Straddle-type tunnel drill carriage for tunneling tunnel of shield tunneling machine and construction method of straddle-type tunnel drill carriage

By designing a straddle-type tunnel drilling vehicle for shield machine excavation tunnels, traditional equipment is solved inefficient and inability to drill holes in rocky environments, efficient drilling and pre-drawing of gas are achieved, and tunnel boring and tunnel boring are improved. Comprehensive efficiency and safety of transportation.

CN118911595AActive Publication Date: 2024-11-08JIANGSU ZHONGGUI HEAVY IND CO LTD
View PDF 9 Cites 0 Cited by

Patent Information

Application Number
CN202411372162.8
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-29
Publication Date
2024-11-08
Estimated Expiration
2044-09-29

AI Technical Summary

Technical Problem

During the excavation of coal mine tunnels, traditional equipment is inefficient and cannot effectively drill holes on narrow working surfaces, which affects the safety of the tunnels, especially in environments with lots of rocks.

Method used

Design a straddle-style tunnel drill for shield machine tunneling tunnels, including chassis, track assembly, transverse track, drill assembly and box structure, allowing drill assembly to move on the track and through a specific space for convenience The belt conveyor and monorail crane pass through, enabling drilling and pre-drawing of gas.

Benefits of technology

The integration of drilling and transportation has been achieved, the efficiency and safety of excavation have been improved, the efficient construction of the tunnels and the smooth transportation of materials and personnel have been ensured, and the construction efficiency has been improved.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118911595A_ABST
    Figure CN118911595A_ABST
Patent Text Reader

Abstract

The invention aims to disclose a straddle type tunnel drill carriage for tunneling a tunnel by a shield tunneling machine and a construction method, and relates to the technical field of coal mine tunnel drilling, the straddle type tunnel drill carriage comprises a chassis, and a first track assembly and a second track assembly which are arranged on two sides below the chassis; a transverse rail and a drilling assembly moving along the transverse rail are arranged at the end of the chassis. The drilling assembly comprises an operation table, a swing mechanism and a drill arm. A first space between the first crawler belt assembly and the second crawler belt assembly allows a belt conveyor to pass through; a first box body and a second box body are arranged on the two sides of the upper portion of the chassis respectively, and a second space between the first box body and the second box body allows a monorail hoist arranged at the top of a roadway to pass through. Materials and personnel are transported to the roadway through the monorail hoist, and the bestriding type underground drill carriage bestrides the belt conveyor and drills holes, so that high-efficiency tunneling is realized.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of coal mine tunnel drilling, and in particular to a straddle-type tunnel drilling vehicle used for tunneling a tunnel with a shield machine and a construction method. Background Art

[0002] For coal mines with more rocks, the traditional excavation equipment has low excavation efficiency during tunnel excavation. In addition, how to drill holes and pre-extract gas in time during the excavation process is related to the safety of the tunnel. The existing drilling equipment takes up a large space and cannot drill holes normally for narrow working surfaces.

[0003] In view of this, there is an urgent need to develop a straddle-type tunnel drilling vehicle and a construction method for tunneling with a shield machine to overcome the above-mentioned defects. Summary of the invention

[0004] The purpose of the present invention is to disclose a straddle-type tunnel drilling vehicle and a construction method for tunneling a tunnel with a shield machine.

[0005] The first object of the present invention is to provide a straddle-type tunnel drilling vehicle for tunneling with a shield machine.

[0006] The second object of the present invention is to provide a comprehensive construction method for coal mine tunnel excavation, drilling and transportation.

[0007] To achieve the above first invention objective, the present invention provides a straddle-type tunnel drilling vehicle for tunneling a tunnel with a shield machine, comprising a chassis and a first crawler assembly and a second crawler assembly arranged on both sides below the chassis; A transverse track and a drilling assembly moving along the transverse track are arranged at the end of the chassis; The drilling assembly includes an operating table, a slewing mechanism and a drilling arm; A first space between the first crawler assembly and the second crawler assembly allows a conveyor belt to pass through; A first box and a second box are respectively arranged on both sides above the chassis. The second space between the first box and the second box allows a monorail crane disposed on the top of the tunnel to pass through.

[0008] Preferably, the first track assembly includes a first track and a first track frame.

[0009] Preferably, a first lifting cylinder and first lifting slide columns respectively arranged on both sides of the first lifting cylinder are arranged between the first crawler support and the chassis.

[0010] Preferably, the second track assembly includes a second track and a second track frame.

[0011] Preferably, a second lifting cylinder and second lifting slide columns respectively arranged on both sides of the second lifting cylinder are arranged between the second crawler support and the chassis.

[0012] Preferably, a translation cylinder is arranged on one side of the transverse track, and the translation cylinder drives the drilling assembly to move along the transverse track with the chassis as a fulcrum.

[0013] Preferably, a power assembly is disposed in the first housing, and an oil tank is disposed in the second housing; The translation cylinder drives the drilling assembly to the rear of the second box and avoids the second space.

[0014] Preferably, when the drilling assembly is located at the rear of the second box, the slewing mechanism drives the drill arm to be in a vertical state.

[0015] Preferably, the slewing mechanism is connected to the drill arm via an L-shaped support frame; A swing angle oil cylinder is arranged on the L-shaped support frame, and the swing angle oil cylinder drives the drill arm to swing forward and backward; A number of drill rods are stored at the bottom of the second space.

[0016] Based on the same inventive principle, in order to achieve the above second inventive object, the present invention provides a coal mine tunnel excavation, drilling and transportation integrated construction method, comprising the following steps: Step S1: Excavating and forming a coal mine tunnel by a shield machine; Step S2: installing a monorail crane at the top of the coal mine tunnel, installing a belt conveyor at the bottom of the coal mine tunnel and transporting coal; Step S3: The straddle-type tunnel drilling vehicle for tunneling with a shield machine according to the first invention straddles the belt conveyor and performs drilling.

[0017] Compared with the prior art, the present invention has the following beneficial effects: Through the present invention, the integration of excavation, drilling and transportation is realized, that is, while the shield machine is used for excavation, the coal is transported outward through the belt conveyor, the materials and personnel are transported to the tunnel by the monorail crane, and the straddle-type tunnel drilling vehicle straddles the belt conveyor and drills holes, and pre-gas is extracted after drilling, thereby achieving high-efficiency excavation and ensuring safety; the first space of the present invention allows the belt conveyor to pass through, and the second space allows the monorail crane set at the top of the tunnel to pass through, so that excavation, coal transportation, material transportation and drilling are coordinated with each other, and the comprehensive construction efficiency is greatly improved. BRIEF DESCRIPTION OF THE DRAWINGS

[0018] Figure 1 The present invention is a schematic diagram of the three-dimensional structure of a straddle-type tunnel drilling vehicle used for tunneling a tunnel with a shield machine.

[0019] Figure 2It is a front view schematic diagram of a straddle-type tunnel drilling vehicle used for tunneling a tunnel with a shield machine according to the present invention.

[0020] Figure 3 It is a schematic diagram of the three-dimensional structure of the drilling assembly of the present invention.

[0021] Figure 4 It is a side view schematic diagram of the first track assembly or the second track assembly of the present invention.

[0022] Figure 5 The present invention is a schematic diagram of the three-dimensional structure of a straddle-type tunnel drilling vehicle used for tunneling a tunnel with a shield machine.

[0023] Figure 6 The present invention is a flow chart of the comprehensive construction method for coal mine tunnel excavation, drilling and transportation.

[0024] Among them, 1. chassis; 11. first crawler assembly; 111. first crawler; 112. first crawler bracket; 113. first lifting cylinder; 114. first lifting slide; 12. second crawler assembly; 121. second crawler; 122. second crawler bracket; 123. second lifting cylinder; 124. second lifting slide; 13. transverse track; 14. first box; 15. second box; 2. drilling assembly; 21. operating table; 22. slewing mechanism; 23. drilling arm; 24. L-shaped support frame; 25. swing cylinder; 3. drill rod; 4. first space; 5. belt conveyor; 6. second space; 7. monorail crane; 8. translation cylinder; 9. outrigger; 10. crane operating table. DETAILED DESCRIPTION

[0025] The present invention is described in detail below in conjunction with the various embodiments shown in the accompanying drawings, but it should be noted that these embodiments are not limitations of the present invention, and any equivalent transformations or substitutions in functions, methods, or structures made by ordinary technicians in the field based on these embodiments are all within the scope of protection of the present invention.

[0026] In the description of the present invention, it should be understood that the terms "center", "longitudinal", "lateral", "length", "width", "thickness", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside", "clockwise", "counterclockwise" and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the referred device or element must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as limiting the present invention.

[0027] The specific implementation process of the present invention is described below through multiple embodiments. Example 1

[0028] See also Figures 1 to 5 This embodiment discloses a specific implementation of a straddle-type tunnel drilling vehicle (hereinafter referred to as “drilling vehicle”) for tunneling with a shield machine.

[0029] See also Figures 1 to 5 The straddle-type tunnel boring vehicle for shield machine tunneling includes a chassis 1 and a first crawler assembly 11 and a second crawler assembly 12 arranged on both sides below the chassis 1. The first crawler assembly 11 includes a first crawler 111 and a first crawler bracket 112. A first lifting cylinder 113 and first lifting slide columns 114 are respectively arranged on both sides of the first lifting cylinder 113 between the first crawler bracket 112 and the chassis 1. The second crawler assembly 12 includes a second crawler 121 and a second crawler bracket 122. The second crawler A second lifting cylinder 123 and second lifting slides 124 are respectively arranged on both sides of the second lifting cylinder 123 between the bracket 122 and the chassis 1; a transverse track 13 and a drilling assembly 2 moving along the transverse track 13 are arranged at the end of the chassis 1; the drilling assembly 2 includes an operating table 21, a slewing mechanism 22 and a drilling arm 23; a first space 4 between the first crawler assembly 11 and the second crawler assembly 12 allows a belt conveyor 5 to pass through; a first box body 14 and a second box body 15 are respectively arranged on both sides above the chassis 1, and a second space 6 between the first box body 14 and the second box body 15 allows a monorail crane 7 arranged at the top of the tunnel to pass through.

[0030] Specifically, see Figures 1 to 5 For high-rock coal mine tunnels, the traditional tunneling machine has low tunneling efficiency and slow construction progress. Therefore, the shield machine of this embodiment is used for tunneling with high efficiency. The tunneled coal is transported to the outside through the belt conveyor 5, and the materials and personnel required for the tunnel are transported through the monorail crane 7 at the top of the tunnel. The purpose of the first space 4 is to provide a transportation path for the belt conveyor 5. The first space 4 is a rectangular space with a width of 2500mm-2900mm and a height of 1150mm-1400mm. The purpose of the second space 6 is to provide a transportation path for the belt conveyor 5. The second space 6 is for operators to stand and provides a passage for the monorail crane 7. The width of the second space 6 is 1300mm-1600mm, and the height direction of the second space 6 is an open structure. In order to make full use of the second space 6, a number of drill rods 3 are stored at the bottom of the second space 6. Through this embodiment, the integration of excavation, drilling and transportation is realized, that is, while the shield machine is used for excavation, the coal is transported outward through the belt conveyor, the monorail crane is used to transport materials and personnel to the tunnel, and the straddle-type tunnel drilling vehicle straddles the belt conveyor and drills holes, thereby realizing high-efficiency excavation.

[0031] See also Figures 1 to 5The drilling assembly 2 of this embodiment is drilled by a drill rod, and the holes are used for pre-extraction of gas or support to ensure the safety of tunnel excavation; the working principle of the drilling assembly 2 is as follows: a translation cylinder 8 is arranged on one side of the transverse track 13, and the translation cylinder 8 drives the drilling assembly 2 to move along the transverse track 13 with the chassis 1 as a fulcrum, and the fulcrum is located behind the first box body 14; a power assembly is arranged in the first box body 14, and an oil tank is arranged in the second box body 15; the translation cylinder 8 drives the drilling assembly 2 to the rear of the second box body 15 and avoids the second space 6. The purpose of avoiding is to facilitate the passage of the monorail crane 7, that is, when the monorail crane 7 needs to pass through the second space 6, the translation cylinder 8 drives the drilling assembly 2 to move to the rear of the second box body 15, and the slewing mechanism 22 drives the drill arm 23 to be in a vertical state to avoid affecting the passage of the monorail crane 7.

[0032] See also Figures 1 to 5 The working range of the drilling assembly 2 involves an arc-shaped laneway. In order to increase the working range of the drilling assembly 2, the following four aspects are guaranteed: First, the translation cylinder 8 provides an overall horizontal moving distance for the drill arm 23, and the propulsion stroke of the translation cylinder 8 is 1000mm-1500mm; second, the slewing mechanism 22 drives the drill arm to swing left and right, that is, it can drill holes in the left and right arcs of the laneway; third, through the synchronous lifting of the first lifting cylinder 113 and the second lifting cylinder 123, the drill arm 23 is provided with a degree of freedom in the height direction; fourth, the slewing mechanism 22 is connected to the drill arm 23 through an L-shaped support frame 24, and a swing angle cylinder 25 is arranged on the L-shaped support frame 24. The swing angle cylinder 25 drives the drill arm 23 to swing back and forth. The purpose of the swing angle cylinder 25 is to fine-tune the front and rear positions of the drill arm 23. The swing angle of the swing angle cylinder is ±10° to improve the drilling accuracy; the above four aspects jointly ensure the working range and working accuracy of the drill arm 23. It should be further explained that the lifting stroke of the first lifting cylinder 113 and the second lifting cylinder 123 is 150mm-200mm. When the first lifting cylinder 113 and the second lifting cylinder 123 are at the maximum lifting stroke, the height of the chassis 1 from the monorail crane 7 must still ensure a height space of 100mm, so as to ensure the smooth passage of the monorail crane 7 when the first lifting cylinder 113 and the second lifting cylinder 123 are lifted.

[0033] When drilling, in order to keep the drilling vehicle stable, legs 9 facing the top of the tunnel are designed behind the first box body 14 and the second box body 15 respectively, and the legs 9 have built-in telescopic cylinders; for the convenience of driving, a driving operating platform 10 is also set next to the legs 9. Example 2

[0034] See also Figure 6This embodiment discloses a specific implementation method of a comprehensive construction method for coal mine tunnel excavation, drilling and transportation (hereinafter referred to as "construction method").

[0035] The comprehensive construction method for coal mine tunnel excavation, drilling and transportation includes the following steps: Step S1: Excavating and forming a coal mine tunnel by a shield machine; Step S2: Install a monorail crane at the top of the coal mine tunnel, and install a belt conveyor at the bottom of the coal mine tunnel to transport coal.

[0036] Step S3: The straddle-type tunnel drilling vehicle for tunneling with a shield machine described in Example 1 straddles the belt conveyor and performs drilling.

[0037] Specifically, for coal mine tunnels with high rocks, the excavation efficiency of traditional tunneling machines is low and the construction progress is slow. Therefore, the high-efficiency shield machine of this embodiment excavates the tunnel to form a circular tunnel. The coal formed by the excavation is transported outward by the belt conveyor 5. The belt conveyor 5 is usually in the middle of the bottom of the tunnel. Due to the existence of the belt conveyor 5, the space between the belt conveyor 5 and the side wall of the tunnel is narrow, and it is difficult for traditional drilling vehicles to enter. Manual drilling is not only inefficient but also faces the risk of gas outburst. Therefore, after installing the monorail crane and the belt conveyor, the straddled tunnel drilling vehicle for shield machine excavation tunnels of Example 1 straddles the belt conveyor and drills holes. The purpose of drilling is to serve as a pre-gas extraction hole or a support hole. The straddled tunnel drilling vehicle for shield machine excavation tunnels of Example 1 has the following features: There is a space 4 and a second space 6. The purpose of the first space 4 is to provide a transportation path for the belt conveyor 5. The first space 4 is a rectangular space. The width of the first space 4 is 2500mm-2900mm, and the height of the first space 4 is 1150mm-1400mm. The purpose of the second space 6 is for the operator to stand and provide a passage path for the monorail crane 7. The width of the second space 6 is 1300mm-1600mm, and the height direction of the second space 6 is an open structure, which makes full use of the second space 6. Through this embodiment, the integration of excavation, drilling and transportation is realized, that is, while the shield machine is used for excavation, the coal is transported outward through the belt conveyor, and the materials and personnel are transported to the tunnel by the monorail crane. The straddle-type tunnel drilling vehicle straddles the belt conveyor and drills holes, thereby realizing high-efficiency excavation.

[0038] The comprehensive construction method for coal mine tunnel excavation, drilling and transportation disclosed in this embodiment has the same technical solution as that in Embodiment 1. Please refer to the description in Embodiment 1 and will not be repeated here.

Claims

1. A straddle-type tunnel drilling vehicle for tunneling with a shield machine, characterized in that: It comprises a chassis and a first crawler assembly and a second crawler assembly arranged on both sides below the chassis; A transverse track and a drilling assembly moving along the transverse track are arranged at the end of the chassis; The drilling assembly includes an operating table, a slewing mechanism and a drilling arm; A first space between the first crawler assembly and the second crawler assembly allows a conveyor belt to pass through; A first box and a second box are respectively arranged on both sides above the chassis. The second space between the first box and the second box allows a monorail crane disposed on the top of the tunnel to pass through.

2. The straddle-type tunnel drilling vehicle for tunneling with a shield machine as claimed in claim 1, characterized in that: The first crawler track assembly includes a first crawler track and a first crawler track bracket.

3. The straddle-type tunnel drilling vehicle for tunneling with a shield machine as claimed in claim 2, characterized in that: A first lifting cylinder and first lifting slide columns are respectively arranged on both sides of the first lifting cylinder.

4. The straddle-type tunnel drilling vehicle for tunneling with a shield machine as claimed in claim 1, characterized in that: The second track assembly includes a second track and a second track frame.

5. The straddle-type tunnel drilling vehicle for tunneling with a shield machine as claimed in claim 4, characterized in that: A second lifting cylinder and second lifting slide columns respectively arranged on both sides of the second lifting cylinder are arranged between the second crawler support and the chassis.

6. The straddle-type tunnel drilling vehicle for tunneling with a shield machine as claimed in any one of claims 1 to 5, characterized in that: A translation oil cylinder is arranged on one side of the transverse track, and the translation oil cylinder drives the drilling assembly to move along the transverse track with the chassis as a fulcrum.

7. The straddle-type tunnel drilling vehicle for tunneling with a shield machine as claimed in claim 6, characterized in that: A power assembly is disposed in the first housing, and an oil tank is disposed in the second housing; The translation cylinder drives the drilling assembly to the rear of the second box and avoids the second space.

8. The straddle-type tunnel drilling vehicle for tunneling with a shield machine as claimed in claim 7, characterized in that: When the drilling assembly is located at the rear of the second box, the rotary mechanism drives the drill arm to be in a vertical state.

9. The straddle-type tunnel drilling vehicle for tunneling with a shield machine as claimed in claim 6, characterized in that: The slewing mechanism is connected to the drill arm via an L-shaped support frame; A swing angle oil cylinder is arranged on the L-shaped support frame, and the swing angle oil cylinder drives the drill arm to swing forward and backward; A number of drill rods are stored at the bottom of the second space.

10. A comprehensive construction method for digging, drilling and transporting coal mine tunnels, characterized in that: The following steps are involved: Step S1: Excavating and forming a coal mine tunnel by a shield machine; Step S2: installing a monorail crane at the top of the coal mine tunnel, installing a belt conveyor at the bottom of the coal mine tunnel and transporting coal; Step S3: The straddle-type tunnel drilling vehicle for tunneling with a shield machine as described in any one of claims 1 to 9 straddles the belt conveyor and performs drilling.

Citation Information

Patent Citations

  • Mining anchor rod drill carriage

    CN107620568A

  • Novel gantry type self-propelled anchor rod drilling machine

    CN108331529A

  • Large-diameter self-guiding horizontal drilling machine

    CN109779525A

  • Gantry type mining hydraulic drill carriage

    CN113863855A

  • Crawler-type lifting platform

    CN115898262A