Close splicing connection laminated slab based on BIM technology and construction method

Through the BIM technology, the densely-connected laminated plate is designed, and the combination of limit plates and prefabricated plates and the through-pipe connections are solved, and the problems of low construction efficiency and uneconomical use of steel bars are achieved. The rapid positioning of prefabricated plates and floor slabs are achieved. The efficient connection improves construction efficiency and integrity, and reduces the waste of steel bars and on-site operation.

CN118933246APending Publication Date: 2024-11-12JIANGSU UNIV OF SCI & TECH
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202411006107.7
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-25
Publication Date
2024-11-12

AI Technical Summary

Technical Problem

The construction efficiency of overlapping floor slabs in existing prefabricated buildings is low, the use of steel bars is uneconomical, and there are problems of positioning difficulties and waste of steel bars during production and construction.

Method used

Using a densely-integrated overlapping plate designed based on BIM technology, the combination of limiting plates and prefabricated plates is used to achieve rapid positioning of prefabricated plates, reducing measurement and adjustment, and improving the combination of waterproof pads and prefabricated angle steel Connection strength and stability.

Benefits of technology

It improves the accuracy and construction efficiency of the connection position of prefabricated plates, reduces the difficulty of production and construction, reduces the use of steel bars and on-site operation, enhances the integrity and lateral stiffness of the floor slabs, and saves construction period and cost.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118933246A_ABST
    Figure CN118933246A_ABST
Patent Text Reader

Abstract

The invention discloses a closely-spliced laminated slab based on a BIM technology and a construction method, and belongs to the technical field of fabricated buildings and construction thereof. The closely-spliced laminated slab comprises laminated layers on the two sides, limiting plates and a prefabricated slab in the middle; the plurality of prefabricated slabs are spliced and connected; the limiting plate, the prefabricated plate and the laminated layer are connected through connecting bolts. The limiting plate is designed based on the BIM technology, the trepanning position is determined, the positioning device is used for firstly fixing the limiting plate and can also be used as a laminated slab supporting cross beam, when the prefabricated slab is hoisted, the prefabricated slab is rapidly in place by inserting the penetrating pipeline on the limiting plate into the limiting hole channel of the prefabricated slab, multiple times of measurement and paying-off during hoisting are not needed, and the hoisting efficiency is improved. Therefore, repeated position adjustment can be reduced when the precast slab is hoisted, and the accuracy of the connecting position of the precast slab in the later period is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of prefabricated buildings and construction thereof, and in particular to a close-jointed composite board and a construction method based on BIM technology. Background Art

[0002] As an important horizontal load-bearing component in a building, the floor slab bears and transmits vertical loads and coordinates various vertical components. In prefabricated buildings, the floor slab is used in large quantities, has a high cost, and takes a long time to construct. Its structural form and construction method have a great impact on the structural force, cost, and construction period.

[0003] At present, common composite slabs are in the form of one-way slabs, which causes problems such as excessive reinforcement and excessive slab thickness; or when the span is small and the slab is thin, it is still designed as a two-way slab. The composite slab is designed to have "reinforcement on all four sides", which increases the difficulty of steel bar positioning and demoulding during component production, and during construction, it is necessary to support the formwork at the joints, which makes the supporting beams shorter and increases the difficulty of construction. Not only is the construction efficiency low, but the cost of work tools and labor is also greatly increased.

[0004] At present, in order to increase the connection stiffness of the transverse plates, the common close-jointed composite slabs often adopt the form of setting additional steel bars. However, the additional steel bars are close to the neutral axis and have limited contribution to the bearing capacity, resulting in a waste of steel bars.

[0005] The lifting and installation of prefabricated components requires operators to repeatedly adjust the position of the components in order to carry out subsequent steel bar connections, which results in low construction efficiency.

[0006] Modeling and construction simulation of prefabricated buildings through BIM (Building Information Modeling) technology can improve construction efficiency and accuracy. Summary of the invention

[0007] In view of the deficiencies in the prior art, the present invention provides a close-joined composite slab and a construction method based on BIM technology. The limit plate is designed based on BIM technology and the position of the opening is determined. The limit plate is first fixed by a positioning device, and can also be used as a supporting beam for the composite slab. When hoisting the prefabricated slab, the prefabricated slab is quickly put into place by inserting the pipe passing through the limit plate into the limit hole of the prefabricated slab. There is no need to measure and lay out lines multiple times during hoisting, which can reduce repeated adjustments of the position when hoisting the prefabricated slab, thereby improving the accuracy of the connection position of the prefabricated slab in the later stage.

[0008] The present invention achieves the above technical objectives through the following technical means.

[0009] A close-jointed composite plate based on BIM technology comprises composite layers on both sides, a limiting plate and a prefabricated plate in the middle; a plurality of the prefabricated plates are spliced ​​and connected; the limiting plates, the prefabricated plates and the composite layers are connected by connecting bolts.

[0010] In the above scheme, the precast panel is a concrete structure, including connecting channels, bottom plate longitudinal reinforcement, bottom plate transverse reinforcement and embedded angle steel; the precast panel is provided with connecting channels; two embedded angle steels are arranged along the longitudinal direction of both sides of the precast panel, and the two embedded angle steels are arranged back to back; the embedded angle steels are connected by the bottom plate transverse reinforcement; the bottom plate transverse reinforcement is tied and connected with the bottom plate longitudinal reinforcement.

[0011] In the above scheme, a plurality of holes are formed on the embedded steel bars, and the holes correspond to the connection holes; and the connection bolts pass through the connection holes.

[0012] In the above scheme, a plurality of through pipes are arranged on the limit plate; a limit hole is opened on the prefabricated plate; the outer diameter of the through pipe is slightly smaller than the inner diameter of the limit hole, the length of the through pipe does not exceed the thickness of the prefabricated plate, and the through pipe is used to pass the limit bolt.

[0013] In the above solution, adjacent prefabricated panels are connected by waterproof pads and connecting bolts; the cross-section of the prefabricated panels is a T-shaped or stepped structure.

[0014] In the above scheme, the prefabricated plate and the limiting plate are connected by a limiting pad and limiting bolts; when the prefabricated plate and the limiting plate are connected, a limiting pad is arranged on the top surface of the prefabricated plate parallel to the direction of the limiting plate.

[0015] In the above scheme, the upper surface of the prefabricated board is a rough surface, and the lower surface is a mold table surface, and the rough surface is used for bonding with the overlapping surface.

[0016] In the above solution, the laminated layer includes concrete and bidirectional steel mesh.

[0017] In the above scheme, when the prefabricated board is connected with the adjacent prefabricated board, a waterproof pad strip parallel to the direction of the close joint is arranged on the upper part of the close joint above the prefabricated board.

[0018] The construction method of closely connected composite slabs based on BIM technology includes the following steps:

[0019] Lay out the lines and position the bottom support;

[0020] Position and temporarily fix the limit plate based on BIM technology;

[0021] First, hoist the prefabricated plate with the protruding part at the bottom, and pass the limiting hole of the prefabricated plate through the pipeline in the limiting plate to connect it in place;

[0022] Then hoist the prefabricated panels with protruding parts on the upper part, overlap the protruding parts of adjacent prefabricated panels with mortise and tenon joints, and pass the limiting holes of the prefabricated panels through the pipes in the limiting panels to achieve connection in place;

[0023] The prefabricated plate and the limiting plate are connected by limiting bolts and limiting pads;

[0024] Connect adjacent precast panels by connecting bolts and waterproof pads;

[0025] Tie up the bidirectional reinforcement in the laminated layer;

[0026] Casting superimposed layer.

[0027] Beneficial effects:

[0028] 1. The present invention designs a limit plate based on BIM technology and determines the position of the opening. The limit plate is first fixed by a positioning device, and can also be used as a supporting beam for the composite plate. When hoisting the prefabricated plate, the prefabricated plate is quickly put in place by inserting a pipe passing through the limit plate into the limit hole of the prefabricated plate. There is no need to measure and lay out lines multiple times during hoisting, so repeated adjustments of the position can be reduced when hoisting the prefabricated plate, thereby improving the accuracy of the connection position of the prefabricated plate in the later stage.

[0029] 2. When a larger rigidity limit plate is used, it can partially replace the composite slab support frame keel. In addition, the limit plate can increase the integrity of the floor slab by connecting with the precast slab. There are no protruding steel bars around the precast slab, which reduces the difficulty of production, demoulding, transportation and hoisting. The transverse reinforcement of the bottom plate of the precast slab is welded to the embedded angle steel as a whole, and is connected to the steel bars in the adjacent precast slab through waterproof pads and connecting bolts. In the present invention, there is no need to set additional steel bars when connecting adjacent precast slabs, and the bottom formwork of the floor slab is eliminated. The waterproof pads of the same length as the precast slabs are set to prevent leakage of post-cast concrete. The connecting bolts limit the deformation and cracking of the floor slab perpendicular to the direction of the close-jointed joints, and strengthen the force transmission and rigidity of the vertical close-jointed joints of adjacent precast slabs. The protruding parts of the corners of the precast slabs are realized by embedded angle steels, which improves the rigidity of this part. BRIEF DESCRIPTION OF THE DRAWINGS

[0030] Figure 1 It is an overall schematic diagram of a close-jointed composite slab based on BIM technology in the present invention;

[0031] Figure 2 It is a schematic diagram of the shape of a single prefabricated panel in the present invention;

[0032] Figure 3 This is a second schematic diagram of the shape of a single prefabricated panel in the present invention;

[0033] Figure 4 It is a schematic diagram of the shape of a single prefabricated panel in the present invention;

[0034] Figure 5 It is a schematic diagram of the shape of a single prefabricated panel in the present invention;

[0035] Figure 6 It is a layout diagram of the steel bar shape in a single prefabricated panel of the present invention;

[0036] Figure 7 It is a second arrangement diagram of the steel bar shape in a single prefabricated panel in the present invention;

[0037] Figure 8 It is a schematic diagram of the limiting plate in the present invention;

[0038] Fig. 9 It is a schematic diagram of the top surface after the adjacent prefabricated panels are assembled and before the superimposed layer is poured in the present invention;

[0039] Fig.10 It is a schematic diagram of the bottom surface of adjacent prefabricated panels after being assembled in the present invention.

[0040] Reference numerals:

[0041] 1- prefabricated board; 2- composite layer; 3- limit plate; 4- connection bolt; 5- waterproof pad; 6- limit bolt; 7- limit pad; 11- connection channel; 12- limit channel; 13- bottom plate longitudinal reinforcement; 14- bottom plate transverse reinforcement; 15- embedded angle steel; 31- through pipe. DETAILED DESCRIPTION

[0042] Embodiments of the present invention are described in detail below, examples of which are shown in the accompanying drawings, wherein the same or similar reference numerals throughout represent the same or similar elements or elements having the same or similar functions. The embodiments described below with reference to the accompanying drawings are exemplary and are intended to be used to explain the present invention, and should not be construed as limiting the present invention.

[0043] In the description of the present invention, it should be understood that the terms "center", "longitudinal", "lateral", "length", "width", "thickness", "upper", "lower", "axial", "radial", "vertical", "horizontal", "inner", "outer" and the like indicate positions or positional relationships based on the positions or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as limiting the present invention. In addition, the terms "first" and "second" are only used for descriptive purposes, and cannot be understood as indicating or implying relative importance or implicitly indicating the number of technical features indicated. Thus, the features defined as "first" and "second" may explicitly or implicitly include one or more of the features. In the description of the present invention, the meaning of "multiple" is two or more, unless otherwise clearly and specifically defined.

[0044] In the present invention, unless otherwise clearly specified and limited, the terms "installed", "connected", "connected", "fixed" and the like should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be an indirect connection through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0045] Combined with Figure 1 As shown, the present invention adds a limit plate 3 designed by BIM technology on the basis of the traditional composite plate, and the precast plate 1 is positioned by the through pipe 31 on the limit plate 3. The precast plate 1 and the limit plate 3 are connected by the limit bolt 6 passing through the through pipe 31, and are combined with the limit pad 7. Adjacent precast plates 1 are connected by connecting bolts 4 and waterproof pads 5, and the composite layer 2 is cast above the precast plates 1 to form a whole; the precast plates 1 and the composite layer 2 are both concrete structures, and the waterproof pads 5 are placed above the close joints between the adjacent precast plates 1; the composite layer 2 contains bidirectional stress-bearing steel bars.

[0046] Combined with Figure 2-5 As shown, the corner of the prefabricated panel 1 is provided with an embedded angle steel 15 along the length direction of the prefabricated panel, and the connection channel 11 on the prefabricated panel 1 is located on the protruding part formed by the embedded angle steel 15, and the reserved holes on the embedded angle steel 15 are aligned one by one with the connection channel 11; Figure 6-7 As shown, two embedded angle steels 15 are arranged back to back, and the openings of the embedded angle steels 15 are arranged downward or upward. The embedded angle steels 15 in the prefabricated panel 1 can be arranged in different directions to form a lower corner protrusion or an upper corner protrusion.

[0047] Combination Figure 2-5 As shown, the upper surface of the prefabricated board 1 is a rough surface, and the lower surface is a smooth surface or a mold table surface. The purpose of setting it as a rough surface is that the rough surface can better bond with the laminated layer. In the figure, mark C represents the rough surface, and M represents the mold table surface.

[0048] Figure 2-3 In the process, these two prefabricated panels are arranged in the middle of the close-fitting composite panels. Figure 4-5 In the method, two types of prefabricated panels are arranged on both sides of the close-fitting composite panel, and different prefabricated panel structures are used to meet the needs of the close-fitting positions.

[0049] Combined with Figure 6-7As shown, there is no steel bar protruding around the precast panel 1. The bottom plate longitudinal reinforcement 13 and the bottom plate transverse reinforcement 14 are arranged inside the precast panel 1. The bottom plate longitudinal reinforcement 13 and the bottom plate transverse reinforcement 14 are connected by binding to form a steel mesh. The bottom plate transverse reinforcement 14 is welded to the embedded angle steel 15. A number of holes are arranged on the embedded angle steel 15, and the holes are aligned one by one with the connection channels 11 on the precast panel 1. The connection channels 11 are used for bolt connection between adjacent precast panels 1. It can be seen that Figure 6 The longitudinal ribs 13 of the middle bottom plate are arranged above the transverse ribs 14 of the bottom plate. Figure 7 The middle bottom plate longitudinal reinforcement 13 is arranged below the bottom plate transverse reinforcement 14, and the bottom plate longitudinal reinforcement and the bottom plate transverse reinforcement are evenly distributed. Both the arrangement modes of the bottom plate transverse reinforcement and the bottom plate longitudinal reinforcement can meet the actual production requirements.

[0050] In the present invention, the embedded angle steel is welded to the bottom plate transverse reinforcement, so that the size of the prefabricated plate can be adjusted according to actual production needs, and therefore, the prefabricated plate has strong adaptability.

[0051] In the present invention, the prefabricated panels are first positioned by the limiting plates, and then the prefabricated panels are connected to each other by mortise and tenon joints or overlapped joints, and then connected by connecting bolts, which is easy to operate and has high precision.

[0052] Combined with Figure 8 As shown, the through pipe 31 is used to insert into the limiting hole 12 to realize the accurate positioning of the prefabricated panel 1. The diameter of the through pipe 31 is slightly larger than the diameter of the limiting hole. The setting of the through pipe enables the prefabricated panel to be positioned quickly, thereby improving the construction efficiency and accuracy.

[0053] Combined with Figure 9-10 As shown, when adjacent prefabricated panels 1 are connected by connecting bolts 4, waterproof pads 5 are placed above the close joints at the top of the prefabricated panels 1; when the prefabricated panels 1 and the limiting panels 3 are connected by limiting bolts 6, limiting pads 7 are placed on the top of the prefabricated panels 1 in parallel to the direction of the limiting panels 3; the limiting panels 3 are the same width as the floor slab after splicing. The purpose of setting waterproof pads in the present invention is to prevent concrete or liquid from entering the mortise and tenon joints of the prefabricated panels when the superimposed layers are poured, thereby improving the strength of the combination and extending the service life; the purpose of setting the limiting pads is to improve the connection strength and stability between the prefabricated panels and the limiting panels.

[0054] The construction method of the close-joined composite slab based on BIM technology in this embodiment is as follows:

[0055] 1. Lay out the lines and position the bottom support;

[0056] 2. Position and temporarily fix the limit plate 3 based on BIM technology;

[0057] 3. First, hoist the prefabricated plate 1 with the protruding part at the bottom, and pass the limiting hole 12 of the prefabricated plate 1 through the through-pipe 12 in the limiting plate 3 to realize the connection in place;

[0058] 4. Then hoist the prefabricated panels 1 with protruding parts on the upper part, overlap the protruding parts of adjacent prefabricated panels 1 with mortise and tenon joints, and pass the limiting holes 12 of the prefabricated panels 1 through the pipes 31 in the limiting panels 3 to achieve connection in place;

[0059] 5. Connect the prefabricated plate 1 and the limiting plate 3 through the limiting bolts 6 and the limiting pads 7;

[0060] 6. Connect adjacent prefabricated panels 1 through connecting bolts 4 and waterproof pads 5;

[0061] 7. Tie up the bidirectional reinforcement in the laminated layer 2;

[0062] 8. Pour the superimposed layer 2.

[0063] In summary, the present invention is based on the BIM technology to closely connect the composite panels, and adopts the BIM technology to design the limit plates. It can reduce the laying-out measurement and repeated correction on site, and can quickly and efficiently realize the accurate positioning of the precast panels. The closely connected joints of adjacent precast panels are formed by the protruding parts of the precast panels and reliably connected with bolts, and then the post-casting superimposed layer is used to realize the closely connected superimposed connection of the precast panels, thereby forming an integral floor slab. The present invention can solve the problems of the difficulty of demoulding the reinforcement production around the composite panels, the low efficiency of the precast panels hoisting and positioning, and the complex connection of the transverse steel bars. The transverse reinforcement of the bottom plate in the adjacent precast panels is reliably connected by angle steel and bolts, which improves the transverse stiffness of the composite panels. There is no need to arrange additional reinforcements with a higher position and limited bearing capacity. The waterproof pads are fixed above the closely connected joints to prevent leakage during the pouring of the post-casting layer. At the same time, the amount of wet work on site and the amount of steel bar connection work are reduced, which can speed up the construction period, improve construction efficiency, and save construction costs.

[0064] In the description of this specification, the description with reference to the terms "one embodiment", "some embodiments", "examples", "specific examples", or "some examples" means that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the present invention. In this specification, the schematic representation of the above terms does not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials or characteristics described may be combined in any one or more embodiments or examples in a suitable manner.

[0065] Although the embodiments of the present invention have been shown and described above, it is to be understood that the above embodiments are exemplary and are not to be construed as limitations on the present invention. A person skilled in the art may change, modify, replace and modify the above embodiments within the scope of the present invention without departing from the principles and intent of the present invention.

Claims

1. A close-jointed composite slab based on BIM technology. It is characterized in that It comprises overlapping layers on both sides, a limiting plate and a prefabricated plate in the middle; a plurality of the prefabricated plates are spliced ​​and connected; the limiting plates, the prefabricated plates and the overlapping layers are connected by connecting bolts.

2. According to the BIM technology-based close-jointed composite slab of claim 1, It is characterized in that The prefabricated panel is a concrete structure, including connecting channels, bottom plate longitudinal reinforcement, bottom plate transverse reinforcement and embedded angle steel; the prefabricated panel is provided with connecting channels; two embedded angle steels are arranged along the longitudinal direction of both sides of the prefabricated panel, and the two embedded angle steels are arranged back to back; the embedded angle steels are connected by the bottom plate transverse reinforcement; the bottom plate transverse reinforcement is tied and connected with the bottom plate longitudinal reinforcement.

3. According to the BIM technology-based close-jointed composite slab of claim 2, It is characterized in that The embedded steel bars are provided with a plurality of holes corresponding to the connection holes; the connection holes are penetrated by connection bolts.

4. According to the BIM technology-based close-jointed composite slab of claim 1, It is characterized in that A plurality of through pipes are arranged on the limit plate; a limit hole is provided on the prefabricated plate; the outer diameter of the through pipe is slightly smaller than the inner diameter of the limit hole, the length of the through pipe does not exceed the thickness of the prefabricated plate, and the through pipe is used to pass the limit bolt.

5. The close-joined composite slab based on BIM technology according to claim 1, It is characterized in that The adjacent prefabricated panels are connected by waterproof pads and connecting bolts; the cross section of the prefabricated panels is a T-shaped or stepped structure.

6. The close-joined composite slab based on BIM technology according to claim 1, It is characterized in that The prefabricated plate and the limiting plate are connected via a limiting pad and limiting bolts; when the prefabricated plate and the limiting plate are connected, a limiting pad parallel to the direction of the limiting plate is arranged on the top surface of the prefabricated plate.

7. The close-joined composite slab based on BIM technology according to claim 1, It is characterized in that The upper surface of the prefabricated board is a rough surface, and the lower surface is a mold table surface. The rough surface is used for bonding with the overlapping surface.

8. The close-joined composite slab based on BIM technology according to claim 1, It is characterized in that The laminated layer includes concrete and a bidirectional steel mesh.

9. The close-joined composite slab based on BIM technology according to claim 1, It is characterized in that When the prefabricated board is connected with adjacent prefabricated boards, a waterproof pad strip parallel to the direction of the close-jointed seam is arranged on the upper part of the close-jointed seam above the prefabricated board.

10. The construction method of closely connected composite slabs based on BIM technology according to any one of claims 1 to 9, It is characterized in that The steps include: Lay out the lines and position the bottom support; Position and temporarily fix the limit plate based on BIM technology; First, hoist the prefabricated plate with the protruding part at the bottom, and pass the limiting hole of the prefabricated plate through the pipeline in the limiting plate to connect it in place; Then hoist the prefabricated panels with protruding parts on the upper part, overlap the protruding parts of adjacent prefabricated panels with mortise and tenon joints, and pass the limiting holes of the prefabricated panels through the pipes in the limiting panels to achieve connection in place; The prefabricated plate and the limiting plate are connected by limiting bolts and limiting pads; Connect adjacent precast panels by connecting bolts and waterproof pads; Tie up the bidirectional reinforcement in the laminated layer; Casting superimposed layer.