Data center planning method, device, equipment, medium and program product
By obtaining candidate business information and the remaining resources of the target data center, the resource gap information prediction model is used to determine the start-up construction time of the data center, which solves the problem of insufficient comprehensive planning of the data center in the central and western regions of the existing technology and improves the reliability of the planning results. and construction guidance value.
Patent Information
- Application Number
- CN202410391020.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-04-02
- Publication Date
- 2024-10-18
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
In the process of promoting the migration and deployment of data processing services to the west, the existing technology does not consider comprehensive factors when planning the western data center. As a result, the planning results are not comprehensive enough, and the reference value for the construction of the western data center is not high.
By obtaining the candidate business information and the remaining resources of the target data center, and using the resource gap information prediction model, the time when the remaining resources of the target data center first appear in short supply in the preset data service cycle is determined as the start-up construction time of the new data center, improving The information richness and construction guidance value of data center planning results.
It improves the reliability and guidance value of data center planning results, ensures that the construction of new data centers is more reasonable and targeted, and avoids waste of resources.
Smart Images

Figure CN118798668A_ABST
Abstract
Description
Technical Field
[0001] The present disclosure relates to the field of information technology, and in particular to a data center planning method, device, equipment, medium and program product. Background Art
[0003] In the relevant technologies, various regions or relevant enterprises actively promote the migration and deployment of data processing businesses to the west; among them, in the process of promoting the migration and deployment of data processing businesses to the west, each enterprise usually needs to determine which businesses are suitable for deployment in the west, as well as determine a reasonable scale of construction of western data centers, etc., in order to carry out western data center planning.
[0004] However, in the related technologies, in the process of planning the western data center, there is usually a problem of insufficient consideration of factors, resulting in incomplete data center planning results and low reference value for the construction of the western data center. Summary of the invention
[0005] The present disclosure provides a data center planning method, device, equipment, medium and program product, so that the data center planning results have more reliable guiding value for data center construction. The technical solution of the present disclosure is as follows:
[0006] According to a first aspect of the present disclosure, a data center planning method is provided, comprising:
[0007] Acquire candidate service information and the remaining resources of the target data center, wherein the candidate service information includes the newly added resources per unit time of each candidate service in a preset data service cycle;
[0008] If a resource gap information prediction model is input based on the remaining resources of the target data center and the newly added resources per unit time of each candidate business in the preset data service cycle, and it is determined that there is a first target unit time in the preset data service cycle, then the preset time before the first target unit time is determined as the start construction time of the new data center, wherein, in the preset data service cycle, the remaining resources of the target data center at the first target unit time are, for the first time, less than the total amount of newly added resources of the candidate business at the first target unit time.
[0009] According to a second aspect of the present disclosure, there is provided a data center planning device, comprising:
[0010] An acquisition module is configured to acquire candidate service information and the remaining resources of the target data center, wherein the candidate service information includes the newly added resources per unit time of each candidate service in a preset data service cycle;
[0011] The determination module is configured to input a resource gap information prediction model based on the remaining resources of the target data center and the newly added resources per unit time of each candidate business in the preset data service cycle, and determine that there is a first target unit time in the preset data service cycle, then determine the preset time before the first target unit time as the start construction time of the new data center, wherein, in the preset data service cycle, the remaining resources of the target data center at the first target unit time is, for the first time, less than the total amount of newly added resources of the candidate business at the first target unit time.
[0012] According to a third aspect of the present disclosure, there is provided an electronic device, including:
[0013] Processor; and
[0014] Memory for storing programs,
[0015] The program includes instructions, which, when executed by the processor, cause the processor to execute the method as described in the first aspect.
[0016] According to a fourth aspect of the present disclosure, a non-transitory computer-readable storage medium storing computer instructions is provided, wherein the computer instructions are used to cause the computer to execute the method as described in the first aspect.
[0017] According to a fifth aspect of the present disclosure, a computer program product is provided, comprising a computer program, wherein the computer program implements the method as described in the first aspect when executed by a processor.
[0018] The data center planning method, apparatus, equipment, medium and program product provided by the present invention can determine the time when the remaining resources of the target data center first become short of in the preset data service cycle based on the remaining resources of the target data center, the newly added resources of the candidate services per unit time in the preset data service cycle, and the resource gap information prediction model, and determine the time when the remaining resources of the target data center first become short of as the start-up construction time of the new data center, which not only improves the richness of information in the determined data center planning results, but also makes the data center planning results have more reliable guiding value for data center construction, so as to guide more reasonable planning and commissioning of new data centers. BRIEF DESCRIPTION OF THE DRAWINGS
[0019] Further details, features and advantages of the present disclosure are disclosed in the following description of exemplary embodiments in conjunction with the accompanying drawings, in which:
[0020] Figure 1 A schematic diagram showing an implementation scenario of a data center planning solution of an exemplary embodiment of the present disclosure is shown;
[0021] Figure 2 A flow chart showing a data center planning method according to an exemplary embodiment of the present disclosure is shown;
[0022] Figure 3 A flowchart showing another data center planning method according to an exemplary embodiment of the present disclosure is shown;
[0023] Figure 4 A schematic block diagram of a data center planning device according to an exemplary embodiment of the present disclosure is shown;
[0024] Figure 5 A schematic block diagram of a chip according to an exemplary embodiment of the present disclosure is shown;
[0025] Figure 6 A structural block diagram of an exemplary electronic device that can be used to implement the embodiments of the present disclosure is shown. DETAILED DESCRIPTION
[0026] Embodiments of the present disclosure will be described in more detail below with reference to the accompanying drawings. Although certain embodiments of the present disclosure are shown in the accompanying drawings, it should be understood that the present disclosure can be implemented in various forms and should not be construed as being limited to the embodiments described herein, which are instead provided for a more thorough and complete understanding of the present disclosure. It should be understood that the drawings and embodiments of the present disclosure are only for exemplary purposes and are not intended to limit the scope of protection of the present disclosure.
[0027] It should be understood that the various steps described in the method embodiments of the present disclosure may be performed in different orders and / or in parallel. In addition, the method embodiments may include additional steps and / or omit the steps shown. The scope of the present disclosure is not limited in this respect.
[0028] The term "including" and its variations used in this document are open inclusions, that is, "including but not limited to". The term "based on" means "based at least in part on". The term "one embodiment" means "at least one embodiment"; the term "another embodiment" means "at least one other embodiment"; the term "some embodiments" means "at least some embodiments". Relevant definitions of other terms will be given in the description below. It should be noted that the concepts of "first", "second", etc. mentioned in this disclosure are only used to distinguish different devices, modules or units, and are not used to limit the order or interdependence of the functions performed by these devices, modules or units.
[0029] It should be noted that the modifications of "one" and "plurality" mentioned in the present disclosure are illustrative rather than restrictive, and those skilled in the art should understand that unless otherwise clearly indicated in the context, it should be understood as "one or more".
[0030] The names of the messages or information exchanged between multiple devices in the embodiments of the present disclosure are only used for illustrative purposes and are not used to limit the scope of these messages or information.
[0031] In the related technologies, in the process of promoting the migration and deployment of data processing services to the west, each enterprise usually needs to determine which services are suitable for deployment in the west, as well as determine a reasonable scale of construction of western data centers, etc., in order to carry out western data center planning.
[0032] However, in the related art, during the planning process of the western data center, what is usually considered is the remaining resources (such as wireless equipment and / or transmission equipment, etc.) in the computer room where the data center is to be relocated and the remaining supporting facilities (such as power supply equipment and command equipment). As a result, the planning results of the data center are not comprehensive and have low reference value for the construction of the western data center.
[0033] In order to solve the above problems, the present disclosure provides a data center planning solution. Figure 1 FIG. 1 shows a schematic diagram of an implementation scenario of a data center planning solution provided by an exemplary embodiment of the present disclosure. Figure 1 As shown, the implementation scenario 100 includes a server 101 and a user device 102; wherein the server 101 may be a server deployed by a service provider that provides data center planning services, and the user device 102 may be a user terminal of a demander of data center planning services, wherein the user terminal may be a computer, notebook, mobile phone, tablet or wearable device, etc.
[0034] like Figure 1 As shown, when executing the data center planning solution provided by the embodiment of the present disclosure, a wireless or wired link can be established between the above-mentioned server 101 and the user device 102 to implement the data center planning method provided by the embodiment of the present disclosure.
[0035] Figure 2 A flow chart of a data center planning method according to an exemplary embodiment of the present disclosure is shown. The method can be applied to a server, such as Figure 2 As shown, the method of the embodiment of the present disclosure may include:
[0036] Step S201, obtaining candidate service information and remaining resources of a target data center;
[0037] The candidate service information includes the amount of newly added resources per unit time for each candidate service in a preset data service cycle;
[0038] Step S202: if the resource gap information prediction model is input based on the remaining resources of the target data center and the newly added resources per unit time of each candidate service in the preset data service cycle, and it is determined that there is a first target unit time in the preset data service cycle, then the preset time before the first target unit time is determined as the start construction time of the new data center;
[0039] In the preset data service cycle, the remaining resources of the target data center at the first target unit time are, for the first time, less than the total amount of new resources of the candidate service at the first target unit time;
[0040] In summary, the data center planning method provided by the embodiment of the present disclosure can obtain candidate business information and the remaining resources of the target data center. If a resource gap information prediction model is input based on the remaining resources of the target data center and the newly added resources per unit time of each candidate business in the preset data service cycle, and it is determined that there is a first target unit time in the preset data service cycle, then the preset time before the first target unit time is determined as the start construction time of the new data center; based on the remaining resources of the target data center, the newly added resources per unit time of the candidate business in the preset data service cycle, and the resource gap information prediction model, it can be determined that in the preset data service cycle, the time when the remaining resources of the target data center are first short of, and the time when the remaining resources of the target data center are first short of is determined as the start construction time of the new data center, which not only improves the richness of information in the determined data center planning results, but also makes the data center planning results have more reliable guiding value for data center construction, so as to guide more reasonable planning and commissioning of new data centers.
[0041] The following Figure 2 The specific implementation methods of each step in the embodiment shown are described in detail:
[0042] In step S201, the server may obtain candidate service information and remaining resources of a target data center.
[0043] In the disclosed embodiment, the candidate service is a service provided by a data service provider, the target data center is a data center determined by the data server to be the service migration location, and the candidate service information includes the amount of new resources per unit time for each candidate service in a preset data service cycle, wherein the preset data service cycle is a time period during which the target data center needs to provide service services remotely, and the preset data service cycle can be determined based on actual needs, and the disclosed embodiment does not limit this, for example, the preset data service cycle can be ten or twenty years after the current year, etc. Among them, the duration of the unit time can also be determined based on actual needs, and the disclosed embodiment does not limit this, for example, the duration of the unit time can be half a year, one year, or two years, etc.
[0044] The remaining resources of the target data center may be the remaining resources of all the resources of the target data center when the data center is planned, excluding the resources required to meet local business service needs, wherein the resources may be at least one of the number of racks and external mains power capacity.
[0045] In an optional implementation, the process of the server acquiring candidate service information and the remaining resources of the target data center may include: receiving a data center planning request sent by a user terminal, parsing the candidate service information and the remaining resources of the target data center in the data center planning request; or, in response to detecting a data center planning instruction, searching the data center planning information table for the remaining resources of the target data center corresponding to the data center identifier carried in the data center planning instruction, and searching for the candidate service information associated with the target data center to obtain the candidate service information and the remaining resources of the target data center. The data center planning information table of the server may store the remaining resources of multiple data information, as well as the candidate service information associated with each data center.
[0046] In an optional implementation, the candidate service information also includes service attribute information of multiple candidate services. After obtaining the candidate service information and the remaining resources of the target data center, the server may further: based on the service attribute information of each candidate service and the migratable service screening strategy, screen at least one target service from multiple candidate services. After obtaining the candidate service information, based on the migratable service screening strategy, the candidate service that meets the migration conditions may be determined as the target service to ensure that the service after migration is not affected and to ensure the data service reliability of the service provider.
[0047] It should be noted that, in the embodiment of the present disclosure, the service attribute information includes at least one of service transmission delay, service access type and service service location information, wherein the service access type may include real-time access type services and non-real-time access type services, and the service service location information may include services that can be served remotely or services that cannot be served remotely; wherein, the migratable service screening strategy may be determined based on actual needs, and the embodiment of the present disclosure does not limit this. For example, the migratable service screening strategy may include that a candidate service whose service access type is a non-real-time access type service is a migratable service; or, the migratable service screening strategy may include that a candidate service whose service transmission delay is greater than a preset threshold is a migratable service; or, the migratable service screening strategy may include that the service service location information of the service indicates that the candidate service is a service that can be served remotely as a migratable service; or, the migratable service screening strategy may include that the service transmission delay is greater than a preset threshold, and the service service location information of the service indicates that the candidate service is a service that can be served remotely as a migratable service, etc.
[0048] In an optional implementation, when the service attribute information includes service transmission delay, service access type, and service service location information, the server may select at least one target service from multiple candidate services based on the service attribute information of each candidate service and the migratable service screening strategy. The process may include: for each candidate service, if the service transmission delay of the candidate service is greater than a preset threshold, or the service access type of the candidate service is a non-real-time access service, or the service service location information of the candidate service indicates that it is a remote service service, then the candidate service is determined as the target service; wherein the preset threshold may be determined based on actual needs, and the embodiments of the present disclosure do not limit this. It is possible to determine whether a candidate service is a migratable service from three dimensions: service transmission delay, service access type, and service service location information of the candidate service, so as to improve the matching degree between the determined migratable service and the actual service demand, so as to improve the service reliability after the service migration.
[0049] In an optional embodiment, when the service attribute information includes service transmission delay, service access type and service service location information, the server may select at least one target service from multiple candidate services based on the service attribute information of each candidate service and the migratable service screening strategy, and the process may include: for each candidate service, if the service transmission delay of the candidate service is greater than a preset threshold, and the service access type of the candidate service is a non-real-time access service, and the service service location information of the candidate service indicates that it is a remote service service, then the candidate service is determined as the target service; when the three dimensions of service transmission delay, service access type and service service location information of the candidate service meet the migration conditions, the candidate service may be determined to be a migratable service, and when there are high requirements for the service service, the match between the determined migration and the actual demand may be improved, so as to further improve the service reliability after the service migration.
[0050] In step S202, if the server inputs the resource gap information prediction model based on the remaining resources of the target data center and the newly added resources per unit time of each candidate business in the preset data service cycle, and determines that there is a first target unit time in the preset data service cycle, then the preset duration before the first target unit time is determined as the start construction time of the new data center.
[0051] In an embodiment of the present disclosure, in a preset data service cycle, the remaining resources of the target data center at the first target unit time are, for the first time, less than the total amount of new resources of the candidate services at the first target unit time. That is, from the first target unit time, a gap has first appeared in the remaining resources of the target data center and will be unable to meet the demand for new resources of the candidate services.
[0052] It can be understood that in the embodiment of the present disclosure, if the server screens candidate services based on the migratable service screening strategy, then when the server determines whether there is a first target unit time in the preset data service cycle, the processing object can be the amount of new resources per unit time for each target service in the preset data service cycle.
[0053] In an optional implementation, the remaining resource amount is the remaining number of racks, the newly added resource amount is the newly added number of racks, and the resource gap information prediction model is the rack gap information prediction model. The server inputs the resource gap information prediction model based on the remaining resource amount of the target data center and the newly added resource amount of each candidate service per unit time in the preset data service cycle. The process of determining whether there is a first target unit time in the preset data service cycle may include: starting from the first unit time in the preset data service cycle, repeatedly determining the difference between the remaining number of racks of the target data center in the previous unit time and the total number of newly added racks in the current unit time to obtain the remaining number of racks of the target data center in the current unit time, and when the remaining number of racks of the target data center is negative for the first time, determining the current unit time as the first target unit time, wherein the total number of newly added racks can be the sum of the number of newly added racks for each target service. The number of remaining racks in the target data center and the number of newly added racks for each candidate business per unit time can be used to determine the time when a data center first encounters a rack resource shortage in a preset data service cycle from the rack dimension in the data center, thereby improving the reliability of determining the time when a shortage of remaining resources in the target data center first occurs.
[0054] Among them, the rack gap information prediction model:
[0055] J n =J n-1 -∑R n ; (Formula 1)
[0056] In Formula 1, J n is the number of remaining racks in the target data center in the preset data service cycle, the nth unit time, J n-1 R is the number of remaining racks in the target data center in the preset data service cycle, the n-1th unit time; n The sum of the newly added resources for each target service in the nth unit time, ∑R n It is the total number of newly added racks for each target business in the nth unit time; it can be understood that J0 is the initial remaining number of racks in the data center in the initial year of planning.
[0057] In an optional implementation, the remaining resource amount is the remaining external power capacity, the newly added resource amount is the average power consumption of a single newly added rack, and the resource gap information prediction model is the external power capacity gap information prediction model. The server inputs the resource gap information prediction model based on the remaining resource amount of the target data center and the newly added resource amount of each candidate service per unit time in the preset data service cycle. The process of determining whether there is a first target unit time in the preset data service cycle may include: starting from the first unit time in the preset data service cycle, repeatedly determining the difference between the remaining external power capacity of the target data center in the previous unit time and the total power consumption of the newly added racks in the current unit time to obtain the remaining external power capacity of the target data center in the current unit time; and when the remaining external power capacity of the target data center is negative for the first time, the current unit time is determined as the first target unit time, wherein the total power consumption of the newly added racks is the product of the total number of newly added racks, the average power consumption of a single newly added rack, and the preset power utilization rate of a single rack. The remaining external power capacity of the target data center and the total power consumption of the newly added racks of each candidate business per unit time can be used to determine the time when a data center will first experience a rack resource shortage during a preset data service cycle from the dimension of the external power capacity of the data center. This further improves the reliability of determining the time when a shortage of remaining resources in the target data center will first occur.
[0058] Among them, the external power capacity gap information prediction model can be:
[0059] W n =W n-1 -∑R n *P n *PUE; (Formula 2)
[0060] In Formula 2, W n is the remaining external power capacity of the target data center in the preset data service cycle, the nth unit time, W n-1 P is the remaining external power capacity of the target data center in the preset data service cycle, the n-1th unit time; n is the average power consumption of a single newly added rack in the nth unit time in the preset data service cycle, and PUE is the preset power utilization rate of a single rack; it can be understood that J0 is the initial remaining external power capacity of the data center in the initial year of planning.
[0061] It should be noted that in the embodiment of the present disclosure, if the server does not screen the candidate services based on the migratable service screening policy, the server determines whether there is a first target unit time in the preset data service cycle, and the processing object can be the amount of newly added resources per unit time for each candidate service in the preset data service cycle. The total number of newly added racks can be the sum of the number of newly added racks for each candidate service.
[0062] In an optional implementation, if the server determines that there is a first target unit time in the preset data service cycle, the preset duration before the first target unit time can be determined as the start construction time of the new data center, wherein the preset duration can be the construction period of the data center, which can be specifically determined based on actual needs, and the present disclosed embodiment does not limit this.
[0063] For example, assuming that the preset data service cycle is M years after the current year, and assuming that a resource gap occurs in the Kth year of the preset data service cycle, the two years before the Kth year can be planned as the start of construction of the new data center; it can be understood that the service cycle of the new data center can be from the Kth year to the Mth year.
[0064] In the disclosed embodiment, when the server base determines that the preset data service cycle has a first target unit time through a rack gap information prediction model and / or an external power capacity gap information prediction model, the construction area of the new data center can be planned.
[0065] In an optional implementation, when the server determines that there is a first target unit time through the rack gap information prediction model, the server can also: determine the absolute value of the number of remaining racks of the target data center in the first target unit time, and the sum of the number of newly added racks of each target business in each second target unit time, to obtain the total number of racks of the new data center; then, determine the number of racks of each power density in the total number of racks of the new data center, and the product of the floor area of a single rack associated with each power density rack, to obtain the planned construction area associated with each power density rack; and determine the sum of the planned construction area associated with each power density rack as the planned construction total area of the new data center. Wherein, the second target unit time is the unit time after the first target unit time in the preset data service cycle; when it is determined that there is a rack gap in the preset data service cycle, the total planned construction area that better meets the service needs can be determined for the new data center in combination with the number of racks of different power densities in the total number of racks in the new data center, and the floor area of single racks of different power densities, to prevent waste of resources.
[0066] It should be noted that in the embodiment of the present disclosure, the number of racks of each power density in the total number of racks of the newly built data center, and the single rack floor space associated with each power density rack can be determined based on actual needs, and the embodiment of the present disclosure does not limit this.
[0067] For example, if the racks with different power densities are low power density (e.g., single rack power is 3-5KW / rack) R1 rack, medium power density (e.g., 5KW / rack < single rack power ≤ 10KW / rack) R2 rack, and high power density (e.g., single rack power is 10-15KW / rack) R3 rack, the single rack area of low power density rack is S1, the single rack area of low power density rack is S2, and the single rack area of high power density rack is S3, then the total planned construction area S of the new data center is:
[0068] S=(R1*S1+R2*S2+R3*S3); (Formula 3)
[0069] It should be noted that in the embodiments of the present disclosure, when the first target unit time determined by the server through the rack gap information prediction model is earlier than the first target unit time determined by the external power capacity gap information prediction model, the server may also determine the total planned construction area of the new data center based on the solution provided in the above embodiments.
[0070] For example, the present disclosure provides a data center planning method, such as Figure 3 As shown, data center planning methods may include:
[0071] Step S301, obtaining candidate service information and remaining resources of a target data center;
[0072] Step S302, based on the service attribute information of each candidate service and the migratable service screening strategy, screening at least one target service from multiple candidate services;
[0073] Step S303, based on the remaining resources of the target data center and the newly added resources per unit time of each candidate service in the preset data service cycle, input the rack gap information prediction model to determine whether there is a first target unit time in the preset data service cycle;
[0074] Step S304: if it does not exist, then end the data center planning process;
[0075] It is understandable that when it is determined that the first target unit time does not exist in the preset data service cycle, the server can generate a prompt message to prompt that the remaining resources of the target data center can meet the service requirements of the candidate business without building a new data center.
[0076] Step S305: If it exists, the preset time before the first target unit time is determined as the start construction time of the new data center.
[0077] Step S306, determining the absolute value of the number of remaining racks of the target data center in the first target unit time, and the sum of the number of newly added racks of each target service in each second target unit time, to obtain the total number of racks of the newly built data center;
[0078] Step S307, determine the number of racks of each power density in the total number of racks of the new data center, and the product of the single rack floor space associated with each power density rack, to obtain the planned construction area associated with each power density rack, and determine the sum of the planned construction areas associated with each power density rack as the total planned construction area of the new data center.
[0079] The above mainly introduces the solution provided by the embodiment of the present disclosure from the perspective of the server. It is understandable that, in order to implement the above functions, the server includes hardware structures and / or software modules corresponding to the execution of each function. Those skilled in the art should easily realize that, in combination with the units and algorithm steps of each example described in the embodiments disclosed herein, the present disclosure can be implemented in the form of hardware or a combination of hardware and computer software. Whether a function is executed in the form of hardware or computer software driving hardware depends on the specific application and design constraints of the technical solution. Professional and technical personnel can use different methods to implement the described functions for each specific application, but such implementation should not be considered to exceed the scope of the present disclosure.
[0080] The embodiments of the present disclosure may divide the server into functional units according to the above method examples. For example, each functional module may be divided corresponding to each function, or two or more functions may be integrated into one processing module. The above integrated modules may be implemented in the form of hardware or in the form of software functional modules. It should be noted that the division of modules in the embodiments of the present disclosure is schematic and is only a logical functional division. There may be other division methods in actual implementation.
[0081] In the case of dividing each functional module according to each function, an exemplary embodiment of the present disclosure provides a data center planning device, which may be a server or a chip applied to a server. Figure 4 FIG. 1 shows a schematic block diagram of functional modules of a data center planning device according to an exemplary embodiment of the present disclosure. Figure 4 As shown, the data center planning device 400 includes:
[0082] The acquisition module 401 is configured to acquire candidate service information and the remaining resources of the target data center, wherein the candidate service information includes the newly added resources per unit time of each candidate service in a preset data service cycle;
[0083] Determination module 402 is configured to input a resource gap information prediction model based on the remaining resources of the target data center and the newly added resources of each candidate business per unit time in the preset data service cycle, and determine that there is a first target unit time in the preset data service cycle, then determine the preset time before the first target unit time as the start construction time of the new data center, wherein, in the preset data service cycle, the remaining resources of the target data center at the first target unit time are, for the first time, less than the total amount of newly added resources of the candidate business at the first target unit time.
[0084] Optionally, the device further includes a screening module 403 configured to:
[0085] At least one target service is selected from a plurality of candidate services based on the service attribute information of each candidate service and the migratable service screening strategy.
[0086] Optionally, the remaining resource amount is the number of remaining racks, the newly added resource amount is the number of newly added racks, and the resource gap information prediction model is a rack gap information prediction model.
[0087] The determination module 402 is configured to:
[0088] Starting from the first unit time in the preset data service cycle, repeatedly determine the difference between the number of remaining racks of the target data center in the previous unit time and the total number of newly added racks in the current unit time to obtain the number of remaining racks of the target data center in the current unit time, wherein the total number of newly added racks is the sum of the number of newly added racks of each target service;
[0089] When the number of remaining racks in the target data center is a negative value for the first time, the current unit time is determined as the first target unit time.
[0090] Optionally, the apparatus further includes a processing module 404 configured to:
[0091] Determine the absolute value of the number of remaining racks of the target data center in the first target unit time, and the sum of the number of newly added racks of each target service in each second target unit time, to obtain the total number of racks of the newly built data center, wherein the second target unit time is a unit time after the first target unit time in the preset data service cycle;
[0092] Determine the number of racks of each power density in the total number of racks of the newly built data center, and the product of the single rack floor space associated with each power density rack, to obtain the planned construction area associated with each power density rack;
[0093] The sum of the planned construction areas associated with each power density rack is determined as the total planned construction area of the new data center.
[0094] Optionally, the remaining resource amount is the remaining external power capacity, the newly added resource amount is the average power consumption of a single newly added rack, and the resource gap information prediction model is the external power capacity gap information prediction model.
[0095] The determination module 402 is configured to:
[0096] Starting from the first unit time in the preset data service cycle, repeatedly determine the remaining external mains power capacity of the target data center in the previous unit time, and the difference between the total power consumption of the newly added racks in the current unit time, to obtain the remaining external mains power capacity of the target data center in the current unit time, wherein the total power consumption of the newly added racks is the product of the total number of newly added racks, the average power consumption of a single newly added rack, and the preset power utilization rate of a single rack;
[0097] When the remaining external commercial power capacity of the target data center is negative for the first time, the current unit time is determined as the first target unit time.
[0098] Optionally, the service attribute information includes at least one of service transmission delay, service access type and service service location information.
[0099] The screening module 403 is configured to:
[0100] For each candidate service, if the service transmission delay of the candidate service is greater than a preset threshold, or the service access type of the candidate service is a non-real-time access service, or the service service location information of the candidate service indicates that it is a remote service, then the candidate service is determined as the target service.
[0101] Figure 5 Schematic block diagram of a chip according to an exemplary embodiment of the present disclosure is shown. Figure 5 As shown, the chip 500 includes one or more (including two) processors 501 and a communication interface 502. The communication interface 502 can support the server to execute the data sending and receiving steps in the above data center planning method, and the processor 501 can support the server to execute the data processing steps in the above data center planning method.
[0102] Optional, such as Figure 5 As shown, the chip 500 also includes a memory 503, which may include a read-only memory and a random access memory, and provides operation instructions and data to the processor. A portion of the memory may also include a non-volatile random access memory (NVRAM).
[0103] In some embodiments, Figure 5 As shown, the processor 501 performs corresponding operations by calling the operation instructions stored in the memory (the operation instructions may be stored in the operating system). The processor 501 controls the processing operations of any one of the servers, and the processor may also be called a central processing unit (CPU). The memory 503 may include a read-only memory and a random access memory, and provides instructions and data to the processor 501. A portion of the memory 503 may also include NVRAM. For example, in an application, the memory, the communication interface, and the memory are coupled together through a bus system, wherein the bus system may include a power bus, a control bus, and a status signal bus in addition to a data bus. However, for the sake of clarity, in Figure 5 Various buses are labeled as bus system 504 .
[0104] The method disclosed in the above-mentioned embodiment of the present disclosure can be applied to a processor or implemented by a processor. The processor may be an integrated circuit chip with signal processing capabilities. In the implementation process, each step of the above method can be completed by an integrated logic circuit of hardware in the processor or an instruction in the form of software. The above-mentioned processor may be a general-purpose processor, a digital signal processor (digital signal processing, DSP), an ASIC, a field-programmable gate array (field-programmable gate array, FPGA) or other programmable logic devices, discrete gates or transistor logic devices, discrete hardware components. The methods, steps and logic block diagrams disclosed in the embodiments of the present disclosure can be implemented or executed. The general-purpose processor may be a microprocessor or the processor may also be any conventional processor, etc. The steps of the method disclosed in conjunction with the embodiment of the present disclosure can be directly embodied as being executed by a hardware decoding processor, or executed by a combination of hardware and software modules in the decoding processor. The software module may be located in a mature storage medium in the field such as a random access memory, a flash memory, a read-only memory, a programmable read-only memory or an electrically erasable programmable memory, a register, etc. The storage medium is located in a memory, and the processor reads the information in the memory and completes the steps of the above method in conjunction with its hardware.
[0105] The exemplary embodiment of the present disclosure also provides an electronic device, comprising: at least one processor; and a memory connected to the at least one processor in communication. The memory stores a computer program that can be executed by the at least one processor, and the computer program is used to cause the electronic device to perform the method according to the embodiment of the present disclosure when executed by the at least one processor.
[0106] The exemplary embodiments of the present disclosure also provide a non-transitory computer-readable storage medium storing a computer program, wherein the computer program, when executed by a processor of a computer, is used to cause the computer to perform the method according to the embodiments of the present disclosure.
[0107] The exemplary embodiments of the present disclosure further provide a computer program product, including a computer program, wherein when the computer program is executed by a processor of a computer, the computer is used to enable the computer to perform the method according to the embodiments of the present disclosure.
[0108] refer to Figure 6 , a block diagram of an electronic device 600 that can be used as a server of the present disclosure will now be described, which is an example of a hardware device that can be applied to various aspects of the present disclosure. The electronic device is intended to represent various forms of digital electronic computer devices, such as laptop computers, desktop computers, workbenches, personal digital assistants, servers, blade servers, mainframe computers, and other suitable computers. The electronic device can also represent various forms of mobile devices, such as personal digital processing, cellular phones, smart phones, wearable devices, and other similar computing devices. The components shown herein, their connections and relationships, and their functions are merely examples and are not intended to limit the implementation of the present disclosure described and / or required herein.
[0109] like Figure 6 As shown, the electronic device 600 includes a computing unit 601, which can perform various appropriate actions and processes according to a computer program stored in a read-only memory (ROM) 602 or a computer program loaded from a storage unit 608 into a random access memory (RAM) 603. In the RAM 603, various programs and data required for the operation of the electronic device 600 can also be stored. The computing unit 601, the ROM 602, and the RAM 603 are connected to each other via a bus 604. An input / output (I / O) interface 605 is also connected to the bus 604.
[0110] A plurality of components in the electronic device 600 are connected to the I / O interface 605, including: an input unit 606, an output unit 607, a storage unit 608, and a communication unit 609. The input unit 606 may be any type of device capable of inputting information to the electronic device 600, and the input unit 606 may receive input digital or character information, and generate key signal inputs related to user settings and / or function control of the electronic device. The output unit 607 may be any type of device capable of presenting information, and may include, but is not limited to, a display, a speaker, a video / audio output terminal, a vibrator, and / or a printer. The storage unit 608 may include, but is not limited to, a disk, an optical disk. The communication unit 609 allows the electronic device 600 to exchange information / data with other devices through a computer network such as the Internet and / or various telecommunication networks, and may include, but is not limited to, a modem, a network card, an infrared communication device, a wireless communication transceiver, and / or a chipset, such as a Bluetooth™ device, a WiFi device, a WiMax device, a cellular communication device, and / or the like.
[0111] The computing unit 601 may be a variety of general and / or special processing components with processing and computing capabilities. Some examples of the computing unit 601 include, but are not limited to, a central processing unit (CPU), a graphics processing unit (GPU), various dedicated artificial intelligence (AI) computing chips, various computing units running machine learning model algorithms, digital signal processors (DSPs), and any appropriate processors, controllers, microcontrollers, etc. The computing unit 601 performs the various methods and processes described above. For example, in some embodiments, the method of the exemplary embodiment of the present disclosure may be implemented as a computer software program, which is tangibly included in a machine-readable medium, such as a storage unit 608. In some embodiments, part or all of the computer program may be loaded and / or installed on the electronic device 600 via the ROM 602 and / or the communication unit 609. In some embodiments, the computing unit 601 may be configured to perform the method of the exemplary embodiment of the present disclosure by any other appropriate means (e.g., by means of firmware).
[0112] The program code for implementing the method of the present disclosure may be written in any combination of one or more programming languages. These program codes may be provided to a processor or controller of a general-purpose computer, a special-purpose computer, or other programmable data processing device, so that the program code, when executed by the processor or controller, enables the functions / operations specified in the flow chart and / or block diagram to be implemented. The program code may be executed entirely on the machine, partially on the machine, partially on the machine and partially on a remote machine as a stand-alone software package, or entirely on a remote machine or server.
[0113] In the context of the present disclosure, a machine-readable medium may be a tangible medium that may contain or store a program for use by or in conjunction with an instruction execution system, device, or equipment. A machine-readable medium may be a machine-readable signal medium or a machine-readable storage medium. A machine-readable medium may include, but is not limited to, an electronic, magnetic, optical, electromagnetic, infrared, or semiconductor system, device, or equipment, or any suitable combination of the foregoing. A more specific example of a machine-readable storage medium may include an electrical connection based on one or more lines, a portable computer disk, a hard disk, a random access memory (RAM), a read-only memory (ROM), an erasable programmable read-only memory (EPROM or flash memory), an optical fiber, a portable compact disk read-only memory (CD-ROM), an optical storage device, a magnetic storage device, or any suitable combination of the foregoing.
[0114] As used in this disclosure, the terms "machine-readable medium" and "computer-readable medium" refer to any computer program product, apparatus, and / or device (e.g., disk, optical disk, memory, programmable logic device (PLD)) for providing machine instructions and / or data to a programmable processor, including a machine-readable medium that receives machine instructions as a machine-readable signal. The term "machine-readable signal" refers to any signal for providing machine instructions and / or data to a programmable processor.
[0115] To provide interaction with a user, the systems and techniques described herein can be implemented on a computer having: a display device (e.g., a CRT (cathode ray tube) or LCD (liquid crystal display) monitor) for displaying information to the user; and a keyboard and pointing device (e.g., a mouse or trackball) through which the user can provide input to the computer. Other types of devices can also be used to provide interaction with the user; for example, the feedback provided to the user can be any form of sensory feedback (e.g., visual feedback, auditory feedback, or tactile feedback); and input from the user can be received in any form (including acoustic input, voice input, or tactile input).
[0116] The systems and techniques described herein may be implemented in a computing system that includes back-end components (e.g., as a data server), or a computing system that includes middleware components (e.g., an application server), or a computing system that includes front-end components (e.g., a user computer with a graphical user interface or a web browser through which a user can interact with implementations of the systems and techniques described herein), or a computing system that includes any combination of such back-end components, middleware components, or front-end components. The components of the system may be interconnected by any form or medium of digital data communication (e.g., a communication network). Examples of communication networks include: a local area network (LAN), a wide area network (WAN), and the Internet.
[0117] A computer system may include clients and servers. Clients and servers are generally remote from each other and usually interact through a communication network. The relationship of client and server is generated by computer programs running on respective computers and having a client-server relationship to each other.
[0118] In the above embodiments, it can be implemented in whole or in part by software, hardware, firmware or any combination thereof. When implemented by software, it can be implemented in whole or in part in the form of a computer program product. The computer program product includes one or more computer programs or instructions. When the computer program or instruction is loaded and executed on a computer, the process or function described in the embodiment of the present disclosure is executed in whole or in part. The computer may be a general-purpose computer, a special-purpose computer, a computer network, a terminal, a user device or other programmable device. The computer program or instruction may be stored in a computer-readable storage medium, or transmitted from one computer-readable storage medium to another computer-readable storage medium, for example, the computer program or instruction may be transmitted from one website site, computer, server or data center to another website site, computer, server or data center by wired or wireless means. The computer-readable storage medium may be any available medium that a computer can access or a data storage device such as a server, data center, etc. that integrates one or more available media. The available medium may be a magnetic medium, for example, a floppy disk, a hard disk, a tape; it may also be an optical medium, for example, a digital video disc (DVD); it may also be a semiconductor medium, for example, a solid state drive (SSD).
[0119] Although the present disclosure has been described in conjunction with specific features and embodiments thereof, it is apparent that various modifications and combinations may be made thereto without departing from the spirit and scope of the present disclosure. Accordingly, this specification and the drawings are merely exemplary illustrations of the present disclosure as defined by the appended claims, and are deemed to have covered any and all modifications, variations, combinations or equivalents within the scope of the present disclosure. Obviously, those skilled in the art may make various modifications and variations to the present disclosure without departing from the spirit and scope of the present disclosure. Thus, if these modifications and variations of the present disclosure fall within the scope of the claims of the present disclosure and their equivalents, the present disclosure is also intended to include these modifications and variations.
Claims
1. A data center planning method, characterized in that: include: Acquire candidate service information and the remaining resources of the target data center, wherein the candidate service information includes the newly added resources per unit time of each candidate service in a preset data service cycle; If a resource gap information prediction model is input based on the remaining resources of the target data center and the newly added resources per unit time of each candidate business in the preset data service cycle, and it is determined that there is a first target unit time in the preset data service cycle, then the preset time before the first target unit time is determined as the start construction time of the new data center, wherein, in the preset data service cycle, the remaining resources of the target data center at the first target unit time are, for the first time, less than the total amount of newly added resources of the candidate business at the first target unit time.
2. The data center planning method according to claim 1, characterized in that: The candidate service information also includes service attribute information of multiple candidate services. After obtaining the candidate service information and the remaining resources of the target data center, the method further includes: At least one target service is selected from a plurality of candidate services based on the service attribute information of each candidate service and the migratable service screening strategy.
3. The data center planning method according to claim 2, characterized in that: The remaining resource amount is the number of remaining racks, the newly added resource amount is the number of newly added racks, and the resource gap information prediction model is a rack gap information prediction model. Based on the remaining resources of the target data center and the newly added resources per unit time of each candidate service in the preset data service cycle, a resource gap information prediction model is input to determine whether there is a first target unit time in the preset data service cycle, including: Starting from the first unit time in the preset data service cycle, repeatedly determine the difference between the number of remaining racks of the target data center in the previous unit time and the total number of newly added racks in the current unit time to obtain the number of remaining racks of the target data center in the current unit time, wherein the total number of newly added racks is the sum of the number of newly added racks of each target service; When the number of remaining racks in the target data center is a negative value for the first time, the current unit time is determined as the first target unit time.
4. The data center planning method according to claim 3, characterized in that: The method further comprises: Determine the absolute value of the number of remaining racks of the target data center in the first target unit time, and the sum of the number of newly added racks of each target service in each second target unit time, to obtain the total number of racks of the newly built data center, wherein the second target unit time is a unit time after the first target unit time in the preset data service cycle; Determine the number of racks of each power density in the total number of racks of the newly built data center, and the product of the single rack floor space associated with each power density rack, to obtain the planned construction area associated with each power density rack; The sum of the planned construction areas associated with each power density rack is determined as the total planned construction area of the new data center.
5. The data center planning method according to claim 2, characterized in that: The remaining resource amount is the remaining external power capacity, the newly added resource amount is the average power consumption of a single newly added rack, and the resource gap information prediction model is the external power capacity gap information prediction model. Based on the remaining resources of the target data center and the newly added resources per unit time of each candidate service in the preset data service cycle, a resource gap information prediction model is input to determine whether there is a first target unit time in the preset data service cycle, including: Starting from the first unit time in the preset data service cycle, repeatedly determine the remaining external mains power capacity of the target data center in the previous unit time, and the difference between the total power consumption of the newly added racks in the current unit time, to obtain the remaining external mains power capacity of the target data center in the current unit time, wherein the total power consumption of the newly added racks is the product of the total number of newly added racks, the average power consumption of a single newly added rack, and the preset power utilization rate of a single rack; When the remaining external commercial power capacity of the target data center is negative for the first time, the current unit time is determined as the first target unit time.
6. The data center planning method according to claim 2, characterized in that: The service attribute information includes at least one of service transmission delay, service access type and service location information. The selecting at least one target service from a plurality of candidate services based on the service attribute information of each candidate service and the migratable service screening strategy comprises: For each candidate service, if the service transmission delay of the candidate service is greater than a preset threshold, or the service access type of the candidate service is a non-real-time access service, or the service service location information of the candidate service indicates that it is a remote service, then the candidate service is determined as the target service.
7. A data center planning device, characterized in that: include: An acquisition module is configured to acquire candidate service information and the remaining resources of the target data center, wherein the candidate service information includes the newly added resources per unit time of each candidate service in a preset data service cycle; The determination module is configured to input a resource gap information prediction model based on the remaining resources of the target data center and the newly added resources per unit time of each candidate business in the preset data service cycle, and determine that there is a first target unit time in the preset data service cycle, then determine the preset time before the first target unit time as the start construction time of the new data center, wherein, in the preset data service cycle, the remaining resources of the target data center at the first target unit time is, for the first time, less than the total amount of newly added resources of the candidate business at the first target unit time.
8. An electronic device, characterized in that: include: processor; as well as, Memory for storing programs, The program includes instructions, which, when executed by the processor, cause the processor to perform the method according to any one of claims 1 to 6.
9. A non-transitory computer-readable storage medium storing computer instructions, characterized in that: The computer instructions are used to cause the computer to execute the method according to any one of claims 1 to 6.
10. A computer program product, comprising a computer program, characterized in that When the computer program is executed by a processor, the computer program implements the method according to any one of claims 1 to 6.
Citation Information
Patent Citations
Application stretching management method and device
CN104317638A
Data center machine position capacity determination method and device and storage medium
CN112381434A
Business resource capacity dynamic allocation method and device, equipment and storage medium
CN114666224A
Resource allocation method and device and storage medium
CN115396514A
Coal data management method and system based on hyper-converged architecture technology
CN115564195A