Construction method for tower crane foundation in deep and thick mucky layer
By combining prestressed pipe piles, reinforced concrete caps, steel sheet piles and steel purlins in the tower crane foundation, the problem of tower crane rotation torsion and pull-out force under the geological conditions of deep silt layers is solved, and the strength of the tower crane foundation is improved. Stability and load carrying capacity.
Patent Information
- Application Number
- CN202410784124.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-06-18
- Publication Date
- 2024-10-11
AI Technical Summary
Under geological conditions involving deep silt layers such as seawalls, the rotational torsion and pull-out force generated during tower crane construction cannot be effectively resisted by the existing enlarged foundation or pile foundation, affecting construction safety.
A composite foundation treatment method of prestressed pipe piles, reinforced concrete caps, steel sheet piles and steel purlins is used to evenly distribute the tower crane load through the reinforced concrete caps. The prestressed pipe piles transmit vertical force to the granite layer, and the steel sheet piles and The I-beam purlin reinforcement forms an overall vertical foundation to improve bending resistance, torsion resistance and shear resistance.
It effectively improves the stability of the tower crane foundation, enhances the bearing capacity of rotational torque and pull-out force, and ensures construction safety.
Smart Images

Figure CN118756745A_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the technical field of slope engineering, and in particular to a method for constructing a tower crane foundation in a thick muddy layer. Background Art
[0002] When constructing under geological conditions involving deep silt layers such as seawalls, the tower crane will generate rotational torque when operating. Therefore, the tower crane using only an expanded foundation or pile foundation or even a combination of the two cannot resist the torque and pull-out force of the tower crane's rotation, and cannot guarantee the safety of the tower crane's operation during construction. Summary of the invention
[0003] In view of this, the present application provides a tower crane foundation construction method in a deep muddy layer, which solves the technical problem in the prior art that when constructing under geological conditions involving deep muddy layers such as seawalls, the torque and pull-out force generated by the rotation of the tower crane affects the safety of the tower crane construction.
[0004] The present application provides a method for constructing a tower crane foundation in a deep muddy layer, which includes the following construction steps: step 100, measuring and laying out, using GPS positioning to set the layout points of prestressed pipe piles, reinforced concrete pedestal edges and steel sheet pile outer edges in the construction area; step 200, prestressed pipe pile construction, using a hydraulic environmentally friendly hammer to construct the prestressed pipe piles according to the layout points in S100; step 300, reinforced concrete pedestal construction, demarcating a designated area according to the layout results in S100, leveling the foundation of the demarcated area, and pouring a layer of concrete after the leveling is completed. After the soil cushion, steel bar binding and formwork installation are completed, the tower crane embedded parts are installed, and after the installation is completed, the reinforced concrete cap is poured; step 400, steel sheet pile construction, steel sheet pile driving construction is carried out according to the outer edge of the steel sheet pile. Before the pile driving construction, the exact position of each pile is determined according to the layout edge line at an interval of 60mm; step 500, setting steel purlins, setting a circle of I-beam purlins around the steel sheet piles, and using steel purlins to reinforce the position 1m below the bottom of the steel sheet piles; step 600, filling stone powder and injecting cement slurry, the gap between the steel sheet pile and the reinforced concrete cap is filled with stone powder, and cement slurry is injected after the filling is completed.
[0005] In one embodiment, in step 400, the steel sheet piles are SP-IV steel sheet piles, and the length of a single steel sheet pile is 18 m and the depth of the steel sheet pile is 15 m underground.
[0006] In one embodiment, in step 400, the steel sheet pile construction machine is a vibrating pile driver.
[0007] In one embodiment, in step 400, after the exact position of each pile is determined, a pile driver is used to drive the steel sheet pile laterally, a pile is pulled under the pile driver, a hydraulic press is started, the steel sheet pile is clamped, and the lifting hammer is moved to the piling location.
[0008] In one embodiment, in step 400, the locking mouth of the steel sheet pile and the positioning pile are aligned, and the steel sheet pile is pressed to the position where the pile is to be driven by the vibrating hammer and its own weight. The steel sheet pile is driven downward by the inertia and vibration force of the vibrating hammer, and the vibrating hammer is started to drive the pile down. When driving the steel sheet pile, the pile is kept flat from the first piece. After several pieces are driven, one piece is driven deep to maintain stability, and then the driving is continued. During the driving process, the inclination is measured at any time and the pile body is kept vertical.
[0009] In one embodiment, in step 400, when the steel sheet pile is 20 cm to 40 cm before the designed height, the vibratory hammer stops vibrating, and the vibratory hammer continues to rotate for a certain period of time due to inertia, and the pile is driven to the designed height. The hydraulic clamp is released, the hammer rises, and the second pile is driven.
[0010] In one embodiment, in step 500, after the steel sheet piles are injected, the steel corbels and steel purlins are welded, the connection parts between the steel sheet piles and the steel purlins are fully welded, the contact parts between the steel corbels and the supporting steel plates are fully welded, the supporting steel plates are arranged on the steel sheet piles and fully welded, the top of the reinforced concrete pedestal is consistent with the top of the steel sheet piles, and the bottom of the steel purlin is consistent with the bottom of the reinforced concrete pedestal.
[0011] In one embodiment, the steel purlin is an I32b I-beam purlin.
[0012] In one embodiment, in step 600, after the steel purlin is set, stone powder is filled in the gap between the steel sheet pile and the reinforced concrete cap, and compaction treatment is performed after the stone powder is filled.
[0013] In one embodiment, in step 600, after the stone powder is filled and compacted, cement slurry is poured into the gap between the steel sheet pile and the reinforced concrete cap.
[0014] In one embodiment, step 200 includes: S201, placing piles, placing piles according to the layout points of prestressed pipe piles, and marking the center of the pile position with steel bars or bamboo sticks; S202, sinking piles, using pile caps and elastic pads to ease piling; S203, connecting piles, using mechanical threaded joints to tighten and connect the upper and lower pile sections to connect the piles; S204, delivering piles, using a pile delivery device to deliver piles.
[0015] In one embodiment, during the pile placement process S201, a check is performed after the pile driver is in place but before the pile is officially sunk, and the positioning deviation of the prestressed pipe pile is less than 20 mm.
[0016] In one embodiment, during the piling process S202, the pile driving is performed after the verticality of the pile body, pile frame and pile hammer are consistent.
[0017] In one embodiment, during the pile sinking process in S203, when the precast pile body sinks to the hard soil layer, the drop hammer height is less than 0.6 m.
[0018] In one embodiment, during the pile delivery process in S205, the verticality deviation of the prestressed pipe pile body is 1%, and the verticality deviation of the first section of the prestressed pipe pile body is 0.5%.
[0019] In one embodiment, the step 300 includes: S301, steel bar binding, which is performed by combining binding connection with welding connection; S302, tower crane embedded parts installation, which is performed after the steel bar binding is completed.
[0020] In one embodiment, in S302, an insert vibrator is inserted into the concrete for vibration. When vibrating the upper layer of concrete, it should be inserted 5-10 cm into the lower layer of concrete to ensure that the two layers of concrete are firmly combined. The correction is completed before the initial setting of the concrete, and the formwork is removed after waiting for 24 hours to carry out concrete curing.
[0021] The present application provides a method for constructing a tower crane foundation in a deep muddy layer, the method comprising the following construction steps: step 100, surveying and laying out, using GPS positioning to set the layout points of prestressed pipe piles, reinforced concrete pedestal edges and steel sheet pile outer edges in the construction area; step 200, prestressed pipe pile construction, using a hydraulic environmentally friendly hammer to construct the prestressed pipe piles according to the layout points in S100; step 300, reinforced concrete pedestal construction, demarcating a designated area according to the layout results in S100, leveling the foundation of the demarcated area, pouring a layer of concrete cushion after the leveling is completed, installing the tower crane embedded parts after the steel bar binding and template installation, and pouring the reinforced concrete pedestal after the installation is completed; step 400, steel sheet pile construction, performing steel sheet pile driving construction according to the outer edges of the steel sheet piles; step 500, setting steel purlins, surrounding the steel sheet piles A circle of I-beam purlins is set; step 600, stone powder is filled and cement slurry is injected, the gap between the steel sheet pile and the reinforced concrete pedestal is filled with stone powder, and cement slurry is injected after the filling is completed. The present application is a composite tower crane foundation treatment method of prestressed pipe piles + reinforced concrete pedestal + steel sheet piles combined with steel purlin enclosure reinforcement + stone powder pouring cement slurry filling reinforcement, the load of the tower crane is evenly distributed to the prestressed pipe piles below through the reinforced concrete pedestal, and the vertical force is evenly transmitted to the lower granite layer through the prestressed pipe piles. At the same time, a circle of 18m long steel sheet piles is closed and driven around the reinforced concrete pedestal and I-beam purlins are set, and cement slurry and stone powder are filled between the steel sheet piles and the pipe piles, so that an integral vertical foundation is formed below the pedestal, which not only improves the vertical bearing capacity, but also improves the foundation's bending resistance, torsion resistance, and shear resistance, and effectively improves the stability of the tower crane foundation. BRIEF DESCRIPTION OF THE DRAWINGS
[0022] Figure 1The figure is a schematic diagram of the process of a tower crane foundation construction method in a thick muddy layer provided by an embodiment of the present application;
[0023] Figure 2 The figure is a schematic diagram of the overall process of a tower crane foundation construction method for a deep muddy layer provided by an embodiment of the present application;
[0024] Figure 3 The figure shows a plan view of a tower crane foundation construction structure in a thick muddy layer provided by an embodiment of the present application;
[0025] Figure 4 The figure shows a cross-sectional view of a tower crane foundation construction structure in a deep muddy layer provided by an embodiment of the present application;
[0026] Figure 5 The figure shows a schematic diagram of welding the supporting steel plate and the steel bracket for the construction of a tower crane foundation in a deep muddy layer provided by an embodiment of the present application;
[0027] Figure 6 The figure shows a schematic diagram of welding between steel brackets for tower crane foundation construction in a deep muddy layer provided by an embodiment of the present application;
[0028] Figure 7 Shown is a schematic diagram of the reinforcement binding of the tower crane cap in a tower crane foundation construction method in a deep muddy layer provided by an embodiment of the present application.
[0029] Description of reference numerals:
[0030] 1. Steel sheet piles; 2. Steel purlins; 3. Grouting stone powder; 4. Prestressed pipe piles; 5. Reinforced concrete cap; 6. Steel corbels; 7. Supporting steel plates; 8. First steel bars; 9. Second steel bars. DETAILED DESCRIPTION
[0031] In the description of the application, the meaning of "multiple" is at least two, for example, two, three, etc., unless otherwise clearly and specifically limited. In the embodiment of the present application, all directional indications (such as up, down, left, right, front, back, top, bottom ...) are only used to explain the relative position relationship, motion conditions, etc. between the components under a certain specific posture (as shown in the drawings). If the specific posture changes, the directional indication also changes accordingly. In addition, the terms "including" and "having" and any of their deformations are intended to cover non-exclusive inclusions. For example, the process, method, system, product or equipment comprising a series of steps or units are not limited to the steps or units listed, but optionally also include the steps or units not listed, or optionally also include other steps or units inherent to these processes, methods, products or equipment.
[0032] In addition, the reference to "embodiment" herein means that a particular feature, structure, or characteristic described in conjunction with the embodiment may be included in at least one embodiment of the present application. The appearance of the phrase in various locations in the specification does not necessarily refer to the same embodiment, nor is it an independent or alternative embodiment that is mutually exclusive with other embodiments. It is explicitly and implicitly understood by those skilled in the art that the embodiments described herein may be combined with other embodiments.
[0033] The following will be combined with the drawings in the embodiments of the present application to clearly and completely describe the technical solutions in the embodiments of the present application. Obviously, the described embodiments are only part of the embodiments of the present application, not all of the embodiments. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of this application.
[0034] The Qianwu Dayong Sluice Gate Project is located at Dayongkou of Jitiming Waterway, Qianwu Town, Doumen District, Zhuhai City. The geological conditions are as follows (the silt thickness below the sluice gate foundation surface is 12.0 to 16.0 m; the silty soil thickness is 0.0 to 7.0 m, which is distributed in a lens shape near the right borehole CZK09; the silty clay thickness is 9.2 to 13.6 m; the gravel sand thickness is 4.5 to 13.6 m; the residual soil thickness is 3.5 to 15.5 m; the granite top surface elevation is -43.68 to -53.18 m, and the upper strongly weathered layer thickness is 0.0 to 2.2 m). Under the existing geological conditions, due to the rotational torque generated during the operation of the tower crane, the tower crane can not resist the torque and pull-out force of the tower crane rotation by only using the expanded foundation or pile foundation or even the combination of the two, and cannot ensure the safety of the tower crane operation.
[0035] Figure 1 The figure is a schematic diagram of the process of a tower crane foundation construction method in a thick muddy layer provided by an embodiment of the present application; Figure 2 The figure is a schematic diagram of the overall process of a tower crane foundation construction method for a deep muddy layer provided by an embodiment of the present application; Figure 3 The figure shows a plan view of a tower crane foundation construction structure in a thick muddy layer provided by an embodiment of the present application; Figure 4 FIG. 1 is a cross-sectional view of a tower crane foundation construction structure in a deep muddy layer provided by an embodiment of the present application; Figure 1-Figure 4 As shown, the present application provides a method for constructing a tower crane foundation in a deep muddy layer, the method comprising the following construction steps:
[0036] Step 100: Measure and lay out
[0037] In the construction area, GPS positioning is used to set the layout points of the prestressed pipe piles, the edge lines of the reinforced concrete pedestal 5 and the outer edge lines of the steel sheet pile 1. The scope and floor area of the composite tower crane foundation pedestal are determined through layout, and the center point of the prestressed pipe pile 4, the vertical and horizontal edge lines of the foundation, the center line and the temporary leveling base point are measured. The edge piles are laid out and marked. The marks should be eye-catching and they should be pulled around with thin lines. Construction can only be carried out after verification.
[0038] Step 200: Prestressed pipe pile construction
[0039] Prestressed pipe piles are constructed using a hydraulic environmentally friendly hammer according to the layout points.
[0040] 201. Piling
[0041] According to the control points and the pile position layout diagram of the prestressed pipe pile 4, the pile position is measured and placed. Prestressed pipe piles are placed in the center and around the pile position. The center of the pile position is marked with steel bars or bamboo sticks. The prestressed pipe pile 4 uses PHC-400AB95 high-strength prestressed concrete pipe piles. In order to prevent the pile driver from being displaced by the weight of the pile driver when it is in place, the pile driver is checked before the pile driver is officially sunk to ensure that the position of the pile driver is correct and the positioning deviation of the prestressed pipe pile 4 is controlled within 20mm. The pile is embedded in the two guide columns of the pile frame with the guide sliding clamp or pile hoop of the pile frame, vertically aligned with the center of the pile, and slowly lowered into the soil. At this time, the pile support is used to correct the position and verticality of the pile. After the position and verticality of the prestressed pipe pile are corrected, the hammer and the pile cap can be pressed on the pile. At the same time, a ruler is set on the side of the pile or on the frame, and records are made.
[0042] 202. Piling
[0043] The prestressed pipe piles 4 penetrate into the slightly weathered rock layer, about 45 meters from the ground, so the prestressed pipe piles 4 at each position are longitudinally connected by multiple prestressed pipe piles 4 to form an integral prestressed pipe pile 4. Before starting to pile, check whether the pile heads of every two longitudinal prestressed pipe piles 4 joints are flat. If the pile heads are uneven, use sacks or thick cardboard to pad them flat, or use epoxy mortar to smooth them first. After the pile heads are flat, start piling. When piling, lightly press or lightly hit the hammer several times. After observing that the verticality of the pile body, pile frame, pile hammer, etc. is consistent, you can turn to normal driving. When starting to pile, the drop distance should be small. After a certain depth into the ground and the pile is stable, drive according to the required drop distance.
[0044] 203. Pile Driving
[0045] The pile head of the top prestressed pipe pile 4 adopts a pile cap suitable for the pile head size, and the pile cap is made of cast steel or steel plate. The pile bottom of the bottom prestressed pipe pile 4 adopts a steel pile shoe. The joints of the two prestressed pipe piles 4 are connected by bolts and welding, and elastic pads are set at the joints. The elastic pads are used to ease the impact during pile driving to make the pile driving stress evenly distributed, and extend the duration of the impact to facilitate the penetration of the pile. The hammer pad is mostly made of hardwood or white palm rope coils, and the pile pad is mostly made of pine wood, paper pads, phenolic laminated plastics, synthetic rubber, etc. The surface of the pile cap in contact with the pile must be flat and should be in the same straight line with the pile body to avoid deflection during pile driving.
[0046] If the pile hammer itself is capped, it is only necessary to protect the top of the pile with a rope pad or a wooden block. During the pile sinking process, always pay attention to whether the pile body is displaced or tilted. If any problem is found, it should be corrected in time. When the pile is sunk to the required depth or reaches the hard soil layer, the height of the hammer drop should generally not be greater than 0.6m to avoid damaging the pile head. During the pile sinking process, keep a record of the pile sinking construction. When it is close to the design requirements, the penetration depth or the earth elevation can be observed until it reaches the design elevation requirements. Then move the pile driver to the new pile position. During the pile sinking construction, control the verticality below 0.5%.
[0047] 204. Connecting piles
[0048] Pipe piles are connected by threaded joints, and the gaps between them should be filled with asphalt fillers for corrosion prevention. Before connecting the piles, check the dimensional deviations and connectors at both ends of the piles. Lifting and construction can be carried out only after they are found to be undamaged. The pile head of the lower pile section should be 0.8m-1.0m above the ground. When connecting the piles, after removing the protective devices at both ends of the upper and lower piles, the joint residues should be cleaned, and the special joint taper should be used for centering. After aligning the upper and lower piles, tighten the connection and use a special chain wrench to tighten. After locking, there should still be a gap of 1mm-2mm between the two end plates. After the pile connection is completed, the butt pile part should be well protected against corrosion before pile sinking.
[0049] 205, Delivery
[0050] A pile driver must be used when delivering piles, and a pin-type pile driver can be used. When delivering piles with a pile delivery rod, the pile delivery depth should be calculated according to the design requirements, and a conspicuous mark should be made on the pile delivery rod or the frame. When the pile is delivered to the design elevation and there is about 1m left, the surveyor instructs the pile driver to reduce the speed and track and observe the pile delivery until the pile is delivered to the design elevation or the bearing layer. If there is any abnormality during the pile delivery process, the pile delivery should be stopped and reported to the supervision unit in time so that timely measures can be taken. The allowable deviation of the verticality of the prefabricated pipe pile body is 1%, and the allowable deviation of the verticality of the first section of the prefabricated pipe pile body is 0.5%. The holes left by the pile delivery should be covered with square wood and bamboo plywood to prevent objects and people from falling, and should be backfilled in time to avoid machine sinking.
[0051] The control standard for ending pile delivery and hammering is to lift the hammer to a height of 40cm. Based on the geological bearing capacity calculation results, each pile has a bearing capacity of 1000 kN. The penetration depth of the last ten hits is controlled below 4cm before hammering.
[0052] Step 300: Construction of reinforced concrete foundation
[0053] 301. Steel bar binding
[0054] Figure 7 The following is a schematic diagram of the reinforcement binding of the tower crane cap according to the method for constructing a tower crane foundation in a deep muddy layer provided by an embodiment of the present application. Before the construction of the reinforced concrete cap, a designated area is marked out according to the results of the survey and layout, and the foundation is leveled. After the leveling is completed, a 10 cm thick concrete C15 cushion layer is poured, such as Figure 7 As shown, the first steel bar 8 is HRB40025Φ with a tying spacing of 20 cm, and the second steel bar 9 is HRB40012Φ with a tying spacing of 40 cm. The steel bar tying adopts a combination of tying connection and welding connection, and arc welding is adopted. The total length of the weld should be no less than 8d (eight times the diameter of the steel bar).
[0055] 302. Installation of embedded parts of tower crane
[0056] After the reinforcement is tied, the tower crane embedded parts are installed. After measuring and laying out, the template is positioned. After verification, the template is installed and reinforced. When mixing the concrete cap, C50 concrete is selected, and an early strength agent is added to the concrete. The early strength agent is selected to be 3 days early strength. The addition of the early strength agent further improves the strength of the cap. When pouring components with concrete mixed by a concrete mixer, the bubbles must be removed and compacted to make the concrete densely combined, eliminate the honeycomb surface of the concrete, improve its strength, and ensure the quality of the concrete components. The concrete vibrator is a machine for mechanized compaction of concrete. When pouring concrete, it should be carried out in layers and continuously. Use an inserted vibrator to insert quickly and dial slowly, arrange the insertion points evenly, and move point by point to achieve uniform compaction. When working, the vibration head of the inserted vibrator is inserted into the concrete, and its vibration wave is directly transmitted to the concrete. The moving spacing is not greater than 30-40 of the depth of the vibrating rod. When vibrating the upper layer of concrete, it should be inserted into the lower layer of concrete by 5-10cm to ensure that the two layers of concrete are firmly combined. During vibration, the vibrating rod must not touch the steel bars and formwork. The moving distance of the flat plate vibrator should ensure that the plate of the vibrator covers the edge of the compacted part. When laying concrete, the formwork, steel bars, embedded parts, etc. should be frequently observed for movement, deformation or blockage. If any problems are found, they should be dealt with immediately and corrected before the poured concrete begins to set. Wait 24 hours before removing the formwork for concrete curing. At the same time, make monitoring signs at the tower crane embedded parts and observe their stability for several days.
[0057] Step 400: Steel sheet pile construction
[0058] Steel sheet pile construction is carried out according to the measured and placed steel sheet pile edge line. The steel sheet pile construction machine mainly adopts the vibrating pile driver. Before the pile driving construction, the accurate position of each pile should be determined according to the measured edge line and the interval of 60mm. When driving steel sheet piles, the pile driver is required to work sideways to facilitate the observation of the surveying personnel. The hammer is lowered, the hydraulic port is opened, a pile is pulled under the pile driver, the lock port is smeared with lubricating oil, and the hammer is started.
[0059] The steel sheet piles are SP-Ⅳ steel sheet piles. The length of a single steel sheet pile is 18.0m. The steel sheet piles are Larsen type and penetrate 15m underground. The steel purlin is used to reinforce the steel sheet pile 1m below the bottom. The internal gaps are filled with stone powder and cement slurry. When the tip of the Larsen steel sheet pile is 30cm away from the ground, stop rising, adjust the pile driver so that the pile is in the clamp, start the hydraulic press, clamp the pile, and move the rising hammer and the steel sheet pile to the piling site.
[0060] When inserting steel sheet piles, if the insertion speed is slow, you can apply butter mixture ointment inside the lock mouth of the single pile to reduce the friction resistance during insertion. When inserting Larsen steel sheet piles, you should keep it flat from the first piece. After several pieces are inserted, insert a deep piece to keep stability, and then continue to insert. During the insertion process, measure the inclination at any time. If there is any inclination, adjust it in time. To ensure the smooth closure of the piles, the pile body must be kept vertical. During the entire steel sheet pile insertion process, it must be ensured that the piles are closed tightly to prevent the occurrence of disengagement and affect the overall stability.
[0061] Align the locking joints of the steel sheet pile and the positioning pile, and use the vibrating hammer and the pile's own weight to press the pile to the position where it will be driven.
[0062] Use the inertia, deadweight and vibration force of the vibratory hammer to insert the steel sheet pile, start the vibratory hammer to drive the pile down, control the speed of the pile hammer's descent, and keep the pile as vertical as possible so that the lock can bite smoothly and improve the overall stability.
[0063] When the steel sheet pile reaches 20cm to 40cm before the designed height, the vibration is stopped. The vibrating hammer continues to rotate for a certain period of time due to inertia. The pile is driven to the designed height. The hydraulic clamp is released, the hammer rises, and the second pile is driven. This process is repeated until all the steel sheet piles are driven.
[0064] Step 500: Setting steel purlins
[0065] Figure 5 FIG. 1 is a schematic diagram of welding support steel plates and steel brackets for tower crane foundation construction in a deep muddy layer provided by an embodiment of the present application; Figure 5As shown, after the steel sheet pile 1 is injected, the steel corbel 6 (20 mm thick, Q235) and the steel purlin 2 are welded. The steel purlin 2 adopts I32b I-beam purlin. The connecting parts of the steel sheet pile 1 and the steel purlin 2 are fully welded, and the contact parts of the steel corbel 6 and the supporting steel plate 7 are fully welded. The supporting steel plate 7 is set on the steel sheet pile 1 and fully welded. The top of the reinforced concrete pedestal 5 is consistent with the top of the steel sheet pile 1, and the bottom of the steel purlin 2 is consistent with the bottom of the reinforced concrete pedestal 5.
[0066] Step 600: Filling with stone powder and injecting cement slurry:
[0067] After the steel purlin 2 is set, the gap between the steel sheet pile 1 and the reinforced concrete cap 5 is backfilled with grouting stone powder 3. First, the stone powder is filled in the gap between the steel sheet pile 1 and the reinforced concrete cap 5. After the stone powder is filled, it is compacted and then cement slurry is injected for grouting.
[0068] This application adopts a composite tower crane foundation treatment method of prestressed pipe piles + reinforced concrete pedestal + steel sheet piles combined with steel purlin enclosure reinforcement + stone powder pouring cement slurry filling reinforcement. The steel sheet pile 1 is 18m long and 15m deep underground. The steel purlin 2 is used to reinforce the position 1m below the bottom of the steel sheet pile, and the internal gap is filled with stone powder and cement slurry. The load of the tower crane is evenly distributed to the prestressed pipe piles 4 below through the reinforced concrete pedestal 5, and the vertical force is evenly transmitted to the lower granite layer through the prestressed pipe piles 4. At the same time, a circle of 18m long steel sheet piles is closed around the reinforced concrete pedestal 5 and an I-beam purlin is set, and cement slurry and stone powder are filled between the steel sheet piles 1 and the prestressed pipe piles 4, so that an integral vertical foundation is formed below the pedestal, which not only improves the vertical bearing capacity, but also improves the foundation's bending resistance, torsion resistance, and shear resistance, effectively improving the stability of the tower crane foundation.
[0069] The above description is only a preferred embodiment of the present application and is not intended to limit the present application. Any modifications, equivalent substitutions, etc. made within the spirit and principles of the present application shall be included in the protection scope of the present application.
Claims
1. A tower crane foundation construction method in a thick muddy layer, characterized in that: The construction steps include: Step 100, measuring and setting out, using GPS positioning to set out points for prestressed pipe piles, reinforced concrete cap edge lines, and steel sheet pile outer edge lines in the construction area; Step 200, prestressed pipe pile construction, using a hydraulic environmental protection hammer to construct the prestressed pipe pile according to the layout points in S100; Step 300, reinforced concrete cap construction, demarcate the designated area according to the layout result in S100, level the foundation of the demarcated area, pour a layer of concrete cushion after the leveling is completed, install the tower crane embedded parts after the steel bar binding and template installation, and pour the reinforced concrete cap after the installation is completed; Step 400, steel sheet pile construction, steel sheet pile driving construction is carried out according to the outer edge of the steel sheet pile. Before the piling construction, the exact position of each pile is determined according to the setout edge at 60mm intervals; Step 500: Set a steel perimeter purlin. Set a circle of I-beam perimeter purlins around the steel sheet piles. Use steel perimeter purlins to reinforce the position 1m below the bottom of the steel sheet piles. Step 600, filling with stone powder and injecting cement slurry, the gap between the steel sheet pile and the reinforced concrete cap is filled with stone powder, and cement slurry is injected after the filling is completed.
2. The tower crane foundation construction method in thick muddy layer according to claim 1 is characterized in that: In step 400, the steel sheet piles are SP-IV steel sheet piles, and the length of a single steel sheet pile is 18 m and the depth is 15 m underground.
3. The tower crane foundation construction method in thick muddy layer according to claim 2 is characterized in that: In step 400, the construction machine for the steel sheet piles is a vibrating pile driver.
4. The tower crane foundation construction method in thick muddy layer according to claim 3 is characterized in that: In step 400, after the accurate position of each pile is determined, a pile is pulled under the pile driver, the hydraulic press is started, the steel sheet pile is clamped, and the lifting hammer is moved to the piling location.
5. The tower crane foundation construction method in thick muddy layer according to claim 4 is characterized in that: In step 400, the locking mouth of the steel sheet pile and the positioning pile is aligned, and the steel sheet pile is pressed to the position where the pile is to be driven by the vibrating hammer and its own weight. The steel sheet pile is driven downward by the inertia and vibration force of the vibrating hammer, and the vibrating hammer is started to drive the pile downward. When driving the steel sheet pile, the pile is kept flat from the first piece. After several pieces are driven, one piece is driven deep to maintain stability, and then the driving is continued. During the driving process, the inclination is measured at any time and the pile body is kept vertical.
6. The tower crane foundation construction method in thick muddy layer according to claim 5 is characterized in that: In step 400, when the steel sheet pile is 20 cm to 40 cm before the designed height, the vibration hammer stops vibrating, and the vibration hammer continues to rotate for a certain period of time due to inertia, and the pile is driven to the designed height. The hydraulic clamp is released, the hammer rises, and the second pile is driven.
7. The tower crane foundation construction method in thick muddy layer according to claim 6 is characterized in that: In step 500, after the steel sheet piles are injected, the steel corbels and steel purlins are welded, the connection parts between the steel sheet piles and the steel purlins are fully welded, the contact parts between the steel corbels and the supporting steel plates are fully welded, the supporting steel plates are fully welded on the steel sheet piles, the top of the reinforced concrete pedestal is consistent with the top of the steel sheet piles, and the bottom of the steel purlin is consistent with the bottom of the reinforced concrete pedestal.
8. The tower crane foundation construction method in thick muddy layer according to claim 7 is characterized in that: The steel purlin adopts I32b I-beam purlin.
9. The tower crane foundation construction method in thick muddy layer according to claim 8, characterized in that: In step 600, after the steel purlin is set, stone powder is filled in the gap between the steel sheet pile and the reinforced concrete cap, and compaction treatment is performed after the stone powder is filled.
10. The tower crane foundation construction method in thick muddy layer according to claim 9, characterized in that: In step 600, after the stone powder is filled and compacted, cement slurry is poured into the gap between the steel sheet pile and the reinforced concrete cap.