Large-scale vertical single-suction three-stage pump set starting pilot run debugging method
Through the systematic start-up and trial operation debugging method, the problem of difficulty in debugging the vertical single-suction three-stage pump unit has been solved, the operational safety and equipment reliability have been improved, and the goal of few people on duty and no one on duty has been achieved.
Patent Information
- Application Number
- CN202411032921.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-30
- Publication Date
- 2024-10-08
AI Technical Summary
There is a lack of debugging technology research and national standards for vertical single-suction three-stage pump units in China, which makes dual-axis installation more difficult to debug and affects the development and promotion of equipment.
A start-up trial operation and debugging method for a large vertical single-suction three-stage pump unit is proposed, including pre-start inspection of the unit, static debugging of the pump unit, no-load debugging and on-load debugging. The specific steps include inspection before the pump unit is started and tested for water discharge. Technical water supply system water filling and guide bearing cooling water flow adjustment, Pump set water inlet and outlet maintenance ball valve hydrostatic test, monitoring system process simulation debugging, pump set motor first manual start-up test, no-load bearing thermal stability test, speed-up test, first pumping test, mechanical accident protection shutdown test, dynamic balance test and 24-hour continuous trial operation.
It improves the accuracy of operation, reduces the risk of ball valve pressure increase, ensures the safety of equipment and pipelines, reduces labor intensity, reduces the impact of human factors, avoids casualties during operation, and achieves fewer personnel Basics of attended and unattended operations.
Smart Images

Figure CN118746008A_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of water conservancy projects, and in particular relates to a method for starting, testing and debugging a large-scale vertical single-suction three-stage pump group. Background Art
[0002] At present, vertical single-suction three-stage pump sets are beginning to be used in water conservancy projects in China, and other water intake hubs in China that use the same level of water pump equipment are in the early stages of construction. There is a lack of relevant debugging technology research literature and no corresponding national standards and specifications; the vertical single-suction three-stage pump set is installed with a double axis line, and the double axis line installation can achieve a relatively independent operation of the motor shaft and the water pump shaft with an offset of 0.1°, and the radial compensation value reaches 7mm, which can effectively eliminate the error in the axis adjustment and improve the installation fault tolerance rate. However, the use of double axis line installation makes the debugging of the pump set difficult, and there is no relevant debugging technology research literature and national standards and specifications, which is not conducive to the development and promotion of vertical single-suction three-stage pump sets. Summary of the invention
[0003] The technical problem to be solved by the present invention is to provide a method for starting, testing and debugging a large-scale vertical single-suction three-stage pump group with high efficiency, safety and low labor cost.
[0004] The technical solution of the present invention is: a method for starting and commissioning a large-scale vertical single-suction three-stage pump group, including the following steps: pre-startup inspection of the unit, static commissioning of the pump group, no-load commissioning of the pump group and on-load commissioning of the pump group. The pre-startup inspection of the unit includes the following steps: pre-startup inspection of the pump group and water filling and drainage test of the water delivery system. The water filling and drainage test of the water delivery system includes the following steps: determining the requirements of the water filling and drainage procedures, the first stage of water filling and drainage, the second stage of water filling and drainage and safety monitoring; the static commissioning of the pump group includes the following steps: technical The technical water supply system is filled with water and the cooling water flow of each guide bearing is adjusted, the pump group water inlet maintenance ball valve static water test, the pump group water outlet maintenance ball valve static water test and the monitoring system process simulation debugging; the pump group no-load debugging includes the following steps: the first manual start-up test of the pump group motor, the pump group no-load grid connection test and the no-load bearing thermal stability test; the pump group load debugging includes the following steps: speed increase test, the first water pumping test, the pump group mechanical accident protection shutdown test, the bearing thermal stability test, the dynamic balance test, the pump group automatic start and stop debugging and the pump group 24 hours continuous trial operation.
[0005] Furthermore, the requirements for determining the filling and drainage procedures are specifically as follows: when the water intake level is between 830m and 834m, the working gate is lowered to adjust the opening to control the water diversion flow; when the reservoir water level is lower than 830.0m or higher than 834m during the filling and drainage tests, no water is taken.
[0006] Furthermore, the first stage of water filling and drainage includes the following steps: water filling preparation, water filling procedure, calculation of water intake gate opening curve, and drainage procedure. The water filling procedure is specifically as follows: first, open the water intake working gate to the specified opening, and observe whether the working gate has any resonance phenomenon. If there is any resonance phenomenon, the working gate opening should be staggered until the resonance phenomenon disappears; then, after the first stage of water filling is completed and the pressure is stabilized for 1 hour, observe whether any abnormality occurs, and start the second stage of water filling after no abnormality is found; then, after the second stage of water filling is completed and the pressure is stabilized for 6 hours, check the blocking conditions of each water inlet valve and water delivery system, and start the third stage after no abnormality is found. Then, after the third section is filled with water and the pressure is stabilized for 2 hours, observe whether there is any abnormality. If no abnormality is found, start the fourth section filling with water; Then, after the third section is filled with water and the pressure is stabilized for 12 hours, observe whether there is any abnormality. If no abnormality is found, start the fifth section filling with water; Then, carry out the fifth section filling with water: close the outlet working ball valve of Unit 1, open the water intake pipe valve and the outlet pipe valve of the water channel filling pump of Unit 1 water inlet pipe, and monitor the running status of the water pump, fill water until the water level of the outlet pipe shaft section reaches 920m, and when the water level of the outlet shaft reaches 920m, close the water intake pipe valve and the outlet pipe valve of the filling pump, stabilize the pressure 12 hours, observe whether there is any abnormality, and start the sixth stage of water filling after no abnormality is found; then, carry out the sixth stage of water filling: open the water intake pipe valve and the outlet pipe valve of the water filling pump of the water inlet pipe of the No. 1 unit, fill water to the vertical shaft section of the outlet pipe, and when the water level of the outlet shaft reaches 1013m, close the water intake pipe valve and the outlet pipe valve of the water filling pump to stabilize the pressure; finally, after the water filling pump has stabilized the pressure for 24 hours, end the water filling procedure; the drainage procedure includes the following steps: first, open the No. 1 outlet pressure steel pipe maintenance drainage valve to return the pressure of the pressure pipe system to the horizontal pressure, and discharge the water above the outlet shaft 828.32m, and the pressure The drainage rate of the pipeline shaft is controlled within 5m / h, and the No. 1 sand clearing gate of the sedimentation tank, the sedimentation tank, the No. 2 sand clearing gate, the sedimentation tank, the No. 1 and No. 2 venting gates, the No. 1 water diversion gate of the sedimentation tank and the two drain valves on the overflow weir of the water inlet tank are opened in sequence to drain the water; then, after there is no water flowing at the outlet of the venting hole, open the drain valves of the water inlet pipes of the seven water pumps to discharge the bypass tunnel, the No. 2 water diversion tunnel and the water above the elevation of 824.28m in the water inlet tank, as well as the water diversion pressure pipeline, the water outlet pressure pipeline and the seven units below the elevation of 825.9m; finally, use a temporary drainage pump to discharge the water below the elevation of 824.28m in the water inlet tank.
[0007] Furthermore, the second stage of water filling and drainage includes the following steps: water filling preparation, water filling procedure, drainage procedure and safety monitoring. The water filling procedure includes the following steps: first, open the working gate of the water intake to the specified opening, observe whether the working gate has resonance phenomenon, if there is resonance phenomenon, stagger the opening of the working gate until the resonance phenomenon disappears; then, let the water flow through the No. 1 water diversion tunnel, the No. 1 water diversion gate of the sedimentation tank, the No. 1-2 sand clearing gate, the sedimentation tank horizontal flow section, the sedimentation tank inclined plate section, the total The water collection trough, No. 2 water diversion tunnel, water intake pool, water diversion pressure pipe, water intake pool spillway, sedimentation tank drain hole and flood control gate; then, after the sedimentation tank No. 1 diversion gate has passed water for about 80 minutes, open the drain gate No. 1 and the drain gate No. 2 at the same time, continue to pass water for 30 minutes, open the diversion gate No. 1, and close the diversion gate No. 1; then, after the sedimentation tank No. 2 diversion gate has passed water for 30 minutes, open the drain gate No. 3 and the drain gate No. 4 at the same time, continue to pass water for 30 minutes, open the diversion gate No. 3, and close the diversion gate No. 2; then Then, 30 minutes after the No. 3 diversion gate of the sedimentation tank flows through, the No. 5 drain gate and the No. 6 drain gate are opened at the same time, and the water continues to flow for 30 minutes. At the same time, the working gate of the water intake and the No. 3 diversion gate are closed, and the bypass tunnel control gate is opened; finally, the working gate of the water intake is closed, and the water filling procedure is terminated after stabilizing the pressure for 12 hours; the drainage procedure includes the following steps: first, open the No. 3 diversion gate and the two drainage valves on the overflow weir of the water inlet tank to drain water at the same time, and discharge the No. 1 water diversion tunnel and the sedimentation tank with an elevation of 825.9m. then, when there is no water flowing at the outlet of the drain hole, with the outlet working valve of the No. 1-7 water pump closed, open the bypass pipe of the No. 1-7 water inlet inspection valve to equalize the pressure, open the No. 1-7 water inlet inspection valve, and then open the drain valve of the No. 1-7 water pump inlet pipe to discharge the water above the No. 2 water diversion tunnel and the water inlet pool at an elevation of 824.280m; finally, use a temporary drainage pump to discharge the water below the elevation of 824.28m in the water inlet pool through the water inlet pool, the drain hole and the drain hole.
[0008] Furthermore, the static water test of the ball valve for water inlet maintenance of the pump group includes: verifying the on-site single-step opening and closing of the ball valve, and checking whether the feedback of the ball valve opening indication is correct; verifying the on-site switch automatic control process, and checking whether the opening and closing time meets the requirements; verifying whether the function of the remote monitoring switch ball valve is normal; the static water test of the ball valve for water outlet maintenance of the pump group includes: exiting the manual locking of the water outlet maintenance ball valve maintenance seal, exiting the ball valve maintenance seal, and checking whether the feedback signal is correct; verifying the on-site investment and withdrawal working seal, and checking whether the feedback signal is correct; verifying the on-site single-step opening and closing of the ball valve, and checking whether the ball valve opening indication is correct; verifying whether the remote monitoring switch ball valve function is normal; checking whether the emergency closing ball valve function is normal; the monitoring system process simulation debugging includes: monitoring system single-step operation control debugging, monitoring system startup and shutdown sequential control process simulation debugging, monitoring system master-slave switching debugging, monitoring system main PLC mechanical and electrical accident shutdown debugging, monitoring system backup PLC mechanical and electrical accident shutdown debugging.
[0009] Furthermore, the first manual start-up test of the pump group motor includes: a jog test, an emergency stop test, a manual speed increase test and a protective stop test. The manual speed increase test includes: (1) after the first start-up and shutdown inspection, restart the motor, adjust the pump group speed between 10%, increase the speed step by step, check the dynamic balance of the pump group, check the inverter pulse operation function, correct the initial excitation current setting value, and check the working condition of the inverter power device; (2) increase the speed and stabilize it at 20% of the rated speed for 3 minutes, check and record the bearing temperature of each guide bearing, the swing of each guide bearing and the vibration of each part, as well as the working condition of the electrical measurement system and the protective device; (3) increase the speed and stabilize it at 50% of the rated speed for 3 minutes, check and record the bearing temperature of each guide bearing, the swing of each guide bearing and the vibration of each part, as well as the working condition of the electrical measurement system and the protective device; (4) increase the speed and stabilize it at 75 % rated speed for 3 minutes, check and record the bearing temperature of each guide bearing, the swing of each guide bearing and the vibration of each part, as well as the working conditions of the electrical measurement system and protection device; (5) increase the speed and stabilize it at 100% rated speed for 5 minutes, check and record the bearing temperature of each guide bearing, the swing of each guide bearing and the vibration of each part, as well as the working conditions of the electrical measurement system and protection device; the no-load bearing thermal stability test includes: (1) pump group temperature curve measurement; (2) record the vibration and swing of each part of the motor under no-load state, record the thrust, upper guide and lower guide bearing swing of the pump group motor, and record the vibration of the upper and lower frames; (3) motor cooling water adjustment test; (4) when there is no obvious sudden change in the temperature, oil temperature, water temperature of the thrust bearing, upper guide bearing, lower guide bearing and stator of the pump group motor and the vibration and swing of the pump group, the coupling operation can be started to prepare for the pump group load commissioning.
[0010] Furthermore, the speed increase test includes: (1) starting the machine in a single step until all auxiliary systems are put into normal operation, the inverter is set to increase the speed to 1%ne, where ne is the rated speed, and check whether there is any friction between the fixed parts and the rotating parts of the pump group. If there is no abnormality, continue to increase the speed to 5%ne, and confirm again whether there is any friction between the fixed parts and the rotating parts of the pump group. Continue to increase the speed to 10%ne, and continue to confirm whether there is any friction between the fixed parts and the rotating parts of the pump group; (2) Confirm that all auxiliary systems of the pump group are working normally, send the inverter start command, monitor the water pressure, temperature and vibration swing of various parts of the pump group during the speed increase process, check whether the bypass valve of the water outlet working ball valve is normally opened when the speed is greater than 70%ne, and record the pressure curve during the speed increase process; the first water pumping test includes: checking whether the inverter up-cut is normal, checking whether the sampling of each measuring meter and protection device for the first water pumping is correct, and after the first water pumping, continuous operation The pump group is run for 30 minutes, and the vibration swing of each part of the pump group, the temperature of each guide bearing and the oil temperature of the oil tank and the main shaft seal temperature are monitored; the pump group mechanical accident protection shutdown test is specifically: simulating the water pump mechanical accident shutdown, checking whether the action logic and timing of the relevant equipment during the shutdown process are correct, and recording the speed drop curve; the bearing thermal stability test includes: pump group temperature curve measurement and recording, recording the vibration and swing of the pump group under steady state, pump group cooling water adjustment test, and the dynamic balancing test can be started after the temperature, oil temperature, water temperature of the thrust bearing, upper guide bearing, lower guide bearing, stator of the pump group motor and water pump, as well as the vibration and swing of the pump group have no obvious sudden changes; the dynamic balancing test includes: (1) recording the swing of the upper guide and lower guide of the pump group motor and water pump and the vibration of each part; (2) analyzing the vibration and swing of each part to determine whether there is mass imbalance of the rotating parts. If so, weight is added and the position and weight of the weight is recorded at the same time.
[0011] Beneficial effects of the invention: The startup, trial operation and debugging method of a large-scale vertical single-suction three-stage pump group of the invention ensures the accuracy of each operation, effectively eliminates or reduces the danger caused by the pressure increase of the ball valve, ensures the safety of equipment and pipelines, reduces labor intensity, eliminates the influence of human factors in operation, and avoids the occurrence of casualties in operation. The control execution process is reliable, the command is issued quickly, and the number of operators is reduced, laying a solid foundation for realizing less-manned and unmanned duty. BRIEF DESCRIPTION OF THE DRAWINGS
[0012] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, for ordinary technicians in this field, other drawings can be obtained based on these drawings without paying any creative work.
[0013] Figure 1The present invention is a flowchart of a method for starting, testing and debugging a large-scale vertical single-suction three-stage pump set. DETAILED DESCRIPTION
[0014] like Figure 1 As shown, a method for starting and commissioning a large vertical single-suction three-stage pump set includes the following steps: 1. Inspection before starting the pump unit to test water The owner is responsible for establishing a leadership group for the filling and drainage tests, which will be attended by relevant technical leaders from the owner, design, supervision, construction and installation units.
[0015] Before the formal water filling, the test team should organize relevant personnel to conduct another systematic inspection. The inspection items include: (1) The construction waste (including stones, steel bar heads, silt, various packaging bags, sundries, etc.) in the water supply system should be thoroughly cleaned up, and the cave walls and floor should be flushed with pressurized water.
[0016] (2) Construction waste (including stones, steel bar heads, silt, various packaging bags, sundries, etc.) between the working gate of the water intake and the trash rack should be thoroughly cleaned up.
[0017] (3) The gate slots of all gates except the working gates and trash racks at the water intake should be systematically inspected and all debris in the gate slots should be thoroughly cleaned. The water stop surface of the gate slot should be cleaned.
[0018] (4) Clean out the construction waste (including stones, steel bar heads, silt, various packaging bags, sundries, etc.) in the inspection and leakage collection wells thoroughly, and rinse them with pressurized water.
[0019] (5) All work related to the water supply system, including concrete pouring, backfill grouting, consolidation grouting, curtain grouting, grouting hole sealing, construction branch hole sealing and defect treatment, has been completed and passed the acceptance inspection, and is ready for water flow.
[0020] (6) Inspection of the appearance and smoothness of the junction between the steel lining and the reinforced concrete lining of the water diversion tunnel.
[0021] (7) Inspection of welding quality of steel pipes and steel linings of each section of pressure pipeline, appearance of parent materials, and quality of anti-corrosion paint spraying.
[0022] (8) Check the water outlet of the drainage pipe at the bottom of the pressure pipe.
[0023] (9) The observation equipment for the relevant parts of the water supply system and underground powerhouse system has been installed, and the corresponding cables, pipelines, and measuring meters have been installed and can operate normally. The initial readings of the prototype observation instruments should be recorded.
[0024] (10) All metal structures of the water delivery system (including trash racks at water intakes, working gates at water intakes, ice melting devices at water intakes, bypass tunnel control gates, gates of sedimentation basins, flood control gates at outlets of drain tunnels, gates of construction branch tunnels, etc.) have been installed, cleaned, inspected and passed the unit project acceptance, and the operation and commissioning of the opening and closing equipment have passed.
[0025] (11) Check the sealing condition of the manhole cover of the unit maintenance water collection well.
[0026] (12) Check the working status of the deep well pump in the factory leakage collection well.
[0027] (13) The installation and commissioning of the No. 1-7 water pump units and their ancillary equipment have been completed, and the water outlet working valve is in the open state.
[0028] (14) The water flow system including the volutes 1-7 and water inlet pipes has been cleaned and inspected and passed.
[0029] (15) The drain valves of the water pump inlet pipes of units 1-7, the drain valves of the volute outlet pipes, the drain valves of the water inlet inspection valves, the drain valves of the water outlet working valves, and the drain valves of the water outlet inspection valves are in good condition and are in the closed position.
[0030] (16) The water inlet inspection valve and water outlet inspection valve of units 1-7 are in good condition and in the closed position.
[0031] (17) The isolating valves of the connecting pipes between the technical water supply main inlet pipe and the discharge pipe of units 1-7 are in the closed state.
[0032] (18) The first valves of all pipelines connected to the water supply system such as the outlet water pressure steel pipe, volute, inlet pipe, etc. are in the closed state, such as the inlet pipe drain valve; the pressure steel pipe, volute, outlet water pressure steel pipe, top cover measuring pipeline valve; technical water supply intake valve, technical water supply drain main valve, etc.
[0033] (19) The common pipeline connecting valves of Units 1-7 or the first valves of the branch pipes leading from the main pipe of Units 1-7 are in the closed state, such as the connecting valve of the technical water supply and intake pipes of Units 1 and 2, the connecting valve of the technical water supply and intake pipes of Units 3, 4 and 5, the connecting valve of the technical water supply and intake pipes of Units 6 and 7, and the valves from the main pipe of the low-pressure gas and oil system to Units 1-7.
[0034] (20) Prepare emergency plans during filling and drainage tests.
[0035] The above work should be completed 3 days before the start of water filling. After inspection, the above items meet the relevant regulations and design requirements, and the water delivery system can be filled with water after confirmation by the command organization. Non-conforming items should be dealt with in a timely manner; After the inspection is completed, no personnel, equipment or materials are allowed to enter any area involved in the water filling system, otherwise the water filling inspection will be carried out again.
[0036] 2. Water delivery system filling and drainage test 2.1 Filling and draining procedures and requirements After confirming that all possible remaining problems have been properly handled and signed and approved by all parties of the test leadership group, the water source project water delivery system can be filled with water. Before the water filling begins, the observers and observation instrument readers at key locations (water intake working gate, bypass tunnel control gate, sedimentation tank water diversion gate, sedimentation tank sand clearing gate, sedimentation tank emptying gate, emptying tunnel flood control gate, water pump water inlet inspection valve, water pump water outlet working valve and inspection valve, underground plant, water delivery system and pressure pipeline monitoring data reading point, etc.) must be in place. After the test begins, each observer must promptly observe and record in detail the stability, leakage, deformation, cracks and other conditions and values of the building; the observation instrument reader must carefully observe and record the readings of all observation instruments in the water delivery system. When the observers and observation instrument readers find abnormal conditions or reach the stage goals, they must immediately report to the person in charge of water filling and the test leadership group. All test instructions should be issued by the test commander.
[0037] The filling and drainage test of the water delivery system shall be carried out on all permanent water-passing structures of the project. The water intake, No. 1 non-pressure water diversion tunnel, sedimentation tank, sedimentation tank drain hole, sedimentation tank spillway, bypass hole, No. 2 non-pressure water diversion tunnel, water inlet pool and spillway, water diversion pressure pipeline, underground pump station and water-passing equipment in the water outlet valve room, water outlet pressure pipeline, water outlet pool, etc. of this project shall be subjected to filling and drainage test. According to the layout characteristics of the water source project and the water delivery project, the filling and drainage test of the water outlet pool will be carried out together with the filling and drainage of the water delivery project. Since the water source project has a long water delivery system, many buildings, and the working conditions of the non-pressure and pressure systems are quite different, the filling and drainage are carried out according to different parts and stages.
[0038] The designed water intake during the operation period of this project is: when the water intake level is between 830m and 834m, the working gate is lowered to adjust the opening to control the water diversion flow. In this filling and drainage test, when the reservoir water level is lower than 830.0m or higher than 834m, the design requires no water intake.
[0039] 2.2 The first stage of water filling and drainage The water filling in this stage is designed based on the conditions that the sedimentation tank does not flow through, the bypass tunnel flows through, and the water inlet pool does not flow through the water discharge tunnel. The water filling test is mainly carried out on the No. 1 water diversion tunnel, bypass tunnel, No. 2 water diversion tunnel, water inlet pool, water diversion pressure pipeline, underground pump station and water outlet valve room water flow equipment, water outlet pressure pipeline, etc.
[0040] 2.2.1 Water filling preparation (1) Confirm that the observation equipment has been installed, and the corresponding cables, pipes, and measuring meters have been installed and can operate normally; the initial readings of the prototype observation instruments should be recorded.
[0041] (2) The bubble blowing ice melting device and the electric heating ice melting device at the water inlet are both in the open state.
[0042] (3) The trash rack at the water intake is in the trash-blocking state, the downstream working gate is blocking water, and the upstream working gate is suspended above the orifice or locked above the orifice.
[0043] (4) The three diversion gates and six sand removal gates of the sedimentation tank are closed.
[0044] (4) The six drain gates of the sedimentation tank are in closed state.
[0045] (5) The bypass tunnel control gate is in the fully open state.
[0046] (6) The drain valve behind the overflow weir of the inlet tank is in the closed state.
[0047] (7) The outlet working ball valves of units 1-7 of the underground pump station are in the open state. The first valves of all pipelines connected to the water supply system such as the penstock, volute, and water inlet pipe are in the closed state, such as the water inlet pipe drainage valve; penstock, volute, water inlet pipe, and top cover measuring pipeline valves; technical water supply intake valve, technical water supply drainage main valve, etc.
[0048] (8) The water inlet inspection ball valve and water outlet inspection valve of units 1-7 of the underground pump station are in the closed state, well sealed, and have passed the acceptance inspection.
[0049] (9) Surveillance and monitoring personnel are in place at each location.
[0050] (10) Issue a water filling order.
[0051] 2.2.2 Water filling procedure The first stage is water filling, and the water filling flow rate is 6.6m³ / s according to the reference flow rate.
[0052] Since the water diversion pressure pipeline and the water outlet pressure pipeline have undergone the first unit filling and drainage test, the filling and drainage test procedures have been appropriately simplified. The unit sections are filled with water in turn according to each unit 1-7. The following takes the filling of the unit section 1 as an example, and the other unit sections are implemented accordingly. The water filling in this stage is carried out in 6 sections: the first section is to fill the water level of the water diversion pressure pipeline to 824.28m; the second section is to fill the water level in the water inlet pool and before the unit water inlet valve to 828.50m; the third section is to fill the water after the unit water inlet valve and before the water outlet inspection valve; the fourth section is to fill the water level after the water outlet inspection valve and the water outlet shaft to the same level as the water inlet pool, that is, the water delivery system is in a flat pressure state; the fifth section is to fill the water level of the water outlet shaft to 920m; the sixth section is to fill the water level of the water outlet shaft to 1013m.
[0053] (1) First, open the working gate of the water intake to the specified opening. Observe whether there is resonance in the working gate. If there is resonance, the working gate opening should be staggered until the resonance disappears. During the filling process, closely observe and record the water level of the water intake, the water level at the bypass tunnel control gate slot, the water level at the total water collection tank of the sedimentation tank, the water level data of the water inlet tank, and other water level data that can be observed or monitored in the water delivery system, and record the time and the water level at the corresponding time. The process of adjusting the working gate opening should also be recorded.
[0054] The working gate is kept open for about 4 minutes and then closed. When the water level in the water diversion pressure pipe reaches 824.28m, the pressure is stabilized. During this water filling period, close attention should be paid to whether the leakage of the No. 1-7 water inlet valves meets the valve design requirements. If there is leakage, the water filling should be stopped immediately, and the water inlet pressure steel pipe should be emptied. After the hidden dangers are eliminated and the acceptance is qualified, the first stage of water filling procedure can be restarted.
[0055] (2) After the first section is filled with water and the pressure is stabilized for 1 hour, the second section can be filled with water only after no abnormal conditions are observed. Open the working gate of the water intake to the specified opening and perform vibration pressure stabilization. Record relevant data at the same time.
[0056] The working gate was opened for about 114 minutes and then closed. When the water level in the inlet pool reached 828.50m, the pressure was stabilized.
[0057] (3) After the second stage of water filling is completed and the pressure is stabilized for 6 hours, check the sealing of each water inlet valve and water delivery system, confirm that there is no water leakage, and observe and inspect that no abnormal situation occurs before the third stage of water filling can be started. Open the bypass pipe of the water inlet valve of unit 1, and fill the water behind the water inlet valve of unit 1 and the front section of the water outlet inspection valve of unit 1. When the water level of the water inlet pool stops dropping, the water filling is completed. After stabilizing the pressure for 2 hours, observe and inspect that no abnormal situation occurs before the next water filling can be started. Then, open the bypass pipe of the water inlet valve of unit 2, and fill the water behind the water inlet valve of unit 2 and the front section of the water outlet inspection valve of unit 2. When the water level of the water inlet pool stops dropping, the water filling is completed. After stabilizing the pressure for 2 hours, observe and inspect that no abnormal situation occurs before the next water filling can be started. After that, open the bypass pipes of the water inlet valves of units 3-7 in turn, fill the water in front section of the water outlet inspection valve of the corresponding units, and stabilize the pressure. Observe the water leakage and record the relevant data of each unit.
[0058] (4) After the third section is filled with water and the pressure is stabilized for 2 hours, the fourth section can be filled with water only after no abnormal conditions are observed. Open the bypass pipe of the outlet inspection valve of unit 1#, and fill the outlet branches, outlet bifurcated pipe sections, outlet main lower horizontal section, and shaft section of 1~7# with water. When the water level of the water inlet pool stops dropping and the water level of the outlet shaft stops rising, the water level upstream and downstream of the pump unit reaches a flat pressure state. At this time, the water level is about 828.32m, and the pressure is stabilized.
[0059] After the 4th section is filled with water and the pressure is stabilized for 12 hours, all parts of the water supply system and water-passing equipment are fully inspected for abnormal conditions. Only if there are no abnormalities can the 5th section be filled with water.
[0060] (5) For the filling of the 5th section, close the outlet working ball valve of Unit 1 and open the water intake pipe valve and outlet pipe valve of the water filling pump of the water inlet pipe of Unit 1. After the water pump is started, the needle valve is opened, and the opening should be adjusted according to the outlet pressure of the water pump. The running status of the water pump should be monitored to ensure that the pump head is within its working head range to prevent the water pump motor from overheating. At the same time, observe the vibration of the water pump and pipeline. If the vibration is too large, stop the pump and reinforce the part with excessive vibration (the same applies to the following stages). Take water from the upstream pressure pipeline of the underground pump station and fill it until the water level of the vertical shaft section of the outlet pipeline reaches 920m.
[0061] When the water level in the outlet shaft reaches 920m, close the water intake pipe valve and the outlet pipe valve of the filling pump, stabilize the pressure for 12 hours, and start filling the 6th section only after no abnormal conditions are observed.
[0062] (6) For the filling of the sixth section, open the valves of the water intake pipe and the outlet pipe of the water inlet pipe of Unit 1. Take water from the upstream pressure pipe of the underground pump station and fill the vertical shaft section of the outlet pipe. When the water level in the outlet shaft reaches 1013m, close the valves of the water intake pipe and the outlet pipe of the water inlet pump to stabilize the pressure.
[0063] (7) After the water filling pump has maintained a stable pressure for 24 hours, the first stage of water filling is completed.
[0064] 2.2.3 Water intake gate opening curve In the calculation of the gate opening in the first stage, the backwater effect of the water level in the downstream inlet pool is not considered, and the water level behind the gate is approximated by the uniform flow depth.
[0065] 2.2.4 Drainage procedures After the water delivery system filling test is completed and all buildings, equipment and units are checked for abnormalities, the drainage test can be carried out. Note that the flood gate of the drainage hole is fully open and locked above the orifice.
[0066] (1) After the first stage of water filling and pressure stabilization is completed, open the No. 1 water outlet pressure steel pipe inspection and drainage valve to return the pressure pipe system to the horizontal pressure, discharge the water above the water shaft 828.32m, about 2320m³ of return water. Pay attention to controlling the needle valve opening, and control the drainage rate of the pressure pipe shaft within 5m / h to prevent the drainage flow rate from being too fast and damaging the flow channel.
[0067] When the water level in the outlet shaft stops dropping and the water level in the inlet pool stops rising, and the water levels in the upstream and downstream are level, it is about 828.32m. Sequentially open the No. 1 sand clearing gate of the sedimentation tank, the No. 2 sand clearing gate of the sedimentation tank, the No. 1 and No. 2 emptying gates of the sedimentation tank, the No. 1 water diversion gate of the sedimentation tank, and the two drainage valves on the overflow weir of the inlet pool to drain water at the same time. The first stage of the first stage of drainage can drain the water above the 825.9m elevation of the water delivery system. The first stage of drainage is about 33532m³.
[0068] (2) When there is no water flowing at the outlet of the vent hole, open the drainage valves of the water inlet pipes of the 7 water pumps, and drain the water out of the ventilation hole through the maintenance drainage pumps of the underground pump station. The two maintenance drainage pumps work at the same time. Drain the water from the bypass hole, No. 2 water diversion tunnel, the water inlet pool above 824.280m, the water diversion pressure pipe, the water outlet pressure pipe and the 7 units below 825.9m. The drainage volume of the second section is about 14,869m³. The drainage time is about 49.4h.
[0069] During drainage, inspectors are required to closely monitor the drainage volume and unit conditions through the water pump inlet pipe pressure gauge and the drainage pump outlet pressure gauge. When draining water using the drainage equipment for maintenance, special attention should be paid to the water seepage in the equipment and pipelines. If any abnormality is found, the inlet pipe drain valve and the outlet steel pipe drain valve should be closed in time, and the drainage test person in charge and the leading group should be reported immediately.
[0070] (3) After the second section of drainage is completed, a temporary drainage pump is used to drain the water below the elevation of 824.280m in the inlet pool through the drainage hole and the drain hole in the inlet pool. The third section of drainage is about 655m³.
[0071] 2.3 The second stage of water filling and drainage The second stage of water filling can be carried out only after the first stage of filling and draining is completed and no abnormalities are found or the abnormalities have been properly handled. The water filling in this stage is designed according to the water flow through the sedimentation tank, the bypass hole, and the water flow through the water inlet tank. The water filling test is mainly carried out on the sedimentation tank, the sedimentation tank emptying hole, and the water inlet tank. Since the project has been left for a long time without water after the first machine of the first phase of the project was filled and drained, it is recommended to do the second stage of filling and draining again. The water filling is carried out in 6 stages.
[0072] 2.3.1 Water filling preparation (1) Confirm that the observation equipment has been installed, and the corresponding cables, pipes, and measuring meters have been installed and can operate normally; the initial readings of the prototype observation instruments should be recorded.
[0073] (2) The bubble blowing ice melting device and the electric heating ice melting device at the water inlet are both in the open state.
[0074] (3) The trash rack at the water intake is in the trash-blocking state, the downstream working gate is blocking water, and the upstream working gate is suspended above the orifice or locked above the orifice.
[0075] (4) The No. 1-6 sand clearing gates of the sedimentation tank are in full open state.
[0076] (5) The drain gates of sedimentation tanks No. 1 to 6 are in the closed state.
[0077] (6) The No. 2-3 diversion gate of the sedimentation tank is in the closed state.
[0078] (7) The No. 1 diversion gate of the sedimentation tank is in full open state.
[0079] (8) The bypass tunnel control gate is in the closed state.
[0080] (9) The drain valve behind the overflow weir of the inlet tank is in the closed state.
[0081] (10) The inlet inspection ball valve, outlet working valve and outlet inspection valve of units 1-7 of the underground pump station are all in the closed state. The first valves of all pipelines connected to the water supply system such as the penstock, volute, inlet pipe, etc. are all in the closed state, such as the inlet pipe drainage valve; the valves of the penstock, volute, inlet pipe, and top cover measuring pipeline; the technical water supply intake valve, the technical water supply drainage main valve, etc.
[0082] (11) The floodgate of the drainage hole is fully open and locked above the opening.
[0083] (12) Surveillance and monitoring personnel are in place at each location.
[0084] (13) Issue a water filling order.
[0085] 2.3.2 Water filling procedure In the second stage, the filling flow rate is selected according to the design flow rate of the two compartments of the sedimentation tank, that is, the design reference flow rate of the water intake is 11.78m³ / s.
[0086] (1) First, open the working gate of the water intake to the specified opening. Observe whether there is resonance in the working gate. If there is resonance, the working gate opening should be staggered until the resonance disappears. During the filling process, closely observe and record the water level at the water intake, the water level at the inlet of the sedimentation tank, the water level at the total water collection tank of the sedimentation tank, the water level data of the water inlet pool, the water level at the outlet of the flood control gate, and other water level data that can be observed or monitored in the water delivery system, and record the time and the water level at the corresponding time. The process of adjusting the opening of the working gate should also be recorded.
[0087] (2) The water flows through the No. 1 diversion tunnel, the No. 1 diversion gate of the sedimentation tank, the No. 1-2 sand clearing gate, the sedimentation tank horizontal flow section, the sedimentation tank inclined plate section, the main water collection tank, the No. 2 diversion tunnel, the water inlet tank, the water diversion pressure pipe, the water inlet tank spillway, the sedimentation tank emptying hole, and the flood control gate.
[0088] (3) After the No. 1 diversion gate of the sedimentation tank has been open for about 80 minutes (the water intake gate is open for 90 minutes), the No. 1 drain gate and the No. 2 drain gate are opened simultaneously, and the water is continued to flow for 30 minutes. Then the No. 2 diversion gate is opened and the No. 1 diversion gate is closed.
[0089] (4) After the No. 2 diversion gate of the sedimentation tank has been drained for 30 minutes, the No. 3 drain gate and the No. 4 drain gate are opened simultaneously, and the water is drained for another 30 minutes. Then the No. 3 diversion gate is opened and the No. 2 diversion gate is closed.
[0090] (5) 30 minutes after the No. 3 diversion gate of the sedimentation tank has passed water, the No. 5 and No. 6 drain gates are opened simultaneously, and the water is continued to pass for 30 minutes. Then, the water intake working gate and the No. 3 diversion gate are closed simultaneously, and the bypass tunnel control gate is opened.
[0091] (6) The working gate of the water intake is closed, and after 12 hours of pressure stabilization, the second stage of water filling is completed.
[0092] 2.3.4 Drainage procedures After the second phase of the water filling test of the water supply system is completed and all buildings, equipment and units are checked to be normal, the drainage test can be carried out.
[0093] (1) First, open the No. 3 diversion gate and the two drainage valves on the overflow weir of the water inlet pool to drain water at the same time. The water on the downstream side flows back to the No. 1 diversion tunnel and the sedimentation tank, and then through the No. 3 diversion gate of the sedimentation tank, the No. 5-6 sand clearing gate, the No. 5-6 emptying gate, and the emptying hole, the water above the elevation of 825.9m can be discharged. The water discharged by the drainage valve of the overflow weir of the water inlet pool is discharged through the water discharge hole and emptying hole of the water inlet pool. The drainage volume of the first section is about 29,585 m³.
[0094] (2) When there is no water flowing at the outlet of the vent hole, open the bypass pipe of the No. 1-7 water inlet inspection valve to level the pressure while the No. 1-7 water pump outlet valve is closed, open the No. 1-7 water inlet inspection valve, and then open the drainage valve of the No. 1-7 water pump inlet pipe. The water is discharged to the outside of the ventilation hole through the underground pump station inspection drainage pump. The two inspection drainage pumps work at the same time. Drain the water from the No. 2 water diversion tunnel, the water inlet pool above 824.280m, and the water diversion pressure pipe. The drainage volume of the second section is about 10032m³, and the drainage time is about 33.5h.
[0095] During drainage, inspectors are required to closely monitor the drainage volume and unit conditions through the water pump inlet pipe pressure gauge and the drainage pump outlet pressure gauge. When draining water using the drainage equipment for maintenance, special attention should be paid to the water seepage of the equipment and pipelines. If any abnormality is found, the drain valve of the water inlet pipe and the drain valve of the water outlet steel pipe should be closed in time, and the drainage test person in charge and the leading group should be reported immediately. The drainage rate of the vertical shaft section pressure pipeline should be controlled within 5m / h to prevent the phenomenon of excessive drainage flow rate damaging the flow channel.
[0096] (3) After the second section of drainage is completed, a temporary drainage pump is used to drain the water below the elevation of 824.280m in the inlet pool through the drainage hole and the drain hole in the inlet pool. The third section of drainage is about 655m³.
[0097] 2.4 Safety Monitoring 2.4.1 Monitoring Purpose (1) In combination with the filling and drainage test procedures, obtain monitoring data and information at each stage, step and process, understand the project operation status during the test, and provide a basis for the filling and drainage test process control; timely warn when abnormal conditions are found so that corresponding measures can be taken to ensure the safe operation of the project.
[0098] (2) Through the water level monitoring facilities at the water intake, sedimentation tank, inlet tank and outlet tank, the water level changes in the corresponding parts are monitored, and water level observation data are provided for the filling and drainage test process, and necessary boundary conditions are provided for the analysis of monitoring data.
[0099] (3) Through inspections and instrument monitoring, the operation of the project is fully understood. Focus on the stability of the slopes along the waterway, the seepage of surface gullies, construction branch hole plugging, powerhouse caverns and corridors, pressure steel pipe wall drainage outlets, and various manholes, so as to take measures to reduce abnormal leakage and eliminate safety hazards.
[0100] (4) Provide necessary monitoring data for project safety evaluation and acceptance.
[0101] 2.4.2 Preparation (1) Before filling with water, historical monitoring data should be analyzed and evaluated to ensure that all parts of the project are in normal condition and meet the test conditions.
[0102] (2) Check the monitoring facilities and equipment at various locations to ensure that the observation conditions can meet the observation requirements of the filling and drainage tests, and that the observation frequency and analysis feedback speed can meet the monitoring needs of the filling and drainage tests.
[0103] (3) In combination with the filling and drainage test procedures and specific implementation plans, prepare in advance for the collection of drawings, inspections, monitoring data collection, recording, analysis, feedback, and early warning, as well as auxiliary work such as transportation, lighting, communications, video recording, tools, personnel dispatch, safety protection, observation and drills that are necessary for monitoring work.
[0104] 2.4.3 Monitoring content (1) Monitor the water level changes at the water intake, sedimentation tank, inlet tank, and outlet tank, and collect and organize the water level changes in the pressure pipe during the filling and drainage tests.
[0105] (2) Monitor the uplift pressure and slope stability of the water intake foundation, the surrounding rock stability and lining steel stress of the 1# non-pressure diversion tunnel and bypass tunnel, the uplift pressure and slope stability of the sedimentation tank foundation, the surrounding rock stability and lining steel stress of the 2# non-pressure diversion tunnel, the surrounding rock stability, seepage and lining steel stress of the inlet pool, the surrounding rock stability, gap value, surrounding rock seepage water pressure and steel lining external water pressure, steel plate stress and temperature of the pressure pipeline, the foundation settlement and seepage pressure of the outlet pool, the change of structural joints, the surrounding rock stability and seepage water pressure of the pump station building, the lining steel stress, the groundwater level around the building, the anchor stress of the crane beam, the settlement of the top of the earth tunnel section of the venting tunnel and the settlement of the highway on the top of the tunnel. Among them, the monitoring instruments related to the external water pressure of the steel lining of the pressure pipeline, the stress of the steel plate and the gap value should be paid special attention.
[0106] (3) Inspection and inspection of the stability of the slopes along the waterway, the seepage conditions at the surface gullies, plugging of construction branch tunnels, factory caverns and corridors, drainage outlets of penstocks attached to the walls, manholes at various locations, and other adverse conditions at other project-related locations.
[0107] (4) Other contents related to the test process that need to be monitored.
[0108] 2.4.4 Observation frequency requirements (1) Monitoring data collection is carried out in conjunction with the filling and drainage test procedures. When the procedure is adjusted, the collection frequency is also adjusted accordingly.
[0109] (2) Before filling or draining, a comprehensive patrol monitoring should be carried out in a timely manner according to the above monitoring contents. On the one hand, all monitoring facilities should be checked, and on the other hand, a benchmark value should be provided for the analysis of filling and draining monitoring data.
[0110] (3) During the filling and drainage period, the water level observation frequency of the water intake, sedimentation tank, inlet tank and outlet tank is once per hour; the leakage observation frequency of abnormal leakage points is once per hour.
[0111] (4) During the period of water level changes in the waterway: First, ensure that the water pressure outside the steel lining, steel plate stress, and gap value are collected 1 to 2 times / hour (higher frequency when the steel plate stress is large), and ensure that the monitoring data of all monitoring items at each stage and at the beginning and end of each step during the filling and drainage process are obtained. It is advisable to conduct synchronous observations on related monitoring items.
[0112] (5) During the pressure stabilization period: At the beginning, the observation frequency of the water pressure outside the steel lining and the steel plate stress is 1 to 2 times / hour (higher frequency is adopted when the steel plate stress is relatively large), until the water pressure outside the steel lining and the steel plate stress are relatively stable or the rate of change is significantly reduced, and the monitoring data of all monitoring items are obtained.
[0113] (6) The above observation frequency is the most basic requirement. When the waterway system is abnormal or there are signs of unsafe conditions, observations should be more frequent.
[0114] (7) When collecting monitoring data, the internal water pressure measurement value of the pipeline should be obtained simultaneously.
[0115] (8) During the test period and within 3 days after water filling, the on-duty personnel at each monitoring location shall not leave the monitoring post without authorization. They shall ensure that they are on duty 24 hours a day, closely monitor the monitoring situation, and immediately report any abnormalities to the command department.
[0116] 2.4.5 Inspection after drainage After drainage, the leadership team organizes personnel from all parties to conduct inspections and certifications of the following items, and the situation of each inspection must be recorded in detail. After the data and calculation parameters of the filling and drainage tests are sorted out, they will be handed over to the filling and drainage test leadership team for reference and analysis.
[0117] (1) Carry out a visual inspection of the entire water supply system (except the penstock), including checking for falling blocks, collapse, cracks, deformation, locations of water infiltration and the amount of water infiltration, concrete damage, etc.
[0118] (2) Perform an appearance inspection on the entire penstock line. Check whether there are any foreign objects inside the steel pipe, whether the inner coating has fallen off, whether there are local leaks, and the quality of the welds.
[0119] (3) Perform a comprehensive appearance inspection on the volute and water inlet pipe. Check whether there is any debris inside, whether the inner coating has fallen off, whether there is local leakage, and the quality of the welds, etc.
[0120] (4) Carry out an appearance inspection of the water collection well and its manhole, volute drain valve, water inlet pipe inspection door, etc. Check whether there is water seepage and the amount of water seepage, whether there are cracks in the concrete and the width of the cracks, etc.
[0121] (5) Carry out a visual inspection of the embedded parts of the door slot and its second-phase concrete.
[0122] If any problems are found during the inspection, the causes must be analyzed and defects must be treated. If a large amount of water seepage is found, grouting must be carried out after the causes are analyzed, and the water pressure and water volume must be tested and analyzed. All parts where problems are found during the inspection must be recorded by television and submitted to the leadership team.
[0123] 3. Static commissioning of pump group 3.1 Filling the technical water supply system and adjusting the cooling water flow of each guide bearing 3.1.1 Debugging Purpose Fill the technical water supply system with water, check whether there are any leakages in the technical water supply related pipelines, joints, instruments, etc., adjust the pressure and flow of cooling water for each guide bearing of the pump group, air cooler, and main shaft sealing water to meet the design requirements, and mark the position of each valve.
[0124] 3.1.2 Debugging content (1) Carry out overall commissioning of the pump group's technical water supply. Open each valve one by one starting from the first valve of the pump group's technical water supply main pipe, and comprehensively check whether the pump group's technical water supply equipment, pipelines, valves and flanges have any leakage; adjust the water pressure and flow of each guide bearing, air cooler, etc. as required to meet the design requirements; (2) Fill the main shaft seal with water, adjust the main shaft seal water pressure and flow rate as required to meet the design requirements; check the main shaft seal lift; 3.2 Hydrostatic test of the ball valve for water inlet inspection of the pump unit 3.2.1 Debugging Purpose Verify that the pump unit's water inlet inspection ball valve can open and close automatically under static water, and review and adjust the ball valve opening and closing time to meet design requirements.
[0125] 3.2.2 Debugging content (1) Open and close the ball valve in a single step on site to check whether the ball valve opening indication, i.e. the position node feedback, is correct.
[0126] (2) Verify the automatic control process of the on-site switch and check whether the opening and closing times meet the contract requirements.
[0127] (3) Verify whether the remote switch ball valve function is normal.
[0128] 3.3 Hydrostatic test of ball valve for water outlet inspection of pump unit 3.3.1 Debugging Purpose Verify that the water inlet inspection ball valve of the pump unit can open and close automatically under static water, and review and adjust the opening and closing time of the ball valve and the setting values of each pressure switch to see if they meet the design requirements.
[0129] 3.3.2 Debugging content (1) Withdraw the water outlet inspection ball valve, inspect the seal and manually lock it. Withdraw the ball valve, inspect the seal and check whether the feedback signal is correct.
[0130] (2) Operate the working seal on site and check whether the feedback signal is correct.
[0131] (3) Open and close the ball valve in a single step on site and check whether the ball valve opening indication, i.e. the position node feedback, is correct.
[0132] (4) Verify the automatic control process of the on-site switch and check whether the opening and closing times meet the contract requirements.
[0133] (5) Verify whether the remote switch ball valve function is normal.
[0134] (6) Check whether the emergency ball valve functions normally.
[0135] 3.4 Monitoring system process simulation debugging 3.4.1 Debugging Purpose Check that the functions and performance of the monitoring system meet the requirements of the contract, technical conditions and relevant regulations to ensure the reliability and stability of the system.
[0136] 3.4.2 Debugging content (1) Single-step operation control test of monitoring system.
[0137] (2) Simulation test of the start / stop sequence control process of the monitoring system.
[0138] (3) Master-slave switching test of monitoring system.
[0139] (4) Monitoring system main PLC (programmable logic controller) mechanical and electrical accident shutdown test.
[0140] (5) Monitoring system backup PLC mechanical and electrical accident shutdown test.
[0141] 4. No-load commissioning of the pump unit 4.1 First manual start-up test of the pump motor 4.1.1 Debugging Purpose (1) Check the friction of the pump motor during the first rotation; (2) Check the mechanical accident shutdown process of the pump group monitoring system; (3) Based on the swing and vibration values of the pump motor, determine whether there is mass imbalance in the pump motor rotor. If so, perform dynamic balancing on the pump rotor until the vibration and swing of each part of the pump motor meet the technical requirements.
[0142] 4.1.2 Debugging content (1) Inching test: Manually start the inverter to check the shaft system; obtain motor parameters, establish the motor model and preliminarily adjust the motor protection value; check that the motor rotation direction is correct and there is no abnormal sound in the pump group.
[0143] (2) Emergency shutdown test: After no abnormality is found, increase the speed to 5% of the rated speed, press the emergency stop button to stop the machine, and check the correctness of the emergency stop process.
[0144] (3) Manual speed increase test: 1) After the first startup and shutdown inspection, restart the machine, adjust the pump speed within 10%, increase the speed step by step, and check the dynamic balance of the pump; check the pulse operation function of the inverter, correct the initial excitation current setting value; check the working condition of the inverter power device.
[0145] 2) Increase the speed gradually and stabilize it at 20% of the rated speed for 3 minutes, check and record the bearing temperature of each guide bearing, the swing of each guide bearing and the vibration of each part, and the working conditions of the electrical measurement system and protection device; 3) Increase the speed gradually and stabilize it at 50% of the rated speed for 3 minutes, check and record the bearing temperature of each guide bearing, the swing of each guide bearing and the vibration of each part, and the working conditions of the electrical measurement system and protection device; 4) Increase the speed gradually and stabilize it at 75% of the rated speed for 3 minutes, check and record the bearing temperature of each guide bearing, the swing of each guide bearing and the vibration of each part, and the working conditions of the electrical measurement system and protection device; 5) Increase the speed gradually and stabilize it at 100% of the rated speed for 5 minutes, check and record the bearing temperature of each guide bearing, the swing of each guide bearing and the vibration of each part, and the working conditions of the electrical measurement system and protection device; (4) Protection shutdown test After the pump unit runs at 100% of the rated speed for 5 minutes, press the electrical emergency shutdown button to shut down the pump and verify whether the electrical emergency shutdown process is correct.
[0146] 4.2 Pump unit no-load grid connection test 4.2.1 Debugging Purpose Verify the correctness of the inverter's grid-connection function.
[0147] 4.2.2 Debugging content Verification of the inverter's up-cut function (grid connection).
[0148] 4.3 Thermal stability test of unloaded bearings 4.3.1 Debugging Purpose Check whether the temperature of each part of the pump group motor and the operating parameters such as vibration and swing of the rotating system meet the design requirements when it is running at no-load.
[0149] 4.3.2 Debugging content (1) Pump unit temperature curve measurement and recording. The monitoring system records the temperature curves and data of various parts, such as the thrust bearing, upper guide bearing, lower guide bearing, oil tank oil temperature, water temperature and other curves of the pump unit motor.
[0150] (2) Record the vibration and swing of each part of the motor under no-load condition. Record the thrust of the pump motor, the swing of the upper and lower guide bearings, and the vibration of the upper and lower frames.
[0151] (3) Motor cooling water adjustment test (if the temperature changes abnormally, consider this item).
[0152] (4) There should be no obvious sudden changes in the temperature, oil temperature, water temperature of the thrust bearing, upper guide bearing, lower guide bearing, stator of the pump unit motor, as well as the vibration and swing of the pump unit. After the data is stable, the coupling operation can be started and load debugging can be prepared.
[0153] 5. Pump group load commissioning 5.1 Speed increase (pressure building) test 5.1.1 Debugging Purpose 1. Measure the opening time of the bypass valve of the water outlet working ball valve of the pump unit (the speed of the pump unit when the pressure is successfully built); 2. Record the manufacturing pressure curve.
[0154] 5.1.2 Debugging content (1) After the single-step startup and the normal operation of all auxiliary systems, the inverter is set to increase the speed to 1%ne (ne is the rated speed) to check whether there is any friction between the fixed parts and the rotating parts of the pump group; if there is no abnormality, continue to increase the speed to 5%ne and confirm again whether there is any friction between the fixed parts and the rotating parts of the pump group; continue to increase the speed to 10%ne and continue to confirm whether there is any friction between the fixed parts and the rotating parts of the pump group.
[0155] (2) Confirm that the auxiliary systems of the pump group are working normally, issue the inverter start command, and monitor the water pressure, temperature, vibration swing and other data of each part of the pump group during the speed increase; confirm whether the bypass valve of the water outlet working ball valve is open normally when the speed is greater than 70%ne; record the pressure curve during the speed increase.
[0156] 5.2 First pumping test 5.2.1 Debugging Purpose Test whether the inverter up-cut is normal (if not, optimize the inverter parameters); after successful up-cut, open the water outlet working ball valve to pump water for the first time, and check that the sampling of the motor protection device and the sampling of the measuring instrument are correct.
[0157] 5.2.2 Debugging content (1) Whether the inverter is switched on normally (if not, the inverter parameters need to be optimized); (2) Check the sampling of each measuring meter and protective device for the first time when pumping water to see if it is correct; (3) After the first pumping, run the pump continuously for 30 minutes and monitor the vibration swing of each part of the pump unit, the temperature of each guide bearing bush, the oil temperature of the oil tank, and the main shaft seal temperature.
[0158] 5.3 Pump unit mechanical accident protection shutdown test 5.3.1 Debugging Purpose Verify the correctness of the pump group monitoring system mechanical accident and emergency shutdown process, and optimize the time parameters in the process.
[0159] 5.3.2 Debugging content Simulate the shutdown of a water pump due to a mechanical accident, check whether the action logic and timing of related equipment are correct during the shutdown process, and record the speed drop curve.
[0160] 5.4 Bearing thermal stability test 5.4.1 Debugging Purpose Check whether the temperature of each part and the operating parameters such as vibration and swing of the rotating system under the stable operation state of the pump unit meet the technical requirements.
[0161] 5.4.2 Debugging content (1) Pump unit temperature curve measurement and recording. The monitoring system records the temperature curves and data of various parts, such as the temperature, oil temperature, water temperature, etc. of the pump unit motor and water pump thrust bearing, upper guide bearing, lower guide bearing, stator, etc.
[0162] (2) Record the vibration and swing of the pump unit in steady state. Record the upstream and downstream water levels, the swing of the upper and lower guide bearings of the pump unit motor and water pump, and record the vibration of the upper and lower pump covers and upper and lower frames.
[0163] (3) Pump unit cooling water adjustment test (if the temperature changes abnormally, consider this item).
[0164] (4) There are no obvious sudden changes in the temperature of the thrust bearing, upper guide bearing, lower guide bearing, stator, oil temperature, water temperature of the pump unit motor and water pump, and the vibration and swing of the pump unit.
[0165] 5.5 Dynamic balance test 5.5.1 Debugging Purpose The unbalanced mass of the pump shaft system is solved by dynamic balancing. The vibration data of each relevant measuring point during the operation of the pump is measured, and the vibration data is analyzed and weights are added when necessary.
[0166] 5.5.2 Debugging content (1) Record the swing and vibration of the pump motor and the upper and lower guides of the water pump as well as the vibration of each part.
[0167] (2) Analyze the vibration and swing of each part to determine whether there is any mass imbalance in the rotating parts. If so, add weights and record the position and weight of the weights.
[0168] 5.6 Pump group automatic start and stop debugging 5.6.1 Debugging Purpose Optimize the automatic start and stop process of the pump group to meet the contract requirements.
[0169] 5.6.2 Debugging content (1) Start-up condition check.
[0170] (2) Record the start and stop time of auxiliary equipment.
[0171] (3) Optimize the start-up and shutdown processes of the pump group.
[0172] 5.7 Pump group 24h continuous trial operation 5.7.1 Test Purpose (1) Record the temperature of each part and the operating parameters such as vibration and swing of the rotating system to confirm whether they meet the technical requirements.
[0173] (2) Verify the stability of the pump unit's long-term continuous operation through 24-hour continuous trial operation.
[0174] 5.7.2 Test content (1) Record the temperature, vibration and swing data of each part during the 24-hour continuous test run; (2) Record abnormal conditions during the trial operation of the pump unit; This debugging method ensures the accuracy of each operation, effectively eliminates or reduces the danger brought by the ball valve boost, ensures the safety of equipment and pipelines, reduces labor intensity, eliminates the influence of human factors in operation, and avoids the occurrence of casualties in operation. The control execution process is reliable, the command is issued quickly, and the number of operators is reduced, laying a solid foundation for achieving less-manned or unmanned duty.
[0175] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principle of the present invention should be included in the protection scope of the invention.
Claims
1. A method for starting and commissioning a large vertical single-suction three-stage pump set, characterized in that: The following steps are involved: The pre-start inspection of the unit, the static commissioning of the pump unit, the no-load commissioning of the pump unit and the on-load commissioning of the pump unit. The pre-start inspection of the unit includes the following steps: the pre-start inspection of the pump unit and the water filling and drainage test of the water supply system. The water filling and drainage test of the water supply system includes the following steps: determining the requirements of the water filling and drainage procedures, the first stage of water filling and drainage, the second stage of water filling and drainage and safety monitoring; the static commissioning of the pump unit includes the following steps: filling of the technical water supply system and adjustment of the cooling water flow of each guide bearing, static water test of the ball valve for water inlet inspection of the pump unit, static water test of the ball valve for water outlet inspection of the pump unit and simulation commissioning of the monitoring system process; the no-load commissioning of the pump unit includes the following steps: the first manual start-up test of the pump unit motor, the grid connection test of the pump unit under no-load and the thermal stability test of the no-load bearing; the on-load commissioning of the pump unit includes the following steps: speed increase test, the first water pumping test, the pump unit mechanical accident protection shutdown test, the bearing thermal stability test, the dynamic balance test, the pump unit automatic start and stop commissioning and the pump unit 24-hour continuous trial operation.
2. A method for starting and commissioning a large vertical single-suction three-stage pump set according to claim 1, characterized in that: The requirements for determining the filling and drainage procedures are specifically as follows: when the water intake level is between 830m and 834m, the working gate is lowered to adjust the opening to control the water diversion flow; when the reservoir water level is lower than 830.0m or higher than 834m during the filling and drainage tests, no water is taken.
3. The startup test run debugging method of a large vertical single-suction three-stage pump set according to claim 1 is characterized in that: The first stage of water filling and drainage includes the following steps: water filling preparation, water filling procedure, calculation of water intake gate opening curve, and drainage procedure. The water filling procedure is specifically as follows: first, open the working gate of the water intake to the specified opening, and observe whether the working gate has any resonance phenomenon. If there is resonance, the working gate opening should be staggered until the resonance phenomenon disappears; then, after the first stage of water filling is completed and the pressure is stabilized for 1 hour, observe whether there is any abnormality, and start the second stage of water filling after no abnormality is found; then, after the second stage of water filling is completed and the pressure is stabilized for 6 hours, check the blocking conditions of each water inlet valve and water delivery system, and start the third stage of water filling after no abnormality is found ; Then, after the third section is filled with water and the pressure is stabilized for 2 hours, observe whether there is any abnormality. If no abnormality is found, start the fourth section of water filling; Then, after the third section is filled with water and the pressure is stabilized for 12 hours, observe whether there is any abnormality. If no abnormality is found, start the fifth section of water filling; Then, carry out the fifth section of water filling: close the outlet working ball valve of Unit 1, open the water intake pipe valve and the outlet pipe valve of the water inlet pipe water channel filling pump of Unit 1, and monitor the running status of the water pump, fill water until the water level of the outlet pipe shaft section reaches 920m, and when the water level of the outlet shaft reaches 920m, close the water intake pipe valve and the outlet pipe valve of the filling pump, and stabilize the pressure for 12 hours, observe whether any abnormality occurs, and start the sixth stage of water filling after no abnormality is found; then, carry out the sixth stage of water filling: open the water intake pipe valve and the outlet pipe valve of the water filling pump of the water inlet pipe of the No. 1 unit, fill water to the vertical shaft section of the outlet pipe, and when the water level of the outlet shaft reaches 1013m, close the water intake pipe valve and the outlet pipe valve of the water filling pump to stabilize the pressure; finally, after the water filling pump has stabilized the pressure for 24 hours, end the water filling procedure; the drainage procedure includes the following steps: first, open the No. 1 outlet pressure steel pipe maintenance drainage valve to return the pressure of the pressure pipe system to the horizontal pressure, and discharge the water above the outlet shaft 828.32m. The drainage rate of the vertical shaft is controlled within 5m / h, and the No. 1 sand clearing gate of the sedimentation tank, the sedimentation tank, the No. 2 sand clearing gate, the sedimentation tank, the No. 1 and No. 2 emptying gates, the No. 1 water diversion gate of the sedimentation tank and the two drainage valves on the overflow weir of the water inlet tank are opened in sequence to drain the water; then, after there is no water flowing at the outlet of the emptying hole, open the drainage valves of the water inlet pipes of the seven water pumps to discharge the water above the bypass tunnel, the No. 2 water diversion tunnel and the water inlet tank at an elevation of 824.28m, as well as the water diversion pressure pipeline, the water outlet pressure pipeline and the seven units below an elevation of 825.9m; finally, use a temporary drainage pump to discharge the water below the elevation of 824.28m in the water inlet tank.
4. A method for starting and commissioning a large vertical single-suction three-stage pump set according to claim 1, characterized in that: The second stage of water filling and drainage includes the following steps: water filling preparation, water filling procedure, drainage procedure and safety monitoring. The water filling procedure includes the following steps: first, open the working gate of the water intake to the specified opening, observe whether the working gate has resonance phenomenon, if there is resonance phenomenon, stagger the opening of the working gate until the resonance phenomenon disappears; then, let the water flow through the No. 1 water diversion tunnel, the No. 1 water diversion gate of the sedimentation tank, the No. 1-2 sand clearing gate, the sedimentation tank horizontal flow section, the sedimentation tank inclined plate section, the total water collection tank, No. 2 water diversion tunnel, water intake tank, water intake pressure pipe, water intake tank spillway, sedimentation tank drain hole and flood control gate; then, after about 80 minutes of water flowing through the No. 1 diversion gate of the sedimentation tank, open the No. 1 drain gate and the No. 2 drain gate at the same time, continue to flow water for 30 minutes, open the No. 1 diversion gate, and close the No. 1 diversion gate; then, after 30 minutes of water flowing through the No. 2 diversion gate of the sedimentation tank, open the No. 3 drain gate and the No. 4 drain gate at the same time, continue to flow water for 30 minutes, open the No. 3 diversion gate, and close the No. 2 diversion gate; then, 30 minutes after the No. 3 diversion gate of the sedimentation tank flows through, the No. 5 drain gate and the No. 6 drain gate are opened at the same time, and the water continues to flow for 30 minutes. At the same time, the working gate of the water intake and the No. 3 diversion gate are closed, and the bypass tunnel control gate is opened; finally, the working gate of the water intake is closed, and the water filling procedure is terminated after stabilizing the pressure for 12 hours; the drainage procedure includes the following steps: first, open the No. 3 diversion gate and the two drainage valves on the overflow weir of the water inlet tank to drain water at the same time, and discharge the No. 1 water diversion tunnel and the sedimentation tank above the elevation of 825.9m then, when there is no water flowing at the outlet of the drain hole, with the outlet working valve of the No. 1-7 water pump closed, open the bypass pipe of the No. 1-7 water inlet inspection valve to equalize the pressure, open the No. 1-7 water inlet inspection valve, and then open the drain valve of the No. 1-7 water pump inlet pipe to discharge the water above the No. 2 water diversion tunnel and the water inlet pool at an elevation of 824.280m; finally, use a temporary drainage pump to discharge the water below the water inlet pool at an elevation of 824.28m through the water inlet pool, the drain hole and the drain hole.
5. The startup test run debugging method of a large vertical single-suction three-stage pump set according to claim 1 is characterized in that: The static water test of the ball valve for water inlet maintenance of the pump group includes: verifying the on-site single-step opening and closing of the ball valve, and checking whether the feedback of the ball valve opening indication is correct; verifying the on-site switch automatic control process, and checking whether the opening and closing time meets the requirements; verifying whether the function of the remote monitoring switch ball valve is normal; the static water test of the ball valve for water outlet maintenance of the pump group includes: exiting the manual locking of the water outlet maintenance ball valve maintenance seal, exiting the ball valve maintenance seal, and checking whether the feedback signal is correct; verifying the on-site investment and withdrawal working seal, and checking whether the feedback signal is correct; verifying the on-site single-step opening and closing of the ball valve, and checking whether the ball valve opening indication is correct; verifying whether the function of the remote monitoring switch ball valve is normal; checking whether the emergency closing ball valve function is normal; the monitoring system process simulation debugging includes: monitoring system single-step operation control debugging, monitoring system startup and shutdown sequential control process simulation debugging, monitoring system master-slave switching debugging, monitoring system main PLC mechanical and electrical accident shutdown debugging, monitoring system backup PLC mechanical and electrical accident shutdown debugging.
6. A method for starting and commissioning a large vertical single-suction three-stage pump set according to claim 1, characterized in that: The first manual start-up test of the pump group motor includes: inching test, emergency stop test, manual speed increase test and protection stop test. The manual speed increase test includes: (1) after the first start-up and shutdown inspection, restart the machine, adjust the pump group speed between 10%, increase the speed step by step, check the dynamic balance of the pump group, check the inverter pulse operation function, correct the initial excitation current setting value, and check the working condition of the inverter power device; (2) increase the speed and stabilize it at 20% of the rated speed for 3 minutes, check and record the bearing temperature of each guide bearing, the swing of each guide bearing and the vibration of each part, as well as the working condition of the electrical measurement system and the protection device; (3) increase the speed and stabilize it at 50% of the rated speed for 3 minutes, check and record the bearing temperature of each guide bearing, the swing of each guide bearing and the vibration of each part, as well as the working condition of the electrical measurement system and the protection device; (4) increase the speed and stabilize it at 75% of the rated speed. Run at a constant speed for 3 minutes, check and record the temperature of each guide bearing bushing, the swing of each guide bearing and the vibration of each part, as well as the working conditions of the electrical measurement system and protection device; (5) Increase the speed and stabilize it at 100% of the rated speed for 5 minutes, check and record the temperature of each guide bearing bushing, the swing of each guide bearing and the vibration of each part, as well as the working conditions of the electrical measurement system and protection device; The no-load bearing thermal stability test includes: (1) Pump group temperature curve measurement; (2) Record the vibration and swing of each part of the motor under no-load state, record the thrust, upper guide and lower guide bearing swing of the pump group motor, and record the vibration of the upper and lower frames; (3) Motor cooling water adjustment test; (4) When there is no obvious sudden change in the temperature, oil temperature, water temperature of the thrust bearing, upper guide bearing, lower guide bearing and stator of the pump group motor, as well as the vibration and swing of the pump group, the coupling operation can be started to prepare for the pump group load commissioning.
7. A method for starting and commissioning a large vertical single-suction three-stage pump set according to claim 1, characterized in that: The speed increase test includes: (1) single-step startup until all auxiliary systems are put into normal operation, the inverter is set to increase the speed to 1%ne, where ne is the rated speed, and check whether there is any friction between the fixed parts and the rotating parts of the pump group. If there is no abnormality, continue to increase the speed to 5%ne, and confirm again whether there is any friction between the fixed parts and the rotating parts of the pump group. Continue to increase the speed to 10%ne, and continue to confirm whether there is any friction between the fixed parts and the rotating parts of the pump group; (2) Confirm that all auxiliary systems of the pump group are working normally, send the inverter start command, monitor the water pressure, temperature and vibration swing of various parts of the pump group during the speed increase process, check whether the bypass valve of the water outlet working ball valve is normally opened when the speed is greater than 70%ne, and record the pressure curve during the speed increase process; the first water pumping test includes: checking whether the inverter up-cut is normal, checking whether the sampling of each measuring meter and protection device for the first water pumping is correct, and running continuously for 3 hours after the first water pumping. 0min, monitor the vibration swing of each part of the pump group, the temperature of each guide bearing and the oil temperature of the oil tank and the main shaft seal temperature; the pump group mechanical accident protection shutdown test is specifically: simulate the water pump mechanical accident shutdown, check whether the action logic and timing of the relevant equipment during the shutdown process are correct, and record the speed drop curve; the bearing thermal stability test includes: pump group temperature curve measurement and recording, recording the vibration and swing of the pump group under steady state, pump group cooling water adjustment test, and the dynamic balancing test can be started after the temperature, oil temperature, water temperature of the thrust bearing, upper guide bearing, lower guide bearing, stator of the pump group motor and water pump, as well as the vibration and swing of the pump group have no obvious sudden changes; the dynamic balancing test includes: (1) recording the swing of the upper and lower guides of the pump group motor and water pump and the vibration of each part; (2) analyzing the vibration and swing of each part to determine whether there is mass imbalance of the rotating parts. If so, weight is added and the position and weight of the weight is recorded.