Construction modeling pre-analysis method based on BIM

Through the BIM-based construction modeling pre-analysis method, combined with intelligent sensing and structural health monitoring, the construction process is intelligent and automated, solving the problems of data consistency and risk assessment during the construction phase, and improving construction quality and safety. Ensure the reliability of the building structure.

CN118780465APending Publication Date: 2024-10-15CCCC SECOND HIGHWAY ENG CO LTD
View PDF 0 Cites 17 Cited by

Patent Information

Application Number
CN202410748230.X
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-06-11
Publication Date
2024-10-15

AI Technical Summary

Technical Problem

The insufficient application of existing BIM technology in the construction stage has led to problems such as data inconsistency, information silos, material conflicts, and unreasonable construction sequences, affecting construction quality and progress. There is a lack of effective structural health monitoring and early warning mechanisms, which increases project risks and maintenance. cost.

Method used

BIM-based construction modeling pre-analysis method, including data collection and integration, model optimization and adjustment, intelligent sensing and structural health monitoring integration, construction process simulation and risk assessment, construction plan optimization and verification, through three-dimensional building information model and structure The health prediction model realizes intelligent and automated management of the construction process, promptly identifies and warns structural abnormalities, and proposes scientific risk control measures.

Benefits of technology

It improves construction quality and efficiency and ensures the safety and reliability of building structures. Through intelligent and automated management, it predicts the health status and performance changes of building structures in real time, provides efficient and accurate decision support, optimizes construction plans, and reduces engineering risks. .

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118780465A_ABST
    Figure CN118780465A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of building engineering, in particular to a BIM-based construction modeling pre-analysis method, which comprises the following steps: S1, data collection and integration: collecting related data of a construction project; s2, model optimization and adjustment: optimizing and adjusting the three-dimensional building information model; s3, intelligent sensing and structure health monitoring integration: predicting the health state and performance change of the building structure; s4, construction process simulation and risk assessment: analyzing potential problems in the construction process; s5, construction scheme optimization and verification, wherein the construction scheme is optimized and adjusted; and S6, result output and application: outputting the optimized and verified construction scheme in the forms of drawings and reports for reference and application of construction units, and guiding the actual construction process. According to the method, the construction quality and efficiency are improved, and a scientific basis is provided for the safety and reliability of a building structure.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of building engineering, and in particular to a construction modeling pre-analysis method based on BIM. Background Art

[0002] As the scale and complexity of construction projects continue to increase, Building Information Modeling (BIM) technology has been widely used in building design, construction and management. BIM technology integrates the geometry and attribute information of buildings through three-dimensional digital models, providing a more intuitive and accurate building data management platform, enabling data from all stages of the construction project to be managed and applied in a unified model, thereby improving the efficiency of engineering design and construction.

[0003] However, the application of existing BIM technology in the construction phase still has many shortcomings. Traditional construction management methods rely on two-dimensional drawings and manual records, which lead to problems such as inconsistent data, information islands, material conflicts and unreasonable construction sequences, affecting construction quality and progress. In addition, there is a lack of effective structural health monitoring and early warning mechanisms, and abnormal situations in the construction process are difficult to detect and handle in a timely manner, increasing project risks and maintenance costs. Existing BIM applications are mainly concentrated in the design and planning stages, and there is insufficient application of dynamic prediction and real-time monitoring of the construction process, making it difficult to fully tap its potential.

[0004] The purpose of this invention is to provide a BIM-based construction modeling pre-analysis method to realize the intelligent and automated management of the construction process, comprehensively analyze and predict potential problems in the construction process, timely identify and warn of structural anomalies, and propose scientific risk control measures to improve construction quality and efficiency and ensure the safety and reliability of building structures. Summary of the invention

[0005] Based on the above objectives, the present invention provides a construction modeling pre-analysis method based on BIM.

[0006] The BIM-based construction modeling pre-analysis method includes the following steps:

[0007] S1, data collection and integration: collect relevant data of the construction project, including architectural design drawings, engineering geological survey reports and construction plans, and import the relevant data into BIM software to form a three-dimensional building information model;

[0008] S2, model optimization and adjustment: optimize and adjust the 3D building information model, and modify the 3D building information model according to actual construction conditions;

[0009] S3, Integration of intelligent sensing and structural health monitoring: Install intelligent materials and sensors on the surface of building structures to monitor building structure data in real time. Building structure data includes stress, deformation and temperature. Collect and process building structure data. Use structural health prediction models to predict the health status and performance changes of building structures. Integrate structural health monitoring with BIM models to achieve visual management and analysis of structural health data.

[0010] S4, construction process simulation and risk assessment: Combined with the prediction results of the structural health prediction model, the optimized three-dimensional building information model is used to simulate the entire construction process, analyze potential problems in the construction process, including material conflicts and unreasonable construction sequence, and conduct risk assessment based on the simulation results to identify risks in the construction process. Risk warnings are issued through the BIM model, and corresponding risk control measures are proposed;

[0011] S5, construction plan optimization and verification: Based on the risk assessment results, the construction plan is optimized and adjusted, and the optimized construction plan is re-imported into the BIM model for construction preview;

[0012] S6, Output and application of results: The optimized and verified construction plan will be output in the form of drawings and reports for reference and application by the construction unit to guide the actual construction process.

[0013] Furthermore, the data collection and integration in S1 includes:

[0014] S11, Collection and import of architectural design drawings: Collect architectural design drawings of construction projects, including 2D CAD drawings, floor plans, elevations and sections, and use the import function of BIM software to convert and import the architectural design drawings into BIM software;

[0015] S12, Collection and integration of engineering geological survey reports: Collect engineering geological survey reports of construction projects, including geological profiles, soil properties, groundwater levels, and seismic activity, and input the engineering geological survey reports into BIM software in a digital form;

[0016] S13, Collection and integration of construction plans: Collect construction plans for construction projects, including construction plans, construction processes, construction schedules, and resource allocation, and import data and information from the construction plans into BIM software;

[0017] S14, Multi-source data fusion: Use BIM software to convert design drawings, engineering geological survey reports and construction plans into a unified format and standardize them, and form a three-dimensional building information model in the BIM model.

[0018] Furthermore, the model optimization and adjustment in S2 includes:

[0019] S21, Geometric accuracy optimization: Use the geometric correction tool in the BIM software to optimize the geometric accuracy of each component in the 3D building information model, including the size, shape and position of the correction component;

[0020] S22, attribute data correction: check and correct the attribute data of each component in the three-dimensional building information model, including material type, strength grade and fire resistance performance, and use the attribute management function of the BIM software to check and correct the attribute data;

[0021] S23, collision detection and resolution: perform collision detection in BIM software, identify the conflicts and interferences between components in the 3D building information model, analyze the detected collision problems, adjust the positions and sizes of related components, and resolve the conflicts and interferences;

[0022] S24, actual construction condition correction: according to the actual situation of on-site construction, the 3D building information model is corrected, including the import and application of on-site measurement data, and the adjustment of the space requirements of construction equipment and machinery;

[0023] S25, Structural rationality verification: Use the structural analysis and verification functions in the BIM software to check and verify the structural rationality of the three-dimensional building information model, including strength analysis, deformation analysis, and stability analysis of load-bearing components.

[0024] Furthermore, the integration of intelligent sensing and structural health monitoring in S3 includes:

[0025] S31, Smart materials and sensor installation: Smart materials and sensors are installed on building structures. Smart materials include piezoelectric materials and shape memory alloys. Sensors include fiber Bragg grating sensors and capacitive strain sensors to monitor building structure data in real time.

[0026] S32, data collection and processing: collecting building structure data in real time, and processing and storing the collected building structure data;

[0027] S33, Establishment of structural health prediction model: Train historical building structure data to establish a structural health prediction model, predict the health status and performance changes of building structures, and identify structural anomalies and risks;

[0028] S34, real-time monitoring and early warning: based on real-time monitoring of building structure data, establish an early warning mechanism to detect and warn of structural anomalies;

[0029] S35, BIM-SHM integrated platform: Integrate structural health monitoring with BIM models to build a BIM-SHM integrated platform, display building structure data and prediction results of structural health prediction models in real time in the BIM model, and display the health status and performance changes of the building structure through a three-dimensional building information model.

[0030] Furthermore, the data collection and processing in S32 includes:

[0031] S321, data processing and analysis: cleaning, filtering and preprocessing of the collected building structure data, including normalization, standardization and missing value processing;

[0032] S322, Data storage and management: Store the processed and analyzed data in a cloud database and use encryption technology and access control strategies to prevent unauthorized access and data leakage.

[0033] Furthermore, the establishment of the structural health prediction model in S33 includes:

[0034] S331, Historical Data Collection and Collation: Collect and collate historical building structure data, including historical stress, deformation, and temperature;

[0035] S332, preliminary processing of historical data: preliminary processing of the collected historical building structure data, including:

[0036] Data cleaning: remove noise and erroneous values, including abnormal spikes, null values, and duplicate values;

[0037] Data standardization: normalize the mean and standard deviation to make the distribution of historical building structure data conform to the standard normal distribution;

[0038] Feature extraction: Extract key features related to structural health, including stress change rate, deformation trend, and temperature fluctuation;

[0039] S333, model selection and training: establish a structural health prediction model, divide the historical building structure data after preliminary processing into a training set and a test set, use the training set data to train the structural health prediction model, adjust the parameters of the structural health prediction model to optimize the prediction performance, and use the test set data to verify the trained structural health prediction model to evaluate the prediction accuracy and robustness of the structural health prediction model;

[0040] S334, Structural health prediction: Use the trained structural health prediction model to predict the building structure data collected in real time, predict the current health status of the building structure, identify structural anomalies and risks, predict the performance change trend of the building structure, and evaluate the structural health status.

[0041] Furthermore, the structural health prediction model adopts a Kalman filter, and the Kalman filter includes:

[0042] State initialization: Initialize the state vector And the state covariance matrix P0, the state vector includes stress, deformation and temperature, and the calculation formula is:

[0043]

[0044] in, is the initial estimate of the building structure stress, is the initial estimate of the building structure deformation, is an initial estimate of the building structure temperature, is the uncertainty in the stress estimate, is the uncertainty of the deformation estimate, is the uncertainty in the temperature estimate;

[0045] State prediction: Based on the current state estimate and the ARIMA model prediction value, the state and state covariance matrix of the next moment are predicted. The calculation formula is:

[0046]

[0047] in, is the predicted value of the state at time k+1, is the estimated value of the state at time k, Δt is the time step, and f is the state prediction function based on the ARIMA model;

[0048] The calculation formula of the state prediction function f is:

[0049]

[0050] Where c is a constant term, p is the order of the autoregressive part in the ARIMA model, is the coefficient of the autoregressive part, is the estimated value of the state at time ki, q is the order of the moving average part in the ARIMA model, and θ j is the coefficient of the moving average part, ∈ k-j is the prediction error (white noise) at time kj;

[0051] Adaptive noise covariance update: According to the real-time building structure data, the covariance matrix of process noise and measurement noise is dynamically adjusted to adapt to the changes in building structure data. The calculation formula is:

[0052]

[0053] Among them, Q kis the process noise covariance matrix at time k, α is the adaptive adjustment coefficient (0<α<1), Q k-1 is the process noise covariance matrix at time k-1, z k is the measurement value at time k, H is the measurement matrix, is the estimated value of the state at time k, R k is the measurement noise covariance matrix at time k, β is the adaptive adjustment coefficient (0<β<1), R k-1 is the measurement noise covariance matrix at time k-1, ∈ k is the prediction error (white noise) at time k;

[0054] Kalman gain calculation: Calculate the Kalman gain at the current moment for state update. The calculation formula is:

[0055] K k =P k|k-1 H T (HP k|k-1 H T +R k ) -1 ;

[0056] Among them, K k is the Kalman gain matrix at time k, P k|k-1 is the predicted value of the state covariance matrix at time k, H T is the transpose of the measurement matrix, R k is the measurement noise covariance matrix at time k;

[0057] State update: Use the measured values ​​to update the state estimate and state covariance matrix. The calculation formula is:

[0058]

[0059] P k|k =(IK k H)P k|k-1 ;

[0060] in, is the state update value at time k, is the state predicted at time k based on the state and measurement value at time k-1, P k|k is the updated value of the state covariance matrix at time k, I is the identity matrix, K k is the Kalman gain matrix at time k.

[0061] Furthermore, the structural health prediction in S334 includes:

[0062] S3341, Abnormality identification and risk assessment: Identify abnormalities and risks in the building structure through the prediction results of the structural health prediction model, and classify and evaluate the abnormalities. The calculation formula is:

[0063] Anomaly Detection:

[0064] Among them, ∈ k is the measurement residual, if ∈ k If it exceeds the preset threshold, it is judged as abnormal;

[0065] risk assessment:

[0066] Among them, R is the risk assessment value, w i is the weight of each anomaly;

[0067] S3342, Performance change trend prediction: Use the structural health prediction model to predict the performance change trend of the building structure and analyze the health status of the building structure. The calculation formula is:

[0068]

[0069] in, is the predicted value at the next h time;

[0070] S3343, Structural health assessment: Combine the real-time prediction results and performance change trends to assess the overall health of the building structure and generate a structural health report. The calculation formula is:

[0071]

[0072] Where S is the health score, N is the number of measurement points, ∈ i is the residual of the i-th measurement point, ∈ max is the maximum residual value.

[0073] Furthermore, the real-time monitoring and early warning in S34 include:

[0074] S341, setting warning thresholds: setting warning thresholds for various monitoring indicators based on historical building structure data;

[0075] S342, real-time warning: when the measurement residual ∈ k Or when the risk assessment value R exceeds the warning threshold, a warning signal is automatically issued;

[0076] S343, Early Warning Notification: Send early warning information to relevant managers and engineers via SMS and email.

[0077] Furthermore, the construction process simulation and risk assessment in S4 includes:

[0078] S41, combining the prediction results of the structural health prediction model: combining the prediction results of the structural health prediction model (such as future stress, deformation, and temperature) with the three-dimensional building information model to form a comprehensive building information database;

[0079] S42, construction process simulation: using the optimized 3D building information model, the entire construction process is simulated using construction simulation software to check material conflicts during the construction process, analyze the rationality of the construction sequence, and identify unreasonable construction sequences that lead to construction delays or waste of resources;

[0080] S43, construction risk assessment: Conduct risk assessment based on the results of construction process simulation;

[0081] S44, Risk Warning: Based on the results of construction risk assessment, risk warning is carried out through the BIM model;

[0082] S45, Risk control measures: Propose corresponding risk control measures based on risk warning information.

[0083] Beneficial effects of the present invention:

[0084] The present invention, by utilizing BIM technology and intelligent sensing technology, realizes the intelligence and automation of data processing, risk assessment, solution optimization and output of results, improves construction quality and efficiency, and provides a scientific basis for the safety and reliability of building structures.

[0085] The present invention, by combining the prediction results of the structural health prediction model and using the optimized three-dimensional building information model to simulate the construction process, can effectively analyze potential problems in the construction process, including material conflicts and unreasonable construction sequence, and conduct a comprehensive risk assessment based on the simulation results. Through risk identification, risk quantification and the establishment of an early warning mechanism, structural anomalies can be discovered and warned in a timely manner, and corresponding risk control measures can be proposed to ensure the safety and smooth progress of the construction process. This method can not only predict the health status and performance changes of the building structure in real time, but also identify and warn potential risks through intelligent algorithms, and provide efficient and accurate decision support.

[0086] The present invention optimizes and adjusts the construction plan through risk assessment results to ensure the rationality and feasibility of the plan, and conducts construction rehearsal through the BIM model to verify the actual effect of the optimization plan. The optimized construction plan is output in the form of drawings and reports for reference and application by the construction unit, guiding the actual construction process and ensuring the smooth completion of the construction project. BRIEF DESCRIPTION OF THE DRAWINGS

[0087] In order to more clearly illustrate the technical solutions in the present invention or the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings in the following description are only for the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0088] Figure 1 This is a schematic diagram of the analysis method flow of an embodiment of the present invention;

[0089] Figure 2 Schematic diagram of the integration of intelligent sensing and structural health monitoring according to an embodiment of the present invention. DETAILED DESCRIPTION

[0090] In order to make the objectives, technical solutions and advantages of the present invention more clearly understood, the present invention is further described in detail below in conjunction with specific embodiments.

[0091] It should be noted that, unless otherwise defined, the technical terms or scientific terms used in the present invention should be understood by people with ordinary skills in the field to which the present invention belongs. The "first", "second" and similar words used in the present invention do not indicate any order, quantity or importance, but are only used to distinguish different components. "Include" or "comprise" and similar words mean that the elements or objects appearing before the word include the elements or objects listed after the word and their equivalents, without excluding other elements or objects. "Connect" or "connected" and similar words are not limited to physical or mechanical connections, but may include electrical connections, whether direct or indirect. "Up", "down", "left", "right" and the like are only used to indicate relative positional relationships. When the absolute position of the described object changes, the relative positional relationship may also change accordingly.

[0092] like Figure 1-Figure 2 As shown in the figure, the BIM-based construction modeling pre-analysis method includes the following steps:

[0093] S1, data collection and integration: collect relevant data of the construction project, including architectural design drawings, engineering geological survey reports and construction plans, and import the relevant data into BIM software to form a three-dimensional building information model;

[0094] S2, model optimization and adjustment: optimize and adjust the 3D building information model to ensure the accuracy of the size, position and attributes of each component in the model, and modify the 3D building information model according to the actual construction conditions;

[0095] S3, Integration of intelligent sensing and structural health monitoring: Install intelligent materials and sensors on the surface of building structures to monitor building structure data in real time. Building structure data includes stress, deformation and temperature. Collect and process building structure data. Use structural health prediction models to predict the health status and performance changes of building structures. Integrate structural health monitoring with BIM models to achieve visual management and analysis of structural health data.

[0096] S4, construction process simulation and risk assessment: Combined with the prediction results of the structural health prediction model, the optimized three-dimensional building information model is used to simulate the entire construction process, analyze potential problems in the construction process, including material conflicts and unreasonable construction sequence, and conduct risk assessment based on the simulation results to identify risks in the construction process. Risk warnings are issued through the BIM model, and corresponding risk control measures are proposed;

[0097] S5, Construction plan optimization and verification: Based on the risk assessment results, optimize and adjust the construction plan, formulate a more reasonable and feasible construction plan, and re-import the optimized construction plan into the BIM model for construction preview to verify the feasibility and rationality of the optimized plan and ensure the smooth implementation of the construction process;

[0098] S6, Output and Application of Results: Output the optimized and verified construction plan in the form of drawings, reports, etc. for reference and application by the construction unit, guide the actual construction process, and ensure the smooth completion of the construction project;

[0099] Through the above steps, it is ensured that potential problems in the construction process can be fully identified and resolved before construction, thus improving construction quality and efficiency, and realizing the intelligence and automation of data processing, risk assessment, solution optimization and output of results.

[0100] Data collection and integration in S1 include:

[0101] S11, Collection and import of architectural design drawings: Collect architectural design drawings of construction projects, including 2D CAD drawings, floor plans, elevations and sections, and use the import function of BIM software to convert and import the architectural design drawings into BIM software;

[0102] S12, Collection and integration of engineering geological survey reports: Collect engineering geological survey reports of construction projects, including geological profiles, soil properties, groundwater levels, and seismic activity, and input the engineering geological survey reports into BIM software in a digital way;

[0103] S13, Collection and integration of construction plans: Collect construction plans for construction projects, including construction plans, construction processes, construction schedules, and resource allocation, and import data and information from the construction plans into BIM software;

[0104] S14, multi-source data fusion: use BIM software to convert design drawings, engineering geological survey reports and construction plans into a unified format and standardize them to ensure data consistency and integrity, and form a three-dimensional building information model in the BIM model;

[0105] Through the above steps, it is ensured that the collected and integrated data can accurately and completely reflect various key information of the construction projects that are about to be constructed or are under construction, thereby providing reliable data support for construction modeling pre-analysis.

[0106] Model optimization and adjustment in S2 include:

[0107] S21, Geometric accuracy optimization: Use the geometric correction tool in the BIM software to optimize the geometric accuracy of each component in the 3D building information model, including correcting the size, shape and position of the component to ensure that the geometric information in the model is consistent with the design drawings;

[0108] S22, attribute data correction: check and correct the attribute data of each component in the 3D building information model, including material type, strength grade and fire resistance performance. Use the attribute management function of the BIM software to check and correct the attribute data to ensure that the attribute information of each component is accurate;

[0109] S23, collision detection and resolution: collision detection is performed in BIM software to identify the conflicts and interferences between components in the 3D building information model, the detected collision problems are analyzed, the positions and sizes of the relevant components are adjusted, and the conflicts and interferences are resolved to ensure that no actual conflicts occur during the construction process;

[0110] S24, actual construction condition correction: according to the actual situation of on-site construction, the 3D building information model is corrected, including the import and application of on-site measurement data, and the adjustment of the space requirements of construction equipment and machinery, to ensure that the model is consistent with the actual construction conditions;

[0111] S25, Structural rationality verification: Use the structural analysis and verification functions in the BIM software to check and verify the structural rationality of the 3D building information model, including strength analysis, deformation analysis, and stability analysis of load-bearing components to ensure that the structural design in the model is reasonable and complies with relevant specifications and standards;

[0112] Through the above steps, the 3D building information model is comprehensively optimized and adjusted to ensure that the size, position and attributes of each component in the model are accurate, and necessary corrections are made according to actual construction conditions, providing a reliable basis for subsequent construction modeling pre-analysis.

[0113] Smart sensing and structural health monitoring integration in S3 includes:

[0114] S31, Smart materials and sensor installation: Smart materials and sensors are installed on building structures. Smart materials include piezoelectric materials and shape memory alloys. Sensors include fiber Bragg grating sensors and capacitive strain sensors to monitor building structure data in real time.

[0115] S32, data collection and processing: real-time collection of building structure data, and processing and storage of the collected building structure data to ensure the integrity and accuracy of the data;

[0116] S33, Establishment of structural health prediction model: Train historical building structure data to establish a structural health prediction model, predict the health status and performance changes of building structures, and identify structural anomalies and risks;

[0117] S34, real-time monitoring and early warning: based on real-time monitoring of building structure data, establish an early warning mechanism to detect and warn of structural anomalies;

[0118] S35, BIM-SHM integrated platform: Integrate structural health monitoring with BIM models to build a BIM-SHM integrated platform, display building structure data and prediction results of structural health prediction models in real time in the BIM model, and display the health status and performance changes of building structures through a three-dimensional building information model, providing analysis reports and decision support;

[0119] Through the above steps, it is ensured that the intelligent sensing and structural health monitoring system can be effectively installed and operated, and the stress, deformation and temperature data of the building structure can be collected and processed in real time. The health status and performance changes of the building structure can be predicted through the structural health prediction model, and the structural health data can be integrated with the BIM model to realize the visual management and analysis of the data, providing a scientific basis for the safety and reliability of the building structure.

[0120] Data acquisition and processing in S32 include:

[0121] S321, Data processing and analysis: Clean, filter and preprocess the collected building structure data. The preprocessing includes normalization, standardization and missing value processing to ensure the integrity and accuracy of the data;

[0122] S322, Data storage and management: Store the processed and analyzed data in a cloud database to ensure data security and traceability, and use encryption technology and access control strategies to ensure the security of stored data and prevent unauthorized access and data leakage;

[0123] Through the above steps, real-time collection, processing and storage of building structure data can be achieved, ensuring the integrity, accuracy and security of the data, providing a reliable data basis for structural health monitoring and prediction.

[0124] The structural health prediction model in S33 includes:

[0125] S331, Historical data collection and organization: Collect and organize historical building structure data, including historical stress, deformation and temperature, to ensure the integrity, accuracy and timeliness of the data, and provide a basis for subsequent model training;

[0126] S332, preliminary processing of historical data: preliminary processing of the collected historical building structure data, including:

[0127] Data cleaning: remove noise and erroneous values, including abnormal spikes, null values, and duplicate values;

[0128] Data standardization: normalize the mean and standard deviation to make the distribution of historical building structure data conform to the standard normal distribution, which is convenient for model training;

[0129] Feature extraction: Extract key features related to structural health, including stress change rate, deformation trend, and temperature fluctuation;

[0130] S333, Model selection and training: Establish a structural health prediction model, divide the historical building structure data after preliminary processing into a training set and a test set to ensure the training and verification effect of the model, use the training set data to train the structural health prediction model, adjust the parameters of the structural health prediction model to optimize the prediction performance, and use the test set data to verify the trained structural health prediction model to evaluate the prediction accuracy and robustness of the structural health prediction model;

[0131] S334, Structural health prediction: Use the trained structural health prediction model to predict the building structure data collected in real time, predict the current health status of the building structure, identify structural anomalies and risks, predict the performance change trend of the building structure, and evaluate the structural health status;

[0132] Through the above steps, a structural health prediction model is established and applied to accurately predict the health status and performance changes of building structures, identify structural anomalies and risks in a timely manner, and provide a scientific basis for structural health monitoring and management.

[0133] The structural health prediction model uses the Kalman filter, which includes:

[0134] State initialization: Initialize the state vector And the state covariance matrix P0, the state vector includes stress, deformation and temperature, and the calculation formula is:

[0135]

[0136] in, is the initial estimate of the building structure stress, is the initial estimate of the building structure deformation, is an initial estimate of the building structure temperature, is the uncertainty in the stress estimate, is the uncertainty of the deformation estimate, is the uncertainty in the temperature estimate;

[0137] State prediction: Based on the current state estimate and the ARIMA model prediction value, the state and state covariance matrix of the next moment are predicted. The calculation formula is:

[0138]

[0139] in, is the predicted value of the state at time k+1, is the estimated value of the state at time k, Δt is the time step, and f is the state prediction function based on the ARIMA model;

[0140] The calculation formula of the state prediction function f is:

[0141]

[0142] Where c is a constant term, p is the order of the autoregressive part in the ARIMA model, is the coefficient of the autoregressive part, is the estimated value of the state at time ki, q is the order of the moving average part in the ARIMA model, and θ j is the coefficient of the moving average part, ∈ k-j is the prediction error (white noise) at time kj;

[0143] Adaptive noise covariance update: According to the real-time building structure data, the covariance matrix of process noise and measurement noise is dynamically adjusted to adapt to the changes in building structure data. The calculation formula is:

[0144]

[0145] Among them, Q k is the process noise covariance matrix at time k, α is the adaptive adjustment coefficient (0<α<1), Q k-1 is the process noise covariance matrix at time k-1, z k is the measurement value at time k, H is the measurement matrix, and defines the measurement model. is the estimated value of the state at time k, R k is the measurement noise covariance matrix at time k, β is the adaptive adjustment coefficient (0<β<1), R k-1 is the measurement noise covariance matrix at time k-1, ∈ k is the prediction error (white noise) at time k;

[0146] Kalman gain calculation: Calculate the Kalman gain at the current moment for state update. The calculation formula is:

[0147] K k =P k|k-1 H T (HP k|k-1 H T +R k ) -1 ;

[0148] Among them, K k is the Kalman gain matrix at time k, P k|k-1 is the predicted value of the state covariance matrix at time k, H T is the transpose of the measurement matrix, R k is the measurement noise covariance matrix at time k;

[0149] State update: Use the measured values ​​to update the state estimate and state covariance matrix to ensure the accuracy of the state estimate. The calculation formula is:

[0150]

[0151] P k|k =(IK k H)P k|k-1 ;

[0152] in, is the state update value at time k, is the state predicted at time k based on the state and measurement value at time k-1, P k|k is the updated value of the state covariance matrix at time k, I is the identity matrix, K k is the Kalman gain matrix at time k;

[0153] Through the intelligent materials and sensors installed on the surface of the building structure, the building structure data such as stress, deformation and temperature are collected in real time, the ARIMA model is used to predict the historical data and real-time data, and the noise covariance is adjusted through the adaptive Kalman filter to optimize the state prediction and update process. The Kalman filter combined with the ARIMA model can effectively integrate historical data and real-time monitoring data, and improve the prediction accuracy and robustness by adaptively adjusting the noise covariance, and adapt to the complex structural health monitoring environment. This method can not only predict the health status and performance changes of the building structure in real time, but also identify and warn of potential risks through intelligent algorithms, and provide efficient and accurate decision support.

[0154] Structural health prediction in S334 includes:

[0155] S3341, Abnormality identification and risk assessment: Identify abnormalities and risks in the building structure through the prediction results of the structural health prediction model, and classify and evaluate the abnormalities. The calculation formula is:

[0156] Anomaly Detection:

[0157] Among them, ∈ k is the measurement residual, if ∈ k If it exceeds the preset threshold, it is judged as abnormal;

[0158] risk assessment:

[0159] Among them, R is the risk assessment value, w i is the weight of each anomaly;

[0160] Abnormal situations include:

[0161] Abnormal stress: Due to excessive structural loading, material degradation, construction defects or unexpected events (such as impact), the monitored stress value is much higher or lower than the normal range;

[0162] Abnormal deformation: Due to foundation settlement, component buckling, material aging or thermal expansion caused by temperature changes, the monitored deformation suddenly increases or exceeds the design limit;

[0163] Abnormal temperature: Due to changes in environmental conditions, fire, heating system failure, or cooling system failure, the monitored temperature value rises or falls abnormally and exceeds the expected range;

[0164] Abnormal vibration: Due to abnormal operation of mechanical equipment, earthquake, increased wind load or external impact, the monitored vibration frequency or amplitude increases abnormally;

[0165] Crack extension: Due to stress concentration, material degradation, environmental erosion or foundation settlement, the monitored crack width or length increases significantly;

[0166] Abnormal humidity: The monitored humidity level increases or decreases significantly due to water seepage, leakage, drainage system failure or environmental changes;

[0167] S3342, Performance change trend prediction: Use the structural health prediction model to predict the performance change trend of the building structure and analyze the health status of the building structure in the future. The calculation formula is:

[0168]

[0169] in, is the predicted value at the next h time;

[0170] S3343, Structural health assessment: Combine the real-time prediction results and performance change trends to assess the overall health of the building structure and generate a structural health report. The calculation formula is:

[0171]

[0172] Where S is the health score, N is the number of measurement points, ∈ i is the residual of the i-th measurement point, ∈ max is the maximum residual value;

[0173] Through the above steps, the structural health prediction model can be effectively applied to the real-time collected building structure data, accurately predict the current health status of the building structure, identify anomalies and risks, predict the performance change trend, evaluate the structural health status, and provide a scientific basis for the maintenance and management of the building structure.

[0174] Real-time monitoring and early warning in S34 include:

[0175] S341, setting warning thresholds: setting warning thresholds for various monitoring indicators based on historical building structure data;

[0176] S342, real-time warning: when the measurement residual ∈ k Or when the risk assessment value R exceeds the warning threshold, a warning signal is automatically issued;

[0177] S343, early warning notification: send early warning information to relevant managers and engineers via SMS and email;

[0178] Through the above steps, the real-time monitoring and early warning system can establish an effective early warning mechanism based on the real-time monitored building structure data to timely discover and warn of structural anomalies.

[0179] Construction process simulation and risk assessment in S4 include:

[0180] S41, combining the prediction results of the structural health prediction model: combining the prediction results of the structural health prediction model (such as future stress, deformation, and temperature) with the three-dimensional building information model to form a comprehensive building information database;

[0181] S42, construction process simulation: using the optimized 3D building information model, the entire construction process is simulated using construction simulation software to check material conflicts during the construction process, ensure the smooth progress of the construction process, analyze the rationality of the construction sequence, and identify unreasonable construction sequences that lead to construction delays or waste of resources;

[0182] S43, construction risk assessment: Conduct risk assessment based on the results of construction process simulation;

[0183] Construction risk assessment specifically includes:

[0184] Calculation of risk probability: Let P i is the probability of the occurrence of the ith risk event, which is evaluated based on historical data and expert judgment and calculated using the Bayesian method. The calculation formula is:

[0185]

[0186] Quantification of risk impact: Assume I i is the impact of the ith risk event, which is quantified based on simulation results and expert evaluation. The calculation formula is:

[0187] I i = Impact score × Impact scope;

[0188] Calculation of risk quantitative assessment value: Calculate the risk quantitative assessment value R i And the total risk assessment value R total , the calculation formula is:

[0189] R i =P i ×I i ;

[0190]

[0191] S44, Risk Warning: Based on the results of construction risk assessment, risk warning is carried out through the BIM model;

[0192] S45, Risk Control Measures: Propose corresponding risk control measures based on risk warning information;

[0193] Specific risk control measures include:

[0194] Immediate inspection: Send professionals to conduct on-site inspections of identified risk points to confirm the severity of the risk situation;

[0195] Temporary reinforcement: Temporary reinforcement of abnormal structural parts to prevent further damage;

[0196] Detailed assessment: Organize experts to conduct a detailed assessment of the structural health status and propose long-term repair plans;

[0197] Dynamic adjustment: Dynamically adjust construction plans and monitoring strategies based on real-time monitoring data and on-site inspection results to ensure construction safety and structural health;

[0198] Through the above steps, the construction process simulation and risk assessment can combine the prediction results of the structural health prediction model, use the optimized three-dimensional building information model to conduct a comprehensive analysis of potential problems in the construction process, and propose scientific risk control measures through risk assessment and early warning systems to ensure the safety and smooth progress of the construction process.

[0199] Those skilled in the art should understand that the discussion of any of the above embodiments is merely illustrative and is not intended to imply that the scope of the present invention is limited to these examples. Under the concept of the present invention, the technical features in the above embodiments or different embodiments may be combined, the steps may be implemented in any order, and there are many other variations of the different aspects of the present invention as described above, which are not provided in detail for the sake of simplicity.

[0200] The present invention is intended to cover all such substitutions, modifications and variations that fall within the broad scope of the claims. Therefore, any omissions, modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the protection scope of the present invention.

Claims

1. The BIM-based construction modeling pre-analysis method is characterized by: The following steps are involved: S1, data collection and integration: collect relevant data of the construction project, including architectural design drawings, engineering geological survey reports and construction plans, and import the relevant data into BIM software to form a three-dimensional building information model; S2, model optimization and adjustment: optimize and adjust the 3D building information model, and modify the 3D building information model according to actual construction conditions; S3, Integration of intelligent sensing and structural health monitoring: Install intelligent materials and sensors on the surface of building structures to monitor building structure data in real time. Building structure data includes stress, deformation and temperature. Collect and process building structure data. Use structural health prediction models to predict the health status and performance changes of building structures. Integrate structural health monitoring with BIM models to achieve visual management and analysis of structural health data. S4, construction process simulation and risk assessment: Combined with the prediction results of the structural health prediction model, the optimized three-dimensional building information model is used to simulate the entire construction process, analyze potential problems in the construction process, including material conflicts and unreasonable construction sequence, and conduct risk assessment based on the simulation results to identify risks in the construction process. Risk warnings are issued through the BIM model, and corresponding risk control measures are proposed; S5, construction plan optimization and verification: Based on the risk assessment results, the construction plan is optimized and adjusted, and the optimized construction plan is re-imported into the BIM model for construction preview; S6, Output and application of results: The optimized and verified construction plan will be output in the form of drawings and reports for reference and application by the construction unit to guide the actual construction process.

2. The BIM-based construction modeling pre-analysis method according to claim 1, characterized in that: The data collection and integration in S1 includes: S11, Collection and import of architectural design drawings: Collect architectural design drawings of construction projects, including 2D CAD drawings, floor plans, elevations and sections, and use the import function of BIM software to convert and import the architectural design drawings into BIM software; S12, Collection and integration of engineering geological survey reports: Collect engineering geological survey reports of construction projects, including geological profiles, soil properties, groundwater levels, and seismic activity, and input the engineering geological survey reports into BIM software in a digital form; S13, Collection and integration of construction plans: Collect construction plans for construction projects, including construction plans, construction processes, construction schedules, and resource allocation, and import data and information from the construction plans into BIM software; S14, Multi-source data fusion: Use BIM software to convert design drawings, engineering geological survey reports and construction plans into a unified format and standardize them, and form a three-dimensional building information model in the BIM model.

3. The BIM-based construction modeling pre-analysis method according to claim 1, characterized in that: The model optimization and adjustment in S2 includes: S21, Geometric accuracy optimization: Use the geometric correction tool in the BIM software to optimize the geometric accuracy of each component in the 3D building information model, including the size, shape and position of the correction component; S22, attribute data correction: check and correct the attribute data of each component in the three-dimensional building information model, including material type, strength grade and fire resistance performance, and use the attribute management function of the BIM software to check and correct the attribute data; S23, collision detection and resolution: perform collision detection in BIM software, identify the conflicts and interferences between components in the 3D building information model, analyze the detected collision problems, adjust the positions and sizes of related components, and resolve the conflicts and interferences; S24, actual construction condition correction: according to the actual situation of on-site construction, the 3D building information model is corrected, including the import and application of on-site measurement data, and the adjustment of the space requirements of construction equipment and machinery; S25, Structural rationality verification: Use the structural analysis and verification functions in the BIM software to check and verify the structural rationality of the three-dimensional building information model, including strength analysis, deformation analysis, and stability analysis of load-bearing components.

4. The BIM-based construction modeling pre-analysis method according to claim 1, characterized in that: The smart sensing and structural health monitoring integration in S3 includes: S31, Smart materials and sensor installation: Smart materials and sensors are installed on building structures. Smart materials include piezoelectric materials and shape memory alloys. Sensors include fiber Bragg grating sensors and capacitive strain sensors to monitor building structure data in real time. S32, data collection and processing: collecting building structure data in real time, and processing and storing the collected building structure data; S33, Establishment of structural health prediction model: Train historical building structure data to establish a structural health prediction model, predict the health status and performance changes of building structures, and identify structural anomalies and risks; S34, real-time monitoring and early warning: based on real-time monitoring of building structure data, establish an early warning mechanism to detect and warn of structural anomalies; S35, BIM-SHM integrated platform: Integrate structural health monitoring with BIM models to build a BIM-SHM integrated platform, display building structure data and prediction results of structural health prediction models in real time in the BIM model, and display the health status and performance changes of the building structure through a three-dimensional building information model.

5. The BIM-based construction modeling pre-analysis method according to claim 4, characterized in that: The data collection and processing in S32 includes: S321, data processing and analysis: cleaning, filtering and preprocessing of the collected building structure data, including normalization, standardization and missing value processing; S322, Data storage and management: Store the processed and analyzed data in a cloud database and use encryption technology and access control strategies to prevent unauthorized access and data leakage.

6. The BIM-based construction modeling pre-analysis method according to claim 5, characterized in that: The establishment of the structural health prediction model in S33 includes: S331, Historical Data Collection and Collation: Collect and collate historical building structure data, including historical stress, deformation, and temperature; S332, preliminary processing of historical data: preliminary processing of the collected historical building structure data, including: Data cleaning: remove noise and erroneous values, including abnormal spikes, null values, and duplicate values; Data standardization: normalize the mean and standard deviation to make the distribution of historical building structure data conform to the standard normal distribution; Feature extraction: Extract key features related to structural health, including stress change rate, deformation trend, and temperature fluctuation; S333, model selection and training: establish a structural health prediction model, divide the historical building structure data after preliminary processing into a training set and a test set, use the training set data to train the structural health prediction model, adjust the parameters of the structural health prediction model to optimize the prediction performance, and use the test set data to verify the trained structural health prediction model to evaluate the prediction accuracy and robustness of the structural health prediction model; S334, Structural health prediction: Use the trained structural health prediction model to predict the building structure data collected in real time, predict the current health status of the building structure, identify structural anomalies and risks, predict the performance change trend of the building structure, and evaluate the structural health status.

7. The BIM-based construction modeling pre-analysis method according to claim 6, characterized in that: The structural health prediction model adopts a Kalman filter, and the Kalman filter includes: State initialization: Initialize the state vector And the state covariance matrix P0, the state vector includes stress, deformation and temperature, and the calculation formula is: in, is the initial estimate of the building structure stress, is the initial estimate of the building structure deformation, is an initial estimate of the building structure temperature, is the uncertainty in the stress estimate, is the uncertainty of the deformation estimate, is the uncertainty in the temperature estimate; State prediction: Based on the current state estimate and the ARIMA model prediction value, the state and state covariance matrix of the next moment are predicted. The calculation formula is: in, is the predicted value of the state at time k+1, is the estimated value of the state at time k, Δt is the time step, and f is the state prediction function based on the ARIMA model; The calculation formula of the state prediction function f is: Where c is a constant term, p is the order of the autoregressive part in the ARIMA model, is the coefficient of the autoregressive part, is the estimated value of the state at time ki, q is the order of the moving average part in the ARIMA model, and θ j is the coefficient of the moving average part, ∈ k-j is the prediction error at time kj; Adaptive noise covariance update: According to the real-time building structure data, the covariance matrix of process noise and measurement noise is dynamically adjusted to adapt to the changes in building structure data. The calculation formula is: Among them, Q k is the process noise covariance matrix at time k, α is the adaptive adjustment coefficient, Q k-1 is the process noise covariance matrix at time k-1, z k is the measurement value at time k, H is the measurement matrix, is the estimated value of the state at time k, R k is the measurement noise covariance matrix at time k, β is the adaptive adjustment coefficient, R k-1 is the measurement noise covariance matrix at time k-1, ∈ k is the prediction error at time k; Kalman gain calculation: Calculate the Kalman gain at the current moment for state update. The calculation formula is: K k =P k|k-1 H T (HP k|k-1 H T +R k ) -1 ; Among them, K k is the Kalman gain matrix at time k, P k|k-1 is the predicted value of the state covariance matrix at time k, H T is the transpose of the measurement matrix, R k is the measurement noise covariance matrix at time k; State update: Use the measured values ​​to update the state estimate and state covariance matrix. The calculation formula is: P k|k =(I-K k H)P k|k -1; in, is the state update value at time k, is the state predicted at time k based on the state and measurement value at time k-1, P k|k is the updated value of the state covariance matrix at time k, I is the identity matrix, K k is the Kalman gain matrix at time k.

8. The BIM-based construction modeling pre-analysis method according to claim 7, characterized in that: The structural health prediction in S334 includes: S3341, Abnormality identification and risk assessment: Identify abnormalities and risks in building structures through the prediction results of the structural health prediction model, and classify and evaluate the abnormalities. The calculation formula is: Anomaly Detection: Among them, ∈ k is the measurement residual, if ∈ k If it exceeds the preset threshold, it is judged as abnormal; risk assessment: Among them, R is the risk assessment value, w i is the weight of each anomaly; S3342, Performance change trend prediction: Use the structural health prediction model to predict the performance change trend of the building structure and analyze the health status of the building structure. The calculation formula is: in, is the predicted value at the next h time; S3343, Structural health assessment: Combine the real-time prediction results and performance change trends to assess the overall health of the building structure and generate a structural health report. The calculation formula is: Where S is the health score, N is the number of measurement points, ∈ i is the residual of the i-th measurement point, ∈ max is the maximum residual value.

9. The BIM-based construction modeling pre-analysis method according to claim 8, characterized in that: The real-time monitoring and early warning in S34 include: S341, setting warning thresholds: setting warning thresholds for various monitoring indicators based on historical building structure data; S342, real-time warning: when the measurement residual ∈ k Or when the risk assessment value R exceeds the warning threshold, a warning signal is automatically issued; S343, Early Warning Notification: Send early warning information to relevant managers and engineers via SMS and email.

10. The BIM-based construction modeling pre-analysis method according to claim 9, characterized in that: The construction process simulation and risk assessment in S4 include: S41, combining the prediction results of the structural health prediction model: combining the prediction results of the structural health prediction model with the three-dimensional building information model to form a comprehensive building information database; S42, construction process simulation: using the optimized 3D building information model, the entire construction process is simulated using construction simulation software to check material conflicts during the construction process, analyze the rationality of the construction sequence, and identify unreasonable construction sequences that lead to construction delays or waste of resources; S43, construction risk assessment: Conduct risk assessment based on the results of construction process simulation; S44, Risk Warning: Based on the results of construction risk assessment, risk warning is carried out through the BIM model; S45, Risk control measures: Propose corresponding risk control measures based on risk warning information.

Citation Information

Cited By

  • Assembly type structure installation process monitoring and management method

    CN118966733A

  • Steel structure collaborative design method, device and equipment based on BIM (Building Information Modeling) driving

    CN119442754A

  • Building construction quality prediction method and system based on data analysis

    CN119443975A

  • Building construction site arrangement optimization method and system and storage medium

    CN119538607A

  • BIM-assisted steel structure construction safety management early warning method, device and equipment

    CN119599442A