Device for reducing rock mass fracture opening degree based on multiple high-pressure ejection grouting and using method
Through multiple high-pressure ejection grouting devices, the problem of repairing cracks in large-scale rock mass is solved by using components such as magnetic slurry, water glass balls and ceramic balls, and the problem of repairing cracks in large-scale rock mass is solved, uniform distribution and rapid solidification of the slurry are achieved, and the stability of the rock mass is enhanced. and construction efficiency.
Patent Information
- Application Number
- CN202411138563.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-19
- Publication Date
- 2024-11-12
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
The prior art is difficult to effectively repair rock mass cracks with large openness, and the slurry cannot be evenly filled and solidified slowly, resulting in insufficient structural strength of the filling material.
Using multiple high-pressure ejection grouting devices, using components such as magnetic slurry, water glass balls and ceramic balls, through precise high-pressure injection and the design of the adhesive layer, the uniform distribution and rapid solidification of the slurry are achieved, and the overall strength of the cracks is enhanced.
Effectively reduce the crack opening of rock mass, improve the coverage area and solidification speed of the slurry, enhance the overall strength after repair, and reduce construction costs and manpower consumption.
Smart Images

Figure CN118933876A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the field of secondary grouting in repairing rock mass fissures, and in particular to a device and a method for using the device to reduce the opening of rock mass fissures based on multiple high-pressure ejection grouting. Background Art
[0002] Since processes such as crustal movement, weathering, igneous rock condensation, and sediment solidification can damage rock masses and form cracks with larger openings, the stability of fractured rock masses is an important research field in rock slope engineering. Its suddenness and destructiveness directly threaten the safety of people's lives and property. Under the influence of geological tectonic activities, human engineering activities, long-term weathering, and heavy rainfall, natural rock masses form various macroscopic and microscopic cracks. Since stress concentration often occurs at the crack tips, the fracture extension at the crack tips is an important factor leading to the instability and destruction of rock slope engineering. Therefore, it is essential to repair rock cracks. In order to more effectively repair rock cracks, a device and method for reducing the opening of rock cracks by multiple high-pressure ejection grouting have been invented, which greatly reduces the consumption of manpower and financial resources and reduces the economic cost of construction. Summary of the invention
[0003] The present invention provides a device and a method for using the device to reduce the opening of rock mass fissures based on multiple high-pressure ejection grouting, which solves the problem that cracks with larger openings formed by processes such as crustal movement, weathering, condensation of igneous rocks and solidification of sediments need to be repaired, and solves the problem that conventional secondary grouting can usually only perform grouting on cracks with smaller openings, but has poor effect on cracks with larger openings. The device and technology provided by the present invention are simple and convenient to operate, and have broad engineering practice significance and application prospects. In addition, the present invention also solves the problem that slurry cannot be evenly filled in cracks, solves the problem of structural strength of filling materials after filling, and solves the problem of slow solidification of slurry.
[0004] In order to realize the above technical features, the technical solution adopted by the present invention is: A device for reducing the opening of rock fractures based on multiple high-pressure ejection grouting, comprising a grouting device, wherein the gun head of the grouting device is slidably engaged with a gun cover, one side of the gun head is connected to a chamber, the upper end of the chamber is connected to a feeding pipe, the top of the feeding pipe is provided with a conical mouth, the bottom of the chamber is connected to a pressurized air pipe, a plurality of springs are provided at the connection between the outer wall of the chamber and the inner wall of a steel pipe, and a plurality of grouting liquid balls and a plurality of water glass balls are respectively provided in the chamber of the grouting device.
[0005] The cladding liquid ball is filled with magnetic slurry, the outside of the magnetic slurry is wrapped with wire mesh, the outside of the wire mesh is connected to the first adhesive layer, and the first adhesive layer contains a plurality of first ceramic balls.
[0006] The water glass ball is filled with water glass, the outer side of the water glass is wrapped with a second adhesive layer, and the second adhesive layer contains a plurality of second ceramic balls.
[0007] The chamber is made of a metal hose.
[0008] The material of the first adhesive layer inside the slurry ball is polyacrylate.
[0009] The exterior of the first ceramic ball inside the slurry ball is a high-temperature fired ceramic material, and the internal holes of the first ceramic ball contain active glue.
[0010] The wire mesh inside the cladding liquid ball is a non-closed semi-ring wire mesh.
[0011] The pressurized gas pipe is filled with high-pressure inert gas, preferably helium.
[0012] Preferably, the second adhesive layer is polyacrylate.
[0013] Preferably, the second ceramic ball is the same as the first ceramic ball.
[0014] Preferably, a feeding valve is provided in the feeding pipe.
[0015] The method for using the device for reducing the opening of rock mass fissures based on multiple high-pressure ejection grouting comprises the following steps: S1. Assemble the grouting device, prepare the grouting liquid ball, the water glass ball, the magnetic block, and the isolation net; S2. Place an isolation net at the crack exit. After cleaning the crack, place magnetic blocks inside the crack at intervals of a certain width. S3, open the feeding valve, load the grouting liquid ball into the precise high-pressure grouting device, and close the feeding valve; adjust the injection angle of the grouting device, inject the grouting liquid ball into the deep of the crack, and clean the device after the injection; the magnetic slurry is distributed on the surface of the crack; S4, open the feeding valve, install the water glass ball into the precise high-pressure grouting device, close the feeding valve; inject the water glass ball into the crack; distribute the water glass on the surface of the slurry to accelerate the solidification of the slurry; clean the device after injection; S5. Repeat steps S3 and S4 until the crack is reduced to an appropriate opening, remove the safety isolation net, and clean the grouting device.
[0016] The composition and mass content of the magnetic slurry in step S3 are respectively 20% to 50% of magnetic powder, 2% to 5% of anti-dispersant, 1% to 4% of water reducer, 1.5% to 5% of epoxy resin, 5% to 8% of flocculant, and the remainder is concrete; wherein, in terms of mass ratio, in concrete, water: ash = 0.35 to 0.5:1.
[0017] Preferably, the magnetic powder is ferroferric oxide, and the particle size of the magnetic powder is 6 to 10 microns.
[0018] Preferably, the anti-dispersant is a modified polyurethane polymer.
[0019] Preferably, the water reducer is a polycarboxylate water reducer.
[0020] Preferably, the flocculant is polyaluminium chloride.
[0021] Preferably, in step S2, magnetic blocks are placed inside the crack every 1m to 2m in length and 0.5m to 1m in width.
[0022] Preferably, the distribution time of the magnetic slurry in step S3 is 1-3 minutes.
[0023] Preferably, in step S3, the injection angle is set according to the angle of the crack.
[0024] Preferably, the water glass distribution time in step S4 is 3-5 minutes.
[0025] Preferably, in step S5, the crack opening is reduced to 0.5 cm-1 cm.
[0026] Compared with the prior art, the present invention has the following beneficial effects: 1. The present invention evenly distributes magnetic blocks on the crack surface from top to bottom, and when the magnetic slurry is released from the slurry ball, the movement of the magnetic slurry can be guided, thereby increasing the slurry coverage area.
[0027] 2. The present invention arranges the adhesive layer in the slurry ball as the outermost layer. When the slurry ball is injected from the precise high-pressure grouting device, it can adhere to the crack surface, thereby reducing its shedding rate.
[0028] 3. The present invention mixes ceramic balls into the adhesive layer, and the ceramic on the outer wall of the ceramic ball is used as an isolation layer between the adhesive layer and the activator. When injected through a precise high-pressure grouting device, the ceramic will be destroyed under the impact force, releasing the activator to digest the adhesive layer.
[0029] 4. The present invention places a wire mesh in the slurry ball. Since the wire mesh is placed in a curled shape inside, when the adhesive layer is decomposed by the activator to form a gap, the wire mesh accelerates the release of the magnetic slurry through elastic tension; the wire mesh can also be integrated with the slurry to enhance the overall strength after repair.
[0030] 5. The present invention injects the water glass ball after the slurry ball, first allowing the slurry to be evenly distributed on the surface of the crack, and then mixing the water glass with the slurry to better evenly reduce the crack opening, and solidify the slurry faster, thereby improving construction efficiency.
[0031] 6. The injection time of the sticky water glass ball and the sticky cladding liquid ball of the present invention cannot differ too much, in order to prevent the cladding liquid ball from releasing the slurry, which will make the subsequently injected water glass ball unable to adhere to the crack surface, causing it to fall off and delay the process.
[0032] 7. The present invention reduces potential safety hazards by placing a safety isolation net at the crack exit to prevent debris, detached cladding balls or water glass balls from falling off and causing danger.
[0033] The present invention increases the thickness of the solidified slurry to the maximum extent by injecting viscous slurry balls into the cracks multiple times, thereby reducing the crack opening, thereby reaching a suitable crack opening for subsequent work. BRIEF DESCRIPTION OF THE DRAWINGS
[0034] Figure 1 It is a schematic diagram of the slurry ball; Figure 2 It is a schematic diagram of a precise high-pressure grouting device; Figure 3 Schematic diagram of the injection of a sticky slurry ball into a crack; Figure 4 This is a schematic diagram of the sticky grouting liquid ball acting on the crack; Figure 5 Schematic diagram of the sticky water glass ball acting on the crack; Figure 6 is a schematic diagram of a water glass ball; Figure numerals: grouting device 1, gun cover 101, gun head 102, feeding tube 103, tapered mouth 104, pressurized air pipe 105, spring 106, chamber 107, steel pipe 108, grouting liquid ball 2, magnetic slurry 3, first adhesive layer 4, first ceramic ball 5, wire mesh 6, water glass ball 7, second adhesive layer 701, second ceramic ball 702; water glass 8, magnetic block 9, isolation net 10, solidified slurry 11. DETAILED DESCRIPTION
[0035] The solidified slurry 11 is a concrete solid that is quickly combined with the magnetic slurry 3 and the water glass 8. The ash of the concrete was purchased from Juyan Technology Factory, model HK-730. The modified polyurethane polymer was purchased from Guangzhou Dashengshi Building Materials Co., Ltd., model D-KFS. In the following embodiments, unless otherwise specified, the water glass 8 is an aqueous solution of sodium silicate; the mass fraction of sodium silicate in the aqueous solution of sodium silicate is preferably 45% to 50%.
[0036] Example 1 Please refer to 1~ Figure 6 , a device for reducing the opening of rock mass fissures based on multiple high-pressure ejection grouting, comprising a grouting device 1, a grouting liquid ball 2, a water glass ball 7, a magnetic block 9, a safety isolation net 10, and a solidified grout 11; The sticky coating liquid ball 2 includes: magnetic slurry 3, a first adhesive layer 4, a first ceramic ball 5, and a wire mesh 6; The sticky water glass ball 7 comprises: a second adhesive layer 701, a second ceramic ball 702; water glass 8, The grouting liquid ball 2 is injected into the top of the large-opening fissure by using the precise high-pressure grouting device 1, and the fissure opening can be reduced later; The first adhesive layer 4 of the outermost layer of the slurry ball 2 can be bonded to the surface of the crack to play a fixing role and be used to spread the slurry at a fixed point; When the precise high-pressure grouting device 1 injects the grouting liquid ball 2 or the water glass ball 7 into the crack, it will cause a collision and destroy the outer ceramics of the first ceramic ball 5 and the second ceramic ball 702, thereby releasing the activator inside; The cladding liquid ball 2 contains a first ceramic ball 5, which can play a stratification role when it is not damaged. When it is damaged and releases an activator, it can digest the first adhesive layer 4 and release the internal magnetic slurry 3, so that the magnetic slurry 3 can be regularly diffused along the lower surface of the crack; The slurry ball 2 contains a wire mesh 6, which can be spread along the crack surface after the first adhesive layer 4 disappears, so as to enhance the overall strength after repair; After the slurry ball 2 is injected, the water glass ball 7 is injected, so that the magnetic slurry 3 can be laid on the crack surface, and then the water glass 8 can contact the magnetic slurry 3, which can accelerate the solidification of the magnetic slurry 3 and improve the construction efficiency; By laying the magnetic block 9 on the crack surface, it can be used to guide the magnetic slurry 3 and expand the diffusion range of the magnetic slurry 3; The safety isolation net 10 is placed at the beginning of the crack outlet, which can be used to receive the stones and slurry spilled from the crack to reduce safety hazards; A device and a method for reducing the opening of rock mass fissures based on multiple high-pressure ejection grouting, comprising the following steps: Step 1: Materials and equipment: Prepare materials and equipment for high-pressure ejection grouting to reduce the opening of rock mass fissures, including precise high-pressure grouting equipment, grouting balls, water glass balls, magnetic blocks, safety isolation nets, and solidified grout; The slurry ball 2 includes: magnetic slurry 3, a first adhesive layer 4, a first ceramic ball 5, and a wire mesh 6; The water glass ball 7 includes: a second adhesive layer 701, a second ceramic ball 702; and water glass 8; Step 2: Place the safety isolation net 10 at the exit of the large-opening fissure, clean the rocks and dust inside the fissure into the safety isolation net 10, and then clean the safety isolation net 10; Step 3: Use a micro camera to observe the internal situation of the large-opening crack, use an instrument to simulate and analyze it, place magnetic blocks 9 at intervals of length and width, and adjust the injection angle of the precise high-pressure grouting device 1; Step 4: Install the grouting liquid ball 7 into the precise high-pressure grouting device 1, and perform a one-time injection to inject the grouting liquid ball into the deep of the crack. After the injection is completed, clean the grouting device 1 to prepare for the next injection; Step 5: Inject the coating liquid ball 7 evenly to the top of the crack. There is an activator inside the first adhesive layer 4. When the first adhesive layer 4 contacts the crack surface through high-pressure injection, the strong impact force will destroy the ceramic, thereby releasing the internal activator to digest the first adhesive layer 4 and release the internal magnetic slurry 3. Step 6: After waiting for 1-3 minutes, the magnetic slurry 3 released by the slurry ball 2 will be attracted by the magnetic block 9 and will be more evenly distributed on the crack surface. Then, the water glass ball 7 is installed into the grouting device 1, and then injected to inject the water glass ball 7 into the upper surface of the crack; Step 7: When the water glass 8 is evenly distributed on the surface of the magnetic slurry 3, the water glass 8 will accelerate the solidification of the magnetic slurry 3. After waiting for 3-5 minutes for the magnetic slurry 3 to completely solidify, the injection is repeated several times until the crack opening is reduced to a suitable opening; Step 8: When the crack opening is reduced to a suitable level, remove the safety isolation net 10 and clean the remaining devices.
[0037] Among them, magnetic slurry 3: concrete water-cement ratio 0.35-0.5, magnetic powder content 20%-50%, anti-dispersant 2%-5%, water reducer 1%-4%, epoxy resin 1.5%-5%, flocculant 5%-8%.
[0038] The first adhesive layer 4 and the second adhesive layer 701 are made of polyacrylate. The first ceramic ball 5 and the second ceramic ball 702 are made of high-temperature fired ceramic material on the outside, with holes inside, and the holes contain active glue. Preferably, the mass fraction of high-temperature fired ceramic material in the first ceramic ball 5 and the second ceramic ball 702 is 50%, and the mass fraction of active glue is 50%.
[0039] Example 2 Please refer to 1~ Figure 6This embodiment further illustrates the specific connection method and use method of the device, a device for reducing the opening of rock fractures based on multiple high-pressure ejection grouting, including a grouting device 1, a gun head 102 of the grouting device 1 slidingly engages with a gun cover 101, one side of the gun head 102 is connected to a chamber 107, the upper end of the chamber 107 is connected to a feeding pipe 103, the top of the feeding pipe 103 is provided with a conical mouth 104, the bottom of the chamber 107 is connected to a pressurized air pipe 105, a plurality of springs 106 are installed at the connection between the outer wall of the chamber 107 and the inner wall of the steel pipe 108, and a plurality of grouting liquid balls 2 and a plurality of water glass balls 7 are respectively and sequentially installed in the chamber 107 of the grouting device 1.
[0040] The cladding liquid ball 2 contains magnetic slurry 3 , the outside of the magnetic slurry 3 is wrapped with a wire mesh 6 , the outside of the wire mesh 6 is connected to a first adhesive layer 4 , and the inside of the first adhesive layer 4 contains a plurality of first ceramic balls 5 .
[0041] The water glass ball 7 contains water glass 8 , the outer side of the water glass 8 is connected to the second adhesive layer 701 , and the second adhesive layer 701 contains a plurality of second ceramic balls 702 .
[0042] The chamber 107 is a metal hose made of 304. The first adhesive layer 4 and the second adhesive layer 701 are both made of polyacrylate.
[0043] The first ceramic ball 5 is made of high temperature fired ceramic material on the outside, and the internal holes of the first ceramic ball 5 contain active glue. The second ceramic ball 702 is made of high temperature fired ceramic material on the outside, and the internal holes of the second ceramic ball 702 contain active glue.
[0044] The wire mesh 6 is a non-closed semi-ring wire mesh. The pressurized air pipe 105 is filled with high-pressure inert gas. Preferably, the inert gas is helium. Preferably, the active glue material is ethylene dichloride. Preferably, a feeding valve is provided in the feeding pipe.
[0045] A method for using a device for reducing the opening of rock mass fissures based on multiple high-pressure ejection grouting, comprising the following steps: S1. Assemble the grouting device, prepare the grouting liquid ball, the water glass ball, the magnetic block, and the isolation net; S2. Place an isolation net at the crack exit. After cleaning the crack, place magnetic blocks inside the crack at intervals of length and width. S3, open the feeding valve, load the grouting liquid ball into the precise high-pressure grouting device, and close the feeding valve; adjust the injection angle of the grouting device, inject the grouting liquid ball into the deep of the crack, and clean the device after the injection; the magnetic slurry is distributed on the surface of the crack; S4, open the feeding valve, install the water glass ball into the precise high-pressure grouting device, close the feeding valve; inject the water glass ball into the crack; distribute the water glass on the surface of the slurry to accelerate the solidification of the slurry; clean the device after injection; S5. Repeat steps S3 and S4 until the crack is reduced to an appropriate opening, remove the safety isolation net, and clean the grouting device.
[0046] The composition and mass content of the magnetic slurry 3 in step S3 are 20% to 50% magnetic powder, 2% to 5% anti-dispersant, 1% to 4% water reducer, 1.5% to 5% epoxy resin, 5% to 8% flocculant, and the remainder is concrete; wherein, in terms of mass ratio, the water: ash in the concrete is 0.35 to 0.5: 1. Preferably, the magnetic powder is ferroferric oxide, and the particle size of the magnetic powder is 6 to 10 microns. Preferably, the anti-dispersant is a modified polyurethane polymer. Preferably, the water reducer is a polycarboxylate water reducer. Preferably, the flocculant is polyaluminum chloride.
[0047] Preferably, in step S2, magnetic blocks are placed inside the crack every 1m to 2m in length and 0.5m to 1m in width.
[0048] Preferably, the distribution time of the magnetic slurry in step S3 is 1-3 minutes.
[0049] Preferably, in step S3, the inert gas pressure inside the high-pressure grouting device is 1-2 MPa.
[0050] Preferably, in step S3, the injection angle is set according to the angle of the crack.
[0051] Preferably, the water glass distribution time in step S4 is 3-5 minutes.
[0052] Preferably, in step S5, the crack opening is reduced to 0.5 cm-1 cm.
[0053] The present invention fills the slurry balls and water glass balls in the cracks through the grouting device. With the assistance of the magnetic block, the problem that the slurry cannot be evenly filled in the cracks is solved, the problem of the structural strength of the filling material after filling is solved, and the problem of slow solidification of the slurry is solved. In addition, the above is only a preferred embodiment of the present invention and is not used to limit the present invention. Although the present invention is described in detail with reference to the aforementioned embodiments, for those skilled in the art, it is still possible to modify the technical solutions recorded in the aforementioned embodiments, such as changing the pressure of the pressurized air pipe 105, changing the formula of the magnetic slurry 3, or making equivalent substitutions for other parts of the technical features. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the protection scope of the present invention.
Claims
1. A device for reducing the opening of rock mass fissures based on multiple high-pressure ejection grouting, comprising a grouting device (1), characterized in that: The gun head (102) of the grouting device (1) is slidably engaged with the gun cover (101), one side of the gun head (102) is connected to the chamber (107), the upper end of the chamber (107) is connected to the feeding pipe (103), the top of the feeding pipe (103) is provided with a conical opening (104), the bottom of the chamber (107) is connected to the pressurized air pipe (105), a plurality of springs (106) are provided at the connection between the outer wall of the chamber (107) and the inner wall of the steel pipe (108), and a plurality of grouting liquid balls (2) and a plurality of water glass balls (7) are respectively provided in the chamber (107) of the grouting device (1).
2. The device for reducing the opening of rock mass fissures based on multiple high-pressure ejection grouting according to claim 1 is characterized in that: The cladding liquid ball (2) contains magnetic slurry (3), the outside of the magnetic slurry (3) is wrapped with a wire mesh (6), the outside of the wire mesh (6) is connected to a first adhesive layer (4), and the first adhesive layer (4) contains a plurality of first ceramic balls (5).
3. The device for reducing the opening of rock mass fissures based on multiple high-pressure ejection grouting according to claim 1 is characterized in that: The water glass ball (7) contains water glass (8), the outside of the water glass (8) is wrapped with a second adhesive layer (701), and the second adhesive layer (701) contains a plurality of second ceramic balls (702).
4. The device for reducing the opening of rock mass fissures based on multiple high-pressure ejection grouting according to claim 1 is characterized in that: The chamber (107) is a metal hose made of 304 material.
5. The device for reducing the opening of rock mass fissures based on multiple high-pressure ejection grouting according to claim 1 is characterized in that: The material of the first adhesive layer (4) inside the slurry ball (2) is polyacrylate.
6. The device for reducing the opening of rock mass fissures based on multiple high-pressure ejection grouting according to claim 1 is characterized in that: The first ceramic ball (5) inside the slurry ball (2) has an exterior made of high-temperature fired ceramic material, and the internal pores of the first ceramic ball (5) contain active glue.
7. The device for reducing the opening of rock mass fissures based on multiple high-pressure ejection grouting according to claim 1 is characterized in that: The wire mesh (6) inside the cladding liquid ball (2) is a non-closed semi-ring wire mesh.
8. The device for reducing the opening of rock mass fissures based on multiple high-pressure ejection grouting according to claim 1 is characterized in that: The pressurized gas pipe (105) is filled with high-pressure inert gas.
9. A method for using a device for reducing the opening of rock mass fissures based on multiple high-pressure ejection grouting as claimed in any one of claims 1 to 8, characterized in that: The following steps are involved: S1. Assemble the grouting device, prepare the grouting liquid ball, the water glass ball, the magnetic block, and the isolation net; S2. Place an isolation net at the crack exit. After cleaning the crack, place magnetic blocks inside the crack at intervals of length and width. S3, open the feeding valve, load the grouting liquid ball into the precise high-pressure grouting device, and close the feeding valve; adjust the injection angle of the grouting device, inject the grouting liquid ball into the deep of the crack, and clean the device after the injection; the magnetic slurry is distributed on the surface of the crack; S4, open the feeding valve, install the water glass ball into the precise high-pressure grouting device, close the feeding valve; inject the water glass ball into the crack; distribute the water glass on the surface of the slurry to accelerate the solidification of the slurry; clean the device after injection; S5. Repeat steps S3 and S4 until the crack is reduced to an appropriate opening, remove the safety isolation net, and clean the grouting device.
10. The method for using the device for reducing the opening of rock mass fissures based on multiple high-pressure ejection grouting according to claim 9, characterized in that: The composition and mass content of the magnetic slurry in step S3 are respectively 20% to 50% of magnetic powder, 2% to 5% of anti-dispersant, 1% to 4% of water reducer, 1.5% to 5% of epoxy resin, 5% to 8% of flocculant, and the remainder is concrete; wherein, in terms of mass ratio, in concrete, water: ash = 0.35 to 0.5:1.