Method and device for monitoring regional electrical load loss
By converting the main wiring diagram of the power grid into a directed point-line diagram and calculating the correlation matrix, the problem of non-real-time and inaccurate load loss data monitoring during power grid accident tripping is solved, rapid and accurate monitoring of power grid load loss is achieved, and the efficiency of monitoring is improved. Real-time and efficiency.
Patent Information
- Application Number
- CN202410876274.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-02
- Publication Date
- 2024-10-29
AI Technical Summary
The existing technology has problems such as non-real-time data, long time consumption, and low accuracy in load loss data monitoring when a power grid accident trips, making it difficult to quickly and accurately monitor the severity of a power grid trip.
By converting the main wiring diagram of the substation into a directed point-line diagram, the state vector, adjacency matrix and node topology matrix are formed, and the regional line load vector and outlet load state matrix are calculated. Combined with the load transfer matrix, real-time analysis of the load loss when the power grid trips is realized. monitor.
The accuracy, real-time and efficiency of power grid switch load loss monitoring are improved, and the load of the outage line can be quickly and accurately identified and the impact of automatic load transfer can be considered.
Smart Images

Figure CN118868097A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to a method and a device for monitoring regional power load loss, belonging to the technical field of power grids. Background Art
[0002] At present, the power system is becoming increasingly complex, and the grid structure is becoming increasingly complex. When the grid trips due to an accident, the difficulty of monitoring load loss data is also increasing. Load loss is an important parameter to measure the severity of the grid tripping, and is directly related to the level of emergency response required to be initiated. The commissioning of automatic devices in power grids at all levels, including reclosing, standby automatic switching, and distribution network feeder automation (FA, Feeden Autonation) equipment, has increased the difficulty of monitoring load loss data when the grid trips due to an accident. The current existing technologies for monitoring load loss data include manual statistical methods, instantaneous power flow estimation methods, and trip switch statistical methods, which have problems such as unreal-time data monitoring, long time consumption, and low accuracy. Summary of the invention
[0003] The purpose of the present invention is to provide a method and device for monitoring regional power load loss when a regional power grid trips due to an accident, so as to solve the problems of the existing method for monitoring load loss data, such as unreal-time data monitoring, long time consumption, and low accuracy, and to achieve fast and accurate load loss monitoring when a power grid trips due to an accident.
[0004] The purpose of the present invention is achieved through the following technical solutions:
[0005] A method for monitoring regional power load loss comprises the following steps:
[0006] 1) The main wiring of the substation is converted into a directed point-line diagram:
[0007] With power source, busbar, main transformer and load as nodes, circuit breaker as edge, and the direction of edge as the normal flow direction of power grid, the main wiring diagram of substation is converted into a directed point-line diagram;
[0008] 2) According to the states of each node in the directed point-line graph, a state vector U is formed:
[0009] where u i is the state of node i. When node i has voltage, u i =1; when there is no voltage at node i, u i =0; where n is the number of nodes, and 1≤i≤n;
[0010] 3) According to the relationship between each node and each edge in the directed point-line graph, an adjacency matrix M is formed, and the adjacency matrix M is an n×n matrix;
[0011] When node i is a power node, the corresponding diagonal element M(i,i)=1; when node i is a non-power node, the corresponding diagonal element M(i,i)=0, 1≤i≤n;
[0012] When node i is connected to node j, and the direction in the directed point-line graph is from i to j, the corresponding element M(i,j)=1, M(j,i)=0, where i≠j and 1≤i,j≤n;
[0013] When node i is connected to node j, and the directions in the directed point-line graph are i and j, M(i,j)=1, M(j,i)=1, where i≠j and 1≤i,j≤n;
[0014] When node i is not directly connected to node j, M(i,j)=0, M(j,i)=0, where i≠j and 1≤i,j≤n;
[0015] 4) Form the node topology matrix T according to the adjacency matrix M:
[0016] Intermediate matrix M1 = M k , where the power k is the maximum number of edges between any two nodes in the directed point-line graph;
[0017] T = f(M1), where f(M1) is a normalization function. When an element in M1 is greater than 0, the corresponding element is assigned a value of 1, and the rest are assigned a value of 0.
[0018] 5) Calculate the regional line load vector P:
[0019] Where 1≤i≤m, m is the number of regional line loads, p i is the load value of the i-th line load;
[0020] 6) List the outgoing line load state matrix Z:
[0021] Where 1≤i≤m, z i =1 means the load of the ith line has voltage, z i =0 means the load of the i-th line loses power;
[0022] 7) Based on the state vector U and the regional line load vector P, a load node extraction matrix R is formed, and the extraction matrix R is an m×n-order matrix;
[0023] When the node j in the state vector U and the i-th load in the regional line load vector P describe the attributes of the same device, R(i,j)=1, and 1≤i≤m, 1≤j≤n;
[0024] 8) Calculate the line load state matrix Z:
[0025] Z=RTU
[0026] 9) Load transfer matrix Y
[0027] Where 1≤i≤m, m is the number of all outgoing loads, y i =1 means the load of the ith outgoing line does not have the automatic transfer function, y i = 0 means the load of the ith outgoing line has the function of automatic transfer;
[0028] 10) The load loss when the grid trips is defined as
[0029]
[0030] A regional power load loss monitoring device includes: a processor and a memory, the memory is used to store executable instructions of the processor, and the processor is configured to execute the above-mentioned regional power load loss monitoring method by executing the executable instructions.
[0031] Compared with the prior art, the beneficial technical effects of the present invention are as follows: the current methods for monitoring load loss of power grid switches mainly include manual statistical methods, instantaneous power flow estimation methods and trip switch statistics, and the methods of the prior art have problems such as long statistical time and low accuracy; the present invention accurately identifies the load of power-lost lines based on the real-time topology of the regional power grid, and considers the impact of automatic line load transfer on load loss statistics, thereby improving the accuracy, real-time and efficiency of power grid switch load loss monitoring. BRIEF DESCRIPTION OF THE DRAWINGS
[0032] Figure 1 The wiring diagram of the regional power grid of the embodiment;
[0033] Figure 2 1 is a directed point-line graph of an embodiment. DETAILED DESCRIPTION
[0034] The present invention will be further described below in conjunction with the accompanying drawings and specific embodiments.
[0035] like Figure 1 The regional power grid wiring diagram of the embodiment is as follows: Figure 2 1 is a directed point-line graph of an embodiment.
[0036] A method for monitoring regional power load loss of the present invention comprises the following steps:
[0037] 1) The main wiring of the substation is converted into a directed point-line diagram:
[0038] With power source, busbar, main transformer and load as nodes, circuit breaker as edge, and the direction of edge as the normal flow direction of power grid, the main wiring diagram of substation is converted into a directed point-line diagram;
[0039] Wiring diagram Figure 1 For example, it is transformed into a directed point-line graph as Figure 2 .
[0040] Among them, node A is power supply 1, node B is power supply 2, node C is the combination of 10kV I section bus and transformer 1, node D is the combination of 10kV II section bus and transformer 2, node E is 400V I section bus, node V is 400V II section bus, node G is load 1, node H is load 2, node O is load 3, node J is load 4, node K is load 5, and node L is load 6.
[0041] Line ac is circuit breaker QF1; line cd is circuit breaker QF3; line bd is circuit breaker QF2; line ce is circuit breaker QF4; line dv is circuit breaker QF5; line eg is circuit breaker QF7; line eh is circuit breaker QF8; line eo is circuit breaker QF9; line ev is circuit breaker QF6; line vj is circuit breaker QF 10 ; Line vq is circuit breaker QF 11 ; Line vl is circuit breaker QF 12 .
[0042] The direction of each line is the normal flow direction of the power grid.
[0043] 2) According to the states of each node in the directed point-line graph, a state vector U is formed:
[0044] where u i is the state of node i. When node i has voltage, u i =1; when there is no voltage at node i, u i =0; where n is the number of nodes, and 1≤i≤n;
[0045] 3) According to the relationship between each node and each edge in the directed point-line graph, an adjacency matrix M is formed, and the adjacency matrix M is an n×n matrix;
[0046] When node i is a power node, the corresponding diagonal element M(i,i)=1; when node i is a non-power node, the corresponding diagonal element M(i,i)=0, 1≤i≤n;
[0047] When node i is connected to node j, and the direction in the directed point-line graph is from i to j, the corresponding element M(i,j)=1, M(j,i)=0, where i≠j and 1≤i,j≤n;
[0048] When node i is connected to node j, and the directions in the directed point-line graph are i and j, M(i,j)=1, M(j,i)=1, where i≠j and 1≤i,j≤n;
[0049] When node i is not directly connected to node j, M(i,j)=0, M(j,i)=0, where i≠j and 1≤i,j≤n;
[0050] For example Figure 2 Example directed point-line diagram: Among them, when the node is a power node, the diagonal elements in the M matrix are 1, and the rest are 0; ac = QF1; bd = QF2; cd = QF3; ce = QF4; dv = QF5; eg = QF7; eh = QF8; eo = QF9; ev = QF6; vj = QF 10 ; vq=QF 11 ; vl = QF 12 . And when the circuit breaker QF i QF i =1, quantile time QF i =0, i is the number of the circuit breaker.
[0051] 4) Form the node topology matrix T according to the adjacency matrix M:
[0052] Intermediate matrix M1 = M k , where the power k is the maximum number of edges between any two nodes in the directed point-line graph;
[0053] T = f(M1), where f(M1) is a normalization function. When an element in M1 is greater than 0, the corresponding element is assigned a value of 1, and the rest are assigned a value of 0; for example
[0054] 5) Calculate the regional line load vector P:
[0055] Where 1≤i≤m, m is the number of regional line loads, p i is the load value of the i-th line load;
[0056] 6) List the outgoing line load state matrix Z:
[0057] Where 1≤i≤m, z i =1 means the load of the ith line has voltage, z i =0 means the load of the i-th line loses power;
[0058] 7) Based on the state vector U and the regional line load vector P, a load node extraction matrix R is formed, and the extraction matrix R is an m×n-order matrix;
[0059] When the node j in the state vector U and the i-th load in the regional line load vector P describe the attributes of the same device, R(i,j)=1, and 1≤i≤m, 1≤j≤n;
[0060] 8) Calculate the line load state matrix Z:
[0061] Z=RTU
[0062] 9) Load transfer matrix Y
[0063] Where 1≤i≤m, m is the number of all outgoing loads, y i =1 means the load of the ith outgoing line does not have the automatic transfer function, y i =0 means that the load of the ith outgoing line has the function of automatic transfer; the automatic load transfer means that when the line loses power due to some reason, the load connected to the line can automatically disconnect from the power-lost line and switch to other normally operating lines, and there is no load loss at this time.
[0064] 10) The load loss when the grid trips is defined as
[0065]
[0066] The specific embodiments of the present invention are as follows:
[0067] by Figure 1 Take for example, at the moment before tripping, the outgoing line load matrix is Unit kW; load transfer matrix Circuit breaker QF1, QF2, QF4, QF5, QF7, QF8, QF9, QF 10 , QF 11 , QF 12 Closed; circuit breakers QF3 and QF6 are open; power supply 1 has power, but power supply 2 loses power due to tripping of the upper power grid.
[0068] According to the above conditions, the state matrix
[0069] Adjacency Matrix Compute node topology matrix Load Node Extraction Matrix Calculation can be obtained
[0070] but
[0071] In order to achieve real-time and accuracy of load loss data monitoring, the present invention provides a regional electricity load loss monitoring device, including: a processor and a memory, the memory is used to store executable instructions of the processor, and the processor is configured to execute the above-mentioned regional electricity load loss monitoring method by executing the executable instructions, so as to perform data monitoring with the built-in processor of the regional electricity load loss monitoring device.
[0072] It should be noted that the terms "include", "comprises" or any other variations thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device. In the absence of further restrictions, an element defined by the sentence "comprises a ..." does not exclude the existence of other identical elements in the process, method, article or device including the element.
[0073] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.
Claims
1. A method for monitoring regional power load loss, characterized in that: The following steps are involved: 1) The main wiring of the substation is converted into a directed point-line diagram: With power source, busbar, main transformer and load as nodes, circuit breaker as edge, and the direction of edge as the normal flow direction of power grid, the main wiring diagram of substation is converted into a directed point-line diagram; 2) According to the states of each node in the directed point-line graph, a state vector U is formed: where u i is the state of node i. When node i has voltage, u i =1; when there is no voltage at node i, u i =0; where n is the number of nodes, and 1≤i≤n; 3) According to the relationship between each node and each edge in the directed point-line graph, an adjacency matrix M is formed, and the adjacency matrix M is an n×n matrix; When node i is a power node, the corresponding diagonal element M(i,i)=1; When node i is a non-power node, the corresponding diagonal element M(i,i)=0, 1≤i≤n; When node i is connected to node j, and the direction in the directed point-line graph is from i to j, the corresponding element M(i,j)=1, M(j,i)=0, where i≠j and 1≤i,j≤n; When node i is connected to node j, and the directions in the directed point-line graph are i and j, M(i,j)=1, M(j,i)=1, where i≠j and 1≤i,j≤n; When node i is not directly connected to node j, M(i,j)=0, M(j,i)=0, where i≠j and 1≤i,j≤n; 4) Form the node topology matrix T according to the adjacency matrix M: Intermediate matrix M1 = M k , where the power k is the maximum number of edges between any two nodes in the directed point-line graph; T = f(M1), where f(M1) is a normalization function. When an element in M1 is greater than 0, the corresponding element is assigned a value of 1, and the rest are assigned a value of 0. 5) Calculate the regional line load vector P: Where 1≤i≤m, m is the number of regional line loads, p i is the load value of the i-th line load; 6) List the outgoing line load state matrix Z: Where 1≤i≤m, z i =1 means the load of the ith line has voltage, z i =0 means the load of the i-th line loses power; 7) Based on the state vector U and the regional line load vector P, a load node extraction matrix R is formed, and the extraction matrix R is an m×n-order matrix; When the node j in the state vector U and the i-th load in the regional line load vector P describe the attributes of the same device, R(i,j)=1, and 1≤i≤m, 1≤j≤n; 8) Calculate the line load state matrix Z: Z=RTU 9) Load transfer matrix Y Where 1≤i≤m, m is the number of all outgoing loads, y i =1 means the load of the ith outgoing line does not have the automatic transfer function, y i = 0 means the load of the ith outgoing line has the function of automatic transfer; 10) The load loss when the grid trips is defined as ▽p, 2. A regional power load loss monitoring device, characterized in that: The regional power load loss monitoring device includes: a processor and a memory, the memory is used to store executable instructions of the processor, and the processor is configured to execute the regional power load loss monitoring method described in claim 1 by executing the executable instructions.