Pile pulling method and pile pulling system

By connecting the anti-resistance and anchoring modules on both sides of the pile wall, the overall lifting of multiple bite piles is achieved, solving the problem of low removal efficiency of multiple pile walls in the existing technology, and improving safety and construction efficiency.

CN118911141APending Publication Date: 2024-11-08SHANGHAI ROAD & BRIDGE (GRP) CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411126776.8
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-16
Publication Date
2024-11-08

AI Technical Summary

Technical Problem

The prior art lacks a pile wall extraction method for multiple bite piles, making it difficult to achieve efficient and safe overall removal.

Method used

By eliminating the two sides of the pile wall, selecting the bite piles containing reinforced concrete piles and plain concrete piles for penetration and cutting, and fixing them with connecting parts and anchoring modules, and applying traction force to achieve the overall lifting of multiple piles .

Benefits of technology

It improves the extraction efficiency, enhances safety, reduces construction time and cost, avoids the complexity of traditional multiple cuttings of single or double-root uproots, and is suitable for the stable removal of large-scale pile walls.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118911141A_ABST
    Figure CN118911141A_ABST
Patent Text Reader

Abstract

The invention discloses a pile pulling method and a pile pulling system. The pile pulling method comprises the following steps: S1, carrying out resistance elimination on two sides of a pile wall; s2, selecting a section of secant pile containing the reinforced concrete pile and the plain concrete pile from the pile wall; s3, the two ends of the secant pile are cut in a penetrating mode; s4, one end of a first connecting piece is implanted into one side face of the secant pile, and the other end of the first connecting piece is exposed out of the secant pile; s5, the other end of the first connecting piece, the side wall of the secant pile and one end of the second connecting piece are solidified and connected through concrete to form an anchoring module; s6, one end of a third connecting piece is implanted into the top face of the secant pile, and the other end of the third connecting piece is exposed out of the secant pile; and S7, lifting equipment is connected with the other end of the second connecting piece and the other end of the third connecting piece, and the secant pile is lifted. According to the method, the multiple secant piles can be pulled out, and the pile pulling efficiency is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to a pile pulling method and a pile pulling system. Background Art

[0002] In recent years, the research on pile removal technology during construction has become increasingly in-depth, and attempts have been made to explore solutions that are more suitable for complex construction site environments. The following are the main research and application technologies currently underway: Hydraulic pile extraction method: Using special hydraulic machinery, high-pressure water pressure is applied around the pile body, gradually squeezing the surrounding soil, so that the pile body is gradually raised and finally pulled out. This method not only reduces the reliance on large cranes, but can also be implemented in a relatively small space. Vibration pile extraction technology: Vibration equipment is used to act on the pile body to loosen the soil around the pile body, and then the pile body is gradually pushed out by hydraulic machinery or human thrust. This technology has low requirements for on-site space and is suitable for occasions where rapid pile extraction is required. Water pressure pulse pile extraction method: Through a water pressure pulse device, an instantaneous high-pressure pulse is applied to the soil around the pile body to loosen the soil and push the pile body out. This method is easy to operate and is suitable for various types of piles and construction environments. Blasting pile extraction technology: Rapid pile extraction is achieved by controlling the explosive force and direction of the blasting charge. This method can effectively handle deeply buried or particularly strong piles, but it requires precise engineering design and strict safety control measures to ensure the safety of the surrounding environment and facilities. In summary, these emerging pile extraction technologies have shown obvious advantages in improving construction efficiency, reducing safety risks and adapting to complex construction environments. However, the existing pile extraction technologies are all methods for extracting single piles, and there is no extraction solution for multiple interlocking piles forming a pile wall. Summary of the invention

[0003] The technical problem to be solved by the present invention is to overcome the lack of a method for pulling out a plurality of interlocking piles in the prior art, and to provide a pile pulling method and a pile pulling system.

[0004] The present invention solves the above technical problems through the following technical solutions:

[0005] A pile extraction method is applied to a pile wall formed by a plurality of reinforced concrete piles and plain concrete piles interlocked with each other and arranged in sequence at intervals, comprising the following steps:

[0006] S1, eliminating the obstruction on both sides of the pile wall;

[0007] S2, selecting a section of interlocking piles containing the reinforced concrete piles and plain concrete piles from the pile wall;

[0008] S3, performing through-cutting on both ends of the occlusal pile;

[0009] S4, implanting one end of the first connecting member into one side of the occlusal post, and exposing the other end of the first connecting member from the occlusal post;

[0010] S5, solidifying and connecting the other end of the first connecting member, the side wall of the bite pile and one end of the second connecting member through concrete to form an anchoring module;

[0011] S6, implanting one end of a third connecting member on the top surface of the occlusal post, and exposing the other end of the third connecting member from the occlusal post;

[0012] S7. A lifting device is respectively connected to the other end of the second connecting member and the other end of the third connecting member, and lifts the bite pile.

[0013] In this solution, the interlocking piles include reinforced concrete piles and plain concrete piles, which interlock with each other at the connection points and are a selected part of the pile wall.

[0014] In the pile pulling method, in step S1, both sides of the pile wall are blocked to reduce the resistance during pile pulling; in step S2, the number of interlocking piles including reinforced concrete piles and plain concrete piles is designed according to the bearing capacity provided by the lifting equipment and the cross-sectional area of ​​the embedded reinforcement, the deadweight of the pile wall, and the friction resistance around the pile, so that the piles can be pulled out successfully; in step S3, the interlocking pile part is separated from the whole pile wall by cutting to reduce the pulling force of the interlocking pile part; in step S4, the first connecting member is implanted into the interlocking pile, so that one end of the first connecting member is firmly fixed on the interlocking pile, and the other end of the first connecting member is used for solid connection with the anchor module, so that the pulling force is transmitted to the interlocking pile when the anchor module is pulled by the second connecting member. The pile-joining part; in step S5, the first connecting member, the second connecting member and the anchoring module are solidified and connected by concrete, and the anchoring module and the bite pile are also formed into a whole. When the second connecting member is lifted, the anchoring module transmits force to the pile wall of the bite pile, and then the reinforced concrete pile and the plain concrete pile are pulled out as a whole; in step S6, the third connecting member is implanted on the top surface of the bite pile to form a connection point, which is convenient for the connection of the lifting equipment, and then the traction force is applied from the top surface of the bite pile; in step S6, when the lifting equipment is lifted, the anchoring module on one side of the bite pile and the third connecting member on the top surface simultaneously apply force to the bite pile, and cleverly realize the pulling out of multiple reinforced concrete piles and plain concrete piles at one time. Compared with the traditional pile pulling method of multiple cutting single or double roots, this pile pulling method breaks through the traditional mindset and forms the effect of pulling out a part of the bite pile as a whole. Because anchor modules are designed before pile extraction and multiple reinforced concrete piles and plain concrete piles are connected together using anchor modules, pile sliding during pile extraction can be effectively prevented. This method is particularly suitable for the extraction of large pile walls in open spaces. The overall method is reliable and stable, and the safety is greatly improved. This method can save a lot of cost and construction time, and improve the efficiency of extracting interlocking piles.

[0015] After pulling out the bite pile, it is necessary to crush it. Multiple static blasting holes can be drilled on the top surface of the bite pile, crushing agent is poured into the blasting hole and the hole of the static blasting hole is blocked with fast-hardening cement. The process takes 12-18 hours. Then the pile body is crushed by crushing equipment. Combined with concrete cutting and gas cutting of steel bars, the concrete can be quickly decomposed to realize the upper demolition of the pile, and the pile extraction project can be smoothly transferred to the next process.

[0016] Preferably, in step S2, both ends of the interlocking pile are plain concrete piles.

[0017] In this solution, both ends of the selected interlocking piles are plain concrete piles, which are convenient for quick cutting, so as to quickly separate the interlocking piles from the pile wall at the upper end, thereby reducing the pull-out force.

[0018] Preferably, in step S4, a reinforcement hole is opened on one side of the occlusal pile, the reinforcement hole is extended along the thickness direction of the occlusal pile, one end of the first connecting member is inserted into the reinforcement hole and connected to the occlusal pile by curing with reinforcement glue;

[0019] A plurality of the first connecting members are implanted, and the plurality of the first connecting members are arranged at intervals along the length direction of the occlusal post.

[0020] In this solution, by implanting the first connecting member on the side of the occlusal pile, it is convenient to add a connecting point on the side of the occlusal pile. During lifting, force is applied to the side of the occlusal pile to pull out the occlusal pile.

[0021] Preferably, the rebar embedding glue is injected into the rebar embedding hole multiple times, and the first connecting piece is pulled each time the rebar embedding glue is injected.

[0022] In this solution, pressure-injected rebar embedding glue is poured into the rebar embedding hole in batches. After the previous rebar embedding glue solidifies and reaches the set strength, the injection is continued until the rebar embedding glue exceeds the rebar embedding hole surface. When injecting glue, the first connecting piece can be appropriately pulled to expel air to ensure the bonding effect.

[0023] Preferably, step S5 further comprises step S51: setting up a mold on the side of the occlusal pile where the first connecting member is planted, for making an anchoring module.

[0024] In this scheme, when making the anchor module, vibration grouting is used to pour concrete slurry into the mold. The concrete slurry is a slurry mixed with PO52.5 cement, cement slurry pore grouting agent and water. The water-cement ratio of the concrete slurry is 0.35-0.45. A mortar mixer and a grouting pump are used for vibration grouting.

[0025] Before making the anchoring module, dust removal is performed at the location where the anchoring module is to be made to ensure close adhesion between the poured concrete slurry and the bite pile.

[0026] Preferably, the anchoring module is arranged at one third of the distance from the bottom of the exposed portion of the occlusal pile, and the implantation depth of the first connecting member is not less than one third of the cross-sectional depth of the occlusal pile.

[0027] Preferably, in step S6, the second connecting member is implanted on the top surface of the reinforced concrete pile in the occlusal pile;

[0028] There are multiple second connecting members, and the multiple second connecting members are arranged at intervals along the length direction of the engaging pile.

[0029] In this solution, the second connecting member is implanted on the top surface of the reinforced concrete pile, which is more firmly connected than the plain concrete pile. When the reinforced concrete pile is pulled out, it can withstand a larger pull-out force and is not easy to collapse. A plurality of second connecting members are arranged at intervals along the length direction of the occlusal pile, which is convenient for evenly applying force to the occlusal pile and making it easier to pull out the occlusal pile.

[0030] Preferably, in step S7, a working platform is provided on the pile wall near the interlocking pile or on the soil around the interlocking pile, and the lifting equipment is erected on the working platform.

[0031] In this scheme, by arranging a working platform capable of bearing a large supporting force, it is convenient to install the lifting device on the working platform. During lifting, the lifting device will not fall over, thereby improving safety.

[0032] Preferably, the working platform is any one of a reinforced concrete platform, a steel structure frame platform or a composite structure platform.

[0033] Preferably, the lifting equipment is a through-hole jack, a crane or a winch arranged on the working platform, the through-hole jack is fixed to the reinforced concrete platform, the steel structure frame platform or the combined structure platform through a reaction frame, and the crane or winch is arranged on the reinforced concrete platform, the steel structure frame platform or the combined structure platform. During lifting, the through-hole jack, the crane or the winch continuously tensions the top surface of the anchor module and the interlocking pile to continuously pull up the interlocking pile to be pulled out. By setting up a reinforced concrete platform, a steel structure frame platform or a combined structure platform, the pile wall partially located above the ground surface or entirely located below the ground surface can be continuously pulled up, and the overall structure is simple and reliable.

[0034] Preferably, after step S7, the following steps are also included:

[0035] S8. If the pile extraction by the lifting device fails, the surrounding side of the interlocking pile is again blocked or the number of the second connecting members and the third connecting members is increased, and step S7 is repeated.

[0036] In this solution, the upper adhesion force on the bite pile is reduced by eliminating the resistance again. By increasing the number of the second connecting member and the third connecting member, the connection points are increased and the pull-out force is increased.

[0037] Preferably, the first connecting member, the second connecting member and the third connecting member are respectively made of any one or more of metal hard materials, metal soft materials, non-metal hard materials or non-metal soft materials.

[0038] In this solution, the metal hard material is such as bonded steel strand, prestressed steel strand, prestressed steel strand, high-strength steel wire, high-strength steel wire rope or high-strength steel bar, etc. Non-metal hard or soft material is such as fiber, plastic or nylon, etc.

[0039] A pile pulling system is used in the pile pulling method as described above, and comprises a lifting device, a mold for making an anchoring module, and a working platform.

[0040] In this solution, the lifting equipment is used to provide the pulling force during lifting, the mold is used to quickly make the anchoring module, and the working platform is used to install the lifting equipment and provide a stable supporting platform.

[0041] On the basis of being in accordance with the common sense in the art, the above-mentioned preferred conditions can be arbitrarily combined to obtain the preferred embodiments of the present invention.

[0042] The positive and progressive effects of the present invention are as follows: in step S1, the pile pulling method eliminates resistance on both sides of the pile wall to reduce the resistance during pile pulling; in step S2, the bite pile (including the number of reinforced concrete piles and plain concrete piles) is designed according to the bearing capacity that can be provided by the lifting equipment and the cross-sectional area of ​​the embedded reinforcement, the deadweight of the pile wall, and the friction resistance around the pile so that it can be successfully pulled out; in step S3, the bite pile part is separated from the overall pile wall by cutting to reduce the pull-out force of the bite pile part; in step S4, the first connecting member is implanted into the bite pile, so that one end of the first connecting member is firmly fixed on the bite pile, and the other end of the first connecting member is used for solid connection with the anchor module, so that the pull-out pile can be pulled out by pulling the anchor module through the second connecting member. The output force is transmitted to the bite pile part; in step S5, the first connecting member, the second connecting member and the anchoring module are solidified and connected by concrete, and the connection is firm, and the anchoring module and the bite pile are also formed into a whole. When the second connecting member is lifted, the anchoring module transmits the force to the pile wall of the bite pile, and then the reinforced concrete pile and the plain concrete pile are pulled out as a whole; in step S6, the third connecting member is implanted on the top surface of the bite pile to form a connection point, which is convenient for the connection of the lifting equipment, and then the traction force is applied from the top surface of the bite pile; in step S6, when the lifting equipment is lifted, the anchoring module on one side of the bite pile and the third connecting member on the top surface simultaneously apply force to the bite pile, and cleverly realize the pulling out of multiple reinforced concrete piles and plain concrete piles at one time. Compared with the traditional pile pulling method of multiple cutting single or double roots, this pile pulling method breaks through the traditional mindset and forms the effect of pulling out the bite pile as a whole. Because the anchoring module is designed before the piles are pulled out, and multiple reinforced concrete piles and plain concrete piles are connected together, the pile sliding during the pile pulling process can be effectively prevented. It is particularly suitable for the removal of a large pile wall in an open space. The overall reliability and stability are greatly improved, and a large amount of cost and construction time can be saved, and the efficiency of pulling out the interlocking piles is improved. BRIEF DESCRIPTION OF THE DRAWINGS

[0043] Figure 1 The figure is a flow chart of a pile pulling method according to a preferred embodiment of the present invention.

[0044] Figure 2 It is a schematic structural diagram of an occlusal pile according to a preferred embodiment of the present invention.

[0045] Figure 3 The structure of the bite pile and pile extraction system of a preferred embodiment of the present invention is shown in FIG. Figure 1 .

[0046] Figure 4 The structure of the bite pile and pile extraction system of a preferred embodiment of the present invention is shown in FIG. Figure 2 .

[0047] Figure 5 The figure is a schematic structural diagram of an interlocking pile and a mold for making an anchoring module according to a preferred embodiment of the present invention.

[0048] Description of reference numerals:

[0049] Reinforced concrete pile 10

[0050] Plain concrete pile 20

[0051] Bite post 30

[0052] First connecting piece 1

[0053] Second connecting piece 2

[0054] The third connecting piece 3

[0055] Anchor module 4

[0056] Work platform 5

[0057] Lifting equipment 6

[0058] Through-hole jack 61

[0059] Reaction frame 62

[0060] Anchor 63

[0061] Mold 7 DETAILED DESCRIPTION

[0062] The present invention will be described more clearly and completely below by way of embodiments in conjunction with the accompanying drawings, but the present invention is not limited to the scope of the embodiments.

[0063] like Figure 1-Figure 5 As shown, this embodiment discloses a pile pulling method, which is applied to a pile wall formed by a plurality of reinforced concrete piles 10 and plain concrete piles 20 arranged in sequence and interlocked with each other, and includes the following steps:

[0064] S1. Eliminate the obstruction on both sides of the pile wall;

[0065] S2, selecting a section of interlocking piles 30 including reinforced concrete piles 10 and plain concrete piles 20 from the pile wall;

[0066] S3, cutting through both ends of the occlusal pile 30;

[0067] S4, implanting one end of the first connecting member 1 into one side of the occlusal pile 30, and exposing the other end of the first connecting member 1 from the occlusal pile 30;

[0068] S5, solidifying and connecting the other end of the first connecting member 1, the side wall of the bite pile 30 and one end of the second connecting member 2 through concrete to form an anchoring module 4;

[0069] S6, implanting one end of the third connecting member 3 on the top surface of the occlusal pile 30, and exposing the other end of the third connecting member 3 from the occlusal pile 30;

[0070] S7 . The lifting device 6 connects the other end of the second connecting member 2 and the other end of the third connecting member 3 respectively, and lifts the bite pile 30 .

[0071] In this embodiment, the interlocking pile 30 includes a reinforced concrete pile 10 and a plain concrete pile 20, which interlock with each other at the connection point and are a part selected from the pile wall. The number of the reinforced concrete pile 10 and the plain concrete pile 20 can be determined according to various factors such as the lifting equipment, the number of the first connecting member, the second connecting member and the third connecting member, and the pile wall.

[0072] like Figure 1-Figure 5 As shown, in the pile pulling method, in step S1, both sides of the pile wall are blocked to reduce the resistance during pile pulling; in step S2, the number of the bite piles 30 including reinforced concrete piles 10 and plain concrete piles 20 is designed according to the bearing capacity that can be provided by the lifting equipment 6 and the cross-sectional area of ​​the embedded reinforcement, the deadweight of the pile wall, and the friction resistance around the pile, so that the piles can be pulled out successfully; in step S3, the bite pile 30 part is separated from the whole pile wall by cutting, so as to reduce the pull-out force of the bite pile 30 part; in step S4, the first connecting member 1 is implanted into the bite pile 30, so that one end of the first connecting member 1 is firmly fixed on the bite pile 30, and the other end of the first connecting member 1 is used for solid connection with the anchor module 4, so that the pull-out force is transmitted to the bite pile 30 when the anchor module 4 is pulled by the second connecting member 2; in step S5, the first connecting member 1 and the second connecting member are connected by concrete. 2 and the anchoring module 4 are solidified and connected firmly, and the anchoring module 4 and the bite pile 30 form a whole. When the second connecting member 2 is lifted, the anchoring module 4 transmits force to the bite pile 30, and then the reinforced concrete pile 10 and the plain concrete pile 20 are pulled out as a whole; in step S6, the third connecting member 3 is implanted on the top surface of the bite pile 30 to form a connection point, which is convenient for the lifting equipment 6 to connect, and then traction is applied from the top surface of the bite pile 30; in step S6, when the lifting equipment 6 lifts, force is applied to the bite pile 30 at the same time through the anchoring module 4 on one side of the bite pile 30 and the third connecting member 3 on the top surface, so as to cleverly realize the pulling out of multiple reinforced concrete piles 10 and plain concrete piles 20 at one time. Compared with the traditional pile pulling out method of cutting single or double piles multiple times to pull out, this pile pulling method breaks through the traditional mindset and forms the effect of pulling out a part of the bite pile 30 as a whole. Because the anchoring module 4 is designed before the piles are pulled out, the anchoring module 4 connects the multiple reinforced concrete piles 10 and the plain concrete piles 20 together, which can effectively prevent the piles from sliding during the pile pulling. It is particularly suitable for the removal of a large pile wall in an open space. The overall structure is reliable and stable, and the safety is greatly improved. A lot of cost and construction time can be saved, and the efficiency of pulling out the interlocking piles 30 is improved.

[0073] In one embodiment, 3 to 5 anchor holes are set on the top surface of the bite pile 30, and 5 to 10 anchor holes are set on the side of the bite pile 30, among which no less than half of the total anchor holes need to be set in the reinforced concrete pile 10 to improve the success rate of extraction.

[0074] In step S4 and step S6, drilling is required when planting reinforcement. The crawler drilling rig D150 is used for drilling. The single-unit power is 75kW. It is also equipped with a 15m 3 , 1.3MPa air compressor, the air compressor power is 135kW, the working efficiency is 60m / 8hr. After drilling, use clean water to clean the dry slurry and drain the water; before implanting the first connecting member 1 and the third connecting member 3, use a plug to block the hole to prevent foreign matter from entering the hole. If the bite pile 30 is still used as an engineering pile, in order to avoid damage to the pile body by a crawler drill, a geological drill can be used to drill the hole.

[0075] Preferably, after the bite pile 30 is pulled out, the exposed part of the pulled out bite pile 30 needs to be crushed. A plurality of static blasting holes can be drilled on the top surface of the bite pile 30, crushing agents are poured into the blasting holes, and the openings of the static blasting holes are blocked with fast-hardening cement for 12-18 hours. The pile body is then crushed by crushing equipment, and combined with concrete cutting and gas cutting of steel bars, the concrete can be quickly decomposed to realize the upper demolition of the pile, so that the pile extraction project can be smoothly transferred to the next process and the next pile.

[0076] In this embodiment, in step S2, both ends of the snap pile 30 are plain concrete piles 20. The selected snap pile 30 has both ends of plain concrete piles 20, which is convenient for quick cutting to quickly separate the snap pile 30 from the pile wall at the upper end, so as to reduce the pull-out force.

[0077] In this embodiment, in step S4, a reinforcing bar hole is opened on one side of the bite pile 30, and the reinforcing bar hole is extended along the thickness direction of the bite pile 30. One end of the first connecting member 1 is inserted into the reinforcing bar hole and connected to the bite pile 30 by curing the reinforcing bar glue. By implanting the first connecting member 1 on the side of the bite pile 30, it is convenient to increase the connection point on the side of the bite pile 30. When lifting, force is applied to the side of the bite pile 30 to pull out the bite pile 30.

[0078] Preferably, the number of implanted first connecting members 1 is multiple, and the multiple first connecting members 1 are arranged at intervals along the length direction of the occlusal pile 30 to increase the number of connection points, thereby increasing the pull-out force that can be sustained.

[0079] In this embodiment, the rebar embedding glue is injected into the rebar embedding hole multiple times, and the first connecting member 1 is pulled each time the rebar embedding glue is injected. The rebar embedding glue is injected into the rebar embedding hole under pressure, and is injected in batches. After the previous rebar embedding glue is solidified and reaches the set strength, the injection is continued until the rebar embedding glue exceeds the rebar embedding hole surface. When injecting the glue, the first connecting member 1 can be appropriately pulled to exhaust air, so as to ensure that the rebar embedding hole is filled with the rebar embedding glue and improve the bonding effect.

[0080] In this embodiment, step S5 also includes step S51: setting up a mold 7 on the side of the interlocking pile 30 where the first connector 1 is planted, for making the anchor module 4. When making the anchor module 4, concrete slurry is poured into the mold 7 by vibration grouting. The concrete slurry is a slurry mixed with PO52.5 cement, cement slurry pore grouting agent and water. The water-cement ratio of the concrete slurry is 0.35-0.45. A mortar mixer and a grouting pump are used for vibration grouting. The mold 7 of this embodiment is made of wood and bamboo plywood nailed together, and the lower end support is fixed on the pile wall.

[0081] Preferably, before manufacturing the anchoring module 4 , dust removal is performed once at the location where the anchoring module 4 is manufactured to ensure tight adhesion between the poured concrete slurry and the bite pile 30 .

[0082] Preferably, the anchoring module 4 is disposed at one third of the distance from the bottom of the exposed portion of the occlusal pile 30 , and the implantation depth of the first connecting member 1 is not less than one third of the cross-sectional thickness of the occlusal pile 30 .

[0083] In this embodiment, in step S6, the second connecting member 2 is implanted on the top surface of the reinforced concrete pile 10 in the occlusal pile 30. The second connecting member 2 is implanted on the top surface of the reinforced concrete pile 10, and the connection is firmer than that of the plain concrete pile 20. When being pulled out, the reinforced concrete pile 10 can withstand a larger pull-out force and is not easy to collapse.

[0084] In this embodiment, there are multiple second connecting members 2, which are spaced apart along the length direction of the bite pile 30, so as to evenly apply force to the bite pile 30 and make it easier to pull out the bite pile 30.

[0085] In this embodiment, in step S7, a working platform 5 is provided on the pile wall near the interlocking pile 30 or on the surrounding soil of the interlocking pile 30, and the lifting device 6 is set up on the working platform 5. By providing the working platform 5, the lifting device 6 is installed on the working platform 5. The working platform 5 can withstand a large supporting force, and the lifting device 6 will not fall down during lifting, which can improve safety.

[0086] Preferably, the working platform 5 is any one of a reinforced concrete platform, a steel frame platform or a composite structure platform. The working platform 5 can also be a caisson platform, which is suitable for continuous pulling out of the interlocking piles 30 that are located below the ground surface as a whole, and the overall structure is simple and reliable.

[0087] Preferably, the lifting device 6 includes a through-hole jack 61, a crane or a winch arranged on the working platform 5, the through-hole jack 61 is fixed on the reinforced concrete platform, the steel structure frame platform or the combined structure platform through the reaction frame 62, and the crane or the winch is arranged on the reinforced concrete platform, the steel structure frame platform or the combined structure platform. During lifting, the through-hole jack 61, the crane or the winch continuously tensions the top surface of the anchor module 4 and the bite pile 30 through the second connecting member 2 and the third connecting member 3 to continuously pull up the bite pile 30 to be pulled up. By setting up a reinforced concrete platform, a steel structure frame platform or a combined structure platform, the pile wall partially located above the ground or entirely located below the ground can be continuously pulled up, and the overall structure is simple and reliable.

[0088] In this embodiment, in step S7, the anchor cable 63 of the lifting device 6 is connected to the second connecting member 2 and the third connecting member 3 respectively, and then the lifting and traction begins. The first connecting member, the second connecting member and the third connecting member are usually called anchor steel bars or anchor rods.

[0089] In this embodiment, the following steps are further included after step S7:

[0090] S8, if the pile extraction by the lifting device 6 fails, the resistance around the occlusal pile 30 is eliminated again or the number of the second connecting members 2 and the third connecting members 3 is increased, and step S7 is repeated. By eliminating the resistance again, the upper adhesion force on the occlusal pile 30 is reduced. By increasing the number of the second connecting members 2 and the third connecting members 3, the connection points are increased, and the extraction force is increased.

[0091] In this embodiment, the first connecting member 1, the second connecting member 2, and the third connecting member 3 are respectively made of any one or more of metal hard materials, metal soft materials, non-metal hard materials, or non-metal soft materials. Metal hard materials include bonded steel strands, prestressed steel strands, prestressed steel strands, high-strength steel wires, high-strength steel wire ropes, or high-strength steel bars, etc. Non-metal hard or soft materials include fibers, plastics, or nylon, etc.

[0092] This embodiment also discloses a pile pulling system, which is used in the pile pulling method as described above, and includes a lifting device 6, a mold 7 for making an anchoring module 4, and a working platform 5. The lifting device 6 is used to provide a pulling force during lifting, the mold 7 is used to quickly make the anchoring module 4, and the working platform 5 is used to install the lifting device 6.

[0093] In a specific pile pulling embodiment, the total length of the wall of the interlocking pile 30 to be pulled out is 24m, the thickness of the pile wall is 4.5m, and the interlocking pile 30 needs to be lifted to a height of 6-7m, accounting for 25% of the total length of the wall of the interlocking pile 30 to be pulled out. After calculation, the design load of the pile pulling force is 24000kN, and the verification load is 30000kN.

[0094] Thus, a total of 12 bundles of CPS15A-12 shear-dispersing anchor cables 63 are selected as the materials for the anchor bars and anchor cables 63. Each bundle of CPS15A-14 shear-dispersing anchor cables 63 uses 14-φ15.24 high-strength, low-relaxation steel strands with a tensile strength of 1860 MPa.

[0095] The lifting device 6 uses a through-hole jack 61, and 10 5000kN through-hole jacks 61 are selected as lifting power equipment. Considering the efficiency of 0.8, the total lifting capacity reaches 40000kN.

[0096] Before laying out the wires, first install the reaction frame 62 on the working platform 5, and then determine the position of the anchor holes according to the layout of the reaction frame 62. The eight anchor holes on the top surface of the occlusal pile 30 are semicircularly distributed on two semicircular arcs with a circumference of 900 cm, and the diameter of the anchor holes is 150 mm. The eight anchor holes on the side of the occlusal pile 30 are semicircularly distributed on two semicircular arcs with a circumference of 900 cm.

[0097] Since the pile is affected by the connection of retaining wall, canal wall, etc., crawler drilling rig D150 can be used to eliminate the connection and achieve the purpose of cutting the interlocking pile 30 from other structures. When eliminating the connection, the drilling range is appropriately enlarged and deepened to prevent large hole expansion and collapse in the range below the strong connection. In order to increase the construction speed, the connection elimination and the reinforcement hole are carried out at the same time.

[0098] The friction between the pile wall and the soil layer is eliminated by drilling a certain number of holes around the pile and flushing water appropriately. A 50-diameter PVC flower pipe is laid in the hole to prevent the hole from collapsing and to lift the pile wall to refill cement slurry, reinforce the soil around the pile, and restore the function of the pile.

[0099] When pulling out piles, the estimated lifting force is divided into 10 levels, and each level is observed for 10 minutes. The data is measured once a minute to analyze the changes in the displacement of the pile top over time and with load. At the same time, the surface settlement, structural stress and deformation are monitored. The estimated lifting force is 24000kN, and the specific load levels are 2400kN, 4800kN, 7200kN, until the starting load.

[0100] Due to the rapid unloading of the soil caused by the large-scale pullout of the pile wall, cement slurry re-injection is required to restore the function of the pile and reduce the adverse effects of pile extraction on surrounding buildings. Determine the timing and pressure of re-injection based on the observation results of building settlement. For the safety of the building, re-injection should be done as early as possible. Excessive re-injection pressure can easily cause the surrounding buildings to rise. The range of this resistance reduction is relatively small, and low-pressure re-injection of no more than 1MPa is used. Use grouting equipment from bottom to top, and the excess water around the pile will be discharged to the surface along the PVC flower pipe. The slurry penetrates into the soil around the pile, connecting the soil and the remaining pile body of the pile as a whole.

[0101] In the description of this article, it is necessary to understand that the terms "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside", etc., indicating the orientation or position relationship, are based on the orientation or position relationship shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the present invention.

[0102] Although the specific embodiments of the present invention are described above, it should be understood by those skilled in the art that this is only for illustration and the protection scope of the present invention is defined by the appended claims. Those skilled in the art may make various changes or modifications to these embodiments without departing from the principles and essence of the present invention, but these changes and modifications all fall within the protection scope of the present invention.

Claims

1. A pile extraction method, applied to a pile wall formed by a plurality of reinforced concrete piles and plain concrete piles interlocked with each other, characterized in that: The following steps are involved: S1, eliminating the obstruction on both sides of the pile wall; S2, selecting a section of interlocking piles containing the reinforced concrete piles and plain concrete piles from the pile wall; S3, performing through-cutting on both ends of the occlusal pile; S4, implanting one end of the first connecting member into one side of the occlusal post, and exposing the other end of the first connecting member from the occlusal post; S5, solidifying and connecting the other end of the first connecting member, the side wall of the bite pile and one end of the second connecting member through concrete to form an anchoring module; S6, implanting one end of a third connecting member on the top surface of the occlusal post, and exposing the other end of the third connecting member from the occlusal post; S7. A lifting device is respectively connected to the other end of the second connecting member and the other end of the third connecting member, and lifts the bite pile.

2. The pile pulling method according to claim 1, characterized in that: In step S2, both ends of the interlocking pile are plain concrete piles.

3. The pile pulling method according to claim 1, characterized in that: In step S4, a reinforcing bar hole is opened on one side of the occlusal pile, the reinforcing bar hole is extended along the thickness direction of the occlusal pile, one end of the first connecting member is inserted into the reinforcing bar hole and connected to the occlusal pile by curing with reinforcing bar glue; There are multiple implanted first connecting members, and the multiple first connecting members are arranged at intervals along the length direction of the occlusal post.

4. The pile extraction method according to claim 3, characterized in that: The rebar embedding glue is injected into the rebar embedding hole multiple times, and the first connecting piece is pulled each time the rebar embedding glue is injected.

5. The pile pulling method according to claim 1, characterized in that: Step S5 also includes step S51: setting up a mold on the side of the occlusal pile where the first connecting member is planted, for making an anchoring module.

6. The pile pulling method according to claim 1, characterized in that: In step S6, the second connecting member is implanted on the top surface of the reinforced concrete pile in the occlusal pile; There are multiple second connecting members, and the multiple second connecting members are arranged at intervals along the length direction of the engaging pile.

7. The pile extraction method according to claim 1, characterized in that: In step S7, a working platform is provided on the pile wall near the interlocking pile or on the soil around the interlocking pile, and the lifting equipment is erected on the working platform.

8. The pile extraction method according to claim 1, characterized in that: After step S7, the method further includes the following steps: S8. If the pile extraction by the lifting device fails, the surrounding side of the interlocking pile is again blocked or the number of the second connecting members and the third connecting members is increased, and step S7 is repeated.

9. The pile pulling method according to claim 1, characterized in that: The first connecting member, the second connecting member, and the third connecting member are respectively made of any one or more of metal hard materials, metal soft materials, non-metal hard materials, or non-metal soft materials.

10. A pile extraction system, characterized in that: It is used in the pile pulling method according to any one of claims 1 to 9, wherein the pile pulling system comprises a lifting device, a mold for making an anchoring module, and a working platform.