Deepwater diamond wire sawing machine

By designing a deep-water diamond wire saw in the marine platform removal technology, the buoyant frame and lifting assembly and pulley assembly are used to achieve serrated cutting, solving the problem of the diamond wire saw and the tilt of the chamfered saw and the conduit frame, and improving the deep-water Cutting reliability.

CN118927422APending Publication Date: 2024-11-12SHENZHEN OFFSHORE OIL ENG UNDERWATER TECH CO LTD
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202411132027.6
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-19
Publication Date
2024-11-12

AI Technical Summary

Technical Problem

In the existing marine platform removal technology, diamond wire sawing often occurs in clamping, and the cut upper conduit frame is easily dumped due to the deviation of the center of gravity, which affects the reliability of deep water cutting.

Method used

A deep-water diamond wire saw machine is designed, using a buoyant frame and clamping assembly to fix the conduit frame, and through the cooperation of the first and second lifting components and the pulley assembly, the conduit frame is cut by beaded rope to form a zigzag-shaped special-shaped cutout. Avoid clip sawing and prevent the catheter from tipping.

Benefits of technology

Through the intermeshing of serrated cuts, the occurrence of clip sawing is avoided, and the conduit frame is prevented from tipping under gravity or seawater disturbances, reducing the use of offshore lifting equipment and improving the reliability of deep water cutting.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118927422A_ABST
    Figure CN118927422A_ABST
Patent Text Reader

Abstract

The invention discloses a deepwater diamond wire sawing machine which comprises a buoyancy frame, a clamping assembly is arranged on the buoyancy frame, a jacket is fixedly clamped on the buoyancy frame through the clamping assembly, a first pulley assembly is arranged on a first lifting assembly in the axial direction of the jacket in a lifting mode, and a second pulley assembly is arranged on a second lifting assembly in the axial direction of the jacket. The first lifting assembly is provided with a first pulley assembly in the axial direction of the jacket in a lifting mode, the second lifting assembly is provided with a second pulley assembly in the axial direction of the jacket in a lifting mode, the first pulley assembly and the second pulley assembly are connected through a beaded rope, and the first pulley assembly and / or the second pulley assembly ascend and descend relative to the buoyancy frame in the axial direction of the jacket so that the jacket can be cut into two sections with irregular sections. According to the deepwater diamond wire sawing machine, the guide pipe frame is cut into the sawtooth-shaped special-shaped notches, through mutual meshing of the upper notches and the lower notches, the saw clamping phenomenon can be avoided, the cut upper guide pipe frame can be prevented from toppling over under the influence of gravity or seawater disturbance, and use of offshore hoisting equipment is reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of marine engineering demolition, and in particular relates to a deep-water diamond wire saw machine. Background Art

[0002] With the enhancement of underwater oil and gas exploration capabilities, the exploitation of marine oil and gas resources has gradually shifted from shallow water to deep water. The design life of general marine oil and gas facilities is about 20 to 30 years. According to legal requirements, these facilities must be properly decommissioned and abandoned after reaching the economic life cycle or are no longer in use. Due to the high cost of decommissioning and abandonment of marine facilities and the strict requirements of relevant laws, how to safely, cleanly and efficiently dismantle these marine facilities has gradually become an important issue in marine oil and gas engineering.

[0003] Existing offshore platform demolition techniques mainly include underwater thermal cutting and underwater cold cutting. Underwater thermal cutting mainly includes oxidation cutting, melting cutting and melting-oxidation cutting, etc., which have the advantages of high efficiency and simple equipment, but require qualified divers who have undergone relevant operation training to complete the cutting operation underwater. It is also limited by the operating water depth, and the safety is poor, and it has great harm to the environment; underwater cold cutting includes shaped energy blasting and underwater mechanical cutting such as abrasive water jet and diamond wire saw. Shaped energy blasting requires placing a shaped energy cutting knife at the cutting pipe column, and then detonating explosives, high-pressure gas is ejected, and the pipe is cut under high temperature and high pressure, and the cut fracture presents an extremely irregular morphology. Because this cutting technology has relatively large safety hazards, it will endanger the ecological environment of the ocean and cause ecological pollution; abrasive water jet and underwater diamond wire saw are commonly used underwater demolition tools in recent years, and their operation process is clean, green and efficient. However, there are also some shortcomings in actual engineering. Abrasive water jet operations require a large number of supporting tools on the mother ship and the maintenance and management costs are high. Diamond wire saws often get stuck, and the upper conductor frame after cutting is prone to tipping over due to the shift in the center of gravity, affecting the reliability of deep-water cutting.

[0004] Therefore, it is urgent to design a deepwater diamond wire saw machine to solve the above-mentioned problems that the diamond wire saw machine often gets stuck and the upper conductor frame after cutting is prone to tipping over due to the center of gravity offset, which affects the reliability of deepwater cutting. Summary of the invention

[0005] In order to solve the technical problems mentioned in the background technology that the diamond wire saw machine often gets stuck and the upper conductor frame after cutting is prone to tipping over due to the center of gravity offset, which affects the reliability of deep-water cutting, a deep-water diamond wire saw machine is provided to solve the above problems.

[0006] To achieve the above purpose, the specific technical solution of the deep-water diamond wire saw machine of the present invention is as follows: A deepwater diamond wire saw comprises a buoyancy frame, a clamping assembly is arranged on the buoyancy frame, the clamping assembly fixes and clamps a conductor frame on the buoyancy frame, a first bracket and a second bracket are arranged horizontally in the buoyancy frame, a first lifting assembly is arranged on the first bracket, a first pulley assembly is arranged on the first lifting assembly for lifting and lowering the first lifting assembly along the axial direction of the conductor frame, a second lifting assembly is arranged on the second bracket, a second pulley assembly is arranged on the second lifting assembly for lifting and lowering the second lifting assembly along the axial direction of the conductor frame, the first pulley assembly and the second pulley assembly are connected by a beaded rope, the beaded rope moves along the radial direction of the conductor frame for cutting the conductor frame, the first pulley assembly and / or the second pulley assembly are lifted and lowered relative to the buoyancy frame along the axial direction of the conductor frame to cut the conductor frame into two sections with irregular cross-sections.

[0007] Furthermore, the first lifting assembly includes a first vertical plate and a first driving member. The first vertical plate is vertically arranged with the first bracket. A first slideway is arranged on the first vertical plate. A first slider is arranged on the first pulley assembly. The first slider is slidably arranged in the first slideway. The first driving member is connected with the first slider. The first driving member drives the first slider to slide in the first slideway so that the first pulley assembly is lifted and lowered along the axial direction of the catheter frame.

[0008] Furthermore, the second lifting assembly includes a second vertical plate and a second driving member, the second vertical plate is vertically arranged with the second bracket, a second slide is arranged on the second vertical plate, a second slider is arranged on the second pulley assembly, the second slider is slidably arranged in the second slide, the second driving member is connected with the second slider, and the second driving member drives the second slider to slide in the second slide, so that the second pulley assembly is lifted and lowered along the axial direction of the catheter frame.

[0009] Furthermore, the first pulley assembly includes a first cutting frame, the first slider is arranged on the first cutting frame, and the second pulley assembly includes a second cutting frame, the second slider is arranged on the second cutting frame.

[0010] Furthermore, a first driving pulley and a first driven pulley are fixedly provided on the first cutting frame, a first feed wheel and a sliding wheel are slidably provided on the first cutting frame along the length direction of the first cutting frame, a second driving pulley and a second driven pulley are fixedly provided on the second cutting frame, a second feed wheel and a tensioning wheel are slidably provided on the second cutting frame along the length direction of the second cutting frame, and the bead rope is connected end to end and is sequentially wound around the first driving pulley, the sliding wheel, the first driven pulley, the second driven pulley, the tensioning wheel, the second driving pulley, the second feed wheel and the first feed wheel.

[0011] Furthermore, two first cutting frames are provided, the two first cutting frames are arranged in parallel, the first feed wheel is slidably arranged on one first cutting frame, and the sliding wheel is slidably arranged on the other first cutting frame.

[0012] Furthermore, two second cutting frames are provided, the two second cutting frames are arranged in parallel, the second feed wheel is slidably arranged on one second cutting frame, and the tensioning wheel is slidably arranged on the other second cutting frame.

[0013] Furthermore, it also includes a third drive motor, a first lead screw and a second lead screw. The third drive motor is arranged at one end of the first lead screw. The first lead screw and the second lead screw are connected by a chain drive. The first lead screw is rotatably arranged on a first cutting frame, and a first lead screw nut is screwed on the first lead screw. The first lead screw nut is connected to the first feed wheel. The second lead screw is rotatably arranged on another first cutting frame, and a second lead screw nut is screwed on the second lead screw. The second lead screw nut is connected to the sliding wheel.

[0014] Furthermore, it also includes a fourth drive motor and a third lead screw. The fourth drive motor is arranged at one end of the third lead screw. The third lead screw is rotatably arranged on a second cutting frame. The third lead screw is threaded with a third lead screw nut, and the third lead screw nut is connected to the second feed wheel.

[0015] Furthermore, it also includes a guide rod and a spring. A fixed seat is provided on another second cutting frame. One end of the guide rod is arranged on the fixed seat. The other end of the guide rod passes through the tensioning wheel. The spring is sleeved outside the guide rod. The spring end abuts against the fixed seat. The other end of the spring abuts against the tensioning wheel.

[0016] The deep-water diamond wire saw machine of the present invention has the following advantages: A first lifting assembly is arranged on the first bracket, and the first lifting assembly is provided with a first pulley assembly for lifting along the axial direction of the jacket, and a second lifting assembly is arranged on the second bracket, and the second lifting assembly is provided with a second pulley assembly for lifting along the axial direction of the jacket, the first pulley assembly and the second pulley assembly are connected by a beaded rope, and the beaded rope moves along the radial direction of the jacket for cutting the jacket, and the first pulley assembly and / or the second pulley assembly are lifted and lowered relative to the buoyancy frame along the axial direction of the jacket to cut the jacket into two sections with irregular cross-sections, and the jacket is cut into serrated special-shaped incisions, and the upper and lower incisions are engaged with each other, which can not only avoid the sawing phenomenon, but also prevent the upper jacket after cutting from tipping over under the influence of gravity or seawater disturbance, thereby reducing the use of offshore lifting equipment. BRIEF DESCRIPTION OF THE DRAWINGS

[0017] Figure 1 The structure of the deep water diamond wire saw machine of the present invention is shown in FIG. Figure 1 ; Figure 2 The structure of the deep water diamond wire saw machine of the present invention is shown in FIG. Figure 2 ; Figure 3 It is a front view of the deep-water diamond wire saw machine of the present invention; Figure 4 for Figure 3 A is a schematic diagram of the enlarged structure of the middle part; Figure 5 It is a rear view of the deep-water diamond wire saw machine of the present invention; Figure 6 It is a structural schematic diagram of the first lifting assembly of the present invention; Figure 7 It is a structural schematic diagram of the second lifting assembly of the present invention; Figure 8 It is a structural schematic diagram of the arrangement of the beaded rope of the present invention; Fig. 9 This is a schematic diagram of the structure of the conductor pipe frame after cutting of the present invention; Fig.10 It is a structural schematic diagram of the buoyancy frame of the present invention.

[0018] Description of the markings in the figure: 100, buoyancy frame; 200, catheter frame; 201, first incision; 202, second incision; 203, third incision; 204, fourth incision; 300, beaded rope; 401, first support; 402, second support; 403, third support; 404, fourth support; 405, fifth support; 406, sixth support; 407, seventh support; 408, eighth support; 1, clamping assembly; 11 clamping and fixing square steel; 12, first connecting plate; 13, second connecting plate; 14, clamping arm; 15, hydraulic cylinder; 16, roller; 2, first bracket; 3, second bracket; 4, first lifting assembly; 41, first vertical plate; 411, first slide; 42, first driving member; 43, first turbine; 44, first worm Rod; 45, first connecting rod; 5, second lifting assembly; 51, second vertical plate; 511, second slide; 52, second driving member; 53, second turbine; 54, second worm; 55, second connecting rod; 6, first pulley assembly; 61, first cutting frame; 62, first driving pulley; 63, first driven pulley; 64, first feed wheel; 65, sliding wheel; 66, first driving motor; 67, third driving motor; 68, first lead screw; 69, second lead screw; 7, second pulley assembly; 71, second cutting frame; 72, second driving pulley; 73, second driven pulley; 74, second feed wheel; 75, tensioning wheel; 76, second driving motor; 77, fourth driving motor; 78, third lead screw; 8, guide rod; 9, spring. DETAILED DESCRIPTION

[0019] In order to make the purpose, technical solution and advantages of the embodiments of the present invention clearer, the technical solution in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those skilled in the art without creative work are within the scope of protection of the present invention.

[0020] Those skilled in the art will appreciate that, although some embodiments herein include certain features included in other embodiments but not other features, the combination of features of different embodiments is meant to be within the scope of the present invention and form different embodiments. For example, in the claims, any one of the claimed embodiments may be used in any combination.

[0021] Please refer to the attached Figure 1 To Attachment Fig.10 A deep water diamond wire saw machine according to the present invention is described.

[0022] like Figures 1 to 5 As shown, the deepwater diamond wire saw machine in the present invention includes a buoyancy frame 100, and a clamping assembly 1 is arranged on the buoyancy frame 100. The clamping assembly 1 fixes and clamps the catheter frame 200 on the buoyancy frame 100. A first bracket 2 and a second bracket 3 are horizontally arranged in the buoyancy frame 100. A first lifting assembly 4 is arranged on the first bracket 2. The first lifting assembly 4 is provided with a first pulley assembly 6 for lifting and lowering along the axial direction of the catheter frame 200. A second lifting assembly 5 is arranged on the second bracket 3. The second lifting assembly 5 is provided with a second pulley assembly 7 for lifting and lowering along the axial direction of the catheter frame 200. The first pulley assembly 6 and the second pulley assembly 7 are connected by a beaded rope 300. The beaded rope 300 moves along the radial direction of the catheter frame 200 for cutting the catheter frame 200. The first pulley assembly 6 and / or the second pulley assembly 7 are lifted and lowered relative to the buoyancy frame 100 along the axial direction of the catheter frame 200 to cut the catheter frame 200 into two sections with irregular cross-sections.

[0023] A first lifting assembly 4 is provided on the first bracket 2, and the first lifting assembly 4 is provided with a first pulley assembly 6 for lifting along the axial direction of the jacket 200; a second lifting assembly 5 is provided on the second bracket 3, and the second lifting assembly 5 is provided with a second pulley assembly 7 for lifting along the axial direction of the jacket 200; the first pulley assembly 6 and the second pulley assembly 7 are connected by a beaded rope 300, and the beaded rope 300 moves along the radial direction of the jacket 200 for cutting the jacket 200; the first pulley assembly 6 and / or the second pulley assembly 7 are lifted and lowered relative to the buoyancy frame 100 along the axial direction of the jacket 200 to cut the jacket 200 into two sections with irregular cross-sections, and the jacket 200 is cut into a serrated special-shaped incision; the upper and lower incisions are meshed with each other, which can not only avoid the sawing phenomenon, but also prevent the upper jacket 200 from tipping over under the influence of gravity or seawater disturbance after cutting, thereby reducing the use of offshore lifting equipment.

[0024] Further, if Figures 2 to 6 As shown, the first lifting assembly 4 includes a first vertical plate 41 and a first driving member 42. The first vertical plate 41 is vertically arranged with the first bracket 2, that is, the first vertical plate 41 is parallel to the axial direction of the wire tube. A first slideway 411 is arranged on the first vertical plate 41, and the first slideway 411 is parallel to the axial direction of the guide tube. A first slider is arranged on the first pulley assembly 6, and the first slider is slidably arranged in the first slideway 411. The first driving member 42 is connected with the first slider, and the first driving member 42 drives the first slider to slide in the first slideway 411, so that the first pulley assembly 6 is lifted and lowered along the axial direction of the catheter frame 200.

[0025] In this embodiment, the first lifting assembly 4 includes two first vertical plates 41, the two first vertical plates 41 are arranged on the first bracket 2 at intervals, the first pulley assembly 6 is arranged between the two first vertical plates 41, one end of the first pulley assembly 6 is slidably arranged on one first vertical plate 41, and the other end of the first pulley assembly 6 is slidably arranged on the other first vertical plate 41, and both ends of the first pulley assembly 6 are provided with first sliders, and the first lifting assembly 4 also includes two first turbines 43 and two first worms 44, and the two ends of the first pulley assembly 6 are respectively provided with a first turbine 43 and a first worm 44, the first turbine 43 cooperates with the first worm 44, and the two first worms 44 are parallel to the first slideway 411, and the two first turbines 43 are connected by a first connecting rod 45 The first drive member 42 is arranged on one of the first worms 44. The first drive member 42 drives the first turbine 43 to rotate, so that the first worm 44 matched with the first turbine 43 rotates, and then the first pulley assembly 6 matched with the first worm 44 moves along the axial direction of the first worm 44, and then drives the first slider to slide in the first slideway 411. Since the two first turbines 43 are connected by the first connecting rod 45, when the first drive member 42 drives one of the first turbines 43 to rotate, the two first turbines 43 will be driven to rotate synchronously at the same time, and then the two first worms 44 will be driven to rotate synchronously, so that the two ends of the first pulley assembly 6 will be raised and lowered synchronously, and the lifting and lowering movement of the first sliding assembly is realized through the first lifting assembly 4. In other embodiments, the cooperation between the first turbine 43 and the first worm 44 can also be replaced by a lifting cylinder or a push rod to realize the lifting and lowering of the first pulley assembly 6.

[0026] Further, if Figures 2 to 7 As shown, the second lifting assembly 5 includes a second vertical plate 51 and a second driving member 52. The second vertical plate 51 is vertically arranged with the second bracket 3. A second slideway 511 is arranged on the second vertical plate 51. A second slider is arranged on the second pulley assembly 7. The second slider is slidably arranged in the second slideway 511. The second driving member 52 is connected to the second slider. The second driving member 52 drives the second slider to slide in the second slideway 511, so that the second pulley assembly 7 is lifted and lowered along the axial direction of the catheter frame 200.

[0027] The second lifting assembly 5 includes two second vertical plates 51, the two second vertical plates 51 are spaced apart on the second bracket 3, the second pulley assembly 7 is arranged between the two second vertical plates 51, the two ends of the second pulley assembly 7 are slidably arranged on one second vertical plate 51, the other end of the second pulley assembly 7 is slidably arranged on the other second vertical plate 51, and second sliders are arranged at both ends of the second pulley assembly 7. The second lifting assembly 5 also includes two second turbines 53 and two second worms 54, a second turbine 53 and a second worm 54 are arranged at both ends of the second pulley assembly 7, the second turbine 53 cooperates with the second worm 54, the two second worms 54 are parallel to the second slideway 511, and the two second turbines 53 are connected by a second connecting rod 55. The second driving member 52 is arranged on one of the second worms 54. The second driving member 52 drives the second turbine 53 to rotate, so that the second worm 54 matched with the second turbine 53 rotates, and then the second pulley assembly 7 matched with the second worm 54 moves along the axial direction of the second worm 54, and then drives the second slider to slide in the second slideway 511. Since the two second turbines 53 are connected by the second connecting rod 55, when the second driving member 52 drives one of the second turbines 53 to rotate, the two second turbines 53 will be driven to rotate synchronously at the same time, and then the two second worms 54 will be driven to rotate synchronously, so that the two ends of the second pulley assembly 7 will be raised and lowered synchronously, and the lifting and lowering movement of the second sliding assembly is realized by the second lifting assembly 5. In other embodiments, the cooperation between the second turbine 53 and the second worm 54 can also be replaced by a lifting cylinder or a push rod to realize the lifting and lowering of the second pulley assembly 7.

[0028] Further, if Figures 1 to 6 As shown, the first pulley assembly 6 includes a first cutting frame 61, and the first slider is arranged on the first cutting frame 61. The second pulley assembly 7 includes a second cutting frame 71, and the second slider is arranged on the second cutting frame 71. In this embodiment, the first slider is arranged at both ends of the first cutting frame 61, and the second slider is arranged at both ends of the second cutting frame 71. The first lifting assembly 4 realizes the lifting movement of the first cutting frame 61, and the second lifting assembly 5 realizes the lifting movement of the second cutting frame 71.

[0029] Further, if Figures 1 to 6As shown, the first cutting frame 61 is fixedly provided with a first driving pulley 62 and a first driven pulley 63, the first cutting frame 61 is slidably provided with a first feed wheel 64 and a sliding wheel 65 along the length direction of the first cutting frame 61, the second cutting frame 71 is fixedly provided with a second driving pulley 72 and a second driven pulley 73, the second cutting frame 71 is slidably provided with a second feed wheel 74 and a tensioning wheel 75 along the length direction of the second cutting frame 71, and the bead rope 300 is connected end to end and is sequentially wound around the first driving pulley 62, the sliding wheel 65, the first driven pulley 63, the second driven pulley 73, the tensioning wheel 75, the second driving pulley 72, the second feed wheel 74 and the first feed wheel 64. The first driving pulley 62 is connected to the first driving motor 66, and the first driving motor 66 rotates to drive the first driving pulley 62 to rotate. The second driving pulley 72 is connected to the second driving motor 76, and the second driving motor 76 rotates to drive the second driving pulley 72 to rotate, thereby realizing high-speed rotation of the bead rope 300 on the first driving pulley 62, the sliding wheel 65, the first driven pulley 63, the second driven pulley 73, the tensioning wheel 75, the second driving pulley 72, the second feed wheel 74 and the first feed wheel 64, thereby realizing the cutting function of the bead rope 300.

[0030] Further, the first driving pulley 62 and the second driving pulley 72 have the same structure, and both include a driving wheel inner ring, a driving wheel outer ring, a driving wheel rubber ring, a driving wheel bearing, a driving wheel bearing end cover, a driving wheel seal, a conical table center shaft, a driving wheel hydraulic motor and a coupling, and the conical table center shaft is connected and fixed to the first cutting frame 61 by bolts. The first feed wheel 64, the second feed wheel 74, the first driven pulley 63, the second driven pulley 73, the tensioning wheel 75 and the sliding wheel 65 have the same structure, and both include an inner ring, an outer ring, a rubber ring, a bearing, a bearing end cover, a seal and a center shaft, and the first feed wheel 64, the second feed wheel 74, the first driven pulley 63, the second driven pulley 73, the tensioning wheel 75 and the sliding wheel 65 are respectively sleeved on the outside of the first cutting frame 61 and the second cutting frame 71 through a support.

[0031] Further, if Figure 5As shown, the deepwater diamond wire saw machine in the present invention also includes a first support 401, a second support 402, a third support 403, a fourth support 404, a fifth support 405, a sixth support 406, a seventh support 407 and an eighth support 408, the first driving pulley 62 is rotatably set on the first support 401, the first driven pulley 63 is rotatably set on the second support 402, the first feed wheel 64 is rotatably set on the third support 403, and the sliding wheel 65 is rotatably set on the fourth support 404, wherein the first support 401 is fixedly set between the two first cutting frames 61, the second support 402 is fixedly set on one first cutting frame 61, the fourth support 404 is slidably set on one first cutting frame 61, and the third support 403 is slidably set on the other first cutting frame 61. The second driving pulley 72 is rotatably set on the fifth support 405, the second driven pulley 73 is rotatably set on the sixth support 406, the second feed wheel 74 is rotatably set on the seventh support 407, and the tensioning wheel 75 is rotatably set on the eighth support 408, wherein the fifth support 405 is fixedly set between the two second cutting frames 71, the sixth support 406 is fixedly set on one second cutting frame 71, the seventh support 407 is slidably set on one second cutting frame 71, and the eighth support 408 is slidably set on the other second cutting frame 71.

[0032] In this embodiment, when the sliding wheel 65 moves along the first chip rack toward the first driving wheel, the first feed wheel 64 moves along the first cutting rack 61 toward the direction away from the first driving wheel, and at the same time, the second feed wheel 74 moves along the second cutting rack 71 toward the direction away from the second driving wheel, so that the beaded rope 300 between the first feed wheel 64 and the second feed wheel 74 gradually approaches the guide tube to cut the guide tube, and the position changes among the first feed wheel 64, the second feed wheel 74 and the sliding wheel 65 cause the same change in the rope length of the beaded rope 300. This rope wheel arrangement scheme increases the rope length of the beaded rope 300 without increasing the overall size of the deep-water diamond wire saw machine, and provides necessary guarantee for completing the pile foundation cutting operation of the conductor frame 200 in one dive installation.

[0033] Further, if Figures 1 to 5As shown, two first cutting frames 61 are provided, and the two first cutting frames 61 are arranged in parallel, the first feed wheel 64 is slidably provided on one first cutting frame 61, and the sliding wheel 65 is slidably provided on the other first cutting frame 61. In this embodiment, two first cutting frames 61 are provided, which can not only support the first driving pulley 62, the first driven pulley 63, the first feed wheel 64 and the sliding wheel 65, but also guide the first feed wheel 64 and the sliding wheel 65 so that the first feed wheel 64 and the sliding wheel 65 can move along the length direction of the first cutting frame 61. In this embodiment, in order to facilitate the first feed wheel 64 and the sliding wheel 65 to slide on the first cutting frame 61, rollers 16 are provided on the first feed wheel 64 and the sliding wheel 65 to reduce the friction force when the first feed wheel 64 and the sliding wheel 65 slide on the first cutting frame 61.

[0034] Further, if Figures 1 to 5 As shown, two second cutting frames 71 are provided, and the two second cutting frames 71 are arranged in parallel, the second feed wheel 74 is slidably arranged on one second cutting frame 71, and the tension wheel 75 is slidably arranged on the other second cutting frame 71. In this embodiment, two second cutting frames 71 are provided, which can not only support the second driving pulley 72, the second driven pulley 73, the second feed wheel 74 and the tension wheel 75, but also guide the second feed wheel 74 and the tension wheel 75 so that the second feed wheel 74 and the tension wheel 75 can move along the length direction of the second cutting frame 71. In this embodiment, in order to facilitate the sliding of the second feed wheel 74 and the tension wheel 75 on the second cutting frame 71, rollers 16 are provided on the second feed wheel 74 and the tension wheel 75 to reduce the friction force when the second feed wheel 74 and the tension wheel 75 slide on the second cutting frame 71.

[0035] Further, if Figures 1 to 6As shown, the deep-water diamond wire saw machine in the present invention also includes a third drive motor 67, a first lead screw 68 and a second lead screw 69. The third drive motor 67 is arranged at one end of the first lead screw 68. The first lead screw 68 and the second lead screw 69 are connected by a chain drive. The first lead screw 68 is rotatably arranged on a first cutting frame 61. The first lead screw 68 is screwed with a first lead screw 68 nut, and the first lead screw 68 nut is connected to the first feed wheel 64. The second lead screw 69 is rotatably arranged on another first cutting frame 61. The second lead screw 69 is screwed with a second lead screw 69 nut, and the second lead screw 69 nut is connected to the sliding wheel 65. When the third drive motor 67 drives the first lead screw 68 to rotate, the second lead screw 69 chain-drivenly connected to the first lead screw 68 will also rotate. The rotation directions of the first lead screw 68 and the second lead screw 69 are opposite. The first lead screw 68 nut matched with the first lead screw 68 will drive the first feed wheel 64 to move along the length direction of the first cutting frame 61, and the second lead screw 69 matched with the second lead screw 69 will drive the sliding wheel 65 to move along the length direction of the first cutting frame 61. The directions in which the first feed wheel 64 and the sliding wheel 65 move on the first cutting frame 61 are opposite.

[0036] Further, if Figures 1 to 7 As shown, the deepwater diamond wire saw machine of the present invention further includes a fourth drive motor 77 and a third lead screw 78. The fourth drive motor 77 is disposed at one end of the third lead screw 78. The third lead screw 78 is rotatably disposed on a second cutting frame 71. A third lead screw 78 nut is threadedly connected to the third lead screw 78. The third lead screw 78 nut is connected to the second feed wheel 74. The third lead screw 78 has the same rotation direction as the first lead screw 68. When the fourth drive motor 77 drives the third lead screw 78 to rotate, the third lead screw 78 nut matched with the third lead screw 78 drives the second feed wheel 74 to move along the length direction of the second cutting frame 71.

[0037] The first feed wheel 64 and the second feed wheel 74 move synchronously, and the beaded rope 300 wound around the first feed wheel 64 and the second feed wheel 74 will cut the guide tube. The first lifting assembly 4 lifts the first cutting frame 61 to lift the first feed wheel 64, or the second lifting assembly 5 lifts the second cutting frame 71. The lifting of the second feed wheel 74 is realized by feeding, and the catheter frame 200 is cut into a sawtooth-shaped special-shaped incision. The mutual engagement of the upper and lower incisions can not only avoid the saw clamping phenomenon, but also prevent the upper catheter frame 200 from tipping over under the influence of gravity or seawater disturbance after cutting, thereby reducing the use of offshore lifting equipment.

[0038] Further, if Figure 7As shown, the deepwater diamond wire saw machine of the present invention further includes a guide rod 8 and a spring 9, a fixing seat is arranged on another second cutting frame 71, one end of the guide rod 8 is arranged on the fixing seat, the other end of the guide rod 8 is arranged through the tensioning wheel 75, the spring 9 is sleeved outside the guide rod 8, one end of the spring 9 abuts against the fixing seat, and the other end of the spring 9 abuts against the tensioning wheel 75. The tensioning of the dynamic spring 9 on the tensioning wheel 75 can adjust the tensioning force of the beaded rope 300 in real time, so as to avoid the beaded rope 300 from breaking due to excessive tensioning force or stopping working due to "stuck car".

[0039] Further, if Fig.10 As shown, the buoyancy frame 100 is formed by vertically or obliquely welding a plurality of steel pipes. The welded steel pipes remain sealed, mainly providing support and protection for the fixed integration of other components, and at the same time providing a certain buoyancy for the whole machine, reducing its weight in water. In this embodiment, the buoyancy frame 100 is a U-shaped buoyancy frame 100. The buoyancy frame 100 is set to a U-shaped structure, which is convenient for positioning the catheter frame 200. The catheter frame 200 is placed in the U-shaped groove of the buoyancy frame 100. At the same time, the catheter frame 200 is clamped on the buoyancy frame 100 by the clamping assembly 1, so as to fix the guide pipe and facilitate cutting of the guide pipe.

[0040] Further, if Figure 3 As shown, the clamping assembly 1 is arranged on the buoyancy frame 100, and the clamping assembly 1 includes a hydraulic cylinder 15, a piston rod and a clamping arm 14. The clamping assembly 1 includes a clamping and fixing square steel, a first connecting plate 11, a clamping and fixing square steel; 12, a second connecting plate 13, a clamping arm 14, a hydraulic cylinder 15 and a roller 16. The clamping and fixing square steel is welded at the U-shaped groove of the external buoyancy frame 100, and the first connecting plate 11 clamps and fixes the square steel; 12 and the second connecting plate 13 are arranged at intervals on the clamping and fixing square steel, the first connecting plate 11 clamps and fixes the square steel; 12 and the second connecting plate 13 are connected to the clamping and fixing square steel by bolts, one end of the hydraulic cylinder 15 is hinged with the first connecting plate 11 clamps and fixes the square steel; 12, the driving end of the other end of the hydraulic cylinder 15 is hinged with the middle part of the clamping arm 14, the second connecting plate 13 is connected with one end of the clamping arm 14, and the adjustment of the clamping arm 14 is realized by the extension and contraction of the driving end of the hydraulic cylinder 15. The roller 16 is arranged at one end of the clamping arm 14 to contact the guide tube to avoid scratches on the guide tube when the clamping arm 14 clamps the guide tube. In this embodiment, clamping assemblies 1 are arranged on both sides of the U-shaped groove. In order to better fix the catheter frame 200, two clamping assemblies 1 are arranged on both sides of the U-shaped groove. In this embodiment, the clamping assembly 1 is configured as the above structure, which avoids the situation that the piston rod of the hydraulic cylinder 15 is deformed due to the bending moment caused by the deadweight of the diamond wire saw machine.

[0041] In the actual application of deepwater diamond wire saw machine to cut the jacket 200 or pile foundation, after lowering the deepwater wire saw machine to a specified distance, it is assisted by an underwater robot to be installed at the position of the jacket 200 to be cut, and the U-shaped groove of the buoyancy frame 100 is used to realize the centering and positioning of the guide pipe. The clamping device hydraulic cylinder 15 pushes the clamping arm 14 to hold the jacket 200 tightly, so as to realize the underwater fixation of the wire saw machine.

[0042] like Figures 1 to 9 As shown, the following is an embodiment of cutting the catheter rack 200.

[0043] In the actual application of deepwater diamond wire saw to cut the jacket 200 or pile foundation, after lowering the deepwater diamond wire saw to the specified distance, it is assisted by an underwater robot to be installed at the position of the jacket 200 to be cut, and the U-shaped groove of the external buoyancy frame 100 is used to achieve centering and positioning. The rodless cavity of the clamping device hydraulic cylinder 15 is passed with oil, and the clamping arm 14 is pushed to hold the jacket 200 tightly, so as to achieve underwater fixation of the wire saw.

[0044] The third drive motor 67 on the first drive pulley 62 and the fourth drive motor 77 on the second drive pulley 72 respectively drive the first drive pulley 62 and the second drive pulley 72 to rotate, so that the bead rope 300 rotates at a high speed, the third drive motor 67 drives the first lead screw 68 and the second lead screw 69 to rotate, and the fourth drive motor 77 drives the third lead screw 78 to rotate, so that the first feed wheel 64 and the second feed wheel 74 move synchronously toward the direction close to the guide tube, such as Figure 8 In the direction indicated by L1, the sliding wheel 65 moves away from the guide tube, as shown in FIG. Figure 8 In the direction indicated by L2, until the bead string 300 is tangent to the guide tube, at which time, the bead string 300 between the first feed wheel 64 and the second feed wheel 74 is parallel to the horizontal plane; The first lifting assembly 4 remains stationary, and the second lifting assembly 5 makes the second cutting frame 71 rise along the axial direction of the guide tube, so that the second driving pulley 72, the second driven pulley 73, the second feed wheel 74 and the tensioning wheel 75 rise along the axial direction of the guide tube. At this time, a certain angle is formed between the bead rope 300 between the first feed wheel 64 and the second feed wheel 74 and the horizontal plane, and the height of the first feed wheel 64 relative to the horizontal plane is lower than the height of the second feed wheel 74 relative to the horizontal plane. The third drive motor 67 drives the first lead screw 68 and the second lead screw 69 to rotate, and the fourth drive motor 77 drives the third lead screw 78 to rotate, so that the first feed wheel 64 and the second feed wheel 74 move synchronously in the direction close to the guide tube, and the sliding wheel 65 moves in the direction away from the guide tube, and the bead rope 300 cuts the guide tube to achieve the first incision 201; The first lifting assembly 4 causes the first cutting frame 61 to rise in the axial direction of the guide tube, so that the first driving pulley 62, the first driven pulley 63, the first feeding wheel 64 and the sliding wheel 65 rise in the axial direction of the guide tube, and the second lifting assembly 5 causes the second cutting frame 71 to descend in the axial direction of the guide tube, so that the second driving pulley 72, the second driven pulley 73, the second feeding wheel 74 and the tensioning wheel 75 rise in the axial direction of the guide tube. At this time, a certain angle is formed between the bead rope 300 between the first feeding wheel 64 and the second feeding wheel 74 and the horizontal plane, and the height of the first feeding wheel 64 relative to the horizontal plane is higher than the height of the second feeding wheel 74 relative to the horizontal plane. The third driving motor 67 drives the first screw 68 and the second screw 69 to rotate, and the fourth driving motor 77 drives the third screw 78 to rotate, so that the first feeding wheel 64 and the second feeding wheel 74 move synchronously in the direction close to the guide tube, and the sliding wheel 65 moves in the direction away from the guide tube, and the bead rope 300 continues to cut the guide tube to achieve the second incision 202; The first lifting assembly 4 causes the first cutting frame 61 to rise down along the axial direction of the guide tube, so that the first driving pulley 62, the first driven pulley 63, the first feeding wheel 64 and the sliding wheel 65 rise down along the axial direction of the guide tube, and the second lifting assembly 5 causes the second cutting frame 71 to descend along the axial direction of the guide tube, so that the second driving pulley 72, the second driven pulley 73, the second feeding wheel 74 and the tensioning wheel 75 rise along the axial direction of the guide tube. At this time, a certain angle is formed between the bead rope 300 between the first feeding wheel 64 and the second feeding wheel 74 and the horizontal plane, and the height of the first feeding wheel 64 relative to the horizontal plane is lower than the height of the second feeding wheel 74 relative to the horizontal plane. The third driving motor 67 drives the first screw 68 and the second screw 69 to rotate, and the fourth driving motor 77 drives the third screw 78 to rotate, so that the first feeding wheel 64 and the second feeding wheel 74 move synchronously toward the direction close to the guide tube, and the sliding wheel 65 moves toward the direction away from the guide tube, and the bead rope 300 continues to cut the guide tube to achieve the third incision 203; The second lifting assembly 5 remains stationary, and the first lifting assembly 4 makes the first cutting frame 61 rise along the axial direction of the guide tube, so that the first driving pulley 62, the first driven pulley 63, the first feed wheel 64 and the sliding wheel 65 rise along the axial direction of the guide tube. At this time, a certain angle is formed between the bead rope 300 between the first feed wheel 64 and the second feed wheel 74 and the horizontal plane. The height of the first feed wheel 64 relative to the horizontal plane is higher than the height of the second feed wheel 74 relative to the horizontal plane. The third driving motor 67 drives the first screw 68 and the second screw 69 to rotate, and the fourth driving motor 77 drives the third screw 78 to rotate, so that the first feed wheel 64 and the second feed wheel 74 move synchronously in the direction close to the guide tube, and the sliding wheel 65 moves in the direction away from the guide tube. The bead rope 300 cuts the guide tube until the guide tube is completely cut, thereby realizing the fourth incision 204. After the deepwater diamond wire saw machine completes the cutting operation, the underwater robot uses hydraulic shears to cut the diamond beaded wire 300, the hydraulic cylinder 15 in the clamping assembly 1 has oil inlet to the rod chamber and oil return to the non-rod chamber, and the clamping arm 14 is retracted. The underwater robot assists in recovering the wire saw machine to the working mother ship, and timely performs equipment maintenance and scientific storage. In other embodiments, by controlling the first lifting assembly 4 and the second lifting assembly 5, other forms of cutting of the guide tube can also be achieved, as long as the guide tube can be cut into a sawtooth-shaped special-shaped incision, and the upper and lower incisions are meshed with each other to avoid the occurrence of the saw clamping phenomenon.

[0045] The cross-section of the two parts of the beaded rope 300 after cutting the guide tube is Fig. 9 As shown in the cross section, the deepwater diamond wire saw can dismantle the pipe frame 200 or pile foundation with a diameter of 60~84in at 1500m underwater. On this basis, a new rope wheel arrangement scheme for the wire saw is formulated. Without increasing the size of the wire saw, the rope length of the diamond bead rope 300 is increased to improve the service life of the wire saw for a single cut. In addition, a first lifting assembly 4 and a second lifting assembly 5 are added to the wire saw to realize a sawtooth-shaped special-shaped cut on the pipe frame 200. Through the mutual engagement of the upper and lower cuts, not only can the saw clamping phenomenon be avoided, but also the upper pipe frame 200 after cutting can be prevented from tipping over under the influence of gravity or seawater disturbance, thereby reducing the use of offshore lifting equipment.

[0046] Obviously, the above embodiments of the present invention are merely examples for clearly illustrating the present invention, and are not intended to limit the embodiments of the present invention. For those skilled in the art, other different forms of changes or modifications can be made based on the above description. It is not necessary and impossible to list all the embodiments here. Any modifications, equivalent substitutions and improvements made within the spirit and principles of the present invention should be included in the protection scope of the claims of the present invention.

Claims

1. A deep water diamond wire saw machine, It is characterized in that The invention comprises a buoyancy frame, and a clamping assembly is arranged on the buoyancy frame, the clamping assembly fixes and clamps the conductor frame on the buoyancy frame, a first bracket and a second bracket are arranged horizontally in the buoyancy frame, a first lifting assembly is arranged on the first bracket, and the first lifting assembly is provided with a first pulley assembly for lifting and lowering along the axial direction of the conductor frame, a second lifting assembly is arranged on the second bracket, and the second lifting assembly is provided with a second pulley assembly for lifting and lowering along the axial direction of the conductor frame, the first pulley assembly and the second pulley assembly are connected by a beaded rope, the beaded rope moves along the radial direction of the conductor frame for cutting the conductor frame, and the first pulley assembly and / or the second pulley assembly are lifted and lowered relative to the buoyancy frame along the axial direction of the conductor frame to cut the conductor frame into two sections with irregular cross-sections.

2. The deepwater diamond wire saw machine according to claim 1, It is characterized in that The first lifting assembly includes a first vertical plate and a first driving member. The first vertical plate is vertically arranged with the first bracket. A first slideway is arranged on the first vertical plate. A first slider is arranged on the first pulley assembly. The first slider is slidably arranged in the first slideway. The first driving member is connected with the first slider. The first driving member drives the first slider to slide in the first slideway so that the first pulley assembly is lifted and lowered along the axial direction of the catheter frame.

3. The deepwater diamond wire saw machine according to claim 2, It is characterized in that The second lifting assembly includes a second vertical plate and a second driving member. The second vertical plate is vertically arranged with the second bracket. A second slideway is arranged on the second vertical plate. A second slider is arranged on the second pulley assembly. The second slider is slidably arranged in the second slideway. The second driving member is connected with the second slider. The second driving member drives the second slider to slide in the second slideway so that the second pulley assembly is lifted and lowered along the axial direction of the catheter frame.

4. The deepwater diamond wire saw machine according to claim 3, It is characterized in that The first pulley assembly includes a first cutting frame, and the first slider is arranged on the first cutting frame. The second pulley assembly includes a second cutting frame, and the second slider is arranged on the second cutting frame.

5. The deepwater diamond wire saw machine according to claim 4, It is characterized in that A first driving pulley and a first driven pulley are fixedly arranged on the first cutting frame, a first feed wheel and a sliding wheel are slidably arranged on the first cutting frame along the length direction of the first cutting frame, a second driving pulley and a second driven pulley are fixedly arranged on the second cutting frame, a second feed wheel and a tensioning wheel are slidably arranged on the second cutting frame along the length direction of the second cutting frame, and the bead rope is connected head to tail and is sequentially wound around the first driving pulley, the sliding wheel, the first driven pulley, the second driven pulley, the tensioning wheel, the second driving pulley, the second feed wheel and the first feed wheel.

6. The deepwater diamond wire saw machine according to claim 4, It is characterized in that Two first cutting frames are provided, and the two first cutting frames are arranged in parallel. The first feed wheel is slidably arranged on one first cutting frame, and the sliding wheel is slidably arranged on the other first cutting frame.

7. The deepwater diamond wire saw machine according to claim 4, It is characterized in that Two second cutting frames are provided, and the two second cutting frames are arranged in parallel. The second feed wheel is slidably arranged on one second cutting frame, and the tensioning wheel is slidably arranged on the other second cutting frame.

8. The deepwater diamond wire saw machine according to claim 6, It is characterized in that It also includes a third drive motor, a first lead screw and a second lead screw. The third drive motor is arranged at one end of the first lead screw. The first lead screw and the second lead screw are connected by a chain drive. The first lead screw is rotatably arranged on a first cutting frame, a first lead screw nut is screwed on the first lead screw, and the first lead screw nut is connected to the first feed wheel. The second lead screw is rotatably arranged on another first cutting frame, a second lead screw nut is screwed on the second lead screw, and the second lead screw nut is connected to the sliding wheel.

9. The deepwater diamond wire saw machine according to claim 7, It is characterized in that It also includes a fourth drive motor and a third lead screw. The fourth drive motor is arranged at one end of the third lead screw. The third lead screw is rotatably arranged on a second cutting frame. The third lead screw is threaded with a third lead screw nut, and the third lead screw nut is connected to the second feed wheel.

10. The deepwater diamond wire saw machine according to claim 6, It is characterized in that It also includes a guide rod and a spring. A fixed seat is arranged on another second cutting frame. One end of the guide rod is arranged on the fixed seat. The other end of the guide rod passes through the tensioning wheel. The spring is sleeved outside the guide rod. The spring end abuts against the fixed seat. The other end of the spring abuts against the tensioning wheel.

Citation Information

Cited By

  • Hydraulic pipe pile cutting device

    WO2026184059A1