Construction method for dismantling continuous beam old bridge on navigation channel of inland river
By dividing the old continuous girder bridge into segments and using a demolition method that combines truck cranes and floating cranes, the problem of dismantling the old continuous girder bridge on the inland waterway has been solved, a fast and safe dismantling process has been achieved, and the navigation time has been reduced. and construction risks.
Patent Information
- Application Number
- CN202410990945.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-23
- Publication Date
- 2024-10-18
AI Technical Summary
The demolition construction of the old continuous-girder bridge on the inland navigation channel is difficult to complete without closing the channel for a long time, and the traditional method has problems of ship collision risk and high construction difficulty.
The old continuous girder bridge is divided into the bridge deck system, mid-span middle section, mid-span side section and side span section. The segments are dismantled using a combination of truck crane and floating crane. The gradual dismantling is achieved through temporary supports and segmental cutting. Reduce the duration of a single flight closure and improve safety.
It effectively reduces the single closure time, reduces the impact of navigation channel operation, avoids the risk of ship collision, and improves the efficiency and safety of dismantling. It is suitable for old continuous girder bridges that do not have the conditions for integral hoisting.
Smart Images

Figure CN118792979A_ABST
Abstract
Description
Technical Field
[0001] The present application belongs to the field of bridge demolition construction, and more specifically, to a method for demolishing an old continuous beam bridge on an inland navigable waterway. Background Art
[0002] Traditionally, old continuous beam bridges across inland waterways and canals are usually demolished on site and by salvaging concrete debris and steel bars from the water due to waterway upgrades or reaching their service life. Each closure lasts for a long time, and passing ships are prone to touching uncleaned concrete blocks, posing a high risk to safe operation of the waterway.
[0003] In order to effectively reduce the safety risks of inland navigable waterways, the canal waterway management department currently does not allow the waterway to be closed for a long time, so the on-site demolition plan cannot be adopted on site. At the same time, due to the restrictions on the waterway grade, the general old continuous beam bridge does not have the conditions for overall hoisting and demolition. Under the condition of taking necessary weight reduction and effective support measures, segmented cutting and hoisting are adopted to gradually realize the overall demolition of the old continuous beam bridge. However, this demolition construction method puts forward higher requirements in time and space, and is relatively difficult to achieve. Summary of the invention
[0004] In view of the defects of the prior art, the present application provides a construction method for dismantling an old continuous beam bridge on an inland navigable waterway, aiming to solve the problem that the inland navigable waterway cannot be closed for a long time for continuous beam dismantling construction operations.
[0005] This application provides a construction method for dismantling an old continuous beam bridge on an inland navigable waterway, specifically:
[0006] S1 The old continuous beam bridge to be demolished is divided into sections, namely the bridge deck system, the middle section of the middle span, the side section of the middle span and the side span section;
[0007] S2 uses a truck crane to dismantle the bridge deck system;
[0008] S3 uses floating crane to dismantle the middle section of the mid-span;
[0009] S4 temporarily supports the side span sections, and then uses floating cranes to remove the side sections of the middle span on both sides;
[0010] S5 finally directly crushed and demolished the side span section.
[0011] Compared with the prior art, the above technical scheme conceived by the present application proposes to divide the old continuous beam bridge into sections and dismantle it in different ways according to the division results, which can effectively reduce the time of a single navigation closure, thereby reducing the impact on the operation of the navigable waterway and avoiding the risk of collision with passing ships due to incomplete salvage.
[0012] As a further preferred embodiment, in step S1, the method for dividing the middle section of the mid-span and the side section of the mid-span is: to ensure that the mass ratio of the middle section of the mid-span to the side section of the mid-span is 9:10 to 13:10, and to ensure that the mass of the middle section of the mid-span or the side section of the mid-span on one side is 60% to 80% of the floating lifting weight.
[0013] As a further preferred embodiment, in step S1, the method for dividing the middle section of the middle span and the side section of the middle span is: ensuring that the length ratio of the middle section of the middle span to the side section of the middle span is 6:5 to 8:5, and ensuring that the mass of the middle section of the middle span or the single-side side section of the middle span is 60% to 80% of the floating lifting weight.
[0014] As a further preference, step S1 further includes: configuring lifting equipment according to the segment division result and determining temporary navigation closure measures.
[0015] As a further preferred embodiment, step S2 is specifically as follows:
[0016] S21 cuts the bridge guardrail and sidewalk slab into sections, then uses a truck crane to load them onto a transport vehicle and transport them to the crushing site;
[0017] S22 drills holes at the root of the flange plate and cuts the flange plate, then uses a truck crane to lift it onto a transport vehicle and transport it to the crushing site.
[0018] As a further preferred embodiment, step S3 is specifically as follows: using a floating crane to perform four-point bottom lifting of the middle section of the middle span, then cutting the left and right sides of the middle section of the middle span to separate it from the bridge body, and finally lifting the middle section of the middle span to the crushing site by turning the floating crane.
[0019] As a further preferred embodiment, step S4 is specifically as follows:
[0020] S41 uses temporary steel piers to support the side spans within a preset distance from the main pier, and uses earth filling under the bridge to support the remaining side spans;
[0021] S42 uses a floating crane to carry out four-point bottom lifting of the middle span side section on one side, then cuts the middle span side section and the side span section, and finally lifts the middle span side section on one side to the crushing site by turning the floating crane;
[0022] S43 repeats step S42 for the mid-span edge segment on the other side.
[0023] As further preferred, in step S41, the preset distance is 8m to 14m.
[0024] As a further preference, in steps S2, S3 and S4, cutting is performed by a rope saw.
[0025] As a further preferred embodiment, step S5 is specifically as follows: starting from the main pier position, the concrete is symmetrically broken in sections toward the side span direction until all the side sections of the middle span are broken, and the concrete slag is pulled to a designated location, and finally the site is restored.
[0026] In general, the above technical solutions conceived by this application have the following technical advantages compared with the prior art:
[0027] 1. This application proposes to divide the old continuous beam bridge into sections and dismantle it in different ways according to the division results, which can effectively reduce the time of a single closure of navigation, thereby reducing the impact on the operation of the navigable waterway and avoiding the risk of collision with passing ships due to incomplete salvage;
[0028] 2. In particular, the present application optimizes the division method of the middle span middle section and the middle span side section, which can take into account both demolition efficiency and demolition stability, and has good application prospects;
[0029] 3. In addition, this application also optimizes the specific demolition processes of the bridge deck system, the middle section of the middle span, the side section of the middle span and the side span section, respectively, and can perform differentiated demolition according to the mechanical characteristics of different positions, further improving the safety of demolition. BRIEF DESCRIPTION OF THE DRAWINGS
[0030] Figure 1 It is a plan view of hoisting the middle section of the middle span in the method for dismantling an old continuous beam bridge on an inland navigable waterway provided in an embodiment of the present application;
[0031] Figure 2 It is a plan view of hoisting the side section of the middle span in the method for dismantling an old continuous beam bridge on an inland navigable waterway provided in an embodiment of the present application;
[0032] Figure 3 It is a schematic diagram of cutting the flange plate in the construction method for dismantling an old continuous beam bridge on an inland navigable waterway provided in an embodiment of the present application. DETAILED DESCRIPTION
[0033] In order to make the purpose, technical solution and advantages of the present application more clearly understood, the present application is further described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are only used to explain the present application and are not used to limit the present application.
[0034] The present application provides a construction method for dismantling an old continuous beam bridge on an inland navigable waterway, specifically:
[0035] Before demolition of S1, the surrounding environment of the old continuous beam bridge was investigated, and the pipelines that affected the demolition were relocated. Then, according to the waterway grade and the floating crane lifting capacity, the old continuous beam bridge to be demolished was divided into sections, including the bridge deck system, the middle section of the middle span, the side section of the middle span and the side span section. At the same time, the lifting equipment was configured according to the results of the section division and the temporary navigation closure measures were determined;
[0036] S2 cuts the bridge deck guardrail, sidewalk slab and flange slab respectively. The land area component segments are hoisted to the transport vehicle by a truck crane and then transported to the crushing site by the transport vehicle to realize the demolition of the bridge deck system.
[0037] S3 hoists the middle section of the middle span, and after the cutting is completed, the middle section of the middle span is dismantled by floating hoisting;
[0038] S4 side span clearance limit under the bridge, using different methods to temporarily support the side span section, and then hoist the middle span side section, after the cutting is completed, the middle span side sections on both sides are dismantled by floating hoisting;
[0039] Finally, S5 was symmetrically demolished in sections starting from the main pier position towards the side span until all demolition was completed, and the concrete slag was pulled to the designated location, and finally the site was restored.
[0040] This application proposes to divide the old continuous beam bridge into sections and adopt different methods to dismantle it according to the division results, which can effectively reduce the time of a single navigation closure, thereby reducing the impact on the operation of the navigable waterway and avoiding the risk of collision with passing ships due to incomplete salvage. At the same time, this segmented lifting and dismantling method is suitable for inland navigable waterways that do not have large floating cranes for overall lifting operations.
[0041] Furthermore, in step S1, when dividing the sections, the section size can be reasonably divided according to the navigable waterway grade and the existing floating crane lifting capacity. If the section is too small, the number of closures and lifting will definitely increase, which will increase the input of various resources and greatly extend the construction period. If the section is too large, the waterway and floating crane will not meet the construction conditions. Preferably, the division method of the middle section of the middle span and the side section of the middle span is as follows: first, the length of the divided sections of the middle span should be controlled within the range of the floating crane's safe lifting capacity, and the quality of the middle section of the middle span or the side section of the middle span on one side should be controlled within 60% to 80% of the floating crane's lifting weight to leave enough safety factor; second, ensure that the side section of the middle span can maintain stability through its own prestressed system, that is, the mass ratio of the middle section of the middle span to the side section of the middle span is 9:10 to 13:10 or the length ratio is 6:5 to 8:5; third, the side span section is strongly supported by various forms such as steel piers and fill to ensure the overall stability of the side span and the side section of the middle span.
[0042] Further, if Figure 3 As shown, step S2 is specifically as follows:
[0043] S21 cuts the bridge guardrail and sidewalk slab into sections, then uses a truck crane to load them onto a transport vehicle and transport them to the crushing site;
[0044] S2 drills holes at the root of the flange plate and cuts the flange plate, then uses a truck crane to lift it onto a transport vehicle and transport it to the crushing site.
[0045] Further, if Figure 1 As shown, step S3 specifically includes: using a floating crane to perform four-point bottom lifting on the middle section of the middle span, then cutting the left and right sides of the middle section of the middle span to separate it from the bridge body, and finally lifting the middle section of the middle span to the crushing site by turning the floating crane.
[0046] Further, if Figure 2 As shown, step S4 is specifically as follows:
[0047] S41 uses temporary steel piers to support the side spans within a preset distance from the main pier, and uses earth filling under the bridge to support the remaining side spans;
[0048] S42 uses a floating crane to carry out four-point bottom lifting of the middle span side section on one side, then cuts the middle span side section and the side span section, and finally lifts the middle span side section on one side to the crushing site by turning the floating crane, loosens the wire rope and uses the crushing head to break it on the spot;
[0049] S43 repeats step S42 for the mid-span edge segment on the other side.
[0050] Furthermore, in step S41, the use of temporary steel piers for support has three main advantages: first, it can ensure that the force of the side span section is stable after the middle span side section is removed; second, it can prevent the concrete residue of the side span section near the main pier from falling into the river, which not only affects the navigation safety but also is difficult to salvage; third, it can give full play to the advantages of temporary steel support and soil, thereby providing a more economical and reasonable demolition plan. In order to achieve the above effects, the preset distance is 8m~14m. In actual application, a suitable distance can be selected from 8m~14m, and temporary steel piers can be used for support within this range.
[0051] Furthermore, in steps S2, S3 and S4, cutting is performed by a rope saw.
[0052] In a specific embodiment of the present application, the existing Wushen Canal is a Class V waterway with a navigation clearance of 38m wide × 5m high, which can meet the maximum lifting operations of a single 610t floating crane. Taking into account the lifting capacity of a single 610t floating crane and the prestressed arrangement of each section of the 56m main span continuous beam, the 56m main span continuous beam is divided into a 15m middle span side section + a 21m middle span middle section + a 15m middle span side section, of which the middle span middle section weighs about 423.1t and the middle span side section weighs about 386.5t. First, the middle span middle section is symmetrically cut under floating crane lifting conditions, which not only meets the safety lifting requirements of a single 610t floating crane, but also ensures the overall stability of the remaining middle span side sections and side spans under the existing prestressed system, greatly reduces safety risks, and ensures the safety of waterway passage.
[0053] It will be easily understood by those skilled in the art that the above description is only a preferred embodiment of the present application and is not intended to limit the present application. Any modifications, equivalent substitutions and improvements made within the spirit and principles of the present application shall be included in the scope of protection of the present application.
Claims
1. A construction method for dismantling an old continuous beam bridge on an inland navigable waterway. It is characterized in that The demolition construction method is specifically as follows: S1 The old continuous beam bridge to be demolished is divided into sections, namely the bridge deck system, the middle section of the middle span, the side section of the middle span and the side span section; S2 uses a truck crane to dismantle the bridge deck system; S3 uses floating crane to dismantle the middle section of the mid-span; S4 temporarily supports the side span sections, and then uses floating cranes to remove the side sections of the middle span on both sides; S5 finally directly crushed and demolished the side span section.
2. The demolition construction method according to claim 1, It is characterized in that In step S1, the method of dividing the middle section of the middle span and the side section of the middle span is to ensure that the mass ratio of the middle section of the middle span to the side section of the middle span is 9:10 to 13:10, and to ensure that the mass of the middle section of the middle span or the side section of the middle span on one side is 60% to 80% of the floating lifting weight.
3. The demolition construction method according to claim 1, It is characterized in that In step S1, the method of dividing the middle section of the middle span and the side section of the middle span is: to ensure that the length ratio of the middle section of the middle span to the side section of the middle span is 6:5 to 8:5, and to ensure that the mass of the middle section of the middle span or the side section of the middle span on one side is 60% to 80% of the floating lifting weight.
4. The demolition construction method according to claim 1, It is characterized in that Step S1 also includes: configuring lifting equipment according to the segment division result and determining temporary navigation closure measures.
5. The demolition construction method according to claim 1, It is characterized in that Step S2 is specifically as follows: S21 cuts the bridge guardrail and sidewalk slab into sections, then uses a truck crane to load them onto a transport vehicle and transport them to the crushing site; S22 drills holes at the root of the flange plate and cuts the flange plate, then uses a truck crane to lift it onto a transport vehicle and transport it to the crushing site.
6. The demolition construction method according to claim 1, It is characterized in that Step S3 specifically includes: using a floating crane to perform four-point bottom lifting on the middle section of the middle span, then cutting the left and right sides of the middle section of the middle span to separate it from the bridge body, and finally lifting the middle section of the middle span to the crushing site by turning the floating crane.
7. The demolition construction method according to claim 1, It is characterized in that Step S4 is specifically as follows: S41 uses temporary steel piers to support the side spans within a preset distance from the main pier, and uses earth filling under the bridge to support the remaining side spans; S42 uses a floating crane to carry out four-point bottom lifting of the middle span side section on one side, then cuts the middle span side section and the side span section, and finally lifts the middle span side section on one side to the crushing site by turning the floating crane; S43 repeats step S42 for the mid-span edge segment on the other side.
8. The demolition construction method according to claim 7, It is characterized in that In step S41, the preset distance is 8m to 14m.
9. The demolition construction method according to claim 1, It is characterized in that In steps S2, S3 and S4, cutting is performed by a wire saw.
10. The demolition construction method according to any one of claims 1 to 9, It is characterized in that Step S5 is specifically as follows: starting from the main pier position, the concrete is symmetrically broken in sections in the direction of the side span until all the side sections of the middle span are broken, and the concrete slag is pulled to the designated location, and finally the site is restored.