Method for controlling power plant

Through collaborative work between the wind turbine generator and the power conversion unit, the problem that traditional solutions cannot effectively provide power grid frequency support is solved, faster and more stable frequency support is achieved, and the inertial simulation response of the wind turbine generator is reduced. energy loss during this period.

CN118786597APending Publication Date: 2024-10-15VESTAS WIND SYSTEMS AS
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202380024516.7
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Priority Date
2022-03-02
Filing Date
2023-02-21
Publication Date
2024-10-15

AI Technical Summary

Technical Problem

Traditional solutions cannot effectively provide sufficient frequency support to the power grid, especially the insufficient frequency support provided by variable-speed wind turbine generators, resulting in grid frequency fluctuations that are difficult to control.

Method used

By cooperating between the wind turbine generator and the power transfer unit, in response to the underfrequency support request of the power grid, it is determined to start the inertia simulation response period to increase power generation, and subsequently start the power consumption reduction period to reduce the power of the power transfer unit consumption to provide more stable frequency support.

Benefits of technology

The frequency support of the wind turbine power plant to the power grid is improved, the power grid responds quickly to frequency fluctuations, the rotational energy lost during the inertia simulation response of the wind turbine generator is reduced, and the frequency control capability of the power plant is improved.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118786597A_ABST
    Figure CN118786597A_ABST
Patent Text Reader

Abstract

A method for controlling a power plant (100), the power plant (100) comprising one or more wind turbine generators (104) and one or more power-to-X units (106), the power-to-X (106) units configured to convert power from the power plant (100) to X, the power plant (100) being connected to a power grid (102). The method comprises: in response to an under-frequency support request with respect to the power grid (102), determining (201) an inertia simulation response period (502b) for starting one or more wind turbine generators (104) to increase power generation by the wind turbine generators (104) to provide frequency support for the power grid (102); and initiating (203a) a power consumption reduction period (502c) of the power-to-X unit (106) to reduce power consumption of the power-to-X unit (106) to a lower level or zero when or after the inertia simulation response period (502b) has been determined to be initiated.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] Aspects of the invention relate to a method for controlling a power plant comprising one or more wind turbine generators, the power plant being connected to an electric power grid. Background Art

[0002] Typically, an electric power grid (e.g., referred to as a utility grid) may have defined parameters, such as a defined frequency, such as 50 Hz or 60 Hz. The stability of the power grid parameters depends on a variety of variables, including the balance between the power generated and the power consumed in the power grid. Typically, any imbalance between the power generated and the power consumed will result in a change in the grid frequency of the power grid. When more power is generated in the power grid than is consumed, the grid frequency increases. When more power is consumed than is generated, the grid frequency decreases. Typically, it is important to have a stable grid frequency in the power grid, i.e., to keep frequency fluctuations of the grid frequency as small as possible. Typically, a grid specification may be specified for the power grid, wherein the grid specification defines parameters that a power plant (such as a power plant including one or more wind turbine generators) connected to the power grid must meet, for example, to provide sufficient frequency support to the power grid. Summary of the invention

[0003] The inventors of the present invention have discovered shortcomings of conventional solutions for providing frequency support to a power grid by a power plant comprising one or more wind turbine generators. For example, some conventional solutions do not provide sufficiently efficient frequency support to the power grid.

[0004] It is an object of the present invention to provide a solution which mitigates or solves the disadvantages and problems of conventional solutions.

[0005] These and other objects are solved by the subject-matter of the independent claims. Further advantageous embodiments of the invention can be found in the dependent claims.

[0006] According to a first aspect of the present invention, the above and other objects are achieved by a method for controlling a power plant, the power plant comprising one or more wind turbine generators and one or more power-to-X units, the power-to-X units being configured to convert power from the power plant to X, the power plant being connected to a power grid, wherein the method comprises:

[0007] In response to an underfrequency support request for the power grid, determining an inertia emulation response period for starting one or more wind turbine generators to increase power generation (electricity generation) of the wind turbine generators to provide frequency support for the power grid; and

[0008] When or after it has been determined to initiate the inertia emulation response period, a power consumption reduction period of the one or more power-to-X units is initiated to reduce the power consumption of the one or more power-to-X units to a lower level or zero.

[0009] In general, the increasing penetration of variable speed wind turbine generators in the power grid has resulted in a reduction in the proportion of connected conventional power plants, including conventional large synchronous generators, which has resulted in a reduction in the inertia of the power grid, since conventional large synchronous generators provide an inertial response to provide frequency support to the power grid, while variable speed wind turbine generators are typically connected to the power grid via one or more power converters, i.e., the variable speed wind turbine generators are decoupled from the power grid via one or more power converters, and thus the wind turbine generators cannot provide a true inertial response for providing frequency support to the power grid. However, conventional control schemes may be applied to the variable speed wind turbine generators, which enables the variable speed wind turbine generators to provide a so-called virtual inertial response or inertial emulation response for providing frequency support to the power grid. During a drop in the power grid frequency, additional power may therefore be released from the variable speed wind turbine generator to the power grid by one or more of the conventional control schemes applied to the variable speed wind turbine generators, so as to provide frequency support to the power grid. The additional power is obtained from the kinetic energy or rotational energy stored in the rotating mass or rotor of the wind turbine generator, which typically results in a deceleration of the rotor of the wind turbine generator.

[0010] The advantage of the method according to the first aspect is that a power plant including one or more wind turbine generators provides improved frequency support to a power grid. The advantage of the method according to the first aspect is that rapid or fast frequency support provided by the power plant to the power grid is provided. The advantage of the method according to the first aspect is that the frequency support provided by the power plant to the power grid involving the inertial simulation response of the wind turbine generator is improved. The advantage of the method according to the first aspect is that the power grid is compensated by the power caused by the reduced power consumption of the power conversion unit, so that the power drop of the wind turbine generator during the recovery period after the initial period of the inertial simulation response, which is lost during the wind turbine generator regains the rotational energy lost during the inertial simulation response, is effectively offset or reduced. The advantage of the method according to the first aspect is that the process of the wind turbine generator regaining the rotational energy lost during the inertial simulation response is effectively improved because the power grid is compensated by the power caused by the reduced power consumption of the power conversion unit.

[0011] It should be understood that for some embodiments, after it has been determined to initiate an inertia emulation response period, there may or may not be a delay before a power consumption reduction period of one or more power-to-X units is initiated. For some embodiments, "X" with respect to a power-to-X unit may include or consist of one or more fuels.

[0012] According to an advantageous embodiment of the method according to the first aspect, the method comprises:

[0013] After determining to start the inertia simulation response period, starting the inertia simulation response period; and

[0014] When the inertia emulation response period is initiated or after it has been initiated, a power consumption reduction period of one or more power-to-X units is initiated.

[0015] An advantage of this embodiment is that the frequency support provided by the power plant to the power grid is further improved. It will be appreciated that for some embodiments, there may be a delay or no delay before the power consumption reduction period of one or more power-to-X units is initiated after the inertia emulation response period has been initiated. For alternative embodiments, the method may instead include the following steps: before initiating the inertia emulation response period, initiating the power consumption reduction period of one or more power-to-X units.

[0016] According to a further advantageous embodiment of the method according to the first aspect, the inertia emulation response period comprises a recovery period for the wind turbine generator to regain rotational energy lost during the inertia emulation response period, and wherein the method comprises:

[0017] determining a recovery period for starting one or more wind turbine generators; and

[0018] When or after the initiation recovery period has been determined, a power consumption reduction period of the one or more power-to-X units is initiated.

[0019] An advantage of this embodiment is that the frequency support provided by the power plant to the power grid is further improved. An advantage of this embodiment is that the frequency support provided by the power plant to the power grid involving the inertial simulation response of the wind turbine generator is further improved. An advantage of this embodiment is that the offset or reduction of the power reduction of the wind turbine generator during the recovery period is further improved. An advantage of this embodiment is that the process of the wind turbine generator regaining rotational energy during the recovery period is further improved. It should be understood that for some embodiments, there may be a delay or no delay before the power consumption reduction period of one or more power-to-power units is initiated after the recovery period has been determined to be initiated.

[0020] According to another advantageous embodiment of the method according to the first aspect, the method comprises:

[0021] After the recovery period has been determined to be initiated, initiating a recovery period for one or more wind turbine generators; and

[0022] Prior to initiating the restoration period, a power consumption reduction period of the one or more power-to-X units is initiated.

[0023] An advantage of this embodiment is that the frequency support provided by the power plant to the power grid is further improved.

[0024] According to a further advantageous embodiment of the method according to the first aspect, the method comprises:

[0025] After the recovery period has been determined to be initiated, initiating a recovery period for one or more wind turbine generators; and

[0026] When the recovery period is initiated or after it has been initiated, a period of reduced power consumption of one or more power-to-X units is initiated.

[0027] The advantage of this embodiment is that the frequency support provided by the power plant to the power grid is further improved. It should be understood that for some embodiments, there may be a delay after the restoration period is initiated before the power consumption reduction period of one or more power-to-X units is initiated, or there may be no delay.

[0028] According to a further advantageous embodiment of the method according to the first aspect, the method comprises:

[0029] terminating a restoration period for one or more wind turbine generators; and

[0030] Prior to terminating the restoration period, a power consumption reduction period of the one or more power-to-X units is initiated.

[0031] An advantage of this embodiment is that the frequency support provided by the power plant to the power grid is further improved.

[0032] According to an advantageous embodiment of the method according to the first aspect, the method comprises:

[0033] terminating the inertial simulation response period; and

[0034] Prior to terminating the inertia emulation response period, a power consumption reduction period of the one or more power-to-X units is initiated.

[0035] An advantage of this embodiment is that the frequency support provided by the power plant to the power grid is further improved.

[0036] According to another advantageous embodiment of the method according to the first aspect, the method comprises:

[0037] terminating the inertial simulation response period; and

[0038] When the inertia emulation response period terminates or after it has terminated, the power consumption reduction period of the one or more power-to-X units is terminated.

[0039] An advantage of this embodiment is that the frequency support provided by the power plant to the power grid is further improved.

[0040] According to another advantageous embodiment of the method according to the first aspect, the power consumption reduction period comprises an initial period and a subsequent period after the initial period,

[0041] The method includes:

[0042] During the initial period, power consumption of the one or more power-to-X units is gradually reduced to a lower level or to zero.

[0043] An advantage of this embodiment is that by gradually reducing the power consumption of one or more power-to-X units, the frequency support provided by the power plant to the power grid is further improved. An advantage of this embodiment is that the control of the frequency support provided to the power grid is improved.

[0044] According to a further advantageous embodiment of the method according to the first aspect, the power consumption reduction period comprises an initial period and a subsequent period after the initial period,

[0045] The method includes:

[0046] During subsequent time periods, power consumption of one or more power-to-X units is gradually increased from a lower level or zero.

[0047] An advantage of this embodiment is that by gradually increasing the power consumption of one or more power-to-X units, the frequency support provided by the power plant to the power grid is further improved. An advantage of this embodiment is that the control of the frequency support provided to the power grid is improved.

[0048] According to a further advantageous embodiment of the method according to the first aspect, the power-to-gas unit comprises a power-to-gas unit configured to convert electricity from the power plant into gas. This embodiment has the advantage that the frequency support provided by the power plant to the power grid is further improved.

[0049] According to an advantageous embodiment of the method according to the first aspect, the power-to-gas unit is configured to convert electricity from the power plant into a gas or a gas mixture comprising or consisting of one or more of the following group:

[0050] ·hydrogen;

[0051] Oxygen; and

[0052] Methane.

[0053] An advantage of this embodiment is that the frequency support provided by the power plant to the power grid is further improved.

[0054] According to a further advantageous embodiment of the method according to the first aspect, the power-to-gas unit comprises an electrolyser system comprising one or more of the following group:

[0055] Alkaline electrolyzer;

[0056] Non-pressurized alkaline electrolyzer;

[0057] Pressurized alkaline electrolyzer;

[0058] Proton exchange membrane electrolyzer;

[0059] Non-pressurized proton exchange membrane electrolyzer;

[0060] Pressurized proton exchange membrane electrolyzer;

[0061] Polymer electrolyte membrane electrolyzer;

[0062] Non-pressurized polymer electrolyte membrane electrolyzer;

[0063] · Pressurized polymer electrolyte membrane electrolyzer; and

[0064] Solid oxide electrolyzer.

[0065] An advantage of this embodiment is that the frequency support provided by the power plant to the power grid is further improved.

[0066] According to another advantageous embodiment of the method according to the first aspect, the method comprises receiving an under-frequency support request. This embodiment has the advantage that the frequency support provided by the power plant to the power grid is further improved.

[0067] According to a further advantageous embodiment of the method according to the first aspect, the underfrequency support request comprises one or more references, wherein the method comprises:

[0068] generating one or more set points based on one or more references; and

[0069] One or more set points are provided to one or more wind turbine generators and / or one or more power conversion units.

[0070] An advantage of this embodiment is that the frequency support provided by the power plant to the power grid is further improved.

[0071] According to a further advantageous embodiment of the method according to the first aspect, the underfrequency support request is triggered by one or more of the following group:

[0072] the operating frequency of the power grid is lower than a predetermined reference frequency by a predetermined frequency value; and

[0073] The operating frequency of the power grid decreases, and the amplitude of the change of its frequency gradient over time exceeds a predetermined change amplitude.

[0074] An advantage of this embodiment is that the frequency support provided by the power plant to the power grid is further improved.

[0075] According to an advantageous embodiment of the method according to the first aspect, wherein the power to X-unit is connected to a connection point of the wind turbine generator. This embodiment has the advantage that the frequency support provided by the power plant to the power grid is further improved.

[0076] According to another advantageous embodiment of the method according to the first aspect, the power-to-X unit is connected to a connection point of the power plant. This embodiment has the advantage that the frequency support provided by the power plant to the power grid is further improved.

[0077] According to another advantageous embodiment of the method according to the first aspect, the power to X-unit is connected to a connection point of a point of common coupling PCC between the power plant and the power grid. This embodiment has the advantage that the frequency support provided by the power plant to the power grid is further improved.

[0078] According to a further advantageous embodiment of the method according to the first aspect, the method comprises:

[0079] At least before the period of reduced power consumption, the power-to-X unit is provided with power from one or more of the following groups:

[0080] ·power plant;

[0081] The source of electricity for the power plant;

[0082] Generators in power plants; and

[0083] Wind turbine generators.

[0084] An advantage of this embodiment is that the frequency support provided by the power plant to the power grid is further improved.

[0085] According to a further advantageous embodiment of the method according to the first aspect, the power-to-X unit is configured to convert into X electric power from one or more of the following group:

[0086] The source of electricity for the power plant;

[0087] Generators in power plants; and

[0088] Wind turbine generators.

[0089] An advantage of this embodiment is that the frequency support provided by the power plant to the power grid is further improved.

[0090] According to a second aspect of the present invention, the above and other objects are achieved by a computer program comprising instructions, which, when executed by a computer, cause the computer to perform the method according to any of the embodiments disclosed above or below. The advantages of the computer program according to the second aspect correspond to the advantages of the method according to the first aspect and its embodiments disclosed above or below.

[0091] According to a third aspect of the present invention, the above and other objects are achieved by a computer-readable medium comprising instructions, and when a computer executes the instructions, the instructions cause the computer to perform a method according to any of the embodiments disclosed above or below. The advantages of the computer-readable medium according to the third aspect correspond to the advantages of the method according to the first aspect and its embodiments disclosed above or below.

[0092] According to one aspect of the present invention, the above-mentioned computer program and / or computer-readable medium is configured to implement the method and embodiments thereof described herein.

[0093] According to a fourth aspect of the present invention, the above and other objects are achieved by a control device for controlling a power plant, the power plant comprising one or more wind turbine generators and one or more power-to-X units configured to convert power from the power plant to X, the power plant being connected to a power grid, wherein the control device is configured to:

[0094] In response to an underfrequency support request for the power grid, determining an inertia emulation response period for activating one or more wind turbine generators to increase power generation of the wind turbine generators to provide frequency support for the power grid; and

[0095] When or after it has been determined to initiate the inertia emulation response period, a power consumption reduction period of the one or more power-to-X units is initiated to reduce the power consumption of the one or more power-to-X units to a lower level or zero.

[0096] The advantages of the control device according to the fourth aspect correspond to the advantages of the method according to the first aspect and the above-mentioned and below-mentioned embodiments thereof.

[0097] It should be understood that all embodiments described for the method aspects of the present invention are also applicable to the control device aspects of the present invention. Therefore, all embodiments described for the method aspects of the present invention can be performed by a control device, which may include one or more controllers, control units or control devices. Embodiments of the control device have advantages corresponding to the advantages of the above-mentioned method and its embodiments.

[0098] According to a fifth aspect of the present invention, the above and other objects are achieved by a power plant for providing electric power to a power grid, wherein the power plant comprises:

[0099] one or more wind turbine generators,

[0100] one or more power-to-X units configured to convert the electricity from the power plant into X, and

[0101] A control device according to any of the embodiments disclosed above or below.

[0102] The advantages of the power plant according to the fifth aspect correspond to the advantages of the method according to the first aspect and its above or below described embodiments.

[0103] Features and embodiments of the above-described method, computer program, computer-readable medium, control device and power plant, respectively, may be combined in various possible ways to provide further advantageous embodiments.

[0104] Further advantageous embodiments of the method, the computer program, the computer-readable medium, the control device and the power plant according to the invention as well as further advantages of embodiments of the invention can be gathered from the detailed description of the embodiments. BRIEF DESCRIPTION OF THE DRAWINGS

[0105] For illustrative purposes, embodiments of the present invention will now be described in more detail by way of example and with reference to the accompanying drawings, wherein like reference numerals are used for like parts and wherein:

[0106] Figure 1 is a schematic diagram illustrating an embodiment of a power plant according to a fifth aspect of the present invention, to which an embodiment of the method according to the first aspect of the present invention may be applied;

[0107] Figure 2 It is a graphic Figure 1 A schematic diagram of an embodiment of a wind turbine generator of a power plant;

[0108] Figure 3 It is a graphic Figure 1 A schematic diagram of an embodiment of a power conversion unit of a power plant;

[0109] Figure 4 is a schematic flow chart illustrating aspects of an embodiment of a method according to the first aspect of the invention;

[0110] Figure 5 is another schematic flow chart illustrating further aspects of an embodiment of the method according to the first aspect of the invention;

[0111] Figure 6is another schematic flow chart illustrating further aspects of an embodiment of the method according to the first aspect of the present invention;

[0112] Figure 7 is a schematic diagram including a schematic diagram illustrating an inertial simulation response of a wind turbine generator according to conventional technology;

[0113] Figure 8 is a schematic diagram comprising schematic diagrams illustrating aspects of an embodiment of a method according to the first aspect of the invention;

[0114] Fig. 9 is a schematic diagram comprising a schematic diagram illustrating further aspects of an embodiment of the method according to the first aspect of the invention;

[0115] Fig.10 is a schematic diagram comprising schematic diagrams illustrating further aspects of an embodiment of the method according to the first aspect of the invention; and

[0116] Fig.11 is a schematic diagram illustrating an embodiment of a control device according to the fourth aspect of the invention, in which a method according to any of the embodiments described herein may be implemented. DETAILED DESCRIPTION

[0117] Reference Figure 1 , schematically illustrates an embodiment of a power plant 100 for providing power or electrical energy to a power grid 102 according to a fifth aspect of the present invention. For example, an embodiment of the method according to the first aspect of the present invention may be applied to Figure 1 The power plant 100 shown in FIG. However, the embodiments of the method according to the first aspect may also be applied to other power plants. The power plant 100 includes one or more wind turbine generators 104, for example, two, three or more wind turbine generators 104. Figure 2 Various aspects of embodiments of wind turbine generator 104 are disclosed in further detail.

[0118] Reference Figure 1 , the power plant 100 includes one or more power-to-X units 106, and the one or more power-to-X units 106 are configured to convert power from the power plant 100 into X. In other words, the power-to-X unit 106 can be described as being configured to convert power from the power plant 100 into X, or the power-to-X unit can be configured to convert power from the power plant 100 or generated by the power plant 100 into X. Various aspects of embodiments of the power-to-X unit 106 will be described below in conjunction with Figure 3 Further details disclosed.

[0119] Reference Figure 1, for some embodiments, wind turbine generator 104 may be described as a power source of power plant 100 or a generator of power plant 100. For some embodiments, power plant 100 may include one or more additional power sources or generators, such as solar panels / photovoltaic panels 108, fuel cells 110, and / or battery units 112. For some embodiments, power plant 100 may be referred to as a hybrid power plant. Power plant 100 may be connected or connectable to power grid 102 via a point of common coupling PCC 114. For some embodiments, power grid 102 may be referred to as a utility grid, a power grid, or a power network. For example, power plant 100 may be located offshore or on land.

[0120] Reference Figure 1 The power plant 100 comprises a control device 116 for controlling the power plant 100 according to any of the embodiments disclosed above or below and / or according to the fourth aspect of the present invention. The control device 116 may comprise or be referred to as a power plant controller PPC. The control device 116 is further disclosed below.

[0121] Reference Figure 2 , schematically illustrates Figure 1 1. Embodiment of a wind turbine generator 104 of a power plant 100. The wind turbine generator 104 may include a rotor 118, the rotor 118 including one or more blades 120 or rotor blades 120, for example two or more blades 120, such as three blades 120 or more. The wind turbine generator 104 may include a tower 122 and a nacelle 124 mounted on top of the tower 122. The rotor 118 may be connected to the nacelle 124, such as rotatably connected or mounted to the nacelle 124. The wind turbine generator 104 may include a generator 126, the rotor 118 being connected to the generator 126. The rotor 118 is configured to drive the generator 126. The nacelle 124 may house the generator 126.

[0122] Reference Figure 2, the rotor 118 can rotate under the action of wind. The wind-induced rotational energy of the blades 120 and the rotor 118 can be transferred to the generator 126 through the coupler 128 (for example, including one or more shafts 130). Therefore, the wind turbine generator 104 can be described as being configured to convert the kinetic energy of the wind into mechanical energy or rotational energy through the blades 120, and then convert it into electricity through the generator 126. The wind turbine generator 104 may include one or more power converters 132 connected to the generator 126. The wind turbine generator 104 and / or the generator 126 can be connected to the power grid 102 through the one or more power converters 132. The one or more power converters 132 may include a first power converter, the first power converter is used to convert the alternating current from the generator 126 into direct current. The one or more power converters 132 may include a second power converter, the second power converter is used to convert the direct current from the first power converter into alternating current to provide to the power grid 102. The nacelle 124 may house the one or more power converters 132, or the one or more power converters 132 may be located elsewhere.

[0123] Reference Figure 2 , the wind turbine generator 104 may include a control device 133 for controlling the wind turbine generator 104. The control device 133 of the wind turbine generator 104 may include a wind turbine generator controller. The control device 133 of the wind turbine generator 104 may be configured to communicate with and / or be connected to the control device 116 of the power plant 100, or be a part of the control device 116. For some embodiments, the wind turbine generator 104 may be referred to as a variable speed wind turbine generator. It should be understood that the wind turbine generator 104 may include other units, components and / or equipment required for the wind turbine generator 104, such as sensors. For some embodiments, as Figure 2 As schematically illustrated in , the power conversion unit 106 can be connected (more specifically electrically connected) to the connection point of the wind turbine generator 102. For some embodiments, the wind turbine generator 102 and the power conversion unit 106 can be arranged together as a unit. However, for some embodiments, the power conversion unit 106 can be located and / or connected to other places in the power plant 100.

[0124] Reference Figure 3 , schematically illustrates Figure 1 106 of a power plant 100. For some embodiments, the "X" with respect to the power-to-X unit may include or consist of one or more fuels. Figure 3In the embodiment, the power-to-gas unit 106 includes and is illustrated as a power-to-gas (P2G) unit 134 that is configured to convert electricity from the power plant 100 into gas. For some embodiments, the power-to-gas unit 134 can be configured to convert electricity from the power plant 110 into a gas or a gas mixture, or to use electricity to produce a gas or a gas mixture that includes or consists of one or more of the following group: hydrogen, oxygen, and methane. Figure 3 In the illustrated embodiment, the power-to-gas unit 134 is configured to convert electricity from the power plant 100 into a gas mixture including hydrogen and oxygen. The power-to-gas unit 134 can be described as being configured to use electricity to decompose water into hydrogen and oxygen in a process known as electrolysis. Thus, hydrogen is produced by electrolysis, which can be used as a fuel. The power-to-gas unit 134 can include a container 136 that is configured to hold or contain water. The power-to-gas unit 134 can include one or more anodes 138 and one or more cathodes 140 that are separated from each other by a membrane 142. The container 136 can include a hydrogen outlet 144 and an oxygen outlet 146.

[0125] Reference Figure 3 For some embodiments, the power-to-gas unit 134 includes an electrolyzer system including one or more of the following:

[0126] Alkaline electrolyzer;

[0127] Non-pressurized alkaline electrolyzer;

[0128] Pressurized alkaline electrolyzer;

[0129] Proton exchange membrane electrolyzer;

[0130] Non-pressurized proton exchange membrane electrolyzer;

[0131] Pressurized proton exchange membrane electrolyzer;

[0132] Polymer electrolyte membrane electrolyzer;

[0133] Non-pressurized polymer electrolyte membrane electrolyzer;

[0134] · Pressurized polymer electrolyte membrane electrolyzer; and

[0135] Solid oxide electrolyzer (SOEC).

[0136] Reference Figure 3For some embodiments, a non-pressurized alkaline electrolyzer may have a power rise rate of about 10% per minute and a power fall rate of about 20% per minute. For some embodiments, a pressurized alkaline electrolyzer may have a power rise rate of about 200% per minute and a power fall rate of about 200% per minute. For some embodiments, a pressurized proton exchange membrane electrolyzer or a pressurized polymer electrolyte membrane electrolyzer may have a power rise rate of about 20% per second and a power fall rate of about 20% per second. The above percentage (%) levels are related to the nominal power of the corresponding electrolyzer.

[0137] Reference Figure 2 and Figure 3 For some embodiments, the power-to-X unit 106 may be connected (more specifically electrically connected) to a connection point of the wind turbine generator 104. For some embodiments, the power-to-X unit 106 may be connected (more specifically electrically connected) to a connection point of the power plant 100. For some embodiments, the power-to-X unit 106 may be connected (more specifically electrically connected) to a connection point of a point of common coupling (PCC) 114 between the power plant 100 and the power grid 102.

[0138] Reference Figure 3 For some embodiments, the power-to-X unit 106 may be configured to convert power from one or more of the following groups to X: a power source of the power plant 100; a generator of the power plant 100; and a wind turbine generator 104. It should be understood that the power-to-X unit 106 may include other units, components, and / or other equipment required for the power-to-X unit 106, such as pumps, vents, storage tanks, and / or separators. It should be understood that the power-to-X unit 106 may include other units, components, and / or other equipment required for the power-to-X unit 106, such as pumps, vents, storage tanks, and / or separators. Figure 3 Other embodiments than those disclosed are possible.

[0139] Reference Figures 4 to 6 , schematically illustrates aspects of an embodiment of a method for controlling a power plant 100 according to a first aspect of the invention, wherein the power plant 100 comprises one or more wind turbine generators 104 and one or more power-to-X units 106, wherein the power-to-X units 106 are configured to convert power from or generated by the power plant 100 into X, and wherein the power plant 100 is connected or connectable to a power grid 102.

[0140] Reference Figure 4 , an embodiment of the method comprises the following steps:

[0141] In response to an underfrequency support request regarding the power grid 102, e.g., from the power grid 102, determining 201 to initiate or start an inertia emulation response period of one or more wind turbine generators 104 (or determining 201 to initiate an inertia emulation response period) to increase power generation or output of the wind turbine generators 104 to provide frequency support for the power grid 102; and

[0142] When or after it has been determined to initiate an inertia emulation response period, initiating 203a or starting a power consumption reduction period for one or more power-to-X units 106 to reduce power consumption of the one or more power-to-X units 106 to a lower level or zero, e.g., from a first or higher level to a lower level or zero.

[0143] Reference Figure 4 For some embodiments, the method may include the following steps: controlling the power conversion unit 106 to counteract or reduce the power drop of the wind turbine generator 104 during a recovery period after the initial period of the inertia simulation response, in which the wind turbine generator 104 regains the rotational energy lost during the inertia simulation response, because the power of the power grid 102 is compensated by means of or through the power consumption reduction of the power conversion unit 106. Thereby, the frequency support provided by the power plant 100 to the power grid 102 is improved. It should be understood that for some embodiments, after it has been determined 201 to start the inertia simulation response period, there may be a delay, or no delay, before the power consumption reduction period of one or more power conversion units 106 is started 203a. The fact that the power consumption of the power conversion unit 106 is zero means that the power conversion unit 106 does not consume power or substantially consumes power. For some embodiments, during or within a period of reduced power consumption by one or more power-to-X units 106, power consumption by one or more power-to-X units 106 may be gradually reduced to a lower level or zero.

[0144] Reference Figure 4, for some embodiments, the inertia simulation response period may be referred to as a virtual inertia response period. It should be understood that during the inertia simulation response period, the wind turbine generator 104 provides or performs an inertia simulation response to provide frequency support for the power grid 102. Through the inertia simulation response, the power generation or output of the wind turbine generator 104 increases, such as rapidly increases, and can provide increased and / or additional power to the power grid 102 for frequency support. However, in general, the inertia simulation response and the resulting additional power output from the wind turbine generator 104 may only last for a limited period of time. Due to the inertia simulation response and the additional power to the power grid 102, generally, the wind turbine generator 104 (such as the rotor 118) loses rotational energy (or stored kinetic energy) and / or slows down. For some embodiments, the inertia simulation response of the wind turbine generator 104 can be described as extracting or additionally extracting stored kinetic energy from the rotor 118, and converting the extracted stored kinetic energy into additional power output to the power grid 102 for frequency support, which generally results in a deceleration of the rotor 118. After the inertia emulation response, in order to restore the wind turbine generator 104 to more optimal operation, the wind turbine generator 104 should generally regain the rotational energy lost during the inertia emulation response, for example during a recovery period. There are several conventional control schemes known to those skilled in the art for the wind turbine generator 104 to perform an inertia emulation response to provide frequency support to the power grid.

[0145] Reference Figure 5 , some embodiments of the method may include the following steps:

[0146] In response to an underfrequency support request regarding the power grid 102 , determining 201 an inertia emulation response period for starting one or more wind turbine generators 104 ;

[0147] After having determined to initiate an inertia simulation response period, initiating 202 an inertia simulation response period; and

[0148] When the inertia emulation response period is initiated or after it has been initiated, initiating 203b a power consumption reduction period of one or more power-to-X units 106 .

[0149] Reference Figure 5 It will be appreciated that for some embodiments, there may or may not be a delay after the inertia emulation response period has been initiated 202 before a power consumption reduction period for one or more power-to-X units is initiated 203b.

[0150] Reference Figure 6, wherein the inertia simulation response period may include a recovery period in which the wind turbine generator regains rotational energy (or rotational kinetic energy or angular kinetic energy) lost during the inertia simulation response period, and wherein the power consumption reduction period may include an initial period and a subsequent period after the initial period, some embodiments of the method may include one or more of the following steps:

[0151] At least before the period of reduced power consumption, providing 200a the power conversion unit 106 with power from one or more of the following: the power plant 100; a power source of the power plant 100; a generator of the power plant 100; and the wind turbine generator 104;

[0152] Receiving 200b an under-frequency support request of the power grid 102 (eg, from the power grid 102 , or from a controller of the power grid 102 );

[0153] In response to the underfrequency support request, determining 201 an inertia emulation response period for starting one or more wind turbine generators 104 ;

[0154] After it has been determined to start the inertia simulation response period, starting 202 the inertia simulation response period;

[0155] Determining 204 a recovery period for starting one or more wind turbine generators 104 ;

[0156] After the start-up recovery period has been determined, starting 205 a recovery period for one or more wind turbine generators 104 ;

[0157] When or after it has been determined that an inertia emulation response period is to be initiated, initiating 203a a power consumption reduction period of one or more power-to-X units 106;

[0158] When the inertia emulation response period is initiated or after it has been initiated, initiating 203b a power consumption reduction period of one or more power-to-X units 106;

[0159] Initiating 206 a period of reduced power consumption of one or more power-to-X units 106 when or after the initiation of a recovery period has been determined;

[0160] Before starting the recovery period, starting 207 a period of reduced power consumption of one or more power-to-X units 106;

[0161] · starting 208 a period of reduced power consumption of one or more power-to-X units 106 when the recovery period starts or after it has started;

[0162] terminating 209 a restoration period for one or more wind turbine generators 104 ;

[0163] Before terminating the restoration period, initiating 210 a period of reduced power consumption of one or more power-to-X units;

[0164] ·Terminate the 211 inertial simulation response period;

[0165] Before terminating the inertial emulation response period, initiating 212 a power consumption reduction period of one or more power-to-X units 106; and

[0166] • When the inertia emulation response period ends or after it has ended, terminating 213 the power consumption reduction period of one or more power-to-X units 104 .

[0167] Reference Figure 6 It should be understood that for some embodiments, there may be a delay, or no delay, after it has been determined 204 that a recovery period is initiated, before a period of reduced power consumption by one or more power-to-X units is initiated 206. It should be understood that for some embodiments, there may be a delay, or no delay, after a recovery period has been initiated 205, before a period of reduced power consumption by one or more power-to-X units is initiated 208.

[0168] Reference Figure 6 , some embodiments of the method may include one or more of the following steps:

[0169] During an initial period, gradually reducing 206a the power consumption of one or more power-to-X units to a lower level or zero; and

[0170] • During a subsequent period, gradually increasing 206b the power consumption of one or more power-to-X units from a lower level or zero.

[0171] It should be understood that although Figure 6 Only steps 206a and 206b are illustrated for step 206, but steps 206a and 206b can be applied to Figures 4 to 6 One or more of the other steps 203a, 203b, 207, 208, 210 and 212 of initiating a power consumption reduction period of one or more power-to-X units 106.

[0172] Reference Figure 6 , some embodiments of the method may include the following steps: controlling the power conversion unit 106 to offset or reduce the power reduction or sag of the wind turbine generator 104 during the recovery period, because the power grid 102 is compensated for the power caused by the reduction of power consumption by the power conversion unit 106.

[0173] For some embodiments, wherein the underfrequency support request includes one or more references, the method may include the following steps:

[0174] generating one or more set points based on one or more references; and

[0175] The one or more set points are provided or sent to one or more wind turbine generators 104 and / or one or more power conversion units 106 .

[0176] For some embodiments, the underfrequency support request may be triggered by one or more situations or events in the following group:

[0177] The operating frequency of the power grid 102 is lower than the predetermined reference frequency by a predetermined frequency value; and

[0178] The operating frequency of the power grid 102 decreases, and the amplitude of the change of its frequency gradient over time exceeds a predetermined change amplitude.

[0179] For some embodiments, the predetermined amplitude of change may be greater than 0.1 Hz / s. For some embodiments, the predetermined amplitude of change may be between 0.2 and 7 Hz / s. For some embodiments, the predetermined amplitude of change may be between 0.5 and 2 Hz / s. For some embodiments, the predetermined reference frequency may be 50 Hz or 60 Hz, and the predetermined frequency value may be greater than 2%. For some embodiments, the predetermined frequency value may be greater than 3%. However, in addition to the levels or thresholds mentioned above, other levels or thresholds are also possible.

[0180] Unless otherwise disclosed, please note that Figures 4 to 6 The method steps shown and described herein do not necessarily have to be followed Figures 4 to 6 The steps may be performed in the order shown in the accompanying claims. These steps may be performed in substantially any suitable order. In addition, one or more steps may be added without departing from the scope of the accompanying claims. One or more steps may be excluded without departing from the scope of the accompanying claims.

[0181] exist Figure 7 , a schematic diagram illustrating an inertial simulation response of a wind turbine generator according to conventional technology is shown, and in Figures 8 to 10 In the drawings, schematic diagrams illustrating aspects of an embodiment of a method according to the first aspect of the invention are shown.

[0182] Reference Figure 7, a diagram 300a schematically illustrates the frequency of the power grid to which the wind turbine generator is connected (grid frequency), and schematically illustrates an underfrequency deviation or event 302a in the power grid. A diagram 300b schematically illustrates the power provided by the wind turbine generator to the power grid. In response to the underfrequency event 302a, the wind turbine generator is controlled to turn on the inertia emulation response during an inertia emulation response period 302b to support the power grid. During the inertia emulation response period 302b, stored kinetic energy is extracted from the rotor of the wind turbine generator and converted into additional power, which is output to the power grid for frequency support, which is illustrated by a rapid increase 304b in power output by the wind turbine generator. The extraction of stored kinetic energy from the rotor causes the rotor to decelerate, resulting in a power drop 306b during a recovery period 308b following an initial period of the inertia emulation response period 302b. During the recovery period 308b, the wind turbine generator is controlled to regain the rotational energy lost during the inertia emulation response in order to return to more optimized operation. After the recovery period 308b, the wind turbine generator has returned to optimal operation.During the inertia emulation response period 302b and during the recovery period 308b, the wind turbine generator is controlled according to one or more conventional control schemes.

[0183] Reference Figure 8, graphs 400a, 400b, 400c, 400c schematically illustrate aspects of an embodiment of the method according to the first aspect. Graph 400a schematically illustrates the frequency (grid frequency) of the power grid 100 to which the wind turbine generator 104 is connected, and schematically illustrates an underfrequency deviation or event 402a in the power grid 100. Graph 400b schematically illustrates the power provided by the wind turbine generator 104 to the power grid 100. When the underfrequency event 402a occurs, the wind turbine generator 104 is controlled to turn on the inertia emulation response during the inertia emulation response period 402b to support the power grid 100. During the inertia emulation response period 402b, the stored kinetic energy is extracted from the rotor 118 of the wind turbine generator 104 and converted into additional power, which is output to the power grid 100 for frequency support, which is illustrated by the rapid increase 404b of the power output by the wind turbine generator 104. The extraction of stored kinetic energy from the rotor may result in a deceleration of the rotor 118, resulting in a power drop 406b during a recovery period 408b following an initial period of the inertia emulation response period 402b. During the recovery period 408b, the wind turbine generator 104 is controlled to regain the rotational energy lost during the inertia emulation response period 402b in order to return to a more optimized operation. After the recovery period 408b, typically, the wind turbine generator 104 returns to optimal operation. However, according to an embodiment of the method according to the first aspect, after the inertia emulation response period 402b has been initiated, a power consumption reduction period 402c of the power-to-electricity converter 106 is initiated, during which the power consumption of the power-to-electricity converter 106 is reduced. Figure 8 400c. With the aid of the power consumption reduction period 402c, during which the power consumption of the power-to-X unit 106 is gradually reduced to a lower level, the power reduction 406b of the wind turbine generator 104 during the recovery period 408b is offset or reduced because the power grid 102 is compensated by or through the power consumption reduction of the power-to-X unit 106. Graph 400d schematically illustrates the power output of the entire power plant 100 to the power grid 102.

[0184] Reference Fig. 9, diagrams 500a, 500b, 500c, 500c schematically illustrate further aspects of an embodiment of the method according to the first aspect. Diagram 500a schematically illustrates the frequency (grid frequency) of the power grid 100. Diagram 500b schematically illustrates the power provided by the wind turbine generator 104 to the power grid 100. In response to the underfrequency event 502a, the wind turbine generator 104 is controlled to start the inertial simulation response during the inertial simulation response period 502b to support the power grid 100, which involves a rapid increase 504b of power output and a recovery period 508b after the initial period of the inertial simulation response period 502b. Diagram 500c schematically illustrates that the power consumption reduction period 502c of the power-to-X unit 106 is started with a delay 504c after the inertial simulation response period 502b has been started. In addition, the graph 500c schematically illustrates that the power consumption reduction period 502c includes an initial period 506c and a subsequent period 508c after the initial period 506c. As schematically illustrated in the graph 500c, during the initial period 506c, the power consumption of the power-to-X unit 106 gradually decreases to a lower level, and during the subsequent period 508c, the power consumption of the power-to-X unit 106 is maintained at a lower level and may then gradually increase from the lower level. Fig. 9 The effect of the power consumption reduction period 502c is that the power of the wind turbine generator 104 decreases 506b relative to the power consumption of the wind turbine generator 104 during the inertial simulation response period 502b or during the recovery period 508b. Figure 8 The power reduction 406b of the wind turbine generator 104 is delayed or can be delayed. In addition, for some embodiments, Fig. 9 The power reduction 506b of the wind turbine generator 104 during the recovery period 508b is relative to Figure 8 The power drop 406b of the wind turbine generator 104 can be further reduced. Graph 500d schematically illustrates the power output from the entire power plant 100 to the power grid 102 .

[0185] Reference Fig.10, Graphs 600a, 600b, 600c, 600c schematically illustrate further aspects of an embodiment of the method according to the first aspect. Graph 600a schematically illustrates the frequency (grid frequency) of the power grid 100. Graph 600b schematically illustrates the power provided to the power grid 100 by the wind turbine generator 104. Graph 600c schematically illustrates that the power consumption reduction period 602c of the power conversion unit 106 starts immediately when or after the inertial simulation response period 502b is started, i.e. without any delay. Graph 600c schematically illustrates that the power consumption reduction period 602c includes an initial period 606c and a subsequent period 608c after the initial period 606c. As schematically illustrated in graph 600c, during the initial period 606c, the power consumption of the power conversion unit 106 is gradually reduced to a lower level, and during the subsequent period 608c, the power consumption of the power conversion unit 106 is gradually increased from a lower level. However, power consumption of the power-to-X unit 106 may be maintained at a lower level during the intermediate period, as schematically shown in graph 600c, before power consumption of the power-to-X unit 106 gradually increases from a lower level during a subsequent period 608c. Fig.10 The effect of the power consumption reduction period 602c is that Fig.10 The power reduction 606b of the wind turbine generator 104 during the recovery period 608b in Figure 8 The power drop 406b of the wind turbine generator 104 and relative to Fig. 9 The power drop 506b of the wind turbine generator 104 is further reduced. Graph 600d schematically illustrates the power output from the entire power plant 100 to the power grid 102 .

[0186] Reference Figures 4 to 6 and Figures 8 to 10It should be understood that after the inertia simulation response period, the power consumption reduction period, or the recovery period is started, each period lasts for a certain amount of time before it terminates. It should be understood that the power consumption reduction period overlaps at least with the inertia simulation response period. For some embodiments, the power consumption reduction period can be defined to last during at least a portion or most of the inertia simulation response period, such as during 50% to 100% of the inertia simulation response period, such as during 70% to 100% of the inertia simulation response period, or during the entire inertia simulation response period. For some embodiments, the power consumption reduction period can be defined to last in parallel with the inertia simulation response period or be effective simultaneously with it at least during a certain or specific period, such as during 50% to 100% of the inertia simulation response period, such as during 70% to 100% of the inertia simulation response period, or during the entire inertia simulation response period. For some embodiments, the power consumption reduction period can be defined to overlap at least with the recovery period. For some embodiments, the power consumption reduction period may be defined to last during at least a portion or a majority of the recovery period of the inertial emulation response period, such as during 50% to 100% of the recovery period, such as during 80% to 100% of the recovery period, or during the entire recovery period.

[0187] Reference Figure 1 and Fig.11 , schematically illustrates aspects of an embodiment of a control device 116 for controlling a power plant 100, wherein the power plant 100 includes one or more wind turbine generators 104 and one or more power-to-X units 106, wherein the power-to-X units 106 are configured to convert power from the power plant 100 to X, and wherein the power plant 100 is connected to a power grid 102. An embodiment of the control device 116 is configured to:

[0188] In response to an under-frequency support request regarding the power grid 102, determining 201 to initiate an inertia emulation response period of one or more wind turbine generators 104 to increase power generation of the wind turbine generators 104 to provide frequency support for the power grid 102; and

[0189] When or after it has been determined to initiate an inertia emulation response period, initiating 203a a power consumption reduction period of one or more power-to-X units 106 to reduce power consumption of the one or more power-to-X units 106 to a lower level or zero.

[0190] Reference Figure 1 The illustrated embodiment of the control device 116 includes a first determining unit 116a for determining a start inertia simulation response period in order to execute Figures 4 to 6The illustrated embodiment of the control device 116 comprises a first starting unit 116b for starting a power consumption reduction period in order to perform Figures 4 to 6 Steps 203a, 203b, 206, 207, 208, 210 and 212 in.

[0191] Reference Figure 1 Some embodiments of the control device 116 may include a second starting unit 116c, the second starting unit 116c is used to start the inertial simulation response period, so as to perform Figure 5 and Figure 6 Some embodiments of the control device 116 may include a second determining unit 116d, the second determining unit 116d is used to determine the start recovery period, so as to perform Figure 6 Some embodiments of the control device 116 may include a third starting unit 116e, the third starting unit 116e is used to start the recovery period, so as to perform Figure 6 Some embodiments of the control device 116 may include a first termination unit 116f, the first termination unit 116f is used to terminate the recovery period, so as to perform Figure 6 Some embodiments of the control device 116 may include a second termination unit 116g, the second termination unit 116g is used to terminate the inertial simulation response period, so as to perform Figure 6 Some embodiments of the control device 116 may include a third termination unit 116h, the third termination unit 116h is used to terminate the power consumption reduction period, so as to perform Figure 6 Step 213 in .

[0192] Reference Figure 1 For some embodiments, the control device 116 is configured to communicate directly or indirectly with one or more of the following groups, for example via a signal line (or cable or wire) or wirelessly: the power plant 100; the wind turbine generator 104; the power grid 102; sensors; and other equipment or systems of the power plant 100 or the wind turbine generator 104.

[0193] Fig.11An embodiment of a control device 116 according to a fourth aspect of the invention is shown schematically, the control device 116 may include a control unit 700, which may correspond to or may include one or more of the above-mentioned units 116a-h of the control device 116. The control unit 700 may include a computing unit 701, which may be composed of a processor or microcomputer of substantially any suitable type, such as a circuit for digital signal processing (digital signal processor, DSP) or a circuit with a predetermined specific function (application-specific integrated circuit, ASIC). The computing unit 701 is connected to a storage unit 702 arranged in the control unit 700. The storage unit 702 provides the computing unit 701 with, for example, stored program code and / or stored data required for the computing unit 701 to be able to perform calculations. The computing unit 701 is also arranged to store parts or final results of the calculations in the storage unit 702.

[0194] Reference Fig.11 Furthermore, the control unit 700 may be equipped with devices 711, 712, 713, 714 for receiving and transmitting input and output signals. These input and output signals may contain waveforms, pulses or other properties, which can be detected as information by means of the devices 711, 713 for receiving input signals and can be converted into signals that can be processed by the calculation unit 701. These signals are then available to the calculation unit 701. The devices 712, 714 for transmitting output signals are arranged to convert the signals received from the calculation unit 701 so as to create output signals by, for example, modulating the signals, which output signals can be transmitted, for example, to other parts and / or systems of the power plant 100 or parts and / or systems associated with the power plant 100 (see Figure 1 ). Each connection to the device for receiving and transmitting input and output signals may be made by one or more of a cable, a data bus, and a wireless connection.

[0195] Here and in this document, units are generally described as providing steps for performing a method according to an embodiment of the invention. This also includes that the unit is designed and / or configured to perform these method steps.

[0196] Reference Figure 1 , the units 116a-h of the control device 116 are Figure 1 116a-h are shown as separate units. However, these units 116a-h may be logically separate but physically implemented in the same unit, or may be arranged together both logically and physically. These units 116a-h may, for example, correspond to instruction groups, which may be in the form of programming code, which are input to the processor / computing unit 701 (see FIG. 116b ) when these units are active and / or used to perform their method steps. Fig.11 ) and used by processor / computing unit 701.

[0197] Reference Figure 1 and Fig.11 According to an embodiment of the present invention, one or more control units 700 may be included, such as one or more devices, controllers or control devices 116 may be arranged to perform all method steps described above, in the claims and in connection with the embodiments described herein. The control device 116 is associated with the above advantages of each respective embodiment of the method.

[0198] Reference Fig.11 According to a second aspect of the present invention, a computer program 703 is provided, which includes instructions. When the program is executed by a computer, the instructions cause the computer to perform one or more methods according to the embodiments disclosed above.

[0199] According to a third aspect of the present invention, a computer-readable medium is provided, the computer-readable medium comprising instructions, which, when executed by a computer, enable the computer to perform one or more methods according to the embodiments disclosed above.

[0200] Those skilled in the art will appreciate that the embodiments of the method according to the first aspect described herein may be implemented in a computer program 703 (see Fig.11 ), when the computer program 703 is executed in a computer, the computer program instructs the computer to execute the method. The computer program is usually constituted by a computer program product 703 stored on a non-temporary / non-volatile digital storage medium, wherein the computer program is incorporated into a computer readable medium of the computer program product. The computer readable medium includes suitable memories, such as: ROM (read-only memory), PROM (programmable read-only memory), EPROM (erasable PROM), flash memory, EEPROM (electrically erasable PROM), hard disk unit, etc.

[0201] The present invention is not limited to the embodiments described above. On the contrary, the present invention relates to and covers all different embodiments included within the scope of the independent claims.

Claims

1. A method for controlling a power plant (100), the power plant (100) comprising one or more wind turbine generators (104) and one or more power-to-X units (106), the power-to-X units (106) being configured to convert power from the power plant (100) into X, the power plant (100) being connected to a power grid (102), wherein: The method comprises: In response to an under-frequency support request regarding the power grid (102), determining (201) to initiate an inertia emulation response period (502b) of the one or more wind turbine generators (104) to increase power generation of the wind turbine generators (104) to provide frequency support for the power grid (102); and When or after it has been determined to initiate the inertia emulation response period (502b), initiating (203a) a power consumption reduction period (502c) of the one or more power-to-X units (106) to reduce the power consumption of the one or more power-to-X units (106) to a lower level or zero.

2. The method according to claim 1, wherein: The method comprises: After determining to initiate the inertia emulation response period (502b), initiating (202) the inertia emulation response period (502b); and When the inertia emulation response period (502b) is initiated or after it has been initiated, a power consumption reduction period (502c) of the one or more power-to-X units (106) is initiated (203b).

3. The method according to claim 1 or 2, wherein: The inertia emulation response period (502b) includes a recovery period (508b) to allow the wind turbine generator (104) to regain rotational energy lost during the inertia emulation response period (502b), and wherein the method comprises: determining (204) the restoration period (508b) for starting the one or more wind turbine generators (104); and When or after it has been determined that the restoration period (508b) is to be initiated, a power consumption reduction period (502c) of the one or more power-to-X units (106) is initiated (206).

4. The method according to claim 3, wherein: The method comprises: After having determined to initiate the recovery period (508b), initiating (205) the recovery period (508b) of the one or more wind turbine generators (104); and Prior to initiating the restoration period (508b), a power consumption reduction period (502c) of the one or more power-to-X units (106) is initiated (207).

5. The method according to claim 3, wherein: The method comprises: After having determined to initiate the recovery period (508b), initiating (205) the recovery period (508b) of the one or more wind turbine generators (104); and When the recovery period (508b) is initiated or after it has been initiated, the power consumption reduction period (502c) of the one or more power-to-X units (106) is initiated (208).

6. The method according to any one of claims 3 to 5, wherein: The method comprises: terminating (209) the restoration period (508b) of the one or more wind turbine generators (104); and Prior to terminating the restoration period (508b), the power consumption reduction period (502c) of the one or more power-to-X units (106) is initiated (210).

7. The method according to any one of claims 1 to 6, wherein: The method comprises: terminating (211) the inertial simulation response period (502b); and Prior to terminating the inertia emulation response period (502b), the power consumption reduction period (502c) of the one or more power-to-X units (106) is initiated (212).

8. The method according to any one of claims 1 to 7, wherein: The method comprises: terminating (211) the inertial simulation response period (502b); and When or after the inertia emulation response period (502b) has terminated, the power consumption reduction period (502c) of the one or more power-to-X units (106) is terminated (213).

9. The method according to any one of claims 1 to 8, wherein: The power consumption reduction period (502c) includes an initial period (506c) and a subsequent period (508c) after the initial period (506c), and Wherein, the method comprises: During the initial period (506c), power consumption of the one or more power-to-X units (106) is gradually reduced (206a) to a lower level or zero.

10. The method according to any one of claims 1 to 9, wherein: The power consumption reduction period (502c) includes an initial period (506c) and a subsequent period (508c) after the initial period (506c), and Wherein, the method comprises: During the subsequent period (508c), power consumption of the one or more power-to-X units (106) is gradually increased (206b) from the lower level or zero.

11. The method according to any one of claims 1 to 10, wherein: The power-to-gas unit (106) includes a power-to-gas unit (134) configured to convert electricity from the power plant (100) into gas.

12. The method according to any one of claims 1 to 11, wherein: The power-to-X unit (106) is configured to convert power from one or more of the following groups into X: · a source of electric power for the power plant (100); a generator of the power plant (100); and The wind turbine generator (104).

13. A computer program (703) or a computer readable medium comprising instructions which, when executed by a computer, cause the computer to perform the method according to any one of claims 1 to 12.

14. A control device (116) for controlling a power plant (100), the power plant (100) comprising one or more wind turbine generators (104) and one or more power-to-X units (106), the power-to-X units (106) being configured to convert power from the power plant (100) into X, the power plant (100) being connected to a power grid (102), wherein: The control device (116) is configured to: In response to an under-frequency support request for the power grid (102), determining an inertia simulation response period (502b) for starting the one or more wind turbine generators (104) to increase power generation of the wind turbine generators (104) to provide frequency support for the power grid (102); and When or after it has been determined to initiate the inertia emulation response period (502b), an electric power consumption reduction period (502c) of the one or more electric power-to-X units (106) is initiated to reduce the electric power consumption of the one or more electric power-to-X units (106) to a lower level or zero.

15. A power plant (100) for providing electric power to a power grid (102), wherein: The power plant comprises: one or more wind turbine generators (104); one or more power-to-X units (106), the one or more power-to-X units (106) configured to convert power from the power plant (100) into X; and A control device (116) according to claim 14.