A method for receiving a shield machine arriving at a reinforced concrete box culvert in a water-rich environment
By using concrete box culvert structures in water-rich environments to remove shield machines in step by step and mortar refilling, forming a sealing environment, solving the challenge of shield machines receiving in confined spaces and achieving safety of shield machines Arrival and receive, and reduce construction risks and costs.
Patent Information
- Application Number
- CN202411278549.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-12
- Publication Date
- 2024-11-19
- Estimated Expiration
- 2044-09-12
AI Technical Summary
In a water-rich environment, it is difficult to reach and receive the shield machine in a confined space, and it is difficult to achieve existing reinforcement and steel sleeve installation, resulting in high reception risks.
The shield machine is received by a concrete box culvert structure. By cutting the hole door in steps and refilling the mortar is re-formed to form a sealing environment, adjust the attitude of the shield machine and gradually reduce the thrust to ensure the safe arrival and reception of the shield machine.
Effectively form a sealed environment in the confined space, reducing the risk of water and sand gushing received by the shield machine, improving construction safety and efficiency, and saving costs.
Smart Images

Figure CN118793448B_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the technical field of shield construction, and in particular to a method for receiving a shield machine in a water-rich environment when the shield machine arrives at a reinforced concrete box culvert. Background Art
[0002] In shield construction, it is generally necessary to complete the arrival and reception of the shield machine in a certain underground space. Since the water and soil environment of the shield machine changes during the arrival and reception stages, the risk of water and soil inrush at the receiving end is high in a water-rich environment.
[0003] Among the current arrival and reception technologies, the more common approach is to reinforce the receiving end so that the shield machine arrives in the reinforced body, forming a water-stopping and soil-stopping environment to complete the reception; in addition, a steel sleeve can be set at the receiving end, and the shield machine arrives in the closed steel sleeve to complete the reception, which is also one of the current common technologies. However, when the underground space is limited, the reinforcement of the receiving end and the installation of the steel sleeve are often difficult to carry out, which brings great challenges to the arrival and reception of the shield. Summary of the invention
[0004] The purpose of this application is to provide a method for receiving a shield machine arriving at a reinforced concrete box culvert in a water-rich environment, which can form an effective sealed environment in a confined space so that the shield machine can arrive and be received safely. It can not only effectively solve the problem of shield reception in a limited space in a water-rich environment, but also be economical and efficient, ensuring construction safety while effectively saving costs.
[0005] In order to achieve the above object, the present invention provides a method for receiving a shield machine arriving at a reinforced concrete box culvert in a water-rich environment, and receiving the shield machine in a confined space of an existing station, comprising the following steps:
[0006] Reinforce the stratum at the receiving end of the shield machine;
[0007] Concrete box culverts are constructed at existing stations to completely cover the tunnel portals and provide support for the concrete box culverts;
[0008] The tunnel door is chiseled out step by step in the reverse method, and mortar is poured back into the concrete box culvert as the tunnel door is chiseled out step by step until the tunnel door is completely chiseled out and the entire concrete box culvert is filled;
[0009] Adjust the posture of the shield machine before entering the reinforcement area, and gradually reduce the thrust and speed of the shield machine after entering the reinforcement area, so that the shield machine can completely enter the concrete box culvert;
[0010] Secondary grouting is performed on the shield tail multi-ring segments and water-stop rings are applied to confirm that there is no leakage risk and then dismantle the concrete box culvert;
[0011] The gap between the tunnel portal and the segment is sealed, and the shield machine stops after the tail of the shield detaches from the tunnel portal and separates from the last segment, completing the arrival and reception of the shield machine.
[0012] In a further embodiment, the existing station is reserved with a portal for receiving the shield machine, and a reinforcement area is constructed by drilling and grouting the stratum at the receiving end of the shield machine through the portal. The longitudinal length of the reinforcement area at the receiving end of the shield machine is 5m.
[0013] In a further embodiment, a concrete box culvert is constructed based on the building structure of an existing station, the tunnel door is completely covered in the box space of the concrete box culvert, and the wall of the concrete box culvert is supported by diagonal braces;
[0014] The concrete box culvert includes side walls and end walls. Multiple hidden beams are arranged in the side walls and the end walls, and are connected between the hidden beams and the existing station floor through I-beam diagonal braces.
[0015] In a further embodiment, a plain concrete wall with a height of 2m and a thickness of 800mm is provided in the concrete box culvert, and the plain concrete wall and the wall surface where the door is located have at least a spacing length to separate the internal space of the concrete box culvert, and the plain concrete wall is constructed through the reserved door opening of the concrete box culvert;
[0016] The surface of the plain concrete wall is arranged toward the tunnel portal, and the direction of the plain concrete wall is perpendicular to the line axis of the shield machine.
[0017] In a further embodiment, the tunnel door is chiseled out in a reverse manner in steps, and mortar is refilled at different heights inside the concrete box culvert during the chiseling process. The chiseling out of the tunnel door includes four steps:
[0018] Phase 1: Chisel away the tunnel area within 1.8m below the centerline of the tunnel, and break the surface and internal structure of the tunnel, from bottom to top, from the middle to both sides, first the surface and then the wall, break to the steel bars facing the soil surface, and then cut off the steel bars. After the steel bars are cut off, immediately refill M1.5 mortar in the concrete box culvert, and the refilling height is the area where the tunnel has been broken;
[0019] Phase II: Install the second phase backfill support formwork based on the plain concrete wall. After the formwork is installed, the tunnel area within the range of 1.8m-3.2m from the center line of the tunnel is chiseled out. The demolition and mortar backfilling are the same as the first phase;
[0020] The third stage: The third stage re-injection support formwork is installed based on the solidified second stage re-injection mortar. After the formwork is installed, the tunnel area within the range of 3.2m-4.4m from the center line of the tunnel is chiseled out. The demolition and mortar re-injection are the same as the first stage. The re-injection mortars of different stages are distributed in stacked steps between the tunnel and the plain concrete wall.
[0021] The fourth stage: chisel out the remaining portal area. The surface layer is chiseled from bottom to top, and the structural wall is chiseled from top to bottom, from the middle to both sides. After the steel bars facing the soil surface are removed, the portal is trimmed. After trimming, the steel bars are cut off. After checking the portal contour and the steel bar joints, the reserved portal of the concrete box culvert is sealed, and the remaining internal space of the concrete box culvert is refilled with M1.5 mortar. The refilled mortar is carried out simultaneously through multiple ball valves on the side wall and the top of the end wall, and cement mortar is injected into the internal space of the concrete box culvert through the ball valve.
[0022] In a further embodiment, the receiving excavation of the shield machine includes three stages:
[0023] Phase 1: In the transition section before the shield machine enters the reinforced area at the receiving end of the shield machine, the excavation speed and soil bin pressure are basically consistent with normal operation, which is conventional control; the excavation speed is gradually slowed down from 35-50mm / min in the normal section to 25-35mm / min; the thrust is gradually reduced, and the soil at the tunnel entrance is slowly and evenly cut, accompanied by grouting of the pipe segments into the stratum; when it is 15m away from the receiving tunnel door, the posture of the shield machine is adjusted to make the excavation direction of the shield machine consistent with the actual position direction of the receiving tunnel door, and the axis control accuracy during excavation should reach ±10mm;
[0024] The second stage: the shield machine enters the reinforced area at the receiving end of the shield machine, and the excavation speed is reduced from 25-35mm / min in the transition section to 20mm / min;
[0025] The third stage: The shield machine enters the concrete box culvert, and the excavation speed is reduced from 20mm / min in the transition section to 5-10mm / min;
[0026] When the shield tunnel segments are assembled, but the shield machine has not yet reached the predetermined position of the stop base, the shield machine can continue to move forward by installing negative ring segments on the side of the interval tunnel.
[0027] After the shield machine enters the concrete box culvert, the last few rings of segments in the interval tunnel are sealed with secondary grouting, and the gaps between the segments and the strata are filled by injecting a double slurry of cement and water glass.
[0028] In a further embodiment, the last few rings of the interval tunnel are assembled with porous segments, and the full ring tunnel door is sealed through multiple grouting holes reserved in each ring of the segments, and a water stop ring is applied. The single ring is applied in the order from bottom to top, alternating left and right, and finally interlaced;
[0029] After the water-stop hoop is completed, holes are drilled at three locations: the receiving concrete box culvert side wall, the radial hole of the shield in the shield machine, and the last two rings of segment lifting holes in the section tunnel to observe the seepage water conditions. After confirming that there is no leakage risk and the shield machine has completely entered the concrete box culvert, the diagonal braces of the concrete box culvert side wall are removed and the concrete box culvert is broken down.
[0030] In a further implementation method, when dismantling a concrete box culvert, firstly, the connection portion between the concrete box culvert and the existing station structure is broken manually, and the horizontal and vertical joints of the concrete box culvert side walls are first broken and separated from top to bottom, and then the horizontal and vertical joints of the concrete box culvert end walls are broken and separated from top to bottom, and finally, large-scale breaking is carried out mechanically.
[0031] In a further embodiment, the shield machine stops after the shield tail is separated from the portal structure wall and the negative ring segment, and reaches the stop position of the shield machine;
[0032] The tunnel door is sealed by welding an arc steel plate at the gap between the tunnel door steel ring and the pipe segment;
[0033] After the side wall of the concrete box culvert is chiseled out, the backfill mortar in the portal area is chiseled out. The chiseling process is carried out from top to bottom, and the arc steel plate is welded while chiseling.
[0034] In a further embodiment, after the shield machine is stopped, the tunnel gate ring beam is immediately constructed to complete the arrival and reception of the shield machine;
[0035] The portal ring beam includes an external reinforced concrete portal ring beam. The concrete grade of the portal ring beam is C35, and the water-resistance grade is the same as that of the portal wall of the existing station and is not less than P8.
[0036] The present invention receives the shield machine by constructing a concrete box culvert at an existing station, thereby breaking through the construction restrictions in a confined space and forming an effective closed receiving environment, so that the shield machine can arrive at and be received safely at the existing station.
[0037] Other features and advantages of the present application will be described in detail in the subsequent detailed description. BRIEF DESCRIPTION OF THE DRAWINGS
[0038] In order to more clearly illustrate the technical solutions of the embodiments of the present application, the drawings required for use in the embodiments will be briefly introduced below. It should be understood that the following drawings only show certain embodiments of the present application and therefore should not be regarded as limiting the scope. For ordinary technicians in this field, other related drawings can be obtained based on these drawings without paying creative work.
[0039] Figure 1 This is a schematic diagram of the structure of the concrete box culvert in this application;
[0040] Figure 2 This is a schematic diagram of the step-by-step chiseling of the tunnel in this application;
[0041] Figure 3 This is a schematic diagram of the concrete box culvert after the third stage of mortar backfilling is completed;
[0042] Figure 4 This is a schematic diagram of the shield machine entering the concrete box culvert.
[0043] icon:
[0044] 1-concrete box culvert; 2-plain concrete wall; 3-shield machine; 4-portal; 5-reinforcement area; 6-negative ring segment. DETAILED DESCRIPTION
[0045] In order to make the purpose, technical scheme and advantages of the embodiments of the present application clearer, the technical scheme in the embodiments of the present application will be clearly and completely described below in conjunction with the drawings in the embodiments of the present application. Obviously, the described embodiments are part of the embodiments of the present application, rather than all of the embodiments. The components of the embodiments of the present application described and shown in the drawings here can be arranged and designed in various different configurations.
[0046] In the description of this application, it should be noted that the terms "inside", "outside", etc. indicate the orientation or positional relationship based on the orientation or positional relationship shown in the drawings, or the orientation or positional relationship in which the product of the application is usually placed when in use, which is only for the convenience of describing this application and simplifying the description, and does not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on this application. In addition, the terms "first", "second", etc. are only used to distinguish the description, and cannot be understood as indicating or implying relative importance.
[0047] In the description of this application, it should also be noted that, unless otherwise clearly specified and limited, the terms "disposed" and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a direct connection, or an indirect connection through an intermediate medium, or it can be the internal communication of two elements. For ordinary technicians in this field, the specific meanings of the above terms in this application can be understood according to specific circumstances.
[0048] The method for receiving a shield machine arriving at a reinforced concrete box culvert in a water-rich environment in the present application is mainly used for receiving a shield machine at an existing station in a water-rich stratum. By relying on the structure of the existing station and constructing a highly operable concrete box culvert to form a closed receiving environment for the shield machine, the limitations of the confined space of the existing station can be broken through.
[0049] During shield construction, it is usually necessary to complete the arrival and reception of the shield machine in a certain underground space. After the shield machine cutterhead is pushed out of the tunnel, there is a gap between the shield shell and the stratum, and the shield excavation surface loses pressure and cannot balance the water and soil pressure around it. If there are no corresponding measures, water and soil will gush out from the gap and cause engineering accidents.
[0050] Existing measures are mainly divided into two categories. One is to reinforce the stratum at the receiving end by means of piling, grouting, or freezing, so that the soil around the shield at the receiving end can be stable and water-proof. The other is to establish a sealed receiving environment, such as erecting a steel sleeve at the tunnel portal so that the shield machine can reach the steel sleeve under pressure, and then remove the steel sleeve after the tunnel portal is sealed to complete the receiving. Some projects will use both methods at the same time.
[0051] The method for receiving a shield machine in a water-rich environment arriving at a reinforced concrete box culvert in the present application has a specific application scenario of receiving the shield machine inside an existing station of an existing subway line. Due to the limited underground space of the existing station, the above two types of measures cannot be carried out at all. For receiving at the bottom of an existing operating station, the receiving end cannot reinforce the stratum, and the steel sleeve is restricted by the existing operating subway line and cannot be hoisted to the receiving end.
[0052] In the process of receiving the shield machine upon arrival, the present application receives the shield machine in the confined space of the existing station, which mainly includes the following steps:
[0053] Reinforce the stratum at the receiving end of the shield machine;
[0054] Concrete box culverts are constructed at existing stations to completely cover the tunnel portals and provide support for the concrete box culverts;
[0055] The tunnel door is chiseled out step by step in the reverse method, and mortar is poured back into the concrete box culvert as the tunnel door is chiseled out step by step until the tunnel door is completely chiseled out and the entire concrete box culvert is filled;
[0056] Adjust the posture of the shield machine before entering the reinforcement area, and gradually reduce the thrust and speed of the shield machine after entering the reinforcement area, so that the shield machine can completely enter the concrete box culvert;
[0057] Secondary grouting is performed on the shield tail multi-ring segments and water-stop rings are applied to confirm that there is no leakage risk and then dismantle the concrete box culvert;
[0058] The gap between the tunnel portal and the segment is sealed, and the shield machine stops after the tail of the shield detaches from the tunnel portal and separates from the last segment, completing the arrival and reception of the shield machine.
[0059] In terms of the main operation process, the present application establishes a sealed arrival and receiving environment through a concrete box culvert, which can be used to construct a concrete box culvert inside an existing station, effectively enhancing the operability of the shield machine's reception, thereby breaking through the reception limitations of the shield machine in a confined space. At the same time, during the construction process, a pressure-bearing environment can be constructed in the concrete box culvert through the mortar backfilling after the receiving tunnel portal is chiseled out, which can effectively prevent the stratum pressure on the side of the tunnel portal facing the soil surface, and reduce the risk of the tunnel portal breaking after the structural strength is reduced after the tunnel portal reinforcement is cut.
[0060] The form of mortar backfilling can use its structural strength after solidification to resist the pressure excavation of the shield machine on the soil side of the tunnel portal. After the internal space of the concrete box culvert is completely filled, the structural strength of the mortar backfilling, the structural strength of the concrete wall and the supporting strength of the I-beam diagonal brace can be combined to ensure the high pressure-bearing performance of the closed receiving environment, so that the shield machine can be safely received in the concrete box culvert under the condition of gradually reducing speed and thrust.
[0061] Part of the structure of the existing station is used to construct the concrete wall. The receiving portal is completely covered in the concrete box culvert, and I-beam braces are set on the concrete wall to increase the stability of the wall. The concrete wall and I-beam braces can be hoisted and constructed within the limited space of the existing station.
[0062] Cement mortar is poured into the internal space of the concrete box culvert to form a sealed environment. During the pouring process, the back-soil structure and steel bars of the tunnel portal are broken down step by step using an unconventional "reverse method", that is, the tunnel portal is broken down from bottom to top, and a portion of the tunnel portal is broken down and backfilled with mortar to ensure the stability of the end structure strength during the tunnel portal breaking process.
[0063] After the tunnel door is chiseled out and the concrete box culvert is filled, the shield machine excavates into the concrete box culvert to complete the arrival, and then the tunnel door is sealed and grouting is performed to complete the segment structure and tunnel door water stop. After the exploration hole is free of water, the concrete box culvert is removed, and the arc steel plate and tunnel door ring beam are installed to seal the gap of the tunnel door, completing the overall reception of the shield machine.
[0064] In the specific arrival and receiving method, before the construction of the concrete box culvert, the stratum at the shield receiving end needs to be reinforced. The shield receiving end in this application refers to the stratum range with a depth of 5m on the soil side of the tunnel portal. Since the tunnel portal for receiving the shield machine is reserved on the structural wall of the existing station, the stratum in the area with a depth of 5m on the soil side of the tunnel portal is reinforced by grouting through holes in the tunnel portal.
[0065] During drilling and grouting, multiple grouting holes are evenly distributed in the tunnel portal area. By extending grouting pipes of no less than 5m in length into the multiple grouting holes, grouting is performed to reinforce the bottom layer of the stratum within a depth of 5m to ensure that the stratum has strong stability during the demolition of the tunnel portal.
[0066] It should be pointed out that the reinforcement of the shield receiving end in the present invention is different from the existing conventional reinforcement form. It is specifically a weak reinforcement method with a small reinforcement range and low reinforcement strength, which is only to prevent water and sand from gushing out when the tunnel gate is broken.
[0067] The traditional reinforcement method is strong reinforcement over a large area. The reinforced area can completely cover the shield machine, and the strength and water-stopping properties of the reinforced body are required to be high. The original intentions of the reinforcement of the two are not in the same direction, so this is hereby explained.
[0068] The concrete box culvert in the present invention is specifically a reinforced concrete box structure. The concrete box culvert is constructed based on the building structure of the existing station, the tunnel door is completely covered in the box space of the concrete box culvert, and the wall of the concrete box culvert is supported by diagonal braces.
[0069] Specifically, the middle plate of the second underground floor of the existing station is used as the top plate of the concrete box culvert, reinforcement is planted in the floor of the existing station, and the side walls and end walls of the concrete box culvert are set.
[0070] The thickness of the middle plate of the second underground floor of the existing station is 400mm, the thickness of the side wall and end wall of the concrete box culvert is 800mm, the concrete box culvert uses C30 concrete, and the thickness of the steel bar protective layer is 30mm.
[0071] Three hidden beams are set in the side walls and end walls, and the I-beams are used to connect the hidden beams and the existing station floor. In addition, the delivery pipelines for the pouring of the backfill mortar are pre-buried inside the wall. Figure 1 .
[0072] The reinforced concrete box culvert itself has a high structural strength. By embedding reinforcement in the existing station floor, the connection stability between the concrete box culvert and the existing station can be enhanced to ensure that it has a high pressure-bearing effect. Combined with the set diagonal braces and the overall space mortar backfilling after the tunnel portal is chiseled out, a stable and reliable receiving closed structure can be formed.
[0073] The main purpose of the diagonal brace is to prevent the wall from being damaged due to excessive pressure when the shield machine excavates under pressure into the concrete box culvert. The diagonal brace can effectively resist the pressure of the shield machine when excavating under pressure in the concrete box culvert, thereby ensuring the stability of the concrete box culvert structure.
[0074] A plain concrete wall with a height of 2m and a thickness of 800mm is set in the concrete box culvert. There is a gap between the plain concrete wall and the structural wall where the portal is located, which divides the internal space of the concrete box culvert. The plain concrete wall is constructed through the reserved door opening of the concrete box culvert. The setting of the reserved door opening is convenient for personnel to enter and exit and for the distribution of mortar backfilling operations.
[0075] See also Figure 4The plain concrete wall 2 is cast with M5 mortar, the wall surface is set toward the tunnel gate 4, and the direction of the plain concrete wall 2 is perpendicular to the line axis of the shield machine 3.
[0076] Based on the step-by-step chiseling of the tunnel door and the reinjection of mortar after the chiseling, the setting of the plain concrete wall is conducive to filling the mortar between the plain concrete wall and the tunnel door in the first step of mortar reinjection, reducing the formwork support of the first step of mortar reinjection, and facilitating the installation of the mortar support formwork at different stages.
[0077] It should be pointed out that the setting of plain concrete wall can constitute the coagulation pool structure of the first step of mortar reinjection process, and ensure the structural strength of the bottom reinjection mortar with the coagulated solid structure, laying a good foundation for the overall receiving closed structure of the concrete box culvert.
[0078] The step-by-step removal of the tunnel gate and the mortar refilling in the concrete box culvert specifically include:
[0079] The tunnel portal is chiseled out in steps using the reverse method, with the main and key purpose being to break the steel bars inside the tunnel portal, which can reduce damage to the shield machine when it breaks out of the tunnel portal.
[0080] After the steel bars of the tunnel portal are removed, the structural strength of the tunnel portal will inevitably be affected. In order to prevent the stratum on the facing side of the tunnel portal from breaking through the tunnel portal under the action of the shield machine's excavation pressure, it is necessary to immediately re-inject mortar after removing the steel bars of the tunnel portal and the structure on the back side of the steel bars to resist the risk of breaking through.
[0081] In addition, in order to further reduce the risk of breach, it is necessary to chisel out the tunnel door in small areas in steps, and to refill the concrete box culvert with mortar at different heights as the chiseling progresses. Figure 2 Schematic diagram of the step-by-step chiseling of the middle tunnel door. The chiseling of the tunnel door specifically includes four steps:
[0082] The first stage: the tunnel area within the range of 1.8m below the center line of the tunnel is chiseled out. In the specific embodiment of the present invention, this part of the area specifically corresponds to the area from 1.55m below the center line of the tunnel to the bottom of the tunnel steel ring. The surface and internal structure of the tunnel are broken from bottom to top, from the middle to both sides, first the surface and then the wall. After breaking to the steel bars facing the soil surface, the steel bars are cut off. After the steel bars are cut off, the M1.5 mortar is immediately refilled in the concrete box culvert. The refilling height is the area where the tunnel has been broken. Since the backfilling height of this part is less than the height of the plain concrete wall, no support backfilling template is required. The mortar backfilling height is 20cm lower than the plain concrete wall. The role of the plain concrete wall is to serve as a support template for the first stage of mortar refilling when the tunnel is broken and the mortar is refilled in the first stage, and it can form a concrete pool in the first stage of mortar refilling process, effectively forming a stable mortar refilling structure, and laying a solid foundation for the subsequent refilling of mortar.
[0083] The second stage: In order to be able to immediately carry out mortar backfilling after the tunnel door is broken, the support formwork is installed before the second step of chiseling the tunnel door. Specifically, the chiseling of the tunnel door in the second stage and the backfilling of the mortar formwork are carried out on the backfilled and solidified mortar layer in the first stage. After the first stage of backfilling mortar solidifies, the second stage backfilling support formwork is installed based on the plain concrete wall. After the formwork is installed, the tunnel door area within the range of 1.8m-3.2m from the center line of the tunnel door is chiseled, and the breaking and mortar backfilling are the same as the first stage;
[0084] The third stage: In order to be able to immediately carry out mortar backfilling after the tunnel door is broken, the support formwork is installed before the third step of chiseling the tunnel door. In this step, it is necessary to wait for the second stage backfill mortar to solidify, and then install the third stage backfill support formwork based on the solidified second stage backfill mortar. After the formwork is installed, the tunnel door area within the range of 3.2m-4.4m from the center line of the tunnel door is chiseled out. The breaking and mortar backfilling are the same as the first stage. The backfill mortars at different stages are distributed in stacked steps between the tunnel door and the plain concrete wall. See Figure 3 The schematic diagram after the completion of the third stage is shown in Figure 2. The purpose of the stepped distribution is to facilitate the chiseling and mortar reinjection operations at each stage and enhance operability.
[0085] The fourth stage: after the completion of the fourth stage, the entire interior of the concrete box culvert needs to be backfilled with mortar. Therefore, this step does not require the installation of support formwork. After the mortar backfilled in the third stage solidifies, the remaining portal area is chiseled out. The order of demolition is from bottom to top for the surface layer, and from top to bottom for the structural wall, from the middle to both sides. After demolition to the steel bars facing the soil surface, the portal is trimmed. After trimming, the steel bars are cut off. After checking the portal contour and the steel bar joints, the reserved door opening of the concrete box culvert is sealed, and the remaining internal space of the concrete box culvert is backfilled with M1.5 mortar. The backfilled mortar is carried out simultaneously through multiple ball valves on the side wall and the top of the end wall, and cement mortar is injected into the internal space of the concrete box culvert through the ball valve.
[0086] The purpose of checking the steel bar joints of the portal contour is to prevent the steel bar joints from remaining on the edge of the portal and avoid damage to the shield machine during the excavation process. It should be pointed out that the inspection of steel bar joints involves every stage of portal chiseling to reduce the risk to a minimum.
[0087] In this application, the step-by-step chiseling of the tunnel portal and the step-by-step backfilling of mortar are intended to prevent the stratum at the tunnel portal from being exposed for too long and to avoid water and sand gushing. The step-by-step chiseling from bottom to top is also intended to match the backfilling mortar so that the mortar can seal the chiseled tunnel portal from bottom to top.
[0088] Completing the overall mortar backfilling of the concrete box culvert means completing the construction operation of the shield machine's closed receiving structure, and the shield machine completes the arrival and reception during the receiving excavation at different stages.
[0089] During the overall adjustment process, during the drilling and grouting of different areas of the tunnel portal, the longitudinal length of the reinforced area at the receiving end of the shield machine is 5m. According to the posture of the receiving tunnel portal, the shield machine posture is adjusted before entering the reinforced area to ensure safe and uniform entry into the reinforced range. During this process, the shield machine cutter head and shield shell must be prevented from getting stuck.
[0090] After the shield machine enters the 5m receiving section, the thrust and propulsion speed should be reduced to avoid the large thrust affecting the stability of the soil within the tunnel portal. The shield receiving excavation can be divided into the following three stages. In these stages, different construction parameters should be adopted to control different focuses.
[0091] Specifically:
[0092] The first stage: the transition section 15 to 5 meters away from the receiving tunnel entrance before the shield machine enters the reinforced area of the receiving end of the shield machine. The excavation speed and soil bin pressure are basically consistent with normal operation and are under routine control; the excavation speed is gradually slowed down from 35 to 50 mm / min in the normal section to 25 to 35 mm / min; the thrust is gradually reduced, and the soil at the tunnel entrance is slowly and evenly cut. At the same time, grouting is carried out into the stratum along with the installation of the pipe segments, and the grouting work is done well to cut off the source of water behind the shield machine; when it is 15 meters away from the receiving tunnel entrance, the construction of this section should focus on adjusting the posture of the shield machine so that the excavation direction of the shield machine is consistent with the actual position direction of the receiving tunnel entrance as much as possible, and the axis control accuracy during excavation should reach ±10mm;
[0093] The second stage: When the shield machine enters the reinforced area at the receiving end of the shield, that is, when the shield machine enters 5 to 0 m away from the tunnel entrance, the excavation speed is reduced from 25 to 35 mm / min in the transition section to 20 mm / min. The purpose is to minimize the impact on the tunnel entrance, and then gradually reduce the shield pressure while closely monitoring the surface and the tunnel entrance.
[0094] Phase 3: See Figure 4 The shield machine passes through the tunnel gate 4 from the reinforced area 5 and enters the concrete box culvert 1. The excavation speed is reduced from 20mm / min in the transition section to 5-10mm / min. The third stage of receiving is the continuous advancement of the shield machine 3 after the concrete box culvert 1 and the receiving guide platform. During the excavation process, close attention is paid to the pressure inside the concrete box culvert.
[0095] When the shield tunnel segments are assembled, the shield machine has not yet reached the predetermined position of the stop base, and the shield machine continues to move forward by continuing to install the negative ring segments 6 on the interval tunnel side;
[0096] After the shield machine enters the concrete box culvert, in order to completely block the seepage channel, ensure the smooth reception of the shield, and prevent water and sand gushing from tunnel gate 4 when dismantling the concrete box culvert, the last 8 rings of porous segments in the interval tunnel are sealed by secondary grouting. The grouting material is a double liquid slurry of cement and water glass, which fills the gap between the segments and the stratum.
[0097] The last 8 rings of the interval tunnel are assembled with multi-hole segments. The full-ring tunnel door is sealed through multiple grouting holes reserved in each ring of segments, and water-stop rings are installed. The order of single ring installation is from bottom to top, alternating left and right, and finally crossing the circle;
[0098] After the water-stop ring of the shield receiving end portal is completed, holes are drilled at three locations: the receiving concrete box culvert side wall, the radial hole of the shield in the shield machine, and the last two rings of segment lifting holes in the interval tunnel to observe the seepage water conditions. After confirming that there is no leakage risk, the segment tensioning device is installed, the diagonal braces of the concrete box culvert side wall are removed, and the concrete box culvert is broken.
[0099] When dismantling a concrete box culvert, first manually break down the connection between the concrete box culvert and the existing station structure, first break down and separate the horizontal and vertical joints of the concrete box culvert side walls from top to bottom, then break down and separate the horizontal and vertical joints of the concrete box culvert end walls from top to bottom, and finally use machinery to break down a large area.
[0100] In order to avoid water leakage from the tunnel portal, curved steel plates are used to seal the tunnel portal. The specific methods include: welding curved steel plates at the gap between the receiving tunnel portal steel ring and the segment to seal the gap between the tunnel portal and the segment. The shield tail of the shield machine is separated from the tunnel portal structure wall and the last installed negative ring segment before stopping, reaching the stop position of the shield machine.
[0101] After the side walls of the concrete box are chiseled out, the chiseling of the backfill mortar in the tunnel portal area after solidification begins. The principle of chiseling the backfill mortar near the tunnel portal area is: chiseling from top to bottom, while chiseling, welding the arc steel plate at the same time to shorten the exposure time of the gap of the tunnel portal and avoid water leakage.
[0102] After the shield machine is shut down, the arrival reception of the shield machine is completed. The tunnel gate ring beam is constructed immediately to effectively control the risk of water leakage caused by the removal of the negative ring segments during the reception period. The tunnel gate ring beam structure adopts an external type to reduce the construction risk of the tunnel gate ring beam structure. The structure of the tunnel gate ring beam is a reinforced concrete tunnel gate ring beam with a concrete grade of C35 and a water resistance grade that is the same as the tunnel gate wall of the existing station and is not less than P8.
[0103] The method for receiving a shield machine in a water-rich environment by reaching a reinforced concrete box culvert can break through the reception limitation of the space. The effective sealed environment formed by the concrete box culvert allows the shield machine to arrive and be received safely. This can not only effectively solve the problem of receiving the shield machine in a limited space in a water-rich environment, but is also economical and efficient, ensuring construction safety while effectively saving costs.
[0104] Compared with the conventional receiving method, the receiving method of the shield machine in a water-rich environment reaching the reinforced concrete box culvert in the present invention has the following advantages:
[0105] 1. With regard to the overall reinforcement of the existing receiving end and the installation of the steel sleeve, the receiving method of the shield machine in the present invention does not require large-scale machinery and structural operations, and can be completed in the confined space of the existing station, which is more suitable for application scenarios with limited working space.
[0106] 2. The construction speed is fast, and the process of each step is relatively simple, which can save a lot of construction time and greatly improve work efficiency.
[0107] 3. The step-by-step removal of the tunnel portal and the distributed reinjection of mortar in the concrete box culvert effectively reduce the risk of water and sand gushing during the shield receiving operation, and have little disturbance to the strata in the receiving area, reducing the impact on other structures of the existing station.
[0108] 4. By setting up an effective and reliable enclosed structure, it can ensure that the shield machine can reach the site under pressure in the enclosed concrete box culvert, reducing the risk of water and sand gushing during the arrival of the shield machine.
[0109] 5. After the concrete box culvert is dismantled, the gap between the pipe segment and the portal steel ring can be immediately sealed to further reduce the risk of water and sand gushing during the receiving process.
[0110] It should be noted that, in the absence of conflict, the features in the embodiments of this application may be combined with each other.
[0111] The above description is only the preferred embodiment of the present application and is not intended to limit the present application. For those skilled in the art, the present application may have various modifications and variations. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present application shall be included in the protection scope of the present application.
Claims
1. A method for receiving a shield machine in a water-rich environment arriving at a reinforced concrete box culvert, receiving the shield machine in a confined space of an existing station, characterized in that: The following steps are involved: Reinforce the stratum at the receiving end of the shield machine; Concrete box culverts are constructed at existing stations to completely cover the tunnel portals and provide support for the concrete box culverts; The tunnel door is chiseled out step by step in the reverse method, and mortar is poured back into the concrete box culvert as the tunnel door is chiseled out step by step until the tunnel door is completely chiseled out and the entire concrete box culvert is filled; Adjust the posture of the shield machine before entering the reinforcement area, and gradually reduce the thrust and speed of the shield machine after entering the reinforcement area, so that the shield machine can completely enter the concrete box culvert; Secondary grouting is performed on the shield tail multi-ring segments and water-stop rings are applied to confirm that there is no leakage risk and then dismantle the concrete box culvert; The gap between the tunnel door and the segment is sealed, and the shield tail of the shield machine is separated from the tunnel door and the last segment before stopping, completing the arrival and reception of the shield machine; The tunnel gate is chiseled out in reverse steps, and mortar is refilled at different heights inside the concrete box culvert during the chiseling process. The chiseling of the tunnel gate includes four steps: Phase 1: Chisel away the tunnel area within 1.8m below the centerline of the tunnel, and break the surface and internal structure of the tunnel, from bottom to top, from the middle to both sides, first the surface and then the wall, break to the steel bars facing the soil surface, and then cut off the steel bars. After the steel bars are cut off, immediately refill M1.5 mortar in the concrete box culvert, and the refilling height is the area where the tunnel has been broken; Phase II: Install the second phase backfill support formwork based on the plain concrete wall. After the formwork is installed, the tunnel area within the range of 1.8m-3.2m from the center line of the tunnel is chiseled out. The demolition and mortar backfilling are the same as the first phase; The third stage: The third stage re-injection support formwork is installed based on the solidified second stage re-injection mortar. After the formwork is installed, the tunnel area within the range of 3.2m-4.4m from the center line of the tunnel is chiseled out. The demolition and mortar re-injection are the same as the first stage. The re-injection mortars of different stages are distributed in stacked steps between the tunnel and the plain concrete wall. The fourth stage: the remaining portal area is chiseled out. The surface layer is chiseled out from bottom to top, and the structural wall is chiseled out from top to bottom, from the middle to both sides. After the steel bars facing the soil surface are removed, the portal is trimmed. After trimming, the steel bars are cut off. After checking the portal contour and the steel bar joints, the reserved portal of the concrete box culvert is sealed. The remaining internal space of the concrete box culvert is refilled with M1.5 mortar. The refilled mortar is simultaneously carried out through multiple ball valves on the side wall and the top of the end wall. Cement mortar is injected into the internal space of the concrete box culvert through the ball valve; The receiving excavation of the shield machine includes three stages: Phase 1: In the transition section before the shield machine enters the reinforced area at the receiving end of the shield machine, the excavation speed and soil bin pressure are basically consistent with normal operation, which is conventional control; the excavation speed is gradually slowed down from 35-50mm / min in the normal section to 25-35mm / min; the thrust is gradually reduced, and the soil at the tunnel entrance is slowly and evenly cut, accompanied by grouting of the pipe segments into the stratum; when it is 15m away from the receiving tunnel door, the posture of the shield machine is adjusted to make the excavation direction of the shield machine consistent with the actual position direction of the receiving tunnel door, and the axis control accuracy during excavation should reach ±10mm; The second stage: the shield machine enters the reinforced area at the receiving end of the shield machine, and the excavation speed is reduced from 25-35mm / min in the transition section to 20mm / min; The third stage: The shield machine enters the concrete box culvert, and the excavation speed is reduced from 20mm / min in the transition section to 5-10mm / min; When the shield tunnel segments are assembled, but the shield machine has not yet reached the predetermined position of the stop base, the shield machine can continue to move forward by installing negative ring segments on the side of the interval tunnel. After the shield machine enters the concrete box culvert, the last few rings of segments in the interval tunnel are sealed with secondary grouting, and the gaps between the segments and the strata are filled by injecting a double slurry of cement and water glass.
2. The method for receiving a shield machine in a water-rich environment arriving at a reinforced concrete box culvert according to claim 1, characterized in that: The existing station has a portal reserved for receiving the shield machine. Through the portal, holes are drilled and grouting is injected into the stratum at the receiving end of the shield to create a reinforcement area. The longitudinal length of the reinforcement area at the receiving end of the shield is 5m.
3. The method for receiving a shield machine in a water-rich environment arriving at a reinforced concrete box culvert according to claim 1, characterized in that: Relying on the existing station building structure, a concrete box culvert is constructed, the tunnel portal is completely covered in the box space of the concrete box culvert, and the wall of the concrete box culvert is supported by diagonal braces; The concrete box culvert includes side walls and end walls. Multiple hidden beams are arranged in the side walls and the end walls, and are connected between the hidden beams and the existing station floor through I-beam diagonal braces.
4. The method for receiving a shield machine in a water-rich environment arriving at a reinforced concrete box culvert according to claim 3, characterized in that: A plain concrete wall with a height of 2m and a thickness of 800mm is set in the concrete box culvert. There is at least a certain distance between the plain concrete wall and the wall surface where the door is located, which divides the internal space of the concrete box culvert. The plain concrete wall is constructed through the reserved door opening of the concrete box culvert. The surface of the plain concrete wall is arranged toward the tunnel portal, and the direction of the plain concrete wall is perpendicular to the line axis of the shield machine.
5. The method for receiving a shield machine in a water-rich environment arriving at a reinforced concrete box culvert according to claim 1, characterized in that: The last few rings of the interval tunnel are assembled with multi-hole segments. The full-ring tunnel door is sealed through multiple grouting holes reserved in each ring of segments, and water-stop rings are installed. The order of single ring installation is from bottom to top, alternating left and right, and finally crossing the circle; After the water-stop hoop is completed, holes are drilled at three locations: the receiving concrete box culvert side wall, the radial hole of the shield in the shield machine, and the last two rings of segment lifting holes in the section tunnel to observe the seepage water conditions. After confirming that there is no leakage risk and the shield machine has completely entered the concrete box culvert, the diagonal braces of the concrete box culvert side wall are removed and the concrete box culvert is broken down.
6. The method for receiving a shield machine in a water-rich environment arriving at a reinforced concrete box culvert according to claim 5, characterized in that: When dismantling a concrete box culvert, first manually break down the connection between the concrete box culvert and the existing station structure, first break down and separate the horizontal and vertical joints of the concrete box culvert side walls from top to bottom, then break down and separate the horizontal and vertical joints of the concrete box culvert end walls from top to bottom, and finally use machinery to break down a large area.
7. The method for receiving a shield machine in a water-rich environment arriving at a reinforced concrete box culvert according to claim 6, characterized in that: The shield machine stops after its tail is separated from the portal structure wall and the negative ring segment, reaching the stop position of the shield machine; The tunnel door is sealed by welding an arc steel plate at the gap between the tunnel door steel ring and the pipe segment; After the side wall of the concrete box culvert is chiseled out, the backfill mortar in the portal area is chiseled out. The chiseling process is carried out from top to bottom, and the arc steel plate is welded while chiseling.
8. The method for receiving a shield machine in a water-rich environment arriving at a reinforced concrete box culvert according to claim 7, characterized in that: After the shield machine is shut down, the tunnel gate ring beam is constructed immediately to complete the arrival and reception of the shield machine; The portal ring beam includes an external reinforced concrete portal ring beam. The concrete grade of the portal ring beam is C35, and the water-resistance grade is the same as that of the portal wall of the existing station and is not less than P8.