemble the two frame columns (1) and three cross beams (2) of the upper frame into a portal frame, hoist the two independent portal frames into place, and fix the two portal frames together.
4. The modular installation construction method of a blast furnace frame according to claim 1, characterized in that: The specific installation process in step S3 is to first complete the assembly of the lower frame (100) of the furnace roof frame on the ground, and after hoisting it into place, complete the assembly of the upper frame (200) of the furnace roof frame on the ground, and then hoist the upper frame (200) of the furnace roof frame to the upper end of the lower frame (100) of the furnace roof frame.
5. The modular installation construction method of blast furnace frame according to claim 1, characterized in that: Step S4 specifically includes: first assembling the frame columns (1) and the inter-column supports (7), and then assembling the cantilevered corbels; then laying the platforms (4) on each floor, the railings (5) of the platforms (4) in sequence, and splicing the frame columns (1); finally, erecting the railings (5) of the inter-floor buildings and stairs (6); after the entire furnace top pressure equalizing platform is assembled, it is hoisted as a whole into position on the furnace top frame.
6. The modular installation construction method of blast furnace frame according to claim 1, characterized in that: It also includes the use of SOLIDWORKS 3D modeling software to accurately calculate the overall weight of each section of the lifting module frame after assembly. At the same time, it can accurately calculate the position of the center of gravity of each section of the blast furnace frame, which facilitates the subsequent determination of the lifting eye position and wire rope length.