Construction method of deep foundation pit steel sheet pile for box culvert and pipeline construction

By sorting and sorting the steel sheet piles, the friction resistance during insertion and punching is reduced, and the cooperation of vibrating hammers and cranes is used to solve the problem of errors in order and difficulty in removing steel sheet piles in the construction of deep foundation pits, improving construction efficiency and safety sex.

CN118933002APending Publication Date: 2024-11-12THE 5TH ENGINEERING CO LTD OF CHINA RAILWAY CONSTRUCTION BRIDGE ENGINEERING BUREAU GROUP +2
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411410579.9
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-10-10
Publication Date
2024-11-12

AI Technical Summary

Technical Problem

During the construction of box culverts and pipelines, the process of inserting, driving and removing steel sheet piles in deep foundation pits is prone to errors in sequence, large friction resistance and mud and sand blockage, resulting in low construction efficiency and increased safety risks.

Method used

By sorting and sorting steel sheet piles, marking the order of insertion and punching, and applying butter on both sides of the lock mouth to reduce friction resistance, punching hardwood wedges before inserting and punching to prevent blockage, and at the same time, removing them with a vibration hammer and a crane, using forced vibration to destroy the soil quality Cohesive force to overcome the pulling resistance.

Benefits of technology

It effectively avoids the order errors in the steel sheet piles during the insertion and handling process, reduces friction resistance and blockage risks, improves construction efficiency, and greatly improves the removal efficiency through the use of vibrating hammers.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118933002A_ABST
    Figure CN118933002A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of building construction, in particular to a construction method of a deep foundation pit steel sheet pile for box culvert and pipeline construction, which comprises the following steps of inspection and correction of the steel sheet pile, sorting and preparation of the steel sheet pile, installation of a guide frame, selection of a pile sinking machine, driving of the steel sheet pile, pulling of the steel sheet pile and pile hole treatment. The steel sheet piles are sorted and classified, the steel sheet piles are prevented from being mistakenly ordered in the inserting, driving and carrying processes, the two sides of each steel sheet pile are fully coated with butter before being inserted and driven, the friction resistance during inserting and driving is reduced, meanwhile, hardwood wedges are driven into the lower ends of the locking openings without inserting and sleeving, and the inserting and driving efficiency is improved. And displacement of the steel sheet pile during inserting and driving caused by blockage of a locking opening by mud and sand during sinking is prevented.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of building construction, in particular to a construction method of deep foundation pit steel sheet piles used for box culvert and pipeline construction. Background Art

[0002] When the open excavation method is used for box culvert and pipeline construction, trench support is the key technology to ensure safe construction. When the excavation depth is large, the stability of the trench slope must be considered. The commonly used method is slope reduction. However, when the soil quality is poor or there is no slope reduction condition, support is required. Steel sheet piles can be used for foundation support. Therefore, a construction method of deep foundation pit steel sheet piles for box culvert and pipeline construction is provided. Summary of the invention

[0003] The purpose of the present invention is to provide a construction method for deep foundation pit steel sheet piles used in box culvert and pipeline construction. By sorting and classifying the steel sheet piles, it is avoided that the order of the steel sheet piles is wrong during the insertion and transportation process. Before the insertion, the locking mouths on both sides of the steel sheet piles are fully coated with butter to reduce the frictional resistance during the insertion. At the same time, a hardwood wedge is driven into the lower end of the locking mouth that is not inserted into the sleeve to prevent mud and sand from clogging the locking mouth when sinking, causing the steel sheet pile to move when it is inserted.

[0004] The present invention is implemented by the following technical scheme: A construction method of deep foundation pit steel sheet piles for box culvert and pipeline construction, comprising the following steps: Step 1: Inspection and correction of steel sheet piles. Transport the steel plate to the site and use steel sheet piles of the same type and specification with standard locking joints to check whether the locking joints of the same type of steel sheet piles have passed. The inspection is carried out by pulling a standard steel plate flat car with a winch from the pile head to the pile tail. If the steel sheet piles are found to be bent, damaged, or have mismatched locking joints, they will be repaired with a repair device. If the pile body is twisted or bent, it will be corrected with a hydraulic jack.

[0005] Step 2: Arrange and prepare steel sheet piles. Use a marker to add marks to the inspected and corrected steel sheet piles. Mark the order of driving the steel sheet piles with Arabic numerals according to the situation. Apply butter to the locks on both sides of the steel sheet piles to reduce the friction during driving. At the same time, drive hardwood wedges into the lower end of the locks without sleeves to prevent mud and sand from clogging the locks during sinking and causing the steel sheet piles to move when driven.

[0006] Step 2: Install the guide frame. Set up the guide frame according to the site conditions.

[0007] Step 3: Select the pile driving machine and use an excavator in conjunction with the DZ90 vibrating pile driver to preset the pile column mouth.

[0008] Step 4: Steel sheet pile driving, using self-vibrating steel sheet pile special machinery for driving.

[0009] Step 5: Remove the steel sheet piles by using a vibratory hammer. A crane is used in conjunction with the vibratory hammer to remove the steel sheet piles. The forced vibration generated by the vibratory hammer disturbs the soil and destroys the cohesion of the soil around the sheet piles to overcome the resistance to pulling out the piles. The piles are then removed by relying on the additional lifting force.

[0010] Step 6: Pile hole treatment: After the steel sheet pile is pulled out, immediately insert the grouting pipe to grout the pile hole.

[0011] In order to better realize the present invention, further, in the step 2, after the preparation work is completed, the piles are stacked in the order of pile insertion; the number of stacking layers shall not exceed four, each layer shall be supported by pads, the height difference of the pads shall not be greater than 10m, and the center lines of the upper and lower layers of pads shall be on the same vertical line.

[0012] In order to better implement the present invention, further, the steel sheet pile driving steps are as follows: a. Lift the steel sheet pile with the front arm of the pile driver, open the head clamp and clamp the head, vertically insert the steel sheet pile to the designed depth at the designed position through the hydraulic vibration hammer of the pile driver to complete the first steel sheet pile insertion.

[0013] b. After the first pile is driven, the subsequent steel plates are inserted along the buckle groove of the previous pile to the designed depth until the steel sheet pile retaining system of the foundation pit is formed: the corners of the foundation pit are connected with large buckles to make the steel sheet piles continuous.

[0014] In order to better realize the present invention, further, during the installation of the steel sheet piles, one must be familiar with the conditions of the underground pipelines and structures before driving, and carefully lay out the accurate center line of the support piles; during the driving process, the slope of each pile is measured and monitored at any time to ensure that it does not exceed 2%. When the deflection is too large and cannot be adjusted by the pulling method, pull it out and drive it again.

[0015] In order to better realize the present invention, further, in the steel sheet pile removal, for the closed sheet pile wall, the pulling starting point should be more than 5 piles away from the corner. The pulling starting point can be determined according to the situation when the pile is sunk, and the jump pulling method can be used if necessary; the pulling order is preferably opposite to that when driving.

[0016] In order to better realize the present invention, further, during the removal of the steel sheet piles, when pulling out the piles, the locking mouth of the sheet piles can be firstly vibrated with a vibratory hammer to reduce the adhesion of the soil, and then the piles can be pulled out while vibrating; for sheet piles that are more difficult to pull out, the piles can be first vibrated down 100-300 mm with a diesel hammer, and then alternately vibrated and pulled out with a vibratory hammer.

[0017] In order to better realize the present invention, further, during the removal of the steel sheet piles, the crane should be gradually loaded as the vibrating hammer is started, and the lifting force is generally slightly smaller than the compression limit of the shock absorber spring; the power supply used by the vibrating hammer is 1.2 to 2.0 times the rated power of the vibrating hammer itself; for sheet piles with large pulling resistance, intermittent vibration method is adopted, each vibration is 15 minutes, and the vibrating hammer is not continuous for more than 1.5 hours.

[0018] In order to better realize the present invention, further, in the pile hole treatment, the grouting material adopts 42.5 grade ordinary Portland cement to prepare slurry, the water-cement ratio is 0.55, the grouting flow rate is about 7~10L / min, and shall not be greater than 20L / min, the grouting pressure is controlled between 0.5~1.0MPa, and the amount of cement used for grouting each pile hole of the steel sheet pile shall not be less than 120kg / m; the horizontal spacing of the grouting holes is 0.6m (grouting is carried out for each pile hole), and the grouting depth is from the bottom of the steel plate pile to the natural ground.

[0019] Compared with the prior art, the present invention has the following advantages and beneficial effects: 1. The present invention adopts a vibratory hammer to extract piles, and uses a crane to cooperate with the vibratory hammer to extract the piles. The forced vibration generated by the vibratory hammer is used to disturb the soil and destroy the cohesion of the soil around the sheet pile to overcome the resistance to pile extraction. The piles are extracted by relying on the effect of additional lifting force, which greatly improves the work efficiency.

[0020] 2. The present invention avoids the wrong order of steel sheet piles during driving and transportation by sorting and classifying the steel sheet piles, and reduces the frictional resistance during driving by smearing butter in front of the locking mouths on both sides of the steel sheet piles before driving. At the same time, hardwood wedges are driven into the lower ends of the locking mouths that are not inserted into the sleeves to prevent mud and sand from clogging the locking mouths during sinking, causing the steel sheet piles to move when driven. BRIEF DESCRIPTION OF THE DRAWINGS

[0021] Other features, objects and advantages of the present invention will become more apparent from the detailed description of non-limiting embodiments with reference to the following drawings: Figure 1 It is a schematic diagram of the construction process of the present invention. DETAILED DESCRIPTION

[0022] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0023] Embodiment 1: like Figure 1As shown, a construction method of deep foundation pit steel sheet piles for box culvert and pipeline construction includes the following steps: Step 1: Inspection and correction of steel sheet piles. After the steel sheet piles are transported to the site, a 1.5~2.0m long steel sheet pile with the same type and specifications and standard locking mouth is used to check the locking mouth of all the same type of steel sheet piles. The inspection is carried out by pulling a standard steel plate flat car with a winch from the pile head to the pile tail. If the steel sheet piles are found to be bent, damaged, or have a mismatched locking mouth, they need to be repaired. The twisted and bent pile body is corrected with a hydraulic jack.

[0024] Step 2: Sorting and preparation of steel sheet piles. Before driving the steel sheet piles, use red lines to divide the pile positions on the inner guide ring of the top layer. In order to prevent the steel sheet piles from getting the wrong order during driving and transportation, the steel sheets are divided into two groups, A and B, according to the lock sleeve situation, and then marked with red lines. The locks on both sides of the steel sheet piles are coated with butter before driving to reduce the friction resistance during driving. At the same time, hardwood wedges are driven into the lower end of the lock without sleeves to prevent mud and sand from blocking the lock when sinking, and the steel sheet piles from running out of position when driving. After the preparation of the steel sheet piles is completed, they are stacked in the order of driving. The number of stacking layers shall not exceed four, and each layer shall be supported by pads. The height difference of the pads shall not be greater than 10m, and the center lines of the upper and lower pads shall be on the same vertical line.

[0025] Because the plane shape of the intercepting shaft of this foundation pit is a closed rectangle, it needs to be turned to a right angle and closed when inserted, so it is necessary to prepare corner piles in advance. The corner piles can use matching special angles or be processed on-site. Considering that matching corner piles are relatively rare in the market, on-site processing is adopted. An ordinary plate is cut along the center line, and the cut surface is vertically welded to the "saddle back" of another sheet pile to form a right-angle pile, thereby completing the preparation of the steel sheet pile.

[0026] Step 2: Install the guide frame: set up the guide frame according to the site conditions; Step 3: Select the pile sinking machine, use an excavator and a DZ90 vibrating pile driver to preset the pile column mouth; Step 4: Steel sheet pile driving, use self-vibrating steel sheet pile special machinery for driving; when the first steel sheet pile is driven, the front arm of the pile driver lifts the Larsen steel sheet pile, the head clamp is opened to clamp the head, and then the Larsen steel sheet pile is inserted to the designed depth at the designed position through the hydraulic vibration hammer of the pile driver. When subsequent steel sheet piles are driven, after the first pile is driven, the subsequent steel plates are inserted to the designed depth along the buckle groove of the previous pile until the steel sheet pile retaining system of the foundation pit is formed: the corners of the foundation pit are connected with large buckles to make the steel sheet piles continuous.

[0027] In the construction of steel sheet piles, the allowable errors in driving are: top elevation deviation ±100mm, steel plate axis deviation ±100mm, and steel sheet pile verticality deviation is 1%. During the driving process, it should be monitored whether it is within the allowable error range, and corrected in time if exceeded.

[0028] Steel sheet piles are driven with a vibrating pile driver. Before driving, you must be familiar with the conditions of underground pipelines and structures, and carefully lay out the accurate center line of the supporting piles. Before driving, check each sheet pile one by one, and remove ordinary sheet piles with rusted or severely deformed connecting locks. Those that do not meet the standards can only be used after repair. Before driving, apply grease to the locks of the sheet piles to facilitate insertion and removal. During the driving process, measure and monitor the slope of each pile at any time to ensure that it does not exceed 2%. When the deflection is too large to be adjusted by the alignment method, pull it out and drive it again.

[0029] The steel sheet piles are driven in using the screen-type driving method, which is less likely to cause the sheet piles to buckle, twist, tilt, or have uneven wall surfaces. It has high driving accuracy and is easy to achieve closure. During construction, 10 to 20 sheets are inserted into the guide frame in a row to make it screen-shaped, and then driven in. Usually, a group of sheets at both ends of the screen wall are driven to the designed elevation or a certain depth, and the verticality is strictly controlled. They are fixed to the enclosure with electric welding, and then driven in sequentially in the middle at 1 / 3 or 1 / 2 the height of the sheet piles.

[0030] The smooth progress of steel sheet pile construction is largely determined by the selection of construction machinery. Taking into account the scale of the project, soil conditions, operating capacity and working environment, an excavator is used in conjunction with a DZ90 vibrating pile driver. The pile hammer uses the hydraulic principle to fix the pile end, which is firm and reliable and not easy to damage the pile top. It is suitable for driving in clay layers and can drive any form of sheet piles. It has simple auxiliary facilities, easy operation, large vibration force, fast construction speed and low noise. The steel sheet piles selected are mainly Larsen IV type steel sheet piles with a width of 400mm and lengths of 9 meters, 12 meters and 15 meters.

[0031] For deep foundation pit excavation, a steel fence is set at the excavation depth of 50cm. The double-piece 2xHM350x250 steel section size is: 340x250x9x14, and the steel grade is Q235B; a total of one support is set in the vertical direction of the foundation pit.

[0032] Step 5: Remove the steel sheet piles by using a vibratory hammer. A crane is used in conjunction with the vibratory hammer to remove the steel sheet piles. The forced vibration generated by the vibratory hammer disturbs the soil and destroys the cohesion of the soil around the sheet piles to overcome the resistance to pulling out the piles. The piles are then removed by relying on the additional lifting force.

[0033] When pulling out piles, it should be noted that for closed sheet pile walls, the starting point for pulling out piles should be at least 5 piles away from the corner. The starting point for pulling out piles can be determined based on the conditions during pile sinking, and the jump pulling method can be used if necessary. The order of pulling out piles should preferably be opposite to that of driving piles.

[0034] When pulling out piles, you can first use a vibrating hammer to vibrate the lock of the sheet pile to reduce soil adhesion, and then pull out while vibrating. For sheet piles that are difficult to pull out, you can first use a diesel hammer to vibrate the pile down 100~300mm, and then alternately vibrate and pull out with the vibrating hammer; the crane should gradually add load as the vibrating hammer starts, and the lifting force is generally slightly less than the compression limit of the shock absorber spring; the power supply for the vibrating hammer is 1.2~2.0 times the rated power of the vibrating hammer itself; for sheet piles with large pulling resistance, use intermittent vibration method, each vibration for 15 minutes, and the vibrating hammer should not exceed 1.5 hours continuously.

[0035] Step 6: Pile hole treatment: After the steel sheet pile is pulled out, immediately insert the grouting pipe to grout the pile hole.

[0036] The grouting material is 42.5 grade ordinary Portland cement slurry, with a water-cement ratio of 0.55, a grouting flow rate of about 7~10L / min, not more than 20L / min, and a grouting pressure of 0.5~1.0MPa. The amount of cement used for grouting each pile hole of Larsen steel sheet pile shall not be less than 120kg / m; the horizontal spacing of grouting holes is 0.6m (grouting is performed on each pile hole), and the grouting depth is from the bottom of the steel plate to the natural ground; insert the grouting pipe in time after pulling the pile, and pay attention to controlling the grouting pressure. force, grouting flow rate and pipe pulling speed; grouting can be stopped only after slurry appears at the hole mouth, and grouting should be supplemented two hours later. The grouting pipe should be flushed in time after the grouting is completed; before the formal construction, an on-site grouting test should be carried out first, and the construction-related technical parameters should be determined comprehensively according to the actual grouting situation; the actual grouting data should be sorted out in time; the slurry should be fully stirred in a mixer before injection can be started, and it should be stirred slowly and continuously during the grouting process, and the stirring time should be less than the initial setting time of the slurry; the slurry should be filtered through a mesh before pumping.

[0037] When steel sheet piles exceeding 4.5 meters are driven in, two theodolites are used to control them in two directions to ensure verticality during the driving process. To prevent displacement of the center plane of the lock mouth, a card is installed at the lock mouth of the steel sheet pile in the direction of piling to prevent displacement of the sheet. The construction sequence includes forward sequence, reverse sequence, reciprocating sequence, center-division sequence, neutralization sequence and compound sequence. The driving sequence has a direct impact on the verticality, displacement, expansion and contraction in the axial direction, convexity and concavity of the sheet pile wall and piling efficiency of the sheet pile.

[0038] The above description is only a preferred embodiment of the present invention and does not limit the present invention in any form. Any simple modification or equivalent change made to the above embodiment based on the technical essence of the present invention shall fall within the protection scope of the present invention.

Claims

1. A construction method for deep foundation pit steel sheet piles for box culvert and pipeline construction, characterized in that: The following steps are involved: Step 1: Inspection and correction of steel sheet piles. Transport the steel sheet to the site and use steel sheet piles of the same type and specification with standard locking to check the locking of the same type of steel sheet piles. The inspection is carried out by pulling the standard steel sheet flat car with a winch from the pile head to the pile tail. If the steel sheet pile is found to be bent, damaged, or the locking is not in place, the steel sheet pile is repaired by a repair device. The twisted and bent pile body is corrected by a hydraulic jack. Step 2: Arrangement and preparation of steel sheet piles. Use a marker pen to add marks to the inspected and corrected steel sheet piles, and mark the order of steel sheet pile insertion with Arabic numerals according to the situation; apply butter to the locks on both sides of the steel sheet piles to reduce the friction resistance during insertion, and drive hardwood wedges into the lower end of the locks without sleeves to prevent mud and sand from blocking the locks during sinking and causing displacement of the steel sheet piles during insertion; Step 2: Install the guide frame: set up the guide frame according to the site conditions; Step 3: Select the pile sinking machine, use an excavator and a DZ90 vibrating pile driver to preset the pile column mouth; Step 4: Steel sheet pile driving, using a self-vibrating steel sheet pile special machine for driving; Step 5: Remove the steel sheet piles by using a vibrating hammer. The piles are removed by using a crane and a vibrating hammer. The forced vibration generated by the vibrating hammer disturbs the soil and destroys the cohesion of the soil around the sheet piles to overcome the resistance to pulling out the piles. The piles are removed by relying on the additional lifting force. Step 6: Pile hole treatment: After the steel sheet pile is pulled out, immediately insert the grouting pipe to grout the pile hole.

2. The method for constructing deep foundation pit steel sheet piles for box culvert and pipeline construction according to claim 1, characterized in that: In the step 2, after the preparation work is completed, the piles are stacked in the order of pile insertion; the number of stacking layers shall not exceed four, each layer shall be supported by pads, the height difference of the pads shall not be greater than 10m, and the center lines of the upper and lower pads shall be on the same vertical line.

3. The method for constructing deep foundation pit steel sheet piles for box culvert and pipeline construction according to claim 1, characterized in that: The steps of driving the steel sheet piles are as follows: a. The front arm of the pile driver lifts the steel sheet pile, opens the head clamp plate to clamp the head, and then vertically inserts the steel sheet pile to the designed depth at the designed position through the hydraulic vibration hammer of the pile driver to complete the first steel sheet pile insertion; b. After the first pile is driven, the subsequent steel plates are inserted along the buckle groove of the previous pile to the designed depth until the steel sheet pile retaining system of the foundation pit is formed: the corners of the foundation pit are connected with large buckles to make the steel sheet piles continuous.

4. The method for constructing deep foundation pit steel sheet piles for box culvert and pipeline construction according to claim 1, characterized in that: During the installation of the steel sheet piles, one must be familiar with the conditions of the underground pipelines and structures before driving, and carefully lay out the accurate center line of the support piles; during the driving process, measure and monitor the slope of each pile at any time to ensure that it does not exceed 2%. When the deviation is too large and cannot be adjusted by the pulling method, pull it up and drive it again.

5. The method for constructing deep foundation pit steel sheet piles for box culvert and pipeline construction according to claim 1, characterized in that: When removing the steel sheet piles, for closed sheet pile walls, the pulling point should be at least 5 piles away from the corner; The starting point for pile extraction can be determined according to the conditions during pile sinking. If necessary, the jump extraction method can also be used. The order of extraction is best to be opposite to that of driving.

6. The method for constructing deep foundation pit steel sheet piles for box culvert and pipeline construction according to claim 1, characterized in that: In the removal of the steel sheet piles, when pulling out the piles, the locking mouth of the sheet piles can be first vibrated with a vibrating hammer to reduce the adhesion of the soil, and then the piles can be pulled out while vibrating; for sheet piles that are difficult to pull out, the piles can be first vibrated down 100~300mm with a diesel hammer, and then alternately vibrated and pulled out with a vibrating hammer.

7. The method for constructing deep foundation pit steel sheet piles for box culvert and pipeline construction according to claim 1, characterized in that: During the removal of the steel sheet piles, the crane should be gradually loaded as the vibrator hammer is started, and the lifting force is generally slightly smaller than the compression limit of the shock absorber spring; the power supply used by the vibrator hammer is 1.2~2.0 times the rated power of the vibrator hammer itself; for sheet piles with large pulling resistance, intermittent vibration method is adopted, each vibration is 15 minutes, and the vibrator hammer should not exceed 1.5 hours continuously.

8. The method for constructing deep foundation pit steel sheet piles for box culvert and pipeline construction according to claim 1, characterized in that: In the pile hole treatment, the grouting material is made of 42.5 grade ordinary Portland cement to prepare slurry, the water-cement ratio is 0.55, the grouting flow rate is about 7~10L / min, and shall not be greater than 20L / min, the grouting pressure is controlled between 0.5~1.0MPa, and the amount of cement used for grouting each pile hole of the steel sheet pile shall not be less than 120kg / m; the horizontal spacing of the grouting holes is 0.6m (grouting is carried out for each pile hole), and the grouting depth is from the bottom of the steel plate pile to the natural ground.