Soft and hard rock complex stratum foundation pit supporting structure and construction method thereof
By using the combination technology of support barrels, anchor rods and force components in the complex formation of soft and hard rocks, the problem of cylindrical piles being subjected to a large force in soft and hard rocks is solved, and the stability improvement and construction of cylindrical piles are achieved. Improved efficiency.
Patent Information
- Application Number
- CN202411077272.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-07
- Publication Date
- 2024-11-01
AI Technical Summary
In the complex formation of soft and hard rocks, the cylindrical piles are subjected to a high force when they penetrate the soft rock deformation section, which threatens the overall stability of the building and is difficult to effectively support the existing technology, resulting in the support structure and the side walls of the foundation pit. Unable to level the connection, which is time-consuming and labor-intensive.
The inner and outer parts of the support cartridge are poured in sequence to form an integral support, and a first anchor rod and a component component are provided on the soft rock surface. The stress concentration is reduced through the anchoring and component components, and the stability and connectivity of the support structure are improved.
The overall and local support of cylindrical piles is achieved, stress failure is reduced, the stability of the building and the support capacity of the support structure are improved, and construction time and cost are reduced.
Smart Images

Figure CN118880914A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of foundation building construction, and in particular to a foundation pit support structure with complex soft and hard rock strata and a construction method thereof. Background Art
[0002] During building construction, in order to improve the firmness and earthquake resistance of the foundation, several concrete piles are usually driven into the foundation, thereby setting a large number of columnar piles under the building, which can improve the firmness of the building to a certain extent.
[0003] With the large-scale construction of buildings, construction projects inevitably face high-stress soft rock areas. When the columnar piles pass through the soft rock deformation section, that is, there are strong weathering layers or soft rock layers in the complex soft and hard rock strata, the columnar pile foundation is subjected to excessive stress overall or locally, thus threatening the overall stability of the building project.
[0004] Therefore, there is an urgent need for a building structure that can be applied to complex strata and form overall and local support. Summary of the invention
[0005] The present invention aims to solve the deficiencies of the prior art and to provide a foundation pit support structure in soft and hard rock complex strata and a construction method thereof. By adopting this scheme, not only can the columnar piles be supported as a whole by sequentially pouring the inside and outside of the support tube, but also the columnar piles can be partially supported at the soft rock surface to improve stability.
[0006] The present invention is achieved through the following technical solutions:
[0007] A foundation pit support structure in soft and hard rock complex strata, comprising:
[0008] A support tube, the outer diameter of which matches the inner diameter of the foundation pit, and the support tube is coaxially sleeved on the columnar pile;
[0009] The support tube comprises an inner steel cage and an outer steel cage which are coaxially arranged in sequence from the inside to the outside, the inner steel cage and the outer steel cage are connected by straight bars, a gap is left between the outer steel cage and the inner side wall of the foundation pit, and the lower end of the inner steel cage extends out of the outer steel cage;
[0010] It also includes a first anchor rod, which is used to pass through the side wall of the supporting tube and the soft rock surface on the local inner wall of the foundation pit and extend into the soft rock area, and the extending end of the first anchor rod sequentially extends from the soft rock area into the hard rock area and is anchored in the hard rock area;
[0011] The first anchor rod is arranged horizontally or inclined upward.
[0012] Compared with the prior art, with the large-scale construction of buildings, construction projects inevitably face high-stress soft rock areas. When the columnar piles pass through the soft rock deformation section, that is, there are strongly weathered layers or soft rock layers in the medium-weathered rock layers, which causes the overall or local stress on the columnar pile foundation to be too large, thereby threatening the overall stability of the building project. The present invention provides a foundation pit support structure for complex soft and hard rock strata. By adopting this scheme, not only can the columnar piles be supported as a whole by sequentially pouring the inside and outside of the support tube, but also the columnar piles can be partially supported at the soft rock surface to improve stability. In the specific scheme, a support tube is included for supporting the foundation pit and protecting the columnar piles. In this way, not only can the columnar piles be protected and the stress damage caused by external conditions be reduced, but the columnar piles can also be reused or quickly replaced.
[0013] In addition, in the prior art, the supporting structure or columnar piles are generally directly inserted into the foundation pit, which results in the inability to smoothly connect the supporting structure or columnar piles with the side wall of the foundation pit, and it takes time and effort to trim the side wall of the foundation pit into a plane. Therefore, the interior of the supporting tube in the present invention includes an inner steel cage and an outer steel cage coaxially arranged from the inside to the outside, and the inner steel cage and the outer steel cage are connected and fixed by a plurality of straight bars. After the inner and outer steel cages are lowered, steel drill concrete can be sprayed on the inner steel cage to form an inner template on the inner steel cage, wherein the inner steel cage is woven by a spiral steel cage, a plurality of vertical bars and a steel mesh, and is used To form a dense network of steel bars, reduce the size of the holes, and quickly form the inner formwork; because the lower end of the inner steel cage extends out of the outer steel cage, the inner steel cage can be inserted into the bottom of the foundation pit to form a bottom seal, so that a casting space is formed between the inner formwork and the inner wall of the foundation pit. At this time, the outer steel cage is located in the casting space, and by pouring concrete in the casting space, the solidified concrete after pouring can be seamlessly connected with the inner wall of the foundation pit, so that the support structure and the inner wall of the foundation pit can form a whole, strengthen the support of the hard rock and soil layer to the support structure and the column piles, so as to improve the support capacity of the support structure to the column piles as a whole.
[0014] Secondly, since there is soft rock at a local position on the inner wall of the foundation pit, when the soft rock is horizontal or tilted upward away from the foundation pit, the soft rock layer at this location has a large stress and squeezes the side wall of the support tube, which will produce a large local soil pressure on the support tube, thereby causing stress damage to the support tube locally and even reducing the stability of the support tube. Therefore, the first anchor rod can be set for anchoring. The first anchor rod passes through the support tube and the soft rock area from the inner wall of the support tube in turn, and is anchored in the hard rock area. In this way, through the fixation of the hard rock area, the first anchor rod is tension-anchored at the stress position of the support tube, thereby reducing the stress damage at the stress position. Among them, the direction of the first anchor rod needs to be set along the direction of the initial end of the soft rock area. When this direction cannot be anchored to the hard rock area, the direction of the drilling can be adjusted in the circumferential direction until it can be anchored to the hard rock area.
[0015] Furthermore, in order to reduce the earth pressure of the soft rock area on the supporting tube and reduce stress concentration, a force component is also included, and the force component includes a frame, and the frame is located at the position of the soft rock surface and is perpendicular to the main stress direction of the soft rock surface;
[0016] The frame has a plurality of force distribution areas, each of the force distribution areas has a plurality of thin plates, the plurality of thin plates are arranged at intervals, and the arrangement directions of the thin plates and the frame form an angle with each other;
[0017] In the same force component area, a plurality of thin plates are parallel to each other; between different force component areas, the arrangement directions of the thin plates are different;
[0018] Several second anchor rods are arranged in sequence along the circumferential direction of the frame, and the protruding ends of the second anchor rods penetrate into the hard rock area and are anchored, and the second anchor rods are fixedly connected to the frame. In this scheme, a small amount of excavation can be carried out at the initial end of the soft rock area, that is, the soft rock surface, to determine the direction of the initial end of the soft rock area, and the main stress direction of the soft rock area on the support tube can be roughly determined. At this time, a force component can be set at the excavation surface. The force component includes a frame, several thin plates and several second anchor rods. Several second anchor rods can be used to anchor the frame at the excavation surface, and several thin plates are inserted into the soft rock area and arranged in different directions. In this way, when the soft rock part is loosened and moves and squeezes in the direction of the support tube, it can move toward the force component areas in different directions respectively, so as to divert the main stress and reduce stress concentration.
[0019] In order to ensure that the thin plate has a sufficient length and can provide a sufficiently long diversion length, the inner side of the thin plate extends out of the frame and into the soft rock area.
[0020] To achieve overall protection, the size of the frame is adapted to the circumferential size of the soft rock area, wherein the shape of the frame can be circular, square, etc., as long as it can adapt to the circumferential size of the excavation surface.
[0021] Since the first anchor rod needs to be arranged at or close to the center of the soft rock surface, in order to facilitate providing a position for the first anchor rod to pass through, a sleeve is provided at the center of the frame, and the sleeve is used for the first anchor rod to pass through.
[0022] As a fixed connection method, the second anchor rod and the frame are welded.
[0023] In order to improve the structural strength continuity of the local position of the support tube, a number of spiral steel bars are also arranged in the support tube at the soft rock surface of the local inner wall of the foundation pit. The two ends of the spiral steel bars are respectively welded to the inner steel cage and the outer steel cage, and the spiral steel bars are arranged toward the main pressure direction of the soft rock area on the outer wall of the support tube. In this solution, the direction of the spiral bars is the main pressure direction of the soft rock area on the outer wall of the support tube, that is, the local soft rock area is resisted by the continuous strength of the spiral bars themselves.
[0024] Further solutions:
[0025] The present invention also provides a construction method for a foundation pit support structure in a soft and hard rock complex stratum, comprising the following steps:
[0026] S1: excavating a foundation pit and forming steps at the bottom of the foundation pit;
[0027] S2: Detecting a soft rock surface on the inner wall of the foundation pit and installing a force component on the soft rock surface;
[0028] S3: Then, lowering the inner steel cage and the outer steel cage into the foundation pit, so that the lower end of the inner steel cage is inserted into the step;
[0029] S4: concrete is then sprayed on the inner reinforcement cage to form the inner formwork;
[0030] S5: pouring concrete in the space between the inner membrane plate and the inner wall of the foundation pit to complete the integral casting of the support tube;
[0031] S6: Then, a hole is drilled from the inner side of the support tube to the soft rock area at the soft rock surface, and the first anchor is installed;
[0032] S7: Finally, insert the columnar piles into the support tube to complete the construction.
[0033] 9. The construction method of a foundation pit support structure in a soft and hard rock complex stratum according to claim 8, characterized in that step S2 further comprises the following specific steps:
[0034] S21: after detecting the soft rock surface, excavating into the soft rock area along the circumferential direction of the soft rock surface, and stopping the excavation when the initial direction of the soft rock area is sufficiently determined;
[0035] S22: trimming the excavation surface to an installation surface perpendicular to the initial direction;
[0036] S23: installing a plurality of second anchor rods in sequence along the circumferential direction of the installation surface, so that the extending ends of the second anchor rods penetrate into the hard rock area for anchoring;
[0037] S24: subsequently splicing the frames in sequence along the circumferential direction of the installation surface, and welding and fixing the frames and the ends of the plurality of second anchor rods;
[0038] S25: inserting a plurality of thin plates on the mounting surface in sequence inside the frame, and dividing the plurality of thin plates into a plurality of force component areas;
[0039] S26: Finally, the two ends of the plurality of thin plates are welded to the inner wall of the frame respectively to complete the installation of the force distribution assembly.
[0040] Furthermore, when a plurality of thin plates are sequentially inserted into the installation surface, a cutting device is required to cut a gap on the installation surface for inserting the thin plates.
[0041] Compared with the prior art, the present invention has the following advantages and beneficial effects:
[0042] 1. The present invention provides a foundation pit support structure for complex soft and hard rock strata and a construction method thereof. According to the present invention, steel bar concrete is sprayed on an inner steel cage to form an inner template on the inner steel cage, so that a casting space is formed between the inner template and the inner wall of the foundation pit. At this time, the outer steel cage is located in the casting space. By casting concrete in the casting space, the solidified concrete after casting can be seamlessly connected to the inner wall of the foundation pit, so that the support tube and the inner wall of the foundation pit can form a whole, strengthen the support of the hard rock and soil layer to the support structure and the column piles, so as to improve the support capacity of the support structure to the column pile as a whole.
[0043] 2. The present invention provides a foundation pit support structure for soft and hard rock complex strata and a construction method thereof, which reduces stress damage at the stress-bearing position by setting a first anchor rod for anchoring; a force distribution component is also provided, which can move toward force distribution areas in different directions when the soft rock part loosens and moves and squeezes toward the support tube, thereby diverting the main stress and reducing stress concentration. BRIEF DESCRIPTION OF THE DRAWINGS
[0044] In order to more clearly illustrate the technical solutions of the exemplary embodiments of the present invention, the following briefly introduces the drawings required for use in the embodiments. It should be understood that the following drawings only illustrate certain embodiments of the present invention and should not be regarded as limiting the scope. For those of ordinary skill in the art, other relevant drawings can be obtained based on these drawings without creative work. In the drawings:
[0045] Figure 1 A schematic diagram of the support structure provided by the present invention;
[0046] Figure 2 An axonometric distribution diagram of the inner steel cage and the outer steel cage in the support tube provided by the present invention;
[0047] Figure 3 A front view of an inner steel cage and an outer steel cage in the protective sleeve provided by the present invention;
[0048] Figure 4 The present invention provides Figure 1 A in the enlarged view;
[0049] Figure 5 This is a schematic diagram of the back structure of the force distribution component provided by the present invention.
[0050] Marks and corresponding parts names in the attached drawings:
[0051] 1-support tube, 101-inner steel cage, 102-outer steel cage, 103-spiral steel bar, 2-first anchor rod, 3-force component, 301-frame, 302-thin plate, 303-second anchor rod, 304-sleeve. DETAILED DESCRIPTION
[0052] In order to make the objectives, technical solutions and advantages of the present invention more clearly understood, the present invention is further described in detail below in conjunction with embodiments and drawings. The exemplary embodiments of the present invention and their description are only used to explain the present invention and are not intended to limit the present invention.
[0053] Embodiment 1:
[0054] This embodiment 1 provides a foundation pit support structure with complex soft and hard rock formations, such as Figure 1-Figure 5 As shown, including:
[0055] A support tube 1, wherein the outer diameter of the support tube 1 is adapted to the inner diameter of the foundation pit, and the support tube 1 is coaxially sleeved on the cylindrical pile;
[0056] The support tube 1 comprises an inner steel cage 101 and an outer steel cage 102 which are coaxially arranged from the inside to the outside, the inner steel cage 101 and the outer steel cage 102 are connected by straight bars, a gap is left between the outer steel cage 102 and the inner wall of the foundation pit, and the lower end of the inner steel cage 101 extends out of the outer steel cage 102;
[0057] It also includes a first anchor rod 2, which is used to pass through the side wall of the support tube 1 and the soft rock surface on the local inner wall of the foundation pit, and extend into the soft rock area. The extending end of the first anchor rod 2 sequentially extends from the soft rock area to the hard rock area and is anchored in the hard rock area.
[0058] The first anchor rod 2 is arranged horizontally or inclined upward.
[0059] Compared with the prior art, with the large-scale construction of buildings, construction projects inevitably face high-stress soft rock areas. When the columnar piles pass through the soft rock deformation section, that is, there are strong weathering layers or soft rock layers in the medium weathering rock layer, which causes the overall or local stress of the columnar pile foundation to be too large, thereby threatening the overall stability of the building project. The present invention provides a foundation pit support structure for complex soft and hard rock strata. By adopting this scheme, not only can the columnar piles be supported as a whole by sequentially pouring the inside and outside of the support tube 1, but also the columnar piles can be partially supported at the soft rock surface to improve stability. In the specific scheme, a support tube 1 is included for supporting the foundation pit and protecting the columnar piles. In this way, not only can the columnar piles be protected and the stress damage caused by external conditions be reduced, but the columnar piles can also be reused or quickly replaced.
[0060] In addition, in the prior art, the supporting structure or columnar piles are generally directly inserted into the foundation pit, which results in the inability to smoothly connect the supporting structure or columnar piles with the side wall of the foundation pit, and it takes time and effort to trim the side wall of the foundation pit into a plane. Therefore, in the present invention, the interior of the supporting tube 1 includes an inner steel cage 101 and an outer steel cage 102 coaxially arranged from the inside to the outside, and the inner steel cage 101 and the outer steel cage 102 are connected and fixed by a plurality of straight bars. After the inner and outer steel cages 102 are lowered, steel drill concrete can be sprayed on the inner steel cage 101 to form an inner template on the inner steel cage 101, wherein the inner steel cage 101 is connected by a spiral steel cage 103, a plurality of vertical bars and steel bars. The reinforcement mesh is woven to form a dense mesh of reinforcement and reduce the size of the holes to quickly form an inner formwork. Since the lower end of the inner reinforcement cage 101 extends out of the outer reinforcement cage 102, the inner reinforcement cage 101 can be inserted into the bottom of the foundation pit to form a bottom seal, so that a casting space is formed between the inner formwork and the inner wall of the foundation pit. At this time, the outer reinforcement cage 102 is located in the casting space. By pouring concrete in the casting space, the solidified concrete after pouring can be seamlessly connected with the inner wall of the foundation pit, so that the support structure and the inner wall of the foundation pit can form a whole, strengthen the support of the hard rock and soil layer to the support structure and the columnar piles, so as to improve the support capacity of the support structure to the columnar piles as a whole.
[0061] Secondly, since there is soft rock at a local position on the inner wall of the foundation pit, when the soft rock is horizontal or tilted upward away from the foundation pit, the soft rock layer at this location has a large stress and squeezes the side wall of the support tube 1, which will produce a large local soil pressure on the support tube 1, thereby causing stress damage to the support tube 1 locally, and even reducing the stability of the support tube 1. Therefore, the first anchor rod 2 can be set for anchoring. The first anchor rod 2 passes through the support tube 1 and the soft rock area from the inner wall of the support tube 1 in turn, and is anchored in the hard rock area. In this way, through the fixation of the hard rock area, the first anchor rod 2 is tension-anchored at the stress position of the support tube 1, thereby reducing the stress damage at the stress position. Among them, the direction of the first anchor rod 2 needs to be set along the direction of the initial end of the soft rock area. When this direction cannot be anchored to the hard rock area, the direction of the borehole can be adjusted in the circumferential direction until it can be anchored to the hard rock area.
[0062] Furthermore, in order to reduce the earth pressure of the soft rock area on the supporting tube 1 and reduce stress concentration, a force component 3 is also included, and the force component 3 includes a frame 301, and the frame 301 is located at the soft rock surface and perpendicular to the main stress direction of the soft rock surface;
[0063] The frame 301 has a plurality of force distribution areas, each of which has a plurality of thin plates 302. The plurality of thin plates 302 are arranged at intervals, and the arrangement direction of the thin plates 302 and the frame 301 form an angle with each other.
[0064] In the same force component area, a plurality of thin plates 302 are parallel to each other; between different force component areas, the arrangement directions of the thin plates 302 are different;
[0065] Several second anchor rods 303 are sequentially arranged along the circumferential direction of the frame 301, and the protruding ends of the second anchor rods 303 penetrate into the hard rock area and are anchored, and the second anchor rods 303 are fixedly connected to the frame 301. In this scheme, a small amount of excavation can be carried out at the initial end of the soft rock area, that is, the soft rock surface, to determine the direction of the initial end of the soft rock area, and the main stress direction of the soft rock area on the support tube 1 can be roughly determined. At this time, a force component 3 can be set at the excavation surface. The force component 3 includes a frame 301, several thin plates 302 and several second anchor rods 303. Several second anchor rods 303 can be used to anchor the frame 301 at the excavation surface, and several thin plates 302 are inserted into the soft rock area and arranged in different directions. In this way, when the soft rock part is loosened and moves and squeezes in the direction of the support tube 1, it can move toward the force component areas in different directions respectively, so as to divert the main stress and reduce stress concentration.
[0066] In order to ensure that the thin plate 302 has a sufficient length and can provide a sufficiently long diversion length, the inner side of the thin plate 302 extends out of the frame 301 and into the soft rock area.
[0067] To achieve overall protection, the size of the frame 301 is adapted to the circumferential size of the soft rock area. The shape of the frame 301 can be circular, square, etc., as long as it can adapt to the circumferential size of the excavation surface.
[0068] Since the first anchor rod 2 needs to be arranged at or close to the center of the soft rock surface, in order to facilitate providing a position for the first anchor rod 2 to pass through, the frame 301 has a sleeve 304 at the center thereof, and the sleeve 304 is used for the first anchor rod 2 to pass through.
[0069] As a fixed connection method, the second anchor rod 303 and the frame 301 are welded.
[0070] In order to improve the structural strength continuity of the local position of the supporting tube 1, a number of spiral steel bars 103 are also arranged in the supporting tube 1 at the soft rock surface of the local inner wall of the foundation pit. The two ends of the spiral steel bars 103 are respectively welded to the inner steel cage 101 and the outer steel cage 102, and the spiral steel bars 103 are arranged toward the main pressure direction of the soft rock area on the outer wall of the supporting tube 1. In this solution, the direction of the spiral bars is the main pressure direction of the soft rock area on the outer wall of the supporting tube 1, that is, the local soft rock area is resisted by the continuous strength of the spiral bars themselves.
[0071] Embodiment 2:
[0072] This embodiment 2 is further limited on the basis of embodiment 1, and also provides a construction method of a foundation pit support structure in a soft and hard rock complex stratum, including the following specific steps:
[0073] A foundation pit is excavated at a selected location to form a cylindrical foundation pit, and a step is formed at the bottom of the foundation pit so that the bottom diameter is smaller than the upper diameter.
[0074] During the excavation process, the soft rock surface is synchronously detected on the inner wall of the foundation pit. When the soft rock surface is detected, a small amount of excavation is carried out into the soft rock area along the circumferential direction of the soft rock surface. When the direction of the initial end position of the soft rock area is sufficient to determine, the excavation is stopped. At this time, the principal stress direction of the soft rock area on the supporting tube 1, that is, the principal stress direction of the initial end position of the soft rock area on the supporting tube 1, can be determined. Then the excavation surface is trimmed to a direction perpendicular to the principal stress. Then, holes are drilled in sequence along the circumferential direction of the installation surface. The holes are extended into the hard rock layer through direction adjustment or scanning detection and determination. Then, a number of second anchor rods 303 are installed at the holes, so that the extended ends of the second anchor rods 303 penetrate into the hard rock area for anchoring. Then, holes are drilled along the circumferential direction of the installation surface. The frames 301 are spliced in sequence, and the frames 301 and the ends of the second anchor rods 303 are welded and fixed; then, inside the frame 301, a gap for the thin plate 302 to be inserted into the installation surface is cut by a cutting device, and then a plurality of thin plates 302 are inserted into the installation surface in sequence, and the plurality of thin plates 302 are divided into a plurality of force distribution areas, and the directions of each force distribution area are different; finally, the two ends of the plurality of thin plates 302 are welded to the inner wall of the frame 301 respectively to complete the installation of the force distribution component 3; under the action of the force distribution component 3, when the soft rock part is loosened and moves and squeezes in the direction of the support tube 1, it can move toward the force distribution areas in different directions respectively, thereby diverting the main stress and reducing stress concentration.
[0075] After several force components 3 are set up, the inner steel cage 101 and the outer steel cage 102 are then assembled and welded, and an annular groove is excavated at the step. Then, the inner steel cage 101 and the outer steel cage 102 are lowered into the foundation pit, and the lower end of the inner steel cage 101 is inserted into the annular groove. In this way, when the concrete is sprayed to form the inner formwork, the concrete flows downward into the annular groove to form an overall closed structure.
[0076] Subsequently, steel bar concrete is sprayed on the inner steel cage 101 to form an inner formwork on the inner side of the supporting tube 1, so that a casting space can be formed between the inner formwork and the inner wall of the foundation pit. At this time, the outer steel cage 102 is located in the casting space, and then concrete is poured in the space between the inner membrane plate and the inner wall of the foundation pit to complete the overall casting and forming of the supporting tube 1; at this time, the solidified concrete after pouring can be seamlessly connected with the inner wall of the foundation pit, so that the supporting tube 1 and the inner wall of the foundation pit can form a whole, strengthen the support of the hard rock and soil layer to the supporting structure and the columnar piles, so as to improve the supporting capacity of the supporting structure to the overall columnar piles.
[0077] After the support tube 1 solidifies, a hole is then drilled from the inside of the support tube 1 to the soft rock area at the soft rock surface, and the first anchor rod 2 is installed. A groove can be provided on the inside of the support tube 1 so that the end of the first anchor rod 2 is located in the groove, so that the anchor rod does not affect the insertion of the columnar pile into the support tube 1. Finally, the columnar pile is inserted into the support tube 1 to complete the construction.
[0078] The specific implementation methods described above further illustrate the objectives, technical solutions and beneficial effects of the present invention in detail. It should be understood that the above description is only a specific implementation method of the present invention and is not intended to limit the scope of protection of the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the scope of protection of the present invention.
Claims
1. A foundation pit support structure for soft and hard rock complex strata, characterized in that: include: A support tube (1), wherein the outer diameter of the support tube (1) is matched to the inner diameter of the foundation pit, and the support tube (1) is coaxially sleeved on the columnar pile; The support tube (1) comprises an inner steel cage (101) and an outer steel cage (102) which are coaxially arranged in sequence from the inside to the outside, the inner steel cage (101) and the outer steel cage (102) are connected by straight bars, a gap is left between the outer steel cage (102) and the inner side wall of the foundation pit, and the lower end of the inner steel cage (101) extends out of the outer steel cage (102); It also comprises a first anchor rod (2), the first anchor rod (2) being used to pass through the side wall of the support tube (1), and through the soft rock surface on the local inner wall of the foundation pit, and extend into the soft rock area, the extending end of the first anchor rod (2) sequentially extends from the soft rock area into the hard rock area, and is anchored in the hard rock area; The first anchor rod (2) is arranged horizontally or inclined upwards.
2. A foundation pit support structure for complex soft and hard rock formations according to claim 1, characterized in that: It also includes a force component (3), the force component (3) includes a frame (301), the frame (301) is located at the soft rock surface and is perpendicular to the main stress direction of the soft rock surface; The frame (301) has a plurality of force distribution areas, each of the force distribution areas has a plurality of thin plates (302), the plurality of thin plates (302) are arranged at intervals, and the arrangement directions of the thin plates (302) and the frame (301) form an angle with each other; In the same force component area, a plurality of thin plates (302) are parallel to each other; between different force component areas, the arrangement directions of the thin plates (302) are different; A plurality of second anchor rods (303) are sequentially arranged along the circumferential direction of the frame (301), the extending ends of the second anchor rods (303) penetrate into the hard rock area for anchoring, and the second anchor rods (303) and the frame (301) are fixedly connected.
3. A foundation pit support structure for complex soft and hard rock formations according to claim 2, characterized in that: The inner side of the thin plate (302) extends out of the frame (301) and into the soft rock area.
4. The foundation pit support structure for complex soft and hard rock formations according to claim 2 is characterized in that: The size of the frame (301) is adapted to the circumferential size of the soft rock area.
5. The foundation pit support structure for complex soft and hard rock formations according to claim 2 is characterized in that: The frame (301) is provided with a sleeve (304) at the center thereof, and the sleeve (304) is used for allowing the first anchor rod (2) to pass through.
6. The foundation pit support structure for complex soft and hard rock formations according to claim 2 is characterized in that: The second anchor rod (303) and the frame (301) are welded.
7. The foundation pit support structure for complex soft and hard rock formations according to claim 1 is characterized in that: At the soft rock surface of the local inner wall of the foundation pit, a plurality of spiral steel bars (103) are further arranged in the support tube (1), the two ends of the spiral steel bars (103) are respectively welded to the inner steel cage (101) and the outer steel cage (102), and the spiral steel bars (103) are arranged in the main pressure direction of the outer wall of the support tube (1) towards the soft rock area.
8. The construction method of a foundation pit support structure in a soft and hard rock complex stratum according to any one of claims 2 to 7, characterized in that: The following steps are involved: S1: excavating a foundation pit and forming steps at the bottom of the foundation pit; S2: Detecting a soft rock surface on the inner wall of the foundation pit and installing a force component (3) on the soft rock surface; S3: Subsequently, the inner steel cage (101) and the outer steel cage (102) are lowered into the foundation pit, so that the lower end of the inner steel cage (101) is inserted into the step; S4: Then spraying concrete on the inner reinforcement cage (101) to form an inner formwork; S5: pouring concrete in the space between the inner membrane plate and the inner wall of the foundation pit to complete the integral casting of the support tube (1); S6: then drilling a hole from the inside of the support tube (1) to the soft rock area at the soft rock surface, and installing a first anchor rod (2); S7: Finally, a columnar pile is inserted into the supporting tube (1) to complete the construction.
9. The construction method of a foundation pit support structure in a soft and hard rock complex stratum according to claim 8 is characterized in that: The step S2 also includes the following specific steps: S21: after detecting the soft rock surface, excavating into the soft rock area along the circumferential direction of the soft rock surface, and stopping the excavation when the initial direction of the soft rock area is sufficiently determined; S22: trimming the excavation surface to an installation surface perpendicular to the initial direction; S23: sequentially installing a plurality of second anchor rods (303) along the circumferential direction of the installation surface, so that the extending ends of the second anchor rods (303) penetrate into the hard rock area for anchoring; S24: subsequently, the frames (301) are sequentially spliced along the circumferential direction of the installation surface, and the frames (301) and the ends of the plurality of second anchor rods (303) are fixed by welding; S25: inserting a plurality of thin plates (302) on the mounting surface in sequence inside the frame (301), and dividing the plurality of thin plates (302) into a plurality of force component areas; S26: Finally, the two ends of the plurality of thin plates (302) are respectively welded to the inner wall of the frame (301) to complete the installation of the force distribution assembly (3).
10. The construction method of a foundation pit support structure in a soft and hard rock complex stratum according to claim 9 is characterized in that: When a plurality of thin plates (302) are sequentially inserted into the installation surface, a cutting device is required to cut a gap on the installation surface for the thin plates (302) to be inserted.