Supporting device for building construction and supporting method thereof

By designing a convenient support device, using screw rods and driving mechanisms to realize convenient installation and removal of support plates, and improving the support effect through anchor rods, drainage pipes and pumping components, it solves the problem of difficulty in recycling support components in the existing technology. In order to solve the problem of collapse in rainy days, the recycling of supporting components and the improvement of the stability of the side walls of the foundation pit were realized.

CN118814818APending Publication Date: 2024-10-22NANTONG XINHUA CONSTR GROUP
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411205052.2
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-30
Publication Date
2024-10-22

AI Technical Summary

Technical Problem

In the existing foundation pit support technology, support components are difficult to recycle, installation and disassembly are cumbersome, and the side walls of the foundation pit are prone to collapse in rainy weather.

Method used

Design a support device for building construction, including a connecting plate, a screw rod and a driving mechanism. The support plate can be easily installed and disassembled through the threaded cooperation of the screw rod and the push block, and through the anchor rod and nut, drainage pipe and water pumping The components improve the support effect and the stability of the pit side walls.

Benefits of technology

It realizes the recycling of supporting components, simplifies the installation and disassembly process, reduces the possibility of loosening of supporting plates and collapse of the side walls of the foundation pit, and improves the stability of the foundation pit in rainy weather.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118814818A_ABST
    Figure CN118814818A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of foundation pit supporting, and particularly discloses a supporting device for building construction and a supporting method thereof. Grooves are formed in the two ends of the connecting plate, and a cavity is formed in the connecting plate. The inner side wall of the cavity is rotationally connected with a lead screw. The two ends of the lead screw extend into the two grooves correspondingly, and the ends, extending into the two grooves, of the lead screw are each sleeved with a push block with one end extending out of the corresponding groove. The two pushing blocks are in sliding fit with the inner side walls of the two grooves correspondingly, the pushing blocks are in threaded transmission fit with the lead screws, and supporting plates are installed on the outer side walls of the ends, extending out of the grooves, of the two pushing blocks correspondingly; threads, matched with the two push blocks, of the lead screw are symmetrically arranged; a driving mechanism capable of driving the screw rod to rotate is arranged in the cavity; the lead screw is driven to rotate through the driving mechanism, the two pushing blocks are promoted to drive the two supporting plates to abut against the side wall of the foundation pit, supporting of the foundation pit is achieved, and the troubles that when supporting is conducted through a concrete wall, supporting components are tedious to mount and dismount, and the supporting components cannot be recycled are reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of foundation pit support, and in particular to a support device and a support method for building construction. Background Art

[0002] During the construction process, it is necessary to excavate a foundation pit on the foundation. After the foundation pit is excavated, in order to protect the safety of the underground main structure construction and the environment around the foundation pit, it is necessary to set up a foundation pit support device to support the pressure on the side walls of the foundation pit, resist the soil around the foundation pit, prevent the soil from sliding down, and reduce the possibility of deformation of the foundation pit.

[0003] In the prior art, during the foundation pit construction process, a combination of steel supports and concrete walls is often used to support the foundation pit. Although this support method can support the foundation pit, it has the problem that the supporting components cannot be well recycled and the installation and removal are relatively cumbersome. Summary of the invention

[0004] The present application provides a supporting device and a supporting method for building construction, which can conveniently realize the supporting work of foundation pit, and the supporting components can be recycled and reused after the supporting is completed.

[0005] The present application provides a support device for construction and a support method thereof, which adopts the following technical solutions: A supporting device for building construction, comprising a connecting plate; grooves are provided at both ends of the connecting plate, and a cavity is provided inside the connecting plate in the middle of the two grooves; a screw rod is rotatably connected to the inner wall of the cavity; both ends of the screw rod extend into the two grooves respectively, and the ends of the screw rod extending into the two grooves are sleeved with push blocks with one end extending to the outside of the grooves; the two push blocks are respectively slidably matched with the inner walls of the two grooves, and the push blocks are threadedly matched with the screw rod, and support plates are installed on the outer walls of the ends of the two push blocks extending to the outside of the grooves; the threads of the screw rod and the two push blocks are symmetrically arranged; a driving mechanism that can drive the screw rod to rotate is provided in the cavity.

[0006] By adopting the above technical scheme, when it is necessary to support the side wall of the foundation pit, the two supporting plates are respectively installed at the ends of the two push blocks, and then the connecting plate installed with the supporting plates is placed in the foundation pit, and the screw rod is driven to rotate by the driving mechanism, and the threads of the screw rod and the two push blocks are symmetrically arranged, so that the two push blocks slide in the directions away from each other, prompting the two supporting plates to respectively press against the two inner walls of the foundation pit to support the foundation pit and reduce the possibility of collapse of the side wall of the foundation pit. The overall structure of the device is easy to assemble and disassemble, and the components can be recycled after the support is completed, reducing the cumbersome installation and disassembly of the support components when supporting through the concrete wall, and the trouble of non-recyclable support components.

[0007] Preferably, the screw rod is coaxially fixed with a first bevel gear on the outer wall inside the cavity; the driving mechanism includes a rotating shaft and a locking assembly; the rotating shaft is rotatably connected to the inner wall at the top end of the cavity, and the bottom end of the rotating shaft is coaxially fixed with a second bevel gear meshing with the first bevel gear; the locking assembly is arranged at the end of the rotating shaft away from the second bevel gear, and the locking assembly can lock the rotating shaft.

[0008] By adopting the above technical scheme, when supporting the foundation pit with the support plates, the staff drives the second bevel gear to rotate by rotating the rotating shaft. Under the meshing cooperation of the first bevel gear and the second bevel gear, the rotating shaft drives the screw to rotate, so that the two push blocks drive the two support plates to move away from each other and press against the inner wall of the foundation pit. After the support plates press against the side walls of the foundation pit, the rotating shaft is locked by the locking assembly, so that the positions of the two push blocks remain stable, so that the support plates firmly support the side walls of the foundation pit.

[0009] Preferably, a rectangular groove is provided on the top surface of the connecting plate at a position corresponding to the rotating shaft; the top end of the rotating shaft extends into the rectangular groove, and a rectangular cavity is provided inside the end of the rotating shaft away from the second bevel gear; the locking assembly includes a rectangular block and a clamping block; the rectangular block is slidably connected to the inner wall of the rectangular cavity, and a connecting rod is fixedly connected to the top surface of the rectangular block; the end of the connecting rod away from the rectangular block can extend into the groove; the clamping block is fixedly connected to the end of the connecting rod away from the rectangular block, and the clamping block can be clamped in the rectangular groove to lock the rotating shaft.

[0010] By adopting the above technical solution, when the clamping block is located outside the rectangular groove, the rotating shaft is in an active state. When the clamping block is rotated, the clamping block drives the rotating shaft to rotate through the cooperation of the connecting rod and the rectangular block. By rotating the clamping block, the two supporting plates can be driven to slide away from each other and press against the side walls of the foundation pit; when the supporting plates are pressed against the side walls of the foundation pit, the clamping block is moved down to clamp the clamping block into the rectangular groove. The rotating shaft is locked through the cooperation of the clamping block and the inner wall of the rectangular groove, so that the positions of the two push blocks remain stable.

[0011] Preferably, a first magnetic sheet is fixedly connected to the inner side wall of the bottom end of the rectangular groove; a second magnetic sheet that can contact the first magnetic sheet is fixedly connected to the bottom surface of the block; and the first magnetic sheet and the second magnetic sheet have opposite magnetic properties.

[0012] By adopting the above technical solution, after the card block is inserted into the rectangular groove, the magnetic attraction between the first magnetic sheet and the second magnetic sheet improves the stability of the card block in the rectangular groove, thereby reducing the possibility of the card block being accidentally pulled out.

[0013] Preferably, a first through hole is opened on the support plate; an anchor rod is inserted into the first through hole and penetrates the support plate and is embedded in the foundation pit; a nut is threadedly connected on the outer wall of the rear end of the anchor rod to press the support plate against the side wall of the foundation pit.

[0014] By adopting the above technical solution, when the support plate is supporting the foundation pit, the anchor rod is inserted into the inside of the side wall of the foundation pit after passing through the first through hole, and a nut is sleeved on the tail of the anchor rod to tighten the support plate, so that the support plate is tightly attached to the side wall of the foundation pit, the possibility of the support plate loosening is reduced, and the supporting effect of the support plate is improved.

[0015] Preferably, a second through hole is provided on the support plate; a drainage pipe is passed through the second through hole and penetrates the support plate and is embedded in the foundation pit; a water leakage port is provided on the inner wall at the top end of the drainage pipe; a first filter screen is fixedly connected to the inner wall of the leakage port; a water collecting chamber is provided inside the support plate; a guide pipe connecting the drainage pipe and the water collecting chamber is fixedly connected to the outer wall at one end of the drainage pipe; a pumping assembly is provided on the side wall of the support plate; the pumping assembly can pump water out of the water collecting chamber.

[0016] By adopting the above technical solution, the drainage pipe is inserted into the inside of the side wall of the foundation pit through the second through hole. Rainwater that penetrates into the inside of the side wall of the foundation pit in rainy days flows into the drainage pipe through the leakage hole and then flows into the water collecting chamber through the guide pipe. The rainwater in the water collecting chamber is pumped out and discharged through the drainage component, thereby reducing the water content inside the side wall of the foundation pit, improving the stability of the side wall of the foundation pit, and reducing the possibility of collapse of the side wall of the foundation pit due to excessive water content inside the side wall of the foundation pit. The first filter is set to filter mud and sand impurities, so that mud and sand impurities are not easy to enter the drainage pipe.

[0017] Preferably, the pumping assembly includes a pump body; the pump body is installed on the side wall of the support plate, the input end of the pump body is fixedly connected to a water inlet pipe connected to the inside of the water collecting chamber, and the output end of the pump body is fixedly connected to a water outlet pipe connected to the external environment.

[0018] By adopting the above technical solution, the pump body is started to pump out the rainwater in the water collecting chamber, and the rainwater is discharged to the outside of the water collecting chamber through the water inlet pipe and the water outlet pipe, thereby conveniently realizing the discharge of rainwater in the water collecting chamber.

[0019] Preferably, a water receiving box is fixedly connected to the top surface of the support plate; a connecting pipe is fixedly connected to the inner wall of the top end of the water collecting chamber; the top end of the connecting pipe extends to the inner wall of the bottom end of the water receiving box, and the connecting pipe connects the water receiving box and the water collecting chamber.

[0020] By adopting the above technical solution, rainwater flowing down from the top of the side wall of the foundation pit in rainy days will flow into the water receiving box, and the rainwater in the water receiving box will then enter the water accumulation cavity through the connecting pipe for discharge, thereby reducing the possibility of rainwater flowing over a large area in the gap between the support plate and the side wall of the foundation pit and carrying away the soil between the support plate and the side wall of the foundation pit, thereby improving the stability of the side wall of the foundation pit.

[0021] Preferably, a second filter screen is fixedly connected to the inner wall at the top end of the connecting pipe.

[0022] By adopting the above technical solution, the second filter is used to filter the rainwater flowing into the connecting pipe, thereby reducing the possibility of mud and sand impurities mixed in the rainwater entering the water collection chamber.

[0023] A supporting method for a supporting device for building construction, based on the above-mentioned supporting device for building construction, the supporting method comprises the following steps: S1: Install the two support plates on the two push block ends of the connecting plate so that the two support plates and the connecting plate are combined to form an I-shaped whole; S2: Install the I-shaped overall structure in the foundation pit, and drive the two supporting plates to press against the two inner walls of the foundation pit respectively through the driving mechanism; S3: insert the anchor rod through the support plate and embed it into the side wall of the foundation pit, and sleeve a nut on the tail of the anchor rod to press the support plate onto the side wall of the foundation pit; S4: The drainage pipe is passed through the support plate and embedded into the side wall of the foundation pit, thereby completing the installation of the support device in the foundation pit.

[0024] In summary, this application has the following beneficial effects: 1. When supporting the foundation pit, the connecting plate with the supporting plate installed is placed in the foundation pit, and the screw rod is driven to rotate by the driving mechanism, so that the two push blocks drive the two supporting plates to slide in the direction away from each other and press against the side wall of the foundation pit, thereby achieving the support work of the foundation pit. The overall structure of the device is easy to assemble and disassemble, and the supporting components can be recycled after the support is completed, which reduces the cumbersome installation and disassembly of the supporting components when supporting through the concrete wall, and the trouble of non-recyclable supporting components; 2. The support plate is pressed against the side wall of the foundation pit through the cooperation of the anchor rod and the nut, so that the support plate is in close contact with the side wall of the foundation pit, reducing the possibility of loosening of the support plate and further improving the support effect of the support plate on the side wall of the foundation pit; 3. Rainwater that penetrates from the top of the foundation pit into the side walls of the foundation pit in rainy days flows into the drainage pipe through the leak, and then enters the water collection chamber through the diversion pipe, thereby reducing the possibility of collapse of the side walls of the foundation pit due to high water content in rainy days; rainwater that flows down from the surface of the foundation pit along the inner wall of the foundation pit falls into the water collection box, and then enters the water collection chamber through the connecting pipe, thereby reducing the possibility of rainwater flowing in the gap between the support plate and the side walls of the foundation pit over a large area and carrying away the soil on the side walls of the foundation pit, thereby improving the stability of the foundation pit in rainy days. BRIEF DESCRIPTION OF THE DRAWINGS

[0025] Figure 1 It is a structural schematic diagram of a support device for building construction in this application; Figure 2 It is a schematic diagram of the matching structure of the connecting plate, the push block and the driving mechanism in this application; Figure 3 yes Figure 2The enlarged view of point A in the middle; Figure 4 It is a schematic diagram of the matching structure of the rotating shaft and the locking assembly in this application; Figure 5 It is a schematic diagram of the matching structure of the support plate and the anchor rod in this application; Figure 6 It is a schematic diagram of the matching structure of the support plate, drain pipe and pumping assembly in this application.

[0026] Explanation of the reference numerals: 1. connecting plate; 11. groove; 12. cavity; 13. rectangular groove; 131. first magnetic sheet; 2. screw rod; 21. first bevel gear; 3. push block; 4. support plate; 41. first through hole; 42. second through hole; 43. water collecting chamber; 431. water inlet pipe; 44. water receiving box; 45. connecting pipe; 451. second filter screen; 5. driving mechanism; 51. rotating shaft; 511. rectangular cavity; 52. locking assembly; 521. rectangular block; 522. clamping block; 523. connecting rod; 53. second bevel gear; 54. second magnetic sheet; 6. anchor rod; 61. nut; 7. drain pipe; 71. water leakage port; 72. first filter screen; 73. guide pipe; 8. pumping assembly; 81. pump body; 82. water inlet pipe; 83. water outlet pipe. DETAILED DESCRIPTION

[0027] The present invention will be further described in detail below with reference to the accompanying drawings. The same components are denoted by the same reference numerals. It should be noted that the terms "front", "rear", "left", "right", "upper", "lower", "bottom" and "top" used in the following description refer to directions in the accompanying drawings, and the terms "inside" and "outside" refer to directions toward or away from the geometric center of a specific component, respectively.

[0028] The present invention discloses a supporting device for building construction, such as Figure 1 and Figure 2 As shown, it includes a connecting plate 1, a screw rod 2 and a driving mechanism 5. Rectangular grooves 11 are provided at both ends of the connecting plate 1. A cavity 12 is provided inside the connecting plate 1 at the middle position of the two grooves 11. The screw rod 2 is horizontally rotatably connected to the inner wall of the cavity 12. Both ends of the screw rod 2 extend into the two grooves 11 respectively. Both ends of the screw rod 2 extending into the grooves 11 are sleeved with push blocks 3 that are threadedly matched with the screw rod 2. The threads on the screw rod 2 that are matched with the two push blocks 3 are symmetrically arranged. The two push blocks 3 are respectively slidably matched with the inner walls of the two grooves 11, and the ends of the two push blocks 3 that are away from each other extend to the outside of the two ends of the connecting plate 1 respectively. The ends of the two push blocks 3 extending outside the connecting plate 1 are detachably connected to the support plate 4 by bolts; the driving mechanism 5 is arranged inside the cavity 12, and the driving mechanism 5 can drive the screw rod 2 to rotate so that the push blocks 3 drive the support plate 4 to press against the side wall of the foundation pit.

[0029] When supporting the side walls of the foundation pit, the connecting plate 1 equipped with the supporting plate 4 is placed in the foundation pit, and the screw rod 2 is driven to rotate by the driving mechanism 5, so that the two push blocks 3 drive the two supporting plates 4 to move away from each other and press against the side walls of the foundation pit, thereby supporting the side walls of the foundation pit. The device as a whole is easy to assemble and disassemble. After the support is completed, the supporting plate 4 and the connecting plate 1 can be disassembled and reused, thereby reducing the trouble of supporting the side walls of the foundation pit through concrete walls and the inconvenience of reusing the supporting components.

[0030] like Figure 1 , Figure 2 and Figure 3 As shown, the screw rod 2 is coaxially fixed with the first bevel gear 21 on the outer wall inside the cavity 12, and the driving mechanism 5 includes a rotating shaft 51, a second bevel gear 53 and a locking assembly 52; the rotating shaft 51 is vertically rotatably connected to the inner wall at the top end of the cavity 12, the second bevel gear 53 is coaxially fixed to the bottom end of the rotating shaft 51, the second bevel gear 53 is meshed with the first bevel gear 21, and the end of the rotating shaft 51 away from the second bevel gear 53 extends to the top surface of the connecting plate 1, and the locking assembly 52 is arranged at the top end of the rotating shaft 51, and the locking assembly 52 can lock the rotating shaft 51.

[0031] The second bevel gear 53 is driven to rotate by rotating the rotating shaft 51, and the rotating shaft 51 drives the screw rod 2 to rotate under the meshing cooperation of the first bevel gear 21 and the second bevel gear 53, thereby prompting the two push blocks 3 to drive the two support plates 4 to press against the side walls of the foundation pit. After the support plates 4 press against the side walls of the foundation pit, the rotating shaft 51 is locked by the locking assembly 52, so that the two push blocks 3 remain stable and the possibility of loosening of the support effect of the support plates 4 is reduced.

[0032] like Figure 2 , Figure 3 and Figure 4 As shown, a rectangular groove 13 is provided on the top surface of the connecting plate 1 at a position corresponding to the rotating shaft 51, the center of the inner side wall at the bottom end of the rectangular groove 13 is located on the axis of the rotating shaft 51, and a coaxial rectangular cavity 511 in the vertical direction is provided inside the top end of the rotating shaft 51. The locking assembly 52 includes a rectangular block 521, a connecting rod 523 and a clamping block 522. The rectangular block 521 is slidably connected to the inner side wall of the rectangular cavity 511, one end of the connecting rod 523 is fixedly connected to the top surface of the rectangular block 521, the end of the connecting rod 523 away from the rectangular block 521 passes through the top side wall of the rectangular cavity 511 and extends into the rectangular groove 13, the connecting rod 523 slides with the top side wall of the rectangular cavity 511, the clamping block 522 is fixedly connected to the end of the connecting rod 523 away from the rectangular block 521, the clamping block 522 moves down to the rectangular groove 13 and fits with the inner side wall of the rectangular groove 13 to lock the rotating shaft 51, and the clamping block 522 can move up to the top of the rectangular groove 13 to contact and lock the rotating shaft 51.

[0033] By pulling the card block 522 to different positions, the rotating shaft 51 can be easily put into an active and locked state respectively. When the card block 522 is pulled to the outside of the rectangular groove 13, the rotating shaft 51 is in an active state, and the staff can drive the rotating shaft 51 to rotate by rotating the card block 522. When the card block 522 is stuck in the rectangular groove 13, the rotating shaft 51 is locked through the cooperation of the card block 522 and the inner wall of the rectangular groove 13, thereby prompting the positions of the two push blocks 3 to remain stable.

[0034] like Figure 3 As shown, a first magnetic sheet 131 is fixedly connected to the inner side wall of the bottom end of the rectangular groove 13, and a second magnetic sheet 54 that can contact the first magnetic sheet 131 is fixedly connected to the bottom surface of the block 522. The surfaces where the first magnetic sheet 131 and the second magnetic sheet 54 contact each other have opposite magnetic properties.

[0035] The magnetic force of the first magnetic sheet 131 and the second magnetic sheet 54 improves the stability of the clamping block 522 in the rectangular groove 13 , thereby reducing the possibility of the clamping block 522 being accidentally pulled out of the rectangular groove 13 .

[0036] like Figure 1 and Figure 5 As shown, the support plate 4 is rectangular in shape, and a group of first through holes 41 are opened on the support plate 4. The group of first through holes 41 are respectively located at the four corners of the support plate 4. An anchor rod 6 that passes through the support plate 4 is horizontally inserted in each first through hole 41. The outer wall of the anchor rod 6 slides with the inner wall of the first through hole 41. The head of the anchor rod 6 is in a pointed cone shape and embedded in the inside of the side wall of the foundation pit. The tail is exposed to the outside of the support plate 4, and a thread is provided on the outer wall of the tail; a nut 61 is threadedly connected at the threaded position of the tail of each anchor rod 6, and the nut 61 is sleeved on the threaded position of the tail of the anchor rod 6 to press the support plate 4 on the side wall of the foundation pit.

[0037] After the anchor rod 6 is inserted through the supporting plate 4 and embedded into the side wall of the foundation pit, the supporting plate 4 is compressed by the nut 61 to make the supporting plate 4 close to the side wall of the foundation pit, reduce the possibility of loosening of the supporting plate 4, and improve the supporting effect of the supporting plate 4 on the side wall of the foundation pit.

[0038] like Figure 5 and Figure 6As shown, the support plate 4 is provided with a plurality of second through holes 42 arranged at intervals, and a drainage pipe 7 penetrating through the support plate 4 and embedded in the side wall of the foundation pit is horizontally penetrated in the second through hole 42. The outer wall of the drainage pipe 7 is slidably matched with the inner wall of the second through hole 42. The two ends of the drainage pipe 7 are closed and the interior is hollow. The end of the drainage pipe 7 embedded in the side wall of the foundation pit is in a pointed cone shape. A plurality of leakage holes 71 arranged at intervals along the axial direction of the drainage pipe 7 are provided on the top surface of the drainage pipe 7, and a first filter screen 7 is fixedly connected to the inner wall of each leakage hole 71. 2; A water collecting chamber 43 is provided inside the supporting plate 4 at a position lower than the second through hole 42; a plurality of water inlet pipes 431 extending to the outside of the supporting plate 4 are fixedly connected to the inner side wall of the water collecting chamber 43 near the top; an end of each drain pipe 7 away from the pointed cone-shaped end is fixedly connected to a guide pipe 73 connected to the inside of the drain pipe 7; ends of the plurality of guide pipes 73 away from the drain pipe 7 are detachably connected to the plurality of water inlet pipes 431 through flanges; the guide pipe 73 and the water inlet pipe 431 connect the drain pipe 7 with the water collecting chamber 43.

[0039] Rainwater that penetrates into the side walls of the foundation pit from the top surface of the foundation pit in rainy days enters the drain pipe 7 through the leak 71. The rainwater in the drain pipe 7 enters the water collecting chamber 43 through the guide pipe 73 and the water inlet pipe 431 and is stored, thereby reducing the possibility of collapse of the side walls of the foundation pit due to high water content in rainy days and improving the stability of the side walls of the foundation pit. The first filter screen 72 is provided to filter the rainwater flowing into the drain pipe 7 to reduce the possibility of mud and sand impurities entering the drain pipe 7.

[0040] like Figure 1 , Figure 5 and Figure 6 As shown, a water receiving box 44 is fixedly connected to the top surface of the support plate 4, and the water receiving box 44 is funnel-shaped and attached to the inner wall of the foundation pit. A plurality of connecting pipes 45 arranged at intervals are fixedly connected to the inner wall of the top end of the water collecting chamber 43. The top end of the connecting pipe 45 passes through the side wall of the bottom end of the water receiving box 44 and extends to a position flush with the inner wall of the top end of the water receiving box 44. The connecting pipe 45 connects the water receiving box 44 and the water collecting chamber 43, and a second filter screen 451 is fixedly connected to the inner wall of the top end of each connecting pipe 45.

[0041] In a rainy environment, rainwater flowing from the top surface of the foundation pit to the side wall of the foundation pit will flow into the water collecting chamber 43 through the connecting pipe 45 at the bottom of the water collecting box 44, thereby reducing the possibility of rainwater flowing in a large range in the gap between the support plate 4 and the side wall of the foundation pit, avoiding the soil on the side wall of the foundation pit from being washed away by rainwater, and improving the stability of the foundation pit. The second filter screen 451 is set to filter rainwater to reduce the possibility of impurities in rainwater entering the water collecting chamber 43.

[0042] like Figure 5 and Figure 6As shown, a pumping assembly 8 is provided on the side wall of the support plate 4, and the pumping assembly 8 is provided with a pump body 81, a water inlet pipe 82 and a water outlet pipe 83. The pump body 81 is installed on the outer wall of the support plate 4, one end of the water inlet pipe 82 is fixedly connected to the input end of the pump body 81, and the end of the water inlet pipe 82 away from the pump body 81 is fixedly connected to the inner wall of the water collecting chamber 43 near the bottom; one end of the water outlet pipe 83 is fixedly connected to the output end of the pump body 81, and the end of the water outlet pipe 83 away from the pump body 81 is connected to the external environment.

[0043] When rainwater accumulates in the water collecting chamber 43 , the pump body 81 is started to discharge the rainwater in the water collecting chamber 43 to the external environment through the water inlet pipe 82 and the water outlet pipe 83 , thereby conveniently realizing the convenient discharge of rainwater in the water collecting chamber 43 .

[0044] A supporting method for a supporting device for building construction, the supporting method comprising the following steps: S1: The two support plates 4 are respectively mounted on the ends of the two push blocks 3 at the two ends of the connecting plate 1 by bolts, so that the two support plates 4 and the connecting plate 1 are combined to form an I-shaped whole; S2: Install the I-shaped integral structure in the foundation pit, and drive the screw 2 to rotate through the driving mechanism 5, so that the two push blocks 3 drive the two support plates 4 to move away from each other and press against the two inner walls of the foundation pit, so that the support plates 4 can support the side walls of the foundation pit. S3: insert the anchor rod 6 through the first through hole 41 on the support plate 4 and embed it into the side wall of the foundation pit, and sleeve the nut 61 on the tail of the anchor rod 6 to press the support plate 4 on the side wall of the foundation pit, so as to make the support plate 4 close to the side wall of the foundation pit and improve the support effect of the support plate 4; S4: The drainage pipe 7 is passed through the support plate 4 and embedded into the side wall of the foundation pit, thereby completing the installation of the support device in the foundation pit. The rainwater that penetrates into the side wall of the foundation pit is diverted through the set drainage pipe 7, thereby reducing the possibility of collapse of the side wall of the foundation pit due to high water content and improving the stability of the side wall of the foundation pit.

[0045] Working principle: when supporting the foundation pit, the connecting plate 1 with the supporting plate 4 installed is placed in the foundation pit, and the staff pulls out the clamping block 522 located on the top surface of the connecting plate 1 from the clamping groove and rotates the clamping block 522. Under the cooperation of the connecting rod 523 and the rectangular block 521, the clamping block 522 drives the rotating shaft 51 and the second bevel gear 53 to rotate. Under the meshing cooperation of the first bevel gear 21 and the second bevel gear 53, the rotating shaft 51 drives the screw rod 2 to rotate, thereby prompting the two push blocks 3 to drive the two supporting plates 4 to move in the direction away from each other and press against the two inner side walls of the foundation pit to support the foundation pit. After the supporting plates 4 press against the inner side walls of the foundation pit, the clamping block 522 is moved down to clamp the clamping block 522 into the rectangular groove 13. The rotating shaft 51 is locked by the cooperation of the clamping block 522 and the inner side wall of the rectangular groove 13, so that the positions of the two push blocks 3 remain stable, and the supporting plates 4 support the side walls of the foundation pit firmly. The anchor rod 6 is inserted into the inner side wall of the foundation pit through the first through hole 41, and the support plate 4 is pressed against the side wall of the foundation pit by the nut 61 at the tail of the anchor rod 6, so that the support plate 4 is closely attached to the side wall of the foundation pit, the possibility of loosening of the support plate 4 is reduced, and the support effect of the support plate 4 is improved; The drainage pipe 7 is inserted into the inside of the side wall of the foundation pit through the second through hole 42. In a rainy day environment, rainwater that penetrates into the inside of the side wall of the foundation pit from the top surface of the foundation pit flows into the drainage pipe 7 through the leaking port 71, and the rainwater enters the water collecting chamber 43 through the guide pipe 73, thereby reducing the possibility of collapse of the inside of the side wall of the foundation pit due to the high water content in a rainy day environment; rainwater flowing down from the surface of the foundation pit along the inner wall of the foundation pit falls into the water receiving box 44, and the rainwater enters the water collecting chamber 43 through the connecting pipe 45, thereby reducing the possibility of rainwater flowing in a large range in the gap between the support plate 4 and the side wall of the foundation pit and carrying away the soil on the side wall of the foundation pit, thereby improving the stability of the foundation pit in a rainy day environment, and when the rainwater in the water collecting chamber 43 is discharged, the pump body 81 is started to pump out the rainwater in the water collecting chamber 43 and discharge it to the external environment, thereby conveniently realizing the rainwater discharge work in the water collecting chamber 43.

[0046] The above are all preferred embodiments of the present application, and the protection scope of the present application is not limited thereto. Therefore, any equivalent changes made according to the structure, shape, and principle of the present application should be included in the protection scope of the present application.

Claims

1. A support device for building construction, Features: The invention comprises a connecting plate (1); grooves (11) are formed at both ends of the connecting plate (1); a cavity (12) is arranged inside the connecting plate (1) and is located in the middle of the two grooves (11); a screw rod (2) is rotatably connected to the inner wall of the cavity (12); the two ends of the screw rod (2) extend into the two grooves (11) respectively, and the ends of the screw rod (2) extending into the two grooves (11) are sleeved with a push block (3) with one end extending outside the groove (11); the two push blocks (3) are respectively slidably matched with the inner walls of the two grooves (11), the push blocks (3) and the screw rod (2) are threadedly matched, and the two push blocks (3) are installed with a supporting plate (4) on the outer wall of the end portions extending outside the groove (11); the threads of the screw rod (2) and the two push blocks (3) are arranged symmetrically; a driving mechanism (5) is arranged in the cavity (12) for driving the screw rod (2) to rotate.

2. A support device for construction according to claim 1, Features: The screw rod (2) is coaxially fixedly connected to the outer wall of the cavity (12); the driving mechanism (5) comprises a rotating shaft (51) and a locking assembly (52); the rotating shaft (51) is rotatably connected to the inner wall of the top end of the cavity (12); the bottom end of the rotating shaft (51) is coaxially fixedly connected to a second bevel gear (53) meshing with the first bevel gear (21); the locking assembly (52) is arranged at the end of the rotating shaft (51) away from the second bevel gear (53), and the locking assembly (52) can lock the rotating shaft (51).

3. A support device for construction according to claim 2, Features: A rectangular groove (13) is provided on the top surface of the connecting plate (1) at a position corresponding to the rotating shaft (51); the top end of the rotating shaft (51) extends into the rectangular groove (13), and a rectangular cavity (511) is provided inside the end of the rotating shaft (51) away from the second bevel gear (53); the locking assembly (52) comprises a rectangular block (521) and a clamping block (522); the rectangular block (521) is slidably connected to the inner wall of the rectangular cavity (511), and a connecting rod (523) is fixedly connected to the top surface of the rectangular block (521); the end of the connecting rod (523) away from the rectangular block (521) can extend into the groove (11); the clamping block (522) is fixedly connected to the end of the connecting rod (523) away from the rectangular block (521), and the clamping block (522) can be clamped in the rectangular groove (13) to lock the rotating shaft (51).

4. A supporting device for construction according to claim 3, Features: A first magnetic sheet (131) is fixedly connected to the inner side wall of the bottom end of the rectangular groove (13); a second magnetic sheet (54) capable of contacting the first magnetic sheet (131) is fixedly connected to the bottom surface of the clamping block (522); and the first magnetic sheet (131) and the second magnetic sheet (54) have opposite magnetic properties.

5. A supporting device for construction according to claim 1, Features: The support plate (4) is provided with a first through hole (41); an anchor rod (6) is inserted into the first through hole (41) and penetrates through the support plate (4) and is embedded in the foundation pit; a nut (61) is threadedly connected on the outer side wall of the rear end of the anchor rod (6) and is pressed against the side wall of the foundation pit.

6. A supporting device for construction according to claim 1, Features: The support plate (4) is provided with a second through hole (42); a drainage pipe (7) is inserted into the second through hole (42) and penetrates the support plate (4) and is embedded in the foundation pit; a water leakage port (71) is provided on the inner side wall of the top end of the drainage pipe (7); a first filter screen (72) is fixedly connected to the inner side wall of the leakage port (71); a water collecting chamber (43) is provided inside the support plate (4); a guide pipe (73) connecting the drainage pipe (7) and the water collecting chamber (43) is fixedly connected to the outer side wall of one end of the drainage pipe (7); a pumping assembly (8) is provided on the side wall of the support plate (4); the pumping assembly (8) can pump water out of the water collecting chamber (43).

7. A supporting device for construction according to claim 6, Features: The pumping assembly (8) comprises a pump body (81); the pump body (81) is mounted on the side wall of the support plate (4); the input end of the pump body (81) is fixedly connected to a water inlet pipe (82) communicating with the interior of the water collecting chamber (43); and the output end of the pump body (81) is fixedly connected to a water outlet pipe (83) communicating with the external environment.

8. A supporting device for construction according to claim 6, Features: A water receiving box (44) is fixedly connected to the top surface of the support plate (4); a connecting pipe (45) is fixedly connected to the inner side wall of the top end of the water collecting chamber (43); the top end of the connecting pipe (45) extends to the inner side wall of the bottom end of the water receiving box (44), and the connecting pipe (45) connects the water receiving box (44) and the water collecting chamber (43).

9. A supporting device for construction according to claim 8, Features: A second filter screen (451) is fixedly connected to the inner side wall of the top end of the connecting pipe (45).

10. A supporting method for a supporting device for building construction, based on the supporting device for building construction according to any one of claims 1 to 9, Features: The support method includes the following specific steps: S1: installing two supporting plates (4) on the ends of two push blocks (3) on the connecting plate (1), so that the two supporting plates (4) and the connecting plate (1) are combined to form an I-shaped whole; S2: installing the I-shaped integral structure in the foundation pit, and driving the two supporting plates (4) to respectively press against the two inner side walls of the foundation pit through the driving mechanism (5); S3: inserting the anchor rod (6) through the supporting plate (4) and embedding it into the side wall of the foundation pit, and sleeve-fitting a nut (61) on the tail of the anchor rod (6) to press the supporting plate (4) against the side wall of the foundation pit; S4: The drainage pipe (7) is passed through the support plate (4) and embedded into the side wall of the foundation pit, thereby completing the installation of the support device in the foundation pit.