Construction method for low-position construction and high-position assembly of offshore platform chunks
By constructing high-level assembly at the low-level of offshore platform modules, the problem of long assembly period of high-level traditional offshore platform modules is solved. The construction period is shortened, the cost is reduced and the construction efficiency is improved. It is suitable for scenarios in peak years of oil field development.
Patent Information
- Application Number
- CN202410661653.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-05-27
- Publication Date
- 2024-10-22
AI Technical Summary
The high-level final assembly of traditional offshore platform modules at offshore engineering sites takes a long time, resulting in delays in oil field production and economic impact. Especially in the peak years of oil field development, due to limitations of site and slideway resources, the overall schedule is extended.
The method of low-level construction and high-level assembly of offshore platform modules is adopted, including placing and building piers in the buffer area, final assembly of the module frame steel structure, transporting to the high-level area, performing jacking operations, installing drilling rig modules and living buildings, and arranging trailer slides. Channels and DSF, and the modules are positioned and shipped through weight transfer devices.
This method can save about 4-5 months of construction period, improve construction quality and efficiency, reduce production costs, shorten the period of final assembly and slideway occupation, and reduce the cost of module construction, transportation and jacking.
Smart Images

Figure CN118814737A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to a method for low-position construction and high-position assembly of offshore platform modules, belonging to the technical field of offshore petroleum engineering. Background Art
[0002] Traditional modular structures are assembled at high positions (slideway areas) at offshore sites. For the central platform, the construction and assembly period is about 13 to 15 months. In the peak years of oilfield development, the design and construction period will extend the overall schedule due to the constraints of the site and the number of slideway resources, which will have a certain impact on the economic feasibility of oilfield production. Summary of the invention
[0003] In view of the above technical problems, the present invention provides a method for low-level construction and high-level assembly of offshore platform modules, which has great advantages in improving construction quality and efficiency, reducing production costs, and shortening the period of assembly and slideway occupation. The construction scheme of the present invention can save about 4-5 months of construction time.
[0004] To achieve the above object, the present invention adopts the following technical solutions:
[0005] A method for low-position construction and high-position assembly of offshore platform modules, comprising:
[0006] Place construction pads in the cache area;
[0007] The assembly of the modular frame steel structure is carried out in the buffer area where the pier is constructed;
[0008] Transport the frame steel structure assembly to the high-level area by SPMT;
[0009] Arrange lifting equipment and carry out lifting operations on the modules;
[0010] The SPMT is removed, the weight transfer device is arranged, and the final assembly module is in place;
[0011] Install the drilling rig module and the living building on the general assembly module to obtain the offshore platform module;
[0012] Arrange the towing slide and DSF in place;
[0013] Weigh and transfer the offshore platform modules, and load them onto ships for departure.
[0014] The method for constructing offshore platform modules at low positions and assembling at high positions preferably involves placing construction piers in the buffer area. The specific process is as follows:
[0015] During the process of placing the pier pads, first place the pier pads on the layer under each column, with the bottom structure at a certain distance from the ground, and then place the lifting beam. Before placing the pier pads, the bearing capacity of the buffer area site must be checked. For sites that do not meet the construction requirements, the ground must be strengthened.
[0016] The method for constructing offshore platform modules at low position and high position is preferably to assemble the module frame steel structure in the buffer area of the construction pier, and the specific process is as follows:
[0017] During the final assembly of the structure, temporary supports are added to the bottom of the module and adjusted using SPMT.
[0018] The method for constructing offshore platform modules at low locations and assembling at high locations preferably involves transporting the frame steel structure assembly to the high-level area by SPMT. The specific process is as follows:
[0019] The SPMT transport frame steel structure is assembled to the high-level area, and attention needs to be paid to whether reinforcement is required in the area where the transport route crosses the trench.
[0020] The method for constructing offshore platform modules at low positions and assembling them at high positions preferably comprises arranging jacking equipment to carry out jacking operations on the modules. The specific process is as follows:
[0021] During the jacking operation, the jacking equipment is arranged in advance and the components are placed in place on the jacking equipment. After the jacking operation is completed, the weight transfer device is installed and the equipment is dismantled. The entire construction process is carried out in the high-position area, and the bearing capacity of the slideway area needs to be checked.
[0022] The offshore platform module low-position construction and high-position assembly construction method is preferably to withdraw the SPMT, arrange the weight transfer device, and put the final assembly module in place. The specific process is as follows:
[0023] When the weight transfer device is in place, the weight transfer device and the pier below need to be arranged in advance at the horizontal rear position of each duct leg during the jacking stage. After jacking to the predetermined height, the weight transfer device is dragged or the SPMT is in place, the jacking height is lowered, and the weight is transferred to the weight transfer device.
[0024] The present invention adopts the above technical solution, which has the following advantages:
[0025] 1. The assembly blocks of the present invention are constructed at a low position (buffer area) and assembled at a high position (slideway area), which can improve construction quality and efficiency, reduce production costs, and shorten the period of assembly and slideway occupation.
[0026] 2. The construction method of the present invention can reduce the cost of module construction, transportation and jacking when the transportation and assembly period of the jacket is limited. BRIEF DESCRIPTION OF THE DRAWINGS
[0027] Figure 1 A schematic diagram of an upper assembly block of eight legs provided in one embodiment of the present invention;
[0028] Figure 2 A schematic diagram of a slideway area and a buffer area provided in this embodiment of the present invention;
[0029] Figure 3 A schematic diagram of the placement of construction piers (lifting beams into place) provided in this embodiment of the present invention;
[0030] Figure 4 A schematic diagram of the weight transfer device provided in this embodiment of the present invention in place;
[0031] Figure 5 A schematic diagram of the installation of drilling rig modules and living buildings provided in this embodiment of the present invention;
[0032] Figure 6 A schematic diagram of the arrangement of the dragging slide block and the DSF in place provided in this embodiment of the present invention;
[0033] Figure 7 This is a schematic diagram of weighing and weight transfer for loading onto a ship for sea transport provided in this embodiment of the present invention. DETAILED DESCRIPTION
[0034] In order to make the purpose, technical solution and advantages of the present invention clearer, the technical solution of the present invention is described clearly and completely below. Obviously, the described embodiments are part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary persons in the art without creative work are within the scope of protection of the present invention.
[0035] Unless otherwise defined, the technical or scientific terms used in the present invention shall have the usual meanings understood by persons with ordinary skills in the field to which the present invention belongs. The words "first", "second", "third", "fourth" and similar terms used in the present invention do not indicate any order, quantity or importance, but are only used to distinguish different components. Words such as "include" or "comprise" and the like mean that the elements or objects appearing before the word include the elements or objects listed after the word and their equivalents, without excluding other elements or objects. Words such as "connect" or "connected" and the like are not limited to physical or mechanical connections, but may include electrical connections, whether direct or indirect.
[0036] For ease of description, spatially relative terms may be used herein to describe the relationship of one element or feature relative to another element or feature as shown in the figures, such as "inside", "outside", "inner side", "outer side", "below", "above", etc. Such spatially relative terms are intended to include different orientations of the device in use or operation in addition to the orientation depicted in the figures.
[0037] Traditional modular structures are assembled at high positions (slideway areas) at offshore sites. For the central platform, the construction and assembly period is about 13 to 15 months. In the peak years of oilfield development, the design and construction period will extend the overall schedule due to the constraints of the site and the number of slideway resources, which will have a certain impact on the economic feasibility of oilfield production.
[0038] Based on the above problems, the present invention provides a method for low-level construction and high-level assembly of offshore platform modules, which has great advantages in improving construction quality and efficiency, reducing production costs, and shortening the period of assembly and slideway occupation. The construction scheme of the present invention can save about 4-5 months of construction time.
[0039] like Figure 1-Figure 7 As shown, the present invention takes an upper module of an eight-leg jacket platform as an example, the main leg span is (14m+48m+14m)×20m, and the total weight of the module excluding the living building, torch arm, DES, and DSM is about 12,700 tons. This construction scheme can achieve the effect of reducing the cost of module construction, transportation, and jacking when the jacket transportation and assembly period is limited. The specific implementation method is as follows: The modules are constructed at a low location (cache area) in the offshore engineering site and assembled at a high location.
[0041] The entire construction process includes: 1) placing construction pads in the buffer area; 2) assembling the module frame steel structure in the buffer area; 3) transporting the frame steel structure assembly to the high-level area by SPMT; 4) arranging the jacking equipment and jacking the module; 5) withdrawing the SPMT, arranging the weight transfer device, and putting the assembly module in place; 6) installing the drilling rig module and the living building on the assembly module to obtain the offshore platform module; 7) arranging the towing slideway and DSF in place; 8) weighing and transferring the weight of the offshore platform module, and loading the offshore platform module into the sea.
[0042] In step 1), when placing the pier pads, first place the 1.5m*2m*4m pier pads under each column. The bottom structure is about 10m from the ground. Then place the lifting beam. Before placing the pier pads, the bearing capacity of the buffer area site must be checked. For sites that do not meet the construction requirements, the ground must be strengthened (reinforced concrete can be used).
[0043] During the assembly of the frame steel structure in step 2), temporary supports are added to the bottom of the module and adjusted using SPMT.
[0044] In step 3), the SPMT is transported to the high-level area, and attention needs to be paid to whether the transportation route across the trench area needs to be reinforced.
[0045] During the jacking operation in step 4), the jacking equipment is arranged in advance, and the assembly is placed in place on the jacking equipment. After the jacking operation is completed, the weight transfer device is installed and the equipment is removed. The entire construction process is carried out in the high-position area, and the bearing capacity of the slideway area must be checked.
[0046] When the weight transfer device is in place in step 5), the weight transfer device and the cement pad below need to be arranged in advance at the horizontal rear position of each conduit leg during the jacking stage. After jacking to the predetermined height, the weight transfer device is dragged or SPMT (or slid using the sliding equipment of the jacking manufacturer) into place. Lower the jacking height and transfer the weight to the weight transfer device.
[0047] The assembly of the present invention is constructed at a low position (buffer area) and assembled at a high position (slideway area), which can improve construction quality and efficiency, reduce production costs, and shorten the period of assembly and slideway occupation. The construction method of the present invention can achieve the effect of reducing the cost of assembly, transportation and jacking of the assembly when the transportation and assembly period of the jacket is limited.
[0048] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention, rather than to limit it. Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that they can still modify the technical solutions described in the aforementioned embodiments, or make equivalent replacements for some of the technical features therein. However, these modifications or replacements do not deviate the essence of the corresponding technical solutions from the spirit and scope of the technical solutions of the embodiments of the present invention.
Claims
1. A method for low-level construction and high-level assembly of offshore platform modules, characterized in that: include: Place construction pads in the cache area; The assembly of the modular frame steel structure is carried out in the buffer area where the pier is constructed; Transport the frame steel structure assembly to the high-level area by SPMT; Arrange lifting equipment and carry out lifting operations on the modules; The SPMT is removed, the weight transfer device is arranged, and the final assembly module is in place; Install the drilling rig module and the living building on the general assembly module to obtain the offshore platform module; Arrange the towing slide and DSF in place; Weigh and transfer the offshore platform modules, and load them onto ships for departure.
2. The method for low-level construction and high-level assembly of offshore platform modules according to claim 1 is characterized in that: Place the construction piers in the buffer area. The specific process is as follows: During the process of placing the pier pads, first place the pier pads on the layer under each column, with the bottom structure at a certain distance from the ground, and then place the lifting beam. Before placing the pier pads, the bearing capacity of the buffer area site must be checked. For sites that do not meet the construction requirements, the ground must be strengthened.
3. The method for low-level construction and high-level assembly of offshore platform modules according to claim 1 is characterized in that: The assembly of the block frame steel structure is carried out in the buffer area where the pier is built. The specific process is as follows: During the final assembly of the structure, temporary supports are added to the bottom of the module and adjusted using SPMT.
4. The method for low-level construction and high-level assembly of offshore platform modules according to claim 1 is characterized in that: The frame steel structure assembly is transported to the high-level area by SPMT. The specific process is as follows: The SPMT transport frame steel structure is assembled to the high-level area, and attention needs to be paid to whether reinforcement is required in the area where the transport route crosses the trench.
5. The method for low-level construction and high-level assembly of offshore platform modules according to claim 1 is characterized in that: Arrange the lifting equipment and carry out lifting operation on the module. The specific process is as follows: During the jacking operation, the jacking equipment is arranged in advance and the components are placed in place on the jacking equipment. After the jacking operation is completed, the weight transfer device is installed and the equipment is dismantled. The entire construction process is carried out in the high-position area, and the bearing capacity of the slideway area needs to be checked.
6. The method for low-level construction and high-level assembly of offshore platform modules according to claim 1, characterized in that: The SPMT is removed, the weight transfer device is arranged, and the assembly module is in place. The specific process is as follows: When the weight transfer device is in place, the weight transfer device and the pier below need to be arranged in advance at the horizontal rear position of each duct leg during the jacking stage. After jacking to the predetermined height, the weight transfer device is dragged or the SPMT is in place, the jacking height is lowered, and the weight is transferred to the weight transfer device.