Partially cast-in-place post-closed type diaphragm wall structure and construction method thereof

By setting up columnar concrete short walls and anti-seepage walls on the foundation of the deep cover layer to form flexible connections, the problem of slow construction progress of traditional anti-seepage walls is solved, and anti-seepage wall construction is carried out in advance on the foundation of the deep cover layer. Adapting to the complex deformation characteristics of the foundation, the progress of hydropower projects has been optimized.

CN118932935APending Publication Date: 2024-11-12HYDROPOWER WATER CONSERVANCY GUIHUA DESIGN ZONGYUAN +2
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202411064471.9
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-05
Publication Date
2024-11-12

AI Technical Summary

Technical Problem

On the deep covered foundation, traditional anti-seepage wall construction requires the completion of the foundation settlement, resulting in slow construction progress and affecting the technical and economic rationality of hydropower projects.

Method used

A partially cast-in-place rear-closed anti-seepage wall structure is adopted. By setting up columnar concrete short walls and anti-seepage wall staggered joints at the interface between the deep cover foundation and the bedrock, a flexible connection is formed, leaving settlement space, and inside the dam body Set up a segmented anti-seepage structure and carry out anti-seepage wall construction in advance.

Benefits of technology

While ensuring the anti-seepage effect, the anti-seepage wall construction time is advanced, adapting to the complex deformation characteristics of the foundation, optimizing the project schedule, and having strong engineering practice value.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118932935A_ABST
    Figure CN118932935A_ABST
Patent Text Reader

Abstract

The invention discloses a partially cast-in-place post-closed type diaphragm wall structure and a construction method thereof, and belongs to the technical field of hydraulic engineering building construction.The partially cast-in-place post-closed type diaphragm wall structure is characterized in that a columnar concrete short wall is arranged over the interface of a deep covering layer foundation and a bedrock foundation, and diaphragm walls are arranged on the two sides; between every two adjacent diaphragm walls, holes are drilled in the columnar concrete short walls to form diaphragm wall staggered seams, dam body inner seepage-proofing bodies are correspondingly arranged above the two sections of diaphragm walls, and seepage-proofing body segmentation seams are correspondingly arranged above the diaphragm wall staggered seams. By wrapping plastic or low-strength concrete around the diaphragm wall right above the interface, rigid connection of the two sections of diaphragm walls is changed into flexible connection, and a space is reserved for settlement deformation of the diaphragm wall on a deep and thick covering layer foundation; therefore, the starting time of the construction operation of the diaphragm wall can be greatly advanced while the anti-seepage effect of the diaphragm wall is not influenced, and beneficial help is provided for optimizing the project progress arrangement.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the field of water conservancy engineering construction, and in particular relates to a partially cast-in-place rear-enclosed anti-seepage wall structure and a construction method thereof. Background Art

[0002] As a natural material dam, earth-rock dam can adjust the dam shape according to local excavation materials, and has low requirements for the geological conditions of the bedrock at the bottom of the dam. It has the advantages of simple construction technology, low cost, and good seismic performance. It is widely used in the field of hydropower and water conservancy project construction. As hydropower development work gradually advances to deep mountains and high gorges, the dam site construction conditions of hydropower projects are becoming increasingly complex, and dam construction on the foundation of a deep overburden layer is inevitable. The deep overburden layer has unfavorable characteristics such as loose structure, strong permeability, long settlement time, and large compression deformation. The construction of its anti-seepage system has become a key issue restricting the construction of high earth-rock dams on the foundation of a deep overburden layer.

[0003] Traditional anti-seepage wall construction requires waiting until the foundation has settled completely before digging trenches, making holes, grouting and other operations are carried out, and a continuous anti-seepage wall structure is formed by pouring the entire structure at one time. For a deep overburden foundation, since its large deformation and settlement may last for several years, if the anti-seepage wall construction is carried out after the foundation has settled completely, it will inevitably seriously hinder the progress of the project construction, thereby reducing the technical and economic rationality of the hydropower project development. Therefore, in order to better coordinate the timing arrangement of the anti-seepage wall construction on the deep overburden foundation, it is urgent to develop a new anti-seepage wall structure and construction method. Summary of the invention

[0004] In view of the above-mentioned defects or improvement needs of the prior art, the present invention provides a partially cast-in-place post-enclosed anti-seepage wall structure and a construction method thereof, so as to solve the timing problem between the construction of the anti-seepage wall and the stabilization of the settlement of the thick covering layer foundation, and provide an effective solution for optimizing the schedule of hydropower project construction and improving the technical and economic rationality of project development.

[0005] In order to achieve the above object, the technical solution adopted by the present invention is as follows:

[0006] A partially cast-in-place rear-enclosed anti-seepage wall structure, according to different foundation conditions such as thick overburden and bedrock, divides the rigid anti-seepage wall below the foundation surface of the earth-rock dam into several sections, forms an anti-seepage wall staggered joint by high-precision vertical large-diameter drilling between two adjacent sections of the anti-seepage wall, and the two sides are flexibly connected by plastic or low-strength columnar concrete short walls, and connected to the anti-seepage body structure inside the dam body, forming a closed anti-seepage system, which can effectively deal with the leakage problem of the dam foundation and prevent the occurrence of seepage deformation and damage phenomena such as soil flow and pipe gushing behind the dam. It includes a columnar concrete short wall directly above the interface between the thick overburden foundation and the bedrock foundation, an anti-seepage wall is arranged on both sides of the columnar concrete short wall, an anti-seepage wall staggered joint is formed by drilling holes inside the columnar concrete short wall between adjacent anti-seepage walls, an anti-seepage body inside the dam body is correspondingly above the two sections of the anti-seepage wall, and an anti-seepage body segmented joint is correspondingly above the staggered joint of the anti-seepage wall.

[0007] Furthermore, embedded steel bars are arranged in the anti-seepage body inside the dam body. The anti-seepage body inside the dam body is a segmented structure separated by segmented seams of the anti-seepage body. The segmented seams of the anti-seepage body are located directly above the staggered seams of the anti-seepage wall.

[0008] Furthermore, the width of the staggered joint of the anti-seepage wall can be 1.2 to 1.5 m, and it is arranged just above the interface between the thick overburden foundation and the bedrock foundation.

[0009] Furthermore, the segmented seam of the anti-seepage body is a structure that is wider at the upper part and narrower at the lower part, and the lower width of the segmented seam of the anti-seepage body is equal to the width of the staggered seam of the anti-seepage wall.

[0010] In addition, a construction method of a partially cast-in-place rear-enclosed cut-off wall structure is provided, comprising the following steps:

[0011] S1. Drill a square hole directly above the interface between the thick overburden foundation and the bedrock foundation where the axis of the anti-seepage wall structure crosses, pour plastic or low-strength concrete in the square hole to form a columnar concrete short wall, and reserve guide slot holes at the interface between the thick overburden foundation and the bedrock foundation in the columnar concrete short wall;

[0012] S2. After the initial setting of the columnar concrete short wall, take the guide slot hole reserved at the center of the columnar concrete short wall as the starting point, and use a double-wheel slot milling machine to simultaneously excavate the guide slot in different foundation directions on both sides along the axial direction of the anti-seepage wall structure. During the excavation of the guide slot, use an ultrasonic side wall instrument to check the flatness, verticality and other shape control indicators of the slot hole wall. If the requirements are not met, use a grab bucket to correct it;

[0013] S3. Drill holes in sequence at the edge of the guide groove in the vertical downward direction to arrange pre-buried grouting pipes, pour the anti-seepage wall concrete, and form an anti-seepage wall groove section. The pre-buried grouting pipes should meet the requirements of repeatable grouting and be arranged on the outer contour interface of the anti-seepage wall;

[0014] S4. After the columnar concrete short wall and the concrete trough section of the cut-off wall are poured to the foundation surface and cured, the portion of the columnar concrete short wall connecting the two adjacent sections of the cut-off wall is drilled and removed to form a staggered joint of the cut-off wall;

[0015] S5. Continue to pour the internal anti-seepage body of the dam on the anti-seepage wall, and together with the columnar concrete short wall below the foundation surface and the combination of the concrete trough section of the anti-seepage wall, form an anti-seepage structure;

[0016] S6. After the dam body is filled and the thick covering layer foundation settlement is stable, use prefabricated cement slurry to first cast the staggered joints of the anti-seepage wall, and then cast the segmented joints of the anti-seepage body on the upper part of the dam foundation to form a closed anti-seepage system.

[0017] Furthermore, the size of the square hole is twice the thickness of the anti-seepage wall structure in the width along the axial direction of the anti-seepage wall structure, and three times the thickness of the anti-seepage wall in the length in the direction perpendicular to the axial direction of the anti-seepage wall structure; during the pouring of plastic or low-strength concrete, two guide slot holes are reserved in the center of the square hole, the depth of the guide slot holes is greater than 5m, and the length in the direction perpendicular to the axial direction of the anti-seepage wall is equal to the thickness of the anti-seepage wall.

[0018] Furthermore, the rigidity and strength of the concrete material of the columnar concrete short wall are both lower than those of the concrete material of the cut-off wall.

[0019] In step S4, the drilling holes are high-precision vertical large-diameter drilling holes with a hole diameter greater than 108 mm, which are arranged in sequence along a direction perpendicular to the axis of the anti-seepage wall to completely separate the two sections of the anti-seepage wall.

[0020] Furthermore, embedded steel bars are exposed on the contact surfaces of the dam body's internal impermeable body on both sides of the impermeable body segmented seams. In step S6, the embedded steel bars on both sides of the surface of the impermeable body segmented seams are overlapped before the impermeable body segmented seams are cast in situ; during the pouring of the impermeable body inside the dam body, the dam body rockfill, filter material and cushion material within a range of 4 to 5 m around the impermeable body inside the dam body are simultaneously filled.

[0021] Furthermore, when the dam foundation spans across a variety of complex foundation conditions, multiple partially cast-in-place rear-enclosed anti-seepage wall structures are arranged at the junctions of the various foundations.

[0022] The present invention is directed to an anti-seepage wall structure spanning the interface between a thick covering layer foundation and a bedrock foundation. By wrapping plastic or low-strength concrete around the anti-seepage wall just above the interface, the two sections of the anti-seepage wall are transformed from a rigid connection to a flexible connection, thereby reserving space for the settlement and deformation of the anti-seepage wall on the thick covering layer foundation. As a result, the start time of the anti-seepage wall construction work can be greatly advanced without affecting the anti-seepage effect of the anti-seepage wall, thereby providing useful assistance for optimizing the project schedule.

[0023] Further, the double-wheel slot milling machine excavates the guide groove in step S2, specifically including:

[0024] A guide slot hole is reserved at the center of the columnar concrete short wall. After the columnar concrete short wall is initially solidified, a guide slot is formed by excavating on both sides of the guide slot hole along the axis of the anti-seepage wall using a double-wheel milling machine, taking the reserved guide slot hole as the starting point.

[0025] During the guide groove excavation process, the double-wheel slot milling machine excavates simultaneously on both sides of the guide groove hole along the axis direction of the anti-seepage wall, and the shape of the groove hole wall needs to be well controlled.

[0026] Furthermore, pouring the anti-seepage wall concrete to form the trough section in step S3 specifically includes:

[0027] Pre-buried grouting pipes are regularly arranged at the edge of the guide groove formed by the double-wheel slot milling machine, and anti-seepage wall concrete is poured into the inside of the guide groove in the vertical downward direction to form an anti-seepage wall concrete groove section.

[0028] The pre-buried grouting pipe shall meet the requirements of repeatable grouting and be arranged at the interface between the cut-off wall and the plastic or low-strength concrete or dam body filling material;

[0029] The number of pre-buried grouting pipes is determined according to the specific construction requirements of the anti-seepage wall pouring operation, and is used to assist in the pouring and forming of the anti-seepage wall;

[0030] The performance of the anti-seepage wall concrete should be determined according to the specific anti-seepage design requirements of the hydropower project.

[0031] Further, the drilling and cutting of the plastic or low-strength concrete connecting the slot segments in step S4 specifically includes:

[0032] After the columnar concrete short walls and the concrete trough sections of the cut-off wall are poured to the foundation surface and cured, the plastic or low-strength concrete of the short wall connecting the two adjacent sections of the cut-off wall is drilled and removed to form staggered joints in the cut-off wall.

[0033] The drilled holes are high-precision vertical large-diameter drilled holes with a hole diameter greater than 108 mm, which are arranged in sequence along a direction perpendicular to the axis of the cut-off wall to completely separate the two sections of the cut-off wall;

[0034] The width of the staggered seam of the anti-seepage wall is 1.2-1.5 m, and the wall is arranged just above the interface between the thick covering layer foundation and the bedrock foundation.

[0035] Furthermore, the pouring of the anti-seepage structure inside the dam body in step S5 specifically includes:

[0036] Depending on the anti-seepage design needs of the specific project, the anti-seepage structure inside the dam body will continue to be cast on the basis of the anti-seepage wall with staggered joints.

[0037] After the dam body is filled and the thick covering layer foundation settlement is stable, prefabricated cement slurry is poured into the staggered joints of the anti-seepage wall and the segmented joints of the anti-seepage body to form a closed anti-seepage system.

[0038] The anti-seepage structure inside the dam body generally refers to the asphalt concrete core wall anti-seepage body inside the dam;

[0039] The anti-seepage structure inside the dam body also adopts a segmented structure protected by plastic or low-strength concrete, and a segmented seam of the anti-seepage body is reserved just above the staggered seam of the anti-seepage wall;

[0040] The segmented seams of the anti-seepage body adopt a "wide at the top and narrow at the bottom" structure, with the upper width generally being 2 to 3 meters, and the lower width being equal to the staggered seam width of the anti-seepage wall;

[0041] The contact surfaces of the anti-seepage bodies on both sides of the anti-seepage body segmented seams should generally expose the embedded steel bars;

[0042] During the pouring process of the impermeable body inside the dam body, the dam body rockfill, filter material and cushion material within 4 to 5 meters around the impermeable body shall be filled simultaneously;

[0043] During the sealing process of the anti-seepage system, the staggered joints of the anti-seepage wall are first cast in situ to seal the staggered joints, and then the segmented joints of the anti-seepage body inside the dam body are cast in situ to seal the staggered joints;

[0044] During the casting process of the segmented seams of the anti-seepage body, the exposed steel bars on both sides of the segmented seams of the anti-seepage body are overlapped, and then the prefabricated cement slurry is cast to form a closed whole;

[0045] The prefabricated cement slurry may be made of anti-seepage wall concrete or cement-based cementitious material similar to anti-seepage wall concrete.

[0046] Furthermore, when the dam foundation spans across a variety of complex foundation conditions, multiple partially cast-in-place rear-enclosed anti-seepage wall structures can be set up to reduce the adverse effects of differences in settlement and deformation of different foundation conditions on the construction schedule of the hydropower project.

[0047] Compared with the prior art, the partially cast-in-place rear-enclosed anti-seepage wall structure and the construction method thereof provided by the present invention have the following advantages and beneficial effects:

[0048] 1. The present invention transforms the traditional rigid continuum anti-seepage wall structure into a flexible assembled anti-seepage wall structure by setting up columnar concrete short walls. By forming staggered seams between the anti-seepage walls on different foundations, space is reserved for the uneven settlement of the anti-seepage walls, thereby better adapting to the complex deformation characteristics of the foundation while ensuring the anti-seepage effect.

[0049] 2. The present invention sets the anti-seepage wall as a partially cast-in-place post-enclosed form, so that the anti-seepage wall can be cast while the deep covering layer foundation is continuously settling, which greatly advances the start time of the anti-seepage wall construction and provides operating space for optimizing the construction progress;

[0050] 3. The invention has a clear technical route, simple construction method, strong operability, superior technical and economic performance, and strong engineering practice value. BRIEF DESCRIPTION OF THE DRAWINGS

[0051] Figure 1 It is a perspective view of the rear closed anti-seepage wall structure + the internal anti-seepage structure of the dam body of the present invention;

[0052] Figure 2 It is a schematic diagram of forming a columnar concrete short wall of the present invention;

[0053] Figure 3 It is a schematic diagram of a double-wheel slot milling machine excavating a guide slot according to the present invention;

[0054] Figure 4 It is a schematic diagram of a concrete trough section of an anti-seepage wall of the present invention;

[0055] Figure 5 is a schematic diagram of drilling and removing plastic or low-strength concrete according to the present invention;

[0056] Figure 6 The present invention is a flow chart of a construction method of a partially cast-in-place rear-enclosed anti-seepage wall structure.

[0057] Among them, 1. Columnar concrete short wall; 2. Guide groove; 3. Anti-seepage wall; 4. High-precision vertical large-diameter drill holes; 5. Anti-seepage body inside the dam; 6. Staggered joints of the anti-seepage wall; 7. Segmented joints of the anti-seepage body; 11. Square holes; 12. Guide groove holes; 13. Interface between the thick covering layer foundation and the bedrock foundation; 31. Pre-buried grouting pipes; 51. Pre-buried steel bars. DETAILED DESCRIPTION

[0058] In order to make the purpose, technical scheme and advantages of the present invention clearer, the present invention will be further described in detail below in conjunction with the embodiments and drawings. It should be understood that the specific embodiments described herein are only used to explain the present invention and are not intended to limit the present invention. In addition, the technical features involved in each embodiment of the present invention described below can be combined with each other as long as they do not conflict with each other.

[0059] refer to Figure 1The present embodiment provides a partially cast-in-place rear-enclosed anti-seepage wall structure, including a columnar concrete short wall 1 arranged directly above the interface 13 between the thick covering layer foundation and the bedrock foundation, anti-seepage walls 3 are arranged on both sides of the columnar concrete short wall 1, and anti-seepage wall staggered joints 6 are formed by drilling holes inside the columnar concrete short walls 1 between adjacent anti-seepage walls 3, an anti-seepage body 5 inside the dam body is arranged above the two sections of the anti-seepage wall 3, and an anti-seepage body segmented joint 7 is arranged above the anti-seepage wall staggered joint 6.

[0060] Embedded steel bars 51 are arranged in the anti-seepage body 5 inside the dam body. The anti-seepage body structure 5 inside the dam body adopts a segmented structure protected by plastic or low-strength concrete, and an anti-seepage body segmented seam 7 is reserved just above the staggered seam 6 of the anti-seepage wall.

[0061] The width of the staggered joint 6 of the anti-seepage wall is 1.2-1.5 m, and is located directly above the interface 13 between the thick overburden foundation and the bedrock foundation.

[0062] The staggered seams 6 of the cut-off wall are provided to facilitate settlement deformation of different magnitudes in the two sections of the cut-off wall, so that relative displacement can occur.

[0063] The segmented seam 7 of the anti-seepage body adopts a "wide at the top and narrow at the bottom" structure to facilitate maintenance and inspection by personnel before closed grouting. The upper width is generally 2 to 3 meters, and the lower width is equal to the width of the staggered seam 6 of the anti-seepage wall.

[0064] Figure 2 The cross section of the columnar concrete short wall 1 is shown. A square hole 11 is drilled just above the interface 13 between the thick covering layer foundation and the bedrock foundation across the axis of the anti-seepage wall. Plastic or low-strength concrete is poured into the square hole 11 to form the columnar concrete short wall 1. A guide groove hole 12 is reserved in the square hole 11.

[0065] As a preferred embodiment of the present invention, the width of the square hole 11 along the axial direction of the anti-seepage wall is twice the thickness of the anti-seepage wall 3 , and the length in the direction perpendicular to the axial direction of the anti-seepage wall is three times the thickness of the anti-seepage wall 3 .

[0066] As a preferred embodiment of the present invention, the number of guide slot holes 12 is 2, which are located at the center of the square hole 11, with a depth greater than 5 m, and a length in a direction perpendicular to the axis of the anti-seepage wall equal to the thickness of the anti-seepage wall 3.

[0067] As a preferred embodiment of the present invention, the rigidity and strength of the cast plastic or low-strength concrete are relatively small, and cement-based casting materials with good fluidity such as self-compacting concrete are preferred.

[0068] refer to Figure 3After the initial setting of the columnar concrete short wall, the reserved guide slot hole 12 is used as the starting point, and a double-wheel milling machine is used to excavate the guide slot 2 on both sides of the guide slot hole 12 along the axis direction of the anti-seepage wall. The double-wheel milling machine performs construction work along the axis direction of the anti-seepage wall, and excavates the guide slots from the center to both sides along the two guide slot holes 12. In the process of excavating the guide slot, it is preferred to use mud wall protection and other processing methods to control the shape of the slot hole wall.

[0069] refer to Figure 4 A pre-buried grouting pipe 31 is arranged at the edge of the guide groove 2, and the anti-seepage wall concrete is poured into the guide groove 2 through the pre-buried grouting pipe 31 in the vertical downward direction to form a concrete groove section of the anti-seepage wall 3.

[0070] The pre-buried grouting pipe 31 should meet the requirement of repeatable grouting, and the pre-buried grouting pipe 31 is arranged on the outer contour interface of the anti-seepage wall 3 to ensure the compactness and pouring effect of the anti-seepage wall. The performance of the poured anti-seepage wall concrete is determined according to the specific anti-seepage design requirements of the hydropower project, and asphalt concrete is preferably used.

[0071] refer to Figure 5 After the concrete trough sections of the columnar concrete short wall 1 and the cut-off wall 3 are poured to the foundation surface and cured, the high-precision vertical large-diameter drilled holes 4 connecting the two adjacent sections of the cut-off wall 3 are cut off to form the cut-off wall staggered seams 6. The aperture of the high-precision vertical large-diameter drilled holes 4 is greater than 108 mm. The high-precision vertical large-diameter drilled holes 4 are arranged in sequence along the direction perpendicular to the axis of the cut-off wall to completely separate the two sections of the cut-off wall 3 on different foundation conditions.

[0072] refer to Figure 6 This embodiment provides a construction method of a partially cast-in-place rear-enclosed anti-seepage wall structure, which is suitable for anti-seepage wall construction involving various complex foundation conditions. It transforms the traditional rigid continuum anti-seepage wall structure into a flexible assembled anti-seepage wall structure. While ensuring the anti-seepage effect, the start time of the anti-seepage wall construction operation can be greatly advanced. It has a good application effect for a deep overburden foundation with a long settlement time and large compression deformation. Specifically, it includes the following steps:

[0073] S1. Drill a square hole 11 directly above the interface 13 between the thick overburden foundation and the bedrock foundation where the axis of the anti-seepage wall structure crosses, pour plastic or low-strength concrete into the square hole 11 to form a columnar concrete short wall 1, and reserve guide slot holes 12 at the interface between the thick overburden foundation and the bedrock foundation in the columnar concrete short wall 1;

[0074] S2. After the initial setting of the columnar concrete short wall 1, the guide slot hole 12 reserved at the center of the columnar concrete short wall 1 is used as the starting point, and a double-wheel slot milling machine is used to simultaneously excavate the guide slot 2 in different foundation directions on both sides along the axial direction of the anti-seepage wall structure. During the excavation of the guide slot 2, an ultrasonic side wall instrument is used to check the flatness, verticality and other shape control indicators of the slot hole wall. If the requirements are not met, a grab bucket is used to correct it;

[0075] S3, drilling holes in sequence at the edge of the guide groove 2 in the vertical downward direction to arrange the pre-buried grouting pipe 31, pouring the anti-seepage wall concrete to form an anti-seepage wall groove section, the pre-buried grouting pipe should meet the requirements of repeatable grouting, and be arranged on the outer contour interface of the anti-seepage wall 3;

[0076] S4, after the concrete trough sections of the columnar concrete short wall 1 and the cut-off wall 3 are poured to the foundation surface and cured, the portion of the columnar concrete short wall 1 connecting the two adjacent sections of the cut-off wall 3 is drilled and removed to form a staggered seam 6 of the cut-off wall;

[0077] S5, continue to pour the impermeable body 5 inside the dam body on the impermeable wall 3, and together with the columnar concrete short wall 1 below the foundation surface and the concrete trough section assembly of the impermeable wall 3, form an impermeable structure;

[0078] S6. After the dam body is filled and the thick covering layer foundation settlement is stable, prefabricated cement slurry is used to first cast the staggered joints 6 of the anti-seepage wall, and then the anti-seepage body segmented joints 7 on the upper part of the dam foundation are cast to close the dam foundation, so as to form a closed anti-seepage system.

[0079] Furthermore, in step S6, during the process of casting the impermeable body 5 inside the dam body, the dam body rockfill material, filter material and cushion material within a range of 4 to 5 m around the impermeable body 5 inside the dam body need to be filled simultaneously.

[0080] Furthermore, during the sealing process of the anti-seepage system, the staggered joints 6 of the anti-seepage wall are first cast in situ to seal, and then the segmented joints 7 of the anti-seepage body inside the dam body are cast in situ to seal.

[0081] As a preferred embodiment of the present invention, during the casting process of the anti-seepage body segmented seam 7, the exposed steel bars 51 on both sides of the surface of the anti-seepage body segmented seam 7 are overlapped first, and then the precast cement slurry is cast to form a closed whole.

[0082] When the dam foundation spans across a variety of complex foundation conditions, multiple partially cast-in-place post-enclosed cut-off wall structures can be set up to reduce the adverse effects of differences in settlement and deformation of different foundation conditions on the construction schedule of the hydropower project.

[0083] It should be noted that, according to the needs of specific implementation, each step / component described in the present invention can be split into more steps / components, or two or more steps / components or partial operations of steps / components can be combined into new steps / components to achieve the purpose of the present invention. It is easy for those skilled in the art to understand that the above is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions and improvements made within the spirit and principles of the present invention should be included in the protection scope of the present invention.

Claims

1. A partially cast-in-place rear-enclosed anti-seepage wall structure, comprising: a columnar concrete short wall (1) arranged directly above the interface (13) between a thick covering layer foundation and a bedrock foundation, anti-seepage walls (3) arranged on both sides of the columnar concrete short wall (1), anti-seepage wall staggered joints (6) formed by drilling holes inside the columnar concrete short wall (1) between adjacent anti-seepage walls (3), an internal anti-seepage body (5) of the dam body correspondingly arranged above the two sections of the anti-seepage wall (3), and an anti-seepage body segmented joint (7) correspondingly arranged above the anti-seepage wall staggered joints (6).

2. A partially cast-in-place rear-enclosed anti-seepage wall structure according to claim 1, It is characterized in that Embedded steel bars (51) are arranged in the anti-seepage body (5) inside the dam body. The anti-seepage body (5) inside the dam body is a segmented structure separated by the anti-seepage body segmented seams (7). The anti-seepage body segmented seams (7) are located directly above the staggered seams (6) of the anti-seepage wall.

3. A partially cast-in-place rear-enclosed anti-seepage wall structure according to claim 2, It is characterized in that The width of the staggered seam (6) of the anti-seepage wall is 1.2-1.5 m, and the wall is arranged directly above the interface (13) between the thick overburden foundation and the bedrock foundation.

4. A partially cast-in-place rear-enclosed anti-seepage wall structure according to claim 3, It is characterized in that The anti-seepage body segmented seam (7) is a structure with a wider upper portion and a narrower lower portion, and the lower width of the anti-seepage body segmented seam (7) is equal to the width of the anti-seepage wall staggered seam (6).

5. A method for constructing a partially cast-in-place rear-enclosed anti-seepage wall structure according to claims 1-4, It is characterized in that The following steps are involved: S1. Drill a square hole (11) directly above the interface (13) between the thick overburden foundation and the bedrock foundation, where the axis of the anti-seepage wall structure crosses, and pour plastic or low-strength concrete into the square hole (11) to form a columnar concrete short wall (1). In the columnar concrete short wall (1), guide slot holes (12) are reserved at the interface between the thick overburden foundation and the bedrock foundation; S2, after the initial setting of the columnar concrete short wall (1), taking the guide slot hole (12) reserved at the center of the columnar concrete short wall (1) as the starting point, along the axial direction of the anti-seepage wall structure, a double-wheel slot milling machine is used to simultaneously excavate the guide slot (2) in different foundation directions on both sides, and during the excavation of the guide slot (2), an ultrasonic side wall instrument is used to check the flatness, verticality and other shape control indicators of the slot hole wall, and a grab bucket is used to correct it if it does not meet the requirements; S3, drilling holes in sequence at the edge of the guide groove (2) in a vertical downward direction to arrange pre-buried grouting pipes (31), pouring anti-seepage wall concrete to form an anti-seepage wall (3) groove section, wherein the pre-buried grouting pipes (31) should meet the requirements of repeatable grouting and be arranged on the outer contour interface of the anti-seepage wall (3); S4, after the concrete trough sections of the columnar concrete short wall (1) and the anti-seepage wall (3) are poured onto the foundation surface and cured, the section of the columnar concrete short wall (1) connecting the two adjacent sections of the anti-seepage wall (3) is drilled and removed to form an anti-seepage wall staggered joint (6); S5, continue to pour the impermeable body (5) inside the dam body on the impermeable wall (3), and form an impermeable structure together with the columnar concrete short wall (1) below the foundation surface and the concrete trough section assembly of the impermeable wall (3); S6. After the dam body is filled and the thick covering layer foundation is settled and stabilized, prefabricated cement slurry is used to first pour the staggered joints (6) of the anti-seepage wall, and then the segmented joints (7) of the anti-seepage body on the upper part of the dam foundation are poured and sealed to form a closed anti-seepage system.

6. A method for constructing a partially cast-in-place rear-enclosed cut-off wall structure according to claim 5, It is characterized in that The size of the square hole (11) is such that the width along the axial direction of the anti-seepage wall structure is twice the thickness of the anti-seepage wall (3), and the length in the direction perpendicular to the axial direction of the anti-seepage wall structure is three times the thickness of the anti-seepage wall (3); during the pouring of the plastic or low-strength concrete, two guide slot holes (2) are reserved at the center of the square hole (11); the depth of the guide slot holes (2) is greater than 5m, and the length in the direction perpendicular to the axial direction of the anti-seepage wall is equal to the thickness of the anti-seepage wall (3).

7. A method for constructing a partially cast-in-place rear-enclosed cut-off wall structure according to claim 5, It is characterized in that The rigidity and strength of the concrete material of the columnar concrete short wall (1) are both lower than those of the concrete material of the anti-seepage wall (3).

8. The method for constructing a partially cast-in-place rear-enclosed cut-off wall structure according to claim 5, It is characterized in that In step S4, the drilled holes are high-precision vertical large-diameter drilled holes (4) with a hole diameter greater than 108 mm, which are arranged in sequence along a direction perpendicular to the axis of the anti-seepage wall to completely separate the two sections of the anti-seepage wall (3).

9. The method for constructing a partially cast-in-place rear-enclosed cut-off wall structure according to claim 5, It is characterized in that The contact surfaces of the dam body internal impermeable body (5) on both sides of the impermeable body segmented seam (7) expose the embedded steel bars (51). In step S6, the embedded steel bars (51) on both sides of the surfaces of the impermeable body segmented seam (7) are overlapped before the impermeable body segmented seam (7) is cast in situ. During the process of casting the dam body internal impermeable body (5), the dam body rockfill material, filter material and cushion material within a range of 4 to 5 m around the dam body internal impermeable body (5) are simultaneously filled.

10. The method for constructing a partially cast-in-place rear-enclosed cut-off wall structure according to claim 5, It is characterized in that When the dam foundation spans across a variety of complex foundation conditions, multiple partially cast-in-place rear-enclosed anti-seepage wall structures are set up at the junctions of various foundations.