Electric power construction management and control system

By collecting and analyzing construction data in the power construction control system and calculating safety control index, the problem of inability to accurately judge the risk of power construction in the existing technology is solved, and the accurate judgment of risk levels and improvement of construction efficiency is achieved.

CN118886708AInactive Publication Date: 2024-11-01湖北既济电力集团有限公司汉口分公司

Patent Information

Application Number
CN202410906201.1
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-08
Publication Date
2024-11-01
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

The existing power construction management and control system failed to judge the power construction risk level by calculating the safety control index, which made it difficult for managers to accurately make risk control strategies, reducing construction efficiency.

Method used

A power construction control system was designed, including data acquisition module, data analysis module and safety control module. By collecting construction data and calculating safety indicators, equipment utilization rate, personnel efficiency, cost control indicators, construction quality indicators and construction environment indicators. Comprehensively calculate the safety control index, judge the risk level and output it on the large screen of power construction scheduling.

Benefits of technology

By calculating the safety control index, managers can accurately judge the risk level of power construction and formulate effective risk control strategies, which improves the efficiency of power construction.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118886708A_ABST
    Figure CN118886708A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of power construction management and control, and discloses a power construction management and control system. According to the system, constructor data, construction equipment data, construction material data, safety data, quality data, construction environment data, construction progress data and construction cost data are acquired through a data acquisition module; the data analysis module calculates a safety index, an equipment utilization rate, personnel efficiency, a cost control index, a construction quality index, a construction progress index and a construction environment index through a formula according to the data transmitted by the data acquisition module, calculates a safety control index according to all the numerical values, and transmits the safety control index to the safety control module through a network; the safety management and control module carries out risk feedback according to the numerical value of the safety management and control index, judges the risk level and feeds back the risk level to the output scheduling module, and the output scheduling module outputs the risk level fed back by the safety management and control module to a large power construction scheduling screen and displays a risk control strategy of the corresponding level.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of electric power construction management and control, and in particular to an electric power construction management and control system. Background Art

[0002] The power construction management and control system is a system that integrates sensors, monitoring equipment, data management systems and intelligent analysis algorithms. It aims to achieve real-time monitoring, data management, risk warning, resource scheduling and information sharing of power construction sites. The system can collect, store and manage various data generated at the construction site, including monitoring data, construction plans, work logs, etc. These data can be intelligently analyzed and processed by the system to provide decision-making support and reference for managers, and realize information sharing and communication between construction sites and managers, including monitoring data, construction plans, work progress, etc. Managers can understand the situation of the construction site at any time through the system, realize remote monitoring and guidance, and improve work efficiency and collaboration capabilities.

[0003] At present, most power construction management and control systems do not determine the risk level of power construction by calculating the safety management and control index, which results in managers being unable to accurately formulate power construction risk control strategies and reduces the efficiency of power construction. Summary of the invention

[0004] 1. Technical issues to be solved

[0005] In view of the shortcomings of the prior art, the present invention provides an electric power construction management and control system, which has a data acquisition module for collecting construction personnel data Sgry, construction equipment data Sgsb, construction material data Sgcl, safety data Aqsj, quality data Zlsj, construction environment data Sghj, construction progress data Sgjd and construction cost data Sgcb, and a data analysis module calculates the safety index Aqzb, equipment utilization rate Sbly, personnel efficiency Ryxl, cost control index Cbkz, construction quality index Sgzl, construction progress index Jdzb and construction environment data according to the data transmitted by the data acquisition module. Indicator Hjzb, and the safety control index Aqzs is calculated based on all the above values ​​and transmitted to the safety control module through the network. The safety control module performs risk feedback based on the value of the safety control index Aqzs, determines the risk level and feeds back the risk level to the output scheduling module. The output scheduling module outputs the risk level fed back by the safety control module on the power construction scheduling screen, and determines the risk level of power construction by calculating the safety control index and displays it on the power scheduling screen. The management personnel schedule the power construction according to the size of the risk level, accurately make power construction risk control strategies, improve the efficiency of power construction, and solve the above problems.

[0006] (II) Technical solution

[0007] To achieve the above-mentioned object, the present invention provides the following technical solutions: an electric power construction management and control system, comprising a data acquisition module, a data analysis module, a safety management and control module and an output scheduling module;

[0008] The data acquisition module is used to collect construction personnel data Sgry, construction equipment data Sgsb, construction material data Sgcl, safety data Aqsj, quality data Zlsj, construction environment data Sghj, construction progress data Sgjd and construction cost data Sgcb, and transmit the above collected data to the data analysis module through the network for data processing and calculation;

[0009] The data analysis module calculates the safety index Aqzb, equipment utilization rate Sbly, personnel efficiency Ryxl, cost control index Cbkz, construction quality index Sgzl, construction progress index Jdzb and construction environment index Hjzb through the formula according to the data transmitted by the data acquisition module, and calculates the safety control index Aqzs according to all the above values ​​and transmits it to the safety control module through the network;

[0010] The safety control module performs risk feedback according to the value of the safety control index Aqzs, determines the risk level and feeds the risk level back to the output scheduling module;

[0011] The output scheduling module outputs the risk level fed back by the safety management and control module on the power construction scheduling screen and displays the risk control strategy of the corresponding level.

[0012] Preferably, the data analysis module calculates the safety index Aqzb according to the data transmitted by the data acquisition module through a formula, and the calculation formula is as follows:

[0013]

[0014] In the formula, Aqzb represents the safety index, Bzzb represents the safety index value set by the system, and Qzxs represents the weight coefficient set by the system.

[0015] Preferably, the data analysis module calculates the equipment utilization rate Sbly according to the data transmitted by the data acquisition module through a formula, and the calculation formula is as follows:

[0016]

[0017] In the formula, Sbly represents the equipment utilization rate, Sjsy represents the actual usage time, Sbcn represents the unit capacity of the equipment, Zgsj represents the total working time, and Sbsl represents the number of equipment.

[0018] Preferably, the data analysis module calculates the personnel efficiency Ryxl according to the data transmitted by the data acquisition module through a formula, and the calculation formula is as follows:

[0019]

[0020] In the formula, Ryxl represents personnel efficiency, Jxpf represents performance score, which is set by management personnel, Gzfh represents workload coefficient, which is set to 0.6, Zyxs represents professional skill coefficient, which is set by the system, and Sgrw represents the total number of personnel involved in the construction, which is obtained through the system.

[0021] Preferably, the data analysis module calculates the cost control index Cbkz according to the data transmitted by the data acquisition module through a formula, and the calculation formula is as follows:

[0022]

[0023] In the formula, Cbkz represents the cost control indicator, Sjcb represents the actual cost, and Jhcb represents the calculated cost. This formula is used to calculate the performance of a project or enterprise in cost control. A result greater than 100% indicates that the actual cost exceeds the planned cost, and a result less than 100% indicates that the actual cost is lower than the planned cost.

[0024] Preferably, the data analysis module calculates the construction quality index Sgzl according to the data transmitted by the data acquisition module through a formula, and the calculation formula is as follows:

[0025]

[0026] In the formula, Sgzl represents the construction quality index, Gcpf represents the construction project score, that is, the score obtained based on the construction quality evaluation of the project, Zyqz represents the project importance weight set by the system, and Zdfs represents the total score of the construction project.

[0027] Preferably, the data analysis module calculates the construction progress index Jdzb according to the data transmitted by the data acquisition module through a formula, and the calculation formula is as follows:

[0028]

[0029] In the formula, Jdzb represents the construction progress index, Sjwc represents the actual completion of the project tasks, and Jhwc represents the planned completion of the project tasks. This formula evaluates the construction progress of the project by comparing the actual completion percentage with the planned completion percentage. When the construction progress index is 100%, it means that the project is proceeding as planned. When it is less than 100%, it means that the project progress is lagging behind. When it is greater than 100%, it means that the project progress is ahead of schedule.

[0030] Preferably, the data analysis module calculates the construction environment index Hjzb by a formula based on the data transmitted by the data acquisition module. The calculation formula is as follows:

[0031] Hjzb=Hjqz*Zldf*Zhys

[0032] In the formula, Hjzb represents the construction environment index, Hjqz represents the environmental weight set by the system, Zldf represents the environmental impact score, and Zhys represents the total number of environmental factors, which is 5.

[0033] Preferably, the data analysis module comprehensively calculates the safety control index Aqzs according to the safety index Aqzb, equipment utilization rate Sbly, personnel efficiency Ryxl, cost control index Cbkz, construction quality index Sgzl, construction progress index Jdzb and construction environment index Hjzb, and the calculation formula is as follows:

[0034] Aqzs=x1*Aqzb+x2*Sbly+x3*Ryxl+x4*Cbkz+x5*Sgzl+x6

[0035] *Jdzb+x7*Hjzb

[0036] In the formula, Aqzs represents the safety control index, Aqzb represents the safety index, Sbly represents the equipment utilization rate, Ryxl represents the personnel efficiency, Cbkz represents the cost control index, Sgzl represents the construction quality index, Jdzb represents the construction progress index, and Hjzb represents the construction environment index.

[0037] Preferably, the safety control module performs risk feedback according to the value of the safety control index Aqzs and determines the risk level. The determination method is as follows:

[0038] When the safety control index Aqzs is greater than or equal to 100, the risk level is level 5;

[0039] When the safety control index Aqzs is greater than or equal to 80 and less than 100, the risk level is level 4;

[0040] When the safety control index Aqzs is greater than or equal to 60 and less than 80, the risk level is level 3;

[0041] When the safety control index Aqzs is greater than or equal to 40 and less than 60, the risk level is level 2;

[0042] When the safety control index Aqzs is greater than or equal to 10 and less than 40, the risk level is level 1;

[0043] When the safety control index Aqzs is below 10, it means there is no risk.

[0044] Compared with the prior art, the present invention provides a power construction management and control system, which has the following beneficial effects:

[0045] The present invention uses a data acquisition module to collect construction personnel data Sgry, construction equipment data Sgsb, construction material data Sgcl, safety data Aqsj, quality data Zlsj, construction environment data Sghj, construction progress data Sgjd and construction cost data Sgcb. The data analysis module calculates the safety index Aqzb, equipment utilization rate Sbly, personnel efficiency Ryxl, cost control index Cbkz, construction quality index Sgzl, construction progress index Jdzb and construction environment index Hjzb through a formula according to the data transmitted by the data acquisition module, and calculates the safety control index Aqzs according to all the above values ​​and transmits it to the safety control module through the network. The safety control module performs risk feedback according to the value of the safety control index Aqzs, judges the risk level and feeds the risk level back to the output scheduling module. The output scheduling module outputs the risk level fed back by the safety control module on the power construction scheduling large screen, judges the power construction risk level by calculating the safety control index, and displays it on the power scheduling large screen. The management personnel perform power construction scheduling according to the size of the risk level, accurately make power construction risk control strategies, and improve the efficiency of power construction. BRIEF DESCRIPTION OF THE DRAWINGS

[0046] Figure 1 It is a schematic diagram of the system flow of the present invention. DETAILED DESCRIPTION

[0047] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0048] In view of the problem that managers are unable to accurately take risk control measures during power construction, resulting in low efficiency of power construction, a power construction management and control system is proposed. Figure 1 The system includes a data acquisition module, a data analysis module, a security control module and an output scheduling module, wherein:

[0049] The data acquisition module uses different sensors and handheld information acquisition devices to collect construction personnel data Sgry, construction equipment data Sgsb, construction material data Sgcl, safety data Aqsj, quality data Zlsj, construction environment data Sghj, construction progress data Sgjd and construction cost data Sgcb, and transmits the above collected data to the data analysis module through the network for data processing and calculation;

[0050] The data analysis module calculates the safety index Aqzb, equipment utilization rate Sbly, personnel efficiency Ryxl, cost control index Cbkz, construction quality index Sgzl, construction progress index Jdzb and construction environment index Hjzb through formulas based on the data transmitted by the data acquisition module, where:

[0051] Safety index calculation formula:

[0052]

[0053] By calculating the safety index, we can objectively and accurately monitor and evaluate the safety status of a project or organization, timely discover safety hazards and problems, and take targeted preventive and improvement measures. In the formula, Aqzb represents the safety index, Bzzb represents the system-set safety index value, and Qzxs represents the system-set weight coefficient. By calculating the safety index, we can determine which safety aspects have greater risks and problems, so as to give priority to handling and solving key safety hazards and improve the accuracy and pertinence of safety management.

[0054] Equipment utilization calculation formula:

[0055]

[0056] Understanding the utilization rate of power construction equipment can help enterprises evaluate the working efficiency and production capacity of equipment, timely discover equipment operation problems and improve them, improve production efficiency, and ensure construction progress and quality. In the formula, Sbly represents equipment utilization, Sjsy represents actual use time, Sbcn represents equipment unit capacity, Zgsj represents total working time, and Sbsl represents the number of equipment. By monitoring the utilization rate of power construction equipment, abnormal equipment operation or existing problems can be discovered in time, providing data support for equipment maintenance, formulating corresponding maintenance plans, extending the service life of equipment, and ensuring construction safety;

[0057] Staff efficiency calculation formula:

[0058]

[0059] By calculating the efficiency of power construction personnel, it can help enterprises find inefficient links in the work process, take timely measures to optimize the work process, improve production efficiency and reduce production costs. In the formula, Ryxl represents personnel efficiency, Jxpf represents performance score, which is set by management personnel, Gzfh represents workload coefficient, which is set to 0.6, Zyxs represents professional skill coefficient, which is set by the system, and Sgrw represents the total number of personnel involved in the construction, which is obtained through the system. By regularly calculating the efficiency of power construction personnel, problems can be found in time, and work processes and management methods can be continuously improved to improve construction quality and efficiency.

[0060] Cost control index calculation formula:

[0061]

[0062] By calculating the power construction cost control index, it can help power construction companies to timely discover cost overruns, adjust budgets in a timely manner, and reduce cost risks. In the formula, Cbkz represents the cost control index, Sjcb represents the actual cost, and Jhcb represents the calculated cost. This formula is used to calculate the performance of a project or company in cost control. A result greater than 100% indicates that the actual cost exceeds the planned cost, and a result less than 100% indicates that the actual cost is lower than the planned cost.

[0063] Construction quality index calculation formula:

[0064]

[0065] By calculating the power construction quality index, it is used to help enterprises timely evaluate the quality of the construction process, timely discover and solve problems, and ensure that the project quality meets the standards and requirements. In the formula, Sgzl represents the construction quality index, Gcpf represents the construction project score, that is, the score obtained based on the construction quality evaluation of the project, Zyqz represents the project importance weight set by the system, and Zdfs represents the total score of the construction project;

[0066] Construction progress indicator calculation formula:

[0067]

[0068] By calculating the construction progress index, we can timely understand the actual progress of the project, help managers make timely adjustments and decisions, and ensure that the project is completed on time. In the formula, Jdzb represents the construction progress index, Sjwc represents the actual completion of the project task, and Jhwc represents the planned completion of the project task. This formula evaluates the construction progress of the project by comparing the actual completion percentage with the planned completion percentage. When the construction progress index is 100%, it means that the project is proceeding as planned. When it is less than 100%, it means that the project is lagging behind. When it is greater than 100%, it means that the project is ahead of schedule. By calculating the construction progress index, managers can better allocate resources, arrange work plans, and improve the efficiency and effectiveness of project management.

[0069] Construction environment index calculation formula:

[0070] Hjzb=Hjqz*Zldf*Zhys

[0071] By calculating the construction environment index, the safety status of the construction site can be evaluated, potential safety hazards can be discovered in time, and the safety of construction workers can be guaranteed. At the same time, using this index to evaluate the impact of the construction process on the surrounding environment is conducive to taking effective environmental protection measures and reducing the damage to the environment caused by construction. In the formula, Hjzb represents the construction environment index, Hjqz represents the environmental weight set by the system, Zldf represents the environmental impact score, and Zhys represents the total number of environmental factors, specifically 5;

[0072] The data analysis module comprehensively calculates the safety control index Aqzs based on the safety index Aqzb, equipment utilization rate Sbly, personnel efficiency Ryxl, cost control index Cbkz, construction quality index Sgzl, construction progress index Jdzb and construction environment index Hjzb. The calculation formula is as follows:

[0073] Aqzs=x1*Aqzb+x2*Sbly+x3*Ryxl+x4*Cbkz+x5*Sgzl+x6

[0074] *Jdzb+x7*Hjzb

[0075] Safety is one of the important guarantees for construction quality. Through effective calculation and management of safety control index, construction quality can be improved, losses and rework can be reduced. In the formula, Aqzs represents the safety control index, Aqzb represents the safety index, Sbly represents the equipment utilization rate, Ryxl represents the personnel efficiency, Cbkz represents the cost control index, Sgzl represents the construction quality index, Jdzb represents the construction progress index, and Hjzb represents the construction environment index. By calculating the construction safety control index, the safety status of the construction site can be evaluated, potential safety hazards can be discovered in time, and measures can be taken to prevent accidents.

[0076] The security control module provides risk feedback based on the value of the security control index Aqzs and determines the risk level. The determination method is as follows:

[0077] When the safety control index Aqzs is greater than or equal to 100, the risk level is level 5;

[0078] When the safety control index Aqzs is greater than or equal to 80 and less than 100, the risk level is level 4;

[0079] When the safety control index Aqzs is greater than or equal to 60 and less than 80, the risk level is level 3;

[0080] When the safety control index Aqzs is greater than or equal to 40 and less than 60, the risk level is level 2;

[0081] When the safety control index Aqzs is greater than or equal to 10 and less than 40, the risk level is level 1;

[0082] When the safety control index Aqzs is below 10, it means there is no risk;

[0083] The output scheduling module outputs the risk level feedback from the safety management module on the power construction scheduling screen. According to different safety levels, the power scheduling screen will display different risk response measures. Managers select plans for power construction scheduling based on the size of the risk level, accurately formulate power construction risk control strategies, and improve the efficiency of power construction.

[0084] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.

Claims

1. A power construction management and control system, characterized in that: Including data acquisition module, data analysis module, security control module and output scheduling module; The data acquisition module is used to collect construction personnel data Sgry, construction equipment data Sgsb, construction material data Sgcl, safety data Aqsj, quality data Zlsj, construction environment data Sghj, construction progress data Sgjd and construction cost data Sgcb, and transmit the above collected data to the data analysis module through the network for data processing and calculation; The data analysis module calculates the safety index Aqzb, equipment utilization rate Sbly, personnel efficiency Ryxl, cost control index Cbkz, construction quality index Sgzl, construction progress index Jdzb and construction environment index Hjzb through the formula according to the data transmitted by the data acquisition module, and calculates the safety control index Aqzs according to all the above values ​​and transmits it to the safety control module through the network; The safety control module performs risk feedback according to the value of the safety control index Aqzs, determines the risk level and feeds the risk level back to the output scheduling module; The output scheduling module outputs the risk level fed back by the safety management and control module on the power construction scheduling screen and displays the risk control strategy of the corresponding level.

2. The electric power construction management and control system according to claim 1, characterized in that: The data analysis module calculates the safety index Aqzb according to the data transmitted by the data acquisition module through the formula, and the calculation formula is as follows: In the formula, Aqzb represents the safety index, Bzzb represents the safety index value set by the system, and Qzxs represents the weight coefficient set by the system.

3. The electric power construction management and control system according to claim 2, characterized in that: The data analysis module calculates the equipment utilization rate Sbly according to the data transmitted by the data acquisition module through the formula, and the calculation formula is as follows: In the formula, Sbly represents the equipment utilization rate, Sjsy represents the actual usage time, Sbcn represents the unit capacity of the equipment, Zgsj represents the total working time, and Sbsl represents the number of equipment.

4. The electric power construction management and control system according to claim 3 is characterized in that: The data analysis module calculates the personnel efficiency Ryxl through the formula according to the data transmitted by the data acquisition module. The calculation formula is as follows: In the formula, Ryxl represents personnel efficiency, Jxpf represents performance score, which is set by management personnel, Gzfh represents workload coefficient, which is set to 0.6, Zyxs represents professional skill coefficient, which is set by the system, and Sgrw represents the total number of personnel involved in the construction, which is obtained through the system.

5. The electric power construction management and control system according to claim 4 is characterized in that ::The data analysis module calculates the cost control index Cbkz according to the data transmitted by the data acquisition module through the formula, and the calculation formula is as follows: In the formula, Cbkz represents the cost control indicator, Sjcb represents the actual cost, and Jhcb represents the calculated cost. This formula is used to calculate the performance of a project or enterprise in cost control. A result greater than 100% indicates that the actual cost exceeds the planned cost, and a result less than 100% indicates that the actual cost is lower than the planned cost.

6. The electric power construction management and control system according to claim 5, characterized in that: The data analysis module calculates the construction quality index Sgzl according to the data transmitted by the data acquisition module through the formula, and the calculation formula is as follows: In the formula, Sgzl represents the construction quality index, Gcpf represents the construction project score, that is, the score obtained based on the construction quality evaluation of the project, Zyqz represents the project importance weight set by the system, and Zdfs represents the total score of the construction project.

7. The electric power construction management and control system according to claim 6, characterized in that: The data analysis module calculates the construction progress index Jdzb according to the data transmitted by the data acquisition module through the formula, and the calculation formula is as follows: In the formula, Jdzb represents the construction progress index, Sjwc represents the actual completion of the project tasks, and Jhwc represents the planned completion of the project tasks. This formula evaluates the construction progress of the project by comparing the actual completion percentage with the planned completion percentage. When the construction progress index is 100%, it means that the project is proceeding as planned. When it is less than 100%, it means that the project progress is lagging behind. When it is greater than 100%, it means that the project progress is ahead of schedule.

8. The electric power construction management and control system according to claim 7, characterized in that: The data analysis module calculates the construction environment index Hjzb according to the data transmitted by the data acquisition module through the formula, and the calculation formula is as follows: Hjzb=Hjqz*Zldf*Zhys In the formula, Hjzb represents the construction environment index, Hjqz represents the environmental weight set by the system, Zldf represents the environmental impact score, and Zhys represents the total number of environmental factors, which is 5.

9. The electric power construction management and control system according to claim 8, characterized in that: The data analysis module comprehensively calculates the safety control index Aqzs according to the safety index Aqzb, equipment utilization rate Sbly, personnel efficiency Ryxl, cost control index Cbkz, construction quality index Sgzl, construction progress index Jdzb and construction environment index Hjzb. The calculation formula is as follows: Aqzs=x1*Aqzb+x2*Sbly+x3*Ryxl+x4*Cbkz+x5*Sgzl+x6 *Jdzb+x7*Hjzb In the formula, Aqzs represents the safety control index, Aqzb represents the safety index, Sbly represents the equipment utilization rate, Ryxl represents the personnel efficiency, Cbkz represents the cost control index, Sgzl represents the construction quality index, Jdzb represents the construction progress index, and Hjzb represents the construction environment index.

10. The electric power construction management and control system according to claim 9, characterized in that: The safety control module performs risk feedback according to the value of the safety control index Aqzs and determines the risk level. The determination method is as follows: When the safety control index Aqzs is greater than or equal to 100, the risk level is level 5; When the safety control index Aqzs is greater than or equal to 80 and less than 100, the risk level is level 4; When the safety control index Aqzs is greater than or equal to 60 and less than 80, the risk level is level 3; When the safety control index Aqzs is greater than or equal to 40 and less than 60, the risk level is level 2; When the safety control index Aqzs is greater than or equal to 10 and less than 40, the risk level is level 1; When the safety control index Aqzs is below 10, it means there is no risk.

Citation Information

Patent Citations

  • Power grid engineering safety evaluation system based on big data

    CN108805407A

  • Electric power construction management and control system

    CN116258467A

  • Engineering project risk supervision and early warning system based on Internet of Things

    CN117829602A

  • Method and device for making optimum distribution system

    JP2004129404A

  • Security protection method and system for power terminal

    WO2023216641A1

Cited By

  • Intelligent garden construction management method and device

    CN119180426A