Tower column cross beam construction method
By constructing from top to bottom on the tower columns, using the cooperation of corbel supports and threaded reserved holes, efficient construction of multiple beams is achieved, which solves the problem of repeated installation and disassembly of traditional brackets, improves construction efficiency and Security.
Patent Information
- Application Number
- CN202411076904.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-07
- Publication Date
- 2024-10-11
AI Technical Summary
In the construction of multiple beams of long-span suspension bridges, the repeated installation and disassembly of traditional brackets results in a long construction period and high safety risks. It is difficult to significantly improve the overall construction efficiency with existing technology.
Using the top-down construction method, the same beam brackets are lowered in sequence as the pressure-bearing foundation for multiple beams. Through the cooperation of the corbel supports and threaded reserved holes, the overall hoisting and fixation of the brackets are achieved, reducing the need for brackets. Repeat assembly and disassembly.
It effectively shortens the construction period of multiple beams, reduces the amount of high-altitude operations, improves construction efficiency and safety, and avoids repeated installation and disassembly operations of brackets.
Smart Images

Figure CN118756591A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of bridge construction, in particular to a tower column crossbeam construction method. Background Art
[0002] The construction of a long-span suspension bridge involves the construction of multiple beams. As part of the main tower of the suspension bridge, the beam plays the role of connecting the tower column structure. In the construction of the tower column beam, the safety, stability and efficiency of the construction are the most important factors. Therefore, traditional composite brackets or steel composite brackets are usually set up as a temporary support system for the beam before pouring the beam.
[0003] Traditional combined brackets have the advantages of high overall rigidity, good supporting performance and mature process technology. However, traditional combined brackets have heavy overall weight, many reserved embedded parts, many high-altitude welding operations, high operational risks, and difficult welding quality control. Dismantling work requires high lifting equipment. When carrying out multi-beam construction, the brackets need to be repeatedly installed and disassembled, which not only prolongs the construction period but also increases the safety risks of construction.
[0004] The steel composite bracket has the advantages of light weight, fewer embedded parts, easy assembly, convenient installation and disassembly, and low construction risk. However, the overall rigidity of the steel composite bracket is low and the process technology is difficult. When carrying out multi-beam construction, the bracket also needs to be repeatedly installed and disassembled.
[0005] Therefore, no matter whether traditional composite brackets or steel composite brackets are used, when it comes to multi-beam construction, the brackets of each beam need to be installed and disassembled separately, resulting in long working hours at height and high construction safety risks.
[0006] A Chinese invention patent application with publication number CN116716813A discloses a cast-in-place support structure and construction method for a super-high main tower beam of a cable-stayed bridge, which includes a plurality of frame units, a traction mechanism and two corbel brackets. The plurality of frame units are assembled into a frame system, the two corbel brackets are respectively arranged on the inner sides of two tower columns, the traction mechanism is arranged on the side of the tower column, and the connecting end of the traction mechanism is connected to the end of the frame system. When the frame system is hoisted to the installation position, the traction mechanism pulls one end of the frame system in the direction of one of the corbel brackets.
[0007] The Chinese invention patent application with the publication number CN117449215A discloses a method for constructing a bridge main tower beam, which includes the following steps: during the construction of the lower tower column, the design, processing and manufacturing of the lower beam bracket, the embedding of the embedded parts, the erection of the lower beam bracket and the processing of the template are carried out simultaneously, the lower beam reinforcement and prestressing are constructed on the bracket, and then the lower beam template is installed, the lower beam concrete is constructed, the lower beam prestressing is constructed, the tower column is constructed in sections to the upper beam, the upper beam bracket is installed, the upper beam reinforcement and prestressing are constructed, the upper beam template is installed, and then the upper beam concrete is constructed, and finally the upper beam prestressing is constructed, and the tower column is constructed to the top of the tower, the construction of the top section is completed, the tower column is capped, and the formwork is removed. The upper and lower beams are poured with concrete twice, and the tower beam asynchronous construction method is adopted, which can greatly improve the construction efficiency, shorten the construction period, reduce the rental time of equipment, reduce costs, and have higher construction safety.
[0008] Although the technical solution disclosed in the above patent application improves the bracket structure and optimizes the installation method of the bracket, the technical effect is mainly manifested in improving the construction efficiency of a single beam. For the construction of multiple beams on the tower column, the bracket must still be repeatedly installed and disassembled. Therefore, no significant improvement has been achieved in the overall construction efficiency of multiple beams. Summary of the invention
[0009] The technical problem to be solved by the present invention is to provide a tower column crossbeam construction method, which can effectively improve the overall construction efficiency when constructing multiple crossbeams.
[0010] To solve the above technical problems, the technical solution adopted by the present invention is: a tower column beam construction method, wherein each beam is constructed on the tower column from top to bottom in sequence, and during the construction process, the same beam bracket is lowered in sequence as a pressure-bearing foundation for casting each beam.
[0011] As an improvement of the above scheme: the construction method comprises the following steps:
[0012] S1. Installing a first supporting member for supporting a crossbeam bracket at the installation position of a first crossbeam at the upper part of the tower column;
[0013] S2, assembling the crossbeam bracket on the ground, hoisting the entire bracket to the first supporting member, and connecting and fixing the bracket to the first supporting member;
[0014] S3. Install the casting formwork on the beam bracket;
[0015] S4, casting the first crossbeam, and performing curing and tensioning. During casting, a lifting rope channel is reserved on the first crossbeam to longitudinally penetrate the first crossbeam, and a fixing plate for lifting equipment is embedded on the top of the first crossbeam;
[0016] S5. Install a second supporting member and a diagonal brace for supporting the crossbeam bracket at a mounting position of the second crossbeam located below the first crossbeam on the tower column;
[0017] S6. Remove the casting formwork on the first beam;
[0018] S7, installing a lifting device on the fixed plate at the top of the first crossbeam, and connecting the crossbeam bracket to the lifting device using a lifting rope passing through the lifting rope channel;
[0019] S8, after removing the first supporting member supporting the crossbeam bracket, lower the crossbeam bracket to the installation position of the second crossbeam, and connect and fix the crossbeam bracket to the second supporting member;
[0020] S9, installing the casting formwork on the beam bracket and casting the second beam, and performing curing and tensioning;
[0021] S10, completing the construction of the remaining beams according to the above steps S5 to S9;
[0022] S11. After completing the construction of all beams, lower the beam brackets to the ground and disassemble them.
[0023] As an improvement of the above scheme: in step S1 and step S5, the first supporting member and the second supporting member are both corbel supports, and a corbel shear groove, a threaded reserved hole and a platform climbing cone are provided on the tower column; the construction platform is first installed through the platform climbing cone, and then the corbel support is installed in the corbel shear groove on the construction platform, and the corbel support is fixed to the tower column through a threaded steel connector that is compatible with the threaded reserved hole.
[0024] As an improvement of the above scheme: in the step S2, a unloading support is installed on the first supporting member, and the unloading support is used to adjust the installation elevation by configuring a pad; then, a plurality of bracket distribution beams are installed on the unloading support, and a support is formed at the end of the crossbeam bracket by the bracket distribution beam, and a baffle for positioning and limiting the crossbeam bracket is welded on the bracket distribution beam.
[0025] As an improvement of the above scheme: in step S3 and step S9, a template distribution beam and wooden planks are provided below the casting template, a plurality of template distribution beams are evenly spaced along the length direction of the beam bracket, the wooden planks are installed on the top of the template distribution beams, and bamboo plywood is laid between the wooden planks and the casting template.
[0026] As an improvement of the above scheme: in the step S7, the lifting equipment adopts a hydraulic jack, and the hydraulic jack is installed on the fixed plate for no-load debugging; the lifting rope adopts multiple steel strands, and when connecting the beam bracket and the hydraulic jack through the steel strands, the single steel strand is pre-tightened first, and then the whole bundle of steel strands is pre-tightened by the hydraulic jack.
[0027] The beneficial effects of the present invention are as follows: the present invention improves the construction method of the cross beams on the tower column, and only uses one cross beam bracket as a temporary support for the multiple cross beams during the construction of multiple cross beams, and starts the construction from the topmost cross beam. After the construction of the first cross beam at the top is completed, the cross beam bracket is hoisted to the construction height of the second cross beam as a whole, and all the cross beams are constructed in sequence from top to bottom; the present invention uses a common cross beam bracket in the construction of multiple cross beams on the tower column, and there is no need to repeatedly assemble and disassemble the cross beam bracket, thereby effectively reducing the time for installation and disassembly of the cross beam bracket itself, shortening the overall construction period of multiple cross beams while reducing the amount of high-altitude operations, effectively improving construction efficiency and improving construction safety. BRIEF DESCRIPTION OF THE DRAWINGS
[0028] Figure 1 It is a construction flow chart of the present invention;
[0029] Figure 2 It is a schematic diagram of the coordination structure between the first cross beam and the tower column during the construction process of the present invention;
[0030] Figure 3 It is an enlarged schematic diagram of the matching structure of the beam bracket and the tower column during the construction process of the present invention;
[0031] Figure 4 It is a schematic diagram of the coordination structure between the second cross beam and the tower column during the construction process of the present invention.
[0032] Markings in the figure are: 100-tower column, 200-crossbeam, 210-first crossbeam, 220-second crossbeam, 300-crossbeam bracket, 410-first supporting member, 420-second supporting member, 430-diagonal brace, 440-unloading support, 450-bracket distribution beam, 460-formwork distribution beam, 470-wooden square, 480-threaded steel connector, 500-lifting rope channel, 600-lifting equipment. DETAILED DESCRIPTION
[0033] In order to facilitate the understanding of the present invention, the present invention is further described below in conjunction with the accompanying drawings.
[0034] In the description of the present invention, it should be noted that the directions or positional relationships indicated by terms such as “front”, “rear”, “left”, “right”, “up”, “down”, and “inside” are based on the directions or positional relationships shown in the accompanying drawings and are only for the convenience of description. They do not indicate or imply that the device or component referred to must have a specific direction, be constructed and operated in a specific direction. Therefore, they cannot be understood as limitations on the present invention.
[0035] The present invention discloses a tower column cross beam construction method, which does not need to repeatedly disassemble and install the cross beam bracket 300, but uses the same cross beam bracket 300, and does not need to be disassembled after the cross beam bracket 300 is assembled. When constructing multiple cross beams 200 on the tower column 100, the construction sequence is from top to bottom. During the construction process, the same assembled cross beam bracket 300 is sequentially lowered to the installation height of each cross beam 200 as a pressure-bearing foundation for pouring each cross beam 200. Since the present invention saves the time of assembling and disassembling the cross beam bracket 300 multiple times during the construction process, it can effectively shorten the construction period, improve the construction efficiency, and effectively reduce the high-altitude operation time, thereby improving the safety of the construction.
[0036] Specifically, Figures 1 to 4 As shown, the tower column cross beam construction method disclosed in the present invention is constructed in accordance with the following steps in sequence:
[0037] S1, such as Figure 2 As shown, a first supporting member 410 for supporting the beam bracket 300 is installed at the installation position of the first beam 210 on the upper part of the tower column 100 .
[0038] During the construction of the tower column 100, shear grooves of the supporting components, reserved thread holes and platform climbing cones are embedded at the installation positions of each cross beam 200 to ensure accurate installation and straight hole passages. The shear grooves of the supporting components are used to install the supporting components that subsequently support the cross beam bracket 300. The reserved thread holes are used to cooperate with the threads of the subsequent threaded steel connectors 480 to achieve the fixation of the cross beam bracket 300. The platform climbing cone is used to fix the construction platform installed subsequently. In addition, a reinforcing steel mesh can be installed at the bottom of the shear grooves of the supporting components to increase the local bearing strength when the concrete is subsequently poured and vibrated at the bottom.
[0039] In this step S1, the first support member 410 adopts a corbel support, and correspondingly, the shear groove of the support member is set to a corbel shear groove whose shape is compatible with the corbel support; when installing the first support member 410, first install the construction platform through the platform climbing cone, and then the construction personnel install the corbel support in the corbel shear groove on the construction platform, and then insert the threaded steel connector 480 into the threaded reserved hole after passing through the connecting hole on the corbel support, and then tighten the threaded steel connector 480 to complete the fixation of the first support member 410 on the tower column 100.
[0040] S2. After assembling the crossbeam bracket 300 on the ground, hoist it as a whole to the first supporting member 410 and connect and fix it to the first supporting member 410.
[0041] In this step S2, when assembling the crossbeam bracket 300 on the ground, it is necessary to strictly control the size and inclination of each rod in the welding process to ensure accurate positioning during the installation of the transverse connection system; Figure 3 As shown, before hoisting the beam bracket 300, the unloading support 440 is first installed on the first supporting member 410, and the unloading support 440 is installed with a pad to strictly control the installation elevation and design elevation of the unloading support 440; after the unloading support 440 is installed, the bracket distribution beam 450 is installed on the unloading support 440, and multiple bracket distribution beams 450 are evenly spaced on the unloading support 440, so that the bracket distribution beam 450 can provide a stable support effect on the end of the beam bracket 300; the bracket distribution beam 450 can also be welded with a baffle plate, and the side span of the beam bracket 300 is positioned and limited by using an inverted triangle baffle plate. The beam bracket 300 is hoisted above the first supporting member 410, so that the two ends of the beam bracket 300 are respectively placed on the bracket distribution beams 450 on the two first supporting members 410, and the beam bracket 300 is connected and fixed with bolts.
[0042] S3. Install the casting template on the beam bracket 300.
[0043] In this step S3, the casting template is assembled with a bottom mold, a side mold and a fixed mold to form a space for casting and forming the first cross beam 210, and the side mold is fixed with multiple groups of tie rods and bolts. Figure 3 As shown, a template distribution beam 460 and a wooden plank 470 are laid under the bottom form of the casting template, multiple template distribution beams 460 are evenly spaced along the length direction of the beam bracket 300, the wooden plank 470 is installed on the top of the template distribution beam 460, and bamboo plywood is laid between the wooden plank 470 and the casting template.
[0044] S4, such as Figure 4 As shown, the first crossbeam 210 is cast, and is cured and tensioned. During the casting, a lifting rope channel 500 is reserved on the first crossbeam 210 and runs longitudinally through the first crossbeam 210. The lifting rope channel 500 serves as a channel for the lifting rope connecting the lifting device 600 and the crossbeam bracket 300 when the crossbeam bracket 300 is subsequently lifted. A fixing plate for the lifting device 600 is embedded on the top of the first crossbeam 210, and the lifting device 600 is installed on the fixing plate. After the lifting rope is connected to the lifting device 600, it passes downward through the lifting rope channel 500 and is then connected and fixed to the crossbeam bracket 300.
[0045] S5. Install the second supporting member 420 and the diagonal brace 430 for supporting the beam bracket 300 at the installation position of the second beam 220 located below the first beam 210 on the tower column 100 .
[0046] In this step S5, if Figure 4As shown, supporting member shear grooves, threaded reserved holes and platform climbing cones are pre-buried on the tower column 100, and the second supporting member 420 also adopts a corbel support, and the supporting member shear groove adopts a corresponding corbel shear groove; when installing the second supporting member 420, first install the construction platform through the platform climbing cone, and then the construction personnel install the corbel support in the corbel shear groove on the construction platform, and then insert the threaded steel connector 480 into the threaded reserved hole after passing through the connecting hole on the corbel support, and then tighten the threaded steel connector 480 to complete the fixation of the first supporting member 410 on the tower column 100; the diagonal brace 430 is configured with a connection system, and then the diagonal brace 430 is fixed to the second supporting member 420.
[0047] S6. Remove the casting formwork on the first crossbeam 210.
[0048] In this step S6, the casting formwork is removed after the strength of the cast first beam 210 reaches the designed strength. The casting formwork is hoisted and removed piece by piece using a tower crane. The tension rods of the side formwork in the casting formwork are released and the bolts are removed, and then the pieces are removed in sequence. Before removing the bottom formwork, the pads are cut off to lower the bottom distribution beam and the structure above, and the upper distribution beam is separated from the bamboo plywood. The bottom formwork is manually pried with a crowbar to separate the bottom of the formwork.
[0049] S7, such as Figure 4 As shown, a lifting device 600 is installed on the fixing plate on the top of the first crossbeam 210 , and the crossbeam bracket 300 is connected to the lifting device 600 by using a lifting rope passing through the lifting rope channel 500 .
[0050] In this step S7, a hydraulic jack is used as a lifting device 600, and multiple groups of hydraulic jacks are installed and fixed on the fixed plate pre-buried in the first beam 210. After the hydraulic jack, the fixed anchor and the detection device are installed on the fixed plate, no-load debugging is performed. The no-load debugging is used to ensure that the operation in the automatic tensioning process corresponds to the operation of the equipment; the lifting rope uses multiple groups of steel strands, and the multiple groups of steel strands that have been cut are passed through the fixed anchor, the hydraulic jack, the working anchor and the reserved holes on the beam from top to bottom in turn, and the fixed anchor is installed on the fixed anchor. A steel plate is added to the anchor end of the tool to increase the stress area of the anchor end and improve the safety factor, and then the clip of the fixed anchor is anchored to complete the fixation; after the steel strands are connected, they are pre-tightened, and each steel strand is pre-tightened by a single pre-tightening method, and then the whole bundle of steel strands is pre-tightened by a hydraulic jack, and the clip used for pre-tightening on the fixed anchor is removed, and the limit plate of the fixed anchor is installed; when the system is debugged normally and other structural inspections are completed and confirmed to be normal, a trial lift is carried out, and subsequent lowering work is carried out after the trial lift is successful.
[0051] S8. After removing the first supporting member 410 supporting the crossbeam bracket 300, lower the crossbeam bracket 300 to the installation location of the second crossbeam 220, and connect and fix the crossbeam bracket 300 to the second supporting member 420.
[0052] In this step S8, if Figure 4 As shown, the beam bracket 300 is first disassembled from the first supporting member 410, and then the first supporting member 410 is removed. After the beam bracket 300 is completely emptied, the hydraulic jack is controlled by the control system to synchronously and slowly lower the beam bracket 300, and the beam bracket 300 is lowered to the installed diagonal brace 430, and the beam bracket 300 is fixedly connected to the diagonal brace 430, and then the hydraulic jack is gradually relaxed until it is completely relaxed to complete the lowering of the beam bracket 300.
[0053] S9. Install a casting template on the beam bracket 300 and cast the second beam 220, and perform curing and tensioning.
[0054] This step S9 is the same as the above-mentioned step S3. The casting formwork is assembled with a bottom formwork, a side formwork and a fixed formwork to form a space for casting and forming the second beam 220. The side formwork is fixed with multiple sets of tie rods and bolts. The formwork distribution beams 460 and wooden beams 470 are laid under the bottom formwork of the casting formwork. The multiple formwork distribution beams 460 are evenly spaced along the length direction of the beam bracket 300. The wooden beams 470 are installed on the top of the formwork distribution beams 460, and bamboo plywood is laid between the wooden beams 470 and the casting formwork. After the casting formwork is assembled, the second beam 220 is cast and maintained and tensioned.
[0055] S10, if there are other beams 200 that need to be constructed, then complete the construction of the remaining beams 200 according to the above steps S5 to S9;
[0056] S11. After the construction of all beams 200 is completed, the beam bracket 300 is connected to the bottom form of the casting formwork and lowered to the ground as a whole, and the beam bracket 300 is disassembled on the ground to avoid high-altitude operations and reduce the construction safety risks that may exist in high-altitude operations.
Claims
1. Tower column beam construction method, Features: The construction method sequentially constructs each cross beam (200) on the tower column (100) from top to bottom, and during the construction process, the same cross beam bracket (300) is sequentially lowered as a pressure-bearing foundation for pouring each cross beam (200).
2. The tower column beam construction method according to claim 1, Features: The construction method comprises the following steps: S1. Installing a first supporting member (410) for supporting a beam bracket (300) at a location where a first beam (210) is installed on an upper portion of a tower column (100); S2, after assembling the crossbeam bracket (300) on the ground, hoisting the entire bracket to the first supporting member (410), and connecting and fixing the bracket to the first supporting member (410); S3, installing a casting template on the beam bracket (300); S4, casting the first crossbeam (210), and performing curing and tensioning. During casting, a rope channel (500) is reserved on the first crossbeam (210) to longitudinally penetrate the first crossbeam (210), and a fixing plate of a lifting device (600) is embedded on the top of the first crossbeam (210); S5. Installing a second supporting member (420) and a diagonal brace (430) for supporting the crossbeam bracket (300) at the installation position of the second crossbeam (220) located below the first crossbeam (210) on the tower column (100); S6, removing the casting formwork on the first crossbeam (210); S7, installing a lifting device (600) on the fixing plate on the top of the first crossbeam (210), and connecting the crossbeam bracket (300) to the lifting device (600) using a lifting rope passing through the lifting rope channel (500); S8, after removing the first supporting member (410) supporting the crossbeam bracket (300), lower the crossbeam bracket (300) to the installation location of the second crossbeam (220), and connect and fix the crossbeam bracket (300) to the second supporting member (420); S9, installing a casting template on the beam bracket (300) and casting the second beam (220), and performing curing and tensioning; S10, completing the construction of the remaining beams (200) according to the above steps S5 to S9; S11. After the construction of all beams (200) is completed, the beam bracket (300) is lowered to the ground and disassembled.
3. The tower column cross beam construction method as claimed in claim 1, Features: In step S1 and step S5, the first support member (410) and the second support member (420) are both corbel support members, and a corbel shear groove, a threaded reserved hole and a platform climbing cone are provided on the tower column (100); the construction platform is first installed through the platform climbing cone, and then the corbel support member is installed in the corbel shear groove on the construction platform, and the corbel support member is fixed to the tower column (100) through a threaded steel connector (480) adapted to the threaded reserved hole.
4. The tower column beam construction method according to claim 1, Features: In the step S2, a discharging support (440) is installed on the first supporting member (410), and the discharging support (440) is configured with a pad to adjust the installation elevation; then, a plurality of bracket distribution beams (450) are installed on the discharging support (440), and the bracket distribution beams (450) are used to form a support at the end of the beam bracket (300), and a baffle for positioning and limiting the beam bracket (300) is welded on the bracket distribution beam (450).
5. The tower column cross beam construction method according to claim 1, Features: In step S3 and step S9, a template distribution beam (460) and a wooden beam (470) are provided below the casting template, a plurality of template distribution beams (460) are evenly spaced along the length direction of the crossbeam bracket (300), the wooden beam (470) is installed on the top of the template distribution beam (460), and a bamboo plywood is laid between the wooden beam (470) and the casting template.
6. The tower column cross beam construction method according to claim 1, Features: In step S7, the lifting equipment (600) uses a hydraulic jack, and no-load debugging is performed after the hydraulic jack is installed on the fixed plate; the lifting rope uses a plurality of steel strands, and when the crossbeam bracket (300) and the hydraulic jack are connected by the steel strands, a single steel strand is pre-tightened first, and then the entire bundle of steel strands is pre-tightened by the hydraulic jack.
Citation Information
Patent Citations
Cast-in-place support structure for ultrahigh main tower cross beam of cable-stayed bridge and construction method
CN116716813A
Bridge main tower cross beam construction method