Cast-in-situ bored pile construction method under poor stratum
By using the ultra-long steel casing structure that can be assembled in sections and the underwater pouring technology of ready-mixed concrete conduits under special geological conditions, the problems of hole collapse and material waste in the construction of cast-in-place piles are solved, the construction quality and efficiency are improved, and the construction quality and efficiency are ensured. improve the safety and economic benefits of the project.
Patent Information
- Application Number
- CN202411258045.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-09
- Publication Date
- 2024-10-25
AI Technical Summary
Under special geological conditions, the construction of cast-in-place piles is prone to problems such as hole collapse, difficulty in pile formation, and material waste. Especially in pebble formations with very little sand content, traditional mud retaining walls fail, resulting in low construction quality and efficiency, and great safety risks. Hidden danger.
Adopt an extra-long steel casing structure that can be assembled and disassembled in sections. The steel casing is buried through the pilot hole of the rotary drilling rig and the impact hammer to ensure the correct connection and removal of the casing sections. It is gradually completed with the underwater pouring of the ready-mixed concrete pipe. Pile foundation construction reduces concrete waste and risk of hole collapse.
It improves the construction quality and efficiency of cast-in-place piles, reduces concrete waste, shortens the construction period, ensures the safety and quality of the project, reduces costs, and achieves better social and economic benefits.
Smart Images

Figure CN118835595A_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of civil construction of building engineering, and particularly relates to a bored pile construction technology under special geological conditions, in particular to a bored pile construction method under poor strata. Background Art
[0002] In the process of civil construction of building projects, pile foundation technology plays a very critical role. This technology not only has a certain promoting effect on the bearing capacity of the building foundation, but also can effectively control the deformation of the building foundation. It also has a certain seismic performance, improves the overall safety and stability of the building, and has an important impact on the overall quality, efficiency and cost of civil construction in construction projects. Therefore, it is of great practical significance to the field of construction engineering to rationalize and analyze the details of the practical application of this type of technology and continuously improve the pile foundation technology.
[0003] At present, cast-in-place piles are widely used as a form of foundation treatment, and the construction technology is becoming more and more perfect. However, in the face of the complex and changeable special geological conditions underground, there are still construction difficulties such as difficulty in drilling, easy hole collapse, buried drills, etc., and there are major safety hazards, which not only affect the quality of piles, but also have a great impact on the construction period, and will also cause waste of concrete materials during the construction process. For example, during the construction process, it is often encountered that the surface layer is suspected to be a pebble layer formed after sand washing. In the face of such geological conditions, traditional mud wall protection will fail, and the hole collapse will be serious after drilling, which seriously affects the overall quality, efficiency and cost of civil construction. Summary of the invention
[0004] The purpose of the present invention is to solve the problems of easy hole collapse, difficulty in pile formation, and waste of materials in bored pile construction under special geological conditions, and to provide a bored pile construction method under poor strata. The method of the present invention can be widely used in bored pile construction under special geological conditions such as pebble strata with very little sand content and when traditional mud wall protection fails.
[0005] The present invention is achieved through the following technical solutions: A method for constructing bored piles in poor strata comprises the following steps: site leveling → measurement and positioning → drilling rig placement → mud preparation → drilling to 11m by means of a rotary drilling rig → pre-assembly of steel casing → burying a No. 1 casing section by means of a shock hammer → extending the sections one by one and burying the steel casing by shock hammer downwards to 12m → drilling a hole to a designed depth by means of a rotary drilling rig following a pipe → hole cleaning → placing a steel cage by means of a crane → secondary hole cleaning → underwater pouring of a premixed concrete guide pipe to form a pile → during the process of pulling out the guide pipe in sections, the steel casing is also pulled out and removed simultaneously → grouting at the pile end.
[0006] Among them, the steel casing is formed by six casing sections connected in sequence by means of socket and spigot. The six casing sections are respectively recorded as No. 1 casing section, No. 2 casing section, No. 3 casing section, No. 4 casing section, No. 5 casing section and No. 6 casing section. The bottom tube mouth of No. 1 casing section adopts a beveled tube mouth, and the top tube mouth of No. 1 casing section is formed with a socket, and a plurality of external threaded holes are evenly distributed along the mouth wall of the socket, and a plurality of U-shaped protrusions extending upward are evenly fixed along the mouth edge of the socket; the No. 2 casing section, No. 3 casing section, No. 4 casing section and No. 5 casing section have the same structure, and the structure of their top tube mouths is the same as that of the top tube mouth of No. 1 casing section, and their bottom tube mouths are formed with a socket, and a plurality of external threaded holes are evenly distributed along the mouth wall of the socket. A plurality of internal threaded holes are evenly distributed in the circle, and a plurality of U-shaped grooves recessed inwardly are evenly distributed along a circle of the outer tube wall adjacent to the socket; the structure of the bottom tube mouth of the No. 6 casing segment is the same as the structure of the bottom tube mouth of the No. 2, 3, 4 and 5 casing segments, and its top tube mouth is a conventional tube mouth structure; when the No. 1 casing segment, the No. 2 casing segment, the No. 3 casing segment, the No. 4 casing segment, the No. 5 casing segment and the No. 6 casing segment are connected in sequence, the socket at the top of the lower casing segment is connected with the socket at the bottom of the upper casing segment by socket connection, the U-shaped protrusion at the socket is connected with the U-shaped groove at the socket in a one-to-one corresponding bite connection, and the external threaded hole on the socket is aligned with the internal threaded hole on the socket and then connected by fastening bolts.
[0007] As a preferred technical solution, the diameter of each casing section is 900mm, the length is 2m, and the wall thickness is 20mm, wherein the socket shrinks 10mm from the inner wall to the outer wall, and the plug shrinks 10mm from the outer wall to the inner wall; there are eight U-shaped protrusions at the socket and eight U-shaped grooves at the plug; there are four external threaded holes on the socket and four internal threaded holes on the plug, and the aperture of the external threaded holes and the internal threaded holes is 50mm.
[0008] As a preferred technical solution, each casing section is assembled by butting two semicircular cylinders, the butt joint adopts a stepped overlap form, and the stepped overlap part is connected and fixed with connecting bolts.
[0009] As a preferred technical solution, the width of the stepped overlap portion is 200 mm; four connecting bolts are provided and are evenly distributed along the length direction of the casing section.
[0010] As a preferred technical solution, in the step of drilling a hole with a rotary drilling rig, the rotary drilling rig uses a drill bit with a diameter of 900 mm to drill a hole to 11 m, and then pulls out the drill rod.
[0011] As a preferred technical solution, in the pre-assembly step of the steel casing, each casing section is marked and placed in sequence.
[0012] As an optimal technical solution, in the steps of using a shock hammer to shock and bury the No. 1 casing segment and extending it segment by segment and shock-burying the steel casing downward to 12m, the No. 1 casing segment is first shock-buried underground. When the No. 1 casing segment is exposed to the ground at an elevation of 1m, the No. 2 casing segment is lifted by a crane so that the sockets and the plugs of the No. 1 and No. 2 casing segments and the U-shaped protrusions and the U-shaped grooves are aligned, and then the fastening bolts are screwed in to fix the No. 1 and No. 2 casing segments securely. The casing segments are continued to be shock-buried downward, and when the top of the No. 2 casing segment is exposed to the ground at an elevation of 1m, the above steps are repeated to shock and bury the No. 3, 4, 5, and No. 6 casing segments in turn, and finally all the six casing segments with a total of 12 meters of steel casing are buried underground, so that they pass through the poor strata to complete the wall protection.
[0013] As a preferred technical solution, in the step of drilling a hole to a designed depth with a pipe, the rotary drilling rig adopts a drill bit with a diameter of 700 mm.
[0014] As a preferred technical solution, in the step of pouring the premixed concrete pipe into piles underwater, the length of the lower pipe is determined according to the hole depth, and the short-section pipe is used to adjust the pipe to ensure that the pipe is 0.3 to 0.5 m away from the bottom of the hole, and the initial concrete pouring volume is not less than 2.0 m 3 To ensure the sealing of the conduit connection, the test installation, pressure test and water test pressure are 0.6~1.0Mpa. The grade of poured concrete is one level higher than the design, and the concrete pouring height is 1m higher than the design height.
[0015] As an optimal technical solution, during the process of pulling out the conduit in sections, the steel casing is also pulled out and removed at the same time. Before pulling out the conduit, the depth of the concrete surface is measured with a measuring rope and a heavy hammer to prevent the conduit from being pulled out or buried too deep, and the buried depth of the conduit is ensured to be 3 to 6 meters. During the process of pulling out the conduit, the steel casing is also pulled out synchronously and removed section by section. It is ensured that the conduit is always buried in the concrete for 3 to 6 meters, and the concrete liquid level is observed to see if it drops. If so, concrete is added in time. This process is repeated until all six casing sections are pulled out and the concrete pouring is completed.
[0016] Compared with the prior art, the present invention has the following beneficial effects: 1) The method of the present invention is based on strict engineering measurements and solves the problems of bored piles being difficult to form holes and prone to hole collapse under special geological conditions (such as pebble layers formed by sand washing) through innovative technical means. The method of the present invention uses an ultra-long steel casing structure that can be assembled and disassembled in sections and can be recycled to pass through the easily collapsed strata, ensuring the construction quality of the bored piles, reducing concrete waste, and improving work efficiency.
[0017] 2) In view of special geological conditions, the construction method of the present invention can improve the quality of hole formation and pile formation, reduce the waste of concrete caused by hole collapse, and also avoid construction problems such as buried drill and stuck drill caused by hole collapse. The method of the present invention speeds up the construction progress, ensures the quality of the project, shortens the construction period, ensures the safe and smooth implementation of the pile foundation project, and achieves better social and economic benefits. BRIEF DESCRIPTION OF THE DRAWINGS
[0018] The drawings herein are used to provide further explanation of the present invention and constitute a part of this application. The illustrative embodiments of the present invention and their description are used to explain the present invention and do not constitute improper limitations on the present invention.
[0019] Figure 1 It is a construction schematic diagram of the method of the present invention.
[0020] Figure 2 It is a schematic diagram of the structure of the No. 1 casing section in the method of the present invention.
[0021] Figure 3 It is a schematic diagram of the structure of the second, third, fourth and fifth casing sections in the method of the present invention.
[0022] Figure 4 It is a schematic diagram of the structure of the No. 6 casing section in the method of the present invention.
[0023] Figure 5 It is a schematic diagram of connecting adjacent casing sections in the method of the present invention.
[0024] Figure 6 It is a schematic cross-sectional view of the casing section in the method of the present invention.
[0025] In the figure: 1-steel casing, 2-No. 1 casing section, 3-No. 2 casing section, 4-No. 3 casing section, 5-No. 4 casing section, 6-No. 5 casing section, 7-No. 6 casing section, 8-bevel type barrel mouth, 9-socket, 10-socket, 11-external threaded hole, 12-U-shaped protrusion, 13-internal threaded hole, 14-U-shaped groove, 15-fastening bolt, 16-semicircular cylinder, 17-step overlap part, 18-connecting bolt, 19-pebble layer. DETAILED DESCRIPTION
[0026] In order to make those skilled in the art better understand the present invention, the present invention is further clearly and completely described below in conjunction with the accompanying drawings and embodiments. It should be noted that, in the absence of conflict, the features in the embodiments and examples of this application can be combined with each other.
[0027] In the description of the present invention, it is necessary to understand that the orientations or positional relationships indicated by the terms "inside", "outside", "top", "bottom", "upper", "lower", etc. are based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the present invention.
[0028] This embodiment provides a method for constructing cast-in-place piles under special geological conditions. Figure 1 As shown, the bored piles need to pass through the first pebble layer 19 with a thickness of about 5 meters. This stratum is suspected to be the pebble layer 19 formed after sand washing. The hole collapse is very serious after the hole is formed. The traditional mud wall bored pile process cannot effectively avoid the hole collapse problem, so the original construction process must be changed.
[0029] In view of the above situation, this embodiment provides a method for constructing bored piles in poor strata, comprising the following steps: 1) The site is flat.
[0030] 2) Measurement and positioning: Measurement and positioning include determining the pile position, measuring the steel casing elevation, etc., and are performed by professional surveyors. After the measurement is completed, a review must be conducted and then the supervisor must inspect and fill in the measurement record form to ensure the accuracy of the measurement.
[0031] 3) Drilling rig in place: When the drilling rig is in place, compact the site to ensure that the drilling rig is stable, and adjust the frame vertically before drilling.
[0032] 4) Prepare mud: Before drilling, during drilling, after hole formation and before grouting, use a mud density meter and viscometer to check the mud density and viscosity to ensure that they are qualified and to ensure smooth drilling and grouting.
[0033] 5) Use a rotary drilling rig to drill the hole to 11m: The rotary drilling rig uses a drill bit with a diameter of 900mm to drill the hole to 11m, and then pull out the drill rod; check the rotary drilling rig at any time during drilling, and adjust the hole in time if it is found to be inclined.
[0034] 6) Pre-assembly of steel casing 1: First, firmly assemble the steel casing 1 in sections of 2 meters on site, mark each section of the casing, and place them in sequence.
[0035] like Figure 1 As shown, the steel casing 1 is formed by six casing sections connected in sequence by means of socket and spigot, and the six casing sections are respectively recorded as No. 1 casing section 2, No. 2 casing section 3, No. 3 casing section 4, No. 4 casing section 5, No. 5 casing section 6 and No. 6 casing section 7; Figure 2As shown, the bottom opening of the No. 1 casing section 2 adopts a beveled opening 8, and the top opening of the No. 1 casing section 2 is formed with a socket 9, and a plurality of external threaded holes 11 are evenly distributed along the mouth wall of the socket 9, and a plurality of U-shaped protrusions 12 extending upward are evenly fixed along the mouth edge of the socket 9; Figure 3 As shown, the structures of the No. 2 casing segment 3, the No. 3 casing segment 4, the No. 4 casing segment 5 and the No. 5 casing segment 6 are the same, and the structure of the top tube mouth is the same as that of the top tube mouth of the No. 1 casing segment 2, and the bottom tube mouth is formed with a socket 10, and a plurality of internal threaded holes 13 are evenly distributed along the mouth wall of the socket 10, and a plurality of U-shaped grooves 14 that are recessed inwardly are evenly distributed along the outer tube wall adjacent to the socket 10; Figure 4 As shown, the structure of the bottom opening of the sixth casing section 7 is the same as that of the bottom openings of the second, third, fourth, and fifth casing sections 3, 4, 5, and 6, and its top opening is a conventional opening structure; when the first casing section 2, the second casing section 3, the third casing section 4, the fourth casing section 5, the fifth casing section 6, and the sixth casing section 7 are connected in sequence, as shown in FIG. Figure 5 As shown, the socket 9 at the top of the lower casing section is socket-connected with the socket 10 at the bottom of the upper casing section, the U-shaped protrusion 12 located at the socket 9 is engaged with the U-shaped groove 14 located at the socket 10 in a one-to-one corresponding manner, and the external threaded hole 11 located on the socket 9 is aligned with the internal threaded hole 13 located on the socket 10 and then connected by tightening bolts 15.
[0036] The diameter of each casing section is 900mm, the length is 2m, and the wall thickness is 20mm, wherein the socket 9 shrinks 10mm from the inner wall to the outer wall, and the plug 10 shrinks 10mm from the outer wall to the inner wall; there are eight U-shaped protrusions 12 at the socket 9, and eight U-shaped grooves 14 at the plug 10; there are four external threaded holes 11 on the socket 9, and four internal threaded holes 13 on the plug 10, and the apertures of the external threaded holes 11 and the internal threaded holes 13 are 50mm.
[0037] like Figure 6 As shown, each casing section is assembled by butting two semicircular cylinders 16, the butt joint adopts a stepped overlap form, and the stepped overlap part 17 is penetrated by connecting bolts 18 to connect and fix; the width of the stepped overlap part 17 is 200mm; there are four connecting bolts 18, and they are evenly distributed along the length direction of the casing section.
[0038] 7) Use the impact hammer to impact and bury the No. 1 casing section 2, and then extend it section by section and impact and bury the steel casing 1 to 12m downwards: First, impact and bury the No. 1 casing section 2 underground. When the No. 1 casing section 2 is exposed to the ground at an elevation of 1m, lift the No. 2 casing section 3 with a crane, so that the sockets 9 and the sockets 10 of the No. 1 and No. 2 casing sections 2 and 3 are aligned with each other, and the U-shaped protrusions 12 and the U-shaped grooves 14, and then screw in the fastening bolts 15 to align the No. 1 and No. 2 casings. Sections 2 and 3 are firmly fixed; continue to vibrate and bury the casing sections downwards, and when the top of the No. 2 casing section 3 is exposed at a ground elevation of 1m, repeat the above steps to vibrate and bury the No. 3, 4, 5, 6, and 7 casing sections in turn, and finally bury all six casing sections with a total of 12 meters of steel casing 1 underground, so that it passes through the poor strata and completes the wall protection; use a spirit level to measure the verticality of the steel casing 1 during the vibration process, and make timely adjustments if any verticality deviation is found.
[0039] 8) The rotary drilling rig drills the hole to the designed depth with the pipe: After the steel casing 1 is buried, the rotary drilling rig switches to a drill bit with a diameter of 700 mm and drills the hole to the designed depth with the pipe. Figure 1 As shown; Check the rotary drilling rig at any time during drilling, and adjust the hole in time if it is inclined; use a measuring rope to check the hole depth, and recheck the measuring rope regularly to ensure its accuracy.
[0040] 9) Clear the hole.
[0041] 10) Crane placement of steel cage: When the steel cage is manufactured and placed, the steel bars can only be used after passing the inspection, and the steel cage can only be processed and manufactured after the welder passes the trial welding; Measures to ensure the protective layer of the steel cage: When using steel bars, weld two ear bars every 3m. If missing ears are found during stacking and transportation, they must be welded in time to ensure that the steel cage is in the center of the pile hole after it is placed in the pile hole; the steel cage must be lifted and placed steadily to prevent it from hitting the grouting device; the elevation of the top of the steel cage is controlled by hanging bars, and the hanging bars are placed according to the calculated depth of the empty pile; when overlapping the steel cage at the hole mouth, the area around the hole mouth must be padded, and sleepers are placed on both sides of the casing, which should be about 10cm higher than the top of the casing.
[0042] 11) Secondary hole cleaning.
[0043] 12) Premixed concrete pipe underwater pouring pile: timely supply of concrete to ensure the continuity and workability of concrete pouring and slump meet the requirements; determine the length of the pipe according to the hole depth, adjust it with a short pipe section, ensure that the pipe is 0.3-0.5m away from the bottom of the hole, and the initial concrete pouring volume is not less than 2.0m 3 To ensure the sealing of the conduit connection, the test installation, pressure test and water test pressure are 0.6~1.0Mpa. The grade of poured concrete is one level higher than the design. To ensure the quality of bored piles, the concrete pouring height is 1m higher than the design height.
[0044] 13) During the process of pulling out the guide tube in sections, the steel casing 1 is also pulled out and removed simultaneously: before pulling out the guide tube, measure the depth of the concrete surface with a measuring rope and a heavy hammer to prevent the guide tube from being pulled out or buried too deep, and ensure that the guide tube is buried at a depth of 3 to 6 meters; during the process of pulling out the guide tube, the steel casing 1 is also pulled out and removed section by section by a vibrating hammer; ensure that the guide tube is always buried in the concrete for 3 to 6 meters, observe whether the concrete liquid level drops, and if so, add concrete in time; repeat this process until all six casing sections are pulled out, the concrete pouring is completed, the steel casing 1 is recycled, and the next bored pile construction is carried out.
[0045] 14) Post-grouting of pile end: cement slurry is strictly prepared according to the water-cement ratio. Before grouting, a one-way valve is added to the top of the grouting pipe to prevent grouting. The grouting must ensure that the pressure or grouting volume meets the design requirements. Grouting volume control: grouting is stopped when the total grouting volume and grouting pressure meet the design requirements. Pressure control: grouting can be stopped when the total grouting volume reaches 75% of the design value and the grouting pressure exceeds the design value.
[0046] The above-mentioned embodiments only express several implementation methods of the present invention, and the description thereof is relatively specific and detailed, but it cannot be understood as limiting the scope of the present invention. It should be pointed out that, for ordinary technicians in this field, several variations and improvements can be made without departing from the concept of the present invention, which all belong to the protection scope of the present invention.
Claims
1. A method for constructing bored piles in poor strata, characterized in that: The process includes: site leveling → measurement and positioning → drilling rig placement → mud preparation → drilling to 11m by rotary drilling rig → pre-assembly of steel casing → burying No. 1 casing section by shock hammer → extending the sections one by one and shocking and burying the steel casing to 12m → drilling with rotary drilling rig to the designed depth → hole cleaning → placing steel cage by crane → secondary hole cleaning → underwater pouring of premixed concrete guide tube to form piles → steel casing is also pulled out and removed during the process of pulling out the guide tube in sections → post-grouting at the pile end; Among them, the steel casing is formed by six casing sections connected in sequence by means of socket and spigot. The six casing sections are respectively recorded as No. 1 casing section, No. 2 casing section, No. 3 casing section, No. 4 casing section, No. 5 casing section and No. 6 casing section. The bottom tube mouth of No. 1 casing section adopts a beveled tube mouth, and the top tube mouth of No. 1 casing section is formed with a socket, and a plurality of external threaded holes are evenly distributed along the mouth wall of the socket, and a plurality of U-shaped protrusions extending upward are evenly fixed along the mouth edge of the socket; the No. 2 casing section, No. 3 casing section, No. 4 casing section and No. 5 casing section have the same structure, and the structure of their top tube mouths is the same as that of the top tube mouth of No. 1 casing section, and their bottom tube mouths are formed with a socket, and a plurality of external threaded holes are evenly distributed along the mouth wall of the socket. A plurality of internal threaded holes are evenly distributed in the circle, and a plurality of U-shaped grooves recessed inwardly are evenly distributed along a circle of the outer tube wall adjacent to the socket; the structure of the bottom tube mouth of the No. 6 casing segment is the same as the structure of the bottom tube mouth of the No. 2, 3, 4 and 5 casing segments, and its top tube mouth is a conventional tube mouth structure; when the No. 1 casing segment, the No. 2 casing segment, the No. 3 casing segment, the No. 4 casing segment, the No. 5 casing segment and the No. 6 casing segment are connected in sequence, the socket at the top of the lower casing segment is connected with the socket at the bottom of the upper casing segment by socket connection, the U-shaped protrusion at the socket is connected with the U-shaped groove at the socket in a one-to-one corresponding bite connection, and the external threaded hole on the socket is aligned with the internal threaded hole on the socket and then connected by fastening bolts.
2. The method for constructing bored piles in poor strata according to claim 1, characterized in that: The diameter of each casing section is 900mm, the length is 2m, and the wall thickness is 20mm. The socket shrinks 10mm from the inner wall to the outer wall, and the plug shrinks 10mm from the outer wall to the inner wall. There are eight U-shaped protrusions at the socket and eight U-shaped grooves at the plug. There are four external threaded holes on the socket and four internal threaded holes on the plug. The aperture of the external threaded holes and the internal threaded holes is 50mm.
3. The method for constructing bored piles in poor strata according to claim 2, characterized in that: Each casing section is assembled by butting two semicircular cylinders, the butt joint adopts a stepped overlap form, and the stepped overlap part is connected and fixed with connecting bolts.
4. The method for constructing bored piles in poor strata according to claim 3, characterized in that: The width of the stepped overlap portion is 200 mm; there are four connecting bolts, which are evenly distributed along the length of the casing section.
5. The method for constructing bored piles in poor strata according to claim 1 or 4, characterized in that: In the step of drilling a hole with a rotary drilling rig, the rotary drilling rig uses a drill bit with a diameter of 900 mm to drill a hole to 11 m, and then pulls out the drill rod.
6. The method for constructing bored piles in poor strata according to claim 1 or 4, characterized in that: During the pre-assembly step of the steel casing, each casing section is marked and placed in sequence.
7. The method for constructing bored piles in poor strata according to claim 1 or 4, characterized in that: In the steps of using a shock hammer to shock and bury the No. 1 casing section and extending it section by section and shock-bursting the steel casing downward to 12m, first shock-bursting the No. 1 casing section into the ground. When the No. 1 casing section is exposed to the ground at an elevation of 1m, the No. 2 casing section is lifted by a crane to align the sockets and spigots of the No. 1 and No. 2 casing sections and the U-shaped protrusions and U-shaped grooves, and then tighten the fastening bolts to securely fix the No. 1 and No. 2 casing sections. Continue to shock-bursting the casing sections downward, and when the top of the No. 2 casing section is exposed to the ground at an elevation of 1m, repeat the above steps to shock-bursting the No. 3, 4, 5, and No. 6 casing sections in turn, and finally bury all six casing sections with a total of 12 meters of steel casing underground, so that it passes through the poor strata to complete the wall protection.
8. The method for constructing bored piles in poor strata according to claim 1 or 4, characterized in that: In the step of drilling a hole to the designed depth with the pipe, the rotary drilling rig uses a drill bit with a diameter of 700mm.
9. The method for constructing bored piles in poor strata according to claim 1 or 4, characterized in that: In the process of pouring the premixed concrete pipe into piles underwater, the length of the pipe is determined according to the hole depth, and the pipe is adjusted with a short section to ensure that the pipe is 0.3 to 0.5 m away from the bottom of the hole. The initial concrete pouring volume is not less than 2.0 m 3 To ensure the sealing of the conduit connection, the test installation, pressure test and water test pressure are 0.6~1.0Mpa. The grade of poured concrete is one level higher than the design, and the concrete pouring height is 1m higher than the design height.
10. The method for constructing bored piles in poor strata according to claim 1 or 4, characterized in that: During the process of pulling out the conduit in sections, the steel casing is also pulled out. During the removal steps, the depth of the concrete surface is measured with a measuring rope and a heavy hammer before pulling out the conduit to prevent the conduit from being pulled out or buried too deep, and the buried depth of the conduit is ensured to be 3 to 6 meters. During the process of pulling out the conduit, the steel casing is also pulled out synchronously and removed section by section. Ensure that the conduit is always buried in the concrete for 3 to 6 meters, observe whether the concrete liquid level drops, and if so, add concrete in time. Repeat this process until all six casing sections are pulled out and the concrete pouring is completed.