Intelligent composite pile construction system based on digital and intelligent twin integration
Through the combination of digital twin technology and customized equipment, the automation and intelligence of pile foundation construction is realized, the problem of insufficient construction quality and efficiency under complex geological conditions is solved, real-time monitoring and quality assurance are achieved, and construction efficiency and quality are improved. .
Patent Information
- Application Number
- CN202411262576.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-10
- Publication Date
- 2024-11-12
AI Technical Summary
The existing pile foundation construction technology is difficult to achieve precise control under complex geological conditions. The seamless connection between digital and intelligent twin technology and actual construction process has not yet formed a systematic solution, resulting in insufficient construction quality and efficiency, especially in real-time monitoring and quality assurance. There are challenges.
Adopt an intelligent composite pile construction system based on digital twin technology, combining sensors and monitoring equipment, high-spray wet and dry stirring dual-channel contact detection reverse pressure cement soil integrated machine and overload voltage stabilization detection integrated machine to collect and analyze data in real time, dynamic Adjust construction parameters and material ratios to achieve automation and intelligence of the construction process.
It significantly improves the level of construction automation and quality reliability, shortens the construction cycle, realizes real-time inspection and optimization, ensures that the pile foundation meets the design standards, and improves construction efficiency and quality.
Abstract
Description
Technical Field
[0001] The invention relates to a composite foundation construction system. Background Art
[0002] In the traditional pile foundation construction process, the quality control of the pile foundation mainly relies on experienced engineers and manual inspection. This method usually involves detailed geological surveys and design calculations at the construction site, and construction is carried out according to these design drawings and standards. Although this process can theoretically guarantee the quality of construction, there are many challenges in actual operation. Especially under complex geological conditions, the deviation between the design assumptions and the actual situation may have a significant impact on the quality of the pile foundation. In addition, every detail in the construction process, such as the driving depth of the pile, the construction location, the length and diameter of the pile, etc., needs to be strictly monitored, which is often difficult to achieve entirely by manual inspection.
[0003] As a new type of pile foundation technology, rigid composite piles have gradually received attention in recent years. Rigid composite piles combine the advantages of traditional pile foundation technology and the development of modern engineering technology, especially showing great advantages in dealing with complex geological conditions. This pile foundation technology usually consists of two parts: one is the core part of the composite pile, usually a high-strength steel pipe or prestressed concrete pile, and the other is the outer soft soil or fill layer. This design can effectively improve the bearing capacity and stability of the pile foundation. The use of rigid composite piles can significantly improve the overall bearing capacity of the foundation, especially under soft soil or uneven foundation conditions.
[0004] However, there are also certain technical challenges in the construction process of rigid composite piles. First, this pile foundation technology requires precise control of the design and construction details of the pile body to ensure that every part of the composite pile can meet the expected performance standards. In the traditional construction process, these details are often difficult to fully guarantee through manual inspection, thus affecting the overall construction quality. Secondly, the construction process of rigid composite piles may involve a variety of construction processes, such as driving the pile body, pouring concrete, and prestressing the pile body, and each link requires strict quality control.
[0005] With the development of science and technology, the emergence of digital twin technology has brought new opportunities for pile foundation construction, especially rigid composite pile construction. Digital twin technology can simulate and optimize the actual construction process in real time by creating a virtual model of the construction site. This technology can digitize the physical environment and construction process of the construction site, and realize real-time monitoring and data analysis of the construction process. By integrating various real-time data into the virtual model, engineers can simulate operations in a virtual environment, predict possible problems in construction, and adjust construction strategies to optimize construction quality.
[0006] Although the application of digital twin technology in pile foundation construction has shown great potential, the existing technical solutions still have some shortcomings. The current digital twin technology has not yet formed a systematic solution for seamlessly connecting the virtual model with the actual construction process. For example, how to accurately integrate various real-time data into the virtual model and how to dynamically adjust and optimize operations during the construction process are still technical challenges. In addition, the consistency between the digital model and the actual construction situation also needs to be further verified to ensure the overall improvement of construction quality.
[0007] In general, although the application of rigid composite piles has significant advantages in improving pile foundation quality and bearing capacity, quality control problems in traditional construction methods still exist. The introduction of digital twin technology provides a new direction for solving these problems, but the existing technical solutions have not yet completely solved the challenges in real-time monitoring, operation optimization and quality assurance. In the future, a comprehensive and integrated intelligent construction system is needed to effectively integrate digital twin technology with all aspects of the rigid composite pile construction process to achieve a comprehensive improvement in the quality and efficiency of pile foundation construction. This can not only make up for the shortcomings of traditional methods, but also promote the development of pile foundation construction technology and bring a more intelligent construction method.
[0008] The existing pile foundation construction cannot obtain the construction status and quality of the constructed entities in real time during the construction process, and cannot predict the subsequent construction problems and make timely adjustments. The existing pile foundation construction is not smart, systematic, and dynamic enough. The high-pressure spraying and dry-wet mixing cement soil construction in the existing technology cannot control the water-cement ratio. Summary of the invention
[0009] The purpose of the present invention is to provide an intelligent composite pile construction system based on the integration of digital and intelligent twins, which uses digital and intelligent twin technology, cooperates with customized equipment and corresponding construction processes, makes pile foundation construction more forward-looking and systematic, improves the entity quality and completes entity quality detection during construction.
[0010] The technical solution of the present invention is: An intelligent composite pile construction system based on digital and intelligent twin integration, characterized by: including sensors and monitoring equipment, a high-pressure spraying dry-wet mixing dual-channel sounding back-pressure cement-soil integrated machine, and an overload voltage stabilization detection integrated machine; through real-time data collection and analysis by sensors, and through monitoring equipment to simulate the construction process, optimize mechanical operation, and adjust subsequent material models and ratios, it can improve the automation and intelligence level of the construction process and improve the quality and reliability of the pile foundation entity.
[0011] The high-pressure spraying dry-wet mixing dual-channel sounding back-pressure cement-soil integrated machine comprises a stirring shaft driven by a main motor, a knife-shaped blade and a spiral blade are arranged on the stirring shaft, the knife-shaped blade is located above the spiral blade, a water spray pipe and a powder spray pipe are arranged in the stirring shaft, and the nozzles of the water spray pipe and the powder spray pipe are located on the spiral blade; during stirring, multi-layer spiral blade self-tapping back pressure is adopted, and torque and current values are obtained during the construction process in cooperation with sensor equipment, and the water-cement ratio is dynamically adjusted, and the water-cement ratio is adjusted by the current value of the stirring machinery, when the current value is large, the water-cement ratio is increased; when the current value is small, the water-cement ratio is reduced; and according to the torque and current values obtained in real time, the pile diameter, pile length, and the depth of the pile end entering the bearing layer are controlled; the main motor performs back pressure densification on the cement-soil pile body with high energy.
[0012] The overload pressure stabilization detection integrated machine has its own pressure stabilization system, including a pile driving system and a pile holding system. It can hold the pile when the pile reaches the bottom through pile driving and pile sinking construction, control the pile pressure and pressure stabilization and re-pressure time, and use high pressure. The pile stabilization and pile driving force can be stabilized at 6000-10000KN. In conjunction with sensors and monitoring equipment, the core pile material strength and the side friction resistance and end resistance provided by cement soil or soil and cement soil can be verified during the construction process.
[0013] The water-cement ratio is adjusted between 0-0.8; the optimal moisture content of cement soil is 16~22%.
[0014] The system of the present invention uses digital twin technology, customized equipment and corresponding construction technology to make pile foundation construction more forward-looking and systematic, improve entity quality and complete entity quality inspection during construction. The main functions are: data simulation, dry-wet mixing, back pressure densification, penetration detection, data feedback, dynamic adjustment, overload voltage stabilization, and data analysis. It is suitable for foundation treatment, composite pile construction, and composite foundation construction in the geological conditions of the upper soft soil layer and the lower colloid gravel layer.
[0015] The present invention also has the advantages that: Improve the level of construction automation: Through the integration of digital twin technology and intelligent equipment, the system can automatically adjust construction parameters and operations, significantly improve the level of automation in the construction process, and reduce interference from human operations.
[0016] Optimize construction quality: The system monitors various indicators during the construction process in real time, and simulates and optimizes through virtual models, which can effectively improve the quality and reliability of pile foundation construction and reduce construction defects.
[0017] Improve construction efficiency: Through efficient data collection and processing, intelligent construction operations and real-time optimization suggestions, the system can significantly improve construction efficiency and shorten the construction period.
[0018] Achieve comprehensive quality inspection: The system conducts comprehensive quality inspection during and after construction, which can promptly detect and solve quality problems and ensure that the pile foundation meets the design standards.
[0019] The integrated and intelligent composite pile composite foundation construction system based on digital twin of the present invention realizes the comprehensive intelligence of the pile foundation construction process by integrating advanced sensor technology, high-pressure spraying dry-wet mixing dual-channel equipment and overload voltage stabilization detection integrated machine, combined with digital twin technology. The system not only improves the construction quality and efficiency, but also can complete real-time detection and optimization during the construction process, and has broad application prospects and practical value.
[0020] The present invention will be further described below in conjunction with the embodiments. DETAILED DESCRIPTION
[0021] An intelligent composite pile construction system based on digital and intelligent twin integration, including sensors and monitoring equipment, a high-pressure spraying dry-wet mixing dual-channel sounding back-pressure cement-soil integrated machine, and an overload voltage stabilization detection integrated machine; through real-time data collection and analysis by sensors, and through monitoring equipment to simulate the construction process, optimize mechanical operation, and adjust subsequent material models and ratios, it can improve the automation and intelligence level of the construction process and improve the quality and reliability of the pile foundation entity.
[0022] The sensors and monitoring equipment are used to collect various data from the construction site in real time, including geological information, construction equipment status, material ratio, etc. Sensors can be installed in various key links of pile foundation construction, such as drilling, concrete pouring, pile driving, etc., to ensure the comprehensiveness and accuracy of the data. The monitoring equipment can dynamically adjust the construction parameters and optimize the construction operation by connecting with the sensor data in real time.
[0023] The high pressure spraying dry-wet mixing dual-channel sounding back-pressure cement soil integrated machine integrates high pressure spraying dry-wet mixing, sounding and back-pressure cement soil processing functions, and can adjust the cement soil ratio and mixing effect in real time during the construction process to ensure the uniformity and stability of the pile foundation material. The dual-channel design improves construction efficiency, and the sounding function is used to detect the foundation condition in real time to ensure the accuracy of the construction process. It includes a stirring shaft driven by a main motor, on which knife-shaped blades and spiral blades are arranged, the knife-shaped blades are located above the spiral blades, and a water spray pipe and a powder spray pipe are arranged in the stirring shaft, and the nozzles of the water spray pipe and the powder spray pipe are located on the spiral blades; during stirring, multi-layer spiral blades are used for self-tapping back pressure, and sensor equipment is used to obtain torque and current values during construction, and the water-cement ratio is dynamically adjusted. The water-cement ratio is adjusted by the current value of the stirring machinery. When the current value is large, the water-cement ratio is increased; when the current value is small, the water-cement ratio is reduced; and according to the torque and current values obtained in real time, the pile diameter, pile length, and the depth of the pile end entering the bearing layer are controlled; the 2*132KW main motor uses high energy to counter-press and densify the cement soil pile body.
[0024] The overload and pressure stabilization detection integrated machine is used to monitor the overload situation during the pile foundation construction process, and automatically adjust the construction pressure to avoid deformation or damage of the pile body. By detecting the load situation of the pile body in real time, problems in the construction can be discovered and solved in time to ensure the safety and stability of the pile foundation. It comes with a pressure stabilization system, including a pile pressing system and a pile holding system. Through the pile pressing and pile sinking construction, the pile holding system can control the pile pressure and the pressure stabilization and re-pressure time. With high pressure, the pile stabilization and pile pressing force can be stabilized at 6000-10000KN. With sensors and monitoring equipment, the core pile material strength and the side friction resistance and end resistance provided by cement soil or soil and cement soil can be verified during the construction process.
[0025] The water-cement ratio is adjusted between 0-0.8; the optimal moisture content of cement soil is 16~22%.
[0026] Before specific construction: Establish a digital information technology (BIM) model based on the construction drawings and geological survey reports to conduct a forward-looking simulation of the overall construction situation.
[0027] Specific construction in progress: Flexible pile construction uses a 2*132kw main motor high-pressure spraying dry-wet mixing dual-channel penetration back pressure cement soil integrated machine, which has the function of exploration and geophysical exploration, layer-by-layer back pressure (30 tons of self-tapping back pressure of spiral blades per 15mm layer + 15 tons of motor drill rod deadweight + 100 tons of steel rope chain pressure), and timely adjusts the amount of water spray and cement according to the current and torque data, quickly drills into the dense gravel cementation layer, and the high-pressure gas splits the soft soil to form an exhaust and drainage channel, and the disturbance softening discharges the water in the upper silt sand layer, and the soft soil solidifies into a harder cement-containing soil body. According to the geological survey model and on-site exploration, the soft soil situation is judged. When the soil moisture content is more than 30%, dry construction is suitable for simultaneous drainage and precipitation; when the soil moisture content is less than 30%, wet construction is suitable for adding water, stirring and spraying powder, and the physical and mechanical properties of the in-situ soil are improved to achieve the optimal moisture content of the soil. When using the dry or wet mixing method with water, the current increase is more than 35A, and the stirring current of the bearing layer is greater than 20A of the upper soil layer. At the same time, according to the construction data of flexible piles, the length of the pipe pile can be determined to avoid pile cutting.
[0028] The rigid pipe pile construction uses a 1260t overload and pressure stabilization detection integrated machine, which has its own pressure stabilization device and can control the pile pressure and pressure stabilization and re-pressure time. With customized ultra-high-strength pipe piles with increased wall thickness and a diameter of 400-600mm, the maximum pressure stabilization and pile pressure can reach 6000-9000KN; it has its own mechanical sensor to display the depth and pile pressure in real time, so that the pile can be tested at the same time and meet the pile bearing capacity requirements under the most unfavorable conditions. The extrusion pressure during the construction of the rigid core pile will further increase the density and strength of the flexible pile, and at the same time, the soil around the pile will be optimized and reinforced for the second time.
[0029] After construction: After the cement soil is completely hardened (28 days), the final pipe pile bearing capacity can reach 1.5-2 times the stabilizing pressure pile force.
[0030] Optimization of the construction process: During the construction process, the digital twin system will monitor various indicators in real time, including pile driving depth, concrete strength, material ratio, etc. Through data analysis and model simulation, the system can automatically adjust mechanical operation, optimize material ratio, and make suggestions for construction improvement. For example, if it is found that the pile driving depth is insufficient, the system will automatically adjust the operating parameters of the pile driver to ensure that the pile meets the design requirements.
[0031] Quality inspection and feedback: After the construction is completed, the system will conduct a comprehensive inspection of the pile foundation through sensors, including strength testing, stability inspection, etc. The digital twin model will compare these test results with the design standards to ensure that the quality of the pile foundation meets the requirements. If quality problems are found, the system will generate a detailed report and make rectification suggestions to ensure that the construction quality finally meets the standards.
[0032] Intelligent management and maintenance: The system can not only provide real-time support during the construction process, but also conduct long-term monitoring and maintenance after the construction is completed. Through continuous data collection and analysis, the system can monitor the use status of the pile foundation in real time, detect potential quality problems in a timely manner, and conduct early warning and maintenance.
Claims
1. An intelligent composite pile construction system based on digital twin integration, Its characteristics are: It includes sensors and monitoring equipment, a high-pressure spraying dry-wet mixing dual-channel sounding back-pressure cement soil integrated machine, and an overload voltage stabilization detection integrated machine; it collects and analyzes data in real time through sensors, and simulates the construction process, optimizes mechanical operations, and adjusts subsequent material models and ratios through monitoring equipment, which can improve the automation and intelligence level of the construction process and improve the quality and reliability of the pile foundation entity.
2. According to the intelligent composite pile construction system based on digital and intelligent twin integration according to claim 1, Its characteristics are: The high-pressure spraying dry-wet mixing dual-channel sounding back-pressure cement-soil integrated machine comprises a stirring shaft driven by a main motor, a knife-shaped blade and a spiral blade are arranged on the stirring shaft, the knife-shaped blade is located above the spiral blade, a water spray pipe and a powder spray pipe are arranged in the stirring shaft, and the nozzles of the water spray pipe and the powder spray pipe are located on the spiral blade; during stirring, multi-layer spiral blade self-tapping back pressure is adopted, and torque and current values are obtained during the construction process in cooperation with sensor equipment, and the water-cement ratio is dynamically adjusted, and the water-cement ratio is adjusted by the current value of the stirring machinery, when the current value is large, the water-cement ratio is increased; when the current value is small, the water-cement ratio is reduced; and according to the torque and current values obtained in real time, the pile diameter, pile length, and the depth of the pile end entering the bearing layer are controlled; the main motor performs back pressure densification on the cement-soil pile body with high energy.
3. According to the intelligent composite pile construction system based on digital and intelligent twin integration as described in claim 1, Its characteristics are: The overload pressure stabilization detection integrated machine has its own pressure stabilization system, including a pile driving system and a pile holding system. It can hold the pile when the pile reaches the bottom through pile driving and pile sinking construction, control the pile pressure and pressure stabilization and re-pressure time, and use high pressure. The pile stabilization and pile driving force can be stabilized at 6000-10000KN. In conjunction with sensors and monitoring equipment, the core pile material strength and the side friction resistance and end resistance provided by cement soil or soil and cement soil can be verified during the construction process.
4. According to claim 2, the intelligent composite pile construction system based on digital and intelligent twin integration, Its characteristics are: The water-cement ratio is adjusted between 0-0.8; the optimal moisture content of cement soil is 16~22%.
Citation Information
Cited By
Dynamic pile sinking construction control method and system based on digital twinning
CN120006778A
Self-adaptive settlement monitoring and compensation construction integrated system
CN120651189A