Installation and construction method of steel structure riding track

By assembling the steel structure on the ground within the roof frame and using a winch and boom system to lift the steel structure bridleway, the problems of low installation efficiency and high risk in the existing technology are solved, efficient and safe bridleway installation is achieved, and construction costs are reduced.

CN118756935APending Publication Date: 2024-10-11中交四航局第六工程有限公司 +1

Patent Information

Application Number
CN202410984910.1
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-22
Publication Date
2024-10-11

AI Technical Summary

Technical Problem

The existing steel structure horse track installation and construction methods are inefficient and high-risk, especially in irregular-shaped venues, which require multiple hoisting and high-altitude operations, resulting in insufficient construction efficiency and safety.

Method used

A steel structure horse track installation and construction method is adopted. The curved horse track is first assembled on the ground within the roof frame, and the entire horse track is lifted to the preset position through the winch and boom system to reduce the amount of high-altitude work and utilize the existing operating platform. Connect and weld to avoid erecting additional aerial work platforms.

Benefits of technology

It improves the installation efficiency of the horse track, reduces the risks and construction costs of high-altitude operations, ensures the stability and reliability of the horse track, and reduces the construction cost.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118756935A_ABST
    Figure CN118756935A_ABST
Patent Text Reader

Abstract

The invention discloses an installation and construction method of a steel structure riding track, which can integrally lift the riding track indoors, is beneficial to reducing the indoor overhead working amount and reducing the construction risk, does not need to erect a large number of brackets in the construction process, effectively improves the construction efficiency and greatly reduces the construction cost. The installation construction method comprises the steps that an arc-shaped riding track is assembled and divided, a section of first riding track and two sections of second riding track are formed, a first lifting rod is installed, a lifting device is arranged, the first riding track is lifted after the lifting device is connected with the first riding track, and the two ends of the first riding track are welded to the bottom of the first lifting rod; the first riding track is in a hoisting state, two first safety ropes are arranged in the height direction of the first suspender, a second safety rope is arranged at the position, close to the middle, of the first riding track, the second suspender is connected, and the first riding track is repeatedly installed in the direction from the west side to the east side of the roof frame.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of building engineering, and in particular to an installation and construction method of a steel structure horseway. Background Art

[0002] Steel structure bridleway is a kind of safe and convenient passage for maintenance workers. It is mainly used for equipment inspection, maintenance and upkeep. In some construction occasions, steel structure bridleway can also be used as temporary scaffolding, temporary bridge and other platform facilities to provide a safe passage and working platform for construction workers. In the structure of some large venues (such as gymnasiums, exhibition halls, theaters, etc.), stage machinery facilities, lighting equipment, pipelines, controllers and other equipment are usually arranged on the top of the venue to meet the use needs of the venue. These equipment are usually supported by steel structure bridleway. For the purpose of aesthetic effect and architectural mechanics function, the venue is usually set in an irregular shape. For irregular shaped venues, how to set up and install the bridleway structure and improve the installation efficiency and construction safety of the bridleway have become the key issues to be considered in the construction of steel structure bridleway.

[0003] A Chinese invention patent with application publication number CN 111852041 A discloses an installation structure of a roof truss and a curved multi-layered horsewalk and a method for constructing the horsewalk, wherein the whole horsewalk is split into a plurality of horsewalk units, the horsewalk units are hoisted to the roof trusses respectively, and then the loose units between adjacent horsewalk units are connected. The installation of this structure can be carried out simultaneously with the installation of the roof trusses. However, this horsewalk structure involves the hoisting and aerial installation process of a plurality of horsewalk units, and also involves the installation process of the loose units between adjacent horsewalk units. Its construction efficiency is low and the construction risk is high. Summary of the invention

[0004] At least one of the purposes of the present invention is to provide a method for installing and constructing a steel structure horseway in order to overcome the problems existing in the above-mentioned prior art, which can quickly lift the entire horseway to a preset position indoors, reduce the amount of high-altitude work, and help improve the installation efficiency of the steel structure horseway and reduce construction risks. During the installation of the horseway, there is no need to set up an operating platform for high-altitude operations, which further improves construction efficiency and reduces construction costs.

[0005] In order to achieve the above-mentioned purpose, the technical solution adopted by the present invention includes the following aspects.

[0006] A method for installing and constructing a steel structure bridleway comprises the following steps: Step A, assembling a curved bridleway on the ground within the roof frame, and then interrupting the curved bridleway at preset positions at both ends thereof to form a first bridleway section and two second bridleways sections; Step B, installing the first suspension rod through the operating platform; Step C, setting a hoisting device; arranging two first winches on the ground, the two first winches are respectively set at the two ends of the first horseway, fixing a second winch on the top of the floor slab of the roof, and the second winch is correspondingly set in the middle of the first horseway; Step D, after connecting the hoisting device to the first bridleway, hoist the first bridleway; Step E, welding the two ends of the first bridle to the bottom of the first suspension rod respectively, and putting the first bridle in a hoisting state; Step F, arranging two first safety ropes respectively along the height direction of the first suspension rod, and arranging a second safety rope near the middle of the first horseway; Step G, connecting the first bridleway and the roof using a second suspension rod; Step H: Repeat steps A to G along the west side to the east side of the roof frame until all first runways are installed.

[0007] Preferably, the step H further includes a step I: installing a second bridleway, and the installation process of the second bridleway includes: Step I1, lowering the height of the operating platform; Step I2, adjusting the positions of the two first winches in the roof frame so that the two first winches correspond to the two ends of the first section of the first bridleway on the west side; Step I3, connecting the two first winches to the two sections of the second bridleway respectively, and then hoisting the second bridleway to the same height as the first bridleway; Step I4, after adjusting the position of the second horseway so that the second horseway is aligned with the first horseway, one end of the second horseway is welded to the first horseway on the operating platform, and the other end of the second horseway is welded to the horseway embedded part on the wall; Step I5: Repeat steps I2 to I4 along the west side to the east side of the roof frame until all second runways are installed.

[0008] Preferably, in step B, the installation process of the first hanger includes: welding the tops of the first vertical poles of the two groups of first hangers to the steel structures on the north and south sides of the bottom of the roof at the top of the operating platform respectively; then setting a pulley hook on each group of first hangers; when setting the pulley hook, pass one end of a steel wire rope with a diameter of 14 mm around the steel ring pulley hook, and pass the other end around the first cross bar on the first hanger, and the steel wire rope and the steel ring pulley hook, as well as the steel wire rope and the first cross bar are fixed by wire rope clamps.

[0009] Preferably, step G specifically includes: after hoisting the second hanger to the middle of the first horseway, welding the bottom of the second vertical pole of the second hanger to the first horseway, then climbing onto the second hanger through the ladder on the second hanger, welding the top of the second vertical pole to the steel structure at the bottom of the roof, and after the connection of the second hanger is completed, disconnecting the first horseway from the hoisting device.

[0010] Preferably, the columns at both ends of the ladder are detachably connected to the second column of the second suspension rod via connecting assemblies, and a plurality of connecting assemblies are arranged along the height direction of the columns.

[0011] Preferably, the connecting assembly includes two clamping members arranged opposite to each other, the second pole and the column are arranged in close contact, the second pole and the column are located between the two clamping members, connecting through holes are respectively provided at both ends of each clamping member, and the two ends of the two clamping members are respectively connected by a screw rod and a nut.

[0012] Preferably, in step F, two first safety ropes are respectively arranged near the top and bottom of the first hanger, and the two ends of each of the first safety ropes are respectively connected to the safety rope embedded parts on the wall; the second safety rope extends vertically into the roof frame from the safety rope hole reserved on the floor slab of the roof, and the top of the second safety rope is fixed on the floor slab of the roof.

[0013] Preferably, in step C, when setting up the first winch, the steel wire rope of each first winch is passed around the pulley hook on the first suspension rod; when setting up the second winch, a mounting hole with a diameter of 50 mm is opened on the floor near the second winch, and a winch bracket is arranged at the mounting hole. After the steel wire rope of the second winch passes around the steel ring pulley hook of the winch bracket and the mounting hole on the floor, it extends into the roof frame.

[0014] Preferably, step D specifically includes: determining the positions of the hanging points at both ends and the middle of the first horseway, four hanging points are set at each hanging point position, and a hanging rope is used to be looped on the four hanging points of the first horseway at each hanging point position, and then the hanging ropes at both ends of the first horseway are connected to the steel wire rope of the first winch, and the hanging rope in the middle of the first horseway is connected to the steel wire rope of the second winch. After the connection is completed, the first winch and the second winch are synchronously controlled to lift the first horseway.

[0015] Preferably, the operating platform is a scaffolding platform, the height of the operating platform is 14m, the distance between the vertical poles inside the operating platform and the wall columns is 0.3~0.5m, and the distance between the top of the operating platform and the bottom of the roof is 0.4m~0.8m.

[0016] In summary, due to the adoption of the above technical solution, the present invention has at least the following beneficial effects: By arranging a first winch indoors and a second winch on the roof, and hoisting the first horseway as a whole by the first winch and the second winch, the hoisting and installation efficiency of the first horseway can be improved. The overall lifting of the first horseway can reduce the amount of high-altitude work for the installation of the horseway in sections and reduce the risk of high-altitude work. Moreover, the mutual cooperation between the first winch and the second winch can ensure the stability and reliability of the first horseway during the hoisting process, and can prevent the first horseway from being deformed during the hoisting process.

[0017] The first hanger and the first horseway are connected through the operating platform on the inner side of the roof frame. The operating platform is a scaffolding platform set up during the construction of the roof frame. During the connection of the first horseway, the existing operating platform is used without setting up another one, which is conducive to improving construction efficiency. By using the second hanger in the middle of the first horseway to connect the first horseway and the roof, the stability and reliability of the first horseway structure can be guaranteed; during the connection of the second hanger and the roof, the first horseway and the second hanger themselves are used as construction platforms, and there is no need to set up a high-altitude construction platform, which further improves construction efficiency and reduces construction costs. BRIEF DESCRIPTION OF THE DRAWINGS

[0018] Figure 1 It is a schematic diagram of the steel structure horseway installation structure of an exemplary embodiment of the present invention.

[0019] Figure 2 1 is a schematic plan view of a first horse track according to an exemplary embodiment of the present invention.

[0020] Figure 3 yes Figure 2 Side view of the first bridleway hoisting.

[0021] Figure 4 Schematic diagram of the first suspension rod structure of an exemplary embodiment of the present invention.

[0022] Figure 5 yes Figure 1 Schematic diagram of the structure of the second boom in the BB direction.

[0023] Figure 6 yes Figure 5 Schematic diagram of the structure in the CC direction where the second suspension rod is connected to the ladder.

[0024] Figure 7 It is a schematic diagram of the connection between the first and second horse paths of an exemplary embodiment of the present invention.

[0025] Figure 8 It is a flow chart of the installation and construction of a steel structure horseway according to an exemplary embodiment of the present invention.

[0026] Fig. 9 Schematic diagram of arrangement of the first and second horse paths from another perspective of an exemplary embodiment of the present invention.

[0027] Fig.10 It is a schematic diagram of the structure of a winch bracket according to an exemplary embodiment of the present invention.

[0028] Fig.11 It is a structural schematic diagram of a winch bracket from another perspective of an exemplary embodiment of the present invention.

[0029] Fig.12 It is a schematic diagram of the arrangement of the first suspension rod and the second suspension rod from another perspective of an exemplary embodiment of the present invention.

[0030] Markings in the figure: 1-first horseway, 101-arc beam, 102-cross beam, 103-pedal, 2-first suspension rod, 201-first vertical pole, 202-first horizontal rod, 3-operating platform, 4-hoisting device, 401-first winch, 402-second winch, 5-wall, 6-roof, 7-winch bracket, 8-pulley hook, 9-first safety rope, 10-second suspension rod, 10a-second vertical pole, 11-ladder, 11a-column, 12-connecting assembly, 121-clamp, 122-screw, 13-second safety rope, 14-second horseway. DETAILED DESCRIPTION

[0031] The present invention is further described in detail below in conjunction with the accompanying drawings and embodiments to make the purpose, technical solutions and advantages of the present invention more clearly understood. It should be understood that the specific embodiments described herein are only used to explain the present invention and are not intended to limit the present invention.

[0032] refer to Figure 1 The steel structure horseway installation structure of the exemplary embodiment of the present invention includes a first horseway 1, a first hanger 2, an operating platform 3 and a lifting device 4, wherein the two ends of the first horseway 1 extend respectively to the wall 5 opposite to the roof frame, and the two end portions of the first horseway 1 are respectively spaced from the inner side of the wall 5, the top of the first hanger 2 is connected to the roof 6, the first hanger 2 is used to cooperate with the lifting device 4 to lift the first horseway 1 to a preset position, and then connect the first horseway 1 to the roof 6, the operating platform 3 is arranged circumferentially along the wall 5 of the roof frame, and the operating platform 3 is used for the installation of the first hanger 2, and the lifting device 4 includes two first winches 401, the two first winches 401 are arranged on the ground inside the roof frame, and the two first winches 401 are respectively arranged near the two ends of the first horseway 1, and the steel wire rope of each first winch 401 is connected to the first horseway 1 after passing through the first hanger 2. The first horseway is lifted as a whole by the hoisting device inside the frame, which saves the hoisting and high-altitude installation work of multiple horseway units, improves the efficiency of horseway installation, and reduces the risk of horseway installation.

[0033] refer to Figure 2 , Figure 3The first horseway 1 is an integral curved horseway, including two concentrically arranged curved beams 101, a plurality of cross beams 102 are arranged circumferentially between the two curved beams 101, and the two ends of each cross beam 102 are respectively connected to the curved beam 101, and a pedal 103 is arranged on the top of the cross beam 102, and the two ends of the pedal 103 extend to the two curved beams 101 respectively. Guardrails (not shown in the figure) are also arranged at both ends of the pedal 103, which are used to improve the safety of the installers working on the first horseway. The curved beam 101 and the cross beam 102 are both made of H-shaped steel, and the pedal 103 is made of patterned steel plate.

[0034] refer to Figure 1 , Figure 4 The first suspension rod 2 includes two first vertical rods 201 parallel to each other, one or more first cross rods 202 are arranged between the two first vertical rods 201, the first cross rod 202 and the first vertical rod 201 are perpendicular to each other, both ends of the first cross rod 202 are connected to the first vertical rod 201 respectively, the first cross rod 202 is arranged near the top of the first vertical rod 201, and the steel wire rope of the first hoist 401 passes around the first cross rod 202 and is connected to the first horseway 1. The first cross rod 202 is also provided with a pulley hook 8, which is fixed to the first cross rod 202 by a steel wire rope and a steel wire rope clamp. The pulley hook 8 can reduce the degree of wear of the steel wire rope of the first hoist 401 during the adjustment process, and can also play a labor-saving role in the hoisting process of the first horseway 1. During application, the first vertical pole 201 is made of H-shaped steel, the first cross bar 202 is made of H-shaped steel or rectangular tube, the steel wire rope connected to the pulley hook 8 is a steel wire rope with a diameter of 14~20mm, the pulley hook 8 has a dead weight of 4.3kg, a maximum load of 5t, and the distance between the two first vertical poles 201 is 600mm.

[0035] In the preferred embodiment, two first safety ropes 9 are arranged in the height direction of the first suspension rod 2. Figure 1 Two first safety ropes 9 are respectively arranged near the top and bottom of the first suspension rod 2, and both ends of each first safety rope 9 are connected to the safety rope embedded parts on the wall 5, and the safety rope embedded parts can be expansion hooks or other connecting rods. After the first horseway 1 is hoisted in place, the first safety ropes 9 can improve the safety of construction on the first horseway 1.

[0036] In a preferred embodiment, reference Figure 1 , Figure 5The steel structure horseway installation structure also includes a second hanger 10. After the first horseway 1 is hoisted in place, the second hanger 10 is used to connect the first horseway 1 with the roof 6. The second hanger 10 is arranged in the middle of the first horseway 1. The second hanger 10 includes two second vertical poles 10a parallel to each other. A ladder 11 is arranged between the two second vertical poles 10a. The ladder 11 is arranged along the height direction of the second vertical pole 10a. The vertical poles 11a at both ends of the ladder 11 are detachably connected to the second vertical pole 10a through connecting components 12. A plurality of connecting components 12 are arranged along the height direction of the vertical poles 11a. After the first horseway 1 is hoisted in place, the second hanger 10 can be connected to the roof 6 through the ladder 11 on the second hanger 10, thereby improving the anti-deformation ability of the first horseway 1.

[0037] refer to Figure 6 The connecting component 12 includes two clamping members 121 arranged opposite to each other. The second vertical pole 10a and the column 11a are arranged in close contact. The second vertical pole 10a and the column 11a are located between the two clamping members 121. Both ends of each clamping member 121 are respectively provided with connecting through holes. The two ends of the two clamping members 121 are respectively connected by screw rods 122 and nuts. When connected, both ends of each screw rod 122 pass through the connecting through holes of the two clamping members 121 at the same time, and the two ends of the screw rod 122 are respectively connected to the clamping members 121 by nuts, thereby fastening the second vertical pole 10a and the column 11a together. During application, the ladder 11 is made of 30*3 square tube, the clamp 121 is made of L50*4 angle steel, the screw rod 122 is made of M12 screw rod 122, the second vertical pole 10a is made of HN100*100 steel, the length of the second suspension rod 10 is 4~5m, and the length of the second suspension rod 10 is the same as the length of the first suspension rod 2.

[0038] A second safety rope 13 is also provided on one side of the second hanger 10. The second safety rope 13 is arranged close to the second hanger 10. One end of the second safety rope 13 passes through the roof safety rope hole and is fixed on the roof. The second safety rope 13 is used to improve the safety of the second hanger 10 during installation.

[0039] In a preferred embodiment, the steel structure bridleway installation structure further includes a second winch 402, and further reference is made to Figure 1The second winch 402 is arranged on the roof 6, and the second winch 402 is located in the middle of the first horseway 1. After the steel wire rope of the second winch 402 passes through the mounting hole on the roof 6, it is connected to the middle of the first horseway 1. The steel wire rope of the second winch 402 is supported by the winch bracket 7, and the winch bracket 7 is detachably arranged on the roof 6. The second winch 402 is used to assist in lifting the first horseway 1, so as to prevent the first horseway 1 from being deformed during the lifting process, improve the reliability of the structure of the first horseway 1, and with the cooperation of the first winch 401 and the second winch 402, the stability and safety of the first horseway 1 during the lifting process can also be ensured; the first winch 401 and the second winch 402 are preferably JM2T winches, whose rated lifting weight is 2T, the motor power is 7.5KW, and the rope speed is about 16m per minute.

[0040] In a preferred embodiment, a second bridleway 14 is provided at both ends of the first bridleway 1. Figure 7 The second horseway 14 is a straight horseway, one end of which is connected to the first horseway 1, and the other end of which is connected to the horseway embedded part on the wall 5. The second horseway 14 connects the first horseway 1 and the wall 5 into an integral structure, which can further improve the stability and safety of the horseway after installation. The second horseway 14 also includes two straight beams parallel to each other, and a plurality of cross beams parallel to each other are arranged between the two straight beams. The two ends of each cross beam are respectively connected to the straight beams, and a pedal is arranged on the top of the cross beam. The two ends of the pedal extend to the straight beams respectively, and the two ends of the pedal are respectively provided with a guardrail; the width of the two straight beams is the same as the width of the two curved beams of the first horseway.

[0041] The present invention also provides a method for installing and constructing a steel structure bridleway, referring to Figure 8 , the installation construction method comprises the following steps: Step A: transport the components of the assembled steel structure bridle to the bridle installation position in the roof frame, assemble the curved bridle on the ground, and then break the curved bridle at the preset positions at both ends to form a first bridle 1 and two second bridles 14; or assemble the first bridle 1 and the second bridle 2 separately. Preferably, the weight of the first bridle 1 is 1.43 t and the length is 19.2 m; the weight of the second bridle is 0.22 t and the length is 2-3 m.

[0042] Step B, install the first suspension rod 2 through the operating platform 3; the operating platform 3 is a scaffolding platform, with a height of 14m, a vertical distance of 0.9m, a horizontal distance of 0.9m, a step distance of 1.5m, a distance between the vertical rods on the inner side of the operating platform 3 and the wall column of the wall 5 of 0.3~0.5m, and a distance between the top of the operating platform 3 and the bottom of the roof 6 of 0.4m~0.8m; when installing the first suspension rod 2, the tops of the first vertical rods 201 of the two groups of first suspension rods 2 are welded to the north and south sides of the bottom of the roof 6 at the top of the operating platform 3 ( Figure 7 Left and right direction, Fig. 9 , Fig.12 Up and down direction, Fig. 9 Only the first suspension rod on the west edge is shown; then a pulley hook 8 is set on each group of first suspension rods 2. When setting the pulley hook 8, one end of a steel wire rope with a diameter of 14 mm is passed around the steel ring pulley hook, and the other end is passed around the first cross bar 202 on the first suspension rod 2. The steel wire rope and the steel ring pulley hook, and the steel wire rope and the first cross bar 202 are all fixed by wire rope clamps.

[0043] Step C, setting the hoisting device 4; arranging two first hoists 401 on the ground, the two first hoists 401 are respectively arranged at the two ends of the first horseway 1, and the length of the steel wire rope of each first hoist 1 is not less than 50m; fixing the second hoist 402 on the top of the floor of the roof 6, the second hoist 402 is correspondingly arranged in the middle of the first horseway 1; then opening a mounting hole with a diameter of 50mm on the floor near the second hoist 402 (the center of the mounting hole corresponds to the central axis of the first horseway 1), and setting a hoist bracket 7 at the mounting hole, and the hoist bracket 7 is fixed to the floor by post-bolts, refer to Fig.10 , Fig.11 The winch bracket 7 includes two support frames arranged opposite to each other, and the cross-section of the support frames is a triangular structure. The tops of the two support frames are connected by a connecting beam, and the bottoms of the support frames are fixed to the floor of the roof 6 by post-bolts. A pulley hook is also provided on the connecting beam. The steel wire rope of the second winch 402 passes through the steel ring pulley hook of the winch bracket 7 and the mounting hole on the floor, and then extends into the roof frame.

[0044] Step D, after connecting the hoisting device 4 to the first horseway 1, hoist the first horseway 1; determine the hoisting point positions at both ends and the middle of the first horseway 1, four hoisting points are set at each hoisting point position, and a hoisting rope (a steel wire rope with a diameter of 14 mm) is used to be sleeved on the four hoisting points of the first horseway 1 at each hoisting point position, and then the hoisting ropes at both ends of the first horseway 1 are connected to the steel wire rope of the first winch 401, and the hoisting rope in the middle of the first horseway 1 is connected to the steel wire rope of the second winch 402. After the connection is completed, the first winch 401 and the second winch 402 are synchronously controlled by the remote control electric box to hoist the first horseway 1. During the hoisting process of the first horseway 1, the angle between the hoisting rope and the first horseway 1 is 75 degrees, and the distance between the top of the hoisting rope and the first horseway 1 is 1m.

[0045] Step E: After the first horseway 1 is hoisted in place, the two ends of the first horseway 1 are respectively welded to the bottom of the first upright pole 201 of the first suspension rod 2. After welding, the connection state between the hoisting device 4 and the first horseway 1 is maintained to keep the first horseway 1 in a hoisted state.

[0046] Step F, arrange two first safety ropes 9 along the height direction of the first hanger 2, the two first safety ropes 9 are respectively arranged near the top and bottom of the first hanger 2, and the two ends of each first safety rope 9 are respectively connected to the safety rope embedded parts on the wall 5; then arrange the second safety rope 13 near the middle position of the first horseway 1, the second safety rope 13 extends vertically into the roof frame through the safety rope hole reserved on the floor slab of the roof 6, and the top of the second safety rope 13 is fixed on the floor slab of the roof 6.

[0047] Step G, use the second hanger 10 to connect the first horseway 1 and the roof 6; after hoisting the second hanger 10 to the middle of the first horseway 1, weld the bottom of the second vertical pole 10a of the second hanger 10 to the first horseway 1, then climb onto the second hanger 10 through the ladder 11 on the second hanger 10, weld the top of the second vertical pole 10a to the steel structure at the bottom of the roof 6, and after the connection of the second hanger 10 is completed, disconnect the first horseway 1 from the hoisting device 4.

[0048] When the installer climbs up and down the ladder 11, the safety belt of the installer is connected to the second safety rope 13 by a clamp to ensure the safety of the installer. When hoisting the second suspension rod 10, a fourth hoist or electric hoist can be used, that is, after arranging the hoist bracket at the preset position on the top of the floor of the roof 6, the steel wire rope of the fourth hoist is passed around the hoist bracket (or the electric hoist is hung on the hoist bracket) and the installation hole on the floor to hoist the second suspension rod 10. The hoisting of the second suspension rod 10 can also be carried out indoors by a crane. The second suspension rod 10 can also be welded to the middle part of the first horseway 1 during the assembly of the first horseway 1 in step A. When connected in this way, the step of hoisting the second suspension rod 10 separately can be omitted, and the installation efficiency is improved. After the first horseway 1 is connected to the first suspension rod 2, only the top of the second suspension rod 10 needs to be connected to the roof 6. After the second suspension rod 10 is installed, the ladder 11 on the second suspension rod 10 can be removed so that the ladder 11 can be used at other second suspension rods, which is beneficial to saving materials and reducing construction costs.

[0049] When all the steel structure galleries are installed in the roof frame, repeat the above steps A to G along the west side to the east side of the roof frame to install the first galleries 1 in sequence until all the first galleries 1 are installed.

[0050] After all the first horseways are installed, the second horseway 14 is also installed. The installation process of the second horseway 14 includes: lowering the height of the operating platform 3 by removing the steel pipe of the operating platform 3. The installation height of the first horseway 1 is 9.4m. The height of the operating platform 3 is lowered to be slightly lower than the installation height of the first horseway 1. The height of the operating platform 3 after lowering is 9m; adjusting the positions of the two first winches 401 in the roof frame so that the two first winches 401 correspond to the two ends of the first section of the first horseway 1 on the west side respectively; the steel wire ropes of the two first winches 401 are respectively wound around the first section of the first horseway 1 on the west side; After being connected with the second horseway 14 through the pulley hook 8 on the first suspension rod 2, the two sections of the second horseway 14 are hoisted to the same height as the first horseway 1 at the same time; after adjusting the position of the second horseway 14 so that the second horseway 14 is aligned with the first horseway 1, one end of the second horseway 14 is welded to the first horseway 1 on the operating platform 3, and the other end of the second horseway 14 is welded to the horseway embedded part on the wall 5; after the second horseway 14 is connected to the first section of the first horseway 1, the above steps are repeated to install the second horseway 14 along the west side to the east side of the roof frame until all the second horseways 14 are installed.

[0051] When the first and second horseway 1 and 14 are installed, in order to further improve the stability and reliability of the horseway structure, multiple auxiliary hangers can be installed in the length direction of the first horseway 1. The auxiliary hangers have the same structure as the second hangers 10. The auxiliary hangers can be installed in the same way as the second hangers 10, or they can be installed using a fixed or mobile scaffolding platform.

[0052] The above is only a detailed description of the specific implementation of the present invention, rather than a limitation of the present invention. Various substitutions, modifications and improvements made by those skilled in the relevant art without departing from the principle and scope of the present invention should be included in the protection scope of the present invention.

Claims

1. A method for installing and constructing a steel structure bridleway, characterized in that: The following steps are involved: Step A, assembling a curved bridleway on the ground within the roof frame, and then interrupting the curved bridleway at preset positions at both ends thereof to form a first bridleway (1) and two second bridleways (14); Step B, installing the first suspension rod (2) through the operating platform (3); Step C, setting up a hoisting device (4); arranging two first winches (401) on the ground, the two first winches (401) being respectively arranged at two ends of the first horseway (1), fixing a second winch (402) on the top of the floor slab of the roof (6), the second winch (402) being respectively arranged in the middle of the first horseway (1); Step D: After connecting the lifting device (4) to the first bridleway (1), lifting the first bridleway (1); Step E, welding the two ends of the first bridle (1) to the bottom of the first suspension rod (2) respectively, and placing the first bridle (1) in a hoisting state; Step F, arranging two first safety ropes (9) respectively along the height direction of the first suspension rod (2), and setting a second safety rope (13) near the middle of the first horseway (1); Step G, using a second suspension rod (10) to connect the first bridleway (1) and the roof (6); Step H: Repeat steps A to G along the west side of the roof frame toward the east side until all first runways (1) are installed.

2. The installation and construction method of the steel structure bridleway according to claim 1, characterized in that: After step H, step I is also included: installing a second bridleway (14), and the installation process of the second bridleway (14) includes: Step I1, lowering the height of the operating platform (3); Step I2, adjusting the positions of the two first winches (401) in the roof frame so that the two first winches (401) correspond to the two ends of the first section of the first bridleway (1) on the west side respectively; Step I3, connecting the two first winches (401) to the two sections of the second bridleway (14) respectively, and then hoisting the second bridleway (14) to the same height as the first bridleway (1); Step I4, after adjusting the position of the second horseway (14) so ​​that the second horseway (14) is aligned with the first horseway (1), one end of the second horseway (14) is welded to the first horseway (1) on the operating platform (3), and the other end of the second horseway (14) is welded to the horseway embedded part on the wall (5); Step I5: Repeat steps I2 to I4 along the west side of the roof frame toward the east side until all the second horseways (14) are installed.

3. The installation and construction method of the steel structure bridleway according to claim 1, characterized in that: In step B, the installation process of the first suspension rod (2) comprises: welding the tops of the first vertical rods (201) of the two groups of first suspension rods (2) to the steel structures on the north and south sides of the bottom of the roof (6) at the top of the operating platform (3); then arranging a pulley hook (8) on each group of first suspension rods (2); when arranging the pulley hook (8), one end of a steel wire rope with a diameter of 14 mm is passed around the steel ring pulley hook, and the other end is passed around the first cross bar (202) on the first suspension rod (2), and the steel wire rope and the steel ring pulley hook, and the steel wire rope and the first cross bar (202) are all fixed by a steel wire rope clamp.

4. The installation and construction method of the steel structure bridleway according to claim 1, characterized in that: The step G specifically comprises: after hoisting the second hanging rod (10) to the middle of the first horseway (1), welding the bottom of the second vertical rod (10a) of the second hanging rod (10) to the first horseway (1), then climbing onto the second hanging rod (10) via the ladder (11) on the second hanging rod (10), welding the top of the second vertical rod (10a) to the steel structure at the bottom of the roof (6), and after the second hanging rod (10) is connected, disconnecting the first horseway (1) from the hoisting device (4).

5. The installation and construction method of the steel structure bridleway according to claim 4, characterized in that: The upright posts (11a) at both ends of the ladder (11) are detachably connected to the second upright post (10a) of the second suspension rod (10) via connection assemblies (12), and a plurality of connection assemblies (12) are arranged along the height direction of the upright posts (11a).

6. The installation and construction method of the steel structure bridleway according to claim 5, characterized in that: The connection assembly (12) comprises two clamping members (121) arranged opposite to each other, the second upright pole (10a) and the upright column (11a) being arranged in close contact with each other, the second upright pole (10a) and the upright column (11a) being located between the two clamping members (121), each of the two clamping members (121) being provided with connecting through holes at both ends, and the two ends of the two clamping members (121) being connected via a screw rod (122) and a nut.

7. The installation and construction method of the steel structure bridleway according to claim 1, characterized in that: In the step F, two first safety ropes (9) are respectively arranged near the top and bottom of the first suspension rod (2), and the two ends of each first safety rope (9) are respectively connected to the safety rope embedded parts on the wall (5); the second safety rope (13) extends vertically into the roof frame from the safety rope hole reserved on the floor slab of the roof (6), and the top of the second safety rope (13) is fixed on the floor slab of the roof (6).

8. The method for installing and constructing a steel structure bridleway according to claim 3, characterized in that: In the step C, when the first hoist (401) is set, the steel wire rope of each first hoist (401) is passed around the pulley hook (8) on the first suspension rod (2); when the second hoist (402) is set, a mounting hole with a diameter of 50 mm is opened on the floor near the second hoist (402), and a hoist bracket (7) is arranged at the mounting hole. After the steel wire rope of the second hoist (402) passes around the pulley hook of the steel ring sleeve of the hoist bracket (7) and the mounting hole on the floor, it extends into the roof frame.

9. The method for installing and constructing a steel structure bridleway according to claim 1, characterized in that: The step D specifically comprises: determining the positions of the suspension points at both ends and the middle of the first horseway (1), wherein four suspension points are arranged at each suspension point position, and a suspension rope is looped on the four suspension points of the first horseway (1) at each suspension point position, and then the suspension ropes at both ends of the first horseway (1) are connected to the steel wire rope of the first hoist (401), and the suspension rope in the middle of the first horseway (1) is connected to the steel wire rope of the second hoist (402). After the connection is completed, the first hoist (401) and the second hoist (402) are synchronously controlled to lift the first horseway (1).

10. The method for installing and constructing a steel structure bridleway according to any one of claims 1 to 9, characterized in that: The operating platform (3) is a scaffolding platform, the height of the operating platform (3) is 14 m, the distance between the inner side upright pole of the operating platform (3) and the wall column of the wall (5) is 0.3-0.5 m, and the distance between the top of the operating platform (3) and the bottom of the roof (6) is 0.4-0.8 m.

Citation Information

Patent Citations

  • Tile type lap joint riding track and construction method thereof

    CN107476599A

  • Mounting structure for roof trusses and arc-shaped multilayer berm and construction method of berm

    CN111852041A

  • A packway for in foundation ditch construction

    CN207277373U

  • Construction operation method and system for outer curtain walls of high-altitude large-span building corridor

    WO2023201837A1

Cited By

  • Lifting equipment and lifting method for indoor stadium

    CN121292238A