Construction method of steel-concrete combined truss girder with in-situ cast-in-situ integral beam falling

Through modular prefabrication, intelligent assembly, intelligent casting and temperature control maintenance technologies, combined with automation equipment and monitoring systems, the problems of low construction efficiency and accuracy in the existing technology are solved, and efficient and accurate steel-concrete combined truss beam construction is achieved. Reduced construction time and cost.

CN118911423APending Publication Date: 2024-11-08CHINA RAILWAY NO 3 GRP CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411147100.7
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-21
Publication Date
2024-11-08

AI Technical Summary

Technical Problem

During the construction of existing cast-in-place integrated steel-concrete truss beams, the degree of standardization of manual inspection components is low, resulting in low working efficiency and accuracy, which increases construction time and cost.

Method used

Modular prefabrication technology, intelligent assembly, intelligent casting technology, temperature control maintenance technology and automated monitoring methods are adopted, combined with automation equipment and intelligent robots, to improve the standardization of components, achieve precision assembly and efficient casting, reduce on-site operation volume, and improve construction efficiency and precision.

Benefits of technology

Through modular prefabrication and intelligent assembly, intelligent casting and temperature-controlled maintenance technologies ensure concrete quality, automated monitoring and environmental protection measures, significantly improve construction efficiency and accuracy, and reduce construction time and cost.

✦ Generated by Eureka AI based on patent content.
Patent Text Reader

Abstract

A steel-concrete combined truss girder construction method for in-situ cast-in-situ integral beam falling comprises the following steps of a construction preparation stage, a steel structure installation stage, a concrete pouring stage, a beam falling stage and a completion and acceptance stage, modular prefabrication is adopted, in the steel truss prefabrication process, the modular prefabrication technology is adopted, and the steel structure is prefabricated. A large number of automation devices and intelligent robots are introduced to improve the standardization degree of components and reduce the field operation amount, the robot technology and the automation devices are adopted for precise assembly, through cooperation of a plurality of mechanical arms, taking and assembly of parts can be achieved, and the working efficiency and precision can be improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of truss beam construction, in particular to a construction method of an in-situ cast-in-place integrally dropped steel-concrete combined truss beam. Background Art

[0002] The construction method of cast-in-situ integrally dropped steel-concrete truss beam is a relatively complex construction technology, which combines the strength of steel structure and the rigidity of concrete structure and is suitable for bridge construction.

[0003] During the construction process of existing in-situ cast-in-place integrally dropped steel-concrete combined truss beams, the degree of component standardization is mostly tested manually, resulting in a high workload on site and low work efficiency and precision, which will increase construction time and cost. Summary of the invention

[0004] 1. Technical issues to be solved

[0005] In view of the deficiencies in the prior art, the present invention provides a method for constructing an in-situ cast-in-place integrally dropped steel-concrete combined truss beam.

[0006] (II) Technical solution

[0007] To achieve the above object, the present invention provides the following technical solution: a construction method of an in-situ cast-in-place integrally dropped steel-concrete combined truss beam, comprising the following steps:

[0008] Step 1: Construction preparation stage;

[0009] Step 2: Steel structure installation stage;

[0010] Step 3: Concrete pouring stage;

[0011] Step 4: Beam drop stage;

[0012] Step 5: Completion and acceptance stage;

[0013] The first step also includes the following steps:

[0014] 1) Optimize design;

[0015] 2) Accurate measurement;

[0016] 3) Material selection;

[0017] The second step also includes the following steps:

[0018] 1) Modular prefabrication;

[0019] 2) Intelligent assembly;

[0020] 3) Temporary support optimization;

[0021] The third step also includes the following steps:

[0022] 1) Efficient template system;

[0023] 2) Intelligent pouring technology;

[0024] 3) Temperature control maintenance;

[0025] The fourth step also includes the following steps:

[0026] 1) Automated monitoring;

[0027] 2) Drop the beams in steps;

[0028] 3) Environmental protection measures;

[0029] The fifth step also includes the following steps:

[0030] 1) Nondestructive testing;

[0031] 2) Intelligent management;

[0032] 3) Environmental protection measures.

[0033] Further, the present invention is improved in that the construction preparation stage further includes the following steps:

[0034] 1) Drawing design and review;

[0035] 2) On-site investigation.

[0036] Further, the present invention is improved in that the steel structure installation stage further includes the following steps:

[0037] 1) Basic treatment;

[0038] 2) Prefabrication of steel trusses;

[0039] 3) On-site hoisting;

[0040] 4) Node welding.

[0041] Further, the present invention is improved in that the concrete pouring stage further comprises the following steps:

[0042] 1) Template construction;

[0043] 2) Steel bar binding;

[0044] 3) Concrete pouring.

[0045] Further, the present invention is improved in that the beam dropping stage further comprises the following steps:

[0046] 1) Remove the support system;

[0047] 2) Inspection and adjustment.

[0048] Further, the present invention is improved in that the completion and acceptance stage further includes the following steps:

[0049] 1) Surface treatment.

[0050] (III) Beneficial effects

[0051] Compared with the prior art, the present invention provides a method for constructing an in-situ cast-in-place integrally dropped steel-concrete combined truss beam, which has the following beneficial effects:

[0052] The construction method of the steel-concrete combined truss beam with cast-in-situ integral beams adopts modular prefabrication. In the process of steel truss prefabrication, modular prefabrication technology is adopted, and a large number of automated equipment and intelligent robots are introduced to improve the standardization of components and reduce the amount of on-site work. Robot technology and automated equipment are used for precise assembly. Through the cooperation of multiple manipulators, parts can be taken and assembled, which can improve work efficiency and accuracy.

[0053] The intelligent pouring system is used to control the pouring speed and quality of concrete, and modern digital control technology is adopted to realize automatic operation. It can be remotely monitored and controlled through PLC controller and touch screen to avoid bubbles and stratification.

[0054] Advanced temperature control and curing technology is used to ensure that concrete solidifies under optimal conditions and speed up construction progress. Concrete temperature control and curing technology refers to the control of environmental temperature and humidity during the curing period after concrete pouring to ensure that concrete can harden under suitable conditions to achieve the expected strength and durability. DETAILED DESCRIPTION

[0055] The following will be combined with the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without making creative work are within the scope of protection of the present invention.

[0056] The invention discloses a method for constructing an in-situ cast-in-place integrally dropped steel-concrete combined truss beam, comprising the following steps:

[0057] Step 1: Construction preparation stage;

[0058] Step 2: Steel structure installation stage;

[0059] Step 3: Concrete pouring stage;

[0060] Step 4: Beam drop stage;

[0061] Step 5: Completion and acceptance stage;

[0062] The first step also includes the following steps:

[0063] 1) Optimized design: First, use advanced computing software to optimize the structure, including 2D plane design and 3D three-dimensional structure, so that construction workers can see the three-dimensional structure of the construction environment more intuitively, which can reduce material consumption and construction difficulty;

[0064] 2) Accurate measurement: Use measuring tools to detect designated locations and workpieces during the construction process. Measuring tools include calipers, levels, etc., to improve construction accuracy and reduce errors;

[0065] 3) Material selection: choose high-performance steel and concrete, such as high-strength steel and self-compacting concrete, to improve structural performance;

[0066] The second step also includes the following steps:

[0067] 1) Modular prefabrication: In the process of steel truss prefabrication, modular prefabrication technology is adopted, and a large number of automated equipment and intelligent robots are used to improve the standardization of components and reduce the amount of on-site work;

[0068] 2) Intelligent assembly, using robot technology and automated equipment for precision assembly. Through the cooperation of multiple manipulators, parts can be picked up and assembled, which can improve work efficiency and accuracy;

[0069] 3) Temporary support optimization, design a more stable and flexible temporary support system, display the 3D framework through smart devices, facilitate quick installation and disassembly, reduce construction time and cost, and facilitate direct viewing by construction personnel;

[0070] The third step also includes the following steps:

[0071] 1) Efficient formwork system, using a quick-disassembly and quick-installation formwork system to reduce the time of formwork installation and disassembly, making the formwork more efficient during construction;

[0072] 2) Intelligent pouring technology: using intelligent pouring system to control the pouring speed and quality of concrete, using modern digital control technology to achieve automated operation, and can be remotely monitored and controlled through PLC controller and touch screen to avoid bubbles and stratification;

[0073] 3) Temperature control maintenance: Use advanced temperature control maintenance technology to ensure that concrete solidifies under optimal conditions and speed up construction progress. Concrete temperature control maintenance technology refers to the control of the temperature and humidity of the environment during the maintenance period after concrete pouring to ensure that the concrete can harden under appropriate conditions to achieve the expected strength and durability. Concrete temperature control maintenance technology usually consists of the following key equipment:

[0074] 1. Temperature and humidity control system:

[0075] Constant temperature host: responsible for controlling the temperature in the curing room, with functions such as cooling, heating, and dehumidification; temperature and humidity sensor: monitors the temperature and humidity in the curing room and transmits the data to the control system;

[0076] Industrial ultrasonic humidifier: when the humidity is lower than the set value, it increases the indoor humidity by spraying;

[0077] System control box: built-in intelligent control instrument, used to receive sensor data and control the operation of humidification, heating or refrigeration equipment;

[0078] Large-screen touch color LCD display temperature controller: used to display real-time temperature and humidity data in the maintenance room, and can set parameters;

[0079] 2. Heating and cooling system:

[0080] Heating water tank or heating pipe: used to heat the air or water in the curing room to maintain the appropriate temperature;

[0081] Refrigeration and air conditioning system: used to reduce the temperature in the curing room in summer or high temperature environment;

[0082] Air supply and return air system: ensure indoor air circulation and uniform temperature and humidity distribution;

[0083] 3. Humidification system:

[0084] Humidifier: Increase indoor humidity through spray or other means to maintain a high humidity environment;

[0085] Stainless steel heating water tank: used to provide hot water required for humidification.

[0086] The fourth step also includes the following steps:

[0087] 1) Automated monitoring: An automated monitoring system is set up to monitor the deformation and stress changes of the structure during construction in real time to ensure safety;

[0088] 2) Step-by-step beam drop: The step-by-step beam drop technology can gradually release the support system and reduce structural stress concentration;

[0089] 3) Environmental protection measures: Use computer simulation technology to predict various situations during the beam dropping process, and use intelligent display equipment to display the screen to make countermeasures in advance;

[0090] The fifth step also includes the following steps:

[0091] 1) Non-destructive testing: using advanced non-destructive testing technology to ensure the integrity and safety of the structure. Structural non-destructive testing technology (NDT) refers to the technology of detecting the internal and surface defects, state and performance of materials or structures by physical or chemical methods without destroying or affecting the performance of the object being tested. Non-destructive testing technology is very important in industrial production and scientific research. It can be used to ensure the safety, reliability and durability of the structure.

[0092] 2) Intelligent management: Establish an intelligent management system and achieve full monitoring and data recording of the construction process through the cooperation of intelligent monitoring equipment;

[0093] 3) Environmental protection measures: take effective measures to reduce construction noise and environmental pollution and improve the sustainability of construction.

[0094] Furthermore, the construction preparation stage also includes the following steps:

[0095] 1) Drawing design and review: complete the structural design of the truss beam according to the design requirements of the bridge and pass the review by a professional organization;

[0096] 2) On-site investigation: determine the specific conditions of the construction area through various intelligent detection equipment, including geological, hydrological and other information.

[0097] Furthermore, the steel structure installation stage also includes the following steps:

[0098] 1) Foundation treatment: carry out foundation construction of piers and abutments according to design requirements;

[0099] 2) Prefabrication of steel trusses;

[0100] 3) On-site hoisting: Use a large crane to hoist the truss unit to the predetermined position, temporarily fix it and adjust it to the designed elevation;

[0101] 4) Node welding: Welding and reinforcement of truss nodes to ensure the integrity and stability of the structure. Welding by welding robots can reduce labor input.

[0102] Furthermore, the concrete pouring stage also includes the following steps:

[0103] 1) Formwork construction: build the formwork system on the installed steel trusses to ensure that the formwork is stable and easy to remove;

[0104] 2) Steel bar binding;

[0105] 3) Concrete pouring.

[0106] Furthermore, the beam dropping stage also includes the following steps:

[0107] 1) Remove the support system. After the concrete reaches sufficient strength, gradually remove the temporary support system used to support the truss.

[0108] 2) Inspection and adjustment.

[0109] Furthermore, the completion and acceptance stage also includes the following steps:

[0110] 1) Surface treatment: Anti-corrosion treatment of the truss beam, such as painting, etc. The workpiece can be treated with anti-corrosion glue through designated coating equipment.

[0111] In the description of this article, it should be noted that relational terms such as first and second, etc. are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprises" or any other variations thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device.

[0112] While the embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that many changes, modifications, substitutions and variations can be made to the embodiments without departing from the principles and spirit of the invention.

Claims

1. A method for constructing an in-situ cast-in-place integrally dropped steel-concrete combined truss beam, characterized in that: It includes the following steps: Step 1: Construction preparation stage; Step 2: Steel structure installation stage; Step 3: Concrete pouring stage; Step 4: Beam drop stage; Step 5: Completion and acceptance stage; The first step also includes the following steps: 1) Optimize design; 2) Accurate measurement; 3) Material selection; The second step also includes the following steps: 1) Modular prefabrication; 2) Intelligent assembly; 3) Temporary support optimization; The third step also includes the following steps: 1) Efficient template system; 2) Intelligent pouring technology; 3) Temperature control maintenance; The fourth step also includes the following steps: 1) Automated monitoring; 2) Drop the beams in steps; 3) Environmental protection measures; The fifth step also includes the following steps: 1) Nondestructive testing; 2) Intelligent management; 3) Environmental protection measures.

2. The method for constructing an in-situ cast-in-situ integrally dropped steel-concrete combined truss beam according to claim 1, characterized in that: The construction preparation stage also includes the following steps: 1) Drawing design and review; 2) On-site investigation.

3. The method for constructing an in-situ cast-in-situ integrally dropped steel-concrete combined truss beam according to claim 2, characterized in that: The steel structure installation phase also includes the following steps: 1) Basic treatment; 2) Prefabrication of steel trusses; 3) On-site hoisting; 4) Node welding.

4. The method for constructing an in-situ cast-in-situ integrally dropped steel-concrete combined truss beam according to claim 3, characterized in that: The concrete pouring stage also includes the following steps: 1) Template construction; 2) Steel bar binding; 3) Concrete pouring.

5. The method for constructing an in-situ cast-in-place integrally dropped steel-concrete combined truss beam according to claim 4, characterized in that: The beam drop stage also includes the following steps: 1) Remove the support system; 2) Inspection and adjustment.

6. The method for constructing an in-situ cast-in-situ integrally dropped steel-concrete combined truss beam according to claim 5, characterized in that: The completion and acceptance phase also includes the following steps: 1) Surface treatment.