Fabricated steel structure and building method thereof

By introducing the locking mechanism of the limit rod and the clamp block into the prefabricated steel structure, as well as the fixing method of the reinforcement plate and the bolt, the problem of low stability caused by the cooperation between the connector and the slot in the existing technology is solved, and the construction efficiency is significantly improved. stability.

CN118835700APending Publication Date: 2024-10-25CHONGQING RENZHONG STEEL STRUCTURE ENG CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411065745.6
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-05
Publication Date
2024-10-25

AI Technical Summary

Technical Problem

The existing prefabricated steel structure is connected only through the cooperation of connectors and slots, and lacks limiting and reinforcing components, resulting in low stability after erection.

Method used

Using connection components including connecting columns, limit rods, rebound units, rotating rods and clamping blocks, the stability of the steel structure is improved through the limit locking mechanism of the limiting rods and clamping blocks, combined with the fixing methods of reinforcing plates and bolts. .

Benefits of technology

The structural locking of the limit rods and clamping blocks prevents the steel structure from falling off and increases the stability of the construction. The stability of the structure is further improved through the fixation of reinforcing plates and bolts.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118835700A_ABST
    Figure CN118835700A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of assembly type buildings, in particular to an assembly type steel structure and a building method thereof.The assembly type steel structure comprises a base plate, a top plate and a plurality of connecting assemblies, each connecting assembly comprises a connecting column, a limiting rod, a springback unit, a rotating rod and a clamping block, the connecting columns are placed between the base plate and the top plate, the base plate is provided with a groove, and the connecting columns are provided with limiting holes; one part of the limiting rod is pulled out of the groove, the connecting columns are inserted into the groove, the springback units enable the connecting columns to springback to enter the limiting holes, then the top plate is lifted and moved to the position above the connecting columns through the lifting machine, the clamping blocks are aligned with the clamping grooves, the top plate is moved downwards, the clamping blocks enter the clamping grooves and reach the groove bodies, at the moment, the lifting machine is closed and moved away, and a worker pulls the rotating rod to rotate. The clamping block rotates in the groove body and is not matched with the clamping groove in the same vertical line, so that the clamping block cannot be separated from the clamping groove and the groove body, construction of the steel structure is completed, limiting and locking are conducted through the limiting rod and the clamping block, and the construction stability is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of prefabricated buildings, and in particular to a prefabricated steel structure and a construction method thereof. Background Art

[0002] In order to reduce the time spent on installing steel structures at construction sites, prefabricated steel structure brackets are usually used. The steel structure base and the steel structure body are pre-assembled in the factory. However, traditional steel structure assembly and construction is relatively complicated and cannot be completed quickly.

[0003] In the prior art, the four transverse columns are inserted into the second slots of the corresponding connecting parts to complete the assembly of the transverse structure frame. After assembling multiple transverse structure frames on the ground, four of the support columns are inserted into the four installation slots of the base plate. The first transverse structure frame is placed at the end of the support column away from the base plate so that the first slot corresponds to the support column to complete the construction.

[0004] However, in the aforementioned prior art, the connection of the steel structure is only through the cooperation between the connecting piece and the slot, and there is a lack of limiting and reinforcing components, resulting in low stability after construction. Summary of the invention

[0005] The object of the present invention is to provide an assembled steel structure and a method for building it, so as to solve the problem that the connection of the steel structure in the prior art is only through the cooperation between the connecting parts and the slots, and there is a lack of limiting and reinforcing components, resulting in low stability after construction.

[0006] To achieve the above object, the present invention provides an assembled steel structure, comprising a base plate, a top plate and a plurality of connection components, wherein the top plate is arranged above the base plate;

[0007] The connecting assembly includes a connecting column, a limiting rod, a rebound unit, a rotating rod and a block, the connecting column is placed between the base plate and the top plate, the base plate has a groove, one end of the connecting column passes through the base plate and is located inside the groove, the connecting column has a limiting hole, one end of the limiting rod passes through the base plate and is matched with the limiting hole, the rebound unit is arranged on the limiting rod, the top plate has a circular groove, the rotating rod is rotatably connected to the top plate and is located inside the circular groove, one end of the rotating rod is fixedly connected to the block, the connecting column also has a slot and a slot body, and the blocks are matched with the slot and the slot body.

[0008] Among them, the rebound unit includes a fixing ring and a spring, the fixing ring is fixedly connected to the limiting rod and is located on the outer wall of the limiting rod, the two ends of the spring are respectively movably connected to the inner wall of the groove and one side of the fixing ring, and the spring is sleeved on the outside of the limiting rod.

[0009] Wherein, the rebound unit further includes a pulling block, and the pulling block is fixedly connected to the limiting rod and fixedly connected to the other end of the limiting rod.

[0010] Wherein, the rotating rod has a rotating groove.

[0011] Wherein, the prefabricated steel structure also includes two reinforcement components, and the two reinforcement components are arranged on the plurality of connection components.

[0012] Wherein, the reinforcement assembly includes a reinforcement plate and two bolts, each of the connecting columns has a threaded hole, and the two bolts pass through the reinforcement plate in sequence and are respectively adapted to the corresponding threaded holes.

[0013] The present invention also provides a method for constructing an assembled steel structure, using the assembled steel structure described above, comprising the following steps:

[0014] Holding the pull block, pull a portion of the limiting rod out of the groove, and then insert the connecting column into the groove;

[0015] When the pull block is released, the spring rebounds, driving the fixing ring and the limiting rod to rebound into the limiting hole, thereby limiting and fixing the connecting column;

[0016] Lifting the top plate by a crane and moving it above the plurality of connecting columns;

[0017] Align the card block with the card slot, move the top plate downward, the card block enters the card slot and reaches the slot body, and the crane is closed and moved away;

[0018] The staff inserts a tool into the rotating groove and turns the rotating rod to rotate, so that the clamping block rotates in the groove body and no longer fits with the clamping groove and cannot be separated from the clamping groove and the groove body;

[0019] Finally, the reinforcement plate is placed on one side of the corresponding two connecting columns, and the bolts are passed through the reinforcement plate and screwed into the threaded holes to complete the fixation, thereby completing the construction of the steel structure.

[0020] The present invention provides an assembled steel structure and a construction method thereof, wherein a portion of the limit rod is pulled out of the groove, the connecting column is inserted into the groove, and the rebound unit causes it to rebound and enter the limit hole. Then, the top plate is lifted and moved above the plurality of connecting columns by a crane, the clamping block is aligned with the clamping slot, the top plate is moved downward, the clamping block enters the clamping slot, and reaches the slot body. At this time, the crane is closed and removed, and a staff member turns the rotating rod to rotate, so that the clamping block rotates within the slot body and is no longer adapted to be located on the same vertical line as the clamping slot, thereby preventing it from detaching from the clamping slot and the slot body. The above-mentioned structural setting completes the construction of the steel structure, and the setting for limit locking through the limit rod and the clamping block improves the construction stability. BRIEF DESCRIPTION OF THE DRAWINGS

[0021] In order to more clearly illustrate the embodiments of the present application or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art are briefly introduced below.

[0022] Figure 1 It is a schematic diagram of the overall structure of the first embodiment of the present invention.

[0023] Figure 2 It is an overall cross-sectional view of the first embodiment of the present invention.

[0024] Figure 3 The present invention Figure 2 AA line section view.

[0025] Figure 4 The present invention Figure 2 Enlarged view of the local structure at point B.

[0026] Figure 5 It is a schematic diagram of the overall structure of the second embodiment of the present invention.

[0027] Figure 6 It is an overall cross-sectional view of a second embodiment of the present invention.

[0028] Figure 7 The present invention Figure 6 CC line section view.

[0029] Figure 8 It is an overall cross-sectional view of a third embodiment of the present invention.

[0030] Fig. 9 The present invention Figure 8 DD line cross-sectional view.

[0031] Fig.10 The present invention Figure 8 Enlarged view of the local structure at E.

[0032] Fig.11 It is a flow chart of the steps of the method for building a prefabricated steel structure of the present invention.

[0033] 101-base plate, 102-top plate, 103-connecting column, 104-limiting rod, 105-rotating rod, 106-block, 107-groove, 108-limiting hole, 109-circular groove, 110-slot, 111-groove body, 112-fixing ring, 113-spring, 114-pull block, 115-rotating groove, 201-reinforcement plate, 202-bolt, 203-threaded hole, 301-first rubber pad, 302-second rubber pad. DETAILED DESCRIPTION

[0034] Embodiments of the present invention are described in detail below. Examples of the embodiments are shown in the accompanying drawings. The embodiments described below with reference to the accompanying drawings are exemplary and are intended to be used to explain the present invention, but should not be construed as limiting the present invention.

[0035] First embodiment:

[0036] See also Figures 1 to 4 ,in Figure 1 is a schematic diagram of the overall structure of the first embodiment of the present invention, Figure 2 is a cross-sectional view of the entire first embodiment of the present invention, Figure 3 The present invention Figure 2 AA line section view, Figure 4 The present invention Figure 2 The present invention provides an assembled steel structure, comprising a base plate 101, a top plate 102 and a plurality of connection components, wherein the connection components comprise a connection column 103, a limit rod 104, a rebound unit, a rotating rod 105 and a clamping block 106, wherein the connection components comprise a connection column 103, a limit rod 104, a rebound unit, a rotating rod 105 and a clamping block 106, wherein the connection column 103 has a limit hole 108, the top plate 102 has a circular groove 109, the connection column 103 also has a clamping groove 110 and a groove body 111, the rebound unit comprises a fixing ring 112, a spring 113 and a pull block 114, and the rotating rod 105 has a rotating groove 115.

[0037] According to this specific embodiment, the pulling block 114 is held, a part of the limiting rod 104 is pulled out of the groove 107, and then the connecting column 103 is inserted into the groove 107, and the pulling block 114 is released. The spring 113 rebounds, driving the fixing ring 112 and the limiting rod 104 to rebound into the limiting hole 108, and the connecting column 103 is limited and fixed. The top plate 102 is lifted and moved above the multiple connecting columns 103 by a crane, and the blocking block 106 is aligned with the blocking groove 110, and the top plate 102 is moved downward. The blocking block 106 enters the blocking groove 110 and reaches the slot body 111. At this time, the crane is closed and removed, and the staff inserts a tool into the rotating slot 115, pulls the rotating rod 105 to rotate, so that the blocking block 106 rotates in the slot body 111, no longer adapts to the blocking groove 110, and cannot be separated from the blocking groove 110 and the slot body 111.

[0038] Among them, the top plate 102 is arranged above the base plate 101, the connecting column 103 is placed between the base plate 101 and the top plate 102, the base plate 101 has a groove 107, one end of the connecting column 103 passes through the base plate 101 and is located inside the groove 107, the connecting column 103 has a limiting hole 108, one end of the limiting rod 104 passes through the base plate 101 and is adapted to the limiting hole 108, the rebound unit is arranged on the limiting rod 104, the top plate 102 has a circular groove 109, the rotating rod 105 is rotatably connected to the top plate 102 and is located inside the circular groove 109, one end of the rotating rod 105 is fixedly connected to the block 106, the connecting column 103 also has a slot 110 and a slot body 111, and the block 106 is adapted to the slot 110 and the slot body 111. Pull a part of the limiting rod 104 out of the groove 107, insert the connecting column 103 into the groove 107, and the rebound unit makes it rebound and enter the limiting hole 108, then lift the top plate 102 by the crane and move it above the multiple connecting columns 103, align the block 106 with the slot 110, move the top plate 102 downward, and the block 106 enters the slot 110 and reaches the slot body 111. At this time, the crane is closed and removed, and the staff turns the rotating rod 105 to rotate, so that the block 106 rotates in the slot body 111 and no longer adapts to the slot 110 on the same vertical line, thereby making it unable to detach from the slot 110 and the slot body 111, thereby completing the construction of the steel structure, and setting the limiting rod 104 and the block 106 for limit locking to improve the construction stability.

[0039] Secondly, the fixing ring 112 is fixedly connected to the limiting rod 104 and is located on the outer wall of the limiting rod 104. The two ends of the spring 113 are movably connected to the inner wall of the groove 107 and one side of the fixing ring 112 respectively, and the spring 113 is sleeved on the outside of the limiting rod 104. The spring 113 rebounds and drives the limiting rod 104 to rebound through the connection of the fixing ring 112.

[0040] At the same time, the pull block 114 is fixedly connected to the limiting rod 104 and to the other end of the limiting rod 104. The pull block 114 facilitates pulling the limiting rod 104.

[0041] In addition, the rotating rod 105 has a rotating groove 115. The staff inserts a tool into the rotating groove 115 and pulls the rotating rod 105 to rotate.

[0042] When using an assembled steel structure of this embodiment, hold the pull block 114, pull a part of the limiting rod 104 out of the groove 107, then insert the connecting column 103 into the groove 107, release the pull block 114, the spring 113 rebounds, drives the fixing ring 112 and the limiting rod 104 to rebound into the limiting hole 108, and the connecting column 103 is limited and fixed. The top plate 102 is lifted and moved above the plurality of connecting columns 103 by a crane, and the clamping block 106 is aligned with the clamping groove 110. The top plate 102 is moved downward, and the block 106 enters the slot 110 and reaches the slot body 111. At this time, the crane is closed and moved away, and the staff inserts a tool into the rotating slot 115 and turns the rotating rod 105 to rotate, so that the block 106 rotates in the slot body 111 and no longer fits with the slot 110 and cannot be separated from the slot 110 and the slot body 111. The above-mentioned structural setting completes the construction of the steel structure, and the setting is used to limit and lock the limit rod 104 and the block 106 to avoid falling off and improve the construction stability.

[0043] Second embodiment:

[0044] Based on the first embodiment, please refer to Figures 5 to 7 ,in Figure 5 is a schematic diagram of the overall structure of the second embodiment of the present invention, Figure 6 is a cross-sectional view of the entire second embodiment of the present invention, Figure 7 The present invention Figure 6 The present invention provides a prefabricated steel structure, which also includes two reinforcement components, wherein the reinforcement components include a reinforcement plate 201 and two bolts 202 , and each of the connection columns 103 has a threaded hole 203 .

[0045] According to this specific embodiment, after the bolt 202 passes through the reinforcing plate 201, it is aligned with the corresponding threaded hole 203 and screwed in, so as to complete the installation of the reinforcing plate 201 and connect the two connecting columns 103 into one.

[0046] Wherein, two of the reinforcement components are arranged on the plurality of connection components. The reinforcement components reinforce and support the construction of the steel structure to improve stability.

[0047] Secondly, each of the connecting columns 103 has a threaded hole 203, and the two bolts 202 pass through the reinforcing plate 201 in sequence and respectively fit into the corresponding threaded holes 203. After the bolts 202 pass through the reinforcing plate 201, they are aligned with the corresponding threaded holes 203 and screwed in, completing the installation of the reinforcing plate 201 and connecting the two connecting columns 103 as one.

[0048] When using an assembled steel structure of this embodiment, after the bolt 202 passes through the reinforcement plate 201, it is aligned with the corresponding threaded hole 203 and screwed in to complete the installation of the reinforcement plate 201, and the two connecting columns 103 are connected as a whole, thereby reinforcing and supporting the construction of the steel structure and improving stability.

[0049] Third embodiment:

[0050] The fabricated steel structure further includes a plurality of assembly auxiliary components, which are respectively arranged on the corresponding connection components. The assembly auxiliary components include a first rubber pad 301 and a second rubber pad 302, wherein the first rubber pad 301 is fixedly connected to the connection column 103 and is located at an end of the connection column 103 away from the rotating rod 105, and the second rubber pad 302 is fixedly connected to the clamping block 106 and is located at an end of the clamping block 106 away from the rotating rod 105.

[0051] Based on the second embodiment, please refer to Figures 8 to 10 ,in Figure 8 is a cross-sectional view of the entire third embodiment of the present invention, Fig. 9 The present invention Figure 8 DD line cross-sectional view, Fig.10 The present invention Figure 8 The present invention provides a prefabricated steel structure, which further comprises a plurality of assembly auxiliary components, wherein the assembly auxiliary components comprise a first rubber pad 301 and a second rubber pad 302 .

[0052] According to this specific embodiment, after the connecting column 103 is inserted into the groove 107, the first rubber pad 301 contacts the inner wall of the groove 107 to fill the gap space and improve the fitting effect. After the card block 106 passes through the card slot 110 and enters the slot body 111, the second rubber pad 302 fits with the inner wall of the slot body 111 to fill the gap space and improve the fitting effect.

[0053] Wherein, a plurality of the assembly auxiliary components are respectively arranged on the corresponding connection components. The assembly auxiliary components assist in optimizing the construction of the steel structure and improve the stability of the installation of the block 106 and the connection column 103.

[0054] Secondly, the first rubber pad 301 is fixedly connected to the connecting column 103 and is located at the end of the connecting column 103 away from the rotating rod 105, and the second rubber pad 302 is fixedly connected to the clamping block 106 and is located at the end of the clamping block 106 away from the rotating rod 105. After the connecting column 103 is inserted into the groove 107, the first rubber pad 301 contacts the inner wall of the groove 107 to fill the gap space and improve the fitting effect. After the clamping block 106 passes through the clamping groove 110 and enters the slot body 111, the second rubber pad 302 fits with the inner wall of the slot body 111 to fill the gap space and improve the fitting effect.

[0055] When using an assembled steel structure of the present embodiment, after the connecting column 103 is inserted into the groove 107, the first rubber pad 301 contacts the inner wall of the groove 107 to fill the gap space and improve the fitting effect. After the block 106 passes through the slot 110 and enters the slot body 111, the second rubber pad 302 fits with the inner wall of the slot body 111 to fill the gap space and improve the fitting effect. Through the above-mentioned structural setting, the construction of the steel structure is assisted and optimized, and the stability of the installation of the block 106 and the connecting column 103 is improved.

[0056] See also Fig.11 The present invention also provides a method for constructing an assembled steel structure, comprising the following steps:

[0057] S1: holding the pull block 114 , pulling a portion of the limiting rod 104 out of the groove 107 , and then inserting the connecting column 103 into the groove 107 ;

[0058] S2: Release the pull block 114, the spring 113 rebounds, driving the fixing ring 112 and the limiting rod 104 to rebound into the limiting hole 108, and limit and fix the connecting column 103;

[0059] S3: lifting the top plate 102 by a crane and moving it above the plurality of connecting columns 103;

[0060] S4: Align the block 106 with the slot 110, move the top plate 102 downward, the block 106 enters the slot 110, and reaches the slot body 111, at which time the crane is closed and moved away;

[0061] S5: The staff inserts a tool into the rotating groove 115 and turns the rotating rod 105 to rotate, so that the clamping block 106 rotates in the groove body 111 and no longer fits with the clamping groove 110 and cannot be separated from the clamping groove 110 and the groove body 111;

[0062] S6: Finally, the reinforcing plate 201 is placed on one side of the corresponding two connecting columns 103, and the bolts 202 are passed through the reinforcing plate 201 and screwed into the threaded holes 203 to complete the fixation, thereby completing the construction of the steel structure.

[0063] Among them, the pull block 114 is held, a part of the limiting rod 104 is pulled out of the groove 107, and then the connecting column 103 is inserted into the groove 107, and the pull block 114 is released. The spring 113 rebounds, driving the fixing ring 112 and the limiting rod 104 to rebound into the limiting hole 108, and the connecting column 103 is limited and fixed. The top plate 102 is lifted and moved above the multiple connecting columns 103 by a crane, and the block 106 is aligned with the slot 110, and the top plate 102 is moved down. The block 106 enters The slot 110 reaches the slot body 111, and the crane is closed and moved away. The staff inserts a tool into the rotating slot 115 and turns the rotating rod 105 to rotate, so that the block 106 rotates in the slot body 111 and no longer fits with the slot 110, and cannot be separated from the slot 110 and the slot body 111. Finally, the reinforcement plate 201 is placed on one side of the corresponding two connecting columns 103, and the bolt 202 is passed through the reinforcement plate 201 and screwed into the threaded hole 203 to complete the fixation, thereby completing the construction of the steel structure.

[0064] What is disclosed above is only one or more preferred embodiments of the present application, and cannot be used to limit the scope of rights of the present application. Ordinary technicians in this field can understand that all or part of the processes of implementing the above embodiments and equivalent changes made according to the claims of the present application are still within the scope covered by the present application.

Claims

1. An assembled steel structure, comprising a base plate and a top plate, wherein the top plate is arranged above the base plate, characterized in that: Also included are multiple connection components; The connecting assembly includes a connecting column, a limiting rod, a rebound unit, a rotating rod and a block, the connecting column is placed between the base plate and the top plate, the base plate has a groove, one end of the connecting column passes through the base plate and is located inside the groove, the connecting column has a limiting hole, one end of the limiting rod passes through the base plate and is matched with the limiting hole, the rebound unit is arranged on the limiting rod, the top plate has a circular groove, the rotating rod is rotatably connected to the top plate and is located inside the circular groove, one end of the rotating rod is fixedly connected to the block, the connecting column also has a slot and a slot body, and the blocks are matched with the slot and the slot body.

2. The assembled steel structure according to claim 1, characterized in that: The rebound unit includes a fixing ring and a spring. The fixing ring is fixedly connected to the limiting rod and is located on the outer wall of the limiting rod. The two ends of the spring are movably connected to the inner wall of the groove and one side of the fixing ring respectively. The spring is sleeved on the outside of the limiting rod.

3. The assembled steel structure according to claim 2, characterized in that: The rebound unit further includes a pulling block, which is fixedly connected to the limiting rod and to the other end of the limiting rod.

4. The assembled steel structure according to claim 3, characterized in that: The rotating rod has a rotating groove.

5. The assembled steel structure according to claim 4, characterized in that: The fabricated steel structure further includes two reinforcement components, and the two reinforcement components are arranged on the plurality of connection components.

6. The assembled steel structure according to claim 5, characterized in that: The reinforcement assembly includes a reinforcement plate and two bolts. Each of the connecting columns has a threaded hole. The two bolts pass through the reinforcement plate in sequence and are respectively matched with the corresponding threaded holes.

7. A method for constructing an assembled steel structure, using the assembled steel structure according to claim 6, characterized in that: The steps include: Holding the pull block, pull a portion of the limiting rod out of the groove, and then insert the connecting column into the groove; When the pull block is released, the spring rebounds, driving the fixing ring and the limiting rod to rebound into the limiting hole, thereby limiting and fixing the connecting column; Lifting the top plate by a crane and moving it above the plurality of connecting columns; Align the card block with the card slot, move the top plate downward, the card block enters the card slot and reaches the slot body, and the crane is closed and moved away; The staff inserts a tool into the rotating groove and turns the rotating rod to rotate, so that the clamping block rotates in the groove body and no longer fits with the clamping groove and cannot be separated from the clamping groove and the groove body; Finally, the reinforcement plate is placed on one side of the corresponding two connecting columns, and the bolts are passed through the reinforcement plate and screwed into the threaded holes to complete the fixation, thereby completing the construction of the steel structure.