A tube material library for laser cutting equipment

By designing a pipe material library of multi-layer cross frames and mobile components in laser cutting equipment, the problem of inconvenient access to pipes in limited space is solved, convenient access and efficient storage of pipes is achieved, and the efficiency of laser cutting equipment is improved.

CN118811512BActive Publication Date: 2024-11-22FOSHAN LONGXIN LASER TECH CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411295504.0
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-09-18
Publication Date
2024-11-22
Estimated Expiration
2044-09-18

AI Technical Summary

Technical Problem

The existing pipe loading device is difficult to easily access the pipe in a limited space, which affects the efficiency of the laser cutting equipment.

Method used

A pipe material library for laser cutting equipment was designed, using at least two equidistant racks, each layer of racks with multiple layers of cross frames and moving components, which were realized through hydraulic cylinders, reciprocating components and chain belt systems. The pipes are conveniently picked up and placed neatly.

Benefits of technology

It improves the convenience of material removal and storage efficiency of pipes, and ensures the efficient operation of laser cutting equipment.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118811512B_ABST
    Figure CN118811512B_ABST
Patent Text Reader

Abstract

The present application relates to the technical field of pipe material warehouses, and in particular to a pipe material warehouse for laser cutting equipment, which comprises at least two equally spaced material racks, the side walls of the material racks are symmetrically provided with multi-layer cross frames, the multi-layer cross frames are respectively distributed in a linear array along the vertical direction of the material racks, a loading material frame is movably provided on each layer of the cross frames, and each layer of the cross frames is provided with a moving component for driving the loading material frame to move. The present application has the effect of improving the convenience of taking pipe materials.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of tube material libraries, and in particular to a tube material library for laser cutting equipment. Background Art

[0002] Laser tube cutting machines are mainly used for cutting metal tubes. They have the advantages of high cutting accuracy, fast cutting, smooth incision, and low processing cost. Therefore, laser tube cutting machines have been widely used in industry. In order to improve the cutting efficiency of laser tube cutting machines, existing laser tube cutting machines are equipped with tube feeding devices. The automation and efficiency of tube feeding devices are one of the key factors to improve the cutting efficiency of laser tube cutting machines.

[0003] The current pipe loading device includes a stand, and a material table is symmetrically fixedly connected to both sides of the stand. The material table is provided with multiple layers, and the multiple layers of the material table are distributed in a linear array along the vertical direction of the stand. A baffle is fixedly connected to the outer end of the material table. When it is necessary to store pipes, first use a forklift to fork up the pipes, and then push the pipes to the required storage location, and then separate the pipes from the forklift. Under the action of the baffle, the pipes are stored on the material table. Similarly, when it is necessary to take materials, use a forklift to fork up the pipes on the corresponding layer of the material table, and then send the pipes to the loading rack of the laser cutting equipment to complete the storage and retrieval of the pipes.

[0004] However, the floor space in the factory workshop is often limited and not enough for the forklift to move freely. Without the use of a forklift, it is difficult to take out the pipes on the upper layer. In this case, it is not only inconvenient to store and retrieve the pipes, but also affects the efficiency of the laser cutting operation. Summary of the invention

[0005] In order to improve the convenience of taking pipe materials, the present application provides a pipe material library for laser cutting equipment.

[0006] The present application provides a tube material library for laser cutting equipment, which adopts the following technical solution:

[0007] A tube material warehouse for laser cutting equipment comprises at least two equally spaced material racks, the side walls of the material racks being symmetrically provided with multiple layers of cross racks, the multiple layers of cross racks being distributed in a linear array along the vertical direction of the material racks, a loading material frame being movably provided on each layer of the cross racks, and a moving component for driving the loading material frame to move being provided on each layer of the cross racks.

[0008] By adopting the above technical solution, at least two equidistantly arranged material racks are used at the same time, and each layer of the loading material frame is used to load pipes of different types. When it is necessary to take out the pipes on the loading material frame on the corresponding layer, the loading material frame is driven by the moving component to move away from the material rack, and the staff then uses the truss crane to lift the pipes on the loading material frame on the corresponding layer, which is conducive to improving the convenience of taking pipes from the material rack.

[0009] Optionally, the moving component includes a hydraulic cylinder, a guide rod is provided at one end of the bottom surface of the loading frame, a guide groove is provided at one end of the cross frame, the guide rod is slidably provided in the guide groove, the hydraulic cylinder is slidably provided on the top surface of the cross frame, and the telescopic end of the hydraulic cylinder is fixedly connected to the loading frame.

[0010] By adopting the above technical solution, when the hydraulic cylinder is started, the telescopic end of the hydraulic cylinder drives the loading frame to move, the loading frame drives the guide rod to move, and the guide rod moves along the opening direction of the guide groove. At this time, the loading frame drives the pipe to extend or retract into the material rack, which is beneficial to improve the convenience of taking or loading materials from the loading frame.

[0011] Optionally, a support platform is provided at one end of the horizontal frame, a reciprocating frame is provided on the top surface of the support platform, the reciprocating frame is fixedly connected to the hydraulic cylinder, and the support platform is provided with a reciprocating component for driving the reciprocating frame to reciprocate.

[0012] By adopting the above technical scheme, when the reciprocating frame is driven to reciprocate on the support table by the reciprocating assembly, the reciprocating frame drives the loading frame to reciprocate through the hydraulic cylinder. The reciprocating movement of the loading frame causes the pipes in the loading frame to swing left and right. After a period of time, the pipes in the loading frame are stacked flatly and evenly in the loading frame, which is conducive to making full use of the loading space in the loading frame and improving the neatness of the pipe loading and stacking.

[0013] Optionally, the reciprocating component includes a sector gear, which is rotatably arranged in the reciprocating frame, and the inner top wall and the inner bottom wall of the reciprocating frame are both provided with racks, and the sector gear is meshed with the racks. A first motor is arranged on the support platform, and the driving shaft of the first motor is coaxially connected to the sector gear.

[0014] By adopting the above technical solution, when the first motor is started, the driving shaft of the first motor drives the fan gear to rotate, and the fan gear drives the reciprocating frame to move back and forth by meshing with the upper and lower racks respectively. The reciprocating frame then drives the reciprocating frame to move back and forth through the hydraulic cylinder, which is beneficial to improve the stability of the reciprocating movement of the reciprocating frame.

[0015] Optionally, a flip frame is provided on one side of the loading material frame, a vertical frame is symmetrically provided on the top surface of the flip frame, sprockets are respectively provided on one side of the two vertical frames for lifting, a chain belt is provided at one end of the flip frame, the sprocket is meshed with the chain belt, a plurality of shifting blocks are provided on the chain belt, the two vertical frames are respectively provided with lifting components for driving the sprockets to lift and lower, and the vertical frame is provided with a driving member for driving the sprockets to rotate.

[0016] By adopting the above technical solution, when the sprocket is driven to rise by the lifting assembly, the sprocket drives the chain belt to rise. At this time, the chain belt is close to the pipes in the loading frame. When the sprocket is driven to rotate by the driving member, the sprocket drives the chain belt to transmit, and the chain belt then drives the shift block to transmit. At this time, the chain belt moves the pipes at the bottom layer through the shift block, and under the continuous transmission action of the chain belt, the pipes at the bottom layer are finally moved to the top layer, thereby realizing the removal of the pipes at the bottom layer in the loading frame, which is beneficial to improve the practicality of the pipe material warehouse.

[0017] Optionally, the lifting assembly includes a second motor and a screw rod, a lifting slot is opened in the vertical frame, a lifting block is slidably arranged in the lifting slot, the sprocket is rotatably arranged on one side of the lifting block, the screw rod is rotatably arranged in the lifting slot, the screw rod thread passes through the lifting block, the second motor is arranged on the top surface of the vertical frame, and the driving shaft of the second motor is coaxially connected to the screw rod.

[0018] By adopting the above technical solution, when the second motor is started, the driving shaft of the second motor drives the screw to rotate, the screw drives the lifting block to lift and lower along the vertical direction of the stand, the lifting block drives the sprocket to lift and lower, and the sprocket in turn drives the chain belt to rise. At this time, the chain belt is close to the side wall of the pipe, which is beneficial to improve the stability of moving the pipe by the chain belt.

[0019] Optionally, the ratio of the length of the chain belt to the distance between the two stands is 4:1.

[0020] By adopting the above technical solution, the chain length of the chain belt is longer than the distance between the two brackets, so that when the two ends of the chain belt rise, the chain belt has sufficient length to tightly cover the circumference of the pipe in the loading frame, which is beneficial to improve the stability of moving the pipe by the chain belt.

[0021] Optionally, a pressure gear is provided at one end of the flip frame, and the pressure gear is meshed with the chain belt.

[0022] By adopting the above technical solution, the position of the pressure gear and the positions of the two sprockets form a triangle point, which is conducive to ensuring the stability of the chain belt transmission.

[0023] Optionally, guide arc plates are respectively provided on the inner sides of the two vertical frames.

[0024] By adopting the above technical solution, when the pipes on the bottom layer are moved by the chain belt, the pipes on the top layer fall back into the middle of the loading frame along the guide arc plate, while the pipes at the inner edge of the loading frame are moved to the top layer of the pipe pile, which is beneficial to improve the stability of moving the bottom layer of the pipes to the top layer.

[0025] In summary, this application includes the following beneficial technical effects:

[0026] At least two parallel material racks are used at the same time, and each layer of loading frames is used to load pipes of different types. When it is necessary to take out the pipes on the loading frame on the corresponding layer, the loading frame is driven by the moving assembly to move away from the material rack, and the staff then uses the truss crane to lift the pipes on the loading frame on the corresponding layer, which is conducive to improving the convenience of taking pipes from the material rack. BRIEF DESCRIPTION OF THE DRAWINGS

[0027] Figure 1 It is a schematic diagram of the overall structure of the tube material library for laser cutting equipment of the present application;

[0028] Figure 2 is a side view of a tube material library for a laser cutting device of the present application;

[0029] Figure 3 It is a structural schematic diagram of one of the material racks of this application;

[0030] Figure 4 It is a schematic diagram of the structure of one layer of the horizontal frame of the present application;

[0031] Figure 5 yes Figure 4 An enlarged view of part A;

[0032] Figure 6 It is a structural schematic diagram of the loading frame, the turning frame and the standing frame of the present application.

[0033] Explanation of the accompanying drawings: 1. Material rack; 2. Horizontal rack; 3. Loading material frame; 4. Hydraulic cylinder; 5. Guide rod; 6. Guide groove; 7. Support table; 8. Reciprocating frame; 9. Fan gear; 10. Rack; 11. First motor; 12. Turning frame; 13. Vertical frame; 14. Sprocket gear; 15. Chain belt; 16. Shift block; 17. Second motor; 18. Screw rod; 19. Lifting groove; 20. Lifting block; 21. Pressing gear; 22. Third motor; 23. Guide arc plate. DETAILED DESCRIPTION

[0034] The following is combined with Figure 1-6 This application is described in further detail. Example

[0035] See also Figure 1-Figure 3, a tube material warehouse for laser cutting equipment, includes a material rack 1, and the number of the material racks 1 is set to at least two. In the present embodiment, the number of the material racks 1 is set to three, and the three material racks 1 are evenly spaced along the straight direction. Four layers of cross frames 2 are symmetrically fixedly installed on each material rack 1, and the four layers of cross frames 2 are respectively distributed in a linear array along the vertical direction of the material rack 1, and the height of each layer of cross frames 2 on the three material racks 1 is the same. A loading material frame 3 is slidably installed on each layer of the cross frame 2, and the loading material frame 3 is composed of three steel sections, and two loading material frames 3 are provided and symmetrically distributed with the material rack 1 as the axis. A moving component is installed on each layer of the cross frame 2, and the moving component is used to drive the loading material frame 3 to extend from the material rack 1 or retract into the material rack 1.

[0036] The three racks 1 are used at the same time to support and store pipes, and each layer of the loading frame 3 is loaded with pipes of different types. When the pipes need to be taken out of the loading frame 3, the loading frames 3 of the corresponding layers of the three racks 1 are driven by the moving components to move away from the rack 1. At this time, the loading frames 3 of the corresponding layers of the three racks 1 are extended out of the rack 1 together, and then the staff uses the truss crane to lift the pipes in the loading frame 3. After the pipes are lifted, the loading frames 3 of the corresponding layers of the three racks 1 are driven by the moving components to retract into the rack 1 to complete the pipe taking operation.

[0037] For details, see Figure 3 The moving assembly includes a hydraulic cylinder 4, which is slidably mounted on the top surface of the cross frame 2. The hydraulic cylinder 4 includes a fixed end and a telescopic end, and the telescopic end of the hydraulic cylinder 4 is fixedly connected to the side wall of the loading frame 3. A guide rod 5 is fixedly connected to the bottom surface of the loading frame 3, and a guide groove 6 is provided at one end of the cross frame 2 corresponding to the position of the guide rod 5, and the guide rod 5 is slidably mounted in the guide groove 6.

[0038] When the hydraulic cylinders 4 of the corresponding layers of the three racks 1 are started at the same time, the loading racks 3 are extended out of the racks 1 under the guidance of the guide rods 5 and the guide grooves 6. In this way, the staff can extend the loading racks 3 of the corresponding layers according to the required types of pipes, and then lift the pipes from the loading racks 3 by the gantry crane.

[0039] It is worth mentioning that see Figure 4 and Figure 5 When the pipes are stored in the loading frame 3, the pipes are stacked in disorder, so the pipes in the loading frame 3 are easily stacked crookedly and the space utilization rate is not high. For this reason, the end of the horizontal frame 2 away from the loading frame 3 is fixedly connected to a support platform 7, and a reciprocating frame 8 is movably installed on the top surface of the support platform 7, and the reciprocating frame 8 is fixedly connected to the fixed end of the hydraulic cylinder 4.

[0040] See also Figure 4 and Figure 5In order to facilitate the reciprocating frame 8 to reciprocate along the length direction of the horizontal frame 2, the support platform 7 is equipped with a reciprocating assembly, which includes a sector gear 9, which is rotatably installed in the reciprocating frame 8. The inner top wall and the inner bottom wall of the reciprocating frame 8 are fixedly installed with a rack 10, and the sector gear 9 is respectively engaged with the rack 10. A first motor 11 is also fixedly installed on the support platform 7, and the driving shaft of the first motor 11 is coaxially fixedly connected with the sector gear 9.

[0041] After initially stacking the pipes in the loading frame 3, the first motor 11 is started, and the driving shaft of the first motor 11 drives the sector gear 9 to rotate. As the sector gear 9 continues to rotate, the sector gear 9 is respectively engaged with the racks 10 on the inner top wall and the inner bottom wall, and the reciprocating frame 8 reciprocates horizontally on the support platform 7, and the reciprocating frame 8 drives the loading frame 3 to reciprocate through the hydraulic cylinder 4. While the loading frame 3 reciprocates, the loading frame 3 continuously shakes the randomly stacked pipes, and finally the pipes are stacked neatly and evenly in the loading frame 3, thereby improving the space utilization rate in the loading frame 3.

[0042] See also Figure 4 and Figure 6 In order to facilitate the single removal of the tubes stacked at the bottom layer in the loading material frame 3, a turning frame 12 is fixedly connected to one side of the loading material frame 3, and a vertical frame 13 is symmetrically fixedly connected to the top surface of the turning frame 12. The shape enclosed by the turning frame 12 and the two vertical frames 13 is the same as the shape of the loading material frame 3. Sprockets 14 are respectively installed on the side of the two vertical frames 13 away from the loading material frame 3, and a chain belt 15 is installed on the side of the turning frame 12 away from the loading material frame 3. The chain belt 15 is jointly sleeved on the two sprockets 14, and the chain belt 15 is meshed with the two sprockets 14 at the same time. A shifting block 16 is fixedly connected to the surface of the chain belt 15, and the number of the shifting blocks 16 is set to multiple, and the multiple shifting blocks 16 are equidistantly distributed along the surface of the chain belt 15.

[0043] See also Figure 6 In order to improve the stability of the lifting of the sprocket 14, the two vertical frames 13 are respectively installed with lifting components, and the lifting components include a second motor 17 and a screw 18. A lifting slot 19 is provided in the vertical frame 13, and a lifting block 20 is slidably installed in the vertical frame 13 based on the lifting slot 19. One end of the lifting block 20 extends outside the vertical frame 13, and the sprocket 14 is rotatably installed on one end of the lifting block 20. The screw 18 is rotatably installed in the lifting slot 19, and the screw 18 is threadedly inserted into the lifting block 20. The second motor 17 is fixed to the top surface of the vertical frame 13, and the driving shaft of the second motor 17 extends in the lifting slot 19, and the driving shaft of the second motor 17 is coaxially fixedly connected with the top of the screw 18.

[0044] Note that see Figure 6In order to facilitate the chain belt 15 to wrap the pipes in the loading frame 3, the ratio of the chain length of the chain belt 15 to the distance between the two vertical frames 13 is 4:1. This ensures that the wound chain belt 15 has enough length to wrap the pipes loaded in the loading frame 3.

[0045] When it is necessary to take the pipes at the bottom layer, the two second motors 17 are started at the same time, and the two second motors 17 drive the screw rod 18 to rotate respectively, the screw rod 18 drives the lifting block 20 to rise, the lifting block 20 drives the sprocket 14 to rise, and the sprocket 14 then drives the two ends of the chain belt 15 to rise, and at this time the chain belt 15 wraps around the pipes in the loading frame 3. When the sprocket 14 is driven to rotate, the sprocket 14 drives the chain belt 15 to transmit, and the chain belt 15 drives the shifting block 16 to transmit, and at this time the shifting block 16 moves the pipes at the bottom layer, and the pipes at the upper layer are piled down, so as to take out the pipes at the bottom layer, and avoid the pipes at the bottom layer from being unused for a long time, which leads to the reduction of the pipe quality.

[0046] See also Figure 6 In order to improve the transmission stability of the chain belt 15, the end of the flip frame 12 away from the loading frame 3 is rotatably connected to a pressure gear 21. The pressure gear 21 and the two sprockets 14 form a triangle point, and the chain belt 15 is transmitted through the triangle point to prevent the chain belt 15 from being entangled with itself when it is wrapped around the pipe.

[0047] In addition, under the gravity of the chain belt 15 and the pressing action of the pipe, the chain belt 15 is ensured to always remain in meshing with the sprocket 14, thereby improving the transmission stability of the chain belt 15.

[0048] join Figure 6 In order to facilitate the rotation of the sprocket gear 14, the stand 13 is installed with a driving member, which is a third motor 22. The third motor 22 is fixed to the side of the lifting block 20 away from the sprocket gear 14. The driving shaft of the third motor 22 passes through the lifting block 20 and is coaxially fixedly connected with the sprocket gear 14.

[0049] When the third motor 22 is started, the driving shaft of the third motor 22 drives the sprocket 14 to rotate. Under the rotation of the sprocket 14, the sprocket 14 drives the chain belt 15 to transmit, and the chain belt 15 moves the pipe through the shifting block 16.

[0050] It is worth mentioning that see Figure 6 The inner side walls of the two vertical frames 13 are respectively fixedly connected with guide arc plates 23, and the guiding direction of the guide arc plates 23 faces inwards.

[0051] When the pipes on the top layer are moved, the pipes on the top layer fall back along the guide arc plate 23 to the middle of the stacked pipes, and this process is repeated until the pipes on the bottom layer are finally moved to the top layer.

[0052] Working principle of a tube material library for laser cutting equipment:

[0053] When it is necessary to load pipes into the loading material frame 3, first determine the loading material frame 3 layer to be stored, then start the hydraulic cylinders 4 of the required layers of the three material racks 1 at the same time, and under the guiding support of the guide rod 5, the telescopic end of the hydraulic cylinder 4 drives the loading material frame 3 to extend out of the material rack 1. Then, the pipes are stored in the three extended loading material frames 3 at the same time.

[0054] Since the pipes are prone to tilt when they are stored, the first motor 11 is started first, and the driving shaft of the first motor 11 drives the fan gear 9 to rotate. As the fan gear 9 continues to rotate, the fan gear 9 drives the reciprocating frame 8 to move back and forth through the meshing with the upper and lower racks 10, and the reciprocating frame 8 drives the hydraulic cylinder 4 to move back and forth, and the hydraulic cylinder 4 then drives the loading frame 3 to move back and forth, so that the pipes in the loading frame 3 are constantly shaking left and right. After a period of time, the pipes are finally neatly stacked in the loading frame 3, improving the space utilization rate in the loading frame 3. After the loading of the pipes is completed, the hydraulic cylinders 4 of the required layers of the three racks 1 are started again at the same time, and the telescopic ends of the hydraulic cylinders 4 drive the loading frame 3 to retract into the rack 1 to complete the loading of the pipes.

[0055] Similarly, when unloading is required, first determine the pipes of the required layer, and then start the hydraulic cylinders 4 of the required layers of the three material racks 1 at the same time. The telescopic ends of the hydraulic cylinders 4 drive the loading material frames 3 to extend out of the material racks 1. At this time, the staff can lift the pipes in the loading material frames 3 through the truss crane.

[0056] It is worth mentioning that when it is necessary to take out the pipe material with the longest storage time at the bottom layer, the second motor 17 on the two vertical frames 13 is started at the same time, the driving shaft of the second motor 17 drives the screw 18 to rotate, the screw 18 drives the lifting block 20 to rise, and the lifting block 20 drives the sprocket 14 to rise. Since the length of the chain belt 15 is longer than the distance between the two vertical frames 13. Therefore, when the sprocket 14 rises, the sprocket 14 drives both ends of the chain belt 15 to rise and wrap the pipe material. Then the third motor 22 is started, the driving shaft of the third motor 22 drives the sprocket 14 to rotate, and the sprocket 14 drives the chain belt 15 to drive. While the chain belt 15 is driving, the chain belt 15 moves the pipe material at the bottom layer through the shifting block 16. The pipe material at the top layer falls back to the middle of the stacked pipe material along the guide arc plate 23, and this is repeated, so that the pipe material at the bottom layer is moved to the top layer, and finally the pipe material moved from the bottom layer to the top layer is taken out individually.

[0057] In summary, the loading frame 3 is moved away from the rack 1 by the moving assembly, and the staff then uses the gantry crane to lift the pipes on the loading frame 3 of the corresponding layer, which is conducive to improving the convenience of taking the pipes on the rack 1.

[0058] The above are all preferred embodiments of the present application, and the protection scope of the present application is not limited thereto. Therefore, any equivalent changes made according to the structure, shape, and principle of the present application should be included in the protection scope of the present application.

Claims

1. A tube material library for laser cutting equipment, Features: The material rack comprises at least two equidistantly arranged material racks (1), the side walls of the material racks (1) are symmetrically provided with multiple layers of horizontal racks (2), the multiple layers of horizontal racks (2) are respectively distributed in a linear array along the vertical direction of the material rack (1), a loading material frame (3) is movably arranged on each layer of the horizontal racks (2), and each layer of the horizontal racks (2) is provided with a moving component for driving the loading material frame (3) to move; A turning frame (12) is arranged on one side of the loading material frame (3), a vertical frame (13) is symmetrically arranged on the top surface of the turning frame (12), a sprocket (14) is respectively arranged on one side of the two vertical frames (13) for lifting, a chain belt (15) is arranged at one end of the turning frame (12), the sprocket (14) is meshed with the chain belt (15), a plurality of shifting blocks (16) are arranged on the chain belt (15), the two vertical frames (13) are respectively provided with a lifting assembly for driving the sprocket (14) to lift, and the vertical frame (13) is provided with a driving member for driving the sprocket (14) to rotate; The lifting assembly comprises a second motor (17) and a screw rod (18); a lifting slot (19) is provided in the stand (13); a lifting block (20) is slidably arranged in the lifting slot (19); the sprocket (14) is rotatably arranged on one side of the lifting block (20); the screw rod (18) is rotatably arranged in the lifting slot (19); the screw rod (18) is threadedly penetrated through the lifting block (20); the second motor (17) is arranged on the top surface of the stand (13); and the driving shaft of the second motor (17) is coaxially connected with the screw rod (18); A pressure gear (21) is provided at one end of the turning frame (12), and the pressure gear (21) is meshed with the chain belt (15); The inner sides of the two vertical frames (13) are respectively provided with guide arc plates (23).

2. A tube material library for laser cutting equipment according to claim 1, Features: The moving assembly comprises a hydraulic cylinder (4), a guide rod (5) is provided at one end of the bottom surface of the loading frame (3), a guide groove (6) is provided at one end of the cross frame (2), the guide rod (5) is slidably arranged in the guide groove (6), the hydraulic cylinder (4) is slidably arranged on the top surface of the cross frame (2), and the telescopic end of the hydraulic cylinder (4) is fixedly connected to the loading frame (3).

3. A tube material library for laser cutting equipment according to claim 2, Features: A support platform (7) is provided at one end of the cross frame (2), a reciprocating frame (8) is provided on the top surface of the support platform (7), the reciprocating frame (8) is fixedly connected to the hydraulic cylinder (4), and the support platform (7) is provided with a reciprocating assembly for driving the reciprocating frame (8) to reciprocate.

4. A tube material library for laser cutting equipment according to claim 3, Features: The reciprocating assembly comprises a sector gear (9), the sector gear (9) is rotatably arranged in the reciprocating frame (8), the inner top wall and the inner bottom wall of the reciprocating frame (8) are both provided with racks (10), the sector gear (9) is meshed with the racks (10), and a first motor (11) is arranged on the support platform (7), and the driving shaft of the first motor (11) is coaxially connected with the sector gear (9).

5. A tube material library for laser cutting equipment according to claim 1, Features: The ratio of the length of the chain belt (15) to the distance between the two vertical frames (13) is 4:1.