Support-free environment-friendly ecological construction method pile construction method and foundation pile structure

By rotating the holes, liquid solidified soil and insertion steel are poured into a hole, combined with prestressed anchor cables, an unsupported environmentally friendly deep foundation pit enclosure system is formed, which solves the problem of difficult demolition of cast piles and achieves rapid, energy-saving and environmentally friendly foundation pit construction and Steel recycling reduces construction costs and carbon emissions.

CN118880913APending Publication Date: 2024-11-01CHINA RAILWAY CONSTRUCTION ENGINEERING GROUP
View PDF 0 Cites 3 Cited by

Patent Information

Application Number
CN202411316949.2
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-20
Publication Date
2024-11-01

AI Technical Summary

Technical Problem

The existing cast-injected pile construction methods are difficult to remove after construction, resulting in soil pollution and obstacles, affecting the redevelopment and utilization of land, and the construction cost is high, making it difficult to achieve safe, economical and green foundation pit support.

Method used

Using rotary digging into holes and filling liquid solidified soil, insert steel, and a closed reinforced concrete crown beam is installed on the top of the pile, combined with prestressed anchor cables to form an unsupported environmentally friendly deep foundation pit enclosure system. The steel can be recycled and reduce carbon emissions and underground pollution.

Benefits of technology

It has achieved rapid, energy-saving and environmentally friendly foundation pit construction, reduced cost and carbon emissions, and recycled steel, avoided underground pollution and obstacles, and did not affect the future development and utilization of the land.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118880913A_ABST
    Figure CN118880913A_ABST
Patent Text Reader

Abstract

The invention discloses a support-free environment-friendly ecological construction method pile construction method and a foundation pile structure, and relates to the field of foundation device protection, and the method comprises the following steps: rotary drilling and hole forming: adopting a rotary drilling rig to drill and excavate at a construction position, and performing jump excavation on the rotary drilling and hole forming every 2-3 piles; liquid solidified soil is poured, specifically, the liquid solidified soil is poured into the rotary digging formed hole; the section steel is inserted, specifically, before insertion, the section steel is derusted under the dry condition, the surface of the section steel is coated with an anti-friction material, and the section steel is inserted before initial setting of the liquid solidified soil so as to improve the anti-pressure ability to the soil; top beam construction: arranging a closed reinforced concrete top beam at the top of the pile, embedding the profile steel into the top beam, and wrapping the profile steel with an antifriction material; the non-support environment-friendly deep foundation pit support system is formed through the ecological construction method piles, the section steel and the pre-stressed anchor cables, the liquid solidification diagram is inserted into the section steel to form the piles after solidification, the soil retaining and bearing capacities are achieved, and the underground water blocking and seepage preventing effects are achieved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the field of protection of foundation devices, and in particular to an unsupported environmentally friendly ecological construction method pile construction method and a foundation pile structure. Background Art

[0003] At present, most of the deep foundation pit support or protection widely adopts the form of cast-in-place piles + concrete support. This type of support has mature construction technology, is safe and reliable, has a long construction period and a relatively high cost. Therefore, as a temporary protection structure, how to ensure the safe, economical, green and efficient construction of foundation pit support has become a difficult problem that each fixed-price EPC (a company is entrusted by the owner to contract the entire process or several stages of the design, procurement, construction, and trial operation of the engineering construction project in accordance with the contract) project needs to solve urgently.

[0004] When cast-in-place piles are used for support, they are usually constructed by pouring, which requires placing a steel cage in the hole dug by rotary drilling and then pouring concrete. Since cast-in-place piles are difficult to remove, they are usually left underground after construction is completed without being removed, leaving pollution and obstacles in the soil, affecting the redevelopment and utilization of the soil. Summary of the invention

[0005] The purpose of the present invention is to provide an unsupported environmentally friendly ecological pile construction method and a pile foundation structure to solve the problems raised in the above-mentioned background technology.

[0006] In order to solve the above technical problems, the present invention provides the following technical solutions: a method for constructing unsupported environmentally friendly ecological piles, comprising the following steps:

[0007] S1. Rotary drilling: Use a rotary drilling rig to drill holes at the construction site, and the holes are drilled every 2-3 piles;

[0008] S2. Pouring liquid solidified soil: Pouring liquid solidified soil into the rotary drilled hole;

[0009] S3. Inserting steel: Before insertion, remove rust from the steel in dry conditions and apply anti-friction material on the surface. Insert the steel before the liquid solidified soil begins to set, so as to improve the compressive strength of the soil.

[0010] S4. Crown beam construction: A closed reinforced concrete crown beam is set on the top of the pile, and the steel embedded in the crown beam is wrapped with anti-friction material;

[0011] S5. Carry out prestressed anchor cable construction in deep drop areas.

[0012] Preferably, the friction-reducing material is foam cloth.

[0013] Preferably, the method further includes removing the steel sections: after the gap between the liquid solidified soil pile and the outer wall of the main structure is backfilled and compacted, the steel sections are removed, and cement slurry is used to promptly fill the gap after the steel sections are removed until the slurry is filled and overflows, and then the grouting is stopped.

[0014] Preferably, the method further comprises hoisting a bottom pile, and before the hole is drilled and the liquid solidified soil is poured, the bottom pile is hoisted into the interior of the hole drilled.

[0015] A pile foundation structure, comprising:

[0016] Liquid solidified soil;

[0017] Bottom pile: the bottom pile is a cylindrical structure located at the bottom of the liquid solidified soil and solidified into an integrated structure with the solidified soil;

[0018] The steel section is inserted into the liquid solidified soil before the liquid solidified soil initially sets, and solidifies with the liquid solidified soil into an integrated structure;

[0019] The cap beam is located at the top of the pile. The steel is embedded in the cap beam to increase the resistance to the lateral pressure of the soil.

[0020] Preferably, it further comprises a pipeline, which is eccentrically arranged on the bottom pile, and the bottom of the pipeline extends into the interior of the bottom pile.

[0021] Preferably, the bottom pile is a structure with an opening at the bottom, and a hoisting part is fixedly installed at the center of the upper end of the bottom pile.

[0022] Preferably, the bottom pile is a structure with two ends open, and the upper end surface of the bottom pile is provided with evenly distributed grooves, and the inner side wall of the groove is fixedly installed with a limit block;

[0023] An upper partition and a lower partition are arranged at the upper end opening of the bottom pile, wherein the upper partition is located above the lower partition and is arranged alternately with the lower partition;

[0024] The upper partition and the lower partition on one side close to the axis of the bottom pile can move upward;

[0025] The bottom of the upper partition and the bottom of the lower partition are fixedly installed with rails, the rails are slidably installed in the grooves, and a stop bar is fixedly installed on one side of the track located at the edge;

[0026] The upper partition and the lower partition are rotatably mounted with columns at the bottom of one side close to the axis of the bottom pile, and the axis of the column coincides with the axis of the bottom pile;

[0027] A hoisting hole is provided at the upper end of the column. During hoisting, under the gravity of the bottom pile, the column slides obliquely upward in the groove with the upper partition and the lower partition until the stop bar contacts the bottom pile.

[0028] Preferably, the bottom of the column extends into the inner cavity of the bottom pile, a support frame is fixedly installed at the middle position of the inner wall of the bottom pile, the bottom of the column passes through the support frame, and a bearing plate is fixedly installed at one end of the support frame;

[0029] When the column slides upward to the top, the carrying plate just contacts with the supporting frame.

[0030] Preferably, the top end of the pipe extends to the top of the pile, and the top end of the pipe is an open structure, an upper cover that can be rotated upward to open is installed on the open structure, and the upper cover covers the open structure of the pipe;

[0031] A liquid level sensor is also fixedly mounted on the inner wall of the pipeline.

[0032] Compared with the prior art, the present invention has the following beneficial effects:

[0033] The present invention uses ecological engineering piles, steel sections, and prestressed anchor cables to form an unsupported, environmentally friendly deep foundation pit retaining system, which is quick to construct and energy-saving and environmentally friendly. By adopting a new type of fluidized soil instead of the concrete pile body, the cost is reduced and carbon emissions are reduced while ensuring safety. The liquid solidification diagram is inserted into the steel section and solidifies to form a pile, which has both soil retaining and bearing capacity and groundwater (pollution) barrier and anti-seepage functions, eliminating the need for water-stop curtain construction between piles, saving construction time and construction costs. After the basement structure is completed, the steel section can be recycled to reduce costs, while leaving no pollution and obstacles underground, and not affecting future land redevelopment. BRIEF DESCRIPTION OF THE DRAWINGS

[0034] Figure 1 This is a structural diagram of Embodiment 1 of the present invention;

[0035] Figure 2 This is a structural diagram of Embodiment 2 of the present invention;

[0036] Figure 3 A structural diagram of a bottom pile in Embodiment 2 of the present invention;

[0037] Figure 4 This is a diagram showing the hoisting state of the bottom pile in Embodiment 2 of the present invention;

[0038] Figure 5 This is a structural diagram of the bottom pile and the partition plate of the present invention when adjusting the position of the hole during rotary drilling;

[0039] Figure 6 Another structural diagram of the bottom pile in Embodiment 2 of the present invention;

[0040] Figure 7 Another structural exploded view of the bottom pile of the present invention;

[0041] Figure 8 This is a structural diagram of the bottom pile and bottom diaphragm of the present invention;

[0042] Fig. 9 A top view of the upper baffle and the lower baffle of the present invention;

[0043] Fig.10 This is a connection diagram of the upper partition and the vertical pole of the present invention;

[0044] Fig.11 This is an exploded view of the connection between the upper partition and the vertical pole of the present invention;

[0045] Fig.12 A top view of the pipeline and the steel section of the present invention;

[0046] Fig.13 For the present invention Figure 6 The enlarged view of point A in the middle;

[0047] Fig.14 A cross-sectional view of another structure of a bottom pile of the present invention;

[0048] Fig.15 This is a working state diagram of the pile structure of the present invention. DETAILED DESCRIPTION

[0049] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0050] Example 1

[0051] See also Figure 1 This embodiment provides a method for constructing an unsupported environmentally friendly ecological pile, comprising the following steps:

[0052] Before construction, it is necessary to locate and lay out the lines, review the coordinates of the pile positions in the field, and confirm the pile position data provided in the design drawings. Only after confirmation can construction operations be carried out.

[0053] Rotary drilling: According to the designed pile position coordinates, a 420-type rotary drilling rig is used for drilling and excavation, with a mechanical power of 399@2100kW / rpm and a maximum torque of 418kN.m. The rotary drilling is performed every 2 to 3 piles.

[0054] Pouring liquid solidified soil: Pouring liquid solidified soil into the rotary-drilled hole. The liquid solidified soil used in this embodiment is premixed fluidized solidified soil.

[0055] Technical requirements for premixed fluidized solidified soil: Use engineering premixing and concrete tanker transportation, and determine whether to use a pump truck based on site conditions; the slump control range for on-site pouring is: 160mm~200mm; test the test block (70.7mm×70.7mm×70.7mm) 7 days after pouring, and the strength shall not be less than 0.8MPa.

[0056] Insert steel: Before the liquid solidified soil is initially set, insert steel 1. The inserted steel adopts Q235B grade H-shaped steel, which is selected according to the current national standard "Hot-rolled H-shaped steel and some T-shaped steel" GB / T11263 and the industry standard "Welded H-shaped steel" YB3301. The steel to be pulled out for recycling should be derusted under dry conditions before insertion, and then anti-friction material should be applied on its surface. After the coating, the steel should be prevented from collision and strong rubbing during transportation. If the anti-friction material falls off or cracks, it should be re-applied in time.

[0057] Welding can be used for steel splicing. There should be no more than 2 joints for a single steel. Since the connection strength at the welded joint is low, the joint position should be avoided in places where the steel is subjected to greater force, such as near the support or excavation surface. The vertical positions of the joints of adjacent steel sections should be staggered with a staggered distance of not less than 1m, so that the steel can disperse the bearing force, improve the compressive capacity of the soil, and avoid the situation where the steel is broken due to excessive soil pressure. The distance between the steel joint and the pit bottom surface should be not less than 2m.

[0058] Crown beam construction: A closed reinforced concrete crown beam is set on the top of the pile. The concrete strength grade of the crown beam is C30, and the thickness of the protective layer is 35mm. The steel embedded in the crown beam is wrapped with foam cloth to reduce the resistance of steel removal in the later stage.

[0059] Construction of prestressed anchor cables in deep drop areas:

[0060] Earth excavation: The working surface for anchor cable construction is determined according to the height of the mechanical equipment. It is generally excavated to a position 1 to 1.3 m below the hole position. This position is convenient for the placement of the anchor cable machinery.

[0061] Anchor hole positioning: After the soil layer on the pile surface is cleaned, the soil between piles is trimmed, and the surface is positioned, the hole position is determined according to the design elevation and horizontal spacing, and it is marked with spray paint. After marking, a circular hole with a diameter of about 150mm is chiseled out of the liquid solidified soil on the surface to facilitate the positioning of the drill bit and drilling into the soil layer. The anchor hole positioning error is less than 50mm, and the hole inclination error is less than ±3 degrees.

[0062] Drilling rig in place: Align the drill rig with the hole position, adjust the angle, and use the drill rig's built-in angle plate to check the drilling angle, so that the hole angle error does not exceed ±3 degrees, and the plane position (horizontal and vertical) error at the hole is ±50mm. The drilling rig should be placed flat and stable to ensure that the equipment will not shake or change position after being subjected to force.

[0063] Drilling and anchor construction: Use carbide high-pressure rotary drill bits, and set multiple nozzles on the flanks of the drill bits for high-pressure rotary drilling. The depth of the anchor hole should not be less than the designed length, nor should it be greater than the designed length of 0.5m. After being filtered in the mixing tank (barrel), the pure cement slurry is introduced into the hollow spiral drill pipe by a high-pressure pump through a high-pressure conduit, and sprayed outward from the bottom drill bit and the flank nozzles. During the spraying process, the surrounding soil is cut synchronously; the drill bit is gradually pushed forward by power until it reaches the designed depth and diameter to form an anchor body.

[0064] Drilling and anchor construction: Use carbide high-pressure rotary drill bits, and set multiple nozzles on the flanks of the drill bits for high-pressure rotary drilling. The depth of the anchor hole should not be less than the designed length, nor should it be greater than the designed length of 0.5m. After being filtered in the mixing tank (barrel), the pure cement slurry is introduced into the hollow spiral drill pipe by a high-pressure pump through a high-pressure conduit, and sprayed outward from the bottom drill bit and the flank nozzles. During the spraying process, the surrounding soil is cut synchronously; the drill bit is gradually pushed forward by power until it reaches the designed depth and diameter to form an anchor body.

[0065] Tensioning and locking of prestressed anchor cables: Tensioning and locking can be carried out only after the jet-sprayed anchor body has been cured for 10 days and the slurry strength reaches 80%. The tendons, waist beams and anchors should be firmly connected. The elongation value of the anchor cable is measured synchronously with a magnetic displacement meter, and the slippage of the prestressed steel strand should be measured after locking. The stabilization time of each level of tensioning must be guaranteed, and a dual-control operation method with tensioning force control as the main method and elongation value verification should be adopted. The tensioning locking value can be the designed locking value. High-pressure oil pumps and through-hole jacks are used for tensioning. The locking force should be monitored after the anchor cable is tensioned, and secondary tensioning must be carried out when the prestress loss is serious.

[0066] Steel removal: When removing H-shaped steel after the gap between the fluidized soil pile and the main structure outer wall is backfilled and compacted, a special clamp and jack are used to pull out and recover the H-shaped steel with the ring beam as the counter beam. After the H-shaped steel is recovered, the gap after the H-shaped steel is removed is promptly filled with cement slurry with a water-cement ratio of 1.0 using 42.5 cement until the slurry is filled and overflows, and then the grouting is stopped.

[0067] The entire recycling process needs to include the following two aspects:

[0068] Use special clamps and jacks to use the concrete ring beam as the anti-beam base to pull out and recover the H-shaped steel.

[0069] Mix cement slurry with a water-cement ratio of 1.0 and allow it to flow by itself to fill the gap after the H-shaped steel is pulled out, reducing the impact on adjacent buildings.

[0070] The piles made by this method are suitable for areas with less rainfall or thicker soil, such as North China, Central China, or the dry season (such as spring or winter) in the middle and lower reaches of the Yangtze River. Because North China (or the middle and lower reaches of the Yangtze River) has less rainfall and lower groundwater levels, there is no need for additional water interception measures or groundwater precipitation measures.

[0071] In this embodiment, liquid solidified soil, steel, crown beam and prestressed anchor cables form the supporting pile structure of the deep foundation pit. Through the ecological engineering pile, steel and prestressed anchor cables, a support-free and environmentally friendly deep foundation pit enclosure system is formed, which is fast in construction, energy-saving and environmentally friendly. By using new fluidized soil instead of concrete pile body, the cost is reduced and carbon emissions are reduced while ensuring safety. At the same time, by combining the pile body with the prestressed anchor cable, the upper support of the pile is eliminated, the basement support removal process and the generation of construction waste are reduced, and the construction progress is accelerated.

[0072] The method piles produced by the present embodiment are suitable for the construction of foundation pit support projects for the first and second floors of basements with short construction periods and strict progress requirements. Since bored cast-in-place piles are not used, steel cages are not required, which saves time in making steel cages, saves time overall, and can shorten the construction period.

[0073] Since the pile structure is formed between the steel and liquid solidified soil inserted in the rotary drilling hole, the overall support capacity is strong, the support force is large, and the strength is high. It can be used for the construction of projects with low total cost, poor geological conditions, narrow working surface, and high basement support requirements. In addition, the pile formed after the liquid solidified steel is inserted into the steel has solidified, which has both soil retaining and bearing capacity, and groundwater (pollution) barrier and anti-seepage function, eliminating the need for the construction of water-stop curtains between piles, saving construction time and construction costs.

[0074] Since liquid solidified soil is used instead of concrete, it is energy-saving and environmentally friendly, and is more suitable for projects with high environmental protection requirements. After the basement structure is completed, the steel can be recycled, reducing costs, while leaving no pollution and obstacles underground, and not affecting future land redevelopment.

[0075] Example 2

[0076] For areas with abundant groundwater or heavy rainfall, such as the southern coastal areas, due to the abundant groundwater and sufficient rainfall, when supporting the piles of the building foundation pit, it is necessary to carry out underground drainage work or set up a water-stop curtain to intercept the groundwater before construction operations can be carried out.

[0077] Therefore, when carrying out construction operations in the above-mentioned areas, before pouring liquid solidified soil after rotary drilling, a bottom pile 2 is hoisted and placed in the rotary drilling hole, such as Figure 2 and Figure 3As shown, the bottom pile 2 is made of reinforced concrete, and is a cylindrical structure with an open bottom and a closed top. The outer diameter of the bottom pile 2 is just the same as the diameter of the rotary-drilled hole (or slightly smaller than the diameter of the hole), which is convenient for placing the bottom pile 2 into the rotary-drilled hole. The top closed part of the bottom pile 2 is a metal plate, which is welded to the steel bar skeleton of the bottom pile 2. A hoisting part is fixedly installed at the center of the upper end of the bottom pile 2. The hoisting part is a rod-shaped structure, and a hoisting hole is opened on the rod-shaped structure. The rod-shaped structure is placed coaxially with the bottom pile 2. During hoisting, the bottom pile 2 can be ensured to be in a vertical state, which is convenient for placing the bottom pile 2 inside the rotary-drilled hole.

[0078] A pipe 10 is also provided on the bottom pile 2. Figure 3 As shown, when the pipe 10 is a hard pipe, such as a metal hard pipe, a PVC hard pipe, etc., the pipe 10 is eccentrically arranged on the bottom pile 2. The pipe 10 is formed by splicing multiple pipes. When the selected pipe is a metal hard pipe, the spliced ​​pipes are connected by welding. When the selected pipe is a PVC hard pipe, the pipes are welded together by hot melt welding. The pipe 10 is in an eccentric state on the bottom pile 2, as shown in FIG. Fig.12 As shown, when the H-shaped steel is inserted, the pipe 10 will not affect the insertion construction of the steel.

[0079] In this embodiment, when the hole is drilled, the bottom depth of the hole must exceed the bottom of the foundation pit downward, and the depth is more than 1m of the foundation pit depth, preferably 1-2m. Before hoisting the bottom pile 2, one end of the first pipe is inserted from the upper end of the bottom pile 2 into the interior of the bottom pile 2, and the contact part between the pipe 10 and the upper end of the bottom pile is sealed. Then the bottom pile 2 can be hoisted and placed in the hole. When the distance between the top of the first pipe 10 and the upper port of the hole is between 1-1.2m, the bottom pile 2 is stopped from being placed downward, so that the bottom pile 2 is suspended in the hole, and the second pipe is connected to the first pipe. After the connection is completed, it can continue to be transported downward. When the distance between the second pipe and the upper port of the hole is between 1-1.2m, the bottom pile 2 is stopped from being placed downward, so that the bottom pile 2 is suspended in the hole, and the third pipe is connected, and so on and so forth until the bottom pile 2 is placed at the bottom of the hole.

[0080] After the placement is completed, liquid solidified soil is poured into the inside of the rotary-drilled hole, and the steel 1 is inserted to cast the cap beam and prestressed anchor cable. The bottom pile 2 supports the liquid solidified soil and the steel inside the rotary-drilled hole. After the bottom pile 2 is placed inside the rotary-drilled hole, the bottom opening of the bottom pile 2 covers the soil at the bottom of the hole and directly contacts the soil, while the liquid solidified soil flows downward along the bottom pile 2 and the side wall of the hole, filling the gap between the bottom pile 2 and the side wall of the hole, so that the bottom pile 2 is placed more stably and firmly.

[0081] After the pile construction is completed, since the bottom pile 2 is located at the bottom of the rotary drilled hole and the bottom pile 2 is a hollow structure, the bottom pile 2 is in direct contact with the soil. The groundwater in the soil will pass through the soil at the bottom of the hole and gather to (or flow to) the inside of the bottom pile 2. The vacuum pump 21 can be connected to the pipeline 10 to perform vacuum dewatering operations to discharge and intercept groundwater, prevent groundwater from gathering in the foundation pit, and facilitate construction operations on the foundation pit.

[0082] In actual construction, since the outer diameter of the bottom pile 2 is almost the same as the diameter of the hole formed by rotary drilling, when the bottom pile 2 is hoisted, the bottom pile 2 is not easy to slide down in the hole. Therefore, in a further embodiment, the outer diameter of the bottom pile 2 is smaller than the diameter of the hole formed by rotary drilling, and the outer diameter of the bottom pile is 0.6-0.8 times the diameter of the hole. Although it is convenient to place the bottom pile 2, due to the large difference between the outer diameter of the bottom pile 2 and the diameter of the hole, after the bottom pile 2 is placed inside the hole, in order to ensure that the pile body has sufficient supporting strength, it is also necessary to try to ensure that the axis of the bottom pile 2 coincides with the axis of the hole.

[0083] Therefore, in a further embodiment, Figure 4 and Figure 5-Figure 7 As shown, the upper end and the bottom of the bottom pile 2 are both opened, and the upper end surface and the bottom end surface of the bottom pile 12 are both provided with evenly distributed grooves 14, and the inner side wall of the groove is fixedly installed with a limit block 15, and the limit block 15 is a cylindrical structure. The upper opening and the bottom opening of the bottom pile 2 are both provided with partitions. The partitions at the upper opening and the partitions at the bottom opening are introduced respectively as follows:

[0084] like Figure 4 As shown, an upper partition 9 is installed at the upper end opening of the bottom pile 2, and the upper partition 9 is a fan-shaped structure. The center of the upper partition 9 coincides with the axis of the bottom pile 2; in this embodiment, there are 3 upper partitions 9, and they are evenly spaced between adjacent ones. A track 18 is fixedly installed at the bottom of the upper partition 9, and the track 18 points to the center of the upper partition 9. The track 18 is installed in the groove 14 and can slide inside the groove 14. The track 18 is a "T"-shaped structure, and a stop bar 181 is fixedly installed at one end of the track 18 located at the edge of the upper partition 9. When the track 18 moves inward to the extreme position, the stop bar 181 just contacts the outer wall of the bottom pile 2 to limit the upper partition 9.

[0085] A partition groove is provided at the bottom opening of the bottom pile 2, and a bottom partition 23 is installed in the partition groove. Figure 8As shown, a groove 14 is provided on the top side wall of the partition groove, and the bottom partition 23 is also a fan-shaped structure. The center of the bottom partition 23 coincides with the axis of the bottom pile 2. There are also three bottom partitions 23, which are arranged vertically opposite to the upper partition 9. A track 18 is fixedly installed on the upper end surface of the bottom partition 23, and the track 18 points to the center of the bottom partition 23. A stop bar 181 is fixedly installed at the edge of the track 18. The connection method of the track 18, the stop bar 181 and the groove 14 at the bottom of the bottom pile 2 can refer to the setting method of the upper partition 9, which will not be repeated here.

[0086] A column 7 is also placed inside the bottom pile 2. Figure 4 and Figure 6 As shown, the column 7 is coaxially arranged with the bottom pile 2, a support frame 6 is fixedly installed at the middle position of the inner wall of the bottom pile 2, the bottom of the column 7 passes through the support frame 6, and a carrying plate 5 is fixedly installed at one end passing through the support frame 6, when the column 7 slides upward to the top, the carrying plate 5 just contacts with the support frame 6, the carrying plate 5 supports and limits the column 7, and when the column 7 moves upward to the extreme position inside the bottom pile 2, it can move upward with the bottom pile 2.

[0087] The bottom end of the column 7 extends downward and is flush with the bottom of the inner cavity of the bottom pile 2. The upper partition 9 and the bottom partition 23 are both rotatably connected to the column 7 at one end located inside the bottom pile 2 (i.e., the inner end hereinafter). Fig.10 and Fig.11 As shown, hinge supports 20 are fixedly installed at the bottom edge of the inner end of the upper partition 9 and the bottom edge of the inner end of the bottom partition 23, and a support seat 19 is fixedly installed on the outer wall of the column 7. The hinge supports 20 and the support seat 19 are rotatably installed together. When the column 7 moves upward, the inner ends of the upper partition 9 and the bottom partition 23 move upward with the column 7. At the same time, the hinge supports 20 rotate on the support seat 19, and the tracks 18 of the upper partition 9 and the bottom partition 23 move in the groove 14 at the same time. When the column 7 moves upward to the extreme position (that is, moves to the top of the bottom pile 2), the outer wall of the bottom pile 2 of the stop bar 181 contacts, and at the same time, the carrier plate 5 contacts the support frame 6, as shown in FIG. Figure 4 Status shown.

[0088] In the present embodiment, it should be noted that since the track 18 will rotate upward along with the partition while sliding in the groove 14, the track 18 will move upward at an angle in the groove 14. Therefore, there must be sufficient space between the track 18 and the top or bottom of the groove 14 so that the track 18 can move normally inside the groove 14.

[0089] The upper end of the column 7 extends out from the inner cavity of the bottom pile 2 to the outside, and a hoisting hole is opened at the top of the column 7.

[0090] In this embodiment, the diameter of the upper partition 9 and the bottom partition 23 is larger than the diameter of the bottom pile 2, and the diameter of the upper partition 9 and the bottom partition 23 must be at least the same as the diameter of the rotary drilled hole. In this embodiment, the diameter of the upper partition 9 and the bottom partition 23 is 1.1-1.2 times the diameter of the rotary drilled hole. When the bottom pile 2 is hoisted, when the column 7 moves upward to the extreme position, the upper partition 9 and the bottom partition 23 are in a state where the center of the circle is relatively high and the edge is low. In this case, the diameter of the circular surface formed by the projection of the vertical plane where the upper partition 9 and the bottom partition 23 are located is larger than the diameter of the bottom pile 2, but smaller than the diameter of the rotary drilled hole, so that the bottom pile 2 can be more directly placed in the bottom of the rotary drilled hole.

[0091] After the bottom pile 2 is placed inside the rotary-drilled hole, before pouring the liquid solidified soil, a steel pipe or steel section with a closed bottom needs to be inserted into the hole and pressed on the column 7. Under the gravity of the steel pipe or steel section, the column 7 will be pressed downward, and the column 7 will move downward with the higher ends of the upper partition 9 and the bottom partition 23, and the edges of the upper partition 9 and the bottom partition 23 will contact the inner wall of the hole. Until under the action of pressure, the edges of the upper partition 9 and the bottom partition 23 are inserted into the soil of the side wall of the hole and remain in a horizontal state, and at the same time, the inner ends of the upper partition 9 and the bottom partition 23 are attached to the side wall of the column 7.

[0092] The adjustment process of the axis of the bottom pile 2 and the axis of the hole is as follows: after the bottom pile 2 is placed in the hole, once the bottom pile is in an eccentric state, such as Figure 5 As shown, when the column 7 moves downward with the upper partition 9 and the bottom partition 23, since all the upper partitions 9 and the bottom partitions 23 move synchronously under the drive of the column 7, the upper partitions 9 and the bottom partitions 23 will first contact the most adjacent hole side wall, and the hole side wall will form an obstacle to the upper partition 9 and the bottom partition 23. As the column 7 continues to move downward, the bottom pile 2 will move toward the axial direction of the hole, as shown in FIG. Figure 5 As shown by the dotted arrows. When all the edges of the upper partitions 9 and the bottom partitions 23 are in contact with the inner wall of the hole, the axis of the bottom pile 2 coincides with the axis of the hole or the axis of the bottom pile 2 is at the position closest to the axis of the hole, so that the axis of the bottom pile 2 and the axis of the hole are adjusted and the axes of the two coincide as much as possible. After the liquid solidified soil is filled, the support force and support strength of the bottom pile 2 on the solidified soil are guaranteed.

[0093] After the axis of the bottom pile 2 and the axis of the hole are adjusted, the steel pipe or the pile can be hit downward, so that the upper partition 9 and the bottom partition 23 continue to move on the bottom pile 2 to a horizontal state, and the edges of the upper partition 9 and the bottom partition 23 will be inserted into the side wall of the hole, thereby improving the firmness between the bottom pile 2 and the hole, and at the same time, it can also improve the supporting force of the bottom pile 2.

[0094] Since the upper partition 9 and the bottom partition 23 are respectively arranged at the top and the bottom of the bottom pile 2, and the movement states of the two are consistent, when the position of the bottom pile 2 is adjusted, the upper end and the bottom of the bottom pile 2 will move synchronously, making the bottom pile 2 more stable during adjustment. In addition, since a partition groove is provided at the bottom of the bottom pile 2, in order to prevent the bottom of the bottom pile 2 from being inserted into the soil at the bottom of the hole when the bottom pile 2 is under pressure, the height of the partition groove is less than the thickness of the bottom partition 23, ensuring that when the bottom pile 2 is placed at the bottom of the hole, the bottom partition 23 contacts the bottom of the hole, while the bottom pile 2 does not contact the bottom of the hole, and the bottom pile 2 can be prevented from being inserted into the soil at the bottom of the hole when under pressure.

[0095] Theoretically, the more upper baffles 9 and bottom baffles 23 are provided, the higher the accuracy of adjusting the position between the axis of the bottom pile 2 and the axis of the hole will be.

[0096] The upper partition plate 9 is provided with an installation opening for installing the pipe 10. The pipe 10 is made of a PVC hard pipe. The PVC hard pipe has a certain toughness and can be bent and deformed. Figure 4 As shown, when the bottom pile 2 is hoisted, the pipe 10 will bend and deform to a certain extent, which will not affect the hoisting work of the bottom pile 2.

[0097] After the bottom pile 2 is placed, a circular partition can be placed in the hole. The circular partition separates the inner cavity of the bottom pile 2 from the upper control price of the hole. A reserved hole for placing the pipe 10 and the column 7 needs to be opened on the circular partition. The pipe 10 extends upward to the ground. When placing the circular partition, the pipe 10 can be inserted into the reserved hole of the pipe. The pipe 10 can initially limit the circular partition. The circular partition 10 can fall along the pipe 10 in the rotary drilled hole, so that the circular partition moves downward more smoothly.

[0098] The partition is placed in the hole and fits together with the upper partition 9 of the bottom pile 2, and then the liquid solidified soil can be poured into the hole and the steel can be inserted. Since the column 7 extends upward, the poured liquid solidified soil can be connected with the bottom pile 2 after solidification.

[0099] In this embodiment, a plurality of water-permeable holes are provided on the inner wall of the bottom pile 2, and due to the distance between adjacent bottom partitions 23, after the pile body is constructed and formed, the interior of the bottom pile 2 remains in a hollow state, and excess water in the soil can enter the bottom pile 2. The vacuum pump can be connected to the pipeline 10 to perform vacuum dewatering operations to discharge and intercept groundwater, thereby preventing groundwater from gathering in the foundation pit and facilitating the construction operations of the foundation pit.

[0100] Example 3

[0101] The difference from Example 2 is that the applicant discovered through subsequent design that after the lower partition 11 is arranged at the bottom of the upper partition 9, the circular partition can be removed, thereby eliminating the construction operation of placing the circular partition.

[0102] The arrangement of the lower partition 11 is as follows: Figure 6 , Figure 7 , Fig. 9 and Fig.14 As shown, the lower partition 11 is staggered with the upper partition 9, and the bottom of the lower partition 11 is fixedly installed with a track 18 and a stop bar 181. The arrangement of the lower partition 11 is the same as that of the upper partition 9, and no further description is given here. It should be noted that the edge of the upper partition 9 is pressed on the upper part of the lower partition 11, and the diameters of the two are the same, as shown in FIG. Fig. 9 When the column 7 moves upward, the column 7 can move the upper partition 9 and the lower partition 11 upward synchronously.

[0103] In this embodiment, a pressure ring 16 is fixedly installed on the upper part of the column 7, and a protrusion is fixedly installed on the bottom of the pressure ring 16. When the upper partition 9 and the lower partition 11 are in a horizontal state, the pressure ring 16 remains in contact with the upper partition 9, and the protrusion contacts the lower partition 11 and remains in contact with it. At the same time, the upper partition 9 and the lower partition 11 are also in contact with each other to close the top of the bottom pile 2.

[0104] In this embodiment, the function of the lower partition 11 is: when the position of the bottom pile 2 inside the hole is adjusted, the lower partition 11 is set on the top of the bottom pile 2, can move with the upper partition 9, and act on the side wall of the hole to adjust the position of the bottom pile 2.

[0105] At the same time, when the lower partition 11 and the upper partition 9 are in a horizontal position, the bottom pile 2 can be isolated from other spaces of the hole. After the bottom pile 2 is installed, liquid solidified soil can be directly poured. Since the side wall of the bottom pile 2 is provided with a water-permeable hole, the lower partition 11 and the upper partition 9 can be inserted into the soil of the side wall of the hole when they are in a horizontal position, completely isolating the bottom pile 2 from the liquid solidified soil, and avoiding the problem of clogging of the water-permeable hole caused by the liquid solidified soil flowing downward from the bottom pile 2 and the side wall of the hole.

[0106] In addition, since the bottom edges of the upper partition 9, the lower partition 11 and the bottom partition 23 are all rotatably connected to the column 7, when the upper partition 9, the lower partition 11 and the bottom partition 23 are kept in a horizontal state, the inner side ends of the upper partition 9, the lower partition 11 and the bottom partition 23 will generate a clamping force on the column 7. Therefore, in this embodiment, the column 7 is designed as a solid structure to ensure that the column 7 can withstand sufficient clamping force. Moreover, the greater the force the column 7 withstands, the greater the amount of deformation of the downward movement, and accordingly, the greater the clamping force generated by the upper partition 9, the lower partition 11 and the bottom partition 23 on the column 7. The reaction force generated by the column 7 on the upper partition 9, the lower partition 11 and the bottom partition 23 will keep the upper partition 9, the lower partition 11 and the bottom partition 23 in a horizontal state and plug together with the side wall of the hole, which can ensure the stability of the connection. Of course, after the construction of the supporting piles is completed, the soil is backfilled and the steel sections are removed, the pipes 10 of the bottom piles 2 are not removed.

[0107] After the basement structure is completed, the pile body serves as the outermost protection of the basement structure, and the reserved bottom pile 2 can also serve as a structure to avoid or prevent moisture in the basement, and can also reduce the water pressure in the basement. The pipeline 10 continues to be connected to the external vacuum pump to extract groundwater, lower the groundwater level, and avoid moisture in the basement caused by excessively high groundwater levels. When draining groundwater, an intermittent drainage method can be used according to actual conditions.

[0108] In this embodiment, the main structure of the pile body uses liquid solidified soil to replace concrete. After the basement structure is completed, the steel sections can be recycled, which reduces costs and leaves no pollution or obstacles underground, and does not affect future land redevelopment.

[0109] Example 4

[0110] When using pipes and vacuum pumps to lower the groundwater level, it is still necessary to manually carry out precipitation work according to the actual situation, which undoubtedly increases the intensity of the work. If precipitation is not timely, the basement will become damp, and when the groundwater level is too high, it will cause the basement to float. Although anti-floating design is always carried out when designing the basement, in areas with heavy rainfall, once the groundwater level is too high and exceeds the design standard, the basement will float, causing problems such as bulging and cracking of the basement floor, damage to beam-column joints, and shear damage to wall columns.

[0111] In the embodiment, the top of the pipe 10 extends to the top of the pile and extends out of the pile body. The top of the pipe 10 is an opening mechanism, and an upper cover 13 is rotatably installed at the edge of the opening structure. Fig.13As shown, the upper cover 13 can be rotated upward to open, and when the upper cover 13 is not subjected to external force, under the action of its own weight, the upper cover 13 covers the opening structure of the pipeline 10. A liquid level sensor 22 is also fixedly installed inside the pipeline 10. Since the pipeline 10 is welded together in sections, the sensor 22 can be fixed inside the single-section pipeline 10.

[0112] Since basements are usually buried in the soil, they are usually not completely submerged by water. The buoyancy they bear is related to the height of the groundwater. The higher the groundwater, the greater the buoyancy the basement will bear:

[0113] The height of the liquid level sensor 22 is determined as follows: when designing the basement, the maximum buoyancy that the basement can withstand is known, and is assumed to be F1;

[0114] The bottom area of ​​the basement can be directly obtained from the design dimensions, assuming it is S;

[0115] The water level height at maximum buoyancy is h, that is, the placement height of the liquid level sensor 22 is h. When the groundwater level is lower than the plane of the bottom of the basement, the basement is not affected by buoyancy. Only when the groundwater is higher than the bottom of the basement will the basement receive buoyancy. Therefore, the placement height of the liquid level sensor 22 is h, with the outer bottom of the basement as the benchmark or reference point.

[0116] According to the buoyancy formula: :

[0117] Where: is the density of water;

[0118] Acceleration due to gravity;

[0119] The water level h when the basement is subjected to the maximum buoyancy (that is, the placement height of the liquid level sensor) can be calculated as: .

[0120] In this embodiment, since the top of the pipeline 10 is an open structure, the pipeline 10 is always connected to the outside atmosphere, and the groundwater is also connected to the outside atmosphere. The structure composed of the pipeline 10 and the bottom pile 2 forms a communicating vessel with the groundwater, which can be used to monitor the water level of the groundwater.

[0121] like Fig.15As shown, when the water level rises to the position of the liquid level sensor 22, the liquid level sensor 22 will detect the water and display it on the corresponding display screen or display meter, and the staff can perform precipitation work according to the display of the liquid level sensor 22. When precipitation occurs, it is only necessary to turn on the vacuum pump 21 to perform vacuum precipitation work. When the vacuum pump 21 is working, negative pressure is generated, and the air inside the pipe 10 is first extracted, and then the groundwater is extracted under the suction of the negative pressure, and the underground precipitation work is performed to lower the groundwater level in the basement, and reduce the buoyancy or groundwater pressure on the basement.

[0122] When the vacuum pump 21 is working, negative pressure is generated inside the pipeline 10 . Under the effect of the negative pressure suction, the upper cover 13 will fit tightly against the top of the pipeline 10 to seal the top of the pipeline 10 .

[0123] After the vacuum pump 21 has been working for a period of time, the groundwater level in the basement drops. At this time, the bottom pile 2, the pipeline 10 and the vacuum pump 21 play a role in intercepting water, preventing the groundwater from flowing to the lower water level in the basement, thereby reducing the water pressure or buoyancy of the basement.

[0124] After the groundwater is removed, the vacuum pump stops working, and outside air enters the vacuum pump and the pipeline 10. The pressure inside the pipeline 10 is the same as the outside atmospheric pressure. The negative pressure of the pipeline 10 disappears, and the suction force on the upper cover 13 also disappears.

[0125] In a further embodiment, a valve is installed at the water inlet of the vacuum pump 21. When the precipitation operation is not performed, the valve is in a closed state. When the water is pumped, the valve can be opened manually. The pipeline 10 is connected to the outside atmosphere through the upper cover 13, which can ensure that the water inside the pipeline 10 can be kept flush with the groundwater level.

[0126] Example 5

[0127] Since the bottom pile 2 is arranged at the bottom of the pile body, and the bottom pile 2 is used to reduce groundwater, the foundation pile structure in this embodiment can also be placed on the bank of a stream or river or on the coast, river bank, or lake bank. When the pile body structure is constructed on the bank, firstly, a hole is drilled, then the bottom pile 2 is hoisted, and then liquid solidified soil is poured, steel is inserted, and the crown beam is constructed, and whether the anchor cable is needed is determined according to the actual use needs.

[0128] When constructing on the coast, river bank, or lake bank, water will wash away the soil, and the soil will expand in volume after absorbing water. Especially for clay soil or expansive soil, the bearing capacity will be weakened after absorbing water, and the adhesion between the soil will decrease, resulting in peeling, landslides, etc.

[0129] After the pile structure is supported on the water bank in the above-mentioned areas, the river water can be reduced from soaking the soil and reducing the possibility of soil absorbing water. Especially in the rainy season, when the rain is heavy, the water in the river will rise. After the water level rises, more river banks will be soaked in water. After the soil absorbs water and expands, it is more likely to collapse.

[0130] In the present application, after the foundation piles are supported in the soil on the shore, the solidified liquid solidified soil is prevented from being located between the river and the soil on the shore, and an isolation zone is formed between the river and the shore soil, thereby avoiding direct contact between water and shore soil.

[0131] Although the isolation zone can block the direct contact between the river water and the shore soil, the shore soil will also absorb water and expand due to the communication between the groundwater and the river water (the principle of communicating vessels). After absorbing water, the volume of the soil will increase and expand outward, acting on the solidified liquid solidified soil, and the pressure on the solidified liquid solidified soil will increase. Therefore, in this embodiment, the above problems can be reduced or avoided by the bottom pile 2. The bottom pile 2 is located between the soil and the river, forming an interception barrier. When the river water increases or soaks the soil, the vacuum pump 21 can be used to extract the water inside the bottom pile 2. The water that penetrates into the soil from the river will enter the inside of the bottom pile 2 under the interception effect of the bottom pile 2 and be pumped out by the vacuum pump 21, thereby reducing the water in the river from penetrating into the soil, reducing the possibility of the shore soil absorbing water, thereby reducing the expansion of the shore soil, and further reducing the pressure on the foundation pile caused by the soil expansion.

[0132] While embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the invention, and that the scope of the invention is defined by the appended claims and their equivalents.

Claims

1. A method for constructing unsupported environmentally friendly ecological piles, characterized in that: The steps include: S1. Rotary drilling: Use a rotary drilling rig to drill holes at the construction site, and the holes are drilled every 2-3 piles; S2. Pouring liquid solidified soil: Pouring liquid solidified soil into the rotary drilled hole; S3. Inserting steel: Before insertion, rust the steel (1) under dry conditions, apply anti-friction material on the surface, and insert the steel (1) before the initial setting of the liquid solidified soil to improve the compressive strength of the soil; S4. Crown beam construction: a closed reinforced concrete crown beam is set at the top of the pile, and the steel section (1) is embedded in the crown beam and wrapped with anti-friction material (4); S5. Carry out prestressed anchor cable construction in deep drop areas.

2. The method for constructing unsupported environmentally friendly ecological piles according to claim 1, characterized in that: The anti-friction material (4) is foam cloth.

3. The method for constructing unsupported environmentally friendly ecological piles according to claim 2, characterized in that: It also includes the removal of steel sections: the gap between the liquid solidified soil piles and the outer wall of the main structure is backfilled and compacted before the steel sections are removed, and cement slurry is used to promptly fill the gap after the steel sections are removed until the slurry is filled and overflows, then the grouting is stopped.

4. The method for constructing unsupported environmentally friendly ecological piles according to claim 3 is characterized by: The method also includes hoisting a bottom pile (2), wherein before the hole is drilled and the liquid solidified soil is poured, the bottom pile (2) is hoisted inside the hole drilled.

5. A pile foundation structure, characterized in that: include: Liquid solidified soil; A bottom pile (2), the bottom pile (2) is a cylindrical structure, located at the bottom of the liquid solidified soil, and solidified with the solidified soil to form an integrated structure; The steel section (1) is inserted into the liquid solidified soil before the liquid solidified soil initially solidifies, and solidifies with the liquid solidified soil to form an integrated structure; A crown beam (3) is located at the top of the pile, and a steel section is embedded in the crown beam (3) to increase the resistance to the lateral pressure of the soil.

6. A pile foundation structure according to claim 5, characterized in that: It also includes a pipeline (10), which is eccentrically arranged on the bottom pile (2), and the bottom of the pipeline (10) extends into the interior of the bottom pile (2).

7. A pile foundation structure according to claim 6, characterized in that: The bottom pile (2) is a structure with an opening at the bottom, and a hoisting part is fixedly mounted at the center of the upper end of the bottom pile (2).

8. A pile foundation structure according to claim 6, characterized in that: The bottom pile (2) is a structure with two ends open, the upper end surface of the bottom pile (2) is provided with evenly distributed grooves (14), and the inner side walls of the grooves (14) are fixedly mounted with limit blocks (15); An upper baffle (9) and a lower baffle (11) are provided at the upper opening of the bottom pile (2), wherein the upper baffle (9) is located above the lower baffle (11) and is arranged in an alternating manner with the lower baffle (11); The upper partition plate (9) and the lower partition plate (11) are both able to move upwards on the side close to the axis of the bottom pile (2); A track (18) is fixedly mounted on the bottom of each of the upper partition (9) and the lower partition (11); the track (18) is slidably mounted in the groove (14); and a stop bar (181) is fixedly mounted on one side of the track (18) located at the edge; A column (7) is rotatably mounted on the bottom of the upper partition (9) and the lower partition (11) near the axis of the bottom pile (2), and the axis of the column (7) coincides with the axis of the bottom pile (2); A hoisting hole is provided at the upper end of the column (7). During hoisting, under the gravity of the bottom pile (2), the column (7) slides obliquely upward in the groove (14) with the upper partition (9) and the lower partition (11) until the stop bar (181) contacts the bottom pile (2).

9. A pile foundation structure according to claim 8, characterized in that: The bottom of the column (7) extends into the inner cavity of the bottom pile (2), a support frame (6) is fixedly installed at the middle position of the inner wall of the bottom pile (2), the bottom of the column (7) passes through the support frame (6), and a bearing plate (5) is fixedly installed at one end passing through the support frame (6); When the upright post (7) slides upward to the top, the bearing plate (5) just contacts the support frame (6).

10. A pile foundation structure according to claim 8 or 9, characterized in that: The top end of the pipe (10) extends to the top of the pile, and the top end of the pipe (10) is an open structure, on which an upper cover (13) capable of being rotated upward to open is installed, and the upper cover (13) covers the opening structure of the pipe (10); A liquid level sensor (22) is also fixedly mounted on the inner wall of the pipeline (10).

Citation Information

Cited By

  • Premixed flow state solidification geotechnical method pile construction method and construction method pile

    CN121272895A

  • Long spiral drilling device for occluded cast-in-place pile and construction method

    CN121897254A

  • Bite perfusion pile long auger drilling device and construction method

    CN121897254B