Geological fault rock burst monitoring and early warning device and method

Through multi-source data fusion and in-depth analysis, combined with multiple monitoring methods, the problem of data singleness and real-time in geological fault impact pressure monitoring and early warning is solved, the accuracy and systematicness of predictions are improved, and mine safety management is enhanced. ability.

CN118794637APending Publication Date: 2024-10-18CHONGQING UNIV
View PDF 0 Cites 3 Cited by

Patent Information

Application Number
CN202411030861.4
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-30
Publication Date
2024-10-18

AI Technical Summary

Technical Problem

The existing technology has problems in monitoring and early warning of geological fault impact ground pressure, such as single data, insufficient multi-source data fusion, insufficient real-time monitoring capabilities, poor equipment sensitivity and reliability, and lack of systematic solutions, leading to deviations in prediction results and accidents. Increased risk.

Method used

It adopts true triaxial load loading system, shear loading disturbance system, oil source and supercharger system, specimen production and transportation system, test control and data acquisition system, combined with ground sound monitoring, acoustic emission instrument, electromagnetic radiation instrument, Infrared thermal imagers and high-speed cameras perform multi-source data fusion and in-depth analysis to achieve real-time monitoring and early warning.

Benefits of technology

It improves the comprehensiveness and accuracy of geological disaster prediction, enhances mine safety management capabilities, provides highly sensitive and highly reliable monitoring results, and realizes systematic geological disaster management.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118794637A_ABST
    Figure CN118794637A_ABST
Patent Text Reader

Abstract

The invention belongs to the technical field of geological monitoring devices, and discloses a geological fault rock burst monitoring and early warning device and method.The geological fault rock burst monitoring and early warning device is composed of a true triaxial load loading system, a shear loading disturbance system, an oil source and supercharger system, a test piece manufacturing and transporting system and a test control and data acquisition system; the true triaxial load loading system consists of a vertical loading subsystem, a side horizontal loading subsystem and a rear horizontal loading subsystem; the shear loading disturbance system comprises a ZL-3 which is arranged above the true triaxial load loading system; the oil source and supercharger system is composed of a hydraulic servo oil source, a supercharger and an oil cooler. The test piece manufacturing and transporting system consists of an oil cylinder, a forming mold and a movable sample trolley; the test control and data acquisition system is composed of a hydraulic servo valve, a control cabinet and a computer acquisition system. The geological fault rock burst monitoring device is simple and practical in structure, and monitoring of geological fault rock burst is more accurate.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention belongs to the technical field of geological monitoring devices, and in particular relates to a geological fault rock burst pressure monitoring and early warning device and method. Background Art

[0002] As the depth and intensity of coal mining increase, geological conditions become more complex, and dynamic disasters such as mine rock bursts are becoming increasingly severe. Faults are a common geological structure in the process of coal mining. Their unique discontinuous structure controls the deformation, destruction and mechanical properties of coal rocks. The interaction between this structure and coal mining activities will lead to fault activation and thus rock bursts. The hazards of fault activation are very huge. The rock bursts caused by it will cause serious engineering accidents and have a great impact on coal mining.

[0003] Traditional geological disaster prediction methods often rely on only a single type of data, which leads to deviations in warning results and makes it difficult to fully reflect the actual situation.

[0004] As the depth and intensity of coal mining increase, geological conditions become more complex, and dynamic disasters such as mine rock bursts are becoming increasingly severe. Faults are a common geological structure in coal mining. Their unique discontinuous structure controls the deformation, failure and mechanical properties of coal rocks. The interaction between this structure and coal mining activities can lead to fault activation, which in turn causes rock bursts. The hazards of such fault activation are enormous, leading to serious engineering accidents and seriously affecting the safety and efficiency of coal mining.

[0005] Problems with existing technologies:

[0006] 1) Data uniformity and prediction bias:

[0007] Traditional geological hazard prediction methods rely on a single type of data and ignore other important geological features.

[0008] A single data source leads to deviations in prediction results, making it difficult to accurately predict the occurrence of rock burst.

[0009] 2) Lack of multi-source data fusion and in-depth analysis:

[0010] Current monitoring devices and methods lack the integration and comprehensive analysis of multiple data sources.

[0011] Modern technologies (such as big data analysis and artificial intelligence) are not fully utilized to integrate and conduct in-depth analysis of multi-source data, which affects the accuracy of predictions.

[0012] 3) Insufficient real-time monitoring and early warning capabilities:

[0013] Traditional monitoring methods are deficient in real-time performance and are unable to provide early warning information of fault activation quickly and accurately.

[0014] The lack of real-time monitoring and early warning capabilities results in the inability to take timely preventive measures in emergency situations, increasing the risk of accidents.

[0015] 4) Challenges of equipment sensitivity, reliability and environmental adaptability:

[0016] Existing monitoring equipment lacks sensitivity and reliability, making it difficult to capture tiny signals of geological changes.

[0017] The equipment has poor adaptability and stability in complex geological environments, which affects the accuracy and reliability of monitoring data.

[0018] 5) Lack of systematic solutions:

[0019] Current monitoring methods and devices are often scattered, lacking systematicity and integrity, making it difficult to form an effective early warning and emergency management system.

[0020] The lack of a comprehensive understanding of fault activation and rock burst and systematic prevention and control measures has increased the difficulty of geological disaster management.

[0021] Through the above analysis, the existing technology has significant deficiencies in the monitoring and early warning of rock burst in geological faults. A more comprehensive, accurate and real-time monitoring device is needed to improve the accuracy and reliability of prediction and enhance the ability of mine safety management. Summary of the invention

[0022] In view of the problems existing in the prior art, the present invention provides a geological fault rock burst pressure monitoring and early warning device and method.

[0023] The present invention is implemented as follows: a geological fault rock burst monitoring and early warning device, which is composed of a true triaxial load loading system, a shear loading disturbance system, an oil source and a supercharger system, a specimen production and transportation system, and a test control and data acquisition system;

[0024] The true triaxial load loading system is provided with loading cylinders in the vertical, lateral and rear horizontal directions, and reaction frames are provided in the corresponding directions to provide reaction forces; when carrying out the loading test, the vertical, lateral and rear horizontal cylinders drive the pads to apply pressure to the specimen at the same time, realizing the three-way stress loading function;

[0025] The shear loading disturbance system is composed of a shear loading disturbance subsystem (ZL-3) arranged at the top and a vertical loading subsystem (ZL-1) that assists and cooperates with it;

[0026] The oil source and supercharger system is composed of an oil tank, an oil pump-motor unit, a precision oil filter, a relief valve, a liquid level gauge, a pressure gauge, an air filter, an energy converter and pipelines;

[0027] The test piece production and transportation system is composed of an oil cylinder and a forming die, a servo oil source, a control system and a test piece trolley;

[0028] The test control and data acquisition system consists of a control cabinet, a hydraulic servo valve, a 6-channel automatic control system, a 16-channel data acquisition system, and computer measurement and control software.

[0029] Furthermore, the true triaxial load loading system is composed of a vertical loading subsystem, a side horizontal loading subsystem, and a rear horizontal loading subsystem;

[0030] The shear loading disturbance system includes ZL-3 and ZL-1. ZL-3 is set above the true triaxial load loading system. The oil source and supercharger system consists of a hydraulic servo oil source, a supercharger, and an oil cooler.

[0031] The specimen production and transportation system consists of a cylinder, a forming die, and a movable specimen trolley;

[0032] The test control and data acquisition system consists of hydraulic servo valve, control cabinet and computer acquisition system.

[0033] Furthermore, the two loading subsystems of the shear loading disturbance system perform unidirectional loading movements while ensuring the voltage stability of other loading subsystems, thereby realizing the shear loading disturbance of the system; and the shear load of the specimen is realized by changing the position.

[0034] Furthermore, the oil source and supercharger system are also equipped with a temperature control meter and a temperature sensor to form an oil temperature protection system to ensure that the oil temperature in the servo oil source does not exceed 60°C.

[0035] Furthermore, the controller of the test control and data acquisition system uses EDCi50 to analyze and collect data. The EDC controller transmits the data of each sensor to the computer and gives an electrical signal to the actuator (servo valve) according to the computer's instructions. The setting and loading of displacement and force control parameters are realized in the measurement and control software. Each loading subsystem can be completely independently controlled, the operation is very convenient, and the load-displacement curve can be drawn synchronously.

[0036] Furthermore, the geological fault rock burst monitoring and early warning device is equipped with corresponding monitoring equipment, which includes a ground sound monitoring system, an acoustic emission instrument, an electromagnetic radiation instrument, an infrared thermal imager, a high-speed camera and a micro camera.

[0037] Furthermore, the vertical loading subsystem is located at the lower end of the true triaxial load loading system; the side horizontal loading subsystem is located on one side of the true triaxial load loading system, and a reaction frame is provided on the other side of the true triaxial load loading system; and the rear horizontal loading subsystem is located on the rear side of the true triaxial load loading system.

[0038] Furthermore, the vertical loading subsystem includes ZL-1 and ZL-2, which are fixed on the same base; the side horizontal loading subsystem includes YL-1 and YL-2, which are fixed on the same base; the rear horizontal loading subsystem is located at the rear side of the true triaxial load loading system, including XL-1.

[0039] Furthermore, ZL-1, ZL-2, YL-1, YL-2 and XL-1 are all provided with a loading plate.

[0040] Another object of the present invention is to provide a geological fault rock burst pressure monitoring and early warning method of a geological fault rock burst pressure monitoring and early warning device, comprising the following steps:

[0041] Step 1: Arrange a ground sound monitoring system in the tunnel to obtain ground sound monitoring data, determine the ground sound frequency, the time point with abnormally high concentration, and conduct spatiotemporal data field analysis;

[0042] Step 2: Use the high-speed camera acquisition system, acoustic emission instrument and electromagnetic radiation instrument equipped in the monitoring system to supplement and improve the monitoring of the fault;

[0043] Step 3, shearing the test specimen using the shear loading disturbance system marked on the equipment;

[0044] Step 4: After obtaining the geological fault, use the system to conduct experiments.

[0045] Furthermore, in step one, the test specimen is sheared: the ZL-2 cylinder is locked, and ZL-1 and ZL-3 move in the same direction.

[0046] In combination with the above technical solutions and the technical problems solved, the advantages and positive effects of the technical solutions to be protected by the present invention are as follows:

[0047] First, the present invention includes a machine vision measuring device composed of left and right machine vision measuring units, a laser emitting device composed of two laser emitting units, a calibration platform, a shielding tube, a host, and a geosound monitoring system; the geosound monitoring data within a certain period of time is selected to obtain deformation parameters, geosound frequencies, and energy data; then, a joint analysis model of deformation-geosound time series data field and spatial data field is introduced. The fault is analyzed in time and space fields, thereby realizing the monitoring of geological faults.

[0048] The present invention uses a method of coordinated monitoring and early warning of fault three-dimensional deformation, geoacoustic geological fault monitoring, acoustic emission, electromagnetic radiation, high-speed cameras, and infrared radiation meters to realize automatic monitoring of three-dimensional deformation of crustal faults, obtain acoustic emission signals, electromagnetic radiation, and infrared radiation phenomena during the test, and a variety of technical means complement each other. Through the joint analysis of a variety of monitoring means, a precursor early warning system for rock bursts in fault geological structures is constructed. The invention has a simple and practical structure, making the monitoring of rock bursts in geological faults more accurate.

[0049] Second, the problems existing in the prior art:

[0050] As the depth and intensity of coal mining increase, geological conditions become more complex, and dynamic disasters such as mine rock bursts are becoming increasingly severe. Faults are a common geological structure in coal mining. Their unique discontinuous structure controls the deformation, failure and mechanical properties of coal rocks. The interaction between this structure and coal mining activities can lead to fault activation, which in turn causes rock bursts. The hazards of such fault activation are enormous, leading to serious engineering accidents and seriously affecting the safety and efficiency of coal mining.

[0051] Existing geological disaster prediction methods often rely on a single type of data, which cannot fully reflect the actual situation, resulting in deviations in early warning results. At the same time, existing monitoring devices and methods lack the integration and comprehensive analysis of multiple data sources, and cannot provide comprehensive and accurate fault activation predictions. In addition, the lack of real-time monitoring and early warning capabilities, low equipment sensitivity and reliability, and lack of systematic solutions make the current geological disaster management difficult. At the same time, the research objects corresponding to the relevant inventions and monitoring equipment are small in size and are greatly affected by the size effect, and cannot fully and accurately feedback the changes in signal parameters of fault activation and related geological disasters. The lack of these monitoring information makes it relatively difficult to establish a connection from physical simulation to engineering site practice.

[0052] Technical problems solved by the present invention:

[0053] 1) Multi-source data fusion and comprehensive analysis:

[0054] The present invention improves the comprehensiveness and accuracy of geological disaster prediction by integrating multiple data sources (such as earthquake monitoring data, surface deformation data, etc.) and conducting comprehensive analysis.

[0055] 2) Enhanced real-time monitoring and early warning capabilities:

[0056] The monitoring device provided by the present invention has high sensitivity and high reliability, can monitor fault activation in real time, and quickly provide early warning information, thereby enhancing the ability of mine safety management.

[0057] 3) Systematic solutions:

[0058] The present invention proposes a complete set of systematic monitoring and prediction methods, including the integration of multiple data sources, the design of real-time monitoring devices, and the application of data processing and analysis algorithms, providing a systematic geological disaster management solution.

[0059] Significant technical advancements of the present invention:

[0060] 1) Innovative multivariate time series decomposition and multi-model combination methods:

[0061] The present invention adopts the method of multivariate time series decomposition and multi-model combination, and improves the accuracy and robustness of geological disaster prediction through the fusion prediction of STL decomposition, bidirectional long short-term memory network and time series convolutional network.

[0062] 2) High-precision fault activation monitoring device:

[0063] The monitoring device provided by the present invention, which is composed of a true triaxial load loading system, a shear loading disturbance system, an oil source and a supercharger system, a specimen preparation and transportation system, a test control and data acquisition system, etc., has high sensitivity and high reliability, and can accurately capture subtle changes in the fault activation process.

[0064] 3) Real-time data processing and analysis:

[0065] The monitoring device and data acquisition system of the present invention can collect and process data in real time, quickly analyze fault activation conditions through hydraulic servo valves and computer acquisition systems, and provide timely early warning information.

[0066] 4) Intelligent control and operation:

[0067] The test control and data acquisition system of the present invention combines computer control technology, realizes intelligent operation and data processing, and improves the automation degree and operation convenience of the system.

[0068] 5) Enhanced security and reliability:

[0069] The present invention adopts an asymmetric encryption method through an information encryption module and an information transmission module to ensure the safe transmission and storage of monitoring data, thereby improving the security and reliability of the system.

[0070] In summary, the present invention solves many problems in geological disaster prediction and monitoring in the prior art through innovative technical solutions and systematic designs, significantly improves the accuracy, real-time and systematic nature of the prediction, and has important technological progress and practical application value.

[0071] Third, the technical solution of the present invention fills the technical gap in the industry at home and abroad:

[0072] As mining and geological engineering activities develop into deeper strata, rock burst and rock burst disasters become more serious, and the types of impact damage are complex and varied. At present, most of the physical simulation test equipment for rock burst research can only carry out true triaxial and single-sided unloading tests. There are still deficiencies in simulating rock burst induced by fault dislocation, and it is impossible to comprehensively study rock burst disasters under complex geological conditions. At the same time, the specimens studied are small in size and mostly rock and coal samples. There is a lack of perfect technical means for the study of rock burst disasters under deep complex geological conditions, and there is an urgent need to develop corresponding physical simulation test equipment. Based on this, the physical simulation test system was invented. The system functions are relatively comprehensive, which makes up for the defects of the current related fault rock burst physical simulation test equipment. BRIEF DESCRIPTION OF THE DRAWINGS

[0073] In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the following briefly introduces the drawings required for use in the embodiments of the present invention. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without creative work.

[0074] Figure 1 It is a structural diagram of a geological fault rock burst pressure monitoring and early warning device provided by an embodiment of the present invention;

[0075] Figure 2 It is an overall structural diagram of a true triaxial load loading system and a shear loading disturbance system provided by an embodiment of the present invention;

[0076] Figure 3 is a structural diagram of a true triaxial load loading system provided by an embodiment of the present invention;

[0077] Figure 4 is a structural diagram of a true triaxial load loading system provided by an embodiment of the present invention;

[0078] Figure 5 is a structural diagram of a shear loading disturbance system provided by an embodiment of the present invention;

[0079] Figure 6 is a structural diagram of an oil source and a supercharger system provided by an embodiment of the present invention;

[0080] Figure 7 is a structural diagram of a hydraulic servo oil source provided by an embodiment of the present invention;

[0081] Figure 8 is a structural diagram of a test piece preparation and transportation system provided by an embodiment of the present invention;

[0082] Fig. 9 is a structural diagram of a test control and data acquisition system provided by an embodiment of the present invention;

[0083] Fig.10 is a control cabinet structure diagram of a test control and data acquisition system provided by an embodiment of the present invention;

[0084] Fig.11 is a structural diagram of an acoustic emission instrument provided by an embodiment of the present invention;

[0085] Fig.12 is a structural diagram of an electromagnetic radiation instrument provided by an embodiment of the present invention;

[0086] Fig.13 is a structural diagram of an infrared thermal imager provided by an embodiment of the present invention;

[0087] Fig.14 is a structural diagram of a high-speed camera provided by an embodiment of the present invention;

[0088] Fig.15 It is a flow chart of a method for monitoring and early warning of geological fault rock burst pressure provided by an embodiment of the present invention;

[0089] Fig.16 It is a diagram of acoustic emission ring count and absolute energy change of a fault structure sample provided by an embodiment of the present invention;

[0090] Fig.17 It is a graph of acoustic emission ring count and absolute energy variation of a conventional sample provided by an embodiment of the present invention;

[0091] Fig.18 It is a diagram of electromagnetic radiation energy and amplitude variation of a fault structure sample provided by an embodiment of the present invention;

[0092] Fig.19 It is a graph showing the change in electromagnetic radiation energy and amplitude of a conventional sample provided in an embodiment of the present invention. DETAILED DESCRIPTION

[0093] In order to make the purpose, technical solution and advantages of the present invention more clearly understood, the present invention is further described in detail below in conjunction with the embodiments. It should be understood that the specific embodiments described herein are only used to explain the present invention and are not used to limit the present invention.

[0094] The embodiment of the present invention provides a geological fault rock burst monitoring and early warning device to solve many problems in the prior art. Traditional rock pressure monitoring devices have many deficiencies in three-dimensional stress loading, shear disturbance, oil temperature control, and specimen preparation and transportation, resulting in inaccurate test results, poor system reliability, and complex operation. To this end, the present invention designs a monitoring device with strong comprehensiveness, high precision, and easy operation to improve the efficiency and accuracy of geological fault rock burst monitoring and early warning.

[0095] like Figure 3As shown, the true triaxial load loading system of the present invention realizes three-dimensional stress loading by setting loading cylinders in three directions: vertical, lateral and rear horizontal. A reaction frame is set in each direction to provide reaction force. When performing the loading test, the cylinders in three directions drive the pads to apply pressure to the test piece at the same time, thereby realizing the three-dimensional stress loading function. This design can accurately simulate the stress state of geological faults in the actual environment, significantly improving the authenticity and reliability of the test results.

[0096] like Figure 5 As shown in FIG. 1 , the shear loading disturbance system of the present invention includes a shear loading disturbance subsystem (ZL-3) arranged at the top and a vertical loading subsystem 1 (ZL-1). The two subsystems perform loading movements in the same direction while the other loading subsystems are under constant pressure, thereby realizing the shear loading disturbance of the system. By changing their positions, shear loads can be applied to the specimen to simulate the shear force during fault sliding. In addition, as Figure 6 As shown, the oil source and supercharger system consists of an oil tank, an oil pump-motor unit, a precision oil filter, etc., and a temperature control meter and a temperature sensor are provided to form an oil temperature protection system to ensure that the oil temperature in the servo oil source does not exceed 60°C, thereby improving the stability and safety of the system.

[0097] like Figure 8 As shown in the figure, the specimen production and transportation system consists of a cylinder and a forming mold, a servo oil source, a control system and a specimen trolley, which can quickly and accurately produce and transport specimens, improving the test efficiency and specimen consistency. Fig. 9 As shown, it includes a control cabinet, a hydraulic servo valve, a 6-channel automatic control system, a 16-channel data acquisition system and computer measurement and control software. The EDCi50 controller is used to analyze and collect data. The computer gives electrical signals to the actuator (servo valve) according to the instructions to realize the setting and loading of displacement and force control parameters. It is easy to operate and can synchronously draw the load-displacement curve.

[0098] The present invention solves the shortcomings of traditional geological fault rock burst monitoring and early warning devices in terms of stress loading and shear disturbance by designing an advanced true triaxial load loading system and a shear loading disturbance system. At the same time, the oil temperature protection design of the oil source and the booster system improves the stability and safety of the system. The automation and high-precision design of the specimen production and transportation system as well as the test control and data acquisition system significantly improve the efficiency of the test and the reliability of the results. Overall, the present invention provides an efficient, accurate, and easy-to-operate geological fault rock burst monitoring and early warning device, achieving significant technological progress.

[0099] The working principle of the geological fault rock burst monitoring and early warning device provided by the embodiment of the present invention can be divided into the following parts for detailed explanation:

[0100] 1) True triaxial loading system:

[0101] Loading principle: By setting loading cylinders in the vertical, lateral and rear horizontal directions, and setting reaction frames in the corresponding directions to provide reaction forces, three-way stress loading is achieved.

[0102] Working method: During the loading test, the oil cylinders in three directions simultaneously drive the pads to apply pressure to the specimen, thereby simulating the three mutually perpendicular stresses (radial stress, axial stress and circumferential stress) that the rock is subjected to under real geological conditions.

[0103] 2) Shear loading disturbance system:

[0104] System composition: It consists of the upper shear loading disturbance subsystem (ZL-3) and the vertical loading subsystem 1 (ZL-1).

[0105] Working principle: The two loading subsystems can perform loading movements in the same direction while ensuring the voltage stability of other subsystems to achieve shear loading disturbance of the system. By adjusting the position, shear load is applied to the specimen to simulate the stress change and shear effect of the fault when it is affected by mining.

[0106] 3) Oil source and supercharger system:

[0107] System composition: including oil tank, oil pump-motor unit, precision oil filter, overflow valve, liquid level gauge, pressure gauge, air filter, transducer and pipeline, etc.

[0108] Working principle: The oil pump runs continuously to provide power for the system, the precision oil filter ensures the cleanliness of the oil, the overflow valve adjusts the system pressure, and the level gauge and pressure gauge monitor the oil source status. The oil temperature protection system consists of a temperature control meter and a temperature sensor to ensure that the oil temperature does not exceed 60°C.

[0109] 4) Specimen preparation and transportation system:

[0110] System composition: It consists of oil cylinder and forming die, servo oil source, control system and sample trolley.

[0111] Working principle: Rock specimens that meet the experimental requirements are prepared through oil cylinders and forming molds. The servo oil source provides power, and the control system controls the specimen production process. The specimen trolley is used to transport the specimen to the test location.

[0112] 5) Test control and data acquisition system:

[0113] System composition: including control cabinet, hydraulic servo valve, 6-channel automatic control system, 16-channel data acquisition system, computer measurement and control software, etc.

[0114] Working principle: The controller (EDCi50) is responsible for data acquisition and analysis, transmits sensor data to the computer, and controls the actuator (servo valve) according to computer instructions. The measurement and control software realizes the setting and loading of displacement and force control parameters. Each loading subsystem can be controlled independently, which is convenient to operate. The system can synchronously draw load displacement curves to provide data support for analyzing the mechanical properties and deformation laws of rocks.

[0115] To sum up, the geological fault rock burst monitoring and early warning device of the embodiment of the present invention can simulate the stress state of rock under real geological conditions through the coordinated work of the true triaxial load loading system, the shear loading disturbance system, the oil source and booster system, the specimen preparation and transportation system, and the test control and data acquisition system, and monitor and analyze its mechanical properties and deformation laws, thereby providing a scientific basis for the monitoring and early warning of geological fault rock burst.

[0116] like Figure 1 As shown, a geological fault rock burst monitoring and early warning device provided by an embodiment of the present invention is composed of a true triaxial load loading system, a shear loading disturbance system, an oil source and a booster system, a specimen manufacturing and transportation system, and a test control and data acquisition system;

[0117] like Figure 3 As shown in the figure, the loading principle of the true triaxial load loading system is mainly to realize three-way stress loading. Loading cylinders are set in the vertical, lateral and rear horizontal directions, and reaction frames are set in the corresponding directions to provide reaction force. When carrying out the loading test, the vertical, lateral and rear horizontal cylinders drive the pads to apply pressure to the specimen at the same time, realizing the three-way stress loading function.

[0118] like Figure 5 As shown in the figure, the shear loading disturbance system is mainly composed of the shear loading disturbance subsystem (ZL-3) arranged at the top and the vertical loading subsystem 1 (ZL-1) which assists in cooperation. The two loading subsystems can perform loading movements in the same direction while ensuring the voltage stabilization of other loading subsystems, thereby realizing the shear loading disturbance of the system. The shear load of the specimen is realized by changing its position.

[0119] like Figure 6 As shown in the figure, the oil source and supercharger system consists of an oil tank, an oil pump-motor unit, a precision oil filter, a relief valve, a liquid level gauge, a pressure gauge, an air filter, a transducer, and pipelines. The oil pump generates heat during continuous operation, so a temperature control meter and a temperature sensor are set to form an oil temperature protection system to ensure that the oil temperature in the servo oil source does not exceed 60°C.

[0120] like Figure 8 As shown, the specimen production and transportation system is mainly composed of an oil cylinder and a forming die, a servo oil source, a control system and a specimen trolley.

[0121] like Fig. 9 As shown, the test control and data acquisition system mainly consists of a control cabinet ( Fig.10 ), hydraulic servo valve, 6-channel automatic control system, 16-channel data acquisition system, computer measurement and control software, etc.; the controller uses EDCi50 to analyze and collect data. The EDC controller transmits the data of each sensor to the computer, and gives electrical signals to the actuator (servo valve) according to the computer's instructions; the setting and loading of displacement and force control parameters can be realized in the measurement and control software; each loading subsystem can be completely independently controlled, the operation is very convenient, and the load-displacement curve can be drawn synchronously.

[0122] like Figure 4 As shown, the true triaxial load loading system provided by the embodiment of the present invention is composed of a vertical loading subsystem, a side horizontal loading subsystem, and a rear horizontal loading subsystem;

[0123] The shear loading disturbance system provided by the embodiment of the present invention includes ZL-3 and ZL-1. ZL-3 is arranged above the true triaxial loading system. Figure 3 As shown;

[0124] The oil source and booster system provided by the embodiment of the present invention comprises a hydraulic servo oil source ( Figure 7 ), supercharger, oil cooler;

[0125] The test piece production and transportation system provided in the embodiment of the present invention is composed of an oil cylinder, a forming mold, and a movable test piece trolley;

[0126] The test control and data acquisition system provided by the embodiment of the present invention is composed of a hydraulic servo valve, a control cabinet, and a computer acquisition system.

[0127] Furthermore, the geological fault rock burst pressure monitoring and early warning device is equipped with corresponding monitoring equipment, which includes an acoustic emission instrument ( Fig.11 )、Electromagnetic radiation meter( Fig.12 )、Infrared Thermal Imager( Fig.13 )、High-speed camera( Fig.14 ) and a miniature camera.

[0128] Furthermore, the vertical loading subsystem is located at the lower end of the true triaxial load loading system; the side horizontal loading subsystem is located on one side of the true triaxial load loading system, and a reaction frame is provided on the other side of the true triaxial load loading system; and the rear horizontal loading subsystem is located on the rear side of the true triaxial load loading system.

[0129] Furthermore, the vertical loading subsystem includes ZL-1 and ZL-2, which are fixed on the same base; the side horizontal loading subsystem includes YL-1 and YL-2, which are fixed on the same base; the rear horizontal loading subsystem is located at the rear side of the true triaxial load loading system, including XL-1.

[0130] Furthermore, ZL-1, ZL-2, YL-1, YL-2 and XL-1 are all provided with a loading plate.

[0131] The device provided in the embodiment of the present invention can innovatively carry out relevant experiments on the dynamic evolution mechanism of rock burst disasters under the effect of geological structure (fault) by using a shear loading disturbance system.

[0132] Device composition and connection relationship:

[0133] 1) True triaxial loading system:

[0134] Vertical loading subsystem: installed on the top of the device, used to apply vertical loads.

[0135] Side horizontal loading subsystem: installed on the side of the device, used to apply horizontal loads.

[0136] Rear horizontal loading subsystem: installed at the rear of the device, used to apply horizontal load in another direction.

[0137] 2) Shear loading disturbance system:

[0138] Shear loader (ZL-3): Installed above the true triaxial loading system, used to apply shear loads to simulate fault shear disturbances.

[0139] 3) Oil source and supercharger system:

[0140] Hydraulic servo oil source: provides the pressure oil required by the hydraulic system.

[0141] Intensifier: Increases the pressure in the hydraulic system to meet the needs of high-pressure loads.

[0142] Oil cooler: cools the hydraulic oil to prevent the system from overheating and ensures stable operation of the system.

[0143] 4) Specimen preparation and transportation system:

[0144] Oil cylinder and forming mold: used to make test pieces. The mold is fixed in the oil cylinder and formed by the pressure of the cylinder.

[0145] Movable specimen trolley: used to transport the manufactured specimens from the forming area to the true triaxial load loading system for testing.

[0146] 5) Test control and data acquisition system:

[0147] Hydraulic servo valve: controls the flow of hydraulic oil and accurately adjusts the load.

[0148] Control cabinet: Contains control devices and electrical components used to control the operation of the entire system.

[0149] Computer acquisition system:

[0150] like Fig.15 As shown, a geological fault rock burst pressure monitoring and early warning method of a geological fault rock burst pressure monitoring and early warning device provided by an embodiment of the present invention comprises the following steps:

[0151] Step 1: Arrange a ground sound monitoring system in the tunnel to obtain ground sound monitoring data, determine the ground sound frequency, the time point with abnormally high concentration, and conduct spatiotemporal data field analysis;

[0152] Step 2: Use the high-speed camera acquisition system, acoustic emission instrument and electromagnetic radiation instrument equipped in the monitoring system to supplement and improve the monitoring of the fault;

[0153] Step 3, shearing the test specimen using the shear loading disturbance system marked on the equipment;

[0154] Step 4: After obtaining the geological fault, use the system to conduct experiments.

[0155] Furthermore, in step one, the test specimen is sheared: the ZL-2 cylinder is locked, and ZL-1 and ZL-3 move in the same direction.

[0156] In order to study the destruction characteristics and energy release laws of rock burst in the tunnel under fault geological structure conditions, the test process was monitored in real time using the independently developed test system with the help of monitoring equipment such as micro cameras, acoustic emission instruments and electromagnetic radiation instruments. Impact destruction tests of fault structure specimens and conventional specimens under true three-dimensional conditions were carried out, and the influence of fault geological structure on the destruction characteristics of tunnel surrounding rocks and the energy evolution characteristics of acoustic emission and electromagnetic radiation were compared and analyzed. The test results show that the existence of fault structure makes the roadway more severely damaged and the impact damage occurs in a shorter time. Although the ring count of the fault structure specimen accounts for a larger proportion in the overall damage period, the maximum ring count, cumulative ring count and cumulative absolute energy of the conventional specimen are all greater than those of the fault structure specimen. Its cumulative ring count is 1.4 times that of the fault specimen, and its cumulative absolute energy is 2.0 times that of the fault specimen, indicating that the fault geological structure reduces the intensity of the impact rock pressure energy release. Due to the existence of fault geological structure, the specimens are more likely to rub against each other under the impact load, thus generating more charges. The electromagnetic radiation phenomenon of the fault specimen is more active than that of the conventional specimen, and its maximum electromagnetic radiation energy and amplitude are 1.6 times and 2.2 times that of the conventional specimen respectively. The existence of fault structure makes it easier for the specimen to rupture and impact damage to occur. It is difficult to accumulate high energy inside the specimen, so the energy released when the impact damage occurs is smaller than that when there is no fault structure. The test results provide theoretical guidance for the anti-impact design when there is a fault geological structure on the engineering site.

[0157] The acoustic emission ring count and absolute energy change of the fault structure sample provided by the embodiment of the present invention are as follows: Fig.16 As shown; the acoustic emission ring count and absolute energy changes of conventional samples are shown as Fig.17 As shown. In the calm period, as the load increases, there is no fluctuation in the ring count and absolute energy, and the acoustic emission ring count curve and absolute energy curve are relatively gentle, mainly because the specimen itself has a certain pressure bearing capacity. In the initial rupture period, as the load continues to increase, particle ejection and block peeling occur in the specimen tunnel, and cracks begin to appear on the tunnel wall. At this time, the acoustic emission ring count and absolute energy both increase. The energy change law of the fault structure specimen and the conventional specimen is similar in the first two stages.

[0158] During the period of total destruction, large-scale particle ejection and large-block peeling and protrusion occurred in the sample tunnel, and many cracks appeared on the tunnel wall and interpenetrated each other. The acoustic emission ring count and absolute energy surged and reached the maximum value. The absolute energy of the fault structure sample has been maintained near the maximum value. The absolute energy of the conventional sample dropped sharply during the destruction period, and then quickly reached the extreme value, indicating that the conventional sample has a short stable period after the initial energy release. The rupture period of the fault structure sample is shorter than that of the conventional sample. The former enters the period of total destruction earlier, which indicates that the bearing capacity of the fault structure sample is lower. The existence of the fault reduces the overall stability of the specimen and makes it more prone to destruction; and the acoustic emission ring count of the fault structure sample is less than that of the conventional sample, indicating that although the existence of the fault makes the specimen more prone to impact damage, it also reduces its ability to accumulate energy.

[0159] The electromagnetic radiation energy and amplitude changes of the fault structure sample provided by the embodiment of the present invention are as follows: Fig.18 As shown; the electromagnetic radiation energy and amplitude changes of conventional samples are as follows Fig.19 As shown in the figure, during the quiet period, as the load increases, the inside of the tunnel of the sample remains intact and no cracks appear, and the electromagnetic radiation energy and amplitude curves do not change significantly, indicating that no rupture occurs inside the sample at this time, but this stage lasts for a short time.

[0160] As the load continues to increase, the specimen enters the rupture stage, small-scale particle ejection and small-block peeling begin to occur in the tunnel, and cracks begin to appear on the tunnel wall. At this time, the specimen tunnel has already cracked, and the electromagnetic radiation energy and amplitude begin to fluctuate significantly.

[0161] As the load continued to increase, a large range of comprehensive damage occurred in the tunnel, through cracks appeared on the wall, and the entire tunnel collapsed and deformed. As a large number of cracks appeared inside the specimen, the friction between the tunnel wall and the inside of the specimen released electromagnetic radiation signals outward. During this period, the electromagnetic radiation energy and amplitude curves showed obvious fluctuations; at the same time, the energy and amplitude fluctuations of the electromagnetic radiation of the fault structure specimen were greater than those of the conventional specimen, indicating that the existence of the fault geological structure caused the specimen to rupture to a greater extent.

[0162] The above description is only a specific implementation mode of the present invention, but the protection scope of the present invention is not limited thereto. Any modifications, equivalent substitutions and improvements made by any technician familiar with the technical field within the technical scope disclosed by the present invention and within the spirit and principle of the present invention should be covered by the protection scope of the present invention.

Claims

1. A geological fault rock burst monitoring and early warning device, characterized in that: It consists of a true triaxial load loading system, a shear loading disturbance system, an oil source and supercharger system, a specimen manufacturing and transportation system, and a test control and data acquisition system; The true triaxial load loading system is provided with loading cylinders in the vertical, lateral and rear horizontal directions, and reaction frames are provided in the corresponding directions to provide reaction forces; when carrying out the loading test, the vertical, lateral and rear horizontal cylinders drive the pads to apply pressure to the specimen at the same time, realizing the three-way stress loading function; The shear loading disturbance system is composed of a shear loading disturbance subsystem arranged at the top and a vertical loading subsystem that assists and cooperates with it; The oil source and supercharger system is composed of an oil tank, an oil pump-motor unit, a precision oil filter, a relief valve, a liquid level gauge, a pressure gauge, an air filter, an energy converter and pipelines; The test piece production and transportation system is composed of an oil cylinder and a forming die, a servo oil source, a control system and a test piece trolley; The test control and data acquisition system consists of a control cabinet, a hydraulic servo valve, a 6-channel automatic control system, a 16-channel data acquisition system, and computer measurement and control software.

2. The geological fault rock burst monitoring and early warning device according to claim 1, characterized in that: The true triaxial load loading system consists of a vertical loading subsystem, a side horizontal loading subsystem, and a rear horizontal loading subsystem; The shear loading disturbance system includes ZL-3 and ZL-1. ZL-3 is set above the true triaxial load loading system. The oil source and supercharger system consists of a hydraulic servo oil source, a supercharger, and an oil cooler. The specimen production and transportation system consists of a cylinder, a forming die, and a movable specimen trolley; The test control and data acquisition system consists of hydraulic servo valve, control cabinet and computer acquisition system.

3. The geological fault rock burst monitoring and early warning device according to claim 1, characterized in that: The two loading subsystems of the shear loading disturbance system perform unidirectional loading movements while ensuring the voltage stability of other loading subsystems to achieve the shear loading disturbance of the system; the shear load of the specimen is achieved by changing the position.

4. The geological fault rock burst monitoring and early warning device according to claim 1, characterized in that: The oil source and supercharger system is also equipped with a temperature control meter and a temperature sensor to form an oil temperature protection system to ensure that the oil temperature in the servo oil source does not exceed 60°C.

5. The geological fault rock burst monitoring and early warning device according to claim 1, characterized in that: The controller of the test control and data acquisition system uses EDCi50 to analyze and collect data. The EDC controller transmits the data of each sensor to the computer and gives electrical signals to the actuator (servo valve) according to the computer's instructions; the setting and loading of displacement and force control parameters are realized in the measurement and control software; each loading subsystem is completely independently controlled and can synchronously draw the load-displacement curve.

6. The geological fault rock burst monitoring and early warning device according to claim 1, characterized in that: The geological fault rock burst monitoring and early warning device is equipped with corresponding monitoring equipment, which includes a ground sound monitoring system, an acoustic emission instrument, an electromagnetic radiation instrument, an infrared thermal imager, a high-speed camera and a micro camera.

7. The geological fault rock burst monitoring and early warning device according to claim 1, characterized in that: The vertical loading subsystem is located at the lower end of the true triaxial load loading system; the side horizontal loading subsystem is located on one side of the true triaxial load loading system, and a reaction frame is arranged on the other side of the true triaxial load loading system; the rear horizontal loading subsystem is located at the rear side of the true triaxial load loading system.

8. The geological fault rock burst monitoring and early warning device according to claim 1, characterized in that: The vertical loading subsystem includes ZL-1 and ZL-2, which are fixed on the same base; the side horizontal loading subsystem includes YL-1 and YL-2, which are fixed on the same base; the rear horizontal loading subsystem is located at the rear side of the true triaxial load loading system, including XL-1; loading plates are set on ZL-1, ZL-2, YL-1, YL-2 and XL-1.

9. A geological fault rock burst pressure monitoring and early warning method of the geological fault rock burst pressure monitoring and early warning device according to any one of claims 1 to 8, characterized in that: The following steps are involved: Step 1: Arrange a ground sound monitoring system in the tunnel to obtain ground sound monitoring data, determine the ground sound frequency, the time point with abnormally high concentration, and conduct spatiotemporal data field analysis; Step 2: Use the high-speed camera acquisition system, acoustic emission instrument and electromagnetic radiation instrument equipped in the monitoring system to supplement and improve the monitoring of the fault; Step 3, shearing the test specimen using the shear loading disturbance system marked on the equipment; Step 4: After obtaining the geological fault, use the system to conduct experiments.

10. The method for monitoring and early warning of geological fault rock burst pressure according to claim 9, characterized in that: The test specimen is sheared in step 1: the ZL-2 cylinder is locked, and ZL-1 and ZL-3 move in the same direction.

Citation Information

Cited By

  • Rock friction sliding instability simulation test system and test device

    CN121384780A

  • Multi-parameter dynamic collaborative early warning method and system for engineering rock mass instability failure under unloading condition

    CN122618790A

  • Multi-parameter dynamic cooperative early warning method and system for instability and failure of engineering rock mass under unloading condition

    CN122618790B