Reinforced riser composite structure and construction method thereof

By installing internal casing, spider-web reinforcement ribs and column-shaped rib blocks inside the water-sealing conduit, and combining fixed anchor rods and reinforced components, the problem of insufficient resistance to wind, wave and ice resistance of the water-sealing conduit is solved, and the problem of insufficient resistance to wind, wave and ice is achieved. The structural stability and dump resistance are improved, while reducing the amount of steel and offshore operation costs.

CN118911606APending Publication Date: 2024-11-08JIANGSU YONGWEI OFFSHORE EQUIP CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202410970296.3
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-19
Publication Date
2024-11-08

AI Technical Summary

Technical Problem

The existing water silo conduits have insufficient resistance to wind, wave and ice resistance, resulting in the need to use large-sized water silo conduits or increase wall thickness to improve mechanical properties, thereby increasing steel usage and offshore operation costs.

Method used

Design a combined structure of reinforced water-displacement conduits, by installing multiple sets of internal casing components inside the water-displacement conduit, and installing spider-web-type reinforcement ribs, column-shaped reinforcement blocks and reinforcement rods, combining fixed anchors and reinforcement , forming complex structures to improve stability and anti-pour, while cement casting is used to secure these parts.

Benefits of technology

It effectively improves the stability and anti-dumping ability of the water-sealing conduit, avoids the performance decline caused by the hollow core, reduces the amount of steel, reduces the cost of offshore operations, and extends the service life of the equipment.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118911606A_ABST
    Figure CN118911606A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of riser pipes, and discloses a reinforced riser pipe combined structure. According to the invention, a plurality of groups of reinforcing components are arranged between the waterproof guide pipe and the internal sleeve, specifically, a plurality of outer rib raised lines, and arc-shaped connecting ribs and elastic ribs arranged among the outer rib raised lines are arranged, so that the waterproof guide pipe can be sleeved outside the internal sleeve, and in the sleeving process, the elastic ribs can be slightly compressed, so that the waterproof guide pipe can be prevented from being damaged. An annular cavity is formed between the waterproof guide pipe and an internally-arranged casing pipe, cement paste is injected into the annular cavity till the whole annular cavity is filled with the cement paste, cement solidification is formed after the cement paste is solidified for a certain time, a reinforcing component is poured into the annular cavity between the waterproof guide pipe and the internally-arranged casing pipe, and the reinforcing component and the annular cavity between the waterproof guide pipe and the internally-arranged casing pipe are fixed through cement solidification. And the overall mechanical property is guaranteed, meanwhile, the steel consumption of the waterproof guide pipe is reduced, and the problem that due to the fact that a large-size waterproof guide pipe is used, the offshore operation cost is greatly increased is solved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of watertight ducts, and in particular to a reinforced watertight duct composite structure and a construction method thereof. Background Art

[0002] The riser is generally a large diameter round pipe. Its function is to resist ice accumulation and isolate the quicksand layer on the surface. The riser is the "throat" of marine drilling and is an essential component for all marine oil and gas well construction. The riser is an important pipeline structure, commonly used in oil and gas extraction and transportation in deep sea, high pressure, high temperature and other environments.

[0003] There are several general classifications of water-blocking pipes: 1. Complete water-blocking pipe: avoids longitudinal movement of the oil-water interface and the influence of water stress; 2. Unpinned water-blocking pipe: sheet or disc-shaped sealing components are distributed in a ring shape, and the oil-water interface always makes some longitudinal and lateral movements around the inner circle area; 3. Semi-water-blocking pipe: measures to increase the water stress of the water-blocking method, so that the oil-water interface changes less in parts with smaller pipe diameters, such as the load end, constraint end, and annular seal; 4. Directional water-blocking pipe: fine-tune the offset of the oil-water interface in the area of ​​water stress inside the waterblocking pipe to improve the efficiency of the water-blocking method.

[0004] At present, the conventional method for improving the wind, wave and ice resistance of the combined structure of the watertight duct is to use a large-sized watertight duct structure or increase the wall thickness of the watertight duct to improve the overall mechanical properties of the watertight duct. This type of structure will increase the amount of steel used in the watertight duct, and the use of a large-sized watertight duct will greatly increase the cost of offshore operations. Therefore, we propose a new reinforced combined structure of the watertight duct and its construction method. Summary of the invention

[0005] The object of the present invention is to provide a reinforced watertight duct composite structure and a construction method thereof to solve the problems raised in the above-mentioned background technology.

[0006] To achieve the above-mentioned purpose, the present invention provides the following technical solutions: a reinforced watertight duct combination structure, including a watertight duct, wherein a plurality of groups of internal casing components are installed inside the watertight duct, and the plurality of groups of internal casing components include a plurality of groups of internal casings, and the plurality of groups of internal casings are connected to each other in an upper and lower arrangement, and the top and bottom of each internal casing are integrally connected with spider web-type reinforcement ribs, and a columnar rib block is arranged below the spider web-type reinforcement rib, and rib rods are fixedly connected between the outer wall of the columnar rib block and the inner wall of the internal casing at equal intervals around the circumference; the end face of the internal casing located at the uppermost end of the watertight duct is higher than the top end face of the watertight duct, and the end face of the internal casing located at the lowermost end of the watertight duct is higher than the bottom end face of the watertight duct.

[0007] Preferably, the reinforced watertight duct assembly structure also includes a fixed anchor rod, and the fixed anchor rod is specifically arranged inside the inner casing.

[0008] Preferably, the end of the fixed anchor rod passes through the center point of the entire column-type rib block, the top of the fixed anchor rod is fixedly connected to the middle rib point in the spider web-type reinforcement rib provided on the inner casing located at the uppermost end of the water-proof duct, and the bottom end of the fixed anchor rod passes through the middle rib point in the spider web-type reinforcement rib provided on the inner casing located at the lowermost end of the water-proof duct and extends downward.

[0009] Preferably, a plurality of groups of reinforcing components are circumferentially equidistantly arranged between the water-blocking conduit and the inner casing, and the reinforcing components specifically include a plurality of outer rib ridges circumferentially equidistantly fixedly connected to the outer wall of the inner casing, and arc-shaped connecting ribs and elastic ribs arranged between the plurality of outer rib ridges.

[0010] Preferably, each of the elastic ribs is composed of two crescent-shaped elastic ribs and a curved elastic rib integrally connected between the two crescent-shaped elastic ribs.

[0011] Preferably, the outer wall fixing sleeve of the arc-shaped connecting rib is provided with a plurality of U-shaped groove-type connecting parts, the outer wall fixing sleeve of one of the crescent-shaped elastic ribs located in the elastic rib is provided with a plurality of inner double-hole-type connecting parts, and the outer wall of another crescent-shaped elastic rib located in the elastic rib is in extrusion contact with the inner wall of the watertight duct.

[0012] Preferably, a plurality of annular fasteners of different sizes are fixedly sleeved between the plurality of the square groove type connectors and the plurality of the inner double hole type connectors.

[0013] Another technical problem to be solved by the present invention is to provide a construction method for a reinforced watertight conduit assembly structure, comprising the following steps: Step 1: Measure the number of inner casing components to be used according to the height of the watertight pipe, and after the height is measured, connect the plurality of inner casing components in sequence; Step 2: Then the staff uses a matching fixed anchor rod, and uses the end of the fixed anchor rod to penetrate the center position point of the entire column-shaped reinforcement block, so that the top end of the fixed anchor rod is fixed to the middle reinforcement point of the spider web-type reinforcement ribs provided on the inner casing at the uppermost end of the water-proof duct, and the bottom end of the fixed anchor rod penetrates the middle reinforcement point of the spider web-type reinforcement ribs provided on the inner casing at the lowermost end of the water-proof duct, and extends to the bottom, so that the exposed part of the fixed anchor rod is fixed; Step 3: sequentially install the reinforced components on the outside of the inner casing, and then sleeve the watertight conduit on the outside of the inner casing. During the sleeve installation process, the elastic ribs need to be slightly compressed; Step 4: Next, drive or install the watertight pipe so that the bottom end surface of the watertight pipe is flush with the exposed end surface of the fixed anchor rod; Step 5. Finally, inject cement slurry into the annular cavity formed between the water-blocking duct and the inner casing until the entire annular cavity is filled. After waiting for the cement slurry to solidify for a certain period of time, cement consolidation can be formed between the water-blocking duct and the inner casing, and the reinforced components can be cast.

[0014] The present invention provides a reinforced water-proof conduit assembly structure and a construction method thereof, which has the following beneficial effects: (1) The present invention designs an internal casing component, wherein the internal casing component is mainly composed of multiple groups of internal casings. The spider web-like reinforcement ribs, columnar reinforcement blocks and reinforcement rods on the internal casings can be used in conjunction with anchor rods to improve the stability of the interior of the watertight duct, strengthen and enrich the internal structure of the watertight duct, and avoid the interior of the watertight duct being hollow, which would lead to a decrease in the watertight strength performance and the overall mechanical properties.

[0015] (2) The present invention installs anchor rods inside the inner casing, and such anchor rods can serve as central support columns, effectively improving the anti-tilting and anti-bending capabilities of the watertight duct assembly structure. In this way, the watertight duct assembly structure can maintain the stability of the overall structure when encountering wind, rain, and waves. This design ensures that the watertight duct can still maintain its function under extreme weather conditions, ensuring the safety of offshore operations, while increasing the service life of the watertight duct and reducing maintenance costs.

[0016] (3) The present invention provides a plurality of groups of reinforcing components between the watertight duct and the inner casing, specifically, a plurality of external rib ridges, and arc-shaped connecting ribs and elastic ribs provided between the plurality of external rib ridges. When the watertight duct is sleeved on the outside of the inner casing, the elastic ribs can be slightly compressed during the sleeve process, thereby facilitating the insertion or installation of the watertight duct. Cement slurry is injected into the annular cavity formed between the watertight duct and the inner casing until the annular cavity is filled with cement slurry. After the cement slurry solidifies for a certain period of time, cement solidification is formed, and the reinforcing components are cast in. The annular cavity between the watertight duct and the inner casing is fixed by cement solidification, which is convenient for construction. The steel consumption of the watertight duct is reduced while ensuring the overall mechanical properties, thereby avoiding the problem that the use of large-sized watertight ducts will greatly increase the operating costs at sea. BRIEF DESCRIPTION OF THE DRAWINGS

[0017] Figure 1 It is a front schematic diagram of the overall structure of the present invention; Figure 2 It is a front cross-sectional view of the overall structure of the present invention; Figure 3 It is a top view of the overall structure of the present invention; Figure 4A three-dimensional view of the internal sleeve component of the present invention; Figure 5 For the present invention Figure 4 A is an enlarged schematic view of the structure.

[0018] In the figure: 1 water-proof conduit, 2 internal casing component, 3 fixed anchor rod, 4 reinforcement component, 21 internal casing, 22 spider web type reinforcement ribs, 23 columnar rib blocks, 24 rib rods, 41 external rib convex strips, 42 arc-shaped connecting ribs, 43 elastic ribs, 44 square groove type connector, 45 internal double hole connector, 46 ring type fastener. DETAILED DESCRIPTION

[0019] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0020] Examples of the embodiments are shown in the accompanying drawings, wherein the same or similar reference numerals throughout represent the same or similar elements or elements having the same or similar functions. The embodiments described below with reference to the accompanying drawings are exemplary and are intended to be used to explain the present invention, and should not be construed as limiting the present invention.

[0021] In the present invention, unless otherwise clearly specified and limited, the terms "installed", "connected", "connected", "fixed" and the like should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium, it can be the internal connection of two elements or the interaction relationship between two elements. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances. Example

[0022] A preferred embodiment of a reinforced water-blocking conduit assembly structure and a construction method thereof provided by the present invention is as follows: Figure 1-5As shown: a reinforced watertight duct assembly structure, including a watertight duct 1, wherein a plurality of groups of internal casing components 2 are installed inside the watertight duct 1, and the plurality of groups of internal casing components 2 include a plurality of groups of internal casings 21, and the plurality of groups of internal casings 21 are connected to each other by an upper and lower arrangement, and the top and bottom of each internal casing 21 are integrally connected with spider web-type reinforcing ribs 22, and columnar rib blocks 23 are arranged below the spider web-type reinforcing ribs 22, and rib rods 24 are fixedly connected between the outer wall of the columnar rib blocks 23 and the inner wall of the internal casing 21 at equal intervals in the circumference; the end face of the internal casing 21 located at the uppermost end of the watertight duct 1 is higher than the top end face of the watertight duct 1, and the end face of the internal casing 21 located at the lowermost end of the watertight duct 1 is higher than the bottom end face of the watertight duct 1; In this embodiment, a built-in sleeve component is designed, which is mainly composed of several groups of built-in sleeves 21. The surface of these built-in sleeves 21 is specially designed with a spider web-like reinforcement rib, the function of which is to enhance the stability of the entire structure. In addition, there are columnar rib blocks 23 and rib rods 24, and their presence further enhances the firmness of the structure. Through these designs, the built-in sleeve component can work in conjunction with the anchor rod, which not only significantly improves the stability inside the watertight duct 1, but also makes the structure of the watertight duct 1 more complex and rich. Such a design avoids the occurrence of hollow cores inside the watertight duct 1, thereby effectively preventing the decrease in watertight strength performance and overall mechanical properties due to the hollow core. Such improvements not only improve the use efficiency of the watertight duct 1, but also greatly enhance its safety performance. Example

[0023] See also Figure 1-Figure 5 , and on the basis of Example 1, it is further obtained that: the reinforced watertight duct composite structure also includes a fixed anchor rod 3, the fixed anchor rod 3 is specifically arranged inside the inner casing 21, the end of the fixed anchor rod 3 passes through the center position point of the entire columnar rib block 23, the top of the fixed anchor rod 3 is fixedly connected to the middle rib point of the spider web-type reinforcement rib 22 arranged on the inner casing 21 at the uppermost end of the watertight duct 1, and the bottom end of the fixed anchor rod 3 passes through the middle rib point of the spider web-type reinforcement rib 22 arranged on the inner casing 21 at the lowermost end of the watertight duct 1, and extends to the bottom; In this embodiment, by installing an anchor rod inside the inner casing 21, the anchor rod can be used as a central support column to effectively improve the anti-dumping and anti-bending capabilities of the watertight duct combination structure. In this way, the watertight duct combination structure can maintain the stability of the overall structure when encountering wind, rain and wave currents. This design ensures that the watertight duct can still maintain its function under extreme weather conditions and ensure the safety of offshore operations, while increasing the service life of the watertight duct and reducing maintenance costs. Through this innovative design, the reliability and economy of marine engineering structures can be improved, providing strong technical support for the development and utilization of my country's marine resources. Example

[0024] See also Figure 1-Figure 5 , and on the basis of Examples 1 and 2, it is further obtained that: a plurality of groups of reinforcing components 4 are circumferentially equidistantly arranged between the watertight pipe 1 and the inner casing 21, and the reinforcing components 4 specifically include a plurality of outer rib convex strips 41 circumferentially equidistantly fixedly connected to the outer wall of the inner casing 21, and arc-shaped connecting ribs 42 and elastic ribs 43 arranged between the plurality of outer rib convex strips 41; Each elastic rib 43 is composed of two crescent-shaped elastic ribs and a curved elastic rib integrally connected between the two crescent-shaped elastic ribs. The outer wall fixing sleeve of the arc-shaped connecting rib 42 is provided with a plurality of U-shaped groove type connectors 44, the outer wall fixing sleeve of one of the crescent-shaped elastic ribs in the elastic rib 43 is provided with a plurality of inner double-hole type connectors 45, the outer wall of another crescent-shaped elastic rib in the elastic rib 43 is in extrusion contact with the inner wall of the watertight duct 1, and a plurality of annular fasteners 46 of different sizes are fixedly provided between the plurality of U-shaped groove type connectors 44 and the plurality of inner double-hole type connectors 45.

[0025] In this embodiment, in order to improve the connection strength and stability between the watertight pipe 1 and the inner casing 21 in the development of deep-sea oil and gas fields, the present invention provides a new design scheme for reinforced components. Specifically, a plurality of groups of reinforced components 4 are arranged between the watertight pipe 1 and the inner casing 21. These reinforced components 4 include a plurality of outer rib ridges 41, which are arranged at certain intervals to form a structural reinforcement. In addition, arc-shaped connecting ribs 42 and elastic ribs 43 are also arranged between these outer rib ridges 41. Such a design can make the installation process of the watertight pipe 1 more convenient by slightly compressing the elastic ribs 43 when the watertight pipe 1 is sleeved on the outside of the inner casing 21.

[0026] During the installation process, cement slurry will be injected into the annular space formed between the watertight duct 1 and the inner casing 21. The cement slurry will fill the entire annular space and form a solid cement consolidation layer after a certain period of solidification, thereby firmly fixing the reinforced component 4 between the watertight duct 1 and the inner casing 21. This innovative design not only makes the installation of the watertight duct 1 easier, but also effectively reduces the use of steel while ensuring the overall mechanical properties of the structure. Such a design avoids the problem of a substantial increase in offshore operating costs caused by the use of an oversized watertight duct 1, thereby significantly reducing the cost of deep-sea oil and gas field development while ensuring the quality of the project. Example

[0027] See also Figure 1-Figure 5 , and based on Examples 1, 2, and 3, it is further obtained that another technical problem to be solved by the present invention is to provide a construction method for a reinforced watertight duct assembly structure, including the following method steps: Step 1: Measure the number of inner casing components 2 to be used according to the height of the watertight pipe 1, and after the height is measured, connect the multiple inner casings 21 in sequence; Step 2: Then the staff uses a matching fixed anchor rod 3, and uses the end of the fixed anchor rod 3 to penetrate the center position point of the entire column-shaped rib block 23, so that the top end of the fixed anchor rod 3 is fixed to the middle rib point of the spider web-type reinforcement rib 22 provided on the inner casing 21 at the uppermost end of the watertight pipe 1, and the bottom end of the fixed anchor rod 3 penetrates the middle rib point of the spider web-type reinforcement rib 22 provided on the inner casing 21 at the lowermost end of the watertight pipe 1, and extends to the bottom, so that the exposed part of the fixed anchor rod 3 is fixed; Step 3: sequentially install the reinforcement component 4 on the outside of the inner casing 21, and then sleeve the watertight pipe 1 on the outside of the inner casing 21. During the sleeve installation process, the elastic rib 43 needs to be slightly compressed; Step 4: Next, drive or install the watertight pipe 1 so that the bottom end surface of the watertight pipe 1 is flush with the exposed end surface of the fixing anchor rod 3; Step 5. Finally, inject cement slurry into the annular cavity formed between the water-blocking duct 1 and the inner casing 21 until the entire annular cavity is filled. After waiting for the cement slurry to solidify for a certain period of time, cement solidification can be formed between the water-blocking duct 1 and the inner casing 21, and the reinforced component 4 can be cast.

[0028] It should be noted that, in this article, relational terms such as first and second, etc. are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device.

[0029] Finally, it should be noted that the above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art can still modify the technical solutions described in the aforementioned embodiments or replace some of the technical features therein by equivalents. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention shall be included in the protection scope of the present invention.

Claims

1. A reinforced watertight duct assembly structure, comprising a watertight duct (1), characterized in that: The watertight duct (1) is internally installed with a plurality of groups of internal casing components (2), and the plurality of groups of internal casing components (2) include a plurality of groups of internal casings (21), and the plurality of groups of internal casings (21) are connected to each other in an upper and lower arrangement, and the top and bottom of each internal casing (21) are integrally connected with spider web-type reinforcement ribs (22), and a columnar reinforcement block (23) is arranged below the spider web-type reinforcement ribs (22), and a reinforcement rod (24) is fixedly connected between the outer wall of the columnar reinforcement block (23) and the inner wall of the internal casing (21) at equal intervals in the circumference; the end face of the internal casing (21) located at the uppermost end of the watertight duct (1) is higher than the top end face of the watertight duct (1), and the end face of the internal casing (21) located at the lowermost end of the watertight duct (1) is higher than the bottom end face of the watertight duct (1).

2. A reinforced watertight duct assembly structure according to claim 1, characterized in that: The reinforced watertight conduit assembly structure further comprises a fixed anchor rod (3), wherein the fixed anchor rod (3) is specifically arranged inside the inner casing (21).

3. A reinforced watertight duct assembly structure according to claim 2, characterized in that: The end of the fixed anchor rod (3) passes through the center point of the entire columnar reinforcement block (23), the top end of the fixed anchor rod (3) is fixedly connected to the middle reinforcement point of the spider web-type reinforcement rib (22) provided on the inner casing (21) at the uppermost end of the water-proof duct (1), and the bottom end of the fixed anchor rod (3) passes through the middle reinforcement point of the spider web-type reinforcement rib (22) provided on the inner casing (21) at the lowermost end of the water-proof duct (1) and extends to the bottom.

4. A reinforced watertight duct assembly structure according to claim 1, characterized in that: A plurality of groups of reinforcing components (4) are circumferentially equidistantly arranged between the water-blocking conduit (1) and the inner casing (21), and the reinforcing components (4) specifically include a plurality of outer rib ridges (41) circumferentially equidistantly fixedly connected to the outer wall of the inner casing (21), and arc-shaped connecting ribs (42) and elastic ribs (43) arranged between the plurality of outer rib ridges (41).

5. A reinforced watertight duct assembly structure according to claim 4, characterized in that: Each of the elastic tendons (43) is composed of two crescent-shaped elastic tendons and a curved elastic tendon integrally connected between the two crescent-shaped elastic tendons.

6. A reinforced watertight duct assembly structure according to claim 4, characterized in that: The outer wall fixing sleeve of the arc-shaped connecting rib (42) is provided with a plurality of square groove type connecting parts (44), and the outer wall fixing sleeve of one of the crescent-shaped elastic ribs in the elastic rib strip (43) is provided with a plurality of inner double-hole type connecting parts (45), and the outer wall of another crescent-shaped elastic rib in the elastic rib strip (43) is in compression contact with the inner wall of the watertight conduit (1).

7. A reinforced watertight duct assembly structure according to claim 6, characterized in that: A plurality of annular fasteners (46) of different sizes are fixedly sleeved between the plurality of square-shaped groove-shaped connecting pieces (44) and the plurality of inner double-hole-shaped connecting pieces (45).

8. A method for constructing a reinforced watertight duct assembly structure according to any one of claims 1 to 7, characterized in that: The method includes the following steps: Step 1, measuring the number of inner casing components (2) to be used according to the height of the watertight pipe (1), and after the height measurement is completed, sequentially connecting the plurality of inner casings (21); Step 2: Then the staff uses a matching fixed anchor rod (3) and uses the end of the fixed anchor rod (3) to penetrate the center position point of the entire columnar reinforcement block (23), so that the top end of the fixed anchor rod (3) is fixed to the middle reinforcement point of the spider web-type reinforcement rib (22) provided on the inner casing (21) at the uppermost end of the water-proof pipe (1), and the bottom end of the fixed anchor rod (3) penetrates the middle reinforcement point of the spider web-type reinforcement rib (22) provided on the inner casing (21) at the lowermost end of the water-proof pipe (1) and extends to the bottom, so that the exposed part of the fixed anchor rod (3) is fixed; Step 3: sequentially install the reinforcing components (4) on the outside of the inner casing (21), and then sleeve the watertight pipe (1) on the outside of the inner casing (21). During the sleeve installation process, the elastic ribs (43) need to be slightly compressed; Step 4: Next, drive or install the watertight pipe (1) so that the bottom end surface of the watertight pipe (1) is flush with the exposed end surface of the fixing anchor rod (3); Step 5. Finally, cement slurry is injected into the annular cavity formed between the water-blocking duct (1) and the inner casing (21) until the entire annular cavity is filled. After the cement slurry solidifies for a certain period of time, cement solidification is formed between the water-blocking duct (1) and the inner casing (21), and the reinforced component (4) is cast.