Through the combination of flexible isolators and spiral tubular supports, the problem of poor separation effect of inflatable capsules at beam-column nodes is solved, efficient isolation of concrete of different strengths is achieved, and the quality of the building structure and construction efficiency are ensured.

CN118756949APending Publication Date: 2024-10-11FOSHAN PROJECT CONTRACTING CORP
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202410915591.9
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-09
Publication Date
2024-10-11

AI Technical Summary

Technical Problem

When existing inflatable capsules are used to separate concrete of different strengths at beam-column joints, insufficient inflation can easily lead to extrusion and deformation, and excessive inflation can easily explode, affecting the separation effect and making it difficult to ensure construction efficiency and sealing.

Method used

The partition assembly is a combination of a flexible isolator and a spiral tubular support. By setting the support in the flexible isolator and filling it with water, the stability and weight are increased. The spiral support is used to withstand side pressure, and efficient inflation is achieved through an air pump and a water pump. and water injection to ensure sealing and separation effects.

Benefits of technology

Effectively isolate concrete of different strengths to ensure the quality of the building structure, improve the separation effect and construction efficiency, reduce the spread of concrete, avoid deformation and leakage of inflatable parts, and enhance structural stability.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118756949A_ABST
    Figure CN118756949A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of building construction, in particular to a beam-column joint mixed pouring prevention isolation device and a construction method thereof.The beam-column joint mixed pouring prevention isolation device comprises a separation assembly arranged at a beam-column joint, the separation assembly comprises a plurality of flexible isolation pieces, and supporting pieces are arranged in the flexible isolation pieces; one end of the supporting piece penetrates through the top of the flexible isolation piece and extends to the outer side of the flexible isolation piece; the construction method comprises the steps that S1, after beam-column joint reinforcing steel bars are bound, a plurality of uninflated flexible isolation pieces are placed in gaps of the reinforcing steel bars; s2, a water pump is used for injecting water into the supporting piece; s3, the flexible isolation piece is inflated through an inflation pump, and high-strength-grade concrete pouring is conducted; and S4, after the high-strength grade concrete is initially set, exhausting and draining operation is carried out, so that the flexible isolation piece is separated from the concrete, and the flexible isolation piece is slowly pulled out. According to the invention, the separation effect between concrete with different strengths can be improved so as to adapt to the strength requirements of different building structures.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of building construction, and in particular to a beam-column node anti-mixing pouring isolation device and a construction method thereof. Background Art

[0002] In construction, in order to improve the strength and anti-destruction ability of the entire building, concrete of different grades is usually used for pouring, so that the strength grade of the column is higher than that of the surrounding beams. Therefore, when pouring the column, it is necessary to set nodes to separate the column from the surrounding structure to prevent low-strength concrete from diffusing into the structural parts of high-strength concrete, thereby ensuring the quality of the high-strength concrete structure.

[0003] In the existing method, inflatable capsules are used to separate concrete of different grades. Multiple inflatable capsules are set at the beam-column joints. The gaps between the column steel bars are filled and expanded by inflation. After the high-strength concrete is initially set, the inflatable capsules are deflated to separate them from the concrete. However, when the inflatable capsules are insufficiently inflated, the middle of the capsules is easily squeezed and deformed due to lack of sufficient support, resulting in poor separation effect. When the inflatable capsules are sufficiently inflated, the inflatable capsules are easily squeezed and exploded, which also affects the separation effect of the concrete. Summary of the invention

[0004] In order to improve the separation effect between concretes of different strengths and to adapt to the strength requirements of different building structures, the present application provides a beam-column node anti-mixing isolation device and a construction method thereof.

[0005] In the first aspect, the present application provides a beam-column joint anti-mixing pouring isolation device, which adopts the following technical solution: A beam-column joint anti-mixing pouring isolation device includes a partition assembly arranged at the beam-column joint, the partition assembly includes a plurality of flexible isolation members, a support member is arranged inside the flexible isolation member, and one end of the support member passes through the top of the flexible isolation member and extends to the outside of the flexible isolation member.

[0006] By adopting the above-mentioned device, the partition assembly can effectively isolate the concrete pouring area at the beam-column joint, reduce the mixing of concrete of different strength grades, ensure that the concrete strength of the column in the beam-column joint of different strength concrete grades meets the design requirements, and ensure the quality of the building structure. Since the flexible partition will expand after being inflated, the pores between the column steel bars are filled densely, effectively isolating the high and low grade concrete. Before pouring concrete, water needs to be injected into the support. The setting of the support enhances the stability of the flexible partition and ensures that it will not be deformed during the concrete pouring process. In addition, since the flexible partition is easy to float up during the concrete pouring process after being inflated, injecting water into the support can also increase the weight of the flexible partition, reduce the floating of the flexible partition, and further improve the separation effect of the flexible partition.

[0007] Optionally, the support member is in the shape of a spiral tube, and the outer wall of the support member is fixedly connected to the inner wall of the flexible isolation member.

[0008] By adopting the above device, the spiral tubular support provides better structural stability and can better withstand the lateral pressure generated during concrete pouring due to its spiral shape.

[0009] Optionally, an inflation port is provided at the top of the flexible isolating member, and a first sealing member is connected to the inflation port; a water injection port is provided at one end of the supporting member extending to the outside of the flexible isolating member, and a second sealing member is connected to the water injection port.

[0010] By adopting the above device, after the flexible partition is inflated, the first seal ensures the sealing of the inflation port, and after the support is filled with water, the second seal ensures the sealing of the water injection port, so as to reduce the leakage of gas and water during concrete pouring and ensure the good separation effect of the flexible partition. When the flexible partition is disassembled, the air is exhausted from the inflation port and the water is drained from the water injection port.

[0011] Optionally, the multiple flexible isolation members are connected via a first connecting tube, the first connecting tube is provided with multiple inflation interfaces, the inflation interfaces are connected to the inflation ports on the flexible isolation members, and the number of the inflation interfaces corresponds to the number of the flexible isolation members.

[0012] Optionally, the support members are connected via a second connecting pipe, a plurality of water injection interfaces are provided on the second connecting pipe, the water injection interfaces are connected to the water injection ports on the support members, and the number of the water injection interfaces corresponds to the number of the support members.

[0013] By adopting the above device, the first connecting pipe can connect multiple flexible isolation members, and the second connecting pipe can connect multiple support members, which is convenient for respectively inflating and injecting water into the flexible isolation members and the support members, and is conducive to improving construction efficiency.

[0014] Optionally, an air pump is provided at one end of the first connecting tube away from the inflation interface, and the flexible isolation member is inflated by the air pump. The end of the second connecting tube away from the water injection interface is connected to a water pump, and the water pump is used to inject water into the support member.

[0015] By adopting the above-mentioned device, the air pump can simultaneously inflate multiple flexible isolation members through the first connecting pipe, and the water pump can simultaneously inject water into multiple support members through the second connecting pipe, thereby effectively improving the construction efficiency. Moreover, the air pump and the water pump can accurately control the amount of inflation and water injection to ensure that the flexible isolation members and the support members reach the required pressure and volume.

[0016] Optionally, the flexible isolation member is arranged in the beam body and close to the edge of the column body, and a plurality of the flexible isolation members are arranged in parallel along the width direction of the beam body.

[0017] By adopting the above device, the flexible isolation piece is installed in the beam body, which effectively prevents the low-strength concrete from diffusing into the high-strength grade concrete, thereby ensuring the structural strength of the column. When the flexible isolation piece is inflated, multiple flexible isolation pieces fill the beam slab width densely, effectively isolating the concrete, reducing the diffusion of concrete, and ensuring the structural strength of the concrete.

[0018] Optionally, the height of the flexible isolation piece is greater than the height of the cross section of the beam body.

[0019] By adopting the above device, the height of the flexible isolation piece exceeds the cross-sectional height of the beam body to be cast, thereby ensuring effective isolation within the entire height range of the beam-column node and reducing diffusion between concretes of different strengths.

[0020] Optionally, the transverse width of the flexible isolation member is not less than the transverse spacing between two adjacent beam reinforcements, and the change in the transverse width of the flexible isolation member before and after inflation is not less than the diameter of the beam reinforcement.

[0021] By adopting the above device, the flexible isolation piece can wrap the steel bar after being inflated, thereby reducing the generation of gaps between two adjacent flexible isolation pieces and forming a tight sealing surface, which is beneficial to improving the separation effect of the flexible isolation piece.

[0022] In a second aspect, the present application provides a construction method for a beam-column node anti-mixing pouring isolation device, which adopts the following technical solution: A construction method for a beam-column node anti-mixing pouring isolation device comprises the following steps: S1. After the steel bars at the beam-column joint are tied, multiple uninflated flexible spacers are placed in the gaps between the steel bars; S2. Use a water pump to inject water into the support member so that the middle of the flexible isolation member has sufficient support; S3. Use an air pump to inflate the flexible spacer, so that the flexible spacer expands and fills the gaps between the steel bars tightly, and then pours high-strength concrete; S4. After the high-strength concrete is initially set, exhaust and drain operations are performed. First, the second seal at the end of the support is opened to drain the water, and then the first seal at the top of the flexible isolation member is opened to exhaust the water, so that the flexible isolation member is separated from the concrete, and the flexible isolation member is slowly pulled out for the next use.

[0023] By adopting the above device, during construction, high-strength concrete for the column is poured first, and then low-strength concrete for the beam is poured. Concretes of different strengths are separated by multiple flexible isolation pieces, so that low-strength concrete will not diffuse into the structural parts of high-strength concrete, thereby ensuring the quality of the column structure.

[0024] In summary, the present application includes at least one of the following beneficial technical effects: 1. In this application, the partition assembly can effectively isolate the concrete pouring area at the beam-column joint, reduce the mixing of concrete of different strength grades, ensure that the column concrete strength in the beam-column joint of different strength concrete grades meets the design requirements, and ensure the quality of the building structure. Since the flexible partition will expand after being inflated, the pores between the column steel bars are filled densely, effectively isolating high and low grade concrete. Before pouring concrete, water needs to be injected into the support. The setting of the support enhances the stability of the flexible partition and ensures that it will not be deformed during the concrete pouring process. In addition, since the flexible partition is easy to float up during the concrete pouring process after being inflated, injecting water into the support can also increase the weight of the flexible partition, reduce the floating of the flexible partition, and further improve the separation effect of the flexible partition.

[0025] 2. In the present application, the spiral tubular support provides better structural stability and can better withstand the lateral pressure generated during concrete pouring due to its spiral shape. BRIEF DESCRIPTION OF THE DRAWINGS

[0026] Figure 1 It is a schematic diagram of the three-dimensional structure of the beam-column node anti-mixing pouring isolation device at the beam-column node of an embodiment of the present application; Figure 2 It is a schematic diagram of the overall structure of the beam-column node anti-mixing pouring isolation device of an embodiment of the present application; Figure 3 It is a cross-sectional view of a flexible isolation member of the beam-column node anti-mixing pouring isolation device of an embodiment of the present application.

[0027] Description of reference numerals: 1. Partition assembly; 11. Flexible isolator; 111. Inflation port; 112. First sealing member; 12. Support member; 121. Water injection port; 122. Second sealing member; 2. First connecting pipe; 21. Inflation interface; 22. Inflation pump; 3. Second connecting pipe; 31. Water injection interface; 32. Water pump; 4. Beam; 5. Column. DETAILED DESCRIPTION

[0028] The following is combined with Figure 1-3 This application is described in further detail.

[0029] Example: A beam-column joint anti-mixing pouring isolation device, such as Figure 1 As shown, it includes a partition component 1 arranged around the column 5, the partition component 1 is installed in the beam body 4, and the distance from the edge of the column 5 is not less than 500mm, the partition component 1 is poured with high-strength concrete on one side close to the column 5, and low-strength concrete on the other side. The partition component 1 can effectively separate the high-strength concrete in the column 5 from the low-strength concrete in the beam body 4 to reduce the mutual diffusion between concretes of different strength grades and ensure the quality of the column 5 structure.

[0030] like Figure 1-2 As shown, the partition assembly 1 includes a plurality of flexible isolation members 11, which are arranged in parallel along the width direction of the beam body 4, and each flexible isolation member 11 is located between two adjacent beam reinforcements, so that the plurality of flexible isolation members 11 after inflation form an effective blocking surface to separate concrete of different strength grades. In addition, the transverse width of each flexible isolation member 11 is not less than the transverse spacing between two adjacent beam reinforcements, and the transverse width change value of the flexible isolation member 11 before and after inflation is not less than the diameter of the beam reinforcement, which can ensure that the flexible isolation member 11 can have sufficient expansion during the inflation process to adapt to the spacing change of the reinforcements. The plurality of flexible isolation members 11 fill the width of the beam body 4 tightly and wrap the beam reinforcements, thereby reducing the generation of gaps between two adjacent flexible isolation members 11, so as to reduce the penetration of low-strength concrete into the high-strength concrete area, thereby improving the blocking effect of the flexible isolation member 11. Among them, in this embodiment, the flexible isolation member 11 is selected as an inflatable capsule.

[0031] like Figure 1-2 As shown, the height of the flexible isolation member 11 is greater than the cross-sectional height of the beam body 4 to be cast, which can effectively reduce the overflow of concrete slurry from the top when casting concrete, is beneficial to improve the separation effect at the beam-column node, and avoid the phenomenon of mixed pouring of concrete.

[0032] like Figure 3As shown, in this embodiment, a support member 12 is provided inside the flexible isolator 11, and one end of the support member 12 passes through the top of the flexible isolator 11 and extends to the outside of the flexible isolator 11. An inflation port 111 is provided at the top of the flexible isolator 11, and a first sealing member 112 is threadedly connected to the inflation port 111, which is used to close the inflation port 111 after inflation is completed to prevent gas leakage. A water injection port 121 is provided at one end of the support member 12 extending to the outside of the flexible isolator 11, and a second sealing member 122 is threadedly connected to the water injection port 121, which is used to close the water injection port 121 after water injection is completed to prevent water from flowing out. In this embodiment, both the first sealing member 112 and the second sealing member 122 are sealing covers.

[0033] like Figure 2-3 As shown, in this embodiment, multiple flexible isolation members 11 are connected through a first connecting pipe 2, and multiple inflation interfaces 21 are provided on the first connecting pipe 2. Each inflation interface 21 is threadedly connected to an inflation port 111 on a corresponding flexible isolation member 11. An inflation pump 22 is provided at one end of the first connecting pipe 2 away from the inflation interface 21. The inflation pump 22 is used to inflate multiple flexible isolation members 11 at the same time, effectively improving construction efficiency. In addition, the number of inflation interfaces 21 is equal to the number of flexible isolation members 11, ensuring that each flexible isolation member 11 can be inflated through the first connecting pipe 2.

[0034] Similarly, the supports 12 are connected through the second connecting pipe 3, and a plurality of water injection interfaces 31 are provided on the second connecting pipe 3, and each water injection interface 31 is threadedly connected to the water injection port 121 on the corresponding support 12. A water pump 32 is provided at one end of the second connecting pipe 3 away from the water injection interface 31, and the water pump 32 is used to simultaneously inject water into a plurality of supports 12, thereby reducing the complexity and time cost of manual operation. In addition, the number of water injection interfaces 31 is equal to the number of supports 12, ensuring that each support 12 can be injected with water through the second connecting pipe 3.

[0035] like Figure 3 As shown, in this embodiment, the support member 12 is in a spiral tubular structure, and the outer wall of the support member 12 and the inner wall of the flexible isolation member 11 can be fixedly connected by gluing, hot melting and other processes to ensure that the position of the support member 12 inside the flexible isolation member 11 is stable. The spiral tubular support member 12 can provide sufficient support when subjected to external force, reducing the deformation of the middle part of the flexible isolation member 11 due to squeezing. At the same time, the spiral structure of the support member 12 can also limit the excessive expansion of the flexible isolation member 11 to a certain extent, avoiding bursting due to excessive inflation. In addition, water injection into the support member 12 can increase the weight of the flexible isolation member 11, reduce the floating of the flexible isolation member 11 during the pouring process, and further improve the barrier effect of the flexible isolation member 11.

[0036] The present application also discloses a construction method of a beam-column node anti-mixing pouring isolation device: A construction method for a beam-column node anti-mixing pouring isolation device comprises the following steps: S1. After the steel bars of the beam-column joint are tied, a plurality of uninflated flexible spacers 11 are placed in the gaps between the steel bars. The flexible spacers 11 have good flexibility in the uninflated state, so they can easily pass through the gaps between the steel bars.

[0037] S2. Use the water pump 32 to inject water into the support member 12 so that the middle part of the flexible isolation member 11 has sufficient support. By injecting water, the middle part of the flexible isolation member 11 can be reduced from being sunken or deformed when subjected to external force.

[0038] S3. Use the air pump 22 to inflate the flexible isolation member 11, so that the flexible isolation member 11 expands and fills the gaps between the steel bars tightly. During the inflation process, the flexible isolation member 11 will gradually expand and fit tightly on the surface of the steel bars to form an effective isolation barrier. Through the inflation operation, it can be ensured that the flexible isolation member 11 is fully deployed and achieves the expected separation effect. Next, high-strength concrete is poured. During the pouring process, due to the presence of the flexible isolation member 11, concretes of different grades are effectively separated to avoid confusion with each other. This ensures that the column 5 part is cast with high-strength concrete, thereby improving the overall strength and stability of the building.

[0039] S4. After the high-strength grade concrete has initially set, perform venting and drainage operations. First, open the second seal 122 at the end of the support 12 to drain the water in the support 12. Then open the first seal 112 on the top of the flexible isolation member 11 to vent the air, so that the flexible isolation member 11 gradually shrinks and separates from the concrete, and use a winch to slowly pull out the flexible isolation member 11. After the venting and drainage are completed, the bonding force between the flexible isolation member 11 and the concrete is greatly reduced, and it can be easily pulled out of the concrete. During the pulling process, care should be taken to avoid damaging the concrete that has already initially set. The pulled-out flexible isolation member 11 can be used again after cleaning and inspection, which reduces construction costs.

[0040] Finally, it should be noted that the above is only a preferred embodiment of the present invention and is not intended to limit the present invention. Although the present invention has been described in detail with reference to the aforementioned embodiments, it is still possible for those skilled in the art to modify the technical solutions described in the aforementioned embodiments or to make equivalent substitutions for some of the technical features therein. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the protection scope of the present invention.

Claims

1. A beam-column joint anti-mixing pouring isolation device, characterized in that: The invention comprises a partition assembly (1) arranged at a beam-column node, wherein the partition assembly (1) comprises a plurality of flexible partitions (11), wherein a support member (12) is arranged inside the flexible partition (11), and one end of the support member (12) passes through the top of the flexible partition (11) and extends to the outside of the flexible partition (11).

2. The beam-column joint anti-mixing pouring isolation device according to claim 1 is characterized in that: The support member (12) is in the shape of a spiral tube, and the outer wall of the support member (12) is fixedly connected to the inner wall of the flexible isolation member (11).

3. The beam-column joint anti-mixing pouring isolation device according to claim 1 is characterized in that: The top of the flexible isolating member (11) is provided with an air filling port (111), the air filling port (111) is connected to a first sealing member (112), and one end of the support member (12) extending to the outside of the flexible isolating member (11) is provided with a water filling port (121), the water filling port (121) is connected to a second sealing member (122).

4. A beam-column joint anti-mixing pouring isolation device according to claim 3, characterized in that: The plurality of flexible isolation members (11) are connected to each other via a first connecting pipe (2), the first connecting pipe (2) being provided with a plurality of inflation interfaces (21), the inflation interfaces (21) being connected to inflation ports (111) on the flexible isolation members (11), the number of the inflation interfaces (21) corresponding to the number of the flexible isolation members (11).

5. The beam-column joint anti-mixing pouring isolation device according to claim 4 is characterized in that: The support member (12) is connected via a second connecting pipe (3), and a plurality of water injection interfaces (31) are provided on the second connecting pipe (3), the water injection interfaces (31) are connected to the water injection port (121) on the support member (12), and the number of the water injection interfaces (31) corresponds to the number of the support members (12).

6. The beam-column joint anti-mixing pouring isolation device according to claim 5, characterized in that: An air pump (22) is provided at one end of the first connecting pipe (2) away from the air charging interface (21), and the flexible insulating member (11) is inflated by means of the air pump (22); and a water pump (32) is connected to one end of the second connecting pipe (3) away from the water injection interface (31), and the water pump (32) is used to inject water into the supporting member (12).

7. The beam-column joint anti-mixing pouring isolation device according to claim 1 is characterized in that: The flexible isolating member (11) is arranged inside the beam body (4) and close to the edge of the column body (5), and a plurality of the flexible isolating members (11) are arranged in parallel along the width direction of the beam body (4).

8. The beam-column joint anti-mixing pouring isolation device according to claim 1, characterized in that: The height of the flexible isolation piece (11) is greater than the height of the cross section of the beam body (4).

9. The beam-column joint anti-mixing pouring isolation device according to claim 1, characterized in that: The transverse width of the flexible isolation piece (11) is not less than the transverse spacing between two adjacent beam reinforcement bars, and the change in the transverse width of the flexible isolation piece (11) before and after inflation is not less than the diameter of the beam reinforcement bar.

10. A construction method for a beam-column joint anti-mixing pouring isolation device, characterized in that: The method for installing a beam-column joint anti-mixing pouring isolation device according to any one of claims 1 to 9 comprises the following steps: S1. After the steel bars of the beam-column joint are tied, a plurality of uninflated flexible spacers (11) are placed in the gaps between the steel bars; S2. Use a water pump (32) to inject water into the support member (12) so that the middle portion of the flexible isolation member (11) has sufficient support; S3. Inflate the flexible spacer (11) using an air pump (22) to expand the flexible spacer (11) to fill the gaps between the steel bars and perform high-strength concrete pouring; S4. After the high-strength grade concrete has initially set, exhaust and drainage operations are performed. First, the second sealing member (122) at the end of the support member (12) is opened to drain the water. Then, the first sealing member (112) at the top of the flexible isolation member (11) is opened to exhaust the water. The flexible isolation member (11) is separated from the concrete. The flexible isolation member (11) is slowly pulled out for the next use.