Quick and refined construction method for prefabricated floating slabs
By measuring and adjusting the elevation and load force of the floating panels, the problem of poor construction quality in the existing technology is solved, the efficient and refined construction of the prefabricated floating panels is achieved, and the vibration-damping performance and safety of the floating panels are ensured. sex.
Patent Information
- Application Number
- CN202411003113.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-24
- Publication Date
- 2024-10-18
AI Technical Summary
The existing construction method of prefabricated floating panels is difficult to ensure the uniform load of the isolator and the compensation of the difference in base elevation, resulting in uneven construction quality and affecting the vibration reduction performance and safety of the floating panels.
By measuring the difference between the actual elevation and the design elevation of the floating plate, special lifting equipment, water drills and drilling tools are used to accurately lift and adjust the load force to ensure that the load force of the vibration isolator is uniform and fixed with locking bolts. Adjust the height of the backing plate and the inner cylinder of the vibration isolator to achieve one-time adjustment.
It improves the construction efficiency and accuracy, ensures the uniform load force of the vibration isolator, eliminates overloading and hanging, meets multiple acceptance standards, and ensures the vibration reduction performance and safety of the floating plate.
Smart Images

Figure CN118792916A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of urban rail transit construction, and in particular to a rapid and refined construction method for a prefabricated floating slab. Background Art
[0002] Urban rail transit has the characteristics of large capacity, safety, comfort, speed and punctuality. It is a "green" mode of transportation with low energy consumption and less pollution. While solving the problem of traffic congestion in densely populated urban areas, urban rail transit also faces the problem of causing vibration and noise in the surrounding environment along the line. In order to effectively control the vibration and noise impact of rail transit on the environment, most new lines widely use various vibration reduction and noise reduction technologies including floating slabs.
[0003] The floating slab track bed system consists of rails, fasteners, track bed, vibration isolators, rubber sealing strips, shear hinges, bases, drainage ditches, etc. It is a special track structure that reduces the vibration and noise interference of trains to the outside world by embedding vibration isolators in the reinforced concrete track bed. Floating slab technology has been widely used in areas where rail transit lines pass through residential areas and areas with high environmental protection requirements.
[0004] The floating slab roadbed is divided into cast-in-place and prefabricated types according to the structural form. Compared with the cast-in-place type, the prefabricated floating slab can completely solve the problems of slow construction progress and uneven slab construction quality caused by on-site steel bar binding and concrete pouring. By reasonably arranging the construction process, the construction efficiency can be greatly improved. Therefore, the prefabricated floating slab has become the mainstream structural form of the mainstream floating slab. As the core component of the floating slab vibration reduction system, the stress state of the isolator directly affects the working performance of the floating slab, and its uniform stress is a necessary condition for the normal operation of the floating slab.
[0005] At present, the prefabricated floating slab generally adopts the "bottom-up" construction method, which achieves the effect of lifting the slab body through 2-3 rounds of vibration isolators. This method uses the rail surface elevation as the final acceptance standard. A large number of survey results show that the load capacity of the vibration isolator (4) cannot be guaranteed after multiple rounds of adjustment, and overload and hanging phenomena are frequent. When the height difference of the base (5) is large, the force of the vibration isolator (4) can only be fuzzy processed by the operator's experience, and it is impossible to achieve refined construction. In the end, the force difference of the vibration isolator (4) is huge; at the same time, the elevation of the floating slab after construction by this method is difficult to guarantee, and there are often large differences in the height of the fastener pads, over-pads, and hanging phenomena under the rails, which bring great performance and safety hazards to the safe and stable operation of the floating slab. In addition, since the vibration isolator (4) is a hidden project of the track mechanism, the uneven construction quality brings huge challenges to the later track maintenance. Therefore, a fast and refined construction method for prefabricated floating slabs is proposed. Summary of the invention
[0006] In view of the shortcomings of the prior art, the present invention provides a rapid and refined construction method for a prefabricated floating slab, which can complete high-quality construction of uniform loading of the floating slab isolators and effective compensation for base elevation differences while ensuring high construction efficiency. Rapid and precise construction can ensure that the floating slab can exert excellent vibration reduction performance during operation.
[0007] To achieve the above objectives, the present invention is implemented through the following technical solutions: A method for rapid and refined construction of a prefabricated floating slab, comprising the following steps:
[0008] S1: Carry out the pouring of the floating slab base in the viaduct / tunnel according to the design requirements;
[0009] S2: After detecting that the base strength meets the requirements, the prefabricated floating slab is taken out and hoisted and placed on the base;
[0010] S3: measuring the actual elevations of the four corners of the prefabricated floating slab, and calculating the difference between the actual elevations and the design elevations of the prefabricated floating slab;
[0011] S4: four special lifting devices are placed into the lifting holes reserved in the prefabricated panel body, and the lifting devices lift the prefabricated floating panel body. The lifting devices are controlled according to the difference measured in step S3 to lift the panel body to the designed elevation at one time. After the panel body reaches the designed elevation, the lifting devices are locked;
[0012] S5: Use a water drill and matching drilling tools to drill holes and install positioning pins, and place the inner cylinder of the vibration isolator and an appropriate amount of height adjustment gaskets into the outer cylinder of the vibration isolator corresponding to the entire floating plate;
[0013] S6: Use a dedicated isolator load force measuring device to accurately adjust the load force of all isolator inner cylinders one by one by adding or removing height adjustment pads;
[0014] S7: Remove four special lifting devices from the lifting holes reserved in the precast panel body;
[0015] S8: Check and confirm whether the elevation of the prefabricated floating slab meets the requirements;
[0016] S9: Use locking bolts to fix the height adjustment plate, locking gasket and inner tube of the vibration isolator together.
[0017] Optionally, S1: in the step of casting the base of the floating slab in the viaduct / tunnel according to the design requirements, when casting the base, the elevation, curve superelevation and ditch setting requirements in the design requirements need to be met.
[0018] Optionally, in S2: after detecting that the strength of the base meets the requirements, the prefabricated floating slab is taken out and hoisted to be placed on the base, and the longitudinal and transverse positions of the slab need to be precisely adjusted according to the final design requirements.
[0019] Optionally, S4: four special jacking devices are placed into the jacking holes reserved in the prefabricated plate body, the jacking devices lift the prefabricated floating plate body, and the jacking devices are controlled according to the difference measured in step S3 to lift the plate body to the designed elevation at one time. After the plate body reaches the designed elevation, the four special jacking devices in the step of locking the jacking devices can be hydraulically driven or electrically driven.
[0020] Optionally, in step S5: drilling holes and installing locating pins using a water drill and a matching drilling tool, placing the isolator inner tube and an appropriate amount of height adjustment gaskets into the isolator outer tube corresponding to the entire floating plate, when installing the locating pins, the installation must be carried out in accordance with the requirements, and the installation requirements are that the locating pins are installed with high precision and firmly fixed.
[0021] Optionally, in the step of using a dedicated isolator load force measuring device to accurately adjust the load force of all isolator inner cylinders one by one by adding or subtracting height adjustment pads, when accurately adjusting the load force of the isolator inner cylinder, it is necessary to ensure that all isolators are subjected to basically uniform force.
[0022] Optionally, after completing the step of S9: fixing the height adjustment plate, locking gasket and inner tube of the vibration isolator into one using locking bolts, subsequent adjustment and installation of shear hinges, fasteners and rails can be performed.
[0023] The present invention provides a method for rapid and refined construction of a prefabricated floating slab, which has the following beneficial effects:
[0024] The rapid and refined construction method for prefabricated floating slabs can adjust the prefabricated floating slabs into place at one time by adopting the construction method, and can meet multiple acceptance standards for the elevation of the prefabricated floating slab body, the load distribution of the isolator, and the rail surface elevation. The prefabricated floating slab can be adjusted once to ensure that the slab body elevation reaches the designed elevation, providing a good foundation for the subsequent installation of shear hinges, rails, and fasteners. By adopting the refined construction method, all isolators are loaded more evenly after construction, and overload and hanging are eliminated. The construction method has strong adaptability, and can perform effective elevation compensation in the super-elevated transition section of the curve and in the case of large construction errors in the base elevation. Compared with the conventional 2-3 times of jacking of the existing prefabricated slabs, the construction efficiency is improved. BRIEF DESCRIPTION OF THE DRAWINGS
[0025] Figure 1 This is a schematic diagram of the structure of the prefabricated floating slab of the present invention;
[0026] Figure 2 This is a schematic diagram of the internal structure of the prefabricated floating slab of the present invention;
[0027] Figure 3 This is a schematic diagram of the first lifting and elevation inspection of the plate body of the present invention;
[0028] Figure 4 It is a schematic diagram of load force adjustment of the vibration isolator of the present invention;
[0029] Figure 5 This is a diagram of the rapid and refined construction steps of the prefabricated floating slab of the present invention.
[0030] In the figure: 1. Tunnel; 2. Prefabricated floating plate; 3. Prefabricated jacking hole; 4. Vibration isolator; 5. Base; 6. Leveling pad; 7. Vibration isolator inner tube; 8. Vibration isolator outer tube; 9. Special measuring equipment for vibration isolator load force; 10. Plate one-time jacking equipment. DETAILED DESCRIPTION
[0031] The technical solutions in the embodiments of the present invention will be described clearly and completely below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, rather than all the embodiments.
[0032] See also Figures 1 to 5 The present invention provides a technical solution: a method for rapid and refined construction of a prefabricated floating slab, comprising the following steps:
[0033] S1: According to the design requirements, the floating slab base 5 in the viaduct / tunnel 1 is poured. When pouring the base 5, the elevation, curve superelevation, ditch setting and other requirements in the design requirements need to be met;
[0034] S2: After detecting that the strength of the base 5 meets the requirements, the prefabricated floating slab 2 is taken out and hoisted and placed on the base 5. The longitudinal and transverse positions of the slab need to be precisely adjusted according to the final design requirements;
[0035] S3: measuring the actual elevations of the four corners of the prefabricated floating slab 2, and calculating the difference between the actual elevations and the designed elevations of the prefabricated floating slab 2;
[0036] S4: four special lifting devices are placed into the lifting holes reserved in the prefabricated plate body, and the lifting devices lift the prefabricated floating plate 2 plate body. The lifting devices are controlled according to the difference measured in step S3 to lift the plate body to the designed elevation at one time. After the plate body reaches the designed elevation, the lifting devices are locked. The four special lifting devices can be hydraulically driven or electrically driven.
[0037] S5: Use a water drill and a matching drilling tool to drill holes and install positioning pins, place the vibration isolator inner tube 7 and an appropriate amount of height adjustment gaskets into the vibration isolator outer tube 8 corresponding to the entire floating plate, and the installation requirements for the positioning pins are that the positioning pins need to be installed with high precision and fixed firmly;
[0038] S6: Use the vibration isolator load force special measuring equipment 9 to accurately adjust the load force of all vibration isolator inner tubes 7 one by one by adding or removing height adjustment pads. When accurately adjusting the load force of the vibration isolator inner tube 7, it is necessary to ensure that all vibration isolators 4 are basically evenly stressed.
[0039] S7: Remove four special lifting devices from the lifting holes reserved in the precast panel body;
[0040] S8: Check and confirm whether the elevation of the prefabricated floating slab 2 meets the requirements;
[0041] S9: Use locking bolts to fix the height adjustment pad, locking gasket and isolator inner tube 7 together to ensure that the prefabricated floating plate 2 is stable and reliable, and then the subsequent adjustment and installation of shear hinges, fasteners and rails can be carried out.
[0042] Compared with the prior art, the present invention leaves a special lifting hole on the prefabricated floating plate 2. The floating plate can be directly lifted into place at one time by applying a special lifting tool to the lifting hole. The elevation accuracy of the four corners of the floating plate can be controlled within 0.5 mm, which greatly improves the construction accuracy compared to the original scheme with a construction accuracy of 2 mm.
[0043] Compared with the prior art, which relies on the inner tube 7 of the vibration isolator to lift the height of the plate body, and at the same time adjust the load, the construction quality is difficult to guarantee. After experiments, it is found that the unstressed empty rate of the inner tube of the vibration isolator 4 is as high as 15%. The vibration isolator 4 with extremely uneven load of more than 50% has a load force deviation of more than 25% from the design value, which seriously affects the vibration reduction performance of the floating plate and brings safety hazards to the train operation. The fast and refined construction method of the prefabricated floating plate proposed in the present invention measures and fine-tunes the force of the inner tube 7 of the vibration isolator one by one after the lifting is completed, ensuring the balance of the load force. All vibration isolators 4 can ensure that the deviation of the load force from the design value is not more than 25%, ensuring the vibration reduction performance of the floating plate;
[0044] The prior art requires 2-3 times of jacking (adjusting the load force during jacking) during construction, and repeated checks are required to install the floating plate in place, with a construction progress of about 80-90m / day. The present invention adopts one-time direct jacking into place and then adjusting the load force, and the construction progress can reach 100-120m / day.
[0045] The above description is only a preferred specific implementation manner of the present invention, but the protection scope of the present invention is not limited thereto. Any technician familiar with the technical field can make equivalent replacements or changes according to the technical scheme and inventive concept of the present invention within the technical scope disclosed by the present invention, which should be covered by the protection scope of the present invention.
Claims
1. A method for rapid and refined construction of a prefabricated floating slab, characterized in that: The following steps are involved: S1: According to the design requirements, pouring work of the floating slab base (5) in the viaduct / tunnel (1); S2: After detecting that the strength of the base (5) meets the requirements, the prefabricated floating slab (2) is taken out and hoisted to be placed on the base (5); S3: measuring the actual elevations of the four corners of the prefabricated floating slab (2), and calculating the difference between the actual elevations and the designed elevations of the prefabricated floating slab (2); S4: four special lifting devices are placed in the lifting holes reserved in the prefabricated plate body, and the lifting devices lift the prefabricated floating plate (2) plate body. The lifting devices are controlled according to the difference measured in step S3 to lift the plate body to the designed elevation at one time. After the plate body reaches the designed elevation, the lifting devices are locked; S5: Use a water drill and a matching drilling tool to drill holes and install positioning pins, and place the vibration isolator inner tube (7) and an appropriate amount of height adjustment gaskets into the vibration isolator outer tube (8) corresponding to the entire floating plate; S6: Use a dedicated vibration isolator load force measuring device (9) to accurately adjust the load force of all vibration isolator inner tubes (7) one by one by adding or removing height adjustment pads; S7: Remove four special lifting devices from the lifting holes reserved in the precast panel body; S8: Check and confirm whether the elevation of the prefabricated floating slab (2) meets the requirements; S9: Use locking bolts to fix the height adjustment pad, locking washer and the vibration isolator inner tube (7) together.
2. A method for rapid and refined construction of a prefabricated floating slab according to claim 1, characterized in that: S1: According to the design requirements, in the step of casting the floating slab base (5) in the viaduct / tunnel (1), when casting the base (5), the elevation, curve superelevation and ditch setting requirements in the design requirements need to be met.
3. A method for rapid and refined construction of a prefabricated floating slab according to claim 1, characterized in that: S2: After detecting that the strength of the base (5) meets the requirements, the prefabricated floating slab (2) is taken out and hoisted to be placed on the base (5). The longitudinal and transverse positions of the slab need to be accurately adjusted according to the final design requirements.
4. A method for rapid and refined construction of a prefabricated floating slab according to claim 1, characterized in that: The step S4: placing four special lifting devices into the lifting holes reserved in the prefabricated plate body, the lifting devices lift the prefabricated floating plate (2) plate body, and controlling the lifting devices to lift the plate body to the designed elevation once according to the difference measured in step S3. After the plate body reaches the designed elevation, the step of locking the lifting devices. The four special lifting devices can be hydraulically driven or electrically driven.
5. The method for rapid and refined construction of a prefabricated floating slab according to claim 1 is characterized in that: In the step S5: using a water drill and a matching drilling tool to drill holes and install positioning pins, placing the vibration isolator inner tube (7) and an appropriate amount of height adjustment gaskets into the vibration isolator outer tube (8) corresponding to the entire floating plate, when installing the positioning pins, the installation must be carried out in accordance with the requirements, and the installation requirements are that the positioning pins are installed with high precision and fixed firmly.
6. A method for rapid and refined construction of a prefabricated floating slab according to claim 1, characterized in that: In the step of using a dedicated vibration isolator load force measuring device (9) to precisely adjust the load forces of all vibration isolator inner tubes (7) one by one by adding or removing height adjustment pads, when precisely adjusting the load forces of the vibration isolator inner tubes (7), it is necessary to ensure that the forces on all vibration isolators (4) are basically uniform.
7. A method for rapid and refined construction of a prefabricated floating slab according to claim 1, characterized in that: After the above S9: the step of fixing the height adjustment pad, the locking gasket and the vibration isolator inner tube (7) into one body using locking bolts is completed, the subsequent adjustment and installation of the shear hinge, fasteners and rails can be carried out.
Citation Information
Cited By
Curve section prefabricated floating slab positioning and laying method
CN122304235A
Curved section prefabricated floating slab positioning and laying method
CN122304235B