Beam changing system and beam changing method of bridge
Through the combined system of lifting crane and translation crane, the problems of large area, high difficulty, long time and high risk in bridge replacement are solved, and the safety and efficiency of bridge replacement are achieved and time shortened.
Patent Information
- Application Number
- CN202411126633.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-16
- Publication Date
- 2024-11-01
AI Technical Summary
The existing bridge replacement method has problems such as large area, high difficulty in replacing beams, long construction time and high construction risk.
Using a combination system of lifting crane and translation crane, the prefabricated beams can be removed from or placed on the bridge through the combination of lifting crane and translation crane, thereby completing the bridge replacement, and the lift crane can Supports the extended end of the translation crane to improve lifting capacity, while both are arranged on the ground to reduce bridge deck occupation and shorten replacement time.
The safety and efficiency of bridge replacement have been improved, the footprint of bridge decks has been minimized, the replacement time has been shortened, and the construction risks and costs have been reduced.
Smart Images

Figure CN118880768A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to a beam replacement system and a beam replacement method for a bridge. Background Art
[0002] With the development of urban transportation, urban renewal has gradually been put on the agenda. A large number of bridge projects in cities need to be replaced or repaired. However, the interruption of traffic has a huge impact on urban traffic, so the replacement and repair method that reduces the impact on traffic is the first choice for the implementation of urban traffic renewal. However, it is extremely difficult to replace beam components in a busy and continuous traffic environment, and the safety risks are also relatively large.
[0003] In the prior art, a bridge erection machine is usually used to replace a bridge, but when the bridge erection machine is used, it needs to be installed on the bridge deck before use. Therefore, this method, on the one hand, requires space on the bridge deck, and on the other hand, it also causes the problems of long construction period and high construction cost. Summary of the invention
[0004] The technical problem to be solved by the present invention is to overcome the defects of the prior art such as large occupation of area, high difficulty in beam replacement, long construction time and high construction risk, and to provide a beam replacement system and beam replacement method for a bridge.
[0005] The present invention solves the above technical problems through the following technical solutions:
[0006] A beam replacement system for a bridge, the beam replacement system comprising a lifting crane and a translation crane,
[0007] The translation crane comprises a main body, a main arm and a translation part, wherein the main body is used to be placed on the ground, the main arm extends above the bridge, and one end of the main arm is connected to the main body; the translation part is arranged on the main arm and can move along the main arm, and the translation part is used to hoist the precast beams of the bridge;
[0008] The lifting crane is used to be placed on the ground. The lifting crane includes a lifting part, a first hook and a second hook. The first hook and the second hook are both arranged on the lifting part. The first hook is used to lift the prefabricated beam, and the second hook is used to connect with the end of the main arm away from the main body.
[0009] In this solution, by using the lifting crane and the translation crane in coordination, the prefabricated beam can be removed from the bridge or placed on the bridge, thereby completing the replacement of the prefabricated beam of the bridge. In addition, the lifting crane can also support the extended end of the translation crane to improve the ability of the translation crane to lift the prefabricated beam. In addition, the lifting crane and the translation crane can be set on the ground, thereby minimizing the occupation of the bridge deck space when the bridge beam is replaced, and also shortening the replacement time of the prefabricated beam of the bridge.
[0010] Preferably, the translation crane and the lifting crane are respectively located on both sides of the width direction of the bridge.
[0011] Preferably, the translation portion is arranged on the lower side of the main arm, a suspension point rod is provided on the upper side of the end of the main arm away from the main body, and the second hook is used to be connected to the suspension point rod.
[0012] Preferably, the suspension point rod is connected to both ends of the main arm in the width direction and forms a suspension space between the main arm; the second suspension hook is hooked into the suspension space to be connected to the suspension point rod.
[0013] Preferably, the first hook is provided with an anti-hooking device, and the second hook is not provided with an anti-hooking device.
[0014] In this solution, the first hook is equipped with an anti-unhooking device, which can prevent the prefabricated beam from detaching and improve the safety of the prefabricated beam lifting. The second hook is not equipped with an anti-unhooking device, which can facilitate the connection of the second hook with the lifting point rod in the air.
[0015] Preferably, the second hook has a plurality of hook portions, the plurality of hook portions are arranged around an axis of a lifting rope connected to the second hook, and the hook portion of the second hook has a deeper lifting depth than the hook portion of the first hook.
[0016] In this solution, the convenience of the operation of connecting the second hook to the lifting point rod can be improved.
[0017] Preferably, the lifting crane further comprises a base, the lifting part is placed on the base, and the base is used to be placed on the ground.
[0018] Preferably, the lifting crane is a truck crane, and / or the translation crane is a tower crane.
[0019] A beam replacement method, the beam replacement method adopts the beam replacement system of the bridge as described above, and the beam replacement method comprises:
[0020] The lifting part drives the first hook to lift the precast beam;
[0021] The first hook drives the precast beam to move, so that the precast beam moves to the top of the bridge and is located on a side of the main arm away from the main body;
[0022] The lifting part drives the first hook to place the precast beam on the bridge, and after the precast beam is placed on the bridge, the first hook is separated from the precast beam;
[0023] Connecting the second hook to the end of the main arm away from the main body;
[0024] The translation unit moves along the main arm to the position where the prefabricated beam is located, and hoists the prefabricated beam to drive the prefabricated beam to move along the main arm to a predetermined installation position;
[0025] When the prefabricated beam moves to above the predetermined installation position, the translation portion drives the prefabricated beam so that the prefabricated beam is placed at the predetermined installation position.
[0026] In this solution, through the above steps, the prefabricated beam to be installed can be placed at a predetermined installation position.
[0027] Preferably, the beam replacement method further comprises:
[0028] The second hook is connected to the end of the main arm away from the main body;
[0029] The translation portion moves along the main arm toward the upper side of the predetermined disassembly position;
[0030] When the translation part moves to above the predetermined disassembly position, the translation part is connected to the precast beam at the predetermined disassembly position, and drives the precast beam at the predetermined disassembly position to move toward the position where the first hook is located;
[0031] When the precast beam at the predetermined disassembly position moves to the position where the first hook is located, the translation part is separated from the precast beam at the predetermined disassembly position; and the second hook is separated from the main arm.
[0032] The first hook is connected to the precast beam at the predetermined disassembly position, and the lifting part drives the first hook to move so that the precast beam at the predetermined disassembly position leaves the bridge.
[0033] In this solution, through the above steps, the prefabricated beam to be disassembled can be removed from the predetermined disassembly position and leave the bridge.
[0034] The positive and progressive effect of the present invention is that through the coordinated use of the lifting crane and the translation crane, the prefabricated beam can be removed from the bridge or placed on the bridge, thereby completing the replacement of the prefabricated beam of the bridge. In addition, the lifting crane can also support the extended end of the translation crane to improve the ability of the translation crane to lift the prefabricated beam. In addition, the lifting crane and the translation crane can be set on the ground, so as to minimize the occupation of the bridge deck space when the bridge beam is replaced, and also shorten the replacement time of the prefabricated beam of the bridge. BRIEF DESCRIPTION OF THE DRAWINGS
[0035] Figure 1 A structural schematic diagram of a beam replacement system provided by an embodiment of the present invention; wherein a first hook lifts a prefabricated beam;
[0036] Figure 2 A structural schematic diagram of a beam replacement system provided by an embodiment of the present invention; wherein a lifting crane moves prefabricated beams in the air;
[0037] Figure 3 A structural schematic diagram of a beam replacement system provided by an embodiment of the present invention; wherein a lifting crane drops a prefabricated beam onto a bridge;
[0038] Figure 4 A structural schematic diagram of a beam replacement system provided by an embodiment of the present invention; wherein the second hook of the lifting crane hooks the tail end of the main arm of the translation crane, and at the same time prepares for the translation crane to lift the prefabricated beam;
[0039] Figure 5 A structural schematic diagram of a beam replacement system provided by an embodiment of the present invention; wherein a translation crane transports prefabricated beams;
[0040] Figure 6 A structural schematic diagram of a beam replacement system provided by an embodiment of the present invention; wherein a translation crane transports a prefabricated beam to a predetermined installation position to complete the hoisting;
[0041] Figure 7 A schematic structural diagram of a second hook provided in an embodiment of the present invention;
[0042] Figure 8 A schematic diagram of the structure of another second hook provided in an embodiment of the present invention;
[0043] Fig. 9 for Figure 8 The cross-sectional view at 1-1 in the middle;
[0044] Fig.10 for Figure 8 The cross-sectional view at 2-2 in the middle;
[0045] Fig.11 It is a cross-sectional view of the translation crane with a lifting point rod.
[0046] Description of Reference Numerals
[0047] Lifting crane 100 , lifting part 110 , first hook 120 , second hook 130 , hook part 131 , base 140 , translation crane 200 , main body 210 , main arm 220 , translation part 230 , suspension point rod 240 , lifting space 241 , bridge 300 , precast beam 310 , and ground 400 . DETAILED DESCRIPTION
[0048] The present invention is further described below by way of examples, but the present invention is not limited to the scope of the examples.
[0049] The embodiment of the present invention provides a beam replacement system for a bridge 300, such as Figure 1 As shown, the beam replacement system includes a lifting crane 100 and a translation crane 200. The translation crane 200 includes a main body 210, a main arm 220 and a translation part 230. The main body 210 is used to be placed on the ground 400. The main arm 220 extends above the bridge 300, and one end of the main arm 220 is connected to the main body 210. The translation part 230 is arranged on the main arm 220 and can move along the main arm 220. The translation part 230 is used to lift the precast beam 310 of the bridge 300. The lifting crane 100 is used to be placed on the ground 400. The lifting crane 100 includes a lifting part 110, a first hook 120 and a second hook 130. The first hook 120 and the second hook 130 are both arranged on the lifting part 110. The first hook 120 is used to lift the precast beam 310, and the second hook 130 is used to be connected to the end of the main arm 220 away from the main body 210.
[0050] By using the lifting crane 100 and the translation crane 200 in coordination, the precast beam 310 (such as a box beam) can be removed from the bridge 300 or the precast beam 310 can be placed on the bridge 300, thereby replacing the precast beam 310 of the bridge 300. In addition, the lifting crane 100 can also support the extended end of the translation crane 200, thereby improving the ability of the translation crane 200 to lift the precast beam 310. In addition, the lifting crane 100 and the translation crane 200 can be set on the ground 400, thereby minimizing the occupation of the bridge deck space when the bridge 300 is replaced, and also shortening the replacement time of the precast beam 310 of the bridge 300.
[0051] In specific implementation, the lifting crane 100 is mainly used to transport the precast beam 310 from the bottom to the top and place it at a suitable position on the bridge 300. The translation crane 200 can continue to move the precast beam 310 hoisted on the bridge 300 and place it at a preset installation position. Figure 1 As shown, the lifting crane 100 may be a conventional truck crane, and the translation crane 200 may be a conventional tower crane.
[0052] like Figure 1 As shown in FIG. 1 , the translation crane 200 and the lifting crane 100 are respectively located on both sides of the width direction of the bridge 300. Figure 1Taking the position shown as an example, the truck crane can be moved to the left side ground 400 in the width direction of the bridge 300, the tower crane can be a fixed tower crane, the fixed tower crane can be fixedly set on the right bottom surface in the width direction of the bridge 300, or the tower crane can be a movable tower crane, the movable tower crane can be moved to the right bottom surface in the width direction of the bridge 300. And, taking the precast beam 310 extending along the length direction of the bridge 300 as an example, when the precast beam 310 is hoisted by the first hook 120, its length direction can be parallel to the length direction of the bridge 300, and when the precast beam 310 is placed on the bridge 300, it can also be arranged along the length direction of the bridge 300. The main arm 220 of the translation crane 200 extends along the width direction of the bridge 300, so that the translation crane 200 drives the precast beam 310 to move in the width direction of the bridge 300, so that the precast beam 310 can be aligned with the preset installation position.
[0053] like Figure 1 As shown, the translation part 230 is arranged at the lower side of the main arm 220, and a suspension rod 240 is arranged at the upper side of the end of the main arm 220 away from the main body 210, and the second hook 130 is used to connect with the suspension rod 240. Figure 1 Taking the position shown as an example, the suspension point rod 240 is arranged at a position close to the end of the main arm 220. Thus, one end of the main arm 220 is supported by the main body 210, and the other end of the main arm 220 is connected by the second hook 130, and can be subjected to the support force applied by the lifting crane 100. Both ends of the main arm 220 are supported, the support capacity of the main arm 220 is improved, and the stability and accuracy of the movement of the moving part can also be improved.
[0054] like Figure 1 and Fig.11 As shown, the suspension point rod 240 is connected to both ends of the main arm 220 in the width direction, and a suspension space 241 is formed between the main arm 220; the second hook 130 is hooked into the suspension space 241 to be connected to the suspension point rod 240. Fig.11 As shown, the lifting crane 100 is arranged in the width direction of the bridge 300, and the main arm 220 extends in the width direction of the bridge 300. When the lifting point rod 240 adopts the above connection method, the opening of the lifting space 241 is also consistent with the length direction of the main arm 220, so as to facilitate the second hook 130 to be connected thereto.
[0055] And, if Fig.11 As shown, a triangular space is formed between the suspension point rod 240 and the main arm 220, which can provide ample space for the connection operation of the second suspension hook 130, and after the connection, it can be clamped with the top of the suspension space 241 to improve the connection effect. Figure 1 As shown, the suspension point rod 240 is connected to the main arm 220 at multiple locations along the length direction of the main arm 220 . Figure 1The figure shows a structure in which three rods are connected to the main arm 220 respectively. On the one hand, the structure is stable, and on the other hand, the stability of the connection can be improved.
[0056] In a specific implementation, the first hook 120 is provided with an anti-unhooking device, and the second hook 130 is not provided with an anti-unhooking device. The first hook 120 is provided with an anti-unhooking device, which can prevent the prefabricated beam 310 from being separated, and improve the safety of the prefabricated beam 310. The second hook 130 is not provided with an anti-unhooking device, which can facilitate the connection of the second hook 130 with the suspension point rod 240 in the air. Among them, the anti-unhooking device can adopt a conventional anti-unhooking device in the prior art.
[0057] As a feasible implementation method, Figure 7 As shown, the second hook 130 has a hook portion 131. When connected to the main arm 220, the hook portion 131 faces the hoisting space 241.
[0058] As another possible implementation, Figure 8 , Fig. 9 and Fig.10 As shown, the second hook 130 has a plurality of hooks 131, and the plurality of hooks 131 are arranged around the axis of the suspension rope connected to the second hook 130. The convenience of the operation of connecting the second hook 130 with the suspension point rod 240 can be improved.
[0059] like Figure 7 and Figure 8 As shown, the hook portion 131 of the second hook 130 has a deeper hoisting depth than the hook portion 131 of the first hook 120. The hoisting depth refers to the depth of the U-shaped space of the hook portion 131, which is manifested by the hook portion 131 being longer. During hoisting, the contact point between the hook portion 131 and the suspension point rod 240 is farther away from the hook tip of the hook portion 131, so that it is not easy for the suspension point rod 240 to slide out of the hook portion 131 during the hoisting process; in addition, the second hook 130 is not equipped with an anti-unhooking device, so that the hook can freely hook the target suspension point in the air (i.e., the suspension point rod 240 of the tower crane) or release the target suspension point (i.e., the suspension point rod 240 of the tower crane) by only operating the lifting and lowering of the second hook 130 in the air by the truck crane driver.
[0060] like Figure 1 As shown, the lifting crane 100 further includes a base 140 , on which the lifting unit 110 is placed, and the base 140 is used to be placed on the ground 400 . Figure 1 The schematic diagram of the lifting crane 100 being a truck crane is shown, and the base 140 is a movable part. In other embodiments, the base 140 may also be a fixed structure.
[0061] The embodiment of the present invention further provides a beam replacement method, the beam replacement method adopts the beam replacement system of the bridge 300 as described above, and the beam replacement method includes:
[0062] S110: The lifting unit 110 drives the first hook 120 to lift the prefabricated beam 310; Figure 1 As shown, the first hook 120 lifts the precast beam 310 to be installed, and the rope of the lifting part 110 is connected to the first hook 120, which can drive the lifting of the first hook 120. When the lifting crane 100 is a truck crane, the lifting crane 100 can move to a suitable position relative to the bridge 300, and then lift the precast beam 310; or, the lifting crane 100 can also first lift the precast beam 310, and then move it to a suitable position relative to the bridge 300 with the precast beam 310.
[0063] S120: The first hook 120 drives the precast beam 310 to move, so that the precast beam 310 moves to the top of the bridge 300 and is located on the side of the main arm 220 away from the main body 210; Figure 2 As shown, the lifting crane 100 can further drive the precast beam 310 to be moved above the bridge 300 in the air, and is arranged on a side of the bridge 300 close to the lifting crane 100 .
[0064] S130: The lifting unit 110 drives the first hook 120 to place the precast beam 310 on the bridge 300, and after the precast beam 310 is placed on the bridge 300, the first hook 120 is separated from the precast beam 310; Figure 3 , which is a schematic diagram showing a lifting crane 100 placing a precast beam 310 on a bridge 300 , in which the first hook 120 is about to be separated from the precast beam 310 .
[0065] S140: Connect the second hook 130 to the end of the main arm 220 away from the main body 210; Figure 4 As shown, the second hook 130 is connected to the suspension point rod 240 of the main arm 220, and the first hook 120 has been stowed. In addition, this step can be performed after the above step S130 is completed, or it can be performed simultaneously with the above step S130.
[0066] S150: The translation unit 230 moves along the main arm 220 to the location of the prefabricated beam 310, and hoists the prefabricated beam 310 to drive the prefabricated beam 310 to move along the main arm 220 to the predetermined installation location. Figure 4 and Figure 5As shown, the translation part 230 is connected to the main arm 220, and the translation part 230 is connected to the main arm 220, preferably after the above step S140 is completed. However, during the process of connecting the second hook 130 to the main arm 220, the translation part 230 can simultaneously perform preparation work, such as moving toward the precast beam 310 and being located above the precast beam 310, waiting for the second hook 130 to be connected to the main arm 220, and then descending to achieve the connection. After the translation part 230 is connected to the precast beam 310, the translation part 230 can move upward to drive the translation of the precast beam 310.
[0067] S160: When the prefabricated beam 310 moves to the upper part of the predetermined installation position, the translation unit 230 drives the prefabricated beam 310 so that the prefabricated beam 310 is placed at the predetermined installation position. Figure 6 As shown, the translation part 230 drives the prefabricated beam 310 to translate, and when it moves to the predetermined installation position, the translation part 230 can be lowered to place the prefabricated beam 310 at the predetermined installation position.
[0068] Through the above steps, the prefabricated beam 310 to be installed can be placed at a predetermined installation position.
[0069] And, the beam replacement method further comprises:
[0070] S210: The second hook 130 is connected to the end of the main arm 220 away from the main body 210;
[0071] S220: the translation part 230 moves along the main arm 220 toward the upper side of the predetermined disassembly position;
[0072] S230: When the translation part 230 moves to the upper side of the predetermined disassembly position, the translation part 230 is connected to the precast beam 310 at the predetermined disassembly position, and drives the precast beam 310 at the predetermined disassembly position to move toward the position where the first hook 120 is located;
[0073] S240: When the precast beam 310 at the predetermined disassembly position moves to the position where the first hook 120 is located, the translation part 230 is separated from the precast beam 310 at the predetermined disassembly position; and the second hook 130 is separated from the main arm 220.
[0074] S250 : The first hook 120 is connected to the precast beam 310 at the predetermined disassembly position, and the lifting unit 110 drives the first hook 120 to move so that the precast beam 310 at the predetermined disassembly position leaves the bridge 300 .
[0075] Through the above steps, the prefabricated beam 310 to be disassembled can be removed from the predetermined disassembly position and leave the bridge 300 .
[0076] Although the specific embodiments of the present invention are described above, it should be understood by those skilled in the art that this is only for illustration and the protection scope of the present invention is defined by the appended claims. Those skilled in the art may make various changes or modifications to these embodiments without departing from the principles and essence of the present invention, but these changes and modifications all fall within the protection scope of the present invention.
Claims
1. A bridge beam replacement system, characterized in that: The beam changing system includes a lifting crane and a translation crane. The translation crane comprises a main body, a main arm and a translation part, wherein the main body is used to be placed on the ground, the main arm extends above the bridge, and one end of the main arm is connected to the main body; the translation part is arranged on the main arm and can move along the main arm, and the translation part is used to hoist the precast beams of the bridge; The lifting crane is used to be placed on the ground. The lifting crane includes a lifting part, a first hook and a second hook. The first hook and the second hook are both arranged on the lifting part. The first hook is used to lift the prefabricated beam, and the second hook is used to connect with the end of the main arm away from the main body.
2. The bridge beam replacement system according to claim 1, characterized in that: The translation crane and the lifting crane are respectively located on both sides of the width direction of the bridge.
3. The bridge beam replacement system according to claim 1, characterized in that: The translation portion is arranged at the lower side of the main arm, and a suspension point rod is arranged on the upper side of the end of the main arm away from the main body, and the second suspension hook is used to be connected to the suspension point rod.
4. The bridge beam replacement system according to claim 3, characterized in that: The suspension point rod is connected to both ends of the main arm in the width direction, and forms a suspension space between the main arm and the suspension point rod; the second suspension hook is hooked into the suspension space to be connected to the suspension point rod.
5. The bridge beam replacement system according to claim 1, characterized in that: The first hook is provided with an anti-hooking device, while the second hook is not provided with an anti-hooking device.
6. The bridge beam replacement system according to claim 5, characterized in that: The second hook has a plurality of hook portions, which are arranged around an axis where a lifting rope connected to the second hook is located, and the hook portion of the second hook has a deeper lifting depth than the hook portion of the first hook.
7. The bridge beam replacement system according to claim 1, characterized in that: The lifting crane further comprises a base, the lifting part is placed on the base, and the base is used to be placed on the ground.
8. The beam replacement system for a bridge according to any one of claims 1 to 7, characterized in that: The lifting crane is a truck crane, and / or the translation crane is a tower crane.
9. A beam replacement method, characterized in that: The beam replacement method adopts the beam replacement system for a bridge according to any one of claims 1 to 8, and the beam replacement method comprises: The lifting part drives the first hook to lift the precast beam; The first hook drives the precast beam to move, so that the precast beam moves to the top of the bridge and is located on a side of the main arm away from the main body; The lifting part drives the first hook to place the precast beam on the bridge, and after the precast beam is placed on the bridge, the first hook is separated from the precast beam; Connecting the second hook to the end of the main arm away from the main body; The translation unit moves along the main arm to the position where the prefabricated beam is located, and hoists the prefabricated beam to drive the prefabricated beam to move along the main arm to a predetermined installation position; When the prefabricated beam moves to above the predetermined installation position, the translation portion drives the prefabricated beam so that the prefabricated beam is placed at the predetermined installation position.
10. The beam replacement method according to claim 9, characterized in that: The beam replacement method further comprises: The second hook is connected to the end of the main arm away from the main body; The translation portion moves along the main arm toward the upper side of the predetermined disassembly position; When the translation part moves to above the predetermined disassembly position, the translation part is connected to the precast beam at the predetermined disassembly position, and drives the precast beam at the predetermined disassembly position to move toward the position where the first hook is located; When the precast beam at the predetermined disassembly position moves to the position where the first hook is located, the translation part is separated from the precast beam at the predetermined disassembly position; and the second hook is separated from the main arm. The first hook is connected to the precast beam at the predetermined disassembly position, and the lifting part drives the first hook to move so that the precast beam at the predetermined disassembly position leaves the bridge.