Hanging basket for bridge cantilever construction

By using the pulling mechanism of the hanging basket in the cantilever construction of the bridge, the operating equipment and materials are pulled into the hollow cavity of the poured bridge section, which solves the problem of repeated hoisting, shortens the construction period and reduces costs, and improves Improve construction efficiency and safety.

CN118792973APending Publication Date: 2024-10-18SICHUAN COMM CONSTR MEIZHOU CONSTR CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202410929051.6
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-11
Publication Date
2024-10-18

AI Technical Summary

Technical Problem

In bridge cantilever construction, repeated hoisting of equipment and materials wastes manpower and material resources, prolongs the construction period, and makes the hoisting operation complicated and inconvenient.

Method used

Design a hanging basket for bridge cantilever construction, which is equipped with a pulling mechanism to pull operating equipment and unused materials into the hollow cavity of the poured bridge section before concrete pouring, and directly into the hollow cavity during the construction of the next section. Take it out and avoid repeated lifting.

Benefits of technology

Reduce construction costs, shorten construction cycles, reduce manual labor intensity, and improve construction efficiency and safety.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118792973A_ABST
    Figure CN118792973A_ABST
Patent Text Reader

Abstract

The invention provides a hanging basket for bridge cantilever construction, and belongs to the technical field of bridge construction auxiliary equipment, the hanging basket comprises a truss walking rail, a main truss, a bottom basket, a front suspender and a rear suspender, the truss walking rail is anchored on a poured bridge section, the main truss is arranged on the truss walking rail, the bottom basket is arranged below the main truss and located outside the poured bridge section, and the front suspender and the rear suspender are arranged on the bottom basket. The front suspender is arranged between the bottom basket and the main truss, the top ends of the rear suspenders are anchored on a poured bridge section, the bottom ends of the rear suspenders are fixedly connected to the bottom basket, a placement box is arranged in the bottom basket, and a traction mechanism used for pulling the placement box into a hollow cavity of the poured bridge section is arranged at the bottom of the truss walking rail. Operation equipment and unused materials can be pulled into the poured bridge section before concrete pouring, when the next bridge section is constructed, only the poured bridge section needs to be moved out to the hanging basket which advances by a certain distance, repeated hoisting operation is not needed, and the construction period is shortened while the construction cost is reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of bridge construction auxiliary equipment, and in particular to a hanging basket for bridge cantilever construction. Background Art

[0002] Hanging basket construction refers to the use of a hanging basket method when casting a cantilever beam bridge with a larger span. The cantilever operation is carried out in sections on site. It does not require the erection of a support and does not use a large crane. It has the advantages of light structure, simple and convenient assembly, and no pressure. There is also sufficient space under the hanging basket, which can provide a larger construction working surface, which is conducive to the steel bar formwork construction operation.

[0003] During the construction of the hanging basket, a variety of operating equipment and materials are needed, such as embedded steel bars, shearing equipment for embedded steel bars, welding equipment, anchors, tensioning and traction equipment for anchors, pouring equipment, etc. Before construction, the operating equipment and materials need to be hoisted onto the hanging basket, and then the previous operation process is completed on the hanging basket. Before pouring concrete, the above-mentioned operating equipment and unused materials need to be hoisted to the top of the bridge, and when the next section of the bridge is constructed, the operating equipment and materials are hoisted back onto the hanging basket. Repeated hoisting operations waste manpower and material resources on the one hand, and extend the overall construction period on the other. Summary of the invention

[0004] The object of the present invention is to provide a hanging basket for bridge cantilever construction, which can pull operating equipment and unused materials into the poured bridge section before concrete pouring. When constructing the next bridge section, it is only necessary to move the operating equipment and unused materials from the poured bridge section to the hanging basket after moving forward a certain distance. There is no need to repeatedly hoist the operating equipment and unused materials, thereby reducing construction costs and shortening construction period.

[0005] The embodiment of the present invention is achieved through the following technical solutions: a hanging basket for bridge cantilever construction, comprising a hanging basket body, the hanging basket body comprising a truss walking rail, a main truss, a bottom basket, a plurality of front suspension rods and a plurality of rear suspension rods, the truss walking rail is anchored on a cast bridge section, the main truss is arranged on the truss walking rail, the bottom basket is arranged below the main truss and outside the cast bridge section, a plurality of the front suspension rods are arranged between the bottom basket and the main truss, the top ends of the plurality of the rear suspension rods are all anchored on the cast bridge section, and the bottom ends are all fixedly connected to the bottom basket, a placement box is arranged in the bottom basket, a pulling mechanism is arranged at the bottom of the main truss, and the pulling mechanism is used to move the placement box from the bottom basket to the hollow cavity of the cast bridge section; the pulling mechanism comprises a support frame, a first pulling assembly and a second pulling assembly, the support frame is arranged at the bottom of the main truss and extends into the hollow cavity, the first pulling assembly and the second pulling assembly are both arranged on the support frame and are respectively connected to the head and tail ends of the placement box.

[0006] Furthermore, the first pulling assembly includes a first pulling seat, both sides of the first pulling seat are fixedly connected with a first pulling rope, a first hook is provided at the end of the first pulling rope away from the first pulling seat, and a first connecting piece for the first pulling rope to be laid on the end of the support frame facing outside the hollow cavity is provided, and a first driving electric cylinder is provided on the support frame, and when the first driving electric cylinder drives the first pulling seat to move into the hollow cavity, the first pulling rope applies a pulling force to the placement box; the second pulling assembly includes a second pulling seat, both sides of the second pulling seat are fixedly connected with a second pulling rope, the two second pulling ropes are located between the two first pulling ropes, and the two second pulling ropes The spacing between them is smaller than the spacing between the two first pulling ropes, a second hook is provided at the end of the second pulling rope away from the second pulling seat, a second connecting piece for the second pulling rope is provided on the first pulling seat, a second driving electric cylinder for driving the second pulling seat to move along the length direction of the support frame is provided on the support frame, when the first pulling seat moves into the hollow cavity and the second driving electric cylinder drives the second pulling seat to move out of the hollow cavity, the second pulling rope applies a pulling force to the placement box; a first hanging plate for hanging the first hook is provided on the side of the placement box facing the hollow cavity, and a second hanging plate for hanging the second hook is provided on the side of the placement box facing the outside of the hollow cavity.

[0007] Furthermore, both inner side surfaces of the support frame are provided with a first slide groove and a second slide groove along the length direction of the support frame, the two ends of the first pulling seat are respectively slidably set in the two first slide grooves, and the two ends of the second pulling seat are respectively slidably connected in the two second slide grooves, the first slide groove is located below the second slide groove, and the length of the first slide groove extending in the support frame is greater than the length of the second slide groove extending in the support frame.

[0008] Furthermore, the first connecting member includes a support shaft, which is fixedly arranged on a support frame and located on an opening section of the hollow cavity, and first pulleys are arranged at both ends of the support shaft, and the first pulling rope is correspondingly arranged on the first pulleys; the second connecting member includes two connecting seats, and each of the second connecting seats is provided with two second pulleys, and the circumferential surfaces of the two second pulleys are tangent, and the second pulling rope is sequentially arranged on the two second pulleys and in opposite directions.

[0009] Furthermore, a first touch switch for starting the second driving electric cylinder is provided at one end of the first slide groove facing the hollow cavity, and when the first pulling seat moves to contact with the first touch switch, the piston rod of the second driving electric cylinder moves out of the cylinder barrel and drives the second pulling seat to move out of the hollow cavity; a second touch switch for starting the first driving electric cylinder is provided in the middle section of the second slide groove, and when the second pulling seat contacts with the second touch switch, the piston rod of the first driving electric cylinder moves out of the cylinder barrel and drives the first pulling seat to move out of the hollow cavity.

[0010] Furthermore, the placement box includes a box body, a base is provided at the bottom of the box body, rollers are provided at the bottom of the base, and the first hanging plate and the second hanging plate are respectively provided at two ends of the top of the box body.

[0011] Furthermore, a propulsion mechanism is provided on the side of the bottom basket away from the hollow cavity, the propulsion mechanism includes a propulsion frame, a load-bearing platform is fixedly provided on the outer side of the bottom basket, the propulsion frame is arranged on the load-bearing platform, a propulsion plate is provided on the side of the propulsion frame away from the bottom basket, a hanging belt is provided on the side of the propulsion plate facing the inside of the bottom basket, and a reset member is provided on the side of the propulsion plate facing the outside of the bottom basket.

[0012] Furthermore, the reset member includes a reset rod, which is slidably arranged on the propulsion frame, one end of the reset rod is fixedly connected to the propulsion plate, and the other end is provided with a reset plate, and a compression spring is connected between the reset plate and the propulsion frame.

[0013] Furthermore, a plug-in rod is provided at the bottom of the propulsion frame, a plug-in sleeve for plugging the plug-in rod is provided on the bearing platform, and a tightening bolt for tightening the plug-in rod is provided on the plug-in sleeve.

[0014] The technical solution of the embodiment of the present invention has at least the following advantages and beneficial effects:

[0015] 1. The present invention places operating equipment and materials by providing a placement box, and pulls the placement box into the hollow cavity of the cast bridge section through a pulling mechanism, so that the operating equipment and unused materials can be stored before concrete pouring, without the need to hoist them to the top surface of the cast bridge section; when the concrete pouring of one section of the bridge is completed and the next section of the bridge needs to be constructed, the hanging basket is first moved as a whole to the next construction node, and then the placement box only needs to be moved out of the hollow cavity to the bottom basket of the hanging basket, so that the operating equipment and unused materials can be taken out for use, without the need for repeated hoisting, thereby reducing construction costs and shortening the construction period.

[0016] 2. The present invention arranges a first pulling assembly and a second pulling assembly to pull at the front and rear ends of the placement box respectively, so that the rollers at the front end and the rear end of the placement box can successively pass through the steps formed by the height difference between the bottom basket and the hollow cavity, thereby facilitating the process of the placement box entering the hollow cavity, reducing manual labor intensity, and avoiding the safety hazards caused by manually pushing the placement box. BRIEF DESCRIPTION OF THE DRAWINGS

[0017] In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the drawings required for use in the embodiments are briefly introduced below. It should be understood that the following drawings only show certain embodiments of the present invention and therefore should not be regarded as limiting the scope. For ordinary technicians in this field, other related drawings can be obtained based on these drawings without creative work.

[0018] Figure 1 A schematic diagram of the overall structure of a hanging basket for bridge cantilever construction provided by the present invention;

[0019] Figure 2 It is a schematic diagram of the initial state of the pulling mechanism and the placement box of the present invention;

[0020] Figure 3 It is a schematic diagram of the initial state of the first pulling assembly and the second pulling assembly of the present invention;

[0021] Figure 4 It is a schematic structural diagram of the first pulling assembly of the present invention;

[0022] Figure 5 is a schematic structural diagram of the second pulling assembly of the present invention;

[0023] Figure 6 It is a schematic diagram of the state when the pulling mechanism of the present invention pulls the placement box upward;

[0024] Figure 7 It is a structural schematic diagram of the first pulling assembly and the second pulling assembly when the pulling mechanism of the present invention pulls the placement box upward;

[0025] Figure 8 It is a structural schematic diagram of the propulsion mechanism of the present invention;

[0026] Icons: 1-basket body, 11-truss walking rail, 12-main truss, 13-bottom basket, 14-front suspension rod, 15-rear suspension rod, 2-cast bridge section, 21-hollow cavity, 3-placing box, 31-box, 311-first hanging plate, 312-second hanging plate, 32-base, 321-roller, 4-pulling mechanism, 41-support frame, 411-first slide, 412-second slide, 413-first touch switch, 414-second touch switch, 42-first pulling assembly, 421-first pulling seat, 422-first pulling rope, 423-first hook, 424-first Lapping piece, 4241-support shaft, 4242-first pulley, 425-first driving electric cylinder, 43-second pulling assembly, 431-second pulling seat, 432-second pulling rope, 433-second hook, 434-second lap joint, 4341-lap seat, 4342-second pulley, 435-second driving electric cylinder, 5-propulsion mechanism, 51-propulsion frame, 511-plug-in rod, 52-bearing platform, 521-plug-in sleeve, 5211-tightening bolt, 53-propulsion plate, 54-hanging belt, 55-reset piece, 551-reset rod, 552-reset plate, 553-compression spring. DETAILED DESCRIPTION

[0027] In order to make the purpose, technical solutions and advantages of the embodiments of the present invention clearer, the technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are part of the embodiments of the present invention, not all of the embodiments. Generally, the components of the embodiments of the present invention described and shown in the drawings here can be arranged and designed in various different configurations.

[0028] Therefore, the following detailed description of the embodiments of the present invention provided in the accompanying drawings is not intended to limit the scope of the invention claimed for protection, but merely represents selected embodiments of the present invention. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0029] Example 1

[0030] The following is further described in conjunction with specific embodiments. Figure 1As shown, the present invention is a hanging basket for bridge cantilever construction, including a hanging basket body 1, the hanging basket body 1 includes a truss running rail 11, a main truss 12, a bottom basket 13, a plurality of front suspension rods 14 and a plurality of rear suspension rods 15, the truss running rail 11 is anchored on the cast bridge section 2, the main truss 12 is arranged on the truss running rail 11, the bottom basket 13 is arranged below the main truss 12 and outside the cast bridge section 2, a plurality of front suspension rods 14 are arranged between the bottom basket 13 and the main truss 12, and the top ends of the plurality of rear suspension rods 15 are all anchored on the cast bridge section 2, and the bottom ends are all fixedly connected to the bottom basket 13.

[0031] Reference Figure 1 , Figure 2 As shown, a placement box 3 is arranged in the bottom basket 13 to facilitate the placement and storage of operating equipment and unused materials. The placement box 3 includes a box body 31, a base 32 is arranged at the bottom of the box body 31, and a roller 321 is arranged at the bottom of the base 32. A pulling mechanism 4 is arranged at the bottom of the main truss 12, and the pulling mechanism 4 is used to move the placement box 3 from the bottom basket 13 to the hollow cavity 21 of the cast bridge section 2. Since the installation height of the bottom basket 13 needs to be lower than the height of the lower surface of the cast bridge section 2 to leave installation space for the casting template, there is a large height difference when the placement box 3 enters the hollow cavity 21 of the cast bridge section 2 from the bottom basket 13. It is difficult for the staff to push the placement box 3 to the hollow cavity 21, and under the obstruction of the hanging basket body 1, it is not convenient for the hoisting equipment to enter the bottom basket 13 for operation. The pulling mechanism 4 can conveniently pull the placement box 3, thereby facilitating the process of the placement box 3 entering the hollow cavity 21.

[0032] Reference Figure 2 As shown, the pulling mechanism 4 includes a support frame 41, a first pulling component 42 and a second pulling component 43. The support frame 41 is welded to the bottom of the main truss 12 through a steel member and extends into the hollow cavity 21. The first pulling component 42 and the second pulling component 43 are both arranged on the support frame 41 and are respectively connected to the front and rear ends of the placement box 3, so as to pull the front end and the rear end of the placement box 3 respectively, so that the roller 321 at the front end and the roller 321 at the rear end of the placement box 3 can successively pass through the steps formed by the height difference between the bottom basket 13 and the hollow cavity 21.

[0033] Reference Figure 3 , Figure 4As shown, the first pulling component 42 includes a first pulling seat 421, and the first pulling rope 422 is fixedly connected to both sides of the first pulling seat 421, and a first hook 423 is provided at the end of the first pulling rope 422 away from the first pulling seat 421, and a first hanging plate 311 for hanging the first hook 423 is provided on the side of the box body 31 facing the hollow cavity 21, and a first connecting piece 424 for bridging the first pulling rope 422 is provided at the end of the support frame 41 facing the outside of the hollow cavity 21, and a first driving electric cylinder 425 is provided on the support frame 41. In the initial state, the piston rod of the first driving electric cylinder 425 is located outside the cylinder. When the head end of the placement box 3 needs to be pulled, the first hook 423 is hung on the first hanging plate 311 at the corresponding position, and then the first driving electric cylinder 425 is started and the piston rod of the driving electric cylinder is moved into the cylinder, so that the first pulling seat 421 moves into the hollow cavity 21 and drives the first pulling rope 422 to apply pulling force to the placement box 3, driving the placement box 3 to move in the direction close to the hollow cavity 21. When the placement box 3 moves to directly below the first connecting piece 424, the pulling force applied by the first pulling rope 422 to the placement box 3 is in a vertically upward direction, so that the head end of the placement box 3 can be tilted upward, so that the roller 321 at the head end of the placement box 3 can reach the height of the bottom wall of the hollow cavity 21 from the height of the bottom basket 13.

[0034] Reference Figure 3 , Figure 5 As shown, the second pulling assembly 43 includes a second pulling seat 431, and second pulling ropes 432 are fixedly connected to both sides of the second pulling seat 431. The two second pulling ropes 432 are located between the two first pulling ropes 422, and the spacing between the two second pulling ropes 432 is smaller than the spacing between the two first pulling ropes 422 to avoid entanglement between the second pulling ropes 432 and the first pulling ropes 422. A second hook 433 is provided at one end of the second pulling rope 432 away from the second pulling seat 431, and a second hanging plate 312 for hanging the second hook 433 is provided on the side of the box body 31 facing the outside of the hollow cavity 21, and the first hanging plate 311 and the second hanging plate 312 are respectively arranged at the two ends of the top of the box body 31. The first pulling seat 421 is provided with a second connecting piece 434 for the second pulling rope 432 to be mounted, and the support frame 41 is provided with a second driving electric cylinder 435 for driving the second pulling seat 431 to move along the length direction of the support frame 41. When the first pulling seat 421 moves into the hollow cavity 21 and the second driving electric cylinder 435 drives the second pulling seat 431 to move out of the hollow cavity 21, the second pulling rope 432 applies a pulling force to the placement box 3 so as to apply an inclined upward pulling force to the tail end of the placement box 3, so that the roller 321 at the tail end of the bottom basket 13 reaches the height of the bottom wall of the hollow cavity 2 from the height of the bottom basket 13.

[0035] Reference Figure 3As shown, the two inner side surfaces of the support frame 41 are provided with a first slide groove 411 and a second slide groove 412 along the length direction thereof, the two ends of the first pulling seat 421 are respectively slidably connected in the two first slide grooves 411, and the two ends of the second pulling seat 431 are respectively slidably connected in the two second slide grooves 412, the first slide groove 411 is located below the second slide groove 412, and the length of the first slide groove 411 extending in the support frame 41 is greater than the length of the second slide groove 412 extending in the support frame 41. When the first pulling rope 422 pulls the placement box 3, the overall position of the second hanging plate 312 will move forward as the placement box 3 moves. By setting the second connecting piece 434 on the first pulling seat 421, the state of the second pulling rope 432 can be changed accordingly when the placement box 3 moves as a whole, thereby avoiding a large bending of the second pulling rope 432 due to excessive surplus. When the first pulling seat 421 moves into the support frame 41 to the end of the first slide groove 411, the first pulling seat 421 can continue to move a distance after passing the second pulling seat 431, thereby further changing the state of the second pulling rope 432 from a relaxed state to a tensioned state, so that when the second driving electric cylinder 435 drives the second pulling seat 431 to move, it can immediately apply tension to the second pulling rope 432, so that the second pulling rope 432 pulls the tail end of the placement box 3.

[0036] Reference Figure 4 As shown, the first connecting member 424 includes a support shaft 4241, which is fixedly mounted on the support frame 41 and located on the opening section of the hollow cavity 21. Both ends of the support shaft 4241 are coaxially connected to the first pulley 4242, and the first pulling rope 422 is correspondingly mounted on the first pulley 4242.

[0037] Reference Figure 5 As shown, the second connecting member 434 includes two connecting seats 4341, and each second connecting seat 4341 is provided with two second pulleys 4342. The circumferential surfaces of the two second pulleys 4342 are tangent to each other. The second pulling rope 432 is sequentially mounted on the two second pulleys 4342 and the mounting directions are opposite to each other to adapt to the change in the relative position between the first pulling seat 421 and the second pulling seat 431, so that the second pulling rope 432 is always supported by at least one second pulley 4342 to prevent the second pulling rope 432 from loosening from the second pulley 4342.

[0038] Reference Figure 3 , Figure 6 and Figure 7As shown, a first touch switch 413 for starting the second driving electric cylinder 435 is provided at one end of the first chute 411 facing the hollow cavity 21. When the first pulling seat 421 moves to contact with the first touch switch 413, the piston rod of the second driving electric cylinder 435 moves out of the cylinder barrel and drives the second pulling seat 431 to move out of the hollow cavity 21. By providing the first touch switch 413, when the first pulling seat 421 moves to the end of the first chute 411 in the support frame 41, the second driving electric cylinder 435 is immediately started and pulls the roller 321 at the end of the placement box 3 through the second pulling rope 432. A second touch switch 414 for starting the first driving electric cylinder 425 is provided in the middle section of the second chute 412. When the second pulling seat 431 contacts with the second touch switch 414, the piston rod of the first driving electric cylinder 425 moves out of the cylinder barrel and drives the first pulling seat 421 to move out of the hollow cavity 21. By setting the second touch switch 414, after the second pulling rope 432 pulls the roller 321 at the end of the placement box 3 for a certain distance, the first pulling seat 421 will be lowered for a certain distance, so that the placement box 3 can continue to move forward for a certain distance under the action of the second pulling rope 432, thereby ensuring that the placement box 3 can be driven to move as a whole into the inside of the hollow cavity 21.

[0039] Reference Figure 1 , Figure 8 As shown, a propulsion mechanism 5 is provided on the side of the bottom basket 13 away from the hollow cavity 21, and the propulsion mechanism 5 includes a propulsion frame 51, a bearing platform 52 is fixedly installed on the outer side of the bottom basket 13, and the propulsion frame 51 is installed on the bearing platform 52. A propulsion plate 53 is provided on the side of the propulsion frame 51 away from the bottom basket 13, and a hanging belt 54 is provided on the side of the propulsion plate 53 facing the inside of the bottom basket 13, and a reset member 55 is provided on the side of the propulsion plate 53 facing the outside of the bottom basket 13. During the hoisting operation, the first hook 423 or the second hook 433 is hung on the hanging belt 54. When the operating equipment and materials are hoisted to a height exceeding the bottom basket 13, the hoisted equipment and materials can be pushed from the outside of the bottom basket 13 to the space inside the bottom basket 13 by applying tension to the hanging belt 54, so that the lifting does not require manual assistance from the staff, which reduces manual labor and improves safety.

[0040] Reference Figure 8As shown, the reset member 55 includes a reset rod 551, which is slidably arranged on the propulsion frame 51, one end of the reset rod 551 is fixedly connected to the propulsion plate 53, and the other end is provided with a reset plate 552, and a compression spring 553 is connected between the reset plate 552 and the propulsion frame 51. In the initial state, the propulsion plate 53 is located on the side of the propulsion frame 51 away from the bottom basket 13, and will not hinder the lifting of the operating equipment and materials. After the operating equipment and materials are lifted to a specified height, a pulling force is applied to the propulsion plate 53 through the hanging belt 54, that is, the propulsion plate 53 can push the operating equipment and materials into the bottom basket 13, and the hanging belt 54 releases the opening of the propulsion plate 53. Under the elastic force of the compression spring 553, the reset plate 552 drives the reset rod 551 to move back to the initial position, thereby driving the propulsion plate 53 to move back to the initial position to the side of the propulsion frame 51 away from the bottom basket 13, so as to facilitate the next propulsion process.

[0041] Reference Figure 8 As shown, a plug-in rod 511 is welded to the bottom of the propulsion frame 51, a plug-in sleeve 521 for inserting the plug-in rod 511 is welded to the bearing platform 52, and a tightening bolt 5211 for tightening the plug-in rod 511 is threadedly connected to the plug-in sleeve 521. The insertion depth of the plug-in rod 511 in the plug-in sleeve 521 is adjusted, and then the position of the plug-in rod 511 after adjustment is fixed by the tightening bolt 5211, that is, the overall height of the propulsion frame 51 can be adjusted to adapt to equipment and materials of different sizes.

[0042] The above are only preferred embodiments of the present invention and are not intended to limit the present invention. For those skilled in the art, the present invention may have various modifications and variations. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention shall be included in the protection scope of the present invention.

Claims

1. A hanging basket for bridge cantilever construction, comprising a hanging basket body (1), wherein the hanging basket body (1) comprises a truss running rail (11), a main truss (12), a bottom basket (13), a plurality of front suspension rods (14) and a plurality of rear suspension rods (15), wherein the truss running rail (11) is anchored on a cast bridge section (2), the main truss (12) is arranged on the truss running rail (11), the bottom basket (13) is arranged below the main truss (12) and outside the cast bridge section (2), the plurality of front suspension rods (14) are arranged between the bottom basket (13) and the main truss (12), and the top ends of the plurality of rear suspension rods (15) are all anchored on the cast bridge section (2) and the bottom ends are all fixedly connected to the bottom basket (13), characterized in that: A placement box (3) is arranged in the bottom basket (13), and a pulling mechanism (4) is arranged at the bottom of the main truss (12), and the pulling mechanism (4) is used to move the placement box (3) from the bottom basket (13) into the hollow cavity (21) of the cast bridge section (2); The pulling mechanism (4) comprises a support frame (41), a first pulling assembly (42) and a second pulling assembly (43); the support frame (41) is arranged at the bottom of the main truss (12) and extends into the hollow cavity (21); the first pulling assembly (42) and the second pulling assembly (43) are both arranged on the support frame (41) and are respectively connected to the front and rear ends of the placement box (3).

2. The hanging basket for bridge cantilever construction according to claim 1, characterized in that: The first pulling assembly (42) includes a first pulling seat (421), both sides of the first pulling seat (421) are fixedly connected with a first pulling rope (422), an end of the first pulling rope (422) away from the first pulling seat (421) is provided with a first hook (423), an end of the support frame (41) facing outside the hollow cavity (21) is provided with a first connecting piece (424) for the first pulling rope (422) to be mounted, and a first driving electric cylinder (425) is provided on the support frame (41), and when the first driving electric cylinder (425) drives the first pulling seat (421) to move into the hollow cavity (21), the first pulling rope (422) applies a pulling force to the placement box (3); The second pulling assembly (43) includes a second pulling seat (431), and the second pulling ropes (432) are fixedly connected to both sides of the second pulling seat (431), and the two second pulling ropes (432) are located between the two first pulling ropes (422), and the distance between the two second pulling ropes (432) is smaller than the distance between the two first pulling ropes (422), and the second pulling rope (432) is provided with a second hook (433) at one end away from the second pulling seat (431), and the first pulling seat A second connecting piece (434) for the second pulling rope (432) is provided on the support frame (41), and a second driving electric cylinder (435) for driving the second pulling seat (431) to move along the length direction of the support frame (41) is provided on the support frame (41). When the first pulling seat (421) moves into the hollow cavity (21) and the second driving electric cylinder (435) drives the second pulling seat (431) to move out of the hollow cavity (21), the second pulling rope (432) applies a pulling force to the placement box (3); The side of the placement box (3) facing the inside of the hollow cavity (21) is provided with a first hanging plate (311) for hanging the first hook (423), and the side of the placement box (3) facing the outside of the hollow cavity (21) is provided with a second hanging plate (312) for hanging the second hook (433).

3. The hanging basket for bridge cantilever construction according to claim 2, characterized in that: Both inner side surfaces of the support frame (41) are provided with a first slide groove (411) and a second slide groove (412) along the length direction thereof, the two ends of the first pulling seat (421) are respectively slidably arranged in the two first slide grooves (411), and the two ends of the second pulling seat (431) are respectively slidably connected in the two second slide grooves (412), the first slide groove (411) is located below the second slide groove (412), and the length of the first slide groove (411) extending in the support frame (41) is greater than the length of the second slide groove (412) extending in the support frame (41).

4. The hanging basket for bridge cantilever construction according to claim 3 is characterized in that: The first connecting member (424) includes a support shaft (4241), the support shaft (4241) is fixedly arranged on the support frame (41) and located on the opening section of the hollow cavity (21), and first pulleys (4242) are provided at both ends of the support shaft (4241), and the first pulling rope (422) is correspondingly arranged on the first pulleys (4242); The second connecting member (434) includes two connecting seats (4341), each of which is provided with two second pulleys (4342), the circumferential surfaces of the two second pulleys (4342) are tangent to each other, and the second pulling rope (432) is sequentially mounted on the two second pulleys (4342) in opposite directions.

5. The hanging basket for bridge cantilever construction according to claim 3 is characterized in that: A first touch switch (413) for starting the second driving electric cylinder (435) is provided at one end of the first sliding groove (411) facing the hollow cavity (21); when the first pulling seat (421) moves to contact with the first touch switch (413), the piston rod of the second driving electric cylinder (435) moves out of the cylinder barrel and drives the second pulling seat (431) to move out of the hollow cavity (21); a second touch switch (414) for starting the first driving electric cylinder (425) is provided in the middle section of the second sliding groove (412); when the second pulling seat (431) contacts with the second touch switch (414), the piston rod of the first driving electric cylinder (425) moves out of the cylinder barrel and drives the first pulling seat (421) to move out of the hollow cavity (21).

6. The hanging basket for bridge cantilever construction according to claim 1, characterized in that: The placement box (3) comprises a box body (31), a base (32) is provided at the bottom of the box body (31), a roller (321) is provided at the bottom of the base (32), and the first hanging plate (311) and the second hanging plate (312) are respectively provided at the two ends of the top of the box body (31).

7. The hanging basket for bridge cantilever construction according to claim 1, characterized in that: A propulsion mechanism (5) is provided on a side of the bottom basket (13) away from the hollow cavity (21), and the propulsion mechanism (5) includes a propulsion frame (51). A bearing platform (52) is fixedly provided on the outer side of the bottom basket (13), and the propulsion frame (51) is arranged on the bearing platform (52). A propulsion plate (53) is provided on a side of the propulsion frame (51) away from the bottom basket (13). A hanging belt (54) is provided on a side of the propulsion plate (53) facing the inside of the bottom basket (13), and a reset member (55) is provided on a side of the propulsion plate (53) facing the outside of the bottom basket (13).

8. The hanging basket for bridge cantilever construction according to claim 7, characterized in that: The reset member (55) includes a reset rod (551), which is slidably arranged on the propulsion frame (51), one end of the reset rod (551) is fixedly connected to the propulsion plate (53), and the other end is provided with a reset plate (552), and a compression spring (553) is connected between the reset plate (552) and the propulsion frame (51).

9. The hanging basket for bridge cantilever construction according to claim 7, characterized in that: The bottom of the propulsion frame (51) is provided with a plug rod (511), the bearing platform (52) is provided with a plug sleeve (521) for plugging the plug rod (511), and the plug sleeve (521) is provided with a tightening bolt (5211) for tightening the plug rod (511).