Lightning protection grounding system of cover and excavation top-down structure and construction method of lightning protection grounding system

By simultaneously constructing a lightning protection grounding system during the cut-and-cover reverse construction method, and by pre-embedding the main electrode and grounding electrode inside the building using a grounding grid and connectors, the problem of lightning protection grounding systems affecting construction progress in existing technologies has been solved, and efficient construction of lightning protection grounding systems has been achieved.

CN118920133APending Publication Date: 2024-11-08SHANGHAI YIJIAN INSTALLATION ENG CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411099696.8
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-12
Publication Date
2024-11-08

AI Technical Summary

Technical Problem

Existing lightning protection grounding systems are usually installed after the main structure of the building is completed, which leads to a delay in the construction schedule and affects the efficiency of the cut-and-cover reverse construction method.

Method used

A lightning protection grounding system is constructed simultaneously during the building construction process. This is achieved by embedding a grounding grid in the underground continuous wall and central column, pre-burying the main electrode and grounding electrode, and using connectors to achieve flexible connection between the main electrode and the grounding electrode, ensuring that the lightning protection grounding system is completed simultaneously when the building construction is finished.

Benefits of technology

This reduced the installation time of the lightning protection grounding system, improved construction efficiency, ensured the integrity and effectiveness of the lightning protection grounding system, and reduced the impact on the overall construction progress.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118920133A_ABST
    Figure CN118920133A_ABST
Patent Text Reader

Abstract

The invention relates to a cover and excavation top-down structure lightning protection grounding system and a construction method thereof, and relates to the technical field of building lightning protection construction, the lightning protection grounding system comprises a lightning arrester, and the lightning arrester is arranged on the upper side of a building; the grounding grid is embedded in an underground diaphragm wall of the building and a center pillar of the building, the grounding grid is grounded, and the lightning arrester is connected with the grounding grid; the plurality of main electrodes are arranged on an underground diaphragm wall of the building and a middle stand column of the building, and the main electrodes are connected with the grounding grid; the plurality of grounding electrodes are pre-buried in a plurality of laminates of a building, the grounding electrodes are connected with structural steel bars in the corresponding laminates, a plurality of main electrodes are arranged in one-to-one correspondence with the plurality of grounding electrodes, and the main electrodes are connected with the corresponding grounding electrodes. According to the invention, the installation time of the lightning protection grounding system can be reduced, and the influence on the whole construction progress is reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of building lightning protection construction, and in particular to a cover-and-excavation reverse structure lightning protection grounding system and a construction method thereof. Background Art

[0002] Cut-and-cover construction is a construction technology whose main principle is to first build the underground continuous wall, central column and roof of the underground building, and then use the underground continuous wall and central column as supporting components to excavate layer by layer from top to bottom under the roof and build the main structure to the bottom. As a construction method with less impact on the surrounding environment, the cut-and-cover construction method has been widely used in the construction of urban subway stations.

[0003] However, during the construction of the building with the cover-excavation reverse method, how to effectively design and construct the lightning protection grounding system in the building to ensure the lightning protection safety of the building is an important issue currently faced. At present, the common lightning protection grounding system mainly includes lightning rods, grounding wires and grounding devices. Specifically, the lightning rod is installed on the upper side of the building, the grounding device is buried underground, and the grounding wire is connected to the lightning rod and the grounding device. When a lightning strike occurs, the lightning rod attracts lightning and conducts the current through the grounding wire into the grounding device, and then conducts the current into the ground, which can achieve the lightning protection function.

[0004] However, the existing lightning protection and grounding system is usually installed after the main structure of the building is completed, which makes the construction process of the lightning protection and grounding system incompatible with the building construction process. Therefore, the independent installation of the lightning protection and grounding system will lead to the extension of the overall construction process of the building, which will easily affect the construction progress. Summary of the invention

[0005] The present application provides a lightning protection and grounding system for a cover-and-excavation reverse construction structure and a construction method thereof, the purpose of which is to construct the lightning protection and grounding system while constructing a building, thereby reducing the installation time of the lightning protection and grounding system and thereby reducing the impact on the entire construction progress.

[0006] In the first aspect, the present application provides a cover-excavation reverse construction structure lightning protection and grounding system adopts the following technical solutions: A lightning protection and grounding system for a cover-and-excavation reverse construction structure comprises a lightning rod, which is arranged on the upper side of a building; a grounding grid, which is embedded in the underground continuous wall of the building and in the neutral column of the building, and the grounding grid is grounded, and the lightning rod is connected to the grounding grid; a main electrode, wherein a plurality of main electrodes are provided, and a plurality of the main electrodes are provided on the underground continuous wall of the building and on the neutral column of the building, and the main electrodes are connected to the grounding grid; and a grounding electrode, wherein a plurality of grounding electrodes are provided, and a plurality of the grounding electrodes are pre-buried in a plurality of floor plates of the building, and the grounding electrodes are connected to the structural steel bars in the corresponding floor plates, and a plurality of the main electrodes and a plurality of the grounding electrodes are provided in a one-to-one correspondence, and the main electrodes are connected to the corresponding grounding electrodes.

[0007] By adopting the above technical solution, firstly, the coordinated setting of the lightning arrester and the grounding grid constitutes a lightning protection grounding system, which can realize the lightning protection grounding function. Secondly, since the grounding grid is embedded in the underground continuous wall and the neutral column, the grounding grid can be established synchronously when the underground continuous wall and the neutral column are constructed, and since the underground continuous wall and the neutral column can be deeply inserted into the ground, the grounding of the grounding grid can be realized. Since the main electrode is pre-buried in the underground continuous wall and the neutral column, and the grounding electrode is pre-buried in the corresponding layer plate, the main electrode and the grounding electrode can be pre-buried synchronously during the construction process of the building. After the corresponding layer plate solidifies, the grounding electrode can be connected to the corresponding main electrode through a wire or a tinned flat steel. At this time, the structural steel bars in the layer plate are incorporated into the grounding grid, which can expand the coverage area of ​​the grounding grid in the building.

[0008] Based on the setting of such a lightning protection grounding system, the lightning protection grounding system can be constructed simultaneously during the process of the building's cover-and-excavation reverse construction. Then, when the building construction is completed, the lightning protection grounding system is also completed. This can reduce the installation time of the lightning protection grounding system and reduce the impact on the entire construction progress.

[0009] Optionally, a connector is provided between the main electrode and the corresponding ground electrode, the connector comprising a connecting wire and two connecting pieces, one connecting piece is connected to the corresponding main electrode, and the other connecting piece is connected to the corresponding ground electrode, the connecting wire is located between the two connecting pieces, and both ends of the connecting wire are respectively connected to the corresponding connecting pieces.

[0010] By adopting the above technical solution, the connector is connected to the main electrode and the corresponding grounding electrode respectively through two connecting pieces, and then the two connecting pieces are connected through the connecting wire, so that the connection between the main electrode and the corresponding grounding electrode can be realized, so that the main electrode and the grounding electrode are conductive, so that the structural steel bars of the corresponding layer can be incorporated into the grounding grid. Due to the setting of the connecting wire, the distance and relative position between the two connecting pieces can be changed, which makes the connection between the main electrode and the grounding electrode more flexible and reliable, and improves the convenience of connecting the main electrode with the corresponding negative electrode.

[0011] Optionally, a mounting plate is provided on both the main electrode and the grounding electrode, and the mounting plate is fixedly connected to the corresponding main electrode or the grounding electrode; the connecting member includes a conductive column, one end of which is connected to the connecting wire, and the other end is coaxially connected to the conductive plate; the conductive plate and the mounting plate are arranged in a one-to-one correspondence, and one end of the conductive plate away from the conductive column along its own axial direction abuts against the corresponding mounting plate, and the conductive plate and the corresponding mounting plate are detachably connected.

[0012] By adopting the above technical solution, the design of the mounting plate and the conductive column and the detachable connection between the conductive plate and the mounting plate, the connector and the corresponding mounting plate can be detachably installed, which facilitates the replacement and selection of the connector, and further facilitates the maintenance of the lightning protection grounding system.

[0013] Optionally, the connector further includes an insulating sleeve, which is sleeved on the outside of the conductive column, and the conductive column is slidably connected to the corresponding inner wall of the insulating sleeve along its own axial direction.

[0014] By adopting the above technical solution, the insulating sleeve can provide insulation protection for the conductive column. The insulating sleeve is slidably connected to the conductive column, which makes it easy to adjust the relative position of the conductive column and the insulating sleeve, and facilitates the installation of the conductive plate and the corresponding mounting plate.

[0015] Optionally, the insulating sleeve is penetrated with a plurality of auxiliary holes, the conductive disk is penetrated with a plurality of intermediate holes, the mounting disk is penetrated with a plurality of connecting holes, and the connecting holes are threaded holes; the auxiliary holes are arranged in one-to-one correspondence with the intermediate holes, and the auxiliary holes are coaxially arranged with the corresponding intermediate holes; the intermediate holes are arranged in one-to-one correspondence with the connecting holes, and the intermediate holes are coaxially connected with the corresponding connecting holes; fixing bolts are inserted into the auxiliary holes, the fixing bolts are plug-fitted with the corresponding intermediate holes, one end of the fixing bolts is plug-fitted with the corresponding connecting holes, and the fixing bolts are connected to the corresponding inner walls of the connecting holes by threads; a resistance spring is arranged between the insulating sleeve and the conductive disk, the resistance spring is axially arranged along the axial direction of the insulating sleeve, one end of the resistance spring is connected to the insulating sleeve, and the other end is connected to the conductive disk.

[0016] By adopting the above technical solution, firstly, the cooperation of the auxiliary hole, the middle hole, the connecting hole and the fixing bolt can realize the detachable connection between the connecting piece and the corresponding mounting plate. Secondly, since a resistance spring is arranged between the insulating sleeve and the conductive plate, when the fixing bolt is tightened, the fixing bolt will resist the movement of the insulating sleeve toward the corresponding conductive plate, thereby compressing the resistance spring, which can increase the resistance force between the conductive plate and the corresponding mounting plate, thereby improving the tightness of the installation between the conductive plate and the corresponding mounting plate, and thus improving the stability of the connection between the connecting piece and the corresponding mounting plate.

[0017] Optionally, a sealing ring is further sleeved on the outside of the insulating sleeve, and the sealing ring is slidably connected to the insulating sleeve along its own axial direction; one end of the sealing ring away from the insulating sleeve along its own axial direction is plug-fitted with the corresponding mounting plate.

[0018] By adopting the above technical solution, after the connecting member is fixed to the corresponding mounting plate, the sealing ring can be sleeved on the corresponding mounting plate to achieve insulation protection of the corresponding mounting plate.

[0019] Optionally, the sealing ring is rotatably connected to the insulating sleeve, and the inner wall of the sealing ring is connected to the outer wall of the mounting plate via threads.

[0020] By adopting the above technical solution, the sealing ring and the mounting disk are connected by threads, which can increase the stability of the connection between the sealing ring and the mounting disk.

[0021] Optionally, the conductive column is detachably connected to the connecting wire.

[0022] By adopting the above technical solution, the detachable connection between the conductive column and the connecting wire can replace connecting wires of different specifications, thereby increasing the use range of the connector.

[0023] Optionally, the connecting wire is connected to the outer wall of the conductive column; a connecting plate is fixedly connected to the side of the conductive column away from the conductive plate, the connecting plate is detachably connected to the conductive column, the connecting plate is coaxially arranged with the conductive column, and the connecting plate structure is the same as the mounting plate structure.

[0024] By adopting the above technical solution, since the structure of the connecting plate and the mounting plate is the same, another connector can be installed on the connecting plate, which can connect the two connectors in series. On the one hand, when several connectors are connected in series in sequence, this can extend the length of the connector, which is convenient for connecting the main electrode and the corresponding grounding electrode that are far away; on the other hand, when there is a connector with multiple connectors installed on a connector, it can make a main electrode electrically connected to several grounding electrodes, and it can also make a grounding electrode electrically connected to several main electrodes. This method is mainly used in the case where the number of grounding electrodes is insufficient or the number of main electrodes is insufficient or an equipotential connection point needs to be established.

[0025] In addition, since the connection plate and the conductive column are detachably connected, the connection plate can be installed when it is needed, and can be removed from the corresponding conductive column when it is not needed.

[0026] In the second aspect, the present application provides a construction method for a cover-excavation reverse structure lightning protection grounding system using the following technical solution: A construction method for a cover-excavation reverse construction structure lightning protection and grounding system, used to realize the construction of the above-mentioned cover-excavation reverse construction structure lightning protection and grounding system, comprising the following steps: S1. Use the cover-excavation reverse construction method to complete the construction of the underground continuous wall outside the building area, then construct the middle column in the building area, and weld the steel cage in the middle column to the steel pipe column through the steel column. The structural steel bars in the underground continuous wall and the steel cage and steel pipe column in the middle column form a grounding network, and the main electrode is pre-buried in the underground continuous wall and the middle column, and the main electrode is connected to the grounding network; S2. Construction of building roof; S21, casting a layer plate in the building area as the top plate of the building, and pre-embed a grounding electrode in the layer plate, and the pre-embedded grounding electrode is connected to the structural steel bars in the layer plate; S22. After the layer plate solidifies, several grounding electrodes on the layer plate are connected to several main electrodes on the neutral column, and several grounding electrodes on the layer plate are connected to several main electrodes on the underground continuous wall; S23. Install a lightning rod on the upper side of the layer plate, and connect the lightning rod to the grounding grid; S3, building floor construction; S31. Excavation of foundation pit: excavate the foundation pit under the floor slab until the depth of the foundation pit meets the height requirement of the next floor of the building; S32, layer plate casting: cast a layer plate at the bottom of the foundation pit as the bottom plate of the corresponding floor, and embed a grounding electrode in the layer plate, and the embedded grounding electrode is connected to the structural steel bars in the layer plate; S33. When the layer plate solidifies, connect the ground electrode to the nearest main electrode; S4. Repeat step S3 until the number of floors of the building meets the requirement.

[0027] By adopting the above technical scheme, when the construction method is used for building construction, the structural steel bars in the underground continuous wall of the building, the steel cages and steel pipe columns in the neutral columns of the building, and the structural steel bars in the floor plates form a grounding network covering the entire building, wherein the structural steel bars in the floor plates are incorporated into the grounding network through pre-buried grounding electrodes and main electrodes. Therefore, while the building is constructed using the cover-and-cut reverse method, the lightning protection grounding system inside the building is simultaneously constructed. When the building construction is completed, the grounding and lightning protection system inside the building is also basically completed, which can reduce the layout time of the lightning protection grounding system, and thus reduce the construction time of the entire building.

[0028] In summary, the present application includes at least one of the following beneficial technical effects: 1. The lightning protection grounding system of the present application can cover the entire building, thereby improving the effectiveness and integrity of the lightning protection grounding system.

[0029] 2. The lightning protection grounding wire system of the present application can be constructed simultaneously when the building is being constructed using the cover-excavation reverse construction method, and then when the building construction is completed, the lightning protection grounding system is also completed. This can reduce the installation time of the lightning protection grounding system and reduce the impact on the entire construction progress.

[0030] 3. Through the setting of the connector, this application can effectively improve the speed, stability and flexibility of the connection between the main electrode and the corresponding ground electrode. BRIEF DESCRIPTION OF THE DRAWINGS

[0031] Figure 1 It is a schematic diagram of the overall structure of a building constructed using the cover-and-cut reverse construction method in Example 1 of the present application.

[0032] Figure 2 It is a schematic diagram of the overall structure of the lightning protection and grounding system inside a building of Example 1 of the present application.

[0033] Figure 3 It is a schematic diagram of the overall structure of the connector of Example 2 of the present application.

[0034] Figure 4 It is a schematic diagram of the overall structure of the installation disk of Example 2 of the present application.

[0035] Figure 5It is a schematic diagram of the partial cross-sectional structure of Example 2 of the present application.

[0036] Figure 6 It is a schematic diagram of the overall structure of the connector of Example 3 of the present application.

[0037] Figure 7 It is a schematic diagram of the partial explosion structure of the connector of Example 3 of the present application.

[0038] Figure 8 It is a schematic diagram of the overall structure of the connector of Example 4 of the present application.

[0039] Fig. 9 It is a schematic diagram of the partial cross-sectional structure of Example 4 of the present application.

[0040] Fig.10 It is a schematic diagram of the overall structure of the adapter plate of Example 4 of the present application.

[0041] In the figure, 1. lightning arrester; 2. grounding grid; 3. main electrode; 4. grounding electrode; 5. neutral column; 6. layer plate; 7. top plate; 8. underground continuous wall; 9. connector; 91. mounting plate; 911. connecting hole; 92. connecting wire; 921. connecting bolt; 93. connecting piece; 931. conductive column; 9311. conductive hole; 9312. connecting groove; 932. conductive plate; 9321. middle hole; 9322. fixing bolt; 933. insulating sleeve; 9331. auxiliary hole; 9332. long hole for making way; 934. resisting spring; 935. sealing ring; 936. connecting plate; 937. connecting column; 938. sealing tube; 9381. sealing plate. DETAILED DESCRIPTION

[0042] The following is combined with Figure 1 -Attached Fig.10 , further details of this application are given.

[0043] Embodiment 1: A lightning protection and grounding system for cover-excavation reverse construction structure, referring to Figure 1 and Figure 2 , including a lightning rod 1, a grounding grid 2, a main electrode 3 and a grounding electrode 4.

[0044] Reference Figure 1 and Figure 2 The lightning receptor 1 is vertically arranged on the upper side of the building, and the lightning receptor 1 is connected to the grounding grid 2 by a wire or a galvanized flat steel. When lightning strikes the lightning receptor 1, the current generated by the lightning is introduced into the grounding grid 2, and then the current is introduced into the ground by the grounding grid 2, which can achieve the lightning protection function.

[0045] Reference Figure 1 and Figure 2, the grounding grid 2 is embedded in the underground continuous wall 8 of the building and the central column 5 of the building, and the grounding grid 2 is grounded. In this embodiment, the structural steel bars in the underground continuous wall 8 of the building, the steel cage in the central column 5 of the building, and the steel pipe column in the central column 5 of the building constitute the grounding grid 2. Since the underground continuous wall 8 is inserted underneath and the steel pipe column is pressed into the ground, the grounding grid 2 is grounded. At this time, the grounding grid 2 covers the entire building through the structural steel bars in the underground continuous wall 8 and the steel cage in the central column 5 of the building.

[0046] Reference Figure 1 and Figure 2 , there are several main electrodes 3, several main electrodes 3 are pre-buried in the underground continuous wall 8 of the building and the neutral column 5 of the building, and the main electrode 3 is welded to the corresponding structural steel bars in the underground continuous wall 8 or the steel cage in the neutral column 5. There are several grounding electrodes 4, several grounding electrodes 4 are pre-buried in several floor plates 6 of the building, and the grounding electrodes 4 are welded to the structural steel bars in the corresponding floor plates 6. There are several main electrodes 3 and several grounding electrodes 4 arranged one by one, and the main electrode 3 is electrically connected to the corresponding grounding electrode 4 through a wire or a galvanized flat steel. At this time, the structural steel bars in the floor plate 6 are incorporated into the grounding grid 2, so that the grounding grid 2 can cover the underground continuous wall 8, the neutral column 5 and all the floor plates 6, which can form a lightning protection grounding system covering the entire building and improve the lightning protection performance of the entire building.

[0047] Several grounding electrodes 4 located on the same floor are connected by wires or galvanized flat steel, which can set up equipotential connection points on each floor of the building, thereby ensuring the continuity of lightning protection grounding on each floor of the building. When there are functional rooms and important equipment areas in the building, several grounding electrodes 4 in the area are connected by wires or galvanized flat steel, and several grounding electrodes 4 in the area are separated from other grounding electrodes 4, and several grounding electrodes 4 in the area are independently connected to the grounding network 2, which can form local equipotential connection points in the functional rooms and important equipment areas, which can improve the safety of lightning protection grounding and protect the equipment in the area.

[0048] The implementation principle of the embodiment of the present application is as follows: the grounding grid 2 is composed of structural steel bars, steel cages and steel pipe columns inside the building, and the main electrode 3 and the grounding electrode 4 can also be pre-buried during the construction process, so that the lightning protection grounding system can be built synchronously during the construction process of the building using the cover-excavation reverse construction method. When the building is completed, the lightning protection grounding system can also be completed synchronously, which can improve the construction efficiency. At the same time, since the structural steel bars, steel cages and steel pipe columns of the building cover the entire building, the grounding grid 2 can cover the entire building, which can improve the integrity and effectiveness of the lightning protection grounding system.

[0049] This embodiment also discloses a construction method of a cover-excavation reverse construction structure lightning protection and grounding system, comprising the following steps: S1. Use the cover-excavation reverse method to complete the construction of the underground continuous wall 8 outside the building area, then construct the central column 5 in the building area, and weld the steel cage in the central column 5 to the steel pipe column through the steel column; and during the construction process of the central column 5 and the underground continuous wall 8, a number of main electrodes 3 are pre-buried in the central column 5 and the underground continuous wall 8, the main electrode 3 on the central column 5 is welded to the steel cage in the central column 5, and the main electrode 3 on the underground continuous wall 8 is welded to the structural steel bars in the underground continuous wall 8.

[0050] Specifically, before pouring the underground continuous wall 8, a number of main electrodes 3 are welded to the structural steel bars of the underground continuous wall 8; before pouring the central column 5, the steel cage is welded to the corresponding steel pipe column, and a number of main electrodes 3 are welded on the outside of the steel cage. After the pouring is completed, the main electrodes 3 will be embedded in the outer wall of the underground continuous wall 8 and the outer wall of the central column 5.

[0051] The steel cage and steel pipe column of the middle column 5 and the structural steel bars in the underground continuous wall 8 are all grounding grids 2, and because the underground continuous wall 8 and the middle column 5 are deeply inserted into the ground, the grounding function can be achieved, so that the grounding grid 2 composed of the steel cage and steel pipe column of the middle column 5 and the structural steel bars in the underground continuous wall 8 can cover the entire building. All the main electrodes 3 are electrically connected to the grounding grid 2, so all the main electrodes 3 are grounded.

[0052] S2. Construction of building roof 7.

[0053] S21 , casting a layer plate 6 in the building area, and pre-embedding a grounding electrode 4 in the layer plate 6 , and welding the pre-embedded grounding electrode 4 to the structural steel bars in the layer plate 6 .

[0054] Specifically, the layer slab 6 poured at this time serves as the top slab 7 of the entire building.

[0055] Specifically, when pre-buried grounding electrodes 4, several grounding electrodes 4 are connected by wires or welded by galvanized flat steel. When welding grounding electrodes 4, several grounding electrodes 4 on the same layer 6 are welded by tinned flat steel or connected by wires. At this time, several grounding electrodes 4 on the same layer 6 form equipotential connection points, which can ensure that the grounding electrodes 4 on the top plate 7 are connected.

[0056] S22. After the layer plate 6 solidifies, several grounding electrodes 4 on the layer plate 6 are connected to several main electrodes 3 on the neutral column 5, and several grounding electrodes 4 on the layer plate 6 are connected to several main electrodes 3 on the underground continuous wall 8.

[0057] Specifically, the grounding electrode 4 is connected to the corresponding main electrode 3 by a wire or welded by galvanized flat steel. At this time, the structural steel bars in the underground continuous wall 8, the structural steel bars in the top plate 7, and the steel cage and steel pipe column in the middle column 5 are mutually conductive, so that the structural steel bars in the underground continuous wall 8 and the steel cage and steel pipe column in the middle column 5 have the same potential, which can incorporate the structural steel bars in the top plate 7 into the grounding grid 2, increasing the coverage of the grounding grid 2 in the building.

[0058] S23, installing a lightning receptor 1 on the upper side of the layer plate 6, and connecting the lightning receptor 1 to the grounding grid 2.

[0059] Specifically, a lightning receptor 1 is installed on the top plate 7, and the lightning receptor 1 is electrically connected to the grounding grid 2. The lightning receptor 1 can be connected to the grounding electrode 4 on the top plate 7 through a wire or welded through a tinned flat steel, the lightning receptor 1 can be connected to the steel cage or steel pipe column in the neutral column 5 through a wire or through a tinned flat steel, and the lightning receptor 1 can also be connected to the structural steel bars of the underground continuous wall 8 through a wire or through a tinned flat steel, as long as it is ensured that the lightning receptor 1 can achieve point connection with the grounding grid 2.

[0060] After the lightning receptor 1 is connected to the grounding grid 2, when the lightning receptor 1 is struck by lightning, the lightning receptor 1 will quickly conduct the current into the grounding grid 2, thereby quickly conducting the current into the ground, thereby achieving a lightning protection grounding function.

[0061] S3. Construction of building floors.

[0062] S31, foundation pit excavation: excavate the foundation pit below the above-mentioned layer plate 6 until the depth of the foundation pit meets the height requirement of the next floor of the building.

[0063] S32 , layer plate 6 casting: layer plate 6 is cast at the bottom of the foundation pit as the bottom plate of the corresponding floor, and grounding electrode 4 is embedded in the layer plate 6 , and the embedded grounding electrode 4 is welded to the structural steel bar in the layer plate 6 .

[0064] Specifically, when pre-buried grounding electrodes 4, several grounding electrodes 4 are connected by wires or welded by galvanized flat steel. When welding grounding electrodes 4, several grounding electrodes 4 on the same layer 6 are welded by tinned flat steel or connected by wires. At this time, several grounding electrodes 4 on the same layer 6 form an equipotential connection point, thereby ensuring the continuity of lightning protection grounding on each floor of the building. When there are functional rooms and important equipment areas in the building, several grounding electrodes 4 in the functional rooms and important equipment areas are connected by wires or welded by galvanized flat steel, and several grounding electrodes 4 in the functional rooms and important equipment areas form local equipotential connection points, which can ensure that the grounding potential of the equipment in the area is equal, thereby improving the safety of grounding of the equipment in the area.

[0065] S33. After the layer plate 6 solidifies, the ground electrode 4 is connected to the nearest main electrode 3 through a wire or welded through galvanized flat steel.

[0066] Specifically, after the grounding electrode 4 is connected to the corresponding main electrode 3, the structural steel bars in the layer plate 6 are electrically connected to the grounding grid 2, and the structural steel bars of the corresponding layer plate 6 are incorporated into the grounding grid 2, thereby increasing the coverage of the grounding grid 2 and facilitating the grounding of equipment in the building.

[0067] S4. Repeat the above step S3 until the number of floors of the building meets the requirement.

[0068] The implementation principle of the embodiment of the present application is: when the present construction method is used for building construction, while the building is constructed using the cover-and-excavation reverse method, the lightning protection and grounding system inside the building is simultaneously constructed. When the building construction is completed, the grounding and lightning protection system inside the building is also basically completed. This can reduce the layout time of the lightning protection and grounding system, and thus reduce the construction time of the entire building.

[0069] Embodiment 2: A lightning protection and grounding system for cover-excavation reverse construction structure, referring to Figure 3 and Figure 4 The difference between this embodiment and the embodiment 1 is that a connector 9 is provided between the ground electrode 4 and the corresponding main electrode 3, and the connector 9 includes two mounting plates 91, one mounting plate 91 is welded to the corresponding ground electrode 4, and the other mounting plate 91 is welded to the corresponding main electrode 3. A plurality of connection holes 911 are provided on the mounting plate 91, and the plurality of connection holes 911 are sequentially spaced along the circumference of the mounting plate 91, and the connection holes 911 are all threaded holes.

[0070] Reference Figure 3 and Figure 5 The connector 9 also includes a connecting wire 92 and two connecting pieces 93. The outer layer of the connecting wire 92 is coated with an insulating rubber layer, and the two ends of the connecting wire 92 are fixedly connected to the corresponding connecting pieces 93. The connecting pieces 93 are arranged one by one with the mounting plates 91, and the connecting pieces 93 are detachably connected to the corresponding mounting plates 91. When the connecting pieces 93 are connected to the corresponding mounting plates 91, the main electrode 3 is electrically connected to the corresponding grounding electrode 4. At this time, the internal structural steel bars of the layer plate 6 corresponding to the grounding electrode 4 are incorporated into the grounding grid 2, which can expand the coverage of the grounding grid 2.

[0071] Reference Figure 3 and Figure 5The connecting member 93 includes a conductive column 931, one end of which is connected to the corresponding connecting wire 92, and the other end of which is provided with a conductive plate 932. The conductive column 931 and the conductive plate 932 are coaxially arranged and fixedly connected. The conductive plate 932 is provided with a plurality of intermediate holes 9321, which are arranged in sequence and spaced apart along the circumference of the conductive plate 932.

[0072] Reference Figure 3 and Figure 5 The conductive disk 932 is arranged in one-to-one correspondence with the mounting disk 91, and one end of the conductive disk 932 away from the connecting wire 92 contacts the corresponding mounting disk 91, and the conductive disk 932 is arranged coaxially with the corresponding mounting disk 91. The middle hole 9321 is arranged in one-to-one correspondence with the connecting hole 911, and the middle hole 9321 is coaxially connected with the corresponding connecting hole 911. A fixing bolt 9322 is inserted in the middle hole 9321, one end of the fixing bolt 9322 is inserted into the corresponding connecting hole 911, and the fixing bolt 9322 is connected to the inner wall of the corresponding connecting hole 911 by threading. Through the cooperation of a plurality of fixing bolts 9322, the conductive disk 932 can be connected to the corresponding mounting disk 91, so that the detachable connection between the connecting member 93 and the corresponding mounting disk 91 can be realized.

[0073] Reference Figure 3 and Figure 5 The connector 93 further includes an insulating sleeve 933 , which is sleeved on the outside of the conductive column 931 , and the conductive column 931 is slidably connected to the inner wall of the insulating sleeve 933 along its own axis.

[0074] Reference Figure 3 and Figure 5 , a plurality of auxiliary holes 9331 are formed through the insulating sleeve 933, and the plurality of auxiliary holes 9331 are sequentially spaced along the circumference of the insulating sleeve 933. The auxiliary holes 9331 are arranged one by one with the middle holes 9321, and the auxiliary holes 9331 are coaxially arranged with the corresponding middle holes 9321. Then the auxiliary holes 9331 are coaxially arranged with the corresponding middle holes 9321 and the corresponding connecting holes 911, and the fixing bolts 9322 sequentially pass through the auxiliary holes 9331 and the corresponding middle holes 9321 and are inserted into the corresponding connecting holes 911.

[0075] Reference Figure 3 and Figure 5A plurality of resisting springs 934 are disposed on one side of the insulating sleeve 933 facing the corresponding conductive disk 932. The plurality of resisting springs 934 are sequentially spaced along the circumference of the conductive column 931. The axial direction of the resisting spring 934 is disposed along the axial direction of the insulating sleeve 933. One end of the resisting spring 934 is connected to the insulating sleeve 933, and the other end is connected to the conductive disk 932. In this embodiment, the fixing bolts 9322 and the resisting springs 934 are disposed one by one, and the resisting springs 934 are sleeved on the outer side of the corresponding fixing bolts 9322.

[0076] Reference Figure 3 and Figure 5 Since the fixing bolt 9322 is threadedly connected to the corresponding connecting hole 911, when the fixing bolt 9322 is tightened, the fixing bolt 9322 will resist the movement of the insulating sleeve 933 toward the corresponding conductive disk 932, thereby compressing the resistance spring 934. This can increase the resistance force between the conductive disk 932 and the corresponding mounting disk 91, thereby improving the tightness of the installation between the conductive disk 932 and the corresponding mounting disk 91.

[0077] Reference Figure 3 and Figure 5 , a tin layer is provided on the side of the conductive plate 932 facing the corresponding mounting plate 91. Due to the provision of the tin layer and the resisting spring 934, when a large current flows between the grounding electrode 4 and the main electrode 3, on the one hand, the current can flow into the ground through the grounding grid 2; on the other hand, when the large current exists for a long time or the current is large, the tin layer melts and fills the gap between the conductive plate 932 and the mounting plate 91, thereby further improving the tightness and conductivity of the connection between the conductive plate 932 and the corresponding mounting plate 91.

[0078] Reference Figure 3 and Figure 5 , a sealing ring 935 is sleeved on the outer side of the insulating sleeve 933, and the sealing ring 935 is slidably connected to the insulating sleeve 933 along its own axial direction. One end of the sealing ring 935 away from the insulating sleeve 933 along its own axial direction is sleeved on the outer side of the corresponding mounting plate 91. The inner side wall of the sealing ring 935 is rotatably connected to the insulating sleeve 933, and the inner side wall of the sealing ring 935 is connected to the outer side wall of the mounting plate 91 through a thread. The sealing ring 935 is made of insulating material. The setting of the sealing ring 935 can cover the outer side of the corresponding mounting plate 91, thereby being able to insulate and protect the mounting plate 91.

[0079] The implementation principle of the embodiment of the present application is: through the setting of the connector 9, after the mounting plate 91 is welded on both the main electrode 3 and the grounding electrode 4, the connector 93 can be connected to the corresponding mounting plate 91 through the fixing bolt 9322, so that the connector 9 can be installed between the main electrode 3 and the corresponding grounding electrode 4, and due to the setting of the connecting wire 92 between the two connectors 93, it is convenient to connect the grounding electrode 4 to the main electrode 3 at different positions. Through the setting of the connector 9, the internal structural steel bars of the layer plate 6 corresponding to the grounding electrode 4 are incorporated into the grounding grid 2, which can expand the coverage of the grounding grid 2.

[0080] Example 3: A lightning protection and grounding system for a cover-excavation reverse construction structure, referring to Figure 6 and Figure 7 The difference between this embodiment and the second embodiment is that the connection wire 92 and the conductive column 931 are detachably connected. Both ends of the connection wire 92 are fixedly connected with connection bolts 921, and the conductive column 931 is provided with a conductive hole 9311 facing one end of the connection wire 92. The conductive hole 9311 is a threaded hole, and the axial direction of the conductive hole 9311 is arranged along the axial direction of the corresponding conductive column 931. The connection bolt 921 is plugged into the corresponding conductive hole 9311, and the connection bolt 921 is connected to the inner wall of the corresponding conductive hole 9311 by a thread.

[0081] The implementation principle of the embodiment of the present application is: by cooperating with the connecting bolt 921 and the conductive hole 9311, a detachable connection between the connecting wire 92 and the conductive column 931 is achieved, which enables the connecting wire 92 between the two connecting parts 93 to be replaced according to actual requirements, thereby improving the application scope of the connector 9.

[0082] Example 4: A lightning protection and grounding system for a cover-excavation reverse construction structure, referring to Figure 8 and Fig. 9 , the difference between this embodiment and embodiment 3 is that: the conductive hole 9311 is provided on the outer wall of the conductive column 931, the connecting bolt 921 is plugged into the conductive hole 9311, and the connecting bolt 921 is connected to the inner wall of the conductive hole 9311 by a thread. A long hole 9332 is provided through the outer wall of the insulating sleeve 933, the length direction of the long hole 9332 is arranged along the axial direction of the insulating sleeve 933, and the conductive hole 9311 is connected to the long hole 9332. The connecting bolt 921 is plugged into the long hole 9332, and the connecting bolt 921 is slidably connected to the inner wall of the long hole 9332 along the length direction of the long hole 9332. The opening of the long hole 9332 ensures that the connecting wire 92 can move with the conductive column 931 when the insulating sleeve 933 moves relative to the conductive column 931 along its own axial direction, thereby ensuring the stability of the connection between the connecting wire 92 and the conductive column 931.

[0083] Reference Fig. 9 and Fig.10 The conductive column 931 is provided with a connecting plate 936 at one end thereof which is away from the conductive plate 932 along its own axial direction, and the connecting plate 936 is coaxially arranged with the conductive column 931. The connecting plate 936 is located at a side of the insulating sleeve 933 which is away from the conductive plate 932, and the insulating sleeve 933 is spaced apart from the connecting plate 936 along its own axial direction. The connecting plate 936 has the same structure as the mounting plate 91.

[0084] Since the structure of the connection plate 936 is the same as that of the mounting plate 91, the connection plate 936 can be connected to the connecting piece 93 of another connector 9. When there are multiple connecting pieces 93 connected in this way, multiple ground electrodes 4 can be electrically connected to one main electrode 3, thereby establishing equipotential electrical connection points between multiple ground electrodes 4 connected to the same main electrode 3.

[0085] Reference Fig. 9 and Fig.10 , a connecting column 937 is coaxially arranged at one end of the connecting plate 936 facing the conductive column 931, and a connecting groove 9312 is provided at one end of the conductive column 931 facing the connecting plate 936. The connecting groove 9312 is coaxially arranged with the conductive column 931, and a thread is arranged on the inner side wall of the connecting groove 9312. The connecting column 937 is coaxially arranged with the conductive column 931, one end of the connecting column 937 is fixedly connected to the connecting plate 936, and the other end is plugged into the connecting groove 9312, and the connecting column 937 is connected to the inner side wall of the connecting groove 9312 by a thread. Then, the matching arrangement of the connecting column 937 and the connecting groove 9312 can realize the detachable connection between the connecting plate 936 and the conductive column 931.

[0086] Reference Figure 8 and Fig. 9 The insulating sleeve 933 is sleeved with a sealing tube 938 outside, and the sealing tube 938 is connected to the insulating sleeve 933 by threads. The sealing tube 938 is sleeved on the outside of the connecting plate 936, and the inner wall of the sealing tube 938 is spaced from the connecting plate 936, or the sealing tube 938 is slidably connected to the connecting plate 936 along its own axial direction and the sealing tube 938 is rotatably connected to the connecting plate 936 along its own circumferential direction. Such a setting enables the sealing tube 938 to be sleeved on the outside of the connecting plate 936, and the sealing tube 938 is made of insulating material, which enables the sealing tube 938 to insulate and protect the connecting plate 936.

[0087] Reference Figure 8 and Fig. 9The sealing tube 938 is provided with a sealing plate 9381 at one end thereof which is away from the insulating sleeve 933 along its own axial direction, and the sealing plate 9381 seals the sealing tube 938. The connecting plate 936 is located between the sealing plate 9381 and the insulating sleeve 933 along its own axial direction, and the sealing plate 9381 is made of insulating material. When the connecting plate 936 is not used, the sealing tube 938 is installed on the insulating sleeve 933, so that the connecting plate 936 can be sealed, thereby realizing insulation protection of the connecting plate 936.

[0088] The implementation principle of the embodiment of the present application is: through the setting of the connecting plate 936, another connecting piece 93 can be installed on the connecting plate 936, so that the connecting piece 93 of another connector 9 can be installed on the connecting piece 93, and then a plurality of grounding electrodes 4 can be connected to the first main electrode 3, and a plurality of main electrodes 3 can also be connected to one grounding electrode 4, which can be used in situations where the number of grounding electrodes 4 is insufficient or the number of main electrodes 3 is insufficient or an equipotential connection point needs to be established.

[0089] The embodiments of this specific implementation are all preferred embodiments of the present application, and are not intended to limit the protection scope of the present application. The same components are represented by the same figure marks. Therefore, any equivalent changes made based on the structure, shape, and principle of the present application should be included in the protection scope of the present application.

Claims

1. A lightning protection and grounding system for a cover-excavation reverse construction structure, characterized in that: include: A lightning receptor (1), wherein the lightning receptor (1) is arranged on the upper side of a building; A grounding grid (2), the grounding grid (2) being embedded in an underground continuous wall (8) of a building and in a neutral column (5) of the building, the grounding grid (2) being grounded, and the lightning arrester (1) being connected to the grounding grid (2); A main electrode (3), wherein a plurality of the main electrodes (3) are provided, and the plurality of the main electrodes (3) are provided on an underground continuous wall (8) of a building and on a central column (5) of the building, and the main electrodes (3) are connected to the grounding grid (2); A grounding electrode (4), wherein a plurality of the grounding electrodes (4) are provided, wherein the plurality of the grounding electrodes (4) are pre-buried in a plurality of floor plates (6) of a building, wherein the grounding electrodes (4) are connected to structural steel bars in corresponding floor plates (6), wherein a plurality of the main electrodes (3) are provided in a one-to-one correspondence with the plurality of the grounding electrodes (4), and wherein the main electrodes (3) are connected to corresponding grounding electrodes (4).

2. The lightning protection and grounding system for cover-excavation reverse construction structure according to claim 1 is characterized in that: A connector (9) is provided between the main electrode (3) and the corresponding ground electrode (4), the connector (9) comprising a connecting wire (92) and two connecting pieces (93), one of the connecting pieces (93) being connected to the corresponding main electrode (3), the other of the connecting pieces (93) being connected to the corresponding ground electrode (4), the connecting wire (92) being located between the two connecting pieces (93), and both ends of the connecting wire (92) being connected to the corresponding connecting pieces (93) respectively.

3. The lightning protection and grounding system for cover-excavation reverse construction structure according to claim 2 is characterized in that: The main electrode (3) and the grounding electrode (4) are both provided with a mounting plate (91), and the mounting plate (91) is fixedly connected to the corresponding main electrode (3) or the grounding electrode (4); The connecting member (93) comprises a conductive column (931), one end of the conductive column (931) is connected to the connecting wire (92), and the other end is coaxially connected to a conductive disk (932); The conductive disk (932) and the mounting disk (91) are arranged in one-to-one correspondence, one end of the conductive disk (932) away from the conductive column (931) along its own axial direction abuts against the corresponding mounting disk (91), and the conductive disk (932) and the corresponding mounting disk (91) are detachably connected.

4. The lightning protection and grounding system for cover-excavation reverse construction structure according to claim 3 is characterized in that: The connecting piece (93) further comprises an insulating sleeve (933), wherein the insulating sleeve (933) is sleeved on the outside of the conductive column (931), and the conductive column (931) is slidably connected to the corresponding inner wall of the insulating sleeve (933) along its own axial direction.

5. The lightning protection and grounding system for cover-excavation reverse construction structure according to claim 4 is characterized in that: The insulating sleeve (933) is provided with a plurality of auxiliary holes (9331), the conductive plate (932) is provided with a plurality of intermediate holes (9321), and the mounting plate (91) is provided with a plurality of connection holes (911), and the connection holes (911) are threaded holes; The auxiliary holes (9331) and the middle holes (9321) are arranged in a one-to-one correspondence, and the auxiliary holes (9331) and the corresponding middle holes (9321) are arranged coaxially; the middle holes (9321) and the connecting holes (911) are arranged in a one-to-one correspondence, and the middle holes (9321) and the corresponding connecting holes (911) are coaxially connected; A fixing bolt (9322) is inserted into the auxiliary hole (9331), the fixing bolt (9322) is plugged into and matched with the corresponding middle hole (9321), one end of the fixing bolt (9322) is plugged into and matched with the corresponding connecting hole (911), and the fixing bolt (9322) is connected to the inner wall of the corresponding connecting hole (911) via a thread; A resistance spring (934) is provided between the insulating sleeve (933) and the conductive disk (932); the resistance spring (934) is axially arranged along the axial direction of the insulating sleeve (933); one end of the resistance spring (934) is connected to the insulating sleeve (933), and the other end is connected to the conductive disk (932).

6. The lightning protection and grounding system for cover-excavation reverse construction structure according to claim 4 is characterized in that: A sealing ring (935) is also sleeved on the outside of the insulating sleeve (933), and the sealing ring (935) is slidably connected to the insulating sleeve (933) along its own axial direction; an end of the sealing ring (935) away from the insulating sleeve (933) along its own axial direction is plug-fitted with the corresponding mounting plate (91).

7. The lightning protection and grounding system for cover-excavation reverse construction structure according to claim 6 is characterized in that: The sealing ring (935) is rotatably connected to the insulating sleeve (933), and the inner wall of the sealing ring (935) is threadedly connected to the outer wall of the mounting plate (91).

8. The lightning protection and grounding system for cover-excavation reverse construction structure according to claim 4 is characterized in that: The conductive column (931) is detachably connected to the connecting wire (92).

9. The lightning protection and grounding system for cover-excavation reverse construction structure according to claim 4 is characterized in that: The connecting wire (92) is connected to the outer side wall of the conductive column (931); a connecting plate (936) is fixedly connected to a side of the conductive column (931) away from the conductive plate (932); the connecting plate (936) is detachably connected to the conductive column (931); the connecting plate (936) and the conductive column (931) are coaxially arranged; and the structure of the connecting plate (936) is the same as that of the mounting plate (91).

10. A construction method for a cover-excavation reverse construction structure lightning protection and grounding system, used to implement the construction of a cover-excavation reverse construction structure lightning protection and grounding system according to any one of claims 1 to 9, characterized in that: The following steps are involved: S1. Use the cover-excavation reverse construction method to complete the construction of the underground continuous wall (8) outside the building area, then construct the central column (5) in the building area, and weld the steel cage in the central column (5) to the steel pipe column through the steel column. The structural steel bars in the underground continuous wall (8) and the steel cage and steel pipe column in the central column (5) form a grounding network (2), and the main electrode (3) is pre-buried in the underground continuous wall (8) and the central column (5), and the main electrode (3) is connected to the grounding network (2); S2, construction of building roof (7); S21, casting a layer plate (6) in the building area as the top plate (7) of the building, and pre-embedding a grounding electrode (4) in the layer plate (6), wherein the pre-embedded grounding electrode (4) is connected to the structural steel bars in the layer plate (6); S22. After the layer plate (6) solidifies, a plurality of grounding electrodes (4) on the layer plate (6) are connected to a plurality of main electrodes (3) on the middle column (5), and a plurality of grounding electrodes (4) on the layer plate (6) are connected to a plurality of main electrodes (3) on the underground continuous wall (8); S23, installing a lightning receptor (1) on the upper side of the layer plate (6), and connecting the lightning receptor (1) to the grounding grid (2); S3, building floor construction; S31, foundation pit excavation: excavating the foundation pit under the floor plate (6) until the depth of the foundation pit meets the height requirement of the next floor of the building; S32, pouring of the layer plate (6): pouring the layer plate (6) at the bottom of the foundation pit as the bottom plate of the corresponding floor, and pre-embedding the grounding electrode (4) in the layer plate (6), and connecting the pre-embedded grounding electrode (4) to the structural steel bars in the layer plate (6); S33, when the layer plate (6) solidifies, connecting the ground electrode (4) to the nearest main electrode (3); S4. Repeat step S3 until the number of floors of the building meets the requirement.