Scaffold profile steel overhanging anchoring device and using method
By using components such as connecting rods, top positioning plates, and bottom positioning plates in the cantilever anchoring device to limit the movement of the cantilever beam, the problem that the anchor bars cannot be recycled in the existing technology is solved, and material recycling and construction safety are improved. .
Patent Information
- Application Number
- CN202411189166.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-28
- Publication Date
- 2024-10-25
AI Technical Summary
The existing cantilevered scaffolding anchoring device cannot recycle the anchoring bars during disassembly, resulting in waste of construction materials and potential safety hazards during the removal process.
A cantilever anchoring device including a connecting rod, a top positioning plate, a bottom positioning plate, a top limiter, a bottom limiter and a sleeve is designed. These components limit the movement of the cantilever beam and prevent it from being fixed on the concrete. within the slab, and these components were dismantled after the concrete was poured to recover the metal material.
It realizes the recycling of all metal materials of the cantilever anchoring device, reduces the waste of building materials and construction safety risks, and improves the environmental protection and safety of the construction.
Smart Images

Figure CN118835786A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of scaffold cantilever anchoring, in particular to a scaffold steel cantilever anchoring device and a use method thereof. Background Art
[0002] At present, with the rapid development of the construction industry, building structures are moving towards higher and more complex forms, and high-rise and special-shaped building structures are increasing. Cantilever scaffolding is often a necessary condition to ensure its smooth construction. It has the advantages of flexible layout, good safety performance, and no interference with other processes. It is widely used. It is gradually developing towards toolization, and the research on cantilever steel beam anchoring device is the embodiment of toolization. The device is applied to the cantilever steel beam of the external frame and the concrete floor layer, which plays the role of anchoring the steel beam to the concrete floor and resisting the bending moment force transmitted by the external frame load.
[0003] The existing anchoring device includes a U-shaped anchor bar, which is then pre-buried in a steel bar frame that supports a formwork, and then the position of the anchor bar is fixed with concrete. The concrete forms a concrete slab on the top surface of the formwork, and then the steel cantilever beam is placed on the concrete slab and penetrated through the anchor bar. A sealing steel plate is sleeved on the open end of the anchor bar so that the sealing steel plate spans the open end of the anchor bar in length direction and is pressed on the top wall of the steel cantilever beam. Finally, nuts are threaded on the two steel bars at the open end of the anchor bar to compact the sealing steel plate on the steel cantilever beam.
[0004] The above-mentioned existing technical solutions have the following defects: after the existing building is completed, the outer scaffolding is removed, and the anchor bars are no longer necessary. The cantilever beams can be recycled, but the U-shaped anchor bars are buried in the concrete and cannot be recycled at all, resulting in a waste of building materials. In addition, long anchor bars leak out from the concrete slabs of the building, and it takes time and effort to uniformly cut them out. Safety hazards may also arise in the process of cutting the steel bars. This undoubtedly shows the drawbacks of the existing anchor bar technology. How to solve these drawbacks has become an urgent problem to be solved. Summary of the invention
[0005] The purpose of the present invention is to provide a scaffolding steel cantilever anchoring device and a use method, which can recycle all metal materials in the anchoring device, thereby greatly reducing the waste of building materials.
[0006] To achieve the above object, the present invention provides the following technical solutions: A scaffolding steel cantilever anchoring device, comprising a positioning assembly for limiting the position of a cantilever beam on a concrete slab, wherein the concrete slab is cast on the top surface of a formwork, the cantilever beam comprises a cantilever section extending out of the concrete slab and a fixed section contacting the concrete slab, and a plurality of positioning assemblies are arranged along the extension direction of the fixed section; The positioning assembly includes two connecting rods arranged opposite to each other, a positioning groove for the cantilever beam to pass through is formed between the two connecting rods arranged opposite to each other, a top positioning plate is sleeved on one end of the connecting rod located above the top surface of the template, and a bottom positioning plate is sleeved on one end of the connecting rod located below the bottom surface of the template, and the top positioning plate and the bottom positioning plate are both arranged across the positioning groove; The end of the connecting rod extending from the top surface of the template is provided with a top stopper to prevent the top positioning plate from falling off toward the end away from the template, and the end of the connecting rod extending from the bottom surface of the template is provided with a bottom stopper to prevent the bottom positioning plate from falling off in the direction away from the template; The outer sliding sleeve of the connecting rod is provided with a sleeve, and the sleeve is located on the upper surface of the template. The end of the sleeve close to the template is in contact with the template. The template is provided with a connecting hole for the connecting rod to pass through. The end of the sleeve close to the template is provided with a blocking device for blocking the connecting hole, and the height of the sleeve is greater than the thickness of the concrete slab, and the height of the sleeve is less than the height of the concrete slab plus the cantilever beam.
[0007] By adopting the above technical scheme, two connecting rods are arranged on both sides of the cantilever beam to limit the horizontal movement freedom of the cantilever beam, and a top positioning plate and a bottom positioning plate are respectively arranged at the two ends of the two connecting rods, and then the distance between the top positioning plate and the bottom positioning plate can be controllably tightened by the top positioning device and the bottom limiting device, thereby limiting the vertical displacement of the cantilever beam on the concrete slab; then a sleeve is sleeved on the connecting rod to isolate the concrete cast by the formwork, thereby preventing the connecting rod from being fixed in the concrete slab, preparing for the subsequent recovery of the connecting rod, because the end of the connecting rod located at the bottom surface of the formwork is also removable, which leaves more options for the position of the end of the connecting rod extending out of the bottom wall of the concrete slab, because the bottom positioning plate can be removed, and the end of the connecting rod extending out of the concrete bottom wall can be located between the formwork and the concrete slab, or can extend out of the bottom surface of the formwork. No matter which formwork is selected, it can be removed without affecting the process of formwork removal. If the bottom positioning plate is located The gap between the formwork and the concrete floor will cause the bottom positioning plate and part of the connecting rod to sink into the bottom wall of the concrete slab. Forced removal will leave grooves on the bottom wall of the concrete slab, which will destroy the strength of the concrete slab to a certain extent. This solution chooses to set the bottom positioning plate on the bottom surface of the formwork, and the connecting rods in the concrete slab are all wrapped by the casing. Moreover, the sealing device can block the connecting holes when the concrete is poured. When the cantilever beam can be removed, the operator only needs to remove the top positioning plate and the bottom positioning plate, and then remove the connecting rod from the casing, thereby recovering all the metal materials in the positioning assembly. Moreover, there is only the casing in the solidified concrete slab, and the casing is made of plastic, which is easier to remove. Compared with the connecting rod made of metal, there will not be much cost problem. Moreover, cutting the casing extending out of the top wall of the concrete slab is much safer than cutting the connecting rod made of metal, which greatly reduces the loss of building materials and reduces the construction safety risk. It is environmentally friendly, green and safe.
[0008] Furthermore, the top limiting device and the bottom limiting device both include fixing nuts threadedly sleeved on the connecting rod, and the fixing nuts at both ends of the connecting rod respectively abut against the top positioning plate and the bottom positioning plate.
[0009] By adopting the above technical solution, when the cantilever beam is inserted between the positioning grooves and needs to be finally fixed on the concrete slab, it is only necessary to rotate the fixing nut on the connecting rod, and the fixing nut will apply a downward force to the top positioning plate and an upward force to the bottom positioning plate respectively. The top positioning and bottom positioning plates clamp the cantilever beam on the concrete slab through the transmission of the connecting rod force, thereby facilitating the final fixing of the cantilever beam on the concrete slab.
[0010] Furthermore, an extension sleeve is fixedly provided on a side of the fixing nut away from the template, and the extension sleeve is threadedly sleeved on the connecting rod.
[0011] By adopting the above technical solution, the extension sleeve can increase the thread engagement area between the fixing nut and the connecting rod, thereby improving the connection stability of the fixing nut.
[0012] Furthermore, threaded sleeves at both ends of the connecting rod in the length direction are provided with fastening nuts, and a surface of the fastening nut close to the template abuts against an end surface of the extension sleeve away from the fixing nut.
[0013] By adopting the above technical solution, the fastening nut contacts the end face of the extension sleeve after being tightened, limiting the freedom of the fixing nut in the up and down directions, thereby preventing the fixing nut from loosening and further improving the connection stability of the cantilever beam on the concrete slab.
[0014] Furthermore, the blocking device comprises a sealing ring plate sleeved on one end of the sleeve, and the sealing ring plate covers the communicating hole.
[0015] By adopting the above technical solution, the sealing ring plate covers the connecting hole. When concrete is poured on the template, the weight of the concrete will press the sealing plate on the connecting hole, so that the fluidity of the concrete cannot flow from between the sealing ring plate and the template to the connecting hole, thereby preventing the connecting hole from leaking concrete.
[0016] Furthermore, anti-bending flanges are provided on both sides of the top positioning plate and the bottom positioning plate in the width direction.
[0017] By adopting the above technical scheme, the bending-resistant flange increases the thickness of the top positioning plate and the bottom positioning plate to a certain extent, thereby increasing the stiffness of the top positioning plate and the bottom positioning plate, and increasing the bending resistance of the top positioning plate and the bottom positioning plate to a certain extent, thereby further increasing the connection stability of the concrete slab and the cantilever beam.
[0018] Furthermore, a wedge-shaped positioning block is inserted between the connecting rod and the side wall of the cantilever beam.
[0019] By adopting the above technical solution, the positioning block can fill the gap between the connecting rod and the cantilever beam, thereby preventing the cantilever beam from horizontally displacing on the concrete slab.
[0020] Furthermore, the present invention provides the following technical solutions: A method for using a scaffolding steel cantilever anchoring device comprises the following steps: S1, positioning mark, first determine the position of the cantilever beam on the concrete slab according to the needs, then calculate the penetration position of the connecting rod on the template based on the position of the cantilever beam, draw a mark on the template, and then open a connecting hole at the mark.
[0021] S2, preliminary installation, the construction workers will vertically place the sleeves corresponding to the connecting holes one by one, then put the top positioning plate on the two connecting rods, and screw the fixing nuts of a certain depth on the two connecting rods to ensure that the top positioning plate will not slip off from the end of the connecting rod extending out of the top surface of the template, then lift the top positioning plate and insert the connecting rods into the sleeves one by one, and make the connecting rods pass through the connecting holes and extend to the bottom of the template, then put the bottom positioning plate on the connecting rods extending out of the bottom surface of the template, then put the fixing nuts on the connecting rods extending out of the bottom surface of the template, and use the fixing nuts to make the bottom positioning plate contact with the bottom surface of the template.
[0022] S3, final fixation. After the concrete slab on the formwork is poured and reaches the required strength, the construction personnel rotate the fixing nuts on the connecting rods on the concrete slab to increase the height of the positioning grooves on the concrete slab until the cantilever beam is inserted enough. Then the cantilever beam is inserted into multiple positioning assemblies in turn. The fixing nuts are rotated again to finally compact the top positioning plate on the cantilever beam. Finally, the fastening nuts at both ends of the connecting rod are tightened.
[0023] S4, formwork removal. When the formwork needs to be removed, the construction workers first remove a positioning component, and the other positioning components on the same cantilever beam remain unchanged. Then, the removed positioning component is fixed to the bottom wall of the concrete slab, and then another positioning component is removed, and so on. When the last positioning component is removed, the other positioning components on the same beam have transferred the focus point from the formwork to the bottom wall of the concrete slab. After the focus point of the last positioning component is transferred to the bottom wall of the concrete slab, the formwork can be removed.
[0024] S5, the anchoring device is recovered. When the main structure of the building is completed and the peripheral scaffolding needs to be removed, the fastening nuts and fixing nuts are unscrewed one by one, and then the connecting rod in the sleeve is pulled out.
[0025] By adopting the above technical scheme, a connecting hole is opened on the template through S1, which is not only for opening the hole, but also for preparing for the subsequent casing positioning; an issue that cannot be ignored in this scheme is that in order to completely recover the metal material in the positioning assembly, the connecting rod is movably inserted into the casing, but in the process of pouring concrete, there is a risk that the connecting rod will fall out of the casing, S2 first sets the top positioning plate on the two connecting rods, and then preliminarily positions it through the fixing nuts, and then sets the bottom positioning plate on the connecting rods, and then preliminarily positions it through the fixing nuts, so that the connecting rod will be restricted in the casing by the spatial interference of the top positioning plate and the casing, and will neither fall off from the bottom of the casing nor from the top of the casing. On the one hand, because the top positioning plate and the bottom positioning plate are clamped to each other, the casing can be prevented from tipping over when pouring the concrete slab, and on the other hand, the sealing ring plate on the side wall of the casing will be exerted with a preliminary compacting pressure on the template, which can effectively prevent concrete from flowing into the template and. between the sealing ring plates; in step S3, first rotate the fixing nut to release a certain space of the connecting rod expansion and contraction space, increase the height of the positioning groove, and then the operator lifts the top positioning plate one by one to increase the aperture of the positioning groove on the concrete slab, so as to facilitate the operator to insert the cantilever beam in the positioning groove. When the cantilever beam moves to the specified position in multiple positioning grooves, rotate the fixing nut to compact the top positioning plate on the top wall of the cantilever beam, thereby fixing the cantilever beam on the concrete slab; in step S4, since multiple positioning components are fixed on the cantilever beam, by removing and installing them one by one, the cantilever beam will not be loosened, and the focus point of the positioning component can be transferred to the bottom wall of the concrete slab. The transfer of the focus point is also the process of releasing the bottom positioning plates on the template one by one, and will not affect the removal of the template; in step S5, when the cantilever beam needs to be removed, the fixing nut can be loosened to pull out the connecting rod from the casing, and the fixing nut, tightening nut, top positioning plate and bottom positioning plate can all be recovered.
[0026] Furthermore, the steps of removing the positioning component in S4 are as follows: A1. First unscrew the fastening nut at the end of the connecting rod extending out of the bottom surface of the template, then unscrew the fixing nut at the end of the connecting rod extending out of the bottom surface of the template, and finally remove the bottom positioning plate at the end of the connecting rod extending out of the bottom surface of the template from the connecting rod.
[0027] A2, then screw the fixing nut removed in step A1 onto the connecting rod, the fixing nut passes through the connecting hole and abuts against the bottom wall of the concrete slab, and then screw the fastening nut in step A1 onto the connecting rod and abuts against the end face of the extension sleeve.
[0028] By adopting the above technical solution, in order to ensure that all positioning components can be removed at the beginning of the design, it is thought that other parts of the positioning components except the sleeve will not contact the concrete during the pouring process. At this time, it is thought that the connecting rod is extended out of the bottom surface of the formwork, and then the tendency of the connecting rod to move upward is simultaneously limited by the bottom positioning plate and the fixing nut. However, at this time, the bottom surface of the formwork is a fulcrum of the positioning component, which leads to the problem that the subsequent formwork cannot be removed. Then, by setting up multiple positioning components, even if one positioning component is removed, the other positioning components can still fix the cantilever beam motionlessly, and then a connecting hole is opened on the formwork. When the formwork needs to be removed, the concrete slab can be subjected to force, and then Then continue to rotate the fixing nut, pass the fixing nut through the connecting hole and hit the bottom wall of the concrete slab, thereby completing the transfer of the fulcrum of the positioning assembly. At this time, the fixing nuts on the two connecting rods are sufficient to limit the upward movement of the connecting rods, and the bottom positioning plate has been recovered. By analogy, multiple fulcrums of the positioning assemblies are transferred one by one. At this time, there is no bottom positioning plate on the template to restrict the downward movement of the template, and the normal removal of the template can be completed. In order to prevent the concrete in the flowing state from leaking from the connecting hole, a sealing ring plate is set to cover the connecting hole, so that this scheme can not only do not affect the normal construction, but also completely recover the metal material in the positioning assembly.
[0029] Furthermore, in the step S5, the fastening nut and the fixing nut extending from one end of the connecting rod to the bottom surface of the template are first removed, and then the construction personnel hold the top positioning plate and pull the two connecting rods out of the sleeve together.
[0030] By adopting the above technical solution, the connecting rod is slidably inserted into the sleeve. If the top positioning plate is removed first, the connecting rod will fall due to gravity, which will cause a safety hazard. However, by first removing the bottom positioning plate and then pulling out the connecting rod from above, this safety hazard can be prevented.
[0031] In summary, the beneficial technical effects of the present invention are: 1. Connecting rods, top positioning plates, bottom positioning plates, top limit devices, bottom positioning plates and sleeves are used to recover all metal materials in the cantilever beam anchoring device; 2. The extension sleeve and fastening nut are used to further stabilize and fix the position of the cantilever beam; 3. A sealing ring plate is used to prevent the concrete on the formwork from leaking out of the connecting holes. BRIEF DESCRIPTION OF THE DRAWINGS
[0032] Figure 1 It is a schematic diagram of the overall structure of the present invention; Figure 2 for Figure 1 A schematic diagram of the enlarged structure of the middle part A; Figure 3It is a structural schematic diagram of the positioning component in the present invention; Figure 4 It is a schematic diagram of the explosion cross-section structure at the connecting hole in the present invention; Figure 5 for Figure 4 A schematic diagram of the enlarged structure of the middle B part; Figure 6 It is a schematic diagram of the process structure of the method for using the positioning component in the present invention.
[0033] In the figure, 1. positioning assembly; 11. concrete slab; 12. cantilever beam; 13. fixed section; 14. cantilever section; 15. formwork; 2. connecting rod; 21. sleeve; 22. connecting hole; 23. plugging device; 24. sealing ring plate; 25. positioning groove; 3. top positioning plate; 31. top limiting device; 32. fixing nut; 33. extension sleeve; 34. tightening nut; 35. bottom positioning plate; 36. bottom limiting device; 37. bending-resistant flange; 38. positioning block. DETAILED DESCRIPTION
[0034] The present invention is further described in detail below in conjunction with the accompanying drawings.
[0035] Embodiment 1 Reference Figure 1-Figure 5 The invention discloses a scaffolding steel cantilever anchoring device, which comprises a plurality of positioning components 1 for anchoring cantilever beams 12 on a concrete slab 11. When constructing a main body of a high-rise building, in order to prevent construction workers from falling from the high-rise building, a scaffolding is set up around the main body of the building. However, the overall stability of the scaffolding is limited, so a cantilever beam 12 made of steel is set up on the concrete slab 11 of the main body of the building. A section of the cantilever beam 12 that contacts the concrete slab 11 is a fixed section 13, and a section of the cantilever beam 12 that extends out of the concrete slab 11 is a cantilever section 14. Construction workers fix the scaffolding on the cantilever section 14, and then fix the fixed section 14. By anchoring the section 13 on the concrete slab 11, the scaffolding can be fixed on the concrete slab 11 through the cantilever beam 12, thereby improving the stability of the scaffolding outside the building main body; the existing anchoring method is to preset the anchoring device on the template 15 before pouring the concrete slab 11. After the concrete slab 11 on the template 15 is formed, the anchoring device poured in the concrete slab 11 has been buried in the concrete slab 11, and then the cantilever beam 12 and the anchoring device can be connected. However, when the cantilever beam 12 is recovered, the anchoring device has been buried in the concrete slab 11 and cannot be taken out, which will cause a large amount of building materials to be wasted.
[0036] Reference Figure 1-Figure 5, and the positioning components 1 in this scheme are evenly distributed with three along the fixed section 13, the positioning components 1 include two connecting rods 2, the two connecting rods 2 are arranged on both sides of the width direction of the cantilever beam 12, a positioning groove 25 for placing the cantilever beam 12 is formed between the two connecting rods 2, and a sleeve 21 is arranged outside the two connecting rods 2. The sleeve 21 in the present invention is a plastic tube made of PVC material, a top positioning plate 3 is arranged at one end in the height direction of the positioning groove 25, and a bottom positioning plate 35 is arranged at the other end, and the top positioning plate 3 and the bottom positioning plate 35 are simultaneously sleeved on the two connecting rods 2 and arranged across the width direction of the positioning groove 25. Before pouring the concrete slab 11, the connecting rod 2 is vertically arranged on the template 15, and in order to facilitate the connecting rod 2 to pass through the template 15, a connecting hole 22 for the connecting rod 2 to pass through is opened on the template 15; the top positioning plate 3 is located above the top surface of the template 15, and the bottom positioning plate 35 is located below the bottom surface of the template 15.
[0037] Reference Figure 1-Figure 5 A top limit device 31 for preventing the top positioning plate 3 from falling off and a bottom limit device 36 for preventing the bottom positioning plate 35 from falling off are respectively provided at both ends of the length direction of the connecting rod 2. The top limit device 31 and the bottom limit device 36 are respectively fixed nuts 32 arranged at both ends of the length direction of the connecting rod 2. The fixing nut 32 is threadedly engaged with the connecting rod 2. In order to increase the thread engagement area between the fixing nut 32 and the connecting rod 2, an extension sleeve 33 is provided on the end face of the fixing nut 32. In order to further improve the stability of the fixing nut 32, a fastening nut 34 is provided at the end of the extension sleeve 33 away from the fixing nut 32. The fastening nut 34 is threadedly engaged with the connecting rod 2, and one end of the fastening nut 34 abuts against the end face of the extension sleeve 33.
[0038] Reference Figure 1-Figure 5 In this way, when the cantilever beam 12 needs to be fixed on the concrete slab 11, the cantilever beam 12 only needs to be inserted between the positioning grooves 25, and then the top positioning plate 3 and the bottom positioning plate 35 are clamped on both sides of the height direction of the cantilever beam 12 through the fixing nuts 32, thereby fixing the cantilever beam 12 on the concrete slab 11. When the cantilever beam 12 needs to be recovered, the fixing nuts 32, the top positioning plate 3 and the bottom positioning plate 35 are removed from the connecting rod 2, and then the connecting rod 2 is pulled out of the sleeve 21, so that all the metal materials of the anchoring device can be recovered.
[0039] Reference Figure 1-Figure 5 In order to improve the overall rigidity of the top positioning plate 3 and the bottom positioning plate 35, anti-bending flanges 37 are arranged on both sides of the width direction of the top positioning plate 3 and the bottom positioning plate 35, and the anti-bending flanges 37 are extended along the length direction of the top positioning plate 3 and the bottom positioning plate 35. In order to prevent the cantilever beam 12 from shaking left and right in the positioning groove 25, a wedge-shaped positioning block 38 is inserted between the connecting rod 2 and the cantilever beam 12. The positioning block 38 in this solution is made of solid wood.
[0040] Embodiment 2 Reference Figure 6 , a method for using a scaffolding steel cantilever anchoring device disclosed in the present invention, comprising the following steps: Positioning mark, first determine the position of the cantilever beam 12 on the concrete slab 11 according to the needs, then calculate the penetration position of the connecting rod 2 on the template 15 according to the position of the cantilever beam 12, and draw a mark on the template 15, and then open the connecting hole 22 at the mark; for the initial installation, the construction personnel vertically place the sleeves 21 corresponding to the positions of the connecting holes 22 one by one, and then put the top positioning plate 3 on the two connecting rods 2, and screw the fixing nuts 32 on the two connecting rods 2 to a certain depth to ensure that the top positioning plate 3 does not extend from the connecting rod 2 to the top surface of the template 15 One end slides off, and then the top positioning plate 3 is lifted to insert the connecting rods 2 into the sleeves 21 one by one, and the connecting rods 2 are extended to the bottom of the template 15 through the connecting hole 22, and then the bottom positioning plate 35 is sleeved on the connecting rods 2 extending from the bottom surface of the template 15, and then the fixing nuts 32 are sleeved on the connecting rods 2 extending from the bottom surface of the template 15, and the bottom positioning plate 35 is made to contact the bottom surface of the template 15 through the fixing nuts 32; finally fixed, after the concrete slab 11 on the template 15 is poured and reaches the required strength, the construction personnel rotate the connecting rods on the concrete slab 11 2, increase the height of the positioning groove 25 on the concrete slab 11 until the cantilever beam 12 is inserted, and then the cantilever beam 12 is inserted into the multiple positioning components 1 in sequence, and then the fixing nut 32 is rotated again to finally compact the top positioning plate 3 on the cantilever beam 12, and finally tighten the fastening nuts 34 at both ends of the connecting rod 2; the template 15 is removed. When the template 15 needs to be removed, the construction personnel first remove a positioning component 1, and the other positioning components 1 on the same cantilever beam 12 are not moved, and then the removed positioning component 1 is fixed on On the bottom wall of the concrete slab 11, another positioning assembly 1 is removed, and so on. When the last positioning assembly 1 is removed, the other positioning assemblies 1 on the same beam have transferred the fulcrum from the template 15 to the bottom wall of the concrete slab 11. After the fulcrum of the last positioning assembly 1 is transferred to the bottom wall of the concrete slab 11, the template 15 can be removed; the anchoring device is recovered, and when the main structure of the building is completed and the peripheral scaffolding needs to be removed, the fastening nuts 34 and the fixing nuts 32 are unscrewed one by one, and then the connecting rod 2 in the sleeve 21 is pulled out.
[0041] In the positioning mark, a connecting hole 22 is opened on the template 15, which is not only for the installation of the connecting rod 2, but also for the subsequent positioning of the sleeve 21. In the preliminary installation, the sleeve 21 placed on the template 15 is placed before pouring concrete. The steel bars around the sleeve 21 have been tied, which will play a certain supporting role for the vertical sleeve 21. However, an issue that cannot be ignored in this solution is that in order to completely recover the metal material in the positioning component 1, the connecting rod 2 is movably inserted in the sleeve 21. However, during the pouring of concrete, there is a risk that the connecting rod 2 will fall off the sleeve 21. First, the top positioning plate 3 is placed on the two connecting rods 2, and then through The fixing nut 32 is initially positioned, and then the bottom positioning plate 35 is sleeved on the connecting rod 2, and then initially positioned by the fixing nut 32. In this way, the connecting rod 2 will be restricted in the sleeve 21 by the spatial interference of the top positioning plate 3 and the sleeve 21, and will neither fall off from the bottom of the sleeve 21 nor fall off from the top of the sleeve 21. On the one hand, because the top positioning plate 3 and the bottom positioning plate 35 are clamped to each other, the sleeve 21 can be prevented from tipping over when pouring the concrete slab 11. On the other hand, the sealing ring plate 24 on the side wall of the sleeve 21 will be exerted with a preliminary compacting pressure on the template 15, which can effectively prevent the concrete from flowing into between the template 15 and the sealing ring plate 24. During final fixation, the fixing nut 32 is first rotated to release a certain space of the connecting rod 2 to increase the height of the positioning groove 25. Then the operator lifts the top positioning plate 3 one by one to increase the aperture of the positioning groove 25 on the concrete slab 11, so that the operator can easily insert the cantilever beam 12 in the positioning groove 25. When the cantilever beam 12 moves to the specified position in multiple positioning grooves 25, the fixing nut 32 is rotated to compact the top positioning plate 3 on the top wall of the cantilever beam 12, thereby fixing the cantilever beam 12 on the concrete slab 11. During the removal of the template 15, since multiple positioning components 1 are fixed on the cantilever beam 12, by removing and installing them one by one, it will not cause the cantilever beam 12 to be damaged. When the beam 12 is loosened, the fulcrum of the positioning assembly 1 can be transferred to the bottom wall of the concrete slab 11. The transfer of the fulcrum is also a process of releasing the bottom positioning plates 35 on the formwork 15 one by one, and it will not affect the removal of the formwork 15. The removal of the formwork 15 lags behind the construction of the main building of a higher level. The fundamental reason is that when the formwork of the upper level begins, the beam and slab formwork 15 of the lower level has not reached the age and is not ready for demolding. When the cantilever beam 12 needs to be removed during the recovery of the anchor device, the fixing nut 32 can be loosened to pull out the connecting rod 2 from the sleeve 21, and the fixing nut 32, the tightening nut 34, the top positioning plate 3 and the bottom positioning plate 35 can all be recovered.
[0042] The dismantling steps of the positioning assembly 1 include first unscrewing the fastening nut 34 at one end of the connecting rod 2 extending out of the bottom surface of the template 15, then unscrewing the fixing nut 32 at one end of the connecting rod 2 extending out of the bottom surface of the template 15, and finally removing the bottom positioning plate 35 at one end of the connecting rod 2 extending out of the bottom surface of the template 15 from the connecting rod 2; then screwing the removed fixing nut 32 onto the connecting rod 2, the fixing nut 32 passes through the connecting hole 22 and abuts against the bottom wall of the concrete slab 11, and then screwing the fastening nut 34 onto the connecting rod 2 and abuts against the end surface of the extension sleeve 33.
[0043] At the beginning of the design, in order to ensure that all the positioning components 1 can be removed, it was thought that the positioning components 1, except for the sleeve 21, would not contact the concrete during the pouring process. At this time, it was thought that the connecting rod 2 would extend out of the bottom surface of the template 15, and then the bottom positioning plate 35 and the fixing nut 32 would simultaneously limit the tendency of the connecting rod 2 to move upward. However, at this time, the bottom surface of the template 15 is a fulcrum of the positioning component 1, which leads to the problem that the subsequent template 15 cannot be removed. Then, by setting up multiple positioning components 1, even if one positioning component 1 is removed, the other positioning components 1 can still fix the cantilever beam 12 without moving, and then a connecting hole 22 is opened on the template 15. When the template 15 needs to be removed, the concrete slab 11 can be subjected to force, and then the fixing nut 32 is continued to be rotated to fix the fixing nut 32. The connecting hole 22 passes through and hits the bottom wall of the concrete slab 11, thereby completing the transfer of the fulcrum of the positioning component 1. At this time, the fixing nuts 32 on the two connecting rods 2 are sufficient to limit the upward movement of the connecting rods 2, and the bottom positioning plate 35 has been recovered. By analogy, the fulcrums of multiple positioning components 1 are transferred one by one. At this time, there is no bottom positioning plate 35 on the template 15 to limit the downward movement of the template 15, and the normal removal of the template 15 can be completed. In addition, in order to prevent the concrete in the flowing state from leaking from the connecting hole 22, a sealing ring plate 24 is sleeved on the end of the outer wall of the sleeve 21 close to the template 15, and the sealing ring plate 24 covers the connecting hole 22, so that the present scheme can not only completely recover the metal material in the positioning component 1 without affecting the normal construction.
[0044] The specific recovery and removal process of the positioning assembly 1 is to first remove the fastening nut 34 and the fixing nut 32 of the connecting rod 2 extending to one end of the bottom surface of the template 15, and then the construction personnel hold the top positioning plate 3 to pull the two connecting rods 2 out of the sleeve 21 together; the connecting rod 2 is slidably inserted into the sleeve 21. If the top positioning plate 3 is removed first, the connecting rod 2 will fall under the action of gravity, which will cause a safety hazard. However, by first removing the bottom positioning plate 35 and then pulling out the connecting rod 2 from the top, the occurrence of such a safety hazard can be prevented.
[0045] The embodiments of this specific implementation method are all preferred embodiments of the present invention, and are not intended to limit the protection scope of the present invention. Therefore, any equivalent changes made based on the structure, shape, and principle of the present invention should be included in the protection scope of the present invention.
Claims
1. A scaffolding steel cantilever anchoring device, characterized in that: It comprises a positioning assembly (1) for limiting the position of a cantilever beam (12) on a concrete slab (11), wherein the concrete slab (11) is cast on the top surface of a formwork (15), the cantilever beam (12) comprises a cantilever section (14) extending out of the concrete slab (11) and a fixed section (13) contacting the concrete slab (11), and a plurality of the positioning assemblies (1) are arranged along the extension direction of the fixed section (13); The positioning assembly (1) comprises two connecting rods (2) arranged opposite to each other, a positioning groove (25) for the cantilever beam (12) to pass through is formed between the two connecting rods (2), one end of the connecting rod (2) located above the top surface of the template (15) is sleeved with a top positioning plate (3), and one end of the connecting rod (2) located below the bottom surface of the template (15) is sleeved with a bottom positioning plate (35), and the top positioning plate (3) and the bottom positioning plate (35) are both arranged across the positioning groove (25); The end of the connecting rod (2) extending out of the top surface of the template (15) is provided with a top stop device (31) for preventing the top positioning plate (3) from falling off in the direction away from the template (15), and the end of the connecting rod (2) extending out of the bottom surface of the template (15) is provided with a bottom stop device (36) for preventing the bottom positioning plate (35) from falling off in the direction away from the template (15); The connecting rod (2) is slidably sleeved with a sleeve (21) outside. The sleeve (21) is located on the upper surface of the template (15). One end of the sleeve (21) close to the template (15) abuts against the template (15). The template (15) is provided with a connecting hole (22) for the connecting rod (2) to pass through. One end of the sleeve (21) close to the template (15) is provided with a blocking device (23) for blocking the connecting hole (22). The height of the sleeve (21) is greater than the thickness of the concrete slab (11), and the height of the sleeve (21) is less than the height of the concrete slab (11) plus the cantilever beam (12).
2. The scaffolding steel cantilever anchoring device according to claim 1 is characterized in that: The top limiting device (31) and the bottom limiting device (36) both comprise fixing nuts (32) threadedly sleeved on the connecting rod (2), and the fixing nuts (32) at both ends of the connecting rod (2) respectively abut against the top positioning plate (3) and the bottom positioning plate (35).
3. The scaffolding steel cantilever anchoring device according to claim 2 is characterized in that: An extension sleeve (33) is fixedly provided on a side of the fixing nut (32) away from the template (15), and the extension sleeve (33) is threadedly sleeved on the connecting rod (2).
4. The scaffolding steel cantilever anchoring device according to claim 3 is characterized in that: The threaded sleeves at both ends of the connecting rod (2) in the length direction are provided with fastening nuts (34), and the side of the fastening nut (34) close to the template (15) abuts against the end surface of the extension sleeve (33) away from the fixing nut (32).
5. The scaffolding steel cantilever anchoring device according to claim 4 is characterized in that: The blocking device (23) comprises a sealing ring plate (24) sleeved on one end of the sleeve (21), and the sealing ring plate (24) covers the communicating hole (22).
6. The scaffolding steel cantilever anchoring device according to claim 5, characterized in that: Anti-bending flanges (37) are provided on both sides of the top positioning plate (3) and the bottom positioning plate (35) in the width direction.
7. The scaffolding steel cantilever anchoring device according to claim 6 is characterized in that: A wedge-shaped positioning block (38) is inserted between the connecting rod (2) and the side wall of the cantilever beam (12).
8. A method for using a scaffolding steel cantilever anchoring device according to any one of claims 1 to 7, characterized in that: The following steps are involved: S1, positioning mark, first determine the position of the cantilever beam (12) on the concrete slab (11) according to the requirements, then calculate the penetration position of the connecting rod (2) on the template (15) according to the position of the cantilever beam (12), draw a mark on the template (15), and then open a connecting hole (22) at the marked position; S2, preliminary installation, the construction personnel vertically place the sleeves (21) corresponding to the connecting holes (22) one by one, then put the top positioning plate (3) on the two connecting rods (2), and screw the fixing nuts (32) of a certain depth on the two connecting rods (2) to ensure that the top positioning plate (3) will not slide off from the end of the connecting rod (2) extending out of the top surface of the template (15), then lift the top positioning plate (3) and insert the connecting rods (2) into the sleeves (21) one by one, and make the connecting rods (2) pass through the connecting holes (22) and extend to the bottom of the template (15), then put the bottom positioning plate (35) on the connecting rod (2) extending out of the bottom surface of the template (15), then put the fixing nuts (32) on the connecting rod (2) extending out of the bottom surface of the template (15), and make the bottom positioning plate (35) contact the bottom surface of the template (15) through the fixing nuts (32); S3, final fixation. After the concrete slab (11) on the formwork (15) is poured and reaches the required strength, the construction personnel rotate the fixing nut (32) on the connecting rod (2) on the concrete slab (11) to increase the height of the positioning groove (25) on the concrete slab (11) until it is high enough for the cantilever beam (12) to be inserted. Then, the cantilever beam (12) is inserted into the multiple positioning assemblies (1) in sequence. Then, the fixing nut (32) is rotated again to finally compact the top positioning plate (3) on the cantilever beam (12). Finally, the fastening nuts (34) at both ends of the connecting rod (2) are tightened. S4, the template (15) is removed. When the template (15) needs to be removed, the construction personnel first remove a positioning component (1), and the other positioning components (1) on the same cantilever beam (12) remain unchanged. Then, the removed positioning component (1) is fixed to the bottom wall of the concrete slab (11), and another positioning component (1) is removed. This process is repeated by analogy. When the last positioning component (1) is removed, the other positioning components (1) on the same beam have already transferred their points of force from the template (15) to the bottom wall of the concrete slab (11). After the last positioning component (1) has its point of force transferred to the bottom wall of the concrete slab (11), the template (15) can be removed. S5, the anchoring device is recovered. When the main structure of the building is completed and the peripheral scaffolding needs to be removed, the fastening nuts (34) and the fixing nuts (32) are screwed out one by one, and then the connecting rod (2) in the sleeve (21) is pulled out.
9. The method for using the scaffolding steel cantilever anchoring device according to claim 8, characterized in that: The steps of removing the positioning component (1) in S4 are as follows: A1, first unscrew the fastening nut (34) at the end of the connecting rod (2) extending out of the bottom surface of the template (15), then unscrew the fixing nut (32) at the end of the connecting rod (2) extending out of the bottom surface of the template (15), and finally remove the bottom positioning plate (35) at the end of the connecting rod (2) extending out of the bottom surface of the template (15) from the connecting rod (2); A2, then screw the fixing nut (32) removed in step A1 onto the connecting rod (2), the fixing nut (32) passes through the connecting hole (22) and abuts against the bottom wall of the concrete slab (11), and then screw the fastening nut (34) in step A1 onto the connecting rod (2) and abuts against the end face of the extension sleeve (33).
10. The method for using the scaffolding steel cantilever anchoring device according to claim 9, characterized in that: In the step S5, the fastening nut (34) and the fixing nut (32) extending from one end of the connecting rod (2) to the bottom surface of the template (15) are first removed, and then the construction personnel hold the top positioning plate (3) to pull the two connecting rods (2) out of the sleeve (21) together.
Citation Information
Patent Citations
Cantilever beam anchoring piece and mounting method and dismounting method thereof
CN104060814A
Tool-type section-steel cantilever unloading platform and construction method
CN111119498A
Support arrangement for scaffold frame of encorbelmenting
CN206616843U
Scaffold frame of encorbelmenting and fixed subassembly thereof
CN208718331U
Scaffold profile steel cantilever anchoring device
CN223190031U