Ground jacking and assembling construction method for large-span net rack
By jacking up and assembling the large-span conical silo grid on the ground and using jacking equipment and lifters to stably install the large-span grid, the problems of unstable installation and low safety in the existing technology have been solved and achieved. Efficient and safe grid installation effect.
Patent Information
- Application Number
- CN202411212502.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-30
- Publication Date
- 2024-10-25
AI Technical Summary
Existing grid installation methods are not suitable for large-span conical silo grid structures, resulting in stability and safety issues during the installation process, especially when operating at high altitudes and with uneven weight distribution.
The large-span grid ground jacking assembly construction method is adopted, by splicing the steel platform on the ground inside the concrete shell, and using multiple jacking equipment to gradually lift the steel platform, install the string frame, and carry out the lifting every time Weld the warehouse roof frame on the upper part of the steel platform, use lifters and brackets to gradually lift the grid to close to the top of the shell, and finally use a crane to hoist the bottom string frame to the top of the shell and assemble it.
It realizes the stable, convenient and efficient installation of the grid, avoids the shaking and structural damage caused by the tilt of the lifter in the existing technology, improves the safety and stability of the installation, ensures the verticality and horizontality of the structure, and reduces This reduces the risk of structural deformation and local overloading.
Smart Images

Figure CN118835705A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of grid installation construction, and in particular to a ground jacking and assembling construction method for a large-span grid. Background Art
[0002] As an indispensable building material, cement is used in many fields such as civil construction, water conservancy facilities, road and bridge engineering, and residential construction. Cement clinker, as an intermediate product in the cement production process, is a solid form transformed from basic raw materials such as limestone and clay through a high-temperature calcination process. When cement clinker is mixed with specific additives in a pre-set ratio and undergoes a fine grinding process, it can be transformed into the cement we call in daily life.
[0003] In cement manufacturing, it is usually necessary to build a clinker silo to store cement clinker. The bottom of the clinker silo is a concrete cylindrical shell structure, which can be filled with cement clinker. A conical silo grid is set above the shell, and a steel structure roof room is set above the silo grid. A conveying corridor is set on the roof room to connect to the kiln head for preparing cement clinker. The cement clinker is transported from the kiln head to the roof room through the zipper machine in the conveying corridor, and then falls from the unloading port of the roof room into the silo below for storage.
[0004] Since the silo grid above the cement clinker silo is a large-span grid, it is composed of multiple bolt balls and rods. Not only is the diameter span large, but the grid is also formed by multi-layer string frames spliced layer by layer. There are usually two conventional grid installation methods:
[0005] The first method is to start from the bottom string frame on the ground and splice it upwards layer by layer. Usually, it is necessary to build a scaffolding to facilitate workers to work at high altitudes. After all the splicing is completed, the grid is finally hoisted from the ground to the top of the support beam for fixation.
[0006] The second installation method is to set up multiple lifters on the top of the support beam, first splice the top chord frame on the ground, then use the lifter to lift the top chord frame to a certain height, and then splice the next layer of chord frame. Use the lifter to increase the height step by step until all levels of chord frames are spliced together. Finally, hoist the entire grid to the top of the support beam for splicing and fixing.
[0007] The above two methods are only suitable for grid frames with the same shape and structure of each layer of chords. They are not applicable to silo grid frames on cement clinker storage. The reason is that in the first method, as long as the shape and structure of each layer of chords are the same, as the construction height of the grid frame increases, the height of the scaffolding can also be built upward without interference; in the second method, the hook lock of the lifter only needs to hook the topmost chord frame and gradually lift it upward, and the grid frames of the lower layers can be installed in turn; and the hook lock is always in a vertical state, and it is relatively stable when the hook lock lifts the grid frame. However, the silo grid structure of cement clinker storage is a conical structure with a gradually increasing span diameter from top to bottom. If the first installation method mentioned above is adopted, since the scaffolding is built on the periphery of the grid, after the bottom string frame is installed, the upper string frame will be farther and farther away from the scaffolding due to the smaller span diameter, resulting in workers being unable to reach the grid connection position and unable to install; if the second installation method mentioned above is adopted, since the span diameter of the upper string frame is smaller than that of the lower layer, the hook lock hooks the top string frame and becomes tilted every time it is lifted up a certain distance, which not only causes the grid frame to shake and be unstable when lifted, but also easily causes the grid frame to collide and be damaged. Therefore, the market urgently needs an installation and construction method for a conical silo grid suitable for cement clinker storage. Summary of the invention
[0008] The invention provides a large-span grid ground lifting and assembling construction method, which can solve the problem that the existing grid installation method is not suitable for a conical grid structure.
[0009] The present application provides the following technical solution: a large-span grid ground lifting and assembly construction method, comprising the following steps:
[0010] The first step is to splice the steel platform on the ground inside the concrete shell;
[0011] The second step is to arrange multiple lifting equipment under the steel platform;
[0012] The third step is to gradually lift the steel platform using lifting equipment, and install the first-layer string frame and the second-layer string frame during the lifting process;
[0013] The fourth step is to weld the roof frame on the steel platform;
[0014] Step 5: Use the lifting equipment to gradually lift the steel platform again, and install the third-layer string frame, the fourth-layer string frame and the fifth-layer string frame during each lifting;
[0015] Step 6, evenly distribute multiple lifting brackets along the circumference of the outer circle of the fifth string frame;
[0016] Step 7: a plurality of lifters are evenly distributed along the circumference above the concrete cylinder shell, the lifters are fixed to the top of the cylinder shell through a fixing frame, the fixing frame includes a first pillar and a second pillar fixed to the first pillar cylinder shell, a first horizontal pillar is fixed between the first pillar and the second pillar, a second horizontal pillar is fixed above the first pillar and the second pillar, the top end of the second pillar is fixed to the middle of the second horizontal pillar, one end of the second horizontal pillar extends to the inner side of the cylinder shell, and the lifter is installed above the end of the second horizontal pillar extending from the inner side of the cylinder shell;
[0017] Step 8: Hook the hook of the lifter to the lifting bracket, and use the lifter to lift the entire grid to a height close to the top of the cylinder shell;
[0018] Step 9: Use a crane to hoist the parts of the bottom string frame to the top of the cylinder shell and assemble them under the fifth string frame;
[0019] The tenth step is to install the support on the upper end of the cylinder shell, connect the bottom string frame with the support, and complete the installation of the entire grid.
[0020] Beneficial effects: The present invention adopts the construction method of "lifting from the ground", which has the following advantages:
[0021] 1. The installation is stable and reliable. Since the structural shape of the silo grid is a conical structure with a gradually increasing span diameter from top to bottom, the existing technology of splicing the bottom chord frame upwards layer by layer or the top chord frame downwards layer by layer is not applicable; this solution uses a lifting device to splice a layer of chord frame each time it is lifted from the ground. In this way, there is no need to build a high scaffolding, which reduces the operation process. At the same time, the lifting device always lifts the grid vertically, which has higher stability and avoids the second installation method mentioned in the background technology, because the hook lock of the lifter will tilt, causing the grid to shake when it is lifted, thereby effectively improving the stability of the installation.
[0022] 2. Convenient and efficient installation. Since the silo grid will eventually be fixed on the upper end of the concrete shell so that the grid covers the shell, the span diameter of the lowest chord frame must be larger than the diameter of the inner hole of the shell so that the grid frame can fall on the upper end of the shell; and the grid frame is assembled on the surface of the shell. If the two solutions of the prior art are adopted, the lowest chord frame cannot be installed due to the diameter limit inside the shell. However, this solution sets the installation process of the lowest chord frame to the last step, hoists the grid frame to the upper end of the shell, and then splices the lowest chord frame, so that the lowest chord frame will not interfere with the diameter inside the shell. Its installation method is scientific, reasonable, convenient and efficient.
[0023] 3. High safety. Since the roof frame of the warehouse needs to be welded above the steel platform, in the third step of this plan, the first and second chord frames are installed below the steel platform before installing the roof frame. The reason is that if the roof frame of the warehouse is installed above the steel platform first, when the jacking equipment is used for jacking later, the roof frame of the warehouse is high and heavy, which will cause shaking during the jacking process. In this plan, the first and second chord frames are installed below the steel platform first. The weight of the first and second chord frames can stabilize the center of gravity. After the roof frame of the warehouse is installed, the jacking will be more stable and safer.
[0024] 4. Smooth lifting. The top of the second pillar of the fixed frame is fixed to the middle of the second horizontal pillar, one end of the second horizontal pillar extends to the inside of the cylinder shell, and the lifter is installed above the inner end of the second horizontal pillar extending from the cylinder shell, so that when the hook lock of the lifter is hung on the grid, the support point is located in the middle of the second horizontal pillar, and the first pillar forms a reverse support for the weight of the grid, thereby strengthening the structural strength, and the lifter is more stable when lifting the grid.
[0025] Furthermore, in the second step, a plurality of jacking devices are evenly distributed under the steel platform.
[0026] Beneficial effects: Evenly distributing multiple jacking equipment under the steel platform can ensure that the weight of the entire structure is evenly distributed, avoid local overload, and reduce the risk of structural deformation. Evenly distributed jacking equipment can provide more stable support, reduce the shaking and tilting of the structure during the jacking process, and ensure the verticality and horizontality of the structure.
[0027] Furthermore, in the third step, after the steel platform is lifted for the first time by the lifting equipment, a plurality of support columns are evenly fixed on the outer ring of the steel platform, and the first layer of chord frames is fixed on the support columns.
[0028] Beneficial effects: The support columns fixed on the outer ring of the steel platform provide stable support points for the first layer of string frames, and the support columns can bear the weight of the structure to ensure the stability of the entire structure.
[0029] Furthermore, in the sixth step and the seventh step, the number of lifting brackets and lifters is equal.
[0030] Beneficial effect: Each lifter corresponds to a lifting bracket, so that when the lifter lifts the entire grid, each lifting bracket bears a part of the weight of the structure, which can ensure that the load is evenly distributed and avoid excessive stress on a single lifting point, thereby improving the stability of the entire structure. At the same time, each lifter independently controls its corresponding lifting bracket, which allows the construction team to fine-tune the lifting speed and height of each lifting point, ensuring the synchronous lifting of the entire structure and avoiding structural deformation or damage caused by uneven lifting.
[0031] Furthermore, in the ninth step, the bottom string frame is a small unit structure composed of scattered bolt balls and rods, and the small unit structure includes a bolt ball and a plurality of rods threadedly connected to the bolt ball.
[0032] Beneficial effects: The small unit structure is easy to transport and install on site, which improves construction efficiency. The construction workers of the small unit structure can splice it to the predetermined position in an orderly manner, which improves installation accuracy.
[0033] Furthermore, in the tenth step, after the support is installed, the lifting bracket and the lifter are symmetrically removed.
[0034] Beneficial effects: Symmetrical demolition is to remove the lifting bracket and the lifter in the diagonal direction at the same time to maintain the balance and stability of the structure. It can avoid the tilt or instability of the structure caused by unilateral demolition, avoid deformation or damage caused by premature loss of support in some parts, and ensure the safety of the structure during the demolition process. BRIEF DESCRIPTION OF THE DRAWINGS
[0035] Figure 1 This is a top view of the Bengang platform.
[0036] Figure 2 This is the main view of the first layer of string frame spliced in the cylinder shell.
[0037] Figure 3 This is the main view of the second layer of string frame being spliced inside the cylinder shell.
[0038] Figure 4 This is the main view of the roof frame of the warehouse being assembled inside the cylinder shell.
[0039] Figure 5 This is the main view when the grid is being lifted inside the shell.
[0040] Figure 6 for Figure 5 Enlarged view of the center bracket.
[0041] Figure 7 This is the front view of the completed installation of the grid. DETAILED DESCRIPTION
[0042] The following is further described in detail through specific implementation methods:
[0043] The marks in the drawings of the specification include: steel platform 1, support column 2, first-layer chord frame 3, jacking equipment 4, warehouse roof frame 5, I-beam 6, second-layer chord frame, cylinder shell 8, cylinder shell 8, lifter 9, hook lock 10, rod 11, welding ball 12, bottom layer grid 13, second cross column 14, first pillar 15, first cross column 16, first steel plate 17, second pillar 18, second steel plate 19.
[0044] Embodiment 1
[0045] A large-span grid usually refers to a grid structure with a horizontal span greater than 36 meters. Next, a cement clinker silo grid is used as an example. The chord frames used in the present invention are all composed of bolt balls and connecting rods with end threads, and the entire silo grid is a grid structure with a conical outline formed by multiple bolt balls connected to each other. To facilitate the display of its structure, the attached figure is a view cut along the radial direction of the silo grid, omitting most of the grid structure and retaining only the grid shape on both sides. The installation steps are as follows:
[0046] The first step is to splice the steel platform 1 on the ground inside the concrete shell 8; Figure 1 As shown, the steel platform 1 is circular in top view, and is welded in a cross shape using a plurality of I-beams 6, and reinforced ribs are welded around the periphery; the diameter of the steel platform is 14.7 meters;
[0047] The second step is to arrange multiple jacking equipment 4 under the steel platform 1; the jacking equipment 4 uses a 100t hydraulic jack, the cylinder diameter (inner diameter of the hydraulic cylinder) of the hydraulic jack is 200mm, the stroke is 1300mm, and the piston rod diameter is 125mm. Four sets of jacking equipment 4 are used for jacking, and the jacking points are set at the nodes where the I-beams 6 intersect, and the force of each node is 37.5 tons; the four sets of jacking equipment 4 are all remotely controlled by PLC to open and close the solenoid valves on multiple oil supply pipelines, so as to control the hydraulic pump to supply oil to each jacking equipment 4 synchronously or individually, which can realize the synchronous jacking of the grid or fine-tune the lifting height of a single support point, ensuring the stability and synchronization during the jacking process.
[0048] The third step is to gradually lift the steel platform 1 using the lifting equipment 4, and during the lifting, the height difference of adjacent lifting nodes shall not be greater than 50mm. First, the steel platform 1 is lifted to a height of 1542mm and then maintained, and 16 support columns 2 are evenly welded and fixed on the outer circle of the steel platform 1. The support columns 2 are welded vertically, and then the first layer of chord frame 3 is welded on the support columns 2. After the entire circle is welded; the steel platform 1 is lifted using the lifting equipment 4, and the lifting height range is 1900mm-2000mm. In this embodiment, 1942mm is preferred, and then the second layer of chord frame is installed;
[0049] The fourth step is Figure 4 As shown, the roof frame 5 on the upper part of the welded steel platform 1 is an octagonal pavilion structure;
[0050] The fifth step is to use the lifting device 4 to lift the steel platform 1 three times again, and the lifting height of each time is preferably 1942 mm, and after each lifting, a layer of string frame is installed, that is, the third string frame, the fourth string frame and the fifth string frame are installed downward in sequence after lifting three times;
[0051] The inventor sets a range for the lifting height of each grid frame. When installing the first, second and third layers of string frames, the lifting height is preferably 1942 mm each time. The advantage is that, since there may be wind and rain in the construction site environment, each layer of string frame is easily affected by wind resistance after installation. At the same time, if the construction environment is in a rainy summer, the air humidity is high after a rainstorm, and the surface temperature is high on sunny days. The bottom layer of string frame is closest to the ground, which causes the bottom layer of string frame (especially the threaded part) to be easily rusted due to surface temperature radiation when installing it. After actual on-site testing, the inventor found that as long as it is within the range of the lifting height, after each layer of string frame is installed, the center of gravity of the entire string frame is in the most balanced position, which can not only keep the entire string frame stable, but also minimize the impact of wind resistance, and avoid shaking of the string frame and loosening of the string frame connection point; it also helps to avoid rusting of the threaded connection of the string frame closest to the ground when working in a hot and rainy environment in summer, and effectively improve the installation strength of the string frame structure.
[0052] The sixth step is to evenly distribute 8 lifting brackets along the circumference of the outer circle of the fifth string frame; the lifting brackets include a welding ball 12 and a rod 11 fixed on the welding ball 12, and one end of the rod 11 away from the welding ball 12 is welded and fixed to the outer periphery of the fifth string frame.
[0053] Step 7: 8 lifters 9 are evenly distributed along the circumference above the concrete cylinder shell 8. The number of lifters 9 is equal to the number of lifting brackets. The lifters 9 are fixed to the top of the cylinder shell 8 by a fixing frame. Figure 6 As shown, the fixing frame includes a first pillar 15 and a second pillar 18 fixed on the first pillar 15 cylinder shell 8; the first steel plate 17 and the second steel plate 19 embedded in the top of the cylinder shell 8 are fixed to the bottom ends of the first pillar 15 and the second pillar 18, a first horizontal pillar 16 is fixed between the first pillar 15 and the second pillar 18, a second horizontal pillar 14 is fixed above the first pillar 15 and the second pillar 18, the top end of the second pillar 18 is fixed to the middle of the second horizontal pillar 14, one end of the second horizontal pillar 14 extends to the inside of the cylinder shell 8, and the lifter 9 is installed above the end of the second horizontal pillar 14 extending out of the cylinder shell 8. The lifter 9 is a hydraulic lifter with a model of YS-SJ-75 and a rated lifting capacity of 75t. The hook lock 10 of the lifter 9 uses steel strands with a tensile strength of 1860MPa, a single diameter of 21.80mm, and a breaking tensile force of not less than 58.3t;
[0054] Step 8: Hook the hook 10 of the lifter 9 to the lifting bracket. In this embodiment, the height of the cylinder shell 8 is 26.5 meters, so the lifter 9 is used to lift the entire grid to 27.942 meters.
[0055] The ninth step is to use a crane to hoist the parts of the bottom string frame to the top of the cylinder shell 8 and assemble them under the fifth string frame. The bottom string frame is a small unit structure composed of scattered bolt balls and rods 11. The small unit structure includes a bolt ball and a plurality of rods 11 threadedly connected to the bolt ball.
[0056] Step 10: Figure 7 As shown, a support is installed at the upper end of the cylinder shell 8, the bottom of the support is bolted to the embedded parts at the upper end of the cylinder shell 8, and then the bottom string frame is welded and fixed to the support to complete the installation of the entire grid, and then the lifting bracket and the lifter 9 are symmetrically removed.
[0057] Embodiment 2
[0058] The difference between this embodiment and the first embodiment is that, in the third and fifth steps of the installation procedure, when installing the second-layer chord frame, the third-layer chord frame, the fourth-layer chord frame and the fifth-layer chord frame, the steel platform is lifted to a height of 1900 mm by the lifting device 4, which is the minimum allowable lifting height. In windy weather, the entire chord frame can remain stable and does not shake, and when operating in a summer rainstorm environment, the threaded connection part of the bottom chord frame is not easy to rust due to the high temperature radiation of the surface and the moisture in the air, thereby ensuring the installation strength of the chord frame.
[0059] Embodiment 3
[0060] In the third and fifth steps of the installation procedure, when installing the second, third, fourth and fifth chord frames, the steel platform is lifted to a height of 2000 mm using the lifting device 4. This lifting height is the maximum allowable lifting height. In windy weather, the chord frames shake slightly but do not affect the structural strength of the chord frame installation. At the same time, the bottom chord frame is far from the ground, and the threaded connection of the chord frame will not rust due to the influence of the summer rainstorm environment, thereby ensuring the installation strength of the chord frame.
[0061] Embodiment 4
[0062] The difference between this embodiment and the first embodiment is that in the third and fifth steps of the installation procedure, when installing the second, third, fourth and fifth chord frames, the steel platform is lifted to a height of 1800 mm by the lifting device 4, which is lower than the lower limit of the lifting range. When the construction period is in a summer rainstorm environment, rust appears at the threaded connection of the bottom chord frame, resulting in the inability to completely screw into the threaded hole when the components are connected. Even if they can be tightened, the surface of the thread is easily brittle due to rust, and the gap between the threads increases, causing the connector to loosen and reduce the structural strength of the chord frame.
[0063] Embodiment 5
[0064] The difference between this embodiment and the first embodiment is that in the third and fifth steps of the installation procedure, when installing the second-layer chord frame, the third-layer chord frame, the fourth-layer chord frame and the fifth-layer chord frame, the steel platform is lifted to a height of 2100 mm by the lifting device 4, which is higher than the upper limit of the lifting range. In windy weather, the influence of wind resistance causes the entire chord frame structure to shake, resulting in loosening of the chord frame connection points, which will reduce the structural strength of the chord frame.
[0065] The above are only embodiments of the present invention. The invention is not limited to the fields involved in this implementation case. The common knowledge such as the known specific structure and characteristics in the scheme is not described in detail here. It should be pointed out that for those skilled in the art, several deformations and improvements can be made without departing from the structure of the present invention, which should also be regarded as the protection scope of the present invention, and these will not affect the effect of the implementation of the present invention and the practicality of the patent. The scope of protection required by this application shall be based on the content of its claims, and the specific implementation methods and other records in the specification can be used to interpret the content of the claims.
Claims
1. Construction method of large-span grid ground lifting and assembly, It is characterized in that The steps include: The first step is to splice the steel platform on the ground inside the concrete shell; The second step is to arrange multiple lifting equipment under the steel platform; The third step is to gradually lift the steel platform using lifting equipment, and install the first-layer string frame and the second-layer string frame during the lifting process; The fourth step is to weld the roof frame on the steel platform; Step 5: Use the lifting equipment to gradually lift the steel platform again, and install the third-layer string frame, the fourth-layer string frame and the fifth-layer string frame during each lifting; Step 6, evenly distribute multiple lifting brackets along the circumference of the outer circle of the fifth string frame; Step 7: a plurality of lifters are evenly distributed along the circumference above the concrete cylinder shell, the lifters are fixed to the top of the cylinder shell through a fixing frame, the fixing frame includes a first pillar and a second pillar fixed to the first pillar cylinder shell, a first horizontal pillar is fixed between the first pillar and the second pillar, a second horizontal pillar is fixed above the first pillar and the second pillar, the top end of the second pillar is fixed to the middle of the second horizontal pillar, one end of the second horizontal pillar extends to the inner side of the cylinder shell, and the lifter is installed above the end of the second horizontal pillar extending from the inner side of the cylinder shell; Step 8: Hook the hook of the lifter to the lifting bracket, and use the lifter to lift the entire grid to a height close to the top of the cylinder shell; Step 9: Use a crane to hoist the parts of the bottom string frame to the top of the cylinder shell and assemble them under the fifth string frame; The tenth step is to install the support on the upper end of the cylinder shell, connect the bottom string frame with the support, and complete the installation of the entire grid.
2. According to the large-span grid ground lifting and assembly construction method described in claim 1, Features: In the second step, a plurality of lifting devices are evenly distributed under the steel platform.
3. According to the large-span grid ground lifting and assembly construction method of claim 2, Features: In the third step, after the lifting equipment lifts the steel platform for the first time, a plurality of support columns are evenly fixed on the outer circle of the steel platform, and the first layer of chord frames is fixed on the support columns.
4. According to the large-span grid ground lifting and assembly construction method of claim 3, Features: In the sixth step and the seventh step, the number of lifting brackets and lifters is equal.
5. According to the large-span grid ground lifting and assembly construction method of claim 4, Features: In the ninth step, the bottom string frame is a small unit structure composed of scattered bolt balls and rods, and the small unit structure includes a bolt ball and a plurality of rods threadedly connected to the bolt ball.
6. The large-span grid ground lifting and assembly construction method according to claim 5, Features: In the tenth step, after the support is installed, the lifting bracket and the lifter are symmetrically removed.