Power generation benefit evaluation method for self-contained power plant and new energy enterprise

By improving the win-win model and centralized bidding mechanism of power generation rights transactions, the complexity of power generation rights transactions between self-provided power plants and new energy enterprises and the low consumption rate of new energy are solved, and the transaction benefits are maximized and the efficiency of new energy is achieved. use.

CN118917585AInactive Publication Date: 2024-11-08内蒙古电力(集团)有限责任公司内蒙古电力经济技术研究院分公司
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202410937205.6
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-12
Publication Date
2024-11-08
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

In the existing technology, the power generation rights transaction between self-provided power plants and new energy enterprises is complicated, the lack of unified evaluation model, the bidding mechanism is imperfect, and the new energy consumption rate is low, resulting in the transaction results being unable to maximize the total social benefits and the utilization rate of new energy. high.

Method used

By studying the relationship between price difference settlement and power generation rights transactions, we will improve the win-win model of power generation rights transactions, and conduct transactions using centralized bidding methods, setting the quotation difference between the two parties to the transaction, meeting their respective profit conditions and the total amount of new energy consumption in the system. The upper limit constraints are to find the best transaction price to achieve maximum social benefits and new energy consumption.

Benefits of technology

The power generation rights trading process has been optimized, the real benefits of both parties have been reflected, the total social benefits have been maximized, the consumption rate and utilization rate of new energy have been improved, the transaction costs have been reduced, and the system stability and economics have been improved.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118917585A_ABST
    Figure CN118917585A_ABST
Patent Text Reader

Abstract

The invention discloses a power generation benefit evaluation method for a self-contained power plant and a new energy enterprise, and aims to optimize a power generation right transaction process and maximize total social benefits and new energy consumption. The method comprises the following steps: researching an association relationship between price difference settlement and power generation right transaction; based on a medium and long term price difference settlement mode, considering green power transaction and power generation right transaction cost factors, and improving a power generation right transaction win-win model; a centralized bidding mode is adopted in the transaction, high and low quoted prices are matched for matching, and the power generation right transaction is completed step by step; constraint conditions of concentrated bidding, profit-making conditions of a self-contained power plant and a new energy enterprise, and upper limit constraints of the total amount of new energy consumption in the system are satisfied. And evaluating the total social benefit and the new energy consumption amount according to different transaction prices, and finding the optimal transaction price to realize the maximum total social benefit and the maximum new energy consumption amount. The efficiency and benefit of power generation right transaction are improved, the utilization of new energy is promoted, and the method has remarkable economic and social benefits.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the field of energy technology, and in particular to a method for evaluating the power generation benefits of a self-provided power plant and a new energy enterprise. Background Art

[0002] In recent years, my country's self-owned power plants have reached a considerable scale, playing an important role in ensuring local power supply, attracting investment, and promoting local economic development. However, the proportion of self-owned power plants has been increasing, among which small coal-fired units with high energy consumption and heavy pollution account for a large proportion, which seriously affects the consumption of new energy and causes greater pollution. Faced with the severe trend of increasing abandonment of wind and solar power by new energy power generation companies, using self-owned power plants to trade power generation rights with new energy is an effective trading model.

[0003] In the existing technology, the evaluation of power generation benefits of self-owned power plants and new energy enterprises has the following problems:

[0004] The power generation rights transaction is complex: The power generation rights transaction mechanism in the existing technology is relatively complex, involving comprehensive consideration of multiple factors, including price fluctuations in the electricity market, power generation costs, and changes in electricity demand, which makes it difficult to achieve optimal benefits in the transaction process.

[0005] Lack of a unified evaluation model: There is currently a lack of a unified and effective evaluation model to evaluate the benefits of self-owned power plants and new energy companies in power generation rights trading. Existing models often fail to fully consider factors such as green power trading and power generation rights trading costs, and it is difficult to accurately reflect the real benefits of both parties to the transaction.

[0006] Imperfect bidding mechanism: The existing centralized bidding mechanism has certain limitations in actual operation and fails to fully consider the interests of both parties to the transaction and the overall benefits of the system, resulting in the transaction results being unable to maximize the total social benefits.

[0007] There are bottlenecks in the consumption of new energy: Due to the intermittent and volatile nature of new energy generation, in actual operation, how to maximize the consumption of new energy remains a challenge. Existing technologies lack effective methods to evaluate and optimize the consumption of new energy, resulting in low utilization of new energy.

[0008] Improper handling of the relationship between spot electricity and medium- and long-term electricity: After the power generation rights transaction, users of self-owned power plants need to purchase electricity from the main grid. Existing technologies are insufficient in handling changes in the relationship between spot electricity and medium- and long-term electricity, and are unable to accurately predict and adjust electricity distribution.

[0009] Therefore, there is an urgent need for a new power generation benefit evaluation method that can solve the above problems, optimize the power generation rights trading process, achieve a win-win situation for self-owned power plants and new energy enterprises, and maximize the total social benefits and new energy consumption. Summary of the invention

[0010] The purpose of the present invention is to provide a method for evaluating the power generation benefits of a self-provided power plant and a new energy enterprise.

[0011] To achieve the above object, the present invention is implemented according to the following technical solutions:

[0012] The present invention comprises the following steps:

[0013] S1: Study the relationship between price difference settlement and power generation rights trading: After the self-owned power plant conducts power generation rights trading with new energy enterprises, its users need to purchase additional electricity from the main grid. As the user side, the self-owned power plant may see changes in the relationship between spot electricity and medium- and long-term electricity;

[0014] S2: Based on the medium- and long-term price difference settlement model, considering the cost factors of green power trading and power generation rights trading, improve the win-win model of power generation rights trading;

[0015] S3: In the transaction, a centralized bidding method is adopted, the bid difference between the two parties is set, and the high and low bids are matched to gradually complete the power generation rights transaction, so that all market members can obtain benefits and achieve the maximum total social benefits;

[0016] S4: To meet the constraints of centralized bidding, self-owned power plants and new energy enterprises must meet their own profit conditions, as well as the upper limit of the total amount of new energy consumption in the system;

[0017] S5: Evaluate the total social benefits and new energy consumption based on different transaction prices, and find the best transaction price to achieve the maximum total social benefits and new energy consumption.

[0018] The beneficial effects of the present invention are:

[0019] The present invention is a method for evaluating the power generation benefits of self-provided power plants and new energy enterprises. By studying the correlation between price difference settlement and power generation rights trading, the win-win model of power generation rights trading is improved, and the trading is carried out in a centralized bidding manner. The method has the following technical effects:

[0020] Optimize power generation rights trading: By studying the relationship between price difference settlement and power generation rights trading, improve the existing trading model to make the trading process more efficient and accurately reflect the real benefits of both parties to the transaction;

[0021] Maximizing total social benefits: Through centralized bidding and matching principles, all market members can benefit, while maximizing total social benefits and improving overall economic benefits;

[0022] Improve the consumption rate of new energy: By evaluating and optimizing the consumption of new energy and finding the best transaction price, the utilization rate of new energy is improved, which promotes the further development and application of new energy;

[0023] Flexible response to changes in the electricity market: Taking into account the changes in the relationship between spot electricity and medium- and long-term electricity, the method can flexibly adjust electricity distribution to adapt to fluctuations in the electricity market, thereby improving the stability and reliability of the system;

[0024] Reduce transaction costs: Through the improved power generation rights trading model, the green electricity trading and power generation rights trading costs are comprehensively considered, which reduces transaction costs and improves the economic efficiency of transactions. BRIEF DESCRIPTION OF THE DRAWINGS

[0025] Figure 1 It is a bar chart showing the change in the medium- and long-term spot electricity volume before and after the transaction;

[0026] Figure 2 The spot electricity before and after the transaction is less than the medium and long-term electricity bar chart;

[0027] Figure 3 The spot electricity before and after the transaction is greater than the medium and long-term electricity bar chart;

[0028] Figure 4 is a flow chart of the present invention;

[0029] Figure 5 This is a typical wind power output forecast curve for the strong wind season;

[0030] Figure 6 This is a typical photovoltaic day-ahead output forecast curve for the strong wind season;

[0031] Figure 7 It is a bar chart of time-of-use electricity price and abandoned wind and solar power;

[0032] Figure 8 It is a bar chart of the lowest bids for captive power plants during the windy season;

[0033] Fig. 9 It is a bar chart of total social benefits and new energy consumption. DETAILED DESCRIPTION

[0034] The present invention will be further described below in conjunction with the accompanying drawings and specific embodiments. The illustrative embodiments and descriptions of the present invention are used to explain the present invention but are not intended to limit the present invention.

[0035] The present invention comprises the following steps:

[0036] S1: Study the relationship between price difference settlement and power generation rights trading: After the self-owned power plant conducts power generation rights trading with new energy enterprises, its users need to purchase additional electricity from the main grid. As the user side, the self-owned power plant may see changes in the relationship between spot electricity and medium- and long-term electricity;

[0037] Firstly, the impact of price difference settlement on power generation rights trading is studied.

[0038] After the self-owned power plant conducts power generation rights transactions with new energy enterprises, its users need to purchase additional electricity from the main grid. At this time, the self-owned power plant acts as the user side. After the power generation rights transaction, the self-owned power plant users use more electricity, and the following three situations may occur:

[0039] (1) The spot electricity before the transaction is less than the medium- and long-term electricity, and the spot electricity after the transaction is greater than the medium- and long-term electricity

[0040] like Figure 1 As shown, at this time, the excess electricity used in rights trading that exceeds the medium- and long-term electricity consumption is settled using the spot electricity price, and the remaining electricity is settled using the medium- and long-term electricity price.

[0041] The cost of electricity purchased from the main grid by the self-provided power plant before the transaction is:

[0042] Q i_n ×P i_l -(Q i_l -Q i_n )×(P i_l -P i_n )(1)

[0043] Where P i_n is the spot electricity price, P i_l is the medium and long-term electricity price, Q i_n Q is the spot electricity before the transaction, i_l It refers to the medium- to long-term spot electricity quantity before the transaction.

[0044] After the transaction, the cost of electricity purchased by the self-provided power plant from the main grid is:

[0045]

[0046] In the formula It is the spot electricity after the rights transaction.

[0047] Before and after the transaction on the self-provided power plant side, the cost of purchasing electricity from the main grid changes as follows:

[0048]

[0049] Where Q ij Electricity is traded for rights.

[0050] At this time, the unit electricity price corresponding to the power volume of rights trading is:

[0051] P i_B1 =P i_n ×Q ij / Q ij =P i_n (4)

[0052] (2) The spot electricity volume before and after the transaction is less than the medium- and long-term electricity volume

[0053] like Figure 2 As shown, at this time, after the rights transaction, the part of the spot electricity volume that is still lower than the medium- and long-term electricity volume is settled using the medium- and long-term spot financial price difference, because the electricity volume used in the rights transaction is settled using the medium- and long-term electricity price.

[0054] The cost of electricity purchased by the captive power plant from the main grid before the transaction is shown in formula (1).

[0055] After the transaction, the cost of electricity purchased by the self-provided power plant from the main grid is:

[0056]

[0057] Before and after the transaction on the self-provided power plant side, the cost of purchasing electricity from the main grid changes as follows:

[0058]

[0059] At this time, the unit electricity price corresponding to the power volume of rights trading is:

[0060] P i_B2 =P i_n ×Q ij / Q ij =P i_n (7)

[0061] (3) The spot electricity volume before and after the transaction is greater than the medium- and long-term electricity volume

[0062] like Figure 3 As shown, at this time, the excess electricity consumption due to rights trading is settled using the spot electricity price.

[0063] The cost of electricity purchased from the main grid by the self-provided power plant before the transaction is:

[0064] Q i_l ×P i_l -(Q i_n -Q i_l )×P i_n (8)

[0065] After the transaction, the cost of electricity purchased by the self-provided power plant from the main grid is:

[0066]

[0067] Before and after the transaction on the self-provided power plant side, the cost of purchasing electricity from the main grid changes as follows:

[0068]

[0069] At this time, the unit electricity price corresponding to the power volume of rights trading is:

[0070] P i_B3 =P i_n ×Q ij / Q ij =P i_n(11)

[0071] The situation of new energy enterprises after the transaction is the same as that of self-owned power plants, except that the electricity consumption is converted into power generation, and the electricity price is transferred from the user side to the power generation side.

[0072] According to the above three situations, it can be seen that the extra cost of purchasing electricity from the power grid due to the extra electricity consumption of the self-owned power plant in the rights trading is equal to the spot electricity price, which has nothing to do with the medium- and long-term electricity prices, and has nothing to do with the spot electricity volume before the transaction, the medium- and long-term electricity volume, and the rights trading electricity volume. The same is true for the new energy side.

[0073] S2: Based on the medium- and long-term price difference settlement model, considering the cost factors of green power trading and power generation rights trading, improve the win-win model of power generation rights trading;

[0074] When a self-owned power plant conducts power generation rights trading, its income comes from the transaction fee P paid by the new energy enterprise. ij And the variable cost of power generation corresponding to the saved electricity C i The expenditure is the expenditure on additional electricity purchased from the spot market due to medium- and long-term contracts with new energy companies, including the spot electricity price P i_n In addition, the government fund P must be paid for purchasing electricity from the spot market. i_g And the transmission and distribution price P i_t .

[0075] Since the spot electricity price, government fund and transmission and distribution price correspond to the same amount of electricity in the calculation, in order to simplify the calculation formula, they are combined and recorded as the unit electricity cost:

[0076] P i_N =P i_n +P i_g +P i_t (12)

[0077] After the self-owned power plant and the new energy enterprise conduct the power generation rights transaction, the new energy enterprise will sell this part of the electricity from the spot market. Since my country's current green electricity transaction is established under the medium- and long-term transaction framework, this part of the electricity cannot be regarded as green electricity transaction. In order to compensate the new energy enterprise, the self-owned power plant should also pay an additional part of the environmental premium. At the same time, it is believed that the self-contained power plant has obtained a green certificate.

[0078] For a self-owned power plant to make a profit, its income must be greater than its expenditure, that is:

[0079]

[0080] When considering transaction costs C ij When , the above inequality is modified to:

[0081]

[0082] The income obtained by the self-provided power plant in the rights transaction is:

[0083]

[0084] When a new energy enterprise conducts power generation rights trading, its income comes from the income P earned in the spot market due to the extra power generation in the rights trading. j_n and environmental premium, the expenditure of which is the transaction price P paid to the self-provided power plant ij and the variable cost of power generation C j .

[0085] In order for new energy enterprises to make a profit, their expenditure must be less than their income, that is:

[0086]

[0087] When considering transaction costs C ij When , the above inequality is modified to:

[0088]

[0089] The benefits that new energy enterprises obtain from rights trading are:

[0090]

[0091] The total social benefit of power generation rights trading is:

[0092]

[0093] S3: In the transaction, a centralized bidding method is adopted, the bid difference between the two parties is set, and the high and low bids are matched to gradually complete the power generation rights transaction, so that all market members can obtain benefits and achieve the maximum total social benefits;

[0094] The transaction is conducted through centralized bidding. The specific rules are as follows:

[0095] Let S i , R j (i=1,2,...,n;j=1,2,...m) represent the i-th self-provided power plant and the j-th new energy enterprise respectively, Q Si , P Si They represent the quotation of the i-th self-provided power plant, Q Rj , P Rj They represent the quoted quantity of the j-th new energy enterprise. The difference between the two parties' quotations is obtained by subtracting the quotation of the self-provided power plant from the quotation of the buyer's new energy enterprise as shown in Table 1.

[0096] Table 1: Difference in the bids of both parties

[0097]

[0098] In Table 1, when the transaction difference is positive, that is, when the quotation of the new energy enterprise is greater than the quotation of the self-provided power plant, matching can be carried out, and the principle of quotation difference from high to low is adopted to match. Assume P Rj -P Si To obtain the maximum quote difference, we first need to j and S i Matching, power generation rights transaction volume Q ij =min(Q Rj ,Q Si ), transaction price After the match is successful, this part of the transaction volume will be cleared, and the subsequent transaction volume will be reduced by this part of the transaction volume. j The reported quantity becomes Q Rj -min(Q Rj ,Q Si ),S i The reported quantity becomes Q Si -min(Q Rj ,Q Si ), the quotes of both parties remain unchanged. Then continue to find the maximum quote difference between the two parties and repeat the above steps until one side's quoted volume is 0 or the quote difference is negative.

[0099] The goal of the win-win model of power generation rights trading is to make all market members gain benefits. On this basis, the sum of the benefits of all social members should be maximized, that is, the total social benefit should be maximized.

[0100] S4: To meet the constraints of centralized bidding, self-owned power plants and new energy enterprises must meet their own profit conditions, as well as the upper limit of the total amount of new energy consumption in the system;

[0101] The objective function is:

[0102]

[0103] The constraints are:

[0104] P i <P j (twenty one)

[0105]

[0106] Formula (21-22) is the constraint of centralized bidding, Formula (23-24) is the profit condition of self-owned power plants and new energy enterprises, Formula (25) is the upper limit constraint of power generation rights, where Q max In order to ensure safety (inertia, stability), the maximum amount of new energy consumed in the system.

[0107] S5: Evaluate the total social benefits and new energy consumption based on different transaction prices, and find the best transaction price to achieve the maximum total social benefits and new energy consumption.

[0108] The present invention uses five self-provided power plants to trade power generation rights with five new energy enterprises. The trading mode is centralized bidding trading, and high and low bids are used for matching and clearing. The parameters required for the example are shown in Table 2-5. Figure 5-7 shown.

[0109] Table 2 Some parameters required for the example

[0110]

[0111] Table 3 Variable costs of power generation in power plants

[0112]

[0113] Table 4 Time-of-use electricity prices in strong wind season

[0114]

[0115] Table 5 The proportion of wind and solar power curtailment in different periods

[0116]

[0117] For self-provided power plants, their quotations must be met Calculate the lowest price that five self-provided power plants can earn at different times. Figure 8 As shown. For new energy enterprises, their quotations must be met The highest bids that new energy enterprises can earn in different periods of time are shown in Table 6.

[0118] Table 6 Highest bid for new energy in strong wind season

[0119]

[0120] According to the wind and solar power abandonment curve, the amount of wind and solar power abandoned during peak hours is basically 0, and the power generation rights trading cannot be realized, so it is not considered. In Tables 7 and 8, there are 5 groups of quotations for 5 self-provided power plants and 5 new energy enterprises respectively. The two parties can get 25 groups of transaction results by matching, of which there are 9 different transaction results, which are distinguished by the transaction price.

[0121] Table 7 Quotation of self-owned power plants

[0122]

[0123] Table 8 Quotation and Quantity of New Energy Enterprises

[0124]

[0125] Let 1 represent the transaction result of 0.110 / 0.115, 2 represent the transaction result of 0.120 / 0.125, and so on. Fig. 9 The total social benefits and new energy consumption shown. When the transaction price is 0.150 / 0.155 yuan·kWh -1 When , the total social benefit and the new energy consumption are both the largest. At this time, the total social benefit is 70,379 yuan and the new energy consumption is 345MW.

[0126] The technical solution of the present invention is not limited to the above-mentioned specific embodiments. All technical variations made according to the technical solution of the present invention fall within the protection scope of the present invention.

Claims

1. A method for evaluating the power generation benefits of self-owned power plants and new energy enterprises. It is characterized in that The following steps are involved: S1: Study the relationship between price difference settlement and power generation rights trading: After the self-owned power plant conducts power generation rights trading with new energy enterprises, its users need to purchase additional electricity from the main grid. As the user side, the self-owned power plant may see changes in the relationship between spot electricity and medium- and long-term electricity; S2: Based on the medium- and long-term price difference settlement model, considering the cost factors of green power trading and power generation rights trading, improve the win-win model of power generation rights trading; S3: In the transaction, a centralized bidding method is adopted, the bid difference between the two parties is set, and the high and low bids are matched to gradually complete the power generation rights transaction, so that all market members can obtain benefits and achieve the maximum total social benefits; S4: To meet the constraints of centralized bidding, self-owned power plants and new energy enterprises must meet their own profit conditions, as well as the upper limit of the total amount of new energy consumption in the system; S5: Evaluate the total social benefits and new energy consumption based on different transaction prices, and find the best transaction price to achieve the maximum total social benefits and new energy consumption.

2. The power generation benefit evaluation method of a self-provided power plant and a new energy enterprise according to claim 1, Features: The changes in the relationship between spot electricity and medium- and long-term electricity in step S1 include: the spot electricity before the transaction is less than the medium- and long-term electricity, the spot electricity after the transaction is greater than the medium- and long-term electricity, the spot electricity before and after the transaction is less than the medium- and long-term electricity, and the spot electricity before and after the transaction is greater than the medium- and long-term electricity.

3. The power generation benefit evaluation method of a self-provided power plant and a new energy enterprise according to claim 2, Features: When the spot electricity before the transaction is less than the medium- and long-term electricity, the cost of purchasing electricity from the main grid by the self-provided power plant before the transaction is: Q i_n ×P i_l -(Q i_l -Q i_n )×(P i_l -P i_n )(1) Where P i_n is the spot electricity price, P i_l is the medium and long-term electricity price, Q i_n Q is the spot electricity before the transaction, i_l It is the mid- to long-term spot electricity before the transaction; After the transaction, the cost of electricity purchased by the self-provided power plant from the main grid is: In the formula It is the spot electricity after the rights transaction; Before and after the transaction on the self-provided power plant side, the cost of purchasing electricity from the main grid changes as follows: Where Q ij Electricity is traded for rights; At this time, the unit electricity price corresponding to the power volume of rights trading is: P i_B1 =P i_n ×Q ij / Q ij =P i_n (4)。 4. The power generation benefit evaluation method of a self-provided power plant and a new energy enterprise according to claim 3, Features: When the spot electricity before and after the transaction is less than the medium- and long-term electricity, the cost of purchasing electricity from the main grid by the self-provided power plant before the transaction is as shown in formula (1); After the transaction, the cost of electricity purchased by the self-provided power plant from the main grid is: Before and after the transaction on the self-provided power plant side, the cost of purchasing electricity from the main grid changes as follows: At this time, the unit electricity price corresponding to the power volume of rights trading is: P i_B2 =P i_n ×Q ij / Q ij =P i_n (7)。 5. The power generation benefit evaluation method of a self-provided power plant and a new energy enterprise according to claim 4, Features: When the spot electricity volume before and after the transaction is greater than the medium- and long-term electricity volume: The cost of electricity purchased from the main grid by the self-provided power plant before the transaction is: Q i_l ×P i_l -(Q i_n -Q i_l )×P i_n (8) After the transaction, the cost of electricity purchased by the self-provided power plant from the main grid is: Before and after the transaction on the self-provided power plant side, the cost of purchasing electricity from the main grid changes as follows: At this time, the unit electricity price corresponding to the power volume of rights trading is: P i_B3 =P i_n ×Q ij / Q ij =P i_n (11) The situation of new energy enterprises after the transaction is the same as that of self-owned power plants, except that the electricity consumption is converted into power generation, and the electricity price is transferred from the user side to the power generation side.

6. The method for evaluating the power generation benefits of a self-provided power plant and a new energy enterprise according to claim 5, Features: The step S2 is: when the self-owned power plant conducts power generation rights trading, its income comes from the transaction fee P paid by the new energy enterprise. ij And the variable cost of power generation corresponding to the saved electricity C i ; Its expenditure includes the spot electricity price P i_n 、Government Fund i_g And the transmission and distribution price P i_t ; Recorded as unit electricity cost: P i_N =P i_n +P i_g +P i_t (12) Self-owned power plants should also pay part of the environmental premium For a self-owned power plant to make a profit, its income must be greater than its expenditure, that is: When considering transaction costs C ij When , the above inequality is modified to: The income obtained by the self-provided power plant in the rights transaction is: When a new energy enterprise conducts power generation rights trading, its income comes from the income P earned in the spot market due to the extra power generation in the rights trading. j_n and environmental premium, the expenditure of which is the transaction price P paid to the self-provided power plant ij and the variable cost of power generation C j ; In order for new energy enterprises to make a profit, their expenditure must be less than their income, that is: When considering transaction costs C ij When , the above inequality is modified to: The benefits that new energy enterprises obtain from rights trading are: The total social benefit of power generation rights trading is:

7. The method for evaluating the power generation benefits of a self-provided power plant and a new energy enterprise according to claim 6, Features: In step S3, the centralized bidding method is specifically as follows: Let S i , R j (i=1,2,...,n;j=1,2,...m) represent the i-th self-provided power plant and the j-th new energy enterprise respectively, Q Si , P Si They represent the quotation of the i-th self-provided power plant, Q Rj , P Rj Represents the quotation of the j-th new energy enterprise Let P Rj -P Si For the maximum quote difference, first j and S i Matching, power generation rights transaction volume Q ij =min(Q Rj ,Q Si ), transaction price After the match is successful, this part of the transaction volume will be cleared, and the subsequent transaction volume will be reduced by this part of the transaction volume. j The reported quantity becomes Q Rj -min(Q Rj ,Q S ,S i The reported quantity becomes Q Si -min(Q Rj ,Q Si ), the quotations of both parties remain unchanged, and then continue to look for the maximum quotation difference between the two parties, and repeat the above matching steps until one side's quoted volume is 0, or the quotation difference is negative.

8. The method for evaluating the power generation benefits of a self-provided power plant and a new energy enterprise according to claim 7, Features: The constraint conditions for centralized bidding are met in step S4: The objective function is: The constraints are: P i <P j (21) Formula (21-22) is the constraint of centralized bidding, Formula (23-24) is the profit condition of self-owned power plants and new energy enterprises, Formula (25) is the upper limit constraint of power generation rights, where Q max In order to ensure the maximum amount of new energy consumed in the system while ensuring inertia and stability.