Connection channel synchronous construction system and construction platform

By arranging four or more tracks in the main tunnel and docking tracks and layout areas on the synchronous construction platform, the problem of mutual interference in material transportation during the synchronous construction of the main tunnel and contact passages is solved, achieving efficient material transportation and improving construction efficiency. .

CN118774945AActive Publication Date: 2024-10-15CHINA RAILWAY ENGINEERING EQUIPMENT GROUP CO LTD

Patent Information

Application Number
CN202410960653.8
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-17
Publication Date
2024-10-15
Estimated Expiration
2044-07-17

AI Technical Summary

Technical Problem

In the existing technology, material transportation interferes with each other when the main tunnel and contact passage are constructed simultaneously, resulting in low construction efficiency.

Method used

Design a synchronous construction system for contact passages, including arranging more than four lines of main track in the main tunnel, two lines of track for the passage of material transport vehicles in the main tunnel, and two lines of track for the passage of material transport vehicles of the contact passage, and synchronous construction A docking track and layout area are set up on the platform to ensure that material transport vehicles do not interfere with each other.

Benefits of technology

It achieves non-interference in the material transportation of the main tunnel and the connecting channel, improves construction efficiency, and ensures synchronous construction and synchronous transportation of materials.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118774945A_ABST
    Figure CN118774945A_ABST
Patent Text Reader

Abstract

The invention belongs to the technical field of tunneling, and particularly provides a contact channel synchronous construction system and a construction platform. The synchronous construction system comprises a synchronous construction platform and four or more main rails arranged in a main tunnel, two main rails are used for allowing a main tunnel material transport vehicle to pass through, and the other two main rails are used for allowing a connection channel material transport vehicle to pass through. The synchronous construction platform is provided with walking wheels capable of walking along the main rails, two butt-joint rails and an arrangement area used for arranging the communication channel tunneling equipment, the two butt-joint rails are located on one transverse side of the arrangement area, and butt-joint sections used for being in butt joint with the two main rails allowing a main tunnel material transport vehicle to pass through are arranged on the front portions and the rear portions of the two butt-joint rails correspondingly. The construction platform is a synchronous construction platform in the system. During construction, material transportation of the connection channel and the main tunnel is independent, the main tunnel material transportation vehicle and the connection channel material transportation vehicle do not interfere with each other, synchronous construction and synchronous transportation can be achieved, and higher construction efficiency is achieved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of tunnel excavation, and in particular relates to a communication channel synchronous construction system and a construction platform. Background Art

[0002] The "Metro Design Code" (GB 50157-2013) and the "Railway Tunnel Disaster Prevention, Evacuation and Rescue Engineering Design Code" (TB10020-2017) stipulate that between two single-track section tunnels, when the continuous length of the tunnel is greater than 600m, a communication passage should be set up, and two-way opening Class A fire doors should be installed at both ends of the passage.

[0003] The mechanical method of excavating the communication channel using full-section tunnel boring equipment has high efficiency and safety, and has been gradually promoted and applied. When the mechanical method is used to excavate the communication channel, the relevant supporting devices, such as the starting device, the electric control cabinet, the hydraulic pump station and other devices need to be arranged in the main tunnel, which will inevitably occupy the space in the main tunnel. Therefore, in order to avoid the related supporting devices during the construction of the communication channel affecting the passage of material transport vehicles during the construction of the main tunnel, the communication channel is generally constructed after the construction of the main tunnel is completed. It is not difficult to understand that there is still room for improvement in construction efficiency by dividing the construction of the communication channel and the main tunnel into two independent processes.

[0004] The utility model patent with the authorization announcement number CN219840653U discloses a synchronous construction platform for the construction of a connecting channel, which includes a frame, on which a first track, a second track and a track-changing device (turnout) are arranged, and the first track and the second track can both dock with the main track in the main tunnel, and the track-changing device is used to switch the docking state between the first track and the second track and the main track. Among them, the first track can support the jacking system required for the excavation construction of the connecting channel, and the second track can be used for the passage of material vehicles and personnel during the construction of the main tunnel. While the main tunnel is under construction, the excavation equipment of the connecting channel can be pushed forward to excavate the connecting channel.

[0005] The above patent only considers the material transportation problem of the main tunnel during construction, while the construction of the connecting channel also requires the transportation of materials, such as the pipe segments required for assembly and the slag generated during excavation. In the above patent, it can be determined that the main track in the main tunnel only includes two or two-line tracks. When the materials required to be transported by the main tunnel and the connecting channel are transported by different transport vehicles, there is inevitably a phenomenon of vehicles meeting. When meeting, it is necessary to flexibly apply the first track and the second track on the synchronous construction platform so that one of the material transport vehicles avoids the other material transport vehicle. At this time, one of the material transport vehicles needs to stop and wait for a period of time, which affects the material transportation. In addition, if one of the material transport vehicles fails and stops at the rear side of the synchronous construction platform in the main track, the other material transport vehicle needs to wait for the faulty vehicle to be repaired or towed away before it can pass normally. If the waiting time is too long, the excavation equipment of the main tunnel or the connecting channel needs to be shut down for a period of time, thereby affecting the construction efficiency. Therefore, how to ensure that the material transportation of the main tunnel and the connecting channel does not affect each other is still a problem that needs to be solved at present. Summary of the invention

[0006] The purpose of the present invention is to provide a communication channel synchronous construction system to solve the technical problem in the prior art that the material transportation affects each other during the synchronous construction of the main tunnel and the communication channel, resulting in low construction efficiency. The purpose of the present invention is also to provide a communication channel synchronous construction platform, which can be used for the construction of a main tunnel with more than four main tracks, so as to achieve non-interference transportation of main tunnel materials and communication channel materials, thereby improving construction efficiency.

[0007] To achieve the above-mentioned purpose, the technical solution of the communication channel synchronous construction system provided by the present invention is:

[0008] A synchronous construction system for a communication channel comprises a synchronous construction platform and more than four main tracks arranged in a main tunnel and spaced apart in a transverse direction, wherein two main tracks are provided for passage of material transport vehicles for the main tunnel and two main tracks are provided for passage of material transport vehicles for the communication channel. The synchronous construction platform is provided with running wheels capable of running along the more than two main tracks. Two docking tracks are provided for passage of material transport vehicles for the main tunnel and a layout area for arranging excavation equipment for the communication channel are provided on the synchronous construction platform. The two docking tracks are located on one lateral side of the layout area, and docking sections for docking with the two main tracks for passage of material transport vehicles for the main tunnel are provided at both front and rear ends of the two docking tracks.

[0009] As a further improvement, the two docking rails each include an outward expansion section offset toward a side away from the arrangement area relative to their respective docking sections.

[0010] As a further improvement, the synchronous construction platform includes a large-span section and a small-span section connected to the rear side of the large-span section, the lateral span of the large-span section is larger than the span between the two outermost main rails, the layout area is arranged in the large-span section, the lateral span of the small-span section is larger than the lateral span of the two main rails for the passage of material transport vehicles in the main tunnel, the running wheels configured in the small-span section are used to travel along the two main rails for the passage of material transport vehicles in the main tunnel, the connection position of the small-span section and the large-span section is located at one lateral end of the large-span section, and the space between the small-span section and the other lateral end of the large-span section meets the passage of material transport vehicles in the connecting channel.

[0011] As a further improvement, the running wheels configured for the large span section are used to run along the two outermost main tracks.

[0012] As a further improvement, the arrangement area is arranged with connecting channel excavation equipment, and the connecting channel excavation equipment includes a material transfer device for receiving materials from the connecting channel material transport vehicle and transferring them forward.

[0013] As a further improvement, the material transfer device includes a column arranged on the synchronous construction platform and a track beam supported by the column. The track beam is used for the material crane to travel. The track beam is composed of a feeding section, a transition section and a receiving section from front to back. The feeding section is located in the center of the synchronous construction platform, and the receiving section is offset to the side away from the docking track relative to the feeding section.

[0014] As a further improvement, the layout area is arranged with connecting channel excavation equipment, which includes an excavation main machine and a slag discharge device for receiving the slag discharged by the excavation main machine and transporting the slag to the slag bucket of the connecting channel material transport vehicle.

[0015] As a further improvement, the slag discharge device is composed of a slag discharge pipe connected to the tail of the screw conveyor of the main boring machine.

[0016] The beneficial effect is that the present invention pioneers a synchronous construction system for the liaison channel that can realize the non-interference of the main tunnel material transportation and the liaison channel material transportation. Specifically, the main track is a main track with more than four lines. During construction, the main tunnel material transport vehicle that transports the main tunnel related materials can pass along two of the tracks, and the liaison channel material transport vehicle that transports the liaison channel related materials can pass along the other two main tracks. When walking along the main track, the main tunnel materials and the liaison channel materials do not interfere with each other. At the same time, a docking track and a layout area are provided on the synchronous construction platform. The relevant excavation equipment during the construction of the liaison channel can be arranged in the layout area. The main tunnel material transport vehicle can move from the main track along the docking section to the docking track of the synchronous construction platform. Since the docking track is on one side of the layout area, the main tunnel material transport vehicle will not affect the normal operation of the liaison channel construction equipment at this time. This ensures the synchronous construction of the liaison channel and the main tunnel, as well as the synchronous transportation of materials, thereby improving the efficiency of synchronous construction.

[0017] To achieve the above purpose, the technical solution of the communication channel synchronous construction platform provided by the present invention is:

[0018] A synchronous construction platform for a connecting channel is provided with running wheels for running along more than two main tracks in a main tunnel. The synchronous construction platform is provided with two docking tracks for passage of material transport vehicles of the main tunnel and a layout area for arranging tunneling equipment of the connecting channel. The two docking tracks are located on one lateral side of the layout area. Both front and rear ends of the two docking tracks are provided with docking sections for docking with the two main tracks for passage of material transport vehicles of the main tunnel.

[0019] As a further improvement, the two docking rails each include an outward expansion section offset toward a side away from the arrangement area relative to their respective docking sections.

[0020] As a further improvement, the synchronous construction platform of the connecting channel includes a large-span section and a small-span section connected to the rear side of the large-span section. The lateral span of the large-span section satisfies that it is larger than the span between the two outermost main tracks in the main tunnel. The layout area is arranged in the large-span section. The lateral span of the small-span section satisfies that it is larger than the lateral span of the two main tracks in the main tunnel for the passage of the main tunnel material transport vehicles. The running wheels configured in the small-span section are used to travel along the two main tracks for the passage of the main tunnel material transport vehicles. The connection position of the small-span section and the large-span section is located at one lateral end of the large-span section, and the space between the small-span section and the other lateral end of the large-span section meets the passage of the connecting channel material transport vehicles.

[0021] As a further improvement, the running wheels configured in the large span section are used to run along the two outermost main tracks in the main tunnel.

[0022] As a further improvement, the arrangement area is arranged with connecting channel excavation equipment, and the connecting channel excavation equipment includes a material transfer device for receiving materials from the connecting channel material transport vehicle and transferring them forward.

[0023] As a further improvement, the material transfer device includes a column arranged on the synchronous construction platform and a track beam supported by the column. The track beam is used for the material crane to travel. The track beam is composed of a feeding section, a transition section and a receiving section from front to back. The feeding section is located in the center of the synchronous construction platform, and the receiving section is offset to the side away from the docking track relative to the feeding section.

[0024] As a further improvement, the layout area is arranged with connecting channel excavation equipment, which includes an excavation main machine and a slag discharge device for receiving the slag discharged by the excavation main machine and transporting the slag to the slag bucket of the connecting channel material transport vehicle.

[0025] As a further improvement, the slag discharge device is composed of a slag discharge pipe connected to the tail of the screw conveyor of the main boring machine.

[0026] The beneficial effect is that the present invention pioneers a synchronous construction platform that can be used for the construction of a main tunnel that is arranged with more than four main tracks arranged at intervals in the horizontal direction. Specifically, during construction, the main tunnel material transport vehicle that transports materials related to the main tunnel can travel along two of the tracks, and the liaison channel material transport vehicle that transports materials related to the liaison channel can travel along the other two main tracks. When traveling along the main tracks, the main tunnel materials and the liaison channel materials do not interfere with each other. At the same time, a docking track and a layout area are provided on the synchronous construction platform. The relevant excavation equipment during the construction of the liaison channel can be arranged in the layout area. The main tunnel material transport vehicle can travel from the main track along the docking section to the docking track of the synchronous construction platform. Since the docking track is on one side of the layout area, the main tunnel material transport vehicle will not affect the normal operation of the liaison channel construction equipment at this time. This ensures the synchronous construction of the liaison channel and the main tunnel, as well as the synchronous transportation of materials, thereby improving the efficiency of synchronous construction. BRIEF DESCRIPTION OF THE DRAWINGS

[0027] Figure 1 It is a partial axial view (main tunnel) of the embodiment of the synchronous construction system for the communication channel of the present invention during construction;

[0028] Figure 2 It is a front view of an embodiment of the synchronous construction system of the communication channel in the present invention;

[0029] Figure 3 It is a top view of the docking section (track beam omitted) of the embodiment of the synchronous construction system of the communication channel in the present invention;

[0030] Figure 4It is an axial view of the position of the outer expansion section during the construction of the embodiment of the synchronous construction system of the communication channel in the present invention;

[0031] Figure 5 It is an axial view of the position of the docking section during the construction of the embodiment of the synchronous construction system for the communication channel in the present invention;

[0032] Figure 6 It is a top view of the docking section position (including the track beam) during the construction of the embodiment of the synchronous construction system of the communication channel in the present invention;

[0033] Figure 7 It is a schematic diagram of the slag discharge structure of the excavation main machine during the construction of the embodiment of the communication channel synchronous construction system in the present invention.

[0034] Description of reference numerals:

[0035] 1. Main track; 2. Synchronous construction platform; 3. Material transport vehicle for main tunnel; 4. Material transport vehicle for connecting channel; 5. Excavation main machine; 101. First track; 102. Second track; 201. Traveling wheel; 202. Docking track; 203. Column; 204. Material crane; 205. Reverse pulling device; 206. Track beam; 207. Small span section; 208. Large span section; 2021. Docking section; 2022. Outward expansion section; 2061. Feeding section; 2062. Transition section; 2063. Receiving section; 401. Muck truck; 402. Segment truck; 501. Screw conveyor; 502. Muck discharge pipe. DETAILED DESCRIPTION

[0036] When the main tunnel and the connecting channel are constructed simultaneously, the most basic premise is that the related supporting equipment used in the construction of the connecting channel cannot affect the passage of the material transport vehicle for the main tunnel construction materials (hereinafter referred to as the main tunnel material transport vehicle). During the construction of the connecting channel, materials also need to be transported. The materials mainly include the pipe segments required for assembly and the slag generated during the excavation process. Naturally, corresponding transport vehicles are also required, namely the connecting channel material transport vehicle. The connecting channel material transport vehicle can travel along the main track to transport materials to the corresponding location.

[0037] In order to solve the problem of mutual interference between the material transport vehicle for the liaison channel and the material transport vehicle for the main tunnel during transportation, the basic technical concept of the present invention is to arrange a main track including four or more tracks in the main tunnel, and the material transport vehicle for the main tunnel and the material transport vehicle for the liaison channel respectively travel along the corresponding two-line main track, so that the material transport vehicle for the main tunnel and the material transport vehicle for the liaison channel will not interfere with each other. At the same time, two docking tracks that can be docked with the two-line tracks corresponding to the material transport vehicle for the main tunnel are arranged on the synchronous construction platform, and the front and rear ends of the two docking tracks can be docked with the above-mentioned two-line tracks. During construction, the relevant equipment required for excavation of the liaison channel can be placed on the synchronous construction platform. While excavating the liaison channel, the material transport vehicle for the main tunnel can go from the main track to the docking track and then to the main track, so that through the synchronous construction platform, the material transport vehicle for the liaison channel can travel along its corresponding two-line track to a position close to the synchronous construction platform to transport materials during the construction of the liaison channel.

[0038] The present invention is further described in detail below in conjunction with embodiments and drawings.

[0039] Specific embodiments of the communication channel synchronous construction system provided by the present invention:

[0040] The communication channel synchronous construction system provided in this embodiment is as follows: Figure 1-Figure 3 As shown, it includes a synchronous construction platform 2 and a main track 1 that can be arranged in the main tunnel when in use. The main track 1 is a four-line track (I-shaped), and each main track 1 is arranged at intervals along the transverse direction of the main tunnel. Among the four-line main tracks 1, two lines of main tracks 1 are for the main tunnel material transport vehicles 3 to pass and walk, and the other two lines of main tracks 1 are for the communication channel material transport vehicles 4 to pass and walk. For the convenience of expression, as Figure 3 As shown, the two-line main track 1 for the communication channel material transport vehicle 4 to pass through is defined as the first track 101, and the two-line main track 1 for the main tunnel material transport vehicle 3 to pass through is defined as the second track 102.

[0041] It should be noted here that the connecting channel material transport vehicle 4 and the main tunnel material transport vehicle 3 do not refer to a specific vehicle or a certain section of the vehicle. According to the excavation requirements of the connecting channel and the main tunnel, they may include slag trucks for discharging slag, segment trucks for transporting segments, and tool transport trucks for transporting tools, etc.

[0042] The synchronous construction platform 2 is equipped with running wheels 201 that can run along the two-line main rails 1. The two-line main rails 1 corresponding to the running wheels 201 can support the synchronous construction platform 2. The specific number of running wheels 201 is not limited here, and those skilled in the art can flexibly select them according to the carrying capacity. Preferably, taking the carrying capacity into consideration, when the lateral span of the synchronous construction platform 2 is met, the running wheels 201 can be configured to run along the outermost two-line main rails 1. This can ensure that the running wheels 201 have a longer support span for the synchronous construction platform 2, thereby having a stronger load-bearing support capacity. In other embodiments, according to the weight of the equipment carried on the synchronous construction platform 2 and the different distribution of the center of gravity layout, the running wheels 201 can also be configured to run along other two-line main rails 1, for example Figure 1 The 1st and 3rd lines from left to right are main track 1.

[0043] Two docking tracks 202 for the main tunnel material transport vehicle 3 to pass through are provided on the synchronous construction platform 2. Both front and rear ends of the two docking tracks 202 have docking sections 2021, and the docking sections 2021 can be docked with the second track 102. During construction, the main tunnel material transport vehicle 3 can go from the second track 102 along the docking section 2021 to the docking track 202, and after walking a distance along the docking track 202, it can return to the main track 1 from the docking section 2021 at the other end to achieve normal passage.

[0044] The synchronous construction platform 2 is also provided with a layout area for arranging the communication channel excavation equipment. The communication channel excavation equipment refers to the related equipment required for the construction of the communication channel, including Figure 1 The excavation host 5 shown in the figure, the supporting equipment required by the excavation host 5, such as the electric control cabinet, the hydraulic pump station, and the material transfer device, etc. The material transfer device is used to receive the material from the material transport vehicle 4 of the communication channel and transfer it forward. The docking track 202 mentioned above is located on the lateral side of the layout area, that is, Figure 1 On the right side of the figure, when the main tunnel material transport vehicle 3 moves along the docking track 202, the communication channel construction equipment and the main tunnel material transport vehicle 3 will not interfere with each other, thereby ensuring the normal progress of the synchronous construction.

[0045] It can be seen from the analysis that in this embodiment, during construction, the main tunnel material transport vehicle 3 and the communication channel material transport vehicle 4 move along different tracks. Figure 3As shown, the main tunnel material transport vehicle 3 can continue to move along the second track 102 after connecting to the track 202, and the communication channel material transport vehicle 4 can move along the first track 101 to the rear side of the synchronous construction platform 2 to meet the needs of communication channel construction. Compared with the prior art, during construction, the material transportation during the communication channel construction and the main tunnel construction in this embodiment is independent of each other, the main tunnel material transport vehicle 3 and the communication channel material transport vehicle 4 will not affect each other, and can be constructed and transported synchronously, with higher construction efficiency.

[0046] like Figure 1-Figure 3 As shown in the figure, since more equipment is needed for the construction of the connecting channel, the synchronous construction platform 2 is also long in the front-to-back direction. Among the different related equipment, the main boring machine 5 has the largest volume and occupies the most space. For a main tunnel with a smaller diameter, the main track 1 is generally arranged at the bottom of the main tunnel, and the space at the bottom of the main tunnel is limited. At this time, there may be a problem that the main tunnel material transport vehicle 3 cannot pass through the docking track 202 smoothly. Figure 3 and Figure 4 As shown, in the preferred embodiment, the two docking tracks 202 also include an outward expansion section 2022 offset outwardly relative to the docking section 2021, and the distance between the outward expansion section 2022 and the layout area is greater than the distance between the docking section 2021 and the layout area, so that it can be ensured that the main tunnel material transport vehicle 3 will not interfere with the larger equipment in the layout area when passing through. Of course, in other embodiments, for a main tunnel with a larger diameter, the distance between the two adjacent lines in the main track 1 is sufficient, and the width of the synchronous construction platform 2 is also sufficient to place the equipment, then the docking track 202 can also be made into a track that is consistent with the extension direction of the second track 102 in the main track 1.

[0047] In order to move the communication channel material transport vehicle 4 to a position closer to the main excavation machine 5 for the convenience of receiving and transporting materials, further, from the perspective of different lateral span sizes, such as Figure 3 As shown, the synchronous construction platform 2 includes a large span section 208 and a small span section 207. The small span section 207 is connected to the rear side of the large span section 208, and the connection method is preferably hinged. The lateral span of the large span section 208 is larger than the span between the two outermost main tracks 1, so that the synchronous construction platform 2 can have a larger area for placing equipment. The layout area is actually located in the large span section 208, and the running wheels 201 configured in the small span section 207 actually run along the second track 102. Figure 3As shown, the connection position of the small span section 207 and the large span section 208 is located at one lateral end of the large span section 208, and the space between the small span section 207 and the other lateral end of the large span section 208 is sufficient for the communication channel material transport vehicle 4 to pass through. In this way, during construction, the communication channel material transport vehicle 4, such as the muck truck 401 and the segment truck 402, can be moved to a position close to the large span section 208, that is, closer to the equipment configured in the layout area, to facilitate material conveying and transportation. As mentioned above, the lateral span of the large span section 208 is relatively large. At this time, considering the support and bearing capacity, the walking wheels 201 configured in the large span section 208 preferably travel along the outermost two-line main track 1. It should be noted here that the travel speed of the main tunnel material transport vehicle 3 is very slow, and the second tracks 102 located in different span sections do not need to be welded or connected with fasteners, and the ends can be smoothly docked to meet the passage of the main tunnel material transport vehicle 3.

[0048] In addition, regardless of whether the synchronous construction platform 2 has equal spans in the front and rear length directions or includes different sections of different spans. For main tunnels with smaller diameters, such as main tunnels with a diameter of less than 7m, during actual construction, the connecting channel material transport vehicle 4 is actually located on the side of the main tunnel that is not centered. However, the volume of the tunneling main machine 5 is relatively large, and the tail end of the tunneling main machine 5 will reach the center of the main tunnel. In order to facilitate the connecting channel material transport vehicle 4 to transport materials to the location of the tunneling main machine 5, in this embodiment, the material transfer device described above includes columns 203 and track beams 206. The columns 203 are directly arranged on the connecting channel construction platform, and the track beams 206 are arranged on the columns 203 and supported by the columns 203. The track beams 206 can be used for the material crane 204 (track crane) to travel. As Figure 6 As shown, the track beam 206 is composed of a feeding section 2061, a transition section 2062 and a receiving section 2063 from front to back. The feeding section 2061 (in vertical projection) is located at the center of the synchronous construction platform 2, and the receiving section 2063 is offset relative to the feeding section 2061 toward the first track 101 or away from the docking track 202. In this way, the material crane 204 can move along the track beam 206 to the top close to the segment vehicle 402, and lift the segments or other materials in the segment vehicle 402 to the position of the tunneling main machine 5, as shown in FIG. Figure 5 As shown, the position of the material crane 204 can be moved as a whole to the material transport vehicle 4 close to the communication channel to facilitate the lifting of materials. Similarly, in other embodiments, if the diameter of the main tunnel is large and there is enough space inside the main tunnel to meet the needs of the main boring machine 5 to start and transport the corresponding materials, the track beam 206 can also be made into a straight line. Alternatively, other forms of material transfer devices are used, such as a material transfer trolley (vehicle-mounted crane) equipped with a boom, etc. The material transfer trolley can move flexibly on the synchronous construction platform 2, and transfer and transport materials between the segment vehicle 402 and the main boring machine 5.

[0049] The tunneling host 5 can be a shield machine host or a pipe jacking machine host. Figure 1 As shown, during construction, a back-pull device 205 needs to be configured. If the tunneling machine 5 is a pipe jacking machine, the back-pull device 205 needs to be configured with a back-pull oil cylinder, which pushes the tunneling machine 5 and the pipe segments forward. In addition, the tunneling machine 5 is also connected to a slag discharge device, which is mainly used to receive slag from the tunneling machine 5 and discharge the slag into the slag bucket of the communication channel material transport vehicle 4, that is, the slag vehicle 401.

[0050] For a main tunnel with a small diameter, in order to ensure that the slag discharged by the screw conveyor 501 of the main excavation machine 5 can be smoothly discharged to the slag truck 401, such as Figure 7 As shown, a slag discharge pipe 502 with a turning section is connected to the tail end of the screw conveyor 501 of the main excavation machine 5. The slag discharge pipe 502 can guide the slag to flow to the slag truck 401 to achieve smooth slag discharge. The slag discharge pipe 502 forms the above-mentioned slag discharge device. The size of the slag discharge pipe 502 is more compact and more suitable for main tunnels with small diameters. In fact, for main tunnels with larger diameters, the slag discharge device can also use a belt conveyor. One end of the belt conveyor can be set below the slag discharge port at the tail of the screw conveyor 501, and the other end extends out of the synchronous construction platform 2. During construction, the slag truck 401 can walk to the bottom of the belt conveyor to receive the slag.

[0051] It should also be noted that, in different implementations, the main track 1 can also be arranged with five or even more tracks. Most basically, there must still be two main tracks 1 for the main tunnel material transport vehicle 3 to pass through, and two main tracks 1 for the communication channel material transport vehicle 4 to pass through. However, if possible, the synchronous construction platform 2 can also be configured with three rows of walking wheels 201 on the left, middle and right, and travel along the three-line main track 1.

[0052] Specific embodiments of the communication channel synchronous construction platform in the present invention:

[0053] The embodiment of the communication channel synchronous construction platform is the synchronous construction platform described in the embodiment of the communication channel synchronous construction system described above, and will not be described in detail here.

[0054] Finally, it should be noted that the above is only a preferred embodiment of the present invention and is not intended to limit the present invention. Although the present invention is described in detail with reference to the aforementioned embodiments, those skilled in the art can still modify the technical solutions recorded in the aforementioned embodiments without creative work, or replace some of the technical features therein with equivalents. Any modification, equivalent replacement, improvement, etc. made within the spirit and principles of the present invention shall be included in the protection scope of the present invention.

Claims

1. A communication channel synchronous construction system, characterized in that: It includes a synchronous construction platform and more than four main tracks arranged in the main tunnel and arranged at intervals along the horizontal direction, wherein two main tracks are for the passage of material transport vehicles for the main tunnel, and another two main tracks are for the passage of material transport vehicles for the connecting channel. The synchronous construction platform is equipped with running wheels that can run along the two or more main tracks. The synchronous construction platform is provided with two docking tracks for the passage of material transport vehicles for the main tunnel and a layout area for arranging excavation equipment for the connecting channel. The two docking tracks are located on one lateral side of the layout area, and docking sections for docking with the two main tracks for the passage of material transport vehicles for the main tunnel are provided at both the front and rear ends of the two docking tracks.

2. The communication channel synchronous construction system according to claim 1 is characterized in that: The two docking rails each include an outward expansion section offset toward a side away from the arrangement area relative to the respective docking sections.

3. The communication channel synchronous construction system according to claim 1 or 2, characterized in that: The synchronous construction platform includes a large-span section and a small-span section connected to the rear side of the large-span section. The lateral span of the large-span section is larger than the span between the two outermost main tracks. The layout area is arranged in the large-span section. The lateral span of the small-span section is larger than the lateral span of the two main tracks for the passage of material transport vehicles in the main tunnel. The running wheels configured in the small-span section are used to travel along the two main tracks for the passage of material transport vehicles in the main tunnel. The connection position of the small-span section and the large-span section is located at one lateral end of the large-span section. The space between the small-span section and the other lateral end of the large-span section meets the passage of material transport vehicles in the connecting channel.

4. The communication channel synchronous construction system according to claim 3 is characterized in that: The traveling wheels configured in the large span section are used to travel along the two outermost main tracks.

5. The communication channel synchronous construction system according to claim 1 or 2, characterized in that: The arrangement area is arranged with connecting channel excavation equipment, and the connecting channel excavation equipment includes a material transfer device for receiving materials on the connecting channel material transport vehicle and transferring them forward.

6. The communication channel synchronous construction system according to claim 5 is characterized in that: The material transfer device includes a column arranged on the synchronous construction platform and a track beam supported by the column. The track beam is used for the material crane to travel. The track beam is composed of a feeding section, a transition section and a receiving section from front to back. The feeding section is located in the center of the synchronous construction platform, and the receiving section is offset to the side away from the docking track relative to the feeding section.

7. The communication channel synchronous construction system according to claim 1 or 2, characterized in that: The arrangement area is arranged with connecting channel excavation equipment, which includes an excavation main machine and a slag discharge device for receiving slag discharged by the excavation main machine and transporting the slag to a slag bucket of a connecting channel material transport vehicle.

8. The communication channel synchronous construction system according to claim 7 is characterized in that: The slag discharge device consists of a slag discharge pipe connected to the tail of the screw conveyor of the main excavation machine.

9. A communication channel synchronous construction platform, characterized in that: The synchronous construction platform of the connecting channel is equipped with running wheels for running along more than two main tracks in the main tunnel. The synchronous construction platform is provided with two docking tracks for the passage of material transport vehicles of the main tunnel and a layout area for arranging the excavation equipment of the connecting channel. The two docking tracks are located on one lateral side of the layout area. Both the front and rear ends of the two docking tracks are provided with docking sections for docking with the two main tracks for the passage of material transport vehicles of the main tunnel.

10. The communication channel synchronous construction platform according to claim 9 is characterized in that: The two docking rails each include an outward expansion section offset toward a side away from the arrangement area relative to the respective docking sections.

11. The communication channel synchronous construction platform according to claim 9 or 10, characterized in that: The synchronous construction platform of the connecting channel includes a large-span section and a small-span section connected to the rear side of the large-span section. The lateral span of the large-span section meets the requirement of being larger than the span between the two outermost main tracks in the main tunnel. The layout area is arranged in the large-span section. The lateral span of the small-span section meets the requirement of being larger than the lateral span of the two main tracks in the main tunnel for the passage of the main tunnel material transport vehicles. The running wheels configured in the small-span section are used to run along the two main tracks for the passage of the main tunnel material transport vehicles. The connection position of the small-span section and the large-span section is located at one lateral end of the large-span section. The space between the small-span section and the other lateral end of the large-span section meets the requirement of the passage of the connecting channel material transport vehicles.

12. The communication channel synchronous construction platform according to claim 11, characterized in that: The traveling wheels configured in the large span section are used to travel along the two outermost main tracks in the main tunnel.

13. The communication channel synchronous construction platform according to claim 9 or 10, characterized in that: The arrangement area is arranged with connecting channel excavation equipment, and the connecting channel excavation equipment includes a material transfer device for receiving materials on the connecting channel material transport vehicle and transferring them forward.

14. The communication channel synchronous construction platform according to claim 13, characterized in that: The material transfer device includes a column arranged on the synchronous construction platform and a track beam supported by the column. The track beam is used for the material crane to travel. The track beam is composed of a feeding section, a transition section and a receiving section from front to back. The feeding section is located in the center of the synchronous construction platform, and the receiving section is offset to the side away from the docking track relative to the feeding section.

15. The communication channel synchronous construction platform according to claim 9 or 10, characterized in that: The arrangement area is arranged with connecting channel excavation equipment, which includes an excavation main machine and a slag discharge device for receiving slag discharged by the excavation main machine and transporting the slag to a slag bucket of a connecting channel material transport vehicle.

16. The communication channel synchronous construction platform according to claim 15, characterized in that: The slag discharge device consists of a slag discharge pipe connected to the tail of the screw conveyor of the main excavation machine.

Citation Information

Patent Citations

  • Synchronous construction platform for tunnel group T-shaped contact channel construction

    CN219840653U

  • Shield tunneling machine for tunnel connecting passageway and connecting passageway tunneling method of shield tunneling machine

    CN106437735A

  • Four-rail three-line deslagging and transporting method for variable cross-section tunnel anchor

    CN115584744A

  • Synchronous tunneling construction method for main tunnel and contact channel

    CN117605480A

  • Connection channel construction trolley and construction system

    CN118187903A

Cited By

  • Method and system for synchronous construction of contact channel and starting trolley of contact channel shield tunneling machine

    CN121296132A

  • Synchronous construction system and platform for cross passage

    WO2026016364A1