Adjustable fan foundation and construction method for spoil heaps

By using shock-absorbing spherical connecting columns and jacking mechanisms in the wind turbine foundation, the problems of construction accuracy and bearing capacity of pile-type adjustable foundations in the spoil heap were solved, thereby improving structural stability and seismic performance and reducing foundation settlement.

CN118774164BActive Publication Date: 2026-11-17SHANDONG ELECTRIC POWER ENG CONSULTING INST CORP
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202411071855.3
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-08-06
Publication Date
2026-11-17
Estimated Expiration
2044-08-06

AI Technical Summary

Technical Problem

In open-pit mines with deep slag layers, existing adjustable pile foundations have high requirements for structural connection nodes and are difficult to ensure construction accuracy. The bearing capacity of the soil under the foundation slab is not effectively mobilized, the foundation bearing mode deviates from the original design intention, and the pile bearing characteristics are obvious during wind turbine operation.

Method used

The base plate of the wind turbine foundation and the pile cap of the cast-in-place piles are connected by shock-absorbing spherical connecting columns with tensile strength. Active correction is achieved through a jacking mechanism to optimize the stress on the pile top and activate the bearing capacity of the foundation soil.

Benefits of technology

It achieves structural stability and seismic damping effect of wind turbine foundation under upward pull, reduces foundation settlement, and optimizes foundation stress mode.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118774164B_ABST
    Figure CN118774164B_ABST
Patent Text Reader

Abstract

This invention provides an adjustable wind turbine foundation and construction method for spoil heaps. A circular plain concrete pad has multiple evenly spaced arc-shaped notches around its perimeter, and this plain concrete pad is located at the bottom of the wind turbine foundation. The top of the cast-in-place pile is connected to the bottom of the pile cap, and the top of the pile cap is connected to the base plate of the shock-absorbing spherical connecting column. The top plate of the shock-absorbing spherical connecting column is connected to the base plate of the wind turbine foundation. The working well is connected to the lifting partition wall, which is connected to the inner wall of the arc-shaped notches. The pile cap is located within and connected to the lifting partition wall. A lifting mechanism for lifting the wind turbine foundation is arranged on the pile cap. This invention ensures that the foundation structure does not detach under upward tension, effectively achieves seismic resistance and vibration reduction, optimizes the stress on the pile top, and reduces foundation settlement.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the field of wind power generation technology, and in particular to an adjustable wind turbine foundation and construction method for spoil heaps. Background Technology

[0002] The statements in this section are merely background information related to the present invention and do not necessarily constitute prior art.

[0003] In response to the unique geological conditions of deep spoil layers in open-pit mines, characterized by underconsolidation and high instability, patent number CN113833012A proposes a design and construction method for a pile-type adjustable foundation. This method utilizes cast-in-place piles as a reaction structure to lift and correct foundations that exceed the uneven settlement limit. During wind turbine operation, these cast-in-place piles can still serve as a load-bearing structure, providing vertical tensile, compressive, and horizontal load resistance.

[0004] Practice has shown that the aforementioned adjustable pile foundation involves many structural connection nodes and requires high construction precision. During wind turbine operation, the load of the superstructure, the weight of the foundation and the overburden are basically borne by the cast-in-place piles, and the soil under the foundation slab bears almost no load. The stress characteristics of the foundation structure are pile bearing, the bearing capacity of the foundation is not effectively mobilized, and the foundation bearing mode violates the original design intention. Summary of the Invention

[0005] To address the shortcomings of existing technologies, this invention provides an adjustable wind turbine foundation and construction method for spoil heaps. The construction process is simple, and the adjustable foundation structure transforms passive correction into active correction. By using shock-absorbing spherical connecting columns with tensile strength to connect the bottom plate of the wind turbine foundation and the pile cap of the cast-in-place piles, it is possible to ensure that the wind turbine foundation structure does not detach when subjected to upward tension, and to effectively achieve seismic resistance and vibration reduction. This optimizes the stress on the pile top, actively mobilizes the bearing capacity of the foundation soil, thereby improving the stress on the gravity foundation bottom plate and reducing foundation settlement.

[0006] To achieve the above objectives, the present invention adopts the following technical solution:

[0007] Firstly, the invention provides an adjustable fan foundation for spoil heaps.

[0008] An adjustable wind turbine foundation for a spoil heap includes: a wind turbine foundation, a plain concrete cushion layer, cast-in-place piles, a working well, a jacking partition wall, a pile cap, a shock-absorbing spherical connecting column, and a jacking mechanism. The circular plain concrete cushion layer is provided with multiple notches evenly distributed around its perimeter, and the plain concrete cushion layer is located at the bottom of the wind turbine foundation.

[0009] The top of the cast-in-place pile is connected to the bottom of the pile cap, the top of the pile cap is connected to the bottom plate of the shock-absorbing spherical connecting column, and the top plate of the shock-absorbing spherical connecting column is connected to the bottom plate of the wind turbine foundation.

[0010] The working well is connected to the lifting partition wall, the lifting partition wall is connected to the inner wall of the notch, the pile cap is located inside the lifting partition wall and connected to the lifting partition wall, and the lifting mechanism for lifting the wind turbine foundation is arranged on the pile cap.

[0011] As a further limitation of the first aspect of the invention, the side of the lifting partition wall opposite to the working well is provided with a brick wall for a connecting passage.

[0012] As a further limitation of the first aspect of the invention, each of the pile caps is provided with at least two lifting mechanisms symmetrically arranged along the central axis of the shock-absorbing spherical connecting column.

[0013] As a further limitation of the first aspect of the present invention, the top of the pile cap is bolted to the bottom plate of the shock-absorbing spherical connecting column, and the top plate of the shock-absorbing spherical connecting column is bolted to the bottom plate of the wind turbine foundation.

[0014] As a further limitation of the first aspect of the present invention, the upper part of the plain concrete cushion layer is provided with multiple layers of geotextile bags.

[0015] As a further limitation of the first aspect of the present invention, a geotextile bag grouting port is provided on the inner wall of the notch.

[0016] As a further limitation of the first aspect of the present invention, the top surface of the plain concrete cushion layer is roughened and multiple drainage grooves are provided.

[0017] As a further limitation of the first aspect of the present invention, a first steel pad is provided between the top plate of the shock-absorbing spherical connecting column and the bottom plate of the fan foundation. A hole is made at the position corresponding to the bolt hole on the first steel pad, and a first steel sleeve with internal threads is welded along the periphery of the hole. The first steel sleeve is embedded in the bottom plate of the fan foundation for bolt connection.

[0018] A second steel pad is installed between the base plate of the shock-absorbing spherical connecting column and the top surface of the pile cap. A hole is made at the position of the bolt hole on the second steel pad, and a second steel sleeve with internal threads is welded along the outer perimeter of the hole. The second steel sleeve is embedded below the top surface of the pile cap and is used for bolt connection.

[0019] As a further limitation of the first aspect of the present invention, the shock-absorbing spherical connecting column is made of steel profile.

[0020] Secondly, the present invention provides a construction method for an adjustable fan foundation for a spoil heap as described in the first aspect, comprising the following steps:

[0021] Step (1): On-site layout to determine the location of each cast-in-place pile and the scope of the foundation treatment with dynamic compaction crushed stone. The treatment scope includes the central area of ​​the foundation slab and the local area between the two piles along the circumferential direction.

[0022] Step (2): The area determined in step (1) is reinforced by using the in-hole dynamic compaction method. The filling material in the hole can be soil excavated on site. Other areas under the bottom plate of the wind turbine foundation are treated by dynamic compaction.

[0023] Step (3): Lay out the lines to determine the centroid position of each cast-in-place pile, and construct the pile body of the cast-in-place pile according to the soil conditions using appropriate methods. After completion, perform pile head treatment.

[0024] Step (4): Construct the pile cap with formwork. The top formwork of the pile cap is a second steel pad plate with a welded steel sleeve. The second steel sleeve is embedded in the pile cap. The top elevation of the second steel pad plate is consistent with the design elevation of the pile cap.

[0025] Step (5): Install a shock-absorbing spherical connecting column with tensile strength on the top surface of the pile cap. The bottom plate of the shock-absorbing spherical connecting column is bolted to the second steel pad. The top plate of the shock-absorbing spherical connecting column is bolted to the first steel pad with a welded steel sleeve to ensure that the central axis of the shock-absorbing spherical connecting column is consistent with the centerline axis of the pile cap and the cast-in-place pile.

[0026] Step (6): Construct plain concrete cushion layer, and construct drainage grooves with a slope of 1‰ on its surface before the concrete initially sets, or simultaneously roughen the surface.

[0027] Step (7): Lay multiple layers of geotextile bags on the top surface of the plain concrete cushion layer. The size and shape of the geotextile bags should meet the needs of the jacking space and the pipelines to be laid down, so that the size allowance can meet the construction error. Reserve one grouting port at the edge of the corresponding jacking area.

[0028] Step (8): Lay the formwork on the top surface of the plain concrete foundation and construct the fan foundation;

[0029] Step (9): While constructing in steps (4) to (8), construct the working well. The axis of the working well is consistent with the axis of the pile cap. The size meets the requirements of the jacking operation. The opening at the bottom of the working well is reinforced. The working well and the fan foundation are connected by a brick wall to prevent lateral soil from entering the jacking operation space. A cross beam is set at the bottom of the working well. No bottom plate is set. A crushed stone cushion layer of the same height as the cross beam is constructed to meet the drainage requirements inside the well.

[0030] Compared with the prior art, the beneficial effects of the present invention are:

[0031] This invention provides an adjustable wind turbine foundation for spoil heaps. The construction process is simple, and the adjustable foundation structure transforms passive correction into active correction. By using shock-absorbing spherical connecting columns with tensile strength to connect the base plate of the wind turbine foundation and the pile cap of the cast-in-place piles, it can ensure that the wind turbine foundation structure does not detach when subjected to upward tension, and effectively achieve seismic resistance and vibration reduction. It optimizes the stress on the pile top, actively mobilizes the bearing capacity of the foundation soil, thereby improving the stress on the gravity foundation base plate and reducing foundation settlement.

[0032] Advantages of additional aspects of the invention will be set forth in part in the description which follows, and in part will be obvious from the description, or may be learned by practice of the invention. Attached Figure Description

[0033] The accompanying drawings, which form part of this invention, are used to provide a further understanding of the invention. The illustrative embodiments of the invention and their descriptions are used to explain the invention and do not constitute an improper limitation of the invention.

[0034] Figure 1 This is a schematic diagram of the structure provided by the present invention;

[0035] Figure 2 For the present invention Figure 1 The diagram below shows the lower structure.

[0036] Figure 3 For the present invention Figure 2 A cross-sectional view of the lower structure shown;

[0037] Figure 4 For the present invention Figure 2 A detailed schematic diagram of node I is shown;

[0038] Figure 5 A schematic diagram of the lifting mechanism arrangement for the adjustable foundation provided by the present invention;

[0039] Figure 6 A schematic diagram of the geotextile bag provided by the present invention;

[0040] Figure 7 This is a schematic diagram of the soil removal and compaction area provided by the present invention;

[0041] The components include: 1. Wind turbine foundation; 2. Plain concrete cushion layer; 3. Cast-in-place piles; 4. Working well; 5. Lifting partition wall; 6. Pile cap; 7. Shock-absorbing spherical connecting column; 8. Lifting jacks; 9. Internal drainage system of the foundation; 10. Brick wall of connecting passage; 11. Multi-layer geotextile bags; 12. Grouting port of geotextile bags; 13. Dynamic compaction treatment area. Detailed Implementation

[0042] The present invention will be further described below with reference to the accompanying drawings and embodiments.

[0043] It should be noted that the following detailed descriptions are exemplary and intended to provide further illustration of the invention. Unless otherwise specified, all technical and scientific terms used herein have the same meaning as commonly understood by one of ordinary skill in the art to which this invention pertains.

[0044] Where there is no conflict, the embodiments and features in the embodiments of the present invention can be combined with each other.

[0045] This implementation proposes an adjustable fan foundation for spoil heaps, such as... Figure 1 , Figure 2 , Figure 3 , Figure 4 He Ru Figure 5 As shown, the structure includes a wind turbine foundation 1, a shock-absorbing spherical connecting column 7, cast-in-place piles 3, a pile cap 6, a plain concrete cushion layer 2, a lifting jack 8, a multi-layer geotextile bag 11, and a working well 4. The top and bottom plates of the shock-absorbing spherical connecting column 7 are bolted to the bottom plate of the wind turbine foundation 1 and the top surface of the pile cap 6, respectively. The multi-layer geotextile bag 11 is laid under the bottom plate of the wind turbine foundation 1. The cast-in-place piles 3 and the pile cap 6 are connected by on-site casting.

[0046] In this implementation, the wind turbine foundation 1 provides resistance to uplift and transfers loads to the soil during wind turbine operation. Its dimensions should meet the requirements of the foundation bearing capacity and the impact shear effect of the load on the damping spherical connecting column 7.

[0047] In this implementation, the shock-absorbing spherical connecting column 7 is made of steel profiles. The top plate and bottom plate of the shock-absorbing spherical connecting column 7 are respectively connected to the top surfaces of the wind turbine foundation 1 and the pile cap 6 by bolts. The bolt length should meet the requirements of multiple jacking heights.

[0048] In this implementation, a first steel pad is provided between the top plate of the shock-absorbing spherical connecting column 7 and the bottom plate of the wind turbine foundation 1. A hole is made at the position corresponding to the bolt hole on the first steel pad, and a first steel sleeve with internal threads is welded along the periphery of the hole. The diameter of the hole should be consistent with or about 1mm to 2mm larger than the inner diameter of the first steel sleeve. The first steel sleeve is embedded in the bottom plate of the wind turbine foundation 1 for bolt connection.

[0049] In this implementation, the pile cap 6 is symmetrically arranged at equal intervals around the base plate of the wind turbine foundation 1 (arranged within the arc-shaped notches around the plain concrete cushion layer 2), and its axis passes through the center of the base plate. The pile cap 6 is located inside the lifting partition wall 5, and the lifting partition wall 5 is connected to the inner wall of each arc-shaped notch of the plain concrete cushion layer 2. A second steel pad is pre-embedded on the top surface of the pile cap 6. The planar dimensions of the second steel pad are consistent with those of the pile cap. Similarly, holes are opened at corresponding positions on the second steel pad and a second steel sleeve is welded on it. The sleeve is embedded below the top surface of the pile cap 6, and the top surface elevation of the second steel pad is consistent with the design elevation of the top surface of the pile cap 6.

[0050] In this implementation, the plain concrete cushion layer 2 is laid below the bottom plate of the wind turbine foundation 1. The top surface of the plain concrete cushion layer 2 is roughened and multiple drainage channels are set (i.e., constructing the internal drainage system 9 of the foundation) to prevent rainwater from accumulating on its top surface for a long time and soaking the geotextile bag.

[0051] In this implementation, the lifting mechanism can be a lifting jack (e.g., a hydraulically controlled lifting jack), or other similar equipment can be selected, as long as it meets the lifting requirements of the unit foundation.

[0052] In this implementation, the multi-layer geotextile bag 11 is formed by sewing together multiple pieces of long-filament woven geotextile. Its shape and size are determined according to the gravity foundation base plate and the jacking operation space. It is laid between the gravity foundation base plate and the cushion layer to provide grouting space after the subsequent jacking operation.

[0053] In this implementation, the working well 4 is located at the edge of the wind turbine foundation 1, and its axis is consistent with the axis of the pile cap 6. The size of the space should meet the maintenance operation of the jacking equipment and the subsequent jacking operation construction.

[0054] This implementation proposes a construction method for adjustable fan foundations in spoil heaps, including the following steps:

[0055] Step (1): On-site layout to determine the location of each 3-pile cast-in-place pile and the area for foundation treatment with dynamic compaction crushed stone. The treatment area includes the central area of ​​the bottom plate of the wind turbine foundation (its boundary line is about 2.5D to 3D from the edge of the gravity foundation bottom plate, where D is the diameter of the 3-pile cast-in-place pile) and the local area between the two piles along the circumferential direction.

[0056] Step (2): The area determined in step (1) is reinforced using the borehole dynamic compaction method. The filling material in the borehole can be soil excavated on site. Other areas under the bottom plate of the wind turbine foundation 1 are treated using dynamic compaction. The dynamic compaction treatment area 13 is as follows: Figure 7 As shown;

[0057] Step (3): Lay out the centroid position of each cast-in-place pile 3, and construct the pile body of the cast-in-place pile 3 using an appropriate method according to the soil conditions. After completion, perform pile head treatment.

[0058] Step (4): Construct the pile cap using formwork. The top formwork of the pile cap 6 is a second steel pad plate with a welded second steel sleeve. The second steel sleeve is embedded in the pile cap 6, and the top elevation of the second steel pad plate is consistent with the design elevation of the pile cap.

[0059] Step (5): Install a shock-absorbing spherical connecting column 7 with tensile strength on the top surface of the pile cap 6. The bottom plate of the shock-absorbing spherical connecting column 7 is bolted to the second steel pad pre-embedded on the top of the pile cap 6. The top plate of the shock-absorbing spherical connecting column 7 is also bolted to the first steel pad to ensure that the central axis of the shock-absorbing spherical connecting column 7 is consistent with the centerline axis of the pile cap and the cast-in-place pile 3.

[0060] Step (6): Construct plain concrete cushion layer 2. Drainage channels with a slope of 1‰ can be constructed on its surface before the concrete initially sets, or the surface can be roughened simultaneously.

[0061] Step (7): Lay multiple layers of geotextile bags 11 on the top surface of the plain concrete cushion layer 2. The size and shape of the multiple layers of geotextile bags 11 should meet the needs of jacking space, underground pipelines, etc., and ensure that the dimensional allowance meets the construction error. One geotextile bag grouting port 12 should be reserved at the edge of each corresponding jacking area. Figure 6 As shown;

[0062] Step (8): Lay the formwork on the top surface of the plain concrete cushion layer 2 and construct the fan foundation 1;

[0063] Step (9): While constructing steps (4) to (8) above, construct working well 4. The axis of working well 4 should be consistent with the axis of the pile cap, and the size should meet the requirements of the jacking operation. The opening at the bottom of working well 4 should be reinforced, and the working well 4 and the foundation should be connected by the connecting passage brick wall 10 to prevent lateral soil from entering the jacking operation space. A cross beam is set at the bottom of working well 4, but no bottom plate is set. A crushed stone cushion layer of the same height as the cross beam is constructed to meet the drainage requirements inside the well.

[0064] The above description is merely a preferred embodiment of the present invention and is not intended to limit the invention. Various modifications and variations can be made to the present invention by those skilled in the art. Any modifications, equivalent substitutions, improvements, etc., made within the spirit and principles of the present invention should be included within the scope of protection of the present invention.

Claims

1. An adjustable fan foundation for a spoil heap, characterized in that, include: The wind turbine foundation, plain concrete pad, cast-in-place piles, working well, jacking partition wall, pile cap, shock-absorbing spherical connecting column and jacking mechanism are included. The circular plain concrete pad has multiple notches evenly distributed around its perimeter and is located at the bottom of the wind turbine foundation. The top surface of the plain concrete pad is roughened and has multiple drainage channels. The top of the cast-in-place pile is connected to the bottom of the pile cap, and the top of the pile cap is connected to the bottom plate of the shock-absorbing spherical connecting column. The top of the pile cap and the bottom plate of the shock-absorbing spherical connecting column are connected by bolts. The top plate of the shock-absorbing spherical connecting column is connected to the bottom plate of the wind turbine foundation; the top plate of the shock-absorbing spherical connecting column is connected to the bottom plate of the wind turbine foundation by bolts; A first steel pad is installed between the top plate of the shock-absorbing spherical connecting column and the bottom plate of the wind turbine foundation. A hole is made at the position of the bolt hole on the first steel pad, and a first steel sleeve with internal threads is welded along the outer perimeter of the hole. The first steel sleeve is embedded in the bottom plate of the wind turbine foundation for bolt connection. A second steel pad is installed between the base plate of the shock-absorbing spherical connecting column and the top surface of the pile cap. A hole is made at the position of the bolt hole on the second steel pad, and a second steel sleeve with internal threads is welded along the outer periphery of the hole. The second steel sleeve is embedded below the top surface of the pile cap and is used for bolt connection. The bottom plate of the shock-absorbing spherical connecting column is bolted to the second steel pad, and the top plate of the shock-absorbing spherical connecting column is bolted to the first steel pad with the first steel sleeve welded on it. The working well is connected to the lifting partition wall, the lifting partition wall is connected to the inner wall of the notch, the pile cap is located inside the lifting partition wall and connected to the lifting partition wall, and the lifting mechanism for lifting the wind turbine foundation is arranged on the pile cap. The axis of the working well is aligned with the axis of the pile cap; Each of the pile caps is provided with at least two lifting mechanisms symmetrically arranged along the central axis of the shock-absorbing spherical connecting column.

2. The adjustable fan foundation for a spoil heap as described in claim 1, characterized in that, A connecting passage brick wall is built on the side of the lifting partition wall opposite to the working well.

3. The adjustable fan foundation for a spoil heap as described in claim 1, characterized in that, The plain concrete cushion layer is topped with multiple layers of geotextile bags.

4. The adjustable fan foundation for a spoil heap as described in claim 3, characterized in that, The inner wall of the notch is provided with a geotextile bag grouting port.

5. The adjustable fan foundation for a spoil heap as described in any one of claims 1-4, characterized in that, The shock-absorbing spherical connecting column is made of structural steel.

6. A construction method for an adjustable fan foundation for a spoil heap as described in any one of claims 1, 2, or 4, characterized in that, Includes the following processes: Step (1): On-site layout to determine the location of each cast-in-place pile and the scope of the foundation treatment with dynamic compaction crushed stone. The treatment scope includes the central area of ​​the foundation slab and the local area between the two piles along the circumferential direction. Step (2): The area determined in step (1) is reinforced by using the in-hole dynamic compaction method. The filling material in the hole is soil excavated on site. Other areas under the bottom plate of the wind turbine foundation are treated by dynamic compaction. Step (3): Lay out the lines to determine the centroid position of each cast-in-place pile, and construct the pile body of the cast-in-place pile using appropriate methods according to the soil conditions. After completion, perform pile head treatment. Step (4): Construct the pile cap with formwork. The top formwork of the pile cap is a second steel pad plate with a second steel sleeve welded on it. The second steel sleeve is embedded in the pile cap. The top elevation of the second steel pad plate is consistent with the design elevation of the pile cap. Step (5): Install a shock-absorbing spherical connecting column with tensile strength on the top surface of the pile cap. The bottom plate of the shock-absorbing spherical connecting column is bolted to the second steel pad. The top plate of the shock-absorbing spherical connecting column is bolted to the first steel pad with the first steel sleeve welded on it, so as to ensure that the central axis of the shock-absorbing spherical connecting column is consistent with the centerline axis of the pile cap and the cast-in-place pile. Step (6): Construct plain concrete cushion layer, and construct drainage grooves with a slope of 1‰ on its surface before the concrete initially sets, or simultaneously roughen the surface. Step (7): Lay multiple layers of geotextile bags on the top surface of the plain concrete cushion layer. The size and shape of the geotextile bags should meet the needs of the jacking space and the pipelines to be laid down, so that the size allowance can meet the construction error. Reserve one grouting port at the edge of the corresponding jacking area. Step (8): Lay the formwork on the top surface of the plain concrete cushion layer and construct the fan foundation; Step (9): While constructing in steps (4) to (8), construct the working well. The axis of the working well is consistent with the axis of the pile cap. The size meets the requirements of the jacking operation. The opening at the bottom of the working well is reinforced. The working well and the fan foundation are connected by a brick wall to prevent lateral soil from entering the jacking operation space. A cross beam is set at the bottom of the working well. No bottom plate is set. A crushed stone cushion layer of the same height as the cross beam is constructed to meet the drainage requirements inside the well.

Citation Information

Patent Citations

  • Pile type adjustable fan foundation and construction method

    CN113833012A

  • Box-type adjustable fan foundation and construction method thereof

    CN118207899A