Hybrid time scale electric heating integrated energy system optimization method considering source-load game

By constructing multiple coupling models and dynamic dispatching frameworks in the electric and thermal integrated energy system, we optimize energy prices and equipment output, solve the problem of supply and demand mismatch and system dispatch difficulty, achieve efficient energy utilization and cost optimization, and promote the development of integrated energy Systematic sustainable development.

CN118780463APending Publication Date: 2024-10-15YANSHAN UNIV
View PDF 0 Cites 3 Cited by

Patent Information

Application Number
CN202410745716.8
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-06-11
Publication Date
2024-10-15

AI Technical Summary

Technical Problem

In power systems containing a high proportion of renewable energy, supply and demand mismatch problems and different system dynamic characteristics make integrated energy system dispatching more difficult. A method to optimize the interaction between the system and loads is needed to achieve efficient energy utilization and cost-minimization. optimization.

Method used

A hybrid time-scale electrothermal comprehensive energy system optimization method that considers the source-load game is adopted. By constructing a multi-coupled electrothermal system, a load model and a dynamic dispatch framework are established, and a differential genetic algorithm and Cplex solver are used to optimize energy prices and equipment output to ensure that the system Balance of benefits and user costs.

Benefits of technology

It achieves system optimization scheduling on different time scales, avoids conflicts of interest, reduces load energy costs, and promotes the sustainable development of integrated energy systems.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118780463A_ABST
    Figure CN118780463A_ABST
Patent Text Reader

Abstract

The invention discloses a mixed time scale electric heating integrated energy system optimization method considering a source-load game, and belongs to the technical field of integrated energy systems, and the method comprises the following steps: S1, constructing a multi-coupled electric heating integrated energy system; s2, modeling aiming at electrical and thermal flexible loads; s3, dynamic modeling considering the heat transfer characteristics of the heat distribution pipeline; s4, modeling aiming at the power system network and each system device; s5, based on different dynamic characteristics of the electric heating system, establishing a mixed time scale optimization scheduling framework; s6, establishing a supply and demand double-layer game optimization model, customizing an energy consumption price, and optimizing the output and the electric heating load of each device of the system; and S7, solving the double-layer game optimization model by adopting a differential genetic algorithm and a Cplex solver. The system energy operation efficiency can be effectively improved, the interests of the comprehensive energy system and users are guaranteed, and practical popularization of the comprehensive energy system in practical engineering is promoted.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention belongs to the technical field of integrated energy systems, and in particular relates to an optimization method for a hybrid time-scale electric-thermal integrated energy system taking source-load game into consideration. Background Art

[0002] As the global climate change problem becomes increasingly serious, the public's environmental awareness continues to increase, which has prompted the power generation industry to shift from relying on traditional fossil fuels to using low-carbon renewable energy. However, with the gradual increase in the proportion of renewable energy access to the energy system and the deep transformation of the power system structure, the supply and demand relationship in the power system has undergone tremendous changes. Since most renewable energy sources such as wind power generation and photovoltaic power generation are uncertain and volatile, this has led to a mismatch between supply and demand in new power systems containing a high proportion of renewable energy. At the same time, the traditional energy supply method of directly adjusting the system output power according to the load side demand is no longer applicable.

[0003] The electric-thermal integrated energy system can organically link the power system and the thermal system through coupling equipment, providing a new solution for the consumption of new energy. However, the different dynamic characteristics of different systems have brought new challenges to the coordinated scheduling of the integrated energy system. In order to fully tap the flexibility of the load side, it is necessary to consider different load characteristics on the load side and establish a corresponding demand response model to achieve effective interaction between the load and the system. In order to promote the sustainable development of the integrated energy system, the interactive relationship between the system and the load needs to be continuously explored and optimized during the operation of the entire system.

[0004] Therefore, there is a need for a hybrid time scale electric-thermal integrated energy system optimization method that takes source-load game into consideration and can optimize the interactive relationship between the system and the load while performing optimal scheduling at different time scales to achieve efficient energy utilization and cost optimization. Summary of the invention

[0005] The purpose of the present invention is to provide a hybrid time-scale electric-thermal integrated energy system optimization method taking into account source-load game, which can optimize the interactive relationship between the system and the load while optimizing scheduling on different time scales to achieve efficient energy utilization and cost optimization. On the basis of fully considering the different dynamic characteristics of different systems and loads, a reasonable pricing method is used to avoid the occurrence of conflicts of interest, while ensuring the system benefits and reducing the energy cost of the load, which is more conducive to promoting the sustainable development of the integrated energy system.

[0006] To achieve the above purpose, the technical solution adopted by the present invention is:

[0007] A hybrid time scale electric-thermal integrated energy system optimization method considering source-load game includes the following steps:

[0008] Step S1: construct a multi-coupled electric-thermal integrated energy system;

[0009] Step S2: Modeling electrical and thermal flexible loads, the established load models include an electric power transfer load model and an electric thermal substitution load model;

[0010] Step S3: Dynamic modeling considering the heat transfer characteristics of the thermal pipeline: The partial differential equations about the time and position of the thermal pipeline are processed by the difference method to establish a linear model reflecting the dynamic characteristics of the heat transfer of the thermal pipeline;

[0011] Step S4: Modeling the power system network and each system device, wherein the system devices include CHP units, electric energy storage equipment, electric boilers and ground source heat pumps;

[0012] Step S5: Based on the different dynamic characteristics of the electric and thermal systems, a hybrid time scale optimization scheduling framework is established: Under the hybrid time scale framework, the thermal system dynamic model uses a 3-minute time step to iteratively calculate the temperature distribution of the thermal system, the power equipment uses a 15-minute time step to adjust the equipment output, and the thermal equipment uses a 1-hour or 15-minute time step to adjust the equipment output according to the heat energy transfer distance;

[0013] Step S6: Establish a supply-demand double-layer game optimization model, customize energy prices, and optimize the output of each device in the system and the electric and thermal loads;

[0014] Step S7: using a differential genetic algorithm and a Cplex solver to solve the two-layer game optimization model, and obtaining the optimal energy price, equipment output, and load conditions.

[0015] A further improvement of the technical solution of the present invention is that in step S1, the energy side of the electric-thermal integrated energy system is composed of the upper power grid, CHP units, wind power generation and photovoltaic power generation, its load side is composed of power load, thermal load and ground source heat pump, and its network side is composed of electric energy storage, power network, electric boiler and thermal network. The electric-thermal integrated energy system is triple-coupled at the source, network and load through the CHP units, electric boilers and ground source heat pumps.

[0016] A further improvement of the technical solution of the present invention is that in step S2, the electric load includes a rigid load, a transferable load and an alternative load, and the thermal load is regarded as a rigid load supplied by the system and the ground source heat pump. The composition of the electric thermal load is shown in formula (1):

[0017]

[0018] In the formula, Represents the unregulated electric heating load; P l,e ,P l,hIndicates the regulated electric heating load; Indicates the power transfer load; Indicates electrical and thermal alternative loads;

[0019] The power transfer load model is shown in formula (2):

[0020]

[0021] In the formula, θ sh,up ,θ sh,do The load participation coefficient of transfer regulation is the ratio of the load participating in transfer regulation to the original load size; I sh,up ,I sh,do A 0-1 state variable representing the load translation flag;

[0022] The electric heating replacement load model is shown in formula (3):

[0023]

[0024] Where P GSHP,min ,P GSHP,max Indicates the minimum and maximum values ​​of the ground source heat pump power.

[0025] A further improvement of the technical solution of the present invention is that in step S3, a linear model reflecting the dynamic characteristics of heat transfer of the thermal pipeline is established, including the following steps:

[0026] Step S301: The thermal system includes a heat source, a heat load, and supply and return pipes. The relationship between the hot water temperature, the water flow rate, and the energy transferred by the hot water is set as shown in formula (4):

[0027] P H =Mm(T i -T o ) / λ (4)

[0028] Where P H represents thermal power; M represents mass flow rate; m represents the specific heat capacity of hot water in the pipeline; T i ,T o Indicates the hot water temperature at the inlet and outlet of the pipe; λ indicates the conversion coefficient, which is 3600;

[0029] Step S302: Set a partial differential equation in the pipeline to describe the change of water temperature with time and position, as shown in formula (5):

[0030]

[0031] In the formula, T represents temperature; v represents the flow rate of hot water in the pipe; R represents thermal resistance; T a represents the external temperature of the pipe; t, x represent time and position variables respectively;

[0032] Step S303: Set the initial conditions. In the initial state, the water temperature distribution of the entire pipeline is as shown in formula (6):

[0033]

[0034] Step S304: setting boundary conditions, the change of the input end over time is shown in formula (7):

[0035] T(0,t)=ψ(t),t≥0 (7)

[0036] Step S305: Establish a discrete model of the thermal pipeline. In the discrete model, the space and time variables are respectively as shown in formula (8) and formula (9):

[0037]

[0038] In the formula, h and τ represent the difference step of length and time respectively;

[0039] Step S306: By differential method, the hot water temperature at any position in any time section is set to be represented by a linear combination of the temperatures of other points, as shown in the following formula (10):

[0040]

[0041] Where, T x t represents the hot water temperature at position x in the pipe at time t;

[0042] Differentiate formula (5) in step S302 at (k, t+1) to obtain formula (11):

[0043]

[0044] The partial differential terms in formula (11) are replaced by two difference quotients as shown in formulas (12) and (13):

[0045]

[0046] And introduce intermediate variables α and β, as shown in formula (14):

[0047]

[0048] The dynamic linear model of the thermal pipeline is derived as shown in formula (15):

[0049]

[0050] A further improvement of the technical solution of the present invention is that in step S4, modeling is performed for the power system network and each system device, including the following steps:

[0051] Step S401: Establish a power system network model as a second-order cone power flow model, as shown in formula (16):

[0052]

[0053] Where P j ,Q j Represent the active and reactive power of node j respectively; P ij ,Q ij They represent the active power and reactive power flowing through branch ij respectively; It represents the square of the current flowing through branch ij; represents the square of the voltage at node j; r ij ,x ij They represent the resistance and reactance of branch ij respectively;

[0054] Step S402: Establish a CHP unit model, as shown in formula (17):

[0055]

[0056] Where P CHP ,H CHP Respectively represent the electrical power and thermal power of the CHP unit; (P A ,H A ),(P B ,H B ),(P C ,H C ),(P D ,H D ) represent the four extreme points of the feasible region of CHP unit operation; α A ,α B ,α C ,α D Indicates the operating factor of the CHP unit;

[0057] Step S403: Establish an electric energy storage model, as shown in formula (18):

[0058]

[0059] In the formula, S ES (t) represents the amount of energy stored at a point; P store (t),P release (t) represents the charge and discharge power respectively; η store ,η release Respectively represent the medium charge and discharge efficiency;

[0060] Step S404: Establish an electric boiler model, as shown in formula (19):

[0061] H EB =η EB P EB (19)

[0062] Where P EB ,H EB Respectively represent the electrical input and thermal output power of the electric boiler; η EB Indicates the electric-to-heat conversion efficiency of electric boilers;

[0063] Step S405: Establish a ground source heat pump model, as shown in formula (20):

[0064] H GSHP =η GSHP P GSHP (20)

[0065] Where P GSHP ,H GSHP Respectively represent the electrical input and thermal output power of the ground source heat pump; η GSHP Indicates the electrical-to-heat conversion efficiency of the ground-source heat pump.

[0066] A further improvement of the technical solution of the present invention is that in step S6, the two-layer game optimization model includes a system operator and a load aggregator. The system operator includes the source side and the grid side of the system, and the optimization goal is to maximize the system operating profit. The load aggregator includes the electric heating load and the ground source heat pump on the load side, and the optimization goal is to maximize the user surplus.

[0067] A further improvement of the technical solution of the present invention is that in step S6, establishing a supply-demand double-layer game optimization model includes the following steps:

[0068] Step S601: Establish a master-slave game model, as shown in formula (21):

[0069]

[0070] The game model includes participants, strategies and goals, where {operation, user} represents the system operator and load aggregator, δ operation Represents the strategy of the system operator, including energy prices and the output of each device; δ user Indicates the strategy of the load aggregator, including the regulation of electric and thermal loads; F operation ,F user It represents the optimization goals of the system operator and the load aggregator in the game, which are the highest system operation profit and the highest user consumption surplus respectively;

[0071] Step S602: Establishing the objective function of the upper model, the upper model is a system operation optimization model, the electricity price is customized with the highest system operation cost as the goal, and the output of each device is optimized;

[0072] Step S603: Establishing the objective function of the lower model, the lower model is a load regulation optimization model, and the electric and heating loads are regulated with the goal of minimizing the user's energy cost;

[0073] Step S604: Considering constraints in the upper optimization model, including power system constraints, thermal system constraints, energy storage device constraints, and coupling device constraints;

[0074] The power system constraints considered include power balance constraints, upper grid power constraints, and unit ramp constraints, among which,

[0075] The power balance constraint is shown in formula (24):

[0076]

[0077] Where P G Indicates the power transmitted from the upper power grid to the integrated energy system; P wind Represents wind power generation; P PV Represents photovoltaic power generation; P CHP Indicates CHP power generation; P ESdis Indicates the discharge power of electrical energy storage; P ESch Indicates the energy storage charging power; P EB Indicates the power consumption of electric boiler; P l Indicates the electrical load power;

[0078] The power constraint of the upper grid is shown in formula (25):

[0079] P G,min ≤P G (t)≤P G,max (25)

[0080] Where P G (t) represents the power transmitted from the upper power grid to the integrated energy system during period t; P x,min , P x,max Respectively represent the lower and upper limits of power;

[0081] The unit climbing constraint is shown in formula (26):

[0082] P G,ramp,min ≤P G (t)-P G (t-1)≤P G,ramp,max (26)

[0083] Where Px,ramp,min , P x,ramp,max Indicates the maximum and minimum values ​​of the power ramp transmitted by the upper power grid;

[0084] Consider the thermal system constraints:

[0085] First, according to Kirchhoff's law, the flow rate flowing into a node is equal to the mass flow rate flowing out of the node, as shown in formula (27):

[0086]

[0087] Where M k→i represents the mass flow from a node k to node i; M i→j represents the mass flow from node i to a node j;

[0088] Secondly, according to the first law of thermodynamics, the heat energy flowing into a node is equal to the heat energy flowing out of the node, as shown in formula (28):

[0089]

[0090] Where, T p represents the temperature of hot water flowing into each pipe of node i; T q represents the temperature of hot water in each pipe flowing out of node i;

[0091] The energy storage equipment constraints include energy storage capacity constraints, energy storage power constraints and ramp constraints, among which:

[0092] The energy storage capacity constraint is shown in formula (29):

[0093] S min ≤S ES (t)≤S max (29)

[0094] In the formula, S min ,S max Respectively represent the minimum and maximum values ​​of the SOC state of the energy storage device;

[0095] The energy storage power constraint is shown in formula (30):

[0096] P ES,min ≤P ES (t)≤P ES ,max (30)

[0097] Where P ES (t) represents the power of the energy storage device in period t; P ES,min ,P ES,max Respectively represent the minimum and maximum values ​​of the power of the energy storage device;

[0098] The climbing constraint is shown in formula (31):

[0099] P ES,ramp,min (t)≤P ES (t)-P ES (t-1)≤P ES,ramp,max (t) (31)

[0100] Where P ES,ramp,min ,P ES,ramp,max Respectively represent the minimum and maximum values ​​of the power ramp of the energy storage device;

[0101] The coupled equipment constraints include CHP feasible region constraints and ramp constraints, where:

[0102] The CHP feasible region constraint is shown in formula (32):

[0103]

[0104] The climbing constraint is shown in formula (33):

[0105] P CHP,ramp,min ≤P CHP (t)-P CHP (t-1)≤P CHP ,ramp,max (33)

[0106] Where P CHP,ramp,min ,P CHP,ramp,max They represent the minimum and maximum values ​​of the power ramp of the coupling device respectively.

[0107] A further improvement of the technical solution of the present invention is that in step S602, an upper model objective function is established as shown in formula (22):

[0108]

[0109] In the formula, F in Indicates the income obtained by the system from supplying energy to the load; F oc Indicates the operating cost of the system; F pl and F pw They represent the penalty cost of thermal system load loss and wind curtailment respectively; μ(t) represents the electricity price during period t; γ(t) represents the heat price during period t; Indicates the actual heating power of the load during period t; x G , (x=a,b,c) represents the operation coefficient of the traditional unit; x CHP , (x=a,b,...,f) represents the CHP unit operation coefficient; a ES Represents the unit operating cost of electric energy storage; a EB represents the unit operating cost of electric boiler; a plIndicates the penalty coefficient for thermal system energy supply failure load; a pw P represents the penalty coefficient of wind curtailment in system operation; l,h (t) represents the demand size of load x during period t; P represents the maximum wind power output predicted for period t; wind (t) represents the actual wind power output during period t.

[0110] A further improvement of the technical solution of the present invention is that in step S603, the objective function of the lower model is established as shown in formula (23):

[0111]

[0112] In the formula, F s is the user utility function, which indicates the user's satisfaction after purchasing electricity and heat; e ,α e ,v h ,α h Respectively represent the user's preference coefficients for electricity consumption and thermal energy consumption; F out Indicates the cost of energy used by users.

[0113] A further improvement of the technical solution of the present invention is that in step S7, a differential genetic algorithm and a Cplex solver are used to solve the two-layer game optimization model, including the following steps:

[0114] Step S701: inputting initial load, wind and solar output data, electric and thermal network model and system parameters;

[0115] Step S702: Based on the initial parameters, the initial upper and lower layer objective function values ​​F1 are obtained 0 ,

[0116] Step S703: setting the initial population size, the maximum number of iterations, the population mutation rate, the crossover probability and the convergence error;

[0117] Step S704: Generate n groups of energy prices randomly using a genetic algorithm, and send the prices to the load aggregator. The number of iterations is k, k=1.

[0118] Step S705: The load aggregator solves the lower model based on multiple sets of energy price signals through the Cplex solver to obtain the load adjusted under different energy prices, and calculates and retains the current objective function value. And feed back the adjusted load to the system operator;

[0119] Step S706: Optimize the unit output according to the adjusted load, and obtain and retain the system operation income F1 k and the current optimal energy price;

[0120] Step S707: If F1 k >F1 k-1 , then let F1 k =F1 k , Otherwise, F1 k =F1 k-1 ,

[0121] Step S708: If |F1 k -F1 k-1 |≤ε and Where ε represents a given precision, the game equilibrium is determined to be reached, the program is terminated, and the optimal energy price is obtained; otherwise, k=k+1 is set, a new energy price is generated by selecting and mutating the genetic algorithm, and the process returns to step S704.

[0122] Due to the adoption of the above technical solution, the technical progress achieved by the present invention is:

[0123] The hybrid time-scale electric-thermal integrated energy system optimization method of the present invention takes source-load game into consideration, which can optimize the interactive relationship between the system and the load while performing optimal scheduling on different time scales to achieve efficient energy utilization and cost optimization. On the basis of fully considering the different dynamic characteristics of different systems and loads, a reasonable pricing method is used to avoid conflicts of interest, thereby reducing the energy cost of the load while ensuring system benefits, and is more conducive to promoting the sustainable development of the integrated energy system.

[0124] The present invention fully considers the different dynamic characteristics of the electric heating system and can more accurately describe the dynamic changes of the thermal system when transferring heat energy during the scheduling process.

[0125] The present invention can adjust different loads according to the characteristics of electrical and thermal loads, thereby reducing the energy cost of users while fully exploring the flexibility of the load side.

[0126] The present invention can ensure the balance between system operation income and user energy consumption cost, and is conducive to promoting the sustainable development of the integrated energy system. BRIEF DESCRIPTION OF THE DRAWINGS

[0127] Figure 1 It is a structural schematic diagram of an electric-thermal integrated energy system in a hybrid time-scale electric-thermal integrated energy system optimization method considering source-load game of the present invention;

[0128] Figure 2 It is a schematic diagram of the structure of the thermal system in the hybrid time scale electric-thermal integrated energy system optimization method considering source-load game of the present invention;

[0129] Figure 3It is a differential schematic diagram of a thermal pipeline in the hybrid time scale electric-thermal integrated energy system optimization method considering source-load game of the present invention;

[0130] Figure 4 It is a structural schematic diagram of a hybrid time scale optimization scheduling framework in a hybrid time scale electric-thermal integrated energy system optimization method considering source-load game in the present invention;

[0131] Figure 5 It is a flow chart for solving the double-layer game model in the mixed time scale electric-thermal integrated energy system optimization method considering source-load game in the present invention. DETAILED DESCRIPTION

[0132] The present invention is further described in detail below in conjunction with embodiments:

[0133] like Figure 1-Figure 5 As shown, the present invention provides a hybrid time scale electric-thermal integrated energy system optimization method considering source-load game, comprising the following steps:

[0134] Step S1: Figure 1 As shown, a multi-coupled electric-thermal integrated energy system is constructed;

[0135] The energy side of the electric-thermal integrated energy system consists of the upper power grid, combined heat and power (CHP) units, wind power generation and photovoltaic power generation; the load side consists of power load, thermal load and ground-source heat pumps; the network side consists of electric energy storage, power network, electric boilers and thermal network, among which ground-source heat pumps can realize electric energy substitution for thermal load. In the system, the power network and thermal network serve as bridges to connect various energy sources and multi-energy users. The integrated energy system can balance the relationship between energy and load by purchasing and selling various types of energy; among which, ground-source heat pumps use electricity to transport underground thermal energy. When the price of thermal energy is higher than that of electricity, users can use ground-source heat pumps to convert electricity into thermal energy to achieve electric energy substitution, and coordinate with CHP units and electric boilers to supply thermal loads; the power load is coordinated by wind power, CHP units and electric energy storage equipment. When the power generation of local units cannot meet user needs, electricity can be purchased from the upper power grid;

[0136] The electric-heat integrated energy system realizes triple coupling of electric and heat at the source, grid and load through coupling equipment such as CHP units, electric boilers and ground-source heat pumps, thereby realizing the integrated supply of electric and heat loads;

[0137] Step S2: Modeling electrical and thermal flexible loads;

[0138] The system load side includes electric load and thermal load, and the ground source heat pump is used to replace part of the thermal load with electricity. The electric load includes rigid load, transferable load and replacement load. The thermal load is the heating load for residents in winter. Since the heat demand cannot be transferred over time, the thermal load can be regarded as a rigid load supplied by the system and the ground source heat pump. The composition of the electric heat load is shown in formula (1):

[0139]

[0140] In the formula, Represents the unregulated electric heating load; P l,e ,P l,h Indicates the regulated electric heating load; Indicates the power transfer load; Indicates electrical and thermal alternative loads;

[0141] The established load model includes the power transfer load model and the electric heat substitution load model, among which the power transfer load model is shown in formula (2):

[0142]

[0143] In the formula, θ sh,up ,θ sh,do The load participation coefficient of transfer regulation is the ratio of the load participating in transfer regulation to the original load size; I sh,up ,I sh,do A 0-1 state variable representing the load translation flag;

[0144] The electric heating replacement load model is shown in formula (3):

[0145]

[0146] Where P GSHP,min ,P GSHP,max Indicates the minimum and maximum values ​​of the ground source heat pump power;

[0147] Step S3: Dynamic modeling considering the heat transfer characteristics of the thermal pipeline: The partial differential equations about the time and position of the thermal pipeline are processed by the difference method to establish a linear model that can reflect the dynamic characteristics of the heat transfer of the thermal pipeline, including the following steps:

[0148] Step S301: Figure 2 As shown, the thermal system usually includes a heat source, a heat load, and supply and return pipes. Hot water circulates in the supply and return pipes to transfer energy. The relationship between the hot water temperature, the water flow rate, and the energy transferred by the hot water is shown in formula (4):

[0149] P H =Mm(T i-T o ) / λ (4)

[0150] Where P H represents thermal power; M represents mass flow rate; m represents the specific heat capacity of hot water in the pipeline; T i ,T o Indicates the hot water temperature at the inlet and outlet of the pipe; λ indicates the conversion coefficient, which is 3600;

[0151] Step S302: Set a partial differential equation in the pipeline to describe the change of water temperature with time and position, as shown in formula (5):

[0152]

[0153] In the formula, T represents temperature; v represents the flow rate of hot water in the pipe; R represents thermal resistance; T a represents the external temperature of the pipe; t, x represent time and position variables respectively;

[0154] Step S303: Set the initial conditions. In the initial state, the water temperature distribution of the entire pipeline is known, as shown in formula (6):

[0155]

[0156] Step S304: setting boundary conditions. In order to calculate the output end temperature, the change of the input end over time is also known, as shown in formula (7):

[0157] T(0,t)=ψ(t),t≥0 (7)

[0158] Step S305: Establish a discrete model of the thermal pipeline such as Figure 3 As shown, in the discrete model, the spatial and temporal variables are shown in formula (8) and formula (9) respectively:

[0159]

[0160] In the formula, h and τ represent the difference step of length and time respectively;

[0161] Step S306: By differential method, the hot water temperature at any position in any time section can be expressed by a linear combination of the temperatures of some other points, as shown in the following formula (10):

[0162]

[0163] Where, T x t represents the hot water temperature at position x in the pipe at time t;

[0164] By differentiating formula (5) in step S302 at (k, t+1), we can obtain formula (11):

[0165]

[0166] For point (k, t+1), its temperature is mainly affected by the temperature of the previous node (k-1, t+1) at the same time, the temperature of the same node at the previous time (k, t+1) and the water flow rate. Therefore, two difference quotients as shown in formulas (12) and (13) are used to replace the partial differential term in formula (11):

[0167]

[0168] At the same time, the intermediate variables α and β are introduced, as shown in formula (14):

[0169]

[0170] Therefore, the dynamic linear model of the thermal pipeline can be derived, as shown in formula (15):

[0171]

[0172] Step S4: Modeling the power system network and each system device, wherein the system devices include CHP units, electric energy storage devices, electric boilers and ground source heat pumps, including the following steps:

[0173] Step S401: Establish a power system network model as a second-order cone power flow model, as shown in formula (16):

[0174]

[0175] Where P j ,Q j Represent the active and reactive power of node j respectively; P ij ,Q ij They represent the active power and reactive power flowing through branch ij respectively; It represents the square of the current flowing through branch ij; represents the square of the voltage at node j; r ij ,x ij They represent the resistance and reactance of branch ij respectively;

[0176] Step S402: Establish a CHP unit model, as shown in formula (17):

[0177]

[0178] Where P CHP ,H CHP Respectively represent the electrical power and thermal power of the CHP unit; (PA ,H A ),(P B ,H B ),(P C ,H C ),(P D ,H D ) represent the four extreme points of the feasible region of CHP unit operation; α A ,α B ,α C ,α D Indicates the operating factor of the CHP unit;

[0179] Step S403: Establish an electric energy storage model, as shown in formula (18):

[0180]

[0181] In the formula, S ES (t) represents the amount of energy stored at a point; P store (t),P release (t) represents the charge and discharge power respectively; η store ,η release Respectively represent the medium charge and discharge efficiency;

[0182] Step S404: Establish an electric boiler model, as shown in formula (19):

[0183] H EB =η EB P EB (19)

[0184] Where P EB ,H EB Respectively represent the electrical input and thermal output power of the electric boiler; η EB Indicates the electric-to-heat conversion efficiency of electric boilers;

[0185] Step S405: Establish a ground source heat pump model, as shown in formula (20):

[0186] H GSHP =η GSHP P GSHP (20)

[0187] Where P GSHP ,H GSHP Respectively represent the electrical input and thermal output power of the ground source heat pump; η GSHP Indicates the electric-to-heat conversion efficiency of the ground-source heat pump;

[0188] Step S5: Based on the different dynamic characteristics of the electric and thermal systems, a hybrid time scale optimization scheduling framework is established: Under the hybrid time scale framework, the thermal system dynamic model uses a 3-minute time step to iteratively calculate the temperature distribution of the thermal system, the power equipment uses a 15-minute time step to adjust the equipment output, and the thermal equipment uses a 1-hour or 15-minute time step to adjust the equipment output according to the heat energy transfer distance, that is, the equipment in different systems is scheduled at different time steps according to different dynamic characteristics;

[0189] Specifically, Figure 4 As shown in the figure, the dispatch process of the electric-thermal integrated energy system is divided into three time scales, namely the long time scale of the thermal system, the medium time scale of the power system and the short time scale calculated by the thermal dynamic model; in the short time scale, the thermal pipeline dynamic model calculates the temperature distribution of the thermal network every 3 minutes and converts the temperature into transmission power; after calculating the temperature distribution 5 times, based on the calculated results, the power of wind power, photovoltaic power, upper power grid, electric boiler and electric energy storage in the power system is adjusted to achieve supply and demand balance; the dynamic model calculates the temperature distribution 20 times, and adjusts the thermal power and electric power of the CHP unit of the thermal system according to the power transmission of the thermal pipeline;

[0190] In summary, under the hybrid time scale optimization scheduling framework, the time steps of the long, medium and short time scales are 1h, 15min and 3min respectively. At the same time, in order to be compatible with the hybrid time scale scheduling framework, the time steps of the power load and thermal load regulation are also 1h and 15min respectively.

[0191] Step S6: Establish a supply-demand double-layer game optimization model, customize energy prices, and optimize the output of each device in the system and the electric and thermal loads;

[0192] The two-layer game optimization model consists of two participants: the system operator and the load aggregator. The system operator includes the source side and the grid side of the system, and the optimization goal is to maximize the system operation revenue. The load aggregator includes the electric heat load and ground source heat pump on the load side, and the optimization goal is to maximize the user surplus.

[0193] Establishing the supply and demand two-layer game optimization model includes the following steps:

[0194] Step S601: Establishing a master-slave game model:

[0195] In the game, the system operator first optimizes the output of each device and sets the energy price according to the load demand level and the output level of new energy. The load aggregation adjusts the energy consumption curve through demand response according to the energy price, and feeds the adjusted curve back to the system operator. The source-load coordination repeats the game process until a balance is reached to ensure the interests of both the system operator and the load aggregator. Thus, the master-slave game model is established, as shown in formula (21):

[0196]

[0197] The model mainly includes three elements: participants, strategies and goals, where {operation, user} represents the two participants, the system operator and the load aggregator, δ operation Indicates the strategy of the system operator, mainly including energy prices and the output of each device; δ user Indicates the strategy of the load aggregator, mainly including the regulation of electric and thermal loads; F operation ,F user It represents the optimization goals of the system operator and the load aggregator in the game, which are the highest system operation profit and the highest user consumption surplus respectively;

[0198] Step S602: Establishing the objective function of the upper model, the upper model is a system operation optimization model, the electricity price is customized with the highest system operation cost as the goal, and the output of each device is optimized;

[0199] Specifically, the upper-level optimization aims to maximize the system operation benefits and optimizes the energy price and the output of each device. Its objective function is shown in formula (22):

[0200]

[0201] In the formula, F in Indicates the income obtained by the system from supplying energy to the load; F oc Indicates the operating cost of the system; F pl and F pw They represent the penalty cost of thermal system load loss and wind curtailment respectively; μ(t) represents the electricity price during period t; γ(t) represents the heat price during period t; Indicates the actual heating power of the load during period t; x G , (x=a,b,c) represents the operation coefficient of the traditional unit; x CHP , (x=a,b,...,f) represents the CHP unit operation coefficient; a ES Represents the unit operating cost of electric energy storage; a EB represents the unit operating cost of electric boiler; a pl Indicates the penalty coefficient for thermal system energy supply failure load; a pw P represents the penalty coefficient of wind curtailment in system operation;l,h (t) represents the demand size of load x during period t; P represents the maximum wind power output predicted for period t; wind (t) represents the actual wind power output during period t;

[0202] Step S603: Establishing the objective function of the lower model, the lower model is a load regulation optimization model, and the electric and heating loads are regulated with the goal of minimizing the user's energy cost;

[0203] Specifically, based on the established flexible electric and thermal load model, the load aggregator uses the energy price released by the system operator as a signal and takes the maximum user consumption surplus as the goal to adjust the electric and thermal load. Its objective function is shown in formula (23):

[0204]

[0205] In the formula, F s is the user utility function, which indicates the user's satisfaction after purchasing electricity and heat; e ,α e ,v h ,α h Respectively represent the user's preference coefficients for electricity consumption and thermal energy consumption; F out It indicates the cost of energy used by the user;

[0206] Step S604: Consider the constraints in the upper optimization model:

[0207] In addition to the above-mentioned thermal network dynamic model, power network model and equipment models, constraints need to be considered in the upper optimization model, including power system constraints, thermal system constraints, energy storage equipment constraints and coupling equipment constraints;

[0208] The power system constraints considered include power balance constraints, upper grid power constraints, and unit ramp constraints, among which,

[0209] The power balance constraint is shown in formula (24):

[0210]

[0211] Where P G Indicates the power transmitted from the upper power grid to the integrated energy system; P wind Represents wind power generation; P PV Represents photovoltaic power generation; P CHP Indicates CHP power generation; P ESdis Indicates the discharge power of electrical energy storage; P ESch Indicates the energy storage charging power; P EB Indicates the power consumption of electric boiler; P lIndicates the electrical load power;

[0212] The power constraint of the upper grid is shown in formula (25):

[0213] P G,min ≤P G (t)≤P G,max (25)

[0214] Where P G (t) represents the power transmitted from the upper power grid to the integrated energy system during period t; P x,min , P x,max Respectively represent the lower and upper limits of power;

[0215] The unit climbing constraint is shown in formula (26):

[0216] P G,ramp,min ≤P G (t)-P G (t-1)≤P G,ramp,max (26)

[0217] Where P x,ramp,min , P x,ramp,max Indicates the maximum and minimum values ​​of the power ramp transmitted by the upper power grid;

[0218] Consider the thermal system constraints:

[0219] Mass flow conservation: According to Kirchhoff's law, the flow into a node is equal to the mass flow out of the node, as shown in formula (27):

[0220]

[0221] Where M k→i represents the mass flow from a node k to node i; M i→j represents the mass flow from node i to a node j;

[0222] Consider the conservation of heat energy: According to the first law of thermodynamics, the heat energy flowing into a node is equal to the heat energy flowing out of the node, as shown in formula (28):

[0223]

[0224] Where, T p represents the temperature of hot water flowing into each pipe of node i; T q represents the temperature of hot water in each pipe flowing out of node i;

[0225] The energy storage equipment constraints include energy storage capacity constraints, energy storage power constraints and ramp constraints, among which:

[0226] The energy storage capacity constraint is shown in formula (29):

[0227] S min ≤S ES (t)≤S max (29)

[0228] In the formula, S min ,S max Respectively represent the minimum and maximum values ​​of the SOC state of the energy storage device;

[0229] The energy storage power constraint is shown in formula (30):

[0230] P ES,min ≤P ES (t)≤P ES ,max (30)

[0231] Where P ES (t) represents the power of the energy storage device in period t; P ES,min ,P ES,max Respectively represent the minimum and maximum values ​​of the power of the energy storage device;

[0232] The climbing constraint is shown in formula (31):

[0233] P ES,ramp,min (t)≤P ES (t)-P ES (t-1)≤P ES,ramp,max (t) (31)

[0234] Where P ES,ramp,min ,P ES,ramp,max Respectively represent the minimum and maximum values ​​of the power ramp of the energy storage device;

[0235] The coupled equipment constraints include CHP feasible region constraints and ramp constraints, where:

[0236] The CHP feasible region constraint is shown in formula (32):

[0237] Since the output electrical power and thermal power are interrelated, the operation of condensing CHP equipment needs to meet the feasible domain constraints:

[0238]

[0239] The climbing constraint is shown in formula (33):

[0240] P CHP,ramp,min ≤P CHP (t)-P CHP (t-1)≤P CHP ,ramp,max (33)

[0241] Where P CHP,ramp,min ,P CHP,ramp,max Respectively represent the minimum and maximum values ​​of the power ramp of the coupling device;

[0242] Step S7: Use differential genetic algorithm and mathematical optimization solver (Cplex) to solve the two-layer game optimization model to obtain the optimal energy price, equipment output and load conditions:

[0243] In order to solve the two-layer optimization game model established in the above steps, the differential genetic algorithm is used to solve the upper model, and the energy price and equipment output are optimized. The energy price is passed to the lower model. The lower model uses the Cplex solver to solve the model directly according to the energy price signal to obtain the optimized load, and the adjusted load is fed back to the upper model. It is continuously iterated until the upper and lower objective functions reach equilibrium, and the solution is terminated to obtain the optimal energy price, equipment output and load conditions. The specific solution process is as follows: Figure 5 As shown, the specific solution steps include:

[0244] Step S701: inputting initial load, wind and solar output data, electric and thermal network model and system parameters;

[0245] Step S702: Based on the initial parameters, the initial upper and lower layer objective function values ​​F1 are obtained 0 ,

[0246] Step S703: setting the initial population size, the maximum number of iterations, the population mutation rate, the crossover probability and the convergence error;

[0247] Step S704: Generate n groups of energy prices randomly using a genetic algorithm, and send the prices to the load aggregator. The number of iterations is k, k=1.

[0248] Step S705: The load aggregator solves the lower model based on multiple sets of energy price signals through the Cplex solver to obtain the load adjusted under different energy prices, and calculates and retains the current objective function value F2 k and feed back the adjusted load to the system operator;

[0249] Step S706: Optimize the unit output according to the adjusted load, and obtain and retain the system operation income F1 k and the current optimal energy price;

[0250] Step S707: If F1 k >F1 k-1 , then let F1 k =F1 k , Otherwise, F1 k =F1 k-1 ,

[0251] Step S708: If |F1 k -F1 k-1 |≤ε and Where ε represents the given accuracy, the game equilibrium is determined to be reached, the program is terminated, the optimal energy price is obtained, and the interests of both the system operator and the load aggregator are guaranteed; otherwise, k=k+1 is set, and a new energy price is generated by selecting and mutating the genetic algorithm, and the process returns to step S704.

[0252] It is to be understood that the present invention is described by some embodiments, and it is known to those skilled in the art that various changes or equivalent substitutions may be made to these features and embodiments without departing from the spirit and scope of the present invention. In addition, under the teachings of the present invention, these features and embodiments may be modified to adapt to specific circumstances and materials without departing from the spirit and scope of the present invention. Therefore, the present invention is not limited by the specific embodiments disclosed herein, and all embodiments falling within the scope of the claims of this application are within the scope of protection of the present invention.

Claims

1. A hybrid time-scale electric-thermal integrated energy system optimization method considering source-load game, Features The following steps are involved: Step S1: construct a multi-coupled electric-thermal integrated energy system; Step S2: Modeling electric and thermal flexible loads, the established load models include an electric power transfer load model and an electric thermal substitution load model; Step S3: Dynamic modeling considering the heat transfer characteristics of the thermal pipeline: The partial differential equations about the time and position of the thermal pipeline are processed by the difference method to establish a linear model reflecting the dynamic characteristics of the heat transfer of the thermal pipeline; Step S4: Modeling the power system network and each system device, wherein the system devices include CHP units, electric energy storage devices, electric boilers and ground source heat pumps; Step S5: Based on the different dynamic characteristics of the electric and thermal systems, a hybrid time scale optimization scheduling framework is established: Under the hybrid time scale framework, the thermal system dynamic model uses a 3-minute time step to iteratively calculate the temperature distribution of the thermal system, the power equipment uses a 15-minute time step to adjust the equipment output, and the thermal equipment uses a 1-hour or 15-minute time step to adjust the equipment output according to the heat energy transfer distance; Step S6: Establish a supply-demand double-layer game optimization model, customize energy prices, and optimize the output of each device in the system and the electric and thermal loads; Step S7: using a differential genetic algorithm and a Cplex solver to solve the two-layer game optimization model, and obtaining the optimal energy price, equipment output, and load conditions.

2. According to claim 1, a hybrid time scale electric-thermal integrated energy system optimization method considering source-load game, Features: In step S1, the energy side of the electric-thermal integrated energy system consists of the upper power grid, CHP units, wind power generation and photovoltaic power generation, its load side consists of power load, thermal load and ground-source heat pump, and its network side consists of electric energy storage, power network, electric boiler and thermal network. The electric-thermal integrated energy system is triple-coupled at the source, network and load through CHP units, electric boilers and ground-source heat pumps.

3. According to claim 2, a hybrid time scale electric-thermal integrated energy system optimization method considering source-load game, Features: In step S2, the electric load includes rigid load, transferable load and alternative load, and the thermal load is regarded as the rigid load supplied by the system and the ground source heat pump. The composition of the electric thermal load is shown in formula (1): In the formula, Represents the unregulated electric heating load; P l,e ,P l,h Indicates the regulated electric heating load; Indicates the power transfer load; Indicates electrical and thermal alternative loads; The power transfer load model is shown in formula (2): In the formula, θ sh,up ,θ sh,do The load participation coefficient of transfer regulation is the ratio of the load participating in transfer regulation to the original load size; I sh,up ,I sh,do A 0-1 state variable representing the load translation flag; The electric heating replacement load model is shown in formula (3): Where P GSHP,min ,P GSHP,max Indicates the minimum and maximum values ​​of the ground source heat pump power.

4. According to claim 3, a hybrid time scale electric-thermal integrated energy system optimization method considering source-load game, Features: In step S3, a linear model reflecting the dynamic characteristics of heat transfer in the thermal pipeline is established, including the following steps: Step S301: The thermal system includes a heat source, a heat load, and supply and return water pipes. The relationship between the hot water temperature, the water flow rate, and the energy transferred by the hot water is set as shown in formula (4): P H =Mm(T i -T o ) / λ (4) Where P H represents thermal power; M represents mass flow rate; m represents the specific heat capacity of hot water in the pipeline; T i ,T o Indicates the hot water temperature at the inlet and outlet of the pipe; λ indicates the conversion coefficient, which is 3600; Step S302: Set a partial differential equation in the pipeline to describe the change of water temperature with time and position, as shown in formula (5): In the formula, T represents temperature; v represents the flow rate of hot water in the pipe; R represents thermal resistance; T a represents the external temperature of the pipe; t, x represent time and position variables respectively; Step S303: Set the initial conditions. In the initial state, the water temperature distribution of the entire pipeline is as shown in formula (6): Step S304: setting boundary conditions, the change of the input end over time is shown in formula (7): T(0,t)=ψ(t),t≥0 (7) Step S305: Establish a discrete model of the thermal pipeline. In the discrete model, the space and time variables are respectively as shown in formula (8) and formula (9): In the formula, h and τ represent the difference step of length and time respectively; Step S306: By differential method, the hot water temperature at any position in any time section is set to be represented by a linear combination of the temperatures of other points, as shown in the following formula (10): In the formula, represents the hot water temperature at position x in the pipe at time t; Differentiate formula (5) in step S302 at (k, t+1) to obtain formula (11): The partial differential terms in formula (11) are replaced by two difference quotients as shown in formulas (12) and (13): And introduce intermediate variables α and β, as shown in formula (14): The dynamic linear model of the thermal pipeline is derived as shown in formula (15):

5. According to claim 4, a hybrid time scale electric-thermal integrated energy system optimization method considering source-load game, Features: In step S4, the power system network and each system device are modeled, including the following steps: Step S401: Establish a power system network model as a second-order cone power flow model, as shown in formula (16): Where P j ,Q j Represent the active and reactive power of node j respectively; P ij ,Q ij They represent the active power and reactive power flowing through branch ij respectively; It represents the square of the current flowing through branch ij; represents the square of the voltage at node j; r ij ,x ij They represent the resistance and reactance of branch ij respectively; Step S402: Establish a CHP unit model, as shown in formula (17): Where P CHP ,H CHP Respectively represent the electrical power and thermal power of the CHP unit; (P A ,H A ),(P B ,H B ),(P C ,H C ),(P D ,H D ) represent the four extreme points of the feasible region of CHP unit operation; α A ,α B ,α C ,α D Indicates the operating factor of the CHP unit; Step S403: Establish an electric energy storage model, as shown in formula (18): In the formula, S ES (t) represents the amount of energy stored at a point; P store (t),P release (t) represents the charge and discharge power respectively; η store ,η release Respectively represent the medium charge and discharge efficiency; Step S404: Establish an electric boiler model, as shown in formula (19): H EB =the EB P EB (19) Where P EB ,H EB Respectively represent the electrical input and thermal output power of the electric boiler; η EB Indicates the electric-heat conversion efficiency of the electric boiler; Step S405: Establish a ground source heat pump model, as shown in formula (20): H GSHP =the GSHP P GSHP (20) Where P GSHP ,H GSHP Respectively represent the electrical input and thermal output power of the ground source heat pump; η GSHP Indicates the electrical-to-heat conversion efficiency of the ground-source heat pump.

6. According to claim 5, a hybrid time scale electric-thermal integrated energy system optimization method considering source-load game, Features: In step S6, the two-layer game optimization model includes system operators and load aggregators. The system operator includes the source side and the grid side of the system, and the optimization goal is to maximize the system operating profit. The load aggregator includes the electric heating load and the ground source heat pump on the load side, and the optimization goal is to maximize the user surplus.

7. According to claim 6, a hybrid time scale electric-thermal integrated energy system optimization method considering source-load game, Features: In step S6, establishing a supply-demand dual-layer game optimization model includes the following steps: Step S601: Establish a master-slave game model, as shown in formula (21): The game model includes participants, strategies and goals, where {operation, user} represents the system operator and load aggregator, δ operation Represents the strategy of the system operator, including energy prices and the output of each device; δ user Indicates the strategy of the load aggregator, including the regulation of electric and thermal loads; F operation ,F user It represents the optimization goals of the system operator and the load aggregator in the game, which are the highest system operation profit and the highest user consumption surplus respectively; Step S602: Establishing the objective function of the upper model, the upper model is a system operation optimization model, the electricity price is customized with the highest system operation cost as the goal, and the output of each device is optimized; Step S603: Establishing the objective function of the lower model, the lower model is a load regulation optimization model, and the electric and heating loads are regulated with the goal of minimizing the user's energy cost; Step S604: Considering constraints in the upper optimization model, including power system constraints, thermal system constraints, energy storage device constraints, and coupling device constraints; The power system constraints considered include power balance constraints, upper grid power constraints, and unit ramp constraints, among which, The power balance constraint is shown in formula (24): Where P G Indicates the power transmitted from the upper power grid to the integrated energy system; P wind Represents wind power generation; P PV Represents photovoltaic power generation; P CHP Indicates CHP power generation; P ESdis Indicates the discharge power of electrical energy storage; P ESch Indicates the energy storage charging power; P EB Indicates the power consumption of electric boiler; P l Indicates the electrical load power; The power constraint of the upper grid is shown in formula (25): P G,min ≤P G (t)≤P G,max (25) Where P G (t) represents the power transmitted from the upper power grid to the integrated energy system during period t; P x,min , P x,max Respectively represent the lower and upper limits of power; The unit climbing constraint is shown in formula (26): P G,ramp,min ≤P G (t)-P G (t-1)≤P G,ramp,max (26) Where P x,ramp,min , P x,ramp,max Indicates the maximum and minimum values ​​of the power ramp transmitted by the upper power grid; Consider the thermal system constraints: First, according to Kirchhoff's law, the flow rate flowing into a node is equal to the mass flow rate flowing out of the node, as shown in formula (27): Where M k→i represents the mass flow from a node k to node i; M i→j represents the mass flow from node i to a node j; Secondly, according to the first law of thermodynamics, the heat energy flowing into a node is equal to the heat energy flowing out of the node, as shown in formula (28): Where, T p represents the temperature of hot water flowing into each pipe of node i; T q represents the temperature of hot water in each pipe flowing out of node i; The energy storage equipment constraints include energy storage capacity constraints, energy storage power constraints and ramp constraints, among which: The energy storage capacity constraint is shown in formula (29): S min ≤S ES (t)≤S max (29) In the formula, S min ,S max Respectively represent the minimum and maximum values ​​of the SOC state of the energy storage device; The energy storage power constraint is shown in formula (30): P ES,min ≤P ES (t)≤P ES,max (30) Where P ES (t) represents the power of the energy storage device in period t; P ES,min ,P ES,max Respectively represent the minimum and maximum values ​​of the power of the energy storage device; The climbing constraint is shown in formula (31): P ES,ramp,min (t)≤P ES (t)-P ES (t-1)≤P ES,ramp,max (t) (31) Where P ES,ramp,min ,P ES,ramp,max Respectively represent the minimum and maximum values ​​of the power ramp of the energy storage device; The coupled equipment constraints include CHP feasible region constraints and ramp constraints, where: The CHP feasible region constraint is shown in formula (32): The climbing constraint is shown in formula (33): P CHP,ramp,min ≤P CHP (t)-P CHP (t-1)≤P CHP,ramp,max (33) Where P CHP,ramp,min ,P CHP,ramp,max They represent the minimum and maximum values ​​of the power ramp of the coupling device respectively.

8. According to claim 7, a hybrid time scale electric-thermal integrated energy system optimization method considering source-load game, Features: In step S602, the upper model objective function is established as shown in formula (22): In the formula, F in Indicates the income obtained by the system from supplying energy to the load; F oc Indicates the operating cost of the system; F pl and F pw They represent the penalty cost of thermal system load loss and wind curtailment respectively; μ(t) represents the electricity price during period t; γ(t) represents the heat price during period t; Indicates the actual heating power of the load during period t; x G , (x=a,b,c) represents the operation coefficient of the traditional unit; x CHP , (x=a,b,...,f) represents the CHP unit operation coefficient; a ES Represents the unit operating cost of electric energy storage; a EB represents the unit operating cost of electric boiler; a pl Indicates the penalty coefficient for thermal system energy supply failure load; a pw P represents the penalty coefficient of wind curtailment in system operation; l,h (t) represents the demand size of load x during period t; P represents the maximum wind power output predicted for period t; wind (t) represents the actual wind power output during period t.

9. A hybrid time scale electric-thermal integrated energy system optimization method considering source-load game according to claim 8, Features: In step S603, the lower layer model objective function is established as shown in formula (23): In the formula, F s is the user utility function, which indicates the user's satisfaction after purchasing electricity and heat; e ,α e ,v h ,α h Respectively represent the user's preference coefficients for electricity consumption and thermal energy consumption; F out Indicates the cost of energy used by users.

10. A hybrid time scale electric-thermal integrated energy system optimization method considering source-load game according to claim 9, Features: In step S7, a differential genetic algorithm and a Cplex solver are used to solve the two-layer game optimization model, including the following steps: Step S701: inputting initial load, wind and solar output data, electric and thermal network model and system parameters; Step S702: Based on the initial parameters, the initial upper and lower layer objective function values ​​F are obtained. 1 0 , Step S703: setting the initial population size, the maximum number of iterations, the population mutation rate, the crossover probability and the convergence error; Step S704: Generate n groups of energy prices randomly using a genetic algorithm, and send the prices to the load aggregator. The number of iterations is k, k=1. Step S705: The load aggregator solves the lower model based on multiple sets of energy price signals through the Cplex solver to obtain the load adjusted under different energy prices, and calculates and retains the current objective function value. And feed back the adjusted load to the system operator; Step S706: Optimize the unit output according to the adjusted load to obtain and retain the system operation income F 1 k and the current optimal energy price; Step S707: If Then otherwise, Step S708: If and Where ε represents a given precision, the game equilibrium is determined to be reached, the program is terminated, and the optimal energy price is obtained; otherwise, k=k+1 is set, a new energy price is generated by selecting and mutating the genetic algorithm, and the process returns to step S704.

Citation Information

Cited By

  • Electric heating system decentralized scheduling method and system based on Nash bargaining

    CN119990685A

  • Decentralized scheduling method and system for electric heating system based on Nash bargaining

    CN119990685B

  • Method and system for optimizing low-carbon operation of power system

    CN121998388A