Waterproof structure suitable for tunnel groove construction joint and construction method thereof

By setting up two-stage waterproof structures of components such as cement-based permeable crystalline waterproof coating layer and X-shaped water stop belt at the tunnel trench construction joints, the problem of insufficient waterproof performance at the tunnel trench construction joints is solved, and effective water liquid is achieved Long-term reliability and safety of blocking and tunnel trench.

CN118933916APending Publication Date: 2024-11-12WUHAN TIESIYUAN ENG CONSULTING CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411118817.9
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-15
Publication Date
2024-11-12

AI Technical Summary

Technical Problem

The waterproof structure at the tunnel trench construction joints have problems such as structural continuous damage and insufficient waterproof performance, which leads to water leakage and affects the safety and service life of the tunnel.

Method used

Using a two-stage waterproof structure, including setting up a cement-based permeable crystal waterproof coating layer at the construction joints as a first-stage waterproof structure, and forming a second-stage waterproof structure through components such as X-shaped water stops and water filter belts to block water leakage , and ensure the reliability of the waterproof structure through specific construction methods.

Benefits of technology

Effectively block the leakage of water on the water side of the tunnel trench to the backwater side, extend the service life of the tunnel trench, reduce operation and maintenance costs, and improve the reliability and waterproofing performance of tunnel operations.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118933916A_ABST
    Figure CN118933916A_ABST
Patent Text Reader

Abstract

The invention discloses a waterproof structure suitable for a tunnel groove construction joint and a construction method of the waterproof structure, and belongs to the technical field of tunnel construction.The waterproof structure is characterized in that a first-stage waterproof structure composed of a waterproof coating layer is arranged corresponding to the construction joint between a pre-poured groove and a post-poured groove of a tunnel groove; and the X-shaped waterstop arranged between the new concrete and the old concrete is used as a second-stage waterproof structure, and the two-stage waterproof structure is arranged between the upstream face and the downstream face, so that water on the upstream side of the tunnel groove is effectively prevented from leaking to the downstream side of the tunnel groove. According to the waterproof structure suitable for the tunnel groove construction joints, the structure is simple, construction is convenient and fast, arrangement of waterproof structures at the positions of the two adjacent groove construction joints can be achieved while tunnel groove segmented construction is met, the waterproof stability and reliability of the positions of the two adjacent groove construction joints are guaranteed, and the waterproof effect is good. And water on the upstream side is fully prevented from leaking to the downstream side through the construction joint, the operation reliability after tunnel groove construction is ensured, and the operation and maintenance cost of a tunnel is reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of tunnel construction, and in particular relates to a waterproof structure suitable for tunnel trench construction joints and a construction method thereof. Background Art

[0002] As the last auxiliary project to be constructed during the tunnel construction process, the appearance quality and structural reliability of the tunnel trench cable trough directly affect the overall image of the tunnel, the safety of the communication power cables, and the smoothness of the structural drainage. Limited by the existing construction conditions, the tunnel trench part often cannot be constructed in one go, and can usually only be constructed by segmented pouring, thus forming several trench construction joints in the longitudinal direction of the tunnel.

[0003] For the trench construction joints in the tunnel, their structural appearance is limited by the construction quality, and the width of the construction joints is also different; moreover, it is precisely because of the existence of the construction joints that the longitudinal continuity of the tunnel trench structure is destroyed, and the construction joints often become the weak link of the waterproof structure. Therefore, in actual construction, it is necessary to set up a waterproof structure at the construction joint to ensure the reliability of the tunnel trench structure and extend the service life of the structure.

[0004] For waterproof structures at construction joints, the practice in related technologies is mostly to install rubber waterstop strips that swell when exposed to water. However, due to the difficulty of constructing buried waterstop strips, water-swelling rubber waterstop strips are usually constructed by nailing the waterstop strips directly to the construction joints with a nail gun. Although this method can achieve the installation of waterstop strips to a certain extent. However, since the cable trough itself is a thin-walled structure, once the position of the waterstop strip is improperly controlled, it is very easy to be too close to the edge of the groove, causing the cable trough to swell and crack, which in turn causes the side wall of the ditch to crack and seep water, resulting in the failure of the waterproof structure of the groove construction joint, causing a series of subsequent problems. Summary of the invention

[0005] In response to one or more of the above defects or improvement needs in the prior art, the present invention provides a waterproof structure suitable for tunnel trench construction joints and a construction method thereof, which can effectively meet the waterproofing requirements at tunnel trench construction joints, enhance the structural waterproofing performance at the construction joints, and extend the service life of the waterproof structure.

[0006] To achieve the above object, one aspect of the present invention provides a waterproof structure suitable for tunnel trench construction joints, which is used for waterproofing between the front surface and the back surface of the construction joint between the first cast trench and the second cast trench during the segmented construction of the tunnel trench, and comprises: A primary waterproof structure, which is a waterproof coating layer applied on the water-facing surface of the construction joint; A secondary waterproof structure is provided in the concrete structure between the water-facing surface and the water-retaining surface, and is formed by an X-shaped waterstop extending into the first-cast groove on one side and into the second-cast groove on the other side; and The X-shaped waterstop is arranged along the annular direction to surround the construction joint on the water-facing surface, and includes a strip-shaped middle rib, and a pair of wing bands are respectively arranged on both sides of the width direction of the middle rib; the wing band extends within the full length of the middle rib, and one side of the wing band is fixedly connected to one side of the width direction of the middle rib; the two wing bands in each pair of wing bands are arranged at a certain angle to each other, and one of the wing bands is buried in the end concrete of the pre-cast groove during the construction of the pre-cast groove, and the other wing band is buried in the end concrete of the post-cast groove during the construction of the post-cast groove.

[0007] As a further improvement of the present invention, the waterproof coating layer completely covers the construction joint on the water-facing surface, and is obtained by brushing with a cement-based penetrating crystallization waterproof coating; The cement-based penetrating crystallization waterproof coating is prepared by mixing an inorganic base material, an active compound, and a functional additive in a mass ratio of (70-105):(0.1-1):(0.5-2), and the cement-based penetrating crystallization waterproof coating is mixed with water in a ratio of 0.25:1-0.35:1 when in use.

[0008] As a further improvement of the present invention, the width of the waterproof coating layer is not less than 20 cm; and / or the thickness of the waterproof coating layer is between 1 and 2 mm; and / or The angle between the two wing straps in each pair of wing straps is 90°~150°; correspondingly, the angle between the surface of each wing strap and the end surface of the middle rib is 105°~135°.

[0009] As a further improvement of the present invention, a convex strip is protrudingly provided on at least one side end surface of the wing band, and the convex strip is continuously extended in the length direction of the wing band and extends from one end of the wing band to the other end.

[0010] As a further improvement of the present invention, the convex strip is arranged on a side end surface of the corresponding wing band away from the middle rib, and the number of the convex strips arranged on the side end surface is multiple.

[0011] As a further improvement of the present invention, a water filter belt is provided along the length direction between the two wing belts close to the water-facing surface; The water filter belt extends along the length direction of the wing belt, and its two sides in the width direction are respectively connected to the end faces of the two wing belts away from the middle rib, and a gap is formed between the end face of the water filter belt and one side of the width direction of the middle rib, so that water leaked through the construction joint on the water-facing side can be collected in the gap after passing through the filter water belt; accordingly, a water absorption strip is arranged in the gap, and the end of the water absorption strip extends from the end of the X-shaped waterstop belt, which is used to absorb the water in the gap.

[0012] As a further improvement of the present invention, the X-shaped waterstop is arranged in the middle part of the tunnel trench concrete, one end of which extends to the bottom of the cable trough on one lateral side of the tunnel trench, and the other end of which bypasses the bottom of the ditch in the middle of the tunnel trench and extends to the bottom of the cable trough on the other lateral side.

[0013] As a further improvement of the present invention, a waterproof coating layer is applied on the inner peripheral wall surface of the cable trough corresponding to the construction joints of the first-cast groove and the post-cast groove.

[0014] Another aspect of the present invention provides a construction method of a waterproof structure suitable for a tunnel trench construction joint, which comprises the following process: S1. Design the X-shaped waterstop according to the design size of the tunnel trench, determine its use length, setting position and turning position, and bend the X-shaped waterstop at the turning position for standby use; S2: Tie the steel mesh of the first-cast groove and set the casting template, and set the bent X-shaped water stop strip in the first-cast groove for connecting one end of the post-cast groove, so that the two wing strips on one side of the thickness direction of the X-shaped water stop strip are located in the area to be cast in the first-cast groove; S3, pouring the pre-cast groove to complete the shaping of the pre-cast groove, so that the two wing strips on one side of the X-shaped water stop are buried inside the end of the pre-cast groove, and the two wing strips on the other side of the X-shaped water stop protrude from the pre-cast groove to connect to the end surface of the post-cast groove; S4: Tie the steel mesh of the post-cast groove at one longitudinal end of the formed pre-cast groove and set a casting template so that the two wing strips protruding from the end surface of the pre-cast groove extend into the area to be cast of the post-cast groove; if the post-cast groove is not the last section of the tunnel groove, set an X-shaped water stop strip at the end of the post-cast groove away from the pre-cast groove according to the method in step S2; thereafter, cast and form the post-cast groove; S5: According to the method in step S4, the construction and forming of all sections of the tunnel groove are completed in sequence, and a waterproof coating layer of a certain width and thickness is applied on the water-facing surface of the construction joint between each first-cast groove and the later-cast groove to form a primary waterproof structure between the water-facing surface and the water-receiving surface at the construction joint; accordingly, the X-shaped waterstop strip arranged between the first-cast groove and the later-cast groove forms a secondary waterproof structure between the water-facing surface and the water-receiving surface at the construction joint.

[0015] As a further improvement of the present invention, when the X-shaped water stop is provided in step S2, the two wing strips for extending into the post-cast groove are flattened to be flush with the end surface of the middle rib, and the X-shaped water stop is tightly fixed to the end formwork of the pre-cast groove by using a plurality of fixing members; Correspondingly, after the first-cast groove is formed in step S3, the end template is removed, and the two wing strips for embedding the end of the post-cast groove are cut out from the end surface of the first-cast groove so that the two wing strips protrude from the end surface of the first-cast groove.

[0016] The above-mentioned improved technical features can be combined with each other as long as they do not conflict with each other.

[0017] In general, compared with the prior art, the above technical solution conceived by the present invention has the following beneficial effects: (1) The waterproof structure suitable for the construction joint of the tunnel groove in the present invention is provided with a primary waterproof structure composed of a waterproof coating layer at the construction joint between the first cast groove and the second cast groove of the tunnel groove, and an X-shaped water stop strip provided between new and old concrete as a secondary waterproof structure. By providing the two-level waterproof structure between the water-facing surface and the water-receiving surface, the leakage of water from the water-facing side of the tunnel groove to the water-receiving side is effectively blocked, the reliability of the setting and application of the tunnel groove is fully guaranteed, the service life of the tunnel groove is extended, the operation and maintenance cost of the tunnel groove is reduced, and the reliability of the tunnel operation is improved.

[0018] (2) The waterproof structure suitable for tunnel trench construction joints in the present invention effectively ensures the reliability and accuracy of the waterproof coating layer as a primary waterproof structure after it is set by optimizing the material composition and construction parameters of the waterproof coating layer, using the formula design of the cement-based penetrating crystallization waterproof coating and the coating process design of the waterproof coating layer. At the same time, by coating the construction joint of the corresponding cable trough with a waterproof coating layer, the reliability of the cable trough can be further ensured, and the possibility of water leakage on the backwater side can be reduced. (3) The waterproof structure suitable for tunnel trench construction joints in the present invention can effectively ensure the waterproof barrier at the construction joints of the first-cast trench and the second-cast trench by optimizing the setting position and shape parameters of the X-shaped waterstop and coordinating the corresponding setting of the convex strips on the outer periphery of the wing strip, thereby ensuring the reliability of the waterproof design between the new and old concretes, and further improving the waterproof performance of the tunnel trench. At the same time, by setting the filter strips between the corresponding wing strips, a filter gap can be formed between the X-shaped waterstop and the concrete structure. By coordinating the setting of the water absorption strips in the gap, the leakage water in the gap can be quickly discharged, reducing the leakage of the leakage water at the interface between the waterstop and the concrete, and further improving the waterproof effect of the waterproof structure.

[0019] (4) The construction method of the waterproof structure for the tunnel trench construction joint of the present invention is simple in steps and convenient in operation. It can accurately complete the construction of each section of the tunnel trench in sequence, and form a primary waterproof structure and a secondary waterproof structure between the water-facing surface and the water-receiving surface of two adjacent trench sections after the construction of each section, so as to improve the waterproof performance of the construction joint between the two adjacent trench sections during the segmented construction of the tunnel trench, avoid leakage of water from the water-facing side to the water-receiving side, ensure the reliability of the tunnel trench setting and operation, and extend the service life of the tunnel trench.

[0020] (5) The waterproof structure suitable for tunnel trench construction joints in the present invention has a simple structure and is easy to construct. It can realize the setting of waterproof structures at the construction joints of two adjacent trench sections while meeting the requirements of segmented construction of the tunnel trench, thereby ensuring the stability and reliability of waterproofing at the construction joints of the adjacent trenches at both ends, and fully preventing water from leaking from the water-facing side through the construction joints to the water-receiving side, thereby ensuring the reliability of operation after tunnel trench construction and reducing the operation and maintenance costs of the tunnel. BRIEF DESCRIPTION OF THE DRAWINGS

[0021] In order to more clearly illustrate the technical solutions in the embodiments of the present invention, the drawings required for use in the embodiments will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For those skilled in the art, other drawings can be obtained based on these drawings without creative work.

[0022] Figure 1 It is a cross-sectional view of a waterproof structure applicable to a tunnel trench construction joint at a construction joint in an embodiment of the present invention; Figure 2 is a partial top view of the waterproof structure at the construction joint in an embodiment of the present invention; Figure 3 is a structural cross-sectional view of the secondary waterproof structure of the waterproof structure in an embodiment of the present invention; Figure 4 It is a schematic diagram of the secondary waterproof structure setting form of the tunnel trench in the embodiment of the present invention when the post-cast trench is not constructed; In all the drawings, the same reference numerals represent the same technical features, specifically: 1. Tunnel trench; 2. Primary waterproof structure; 3. Secondary waterproof structure; 4. End formwork; 5. Fixing parts; 101. First pouring groove; 102. Second pouring groove; 103. Construction joint; 104. Ditch; 105. Cable trough; 106. Cover plate; 107. Water-facing surface; 108. Water-receiving surface; 301, center rib; 302, wing band; 303, convex strip; 304, water filter belt. DETAILED DESCRIPTION

[0023] In order to make the purpose, technical solutions and advantages of the present invention more clearly understood, the present invention is further described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are only used to explain the present invention and are not intended to limit the present invention. In addition, the technical features involved in the various embodiments of the present invention described below can be combined with each other as long as they do not conflict with each other.

[0024] In the description of the present invention, it should be understood that, unless otherwise expressly specified and limited, the terms "center", "longitudinal", "lateral", "length", "width", "thickness", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside", "clockwise", "counterclockwise", "axial", "radial", "circumferential" and the like to indicate orientations or positional relationships are based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the referred device or element must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as limiting the present invention.

[0025] In addition, the terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features. Therefore, the features defined as "first" and "second" may explicitly or implicitly include at least one of the features. In the description of the present invention, the meaning of "plurality" is at least two, such as two, three, etc., unless otherwise clearly and specifically defined.

[0026] In the present invention, unless otherwise clearly specified and limited, the terms "installed", "connected", "connected", "fixed" and the like should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium, it can be the internal connection of two elements or the interaction relationship between two elements, unless otherwise clearly defined. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0027] In the present invention, unless otherwise clearly specified and limited, a first feature being "above" or "below" a second feature may mean that the first and second features are in direct contact, or the first and second features are in indirect contact through an intermediate medium. Moreover, a first feature being "above", "above" or "above" a second feature may mean that the first feature is directly above or obliquely above the second feature, or simply means that the first feature is higher in level than the second feature. A first feature being "below", "below" or "below" a second feature may mean that the first feature is directly below or obliquely below the second feature, or simply means that the first feature is lower in level than the second feature.

[0028] Example: For the waterproof structure in the preferred embodiment of the present invention, it corresponds to the construction joint setting between the first poured section and the later poured section of the trench structure in the tunnel, aiming to improve the waterproof ability of the trench structure at the construction joint position, and avoid the water on the water-facing side from leaking through the construction joint to the water-receiving side of the structure, thereby ensuring the reliability of the setting of the corresponding facilities in the trench structure.

[0029] When actually constructing the tunnel trench 1, it is preferably constructed in sections in the longitudinal direction of the tunnel, that is, the construction of the entire tunnel trench 1 involves at least one docking construction of the first cast trench 101 and the later cast trench 102. In other words, at least one construction joint 103 is formed in the longitudinal direction of the tunnel trench 1.

[0030] See also Figure 1 , which is a schematic cross-sectional view of the tunnel trench 1 at a construction joint 103, according to Figure 1 It can be seen from the records that a ditch 104 of a certain depth is formed in the middle of the top surface of the tunnel groove 1. The ditch 104 extends continuously in the longitudinal direction of the tunnel and is used to collect and discharge accumulated water in the tunnel.

[0031] At the same time, cable grooves 105 of a certain depth are respectively arranged on both sides of the ditch 104 in the horizontal direction. The depth of the cable grooves 105 is preferably less than the depth of the ditch 104, and the cable grooves 105 are also arranged to extend longitudinally along the tunnel for corresponding arrangement of relevant cables in the tunnel. Accordingly, a cover plate 106 is arranged on the top of the ditch 104 and the cable groove 105 to ensure the levelness of the top of the tunnel ditch 1.

[0032] It is also due to the above-mentioned structure that the cable trough 105 itself becomes a thin-walled structure, which causes the setting of the conventional water-stop structure to damage the trough wall of the cable trough 105. Accordingly, the technical solution in the preferred embodiment of the present invention is proposed to overcome the defects of the conventional waterproof structure and to improve the waterproof performance of the construction joint after the tunnel trench is set in multiple sections.

[0033] In a preferred embodiment of the present invention, the waterproof structure is arranged as follows: Figure 1 , Figure 2 As shown in , it is correspondingly arranged at the construction joint 103 between the first pouring groove 101 and the second pouring groove 102.

[0034] Specifically, in the preferred embodiment, the waterproof structure corresponding to the new and old concrete construction joints 103 includes a primary waterproof structure 2 and a secondary waterproof structure 3. The two-stage waterproof structure is intended to block the water infiltration path between the water-facing surface 107 and the water-retaining surface 108 at the construction joint 103.

[0035] The primary waterproof structure 2 is arranged on the water-facing surface 107 side of the construction joint 103, that is, on the inner wall side of the ditch 104. Figure 1 In the preferred embodiment shown, the primary waterproof structure 2 is arranged on the inner wall surfaces and the bottom surface of both sides of the ditch 104 .

[0036] In a preferred embodiment, the primary waterproof structure 2 is a waterproof coating layer attached to one side of the water-facing surface 107 of the construction joint 103 (i.e., the inner peripheral wall surface of the ditch 104, i.e., the wall surfaces and bottom surfaces on both sides thereof), and the length direction of the waterproof coating layer extends along the inner peripheral circumferential direction of the ditch 104, i.e., from the inner wall surface outlet on one side in the width direction, closely attached to the inner wall surface, to the inner wall surface outlet on the other side in the width direction. At the same time, the width direction of the waterproof coating layer is the longitudinal direction of the ditch 104, and the waterproof coating layer is arranged across the construction joint 103 in the longitudinal direction of the ditch 104, i.e., the two sides of the waterproof coating layer in the width direction are closely attached to the inner wall surface of the ditch 104 at the end of the first-cast groove 101 and the inner wall surface of the ditch 104 at the end of the later-cast groove 102, respectively, and the waterproof coating layer realizes the separation of the internal space of the ditch 104 from the construction joint 103, and realizes the primary waterproofing of the construction joint 103 between the first-cast groove 101 and the later-cast groove 102.

[0037] In short, for the primary waterproof structure 2 in the preferred embodiment, it is set corresponding to the construction joint 103 on the water-facing surface 107 , and is used to cover the construction joint 103 on the water-facing surface 107 to achieve primary waterproofing of the construction joint 103 .

[0038] In more detail, for the primary waterproof structure 2 in the preferred embodiment, it is preferably obtained by coating a certain thickness of cement-based penetrating crystalline waterproof coating on the water-facing surfaces 107 on both sides of the construction joint 103 in the longitudinal direction. The cement-based penetrating crystalline waterproof coating is prepared by a dry mixing process of an inorganic base material and a certain proportion of active compounds and functional additives. The dry-mixed cement-based penetrating crystalline waterproof coating is in a blue-gray powder state, which is mixed with water in a certain proportion when used.

[0039] In a preferred embodiment, the inorganic base material forming the cement-based penetrating crystallization waterproof coating includes one or more of silicate cement and quartz sand, and the active compound in the preferred embodiment is preferably various complex compounds; at the same time, the functional additives in the preferred embodiment include one or more of silica fume, adhesives, water reducers, etc.

[0040] More specifically, in actual configuration, the mass ratio of the inorganic substrate, the active compound, and the functional additive in actual preparation is preferably (70-105):(0.1-1):(0.5-2).

[0041] For example, in a specific preferred embodiment, the mass ratio of inorganic substrate, active compound and functional additive in cement-based penetrating crystallization waterproof coating is 80:0.4:1.4. At this time, the mass proportions are further specified as follows: 40-60 parts of cement, 35-45 parts of quartz sand, 0.15-0.45 parts of chelating agent, 0.2-0.6 parts of silica fume, 0.3-0.5 parts of binder and 0.3-0.6 parts of water reducer.

[0042] In more detail, for the aforementioned cement-based penetrating crystallization waterproof coating, the mixing ratio with water in actual use is preferably between 0.25:1 and 0.35:1.

[0043] The use of such waterproof coatings in the above-mentioned mixing ratios can fully ensure that their active ingredients can play a role and achieve excellent penetrating crystallization waterproofing effects. Moreover, such coatings can form insoluble crystals inside the substrate under the action of water, thereby effectively blocking the micro pores and cracks in the concrete and improving the overall waterproof performance and durability of the structure.

[0044] In addition, in actual setting, the width of the waterproof coating layer on both sides in the width direction in the longitudinal direction exceeds the width of the construction joint 103 by preferably not less than 10 mm, that is, the overall width of the waterproof coating layer covering the construction joint 103 is not less than 20 cm. At the same time, the thickness of the waterproof coating layer is preferably between 1 mm and 2 mm.

[0045] By using the corresponding arrangement of the aforementioned primary waterproof structure 2 on the water-facing surface 107 , primary waterproofing of the first-cast groove 101 and the post-cast groove 102 at the construction joint 103 can be effectively achieved.

[0046] In actual setting, in order to further improve the waterproof performance of the tunnel trench 1 , it is preferred that a waterproof coating layer is applied on the inner periphery of each cable trough 105 at a position corresponding to the construction joint 103 , so as to form a primary waterproof structure 2 in the cable trough 105 .

[0047] Furthermore, in the waterproof structure of the preferred embodiment, a secondary waterproof structure 3 is provided between the first pouring groove 101 and the second pouring groove 102, and its arrangement form is as follows: Figure 2 , Figure 3 as shown in .

[0048] In a preferred embodiment, the secondary waterproof structure 3 is obtained by constructing an X-shaped water stop at the construction joint 103 between the first cast groove 101 and the second cast groove 102. The X-shaped water stop is made of rubber material and includes a strip-shaped middle rib 301 and two pairs of wing strips 302 arranged on both sides of the width direction of the middle rib 301. Each wing strip 302 extends within the entire length of the middle rib 301, and its two ends are flush with the two ends of the middle rib 301, and one side of each wing strip 302 is fixedly connected to one side of the middle rib 301 in the width direction.

[0049] In actual configuration, the thickness direction of the middle rib 301 is parallel to the longitudinal direction of the tunnel groove 1. Figure 2 The horizontal direction of the tunnel groove 1 is parallel to the horizontal direction of the tunnel groove 1. Figure 2 At the same time, the X-shaped water stop strip forming the secondary waterproof structure 3 is fixed in the concrete of the first pouring groove 101 and the post pouring groove 102 at the same time.

[0050] like Figure 2 As shown in FIG. 1 , a pair of wing strips 302 on one side of the middle rib 301 in the thickness direction are pre-buried in the first cast groove 101, that is, Figure 3 302 (c), 302 (d); at the same time, another pair of wing strips 302 on the other side in the thickness direction can be buried in the concrete end of the post-cast groove 102 during the construction of the post-cast groove, that is, Figure 3 At this time, the middle rib 301 is located at the construction joint 103 of the new and old concrete structures.

[0051] like Figure 3 As shown in , in actual configuration, each wing band 302 is a strip-shaped structure extending continuously along the length direction of the middle rib 301, and its length is preferably equal to the length of the middle rib 301. At the same time, in each pair of wing bands 302 located on both sides of the middle rib 301 in the width direction, the angle α between the two wing bands 302 is preferably 90° to 150°, and more preferably 120°. Accordingly, the angle β between each wing band 302 and the end surfaces on both sides of the middle rib 301 in the thickness direction is preferably 105° to 135°, and more preferably 120°.

[0052] After the construction and setting of the post-cast groove 102 is completed, for each pair of wing strips 302 on both sides of the width direction of the middle rib 301, one of the wing strips 302 is buried in the first cast groove 101, and the other wing strip 302 is buried in the post-cast groove 102. By setting the two pairs of wing strips 302 that are angled to each other and are respectively buried in the new and old concrete, two water retaining barriers are formed in the construction joint 103 between the water-facing surface 107 and the water-retaining surface 108 (only the two pairs of wing strips 302 on both sides of the width direction of the secondary waterproof structure 3, excluding the primary waterproof structure 2), so as to achieve an effective waterproof effect.

[0053] Furthermore, in order to enhance the waterproof effect of the secondary waterproof structure 3, a convex strip 303 is protrudingly provided on at least one side end face of each wing band 302, thereby extending the path length of the leaking water in the construction joint 103 from the water-facing surface 107 to the water-retaining surface 108, thereby further enhancing the waterproof effect.

[0054] In actual configuration, the convex strip 303 is continuously extended in the length direction of the wing strip 302 and extends from one end to the other end of the wing strip 302. In a preferred embodiment, the convex strip 303 can be preferably arranged parallel to the length direction of the wing strip 302; of course, according to the actual configuration requirements, the convex strip 303 can also be arranged to bend and extend in the length direction of the wing strip 302 to form a wavy convex structure.

[0055] In addition, when specifically arranged, the convex strip 303 is preferably arranged on one side end surface of each wing strip 302. Figure 3 In the preferred embodiment shown, two convex strips 303 are spaced apart on the end surface of each wing strip 302 facing away from the central rib 301 , and the cross-sectional shape of each convex strip 303 is further preferably a rectangle.

[0056] It is understandable that, according to actual use needs, a plurality of convex strips 303 may be respectively provided on one end surface of each wing strip 302 close to the middle rib 301 to further extend the water seepage path and enhance the waterproof effect.

[0057] More preferably, in actual setting, a water filter belt 304 is preferably provided between the two wing belts 302 close to the water facing surface 107 along the length direction, and its length direction is parallel to the length direction of the water stop belt, and the two sides of the water filter belt 304 in the width direction are respectively connected to the end faces of the two wing belts 302 away from the middle rib 301, and a certain distance is formed between the water filter belt 304 and one side of the width direction of the middle rib 301. In this way, after completing the corresponding setting of the secondary waterproof structure 3, a gap of a certain width is formed between the water stop belt and the concrete material on one side of the construction joint 103, so that water leaked through the construction joint 103 can enter the above-mentioned gap after being filtered through the water filter belt 304.

[0058] In actual settings, it is preferred to insert a water-absorbing strip in the above-mentioned gap, at least one end of which extends from the end of the X-shaped waterstop belt, which can continuously absorb the water in the gap and evaporate it according to the siphon effect, ensuring that there is no visible water in the gap on one side of the filter belt 304, thereby ensuring the waterproof effect of the secondary waterproof structure 3.

[0059] Furthermore, in actual setting, the X-shaped water stop (i.e., the secondary waterproof structure 3) is set in the middle area of ​​the thickness of the tunnel trench 1 structure, for example Figure 1 The U-shaped structure shown. At this time, the X-shaped water stop strip arranged in a U-shape bypasses the concrete structure below the ditch 104 and extends to the bottom of the two cable troughs 105 at both ends.

[0060] At the same time, based on the above-mentioned arrangement, it is further preferred that the thickness of the concrete structures arranged on the inner and outer sides of the X-shaped water stop is the same, that is, the secondary waterproof structure 3 is arranged in the middle of the concrete structure of the tunnel trench 1. Such an arrangement can effectively ensure the structural strength of the inner and outer concrete structures after the secondary waterproof structure 3 is arranged, avoid the concrete cutting effect caused by the smaller structural thickness of the concrete on one side, and improve the stability and reliability of the overall structure.

[0061] Furthermore, in actual setting, the X-shaped water stop is preferably transitioned in an arc manner at the turning position to ensure the reliability of the setting of the secondary waterproof structure 3. In specific operation, it is preferred to heat the turning position of the X-shaped water stop with a hot air blower to complete the processing of the arc transition area.

[0062] As for the waterproof structure in the preferred embodiment, it is set at the construction joint 103 of the first-cast groove 101 and the second-cast groove 102, and includes a primary waterproof structure 2 painted on the water-facing surface 107 and covering the construction joint 103 on the water-facing surface 107, and a secondary waterproof structure 3 set on both sides of the concrete of the first-cast groove 101 and the second-cast groove 102. Among them, the X-shaped water stop used to form the secondary waterproof structure 3 is set in the concrete on both sides of the ditch 104 and below the bottom, one end of which extends to the bottom of one cable trough 105, and the other end of which bypasses the bottom of the ditch 104 and extends to the bottom of another cable trough 105.

[0063] For the above-mentioned waterproof structure, as another aspect of the preferred embodiment of the present invention, a construction method for the waterproof structure is also provided, which includes the following process: S1. Design an X-shaped waterstop according to the design size of the tunnel trench 1, determine the use length, setting position and turning position of the X-shaped waterstop, and bend the X-shaped waterstop at the turning position for standby use; In a preferred embodiment, the bending process of the X-shaped water stop is preferably completed by a hot air blower, and the X-shaped water stop is hot-bent at the turning position by a hot bending machine and then used for standby; S2, perform pre-construction preparation for the first section of the trench, that is, perform pre-casting preparation for the first pre-cast trench 101, tie the steel mesh and set up the casting template; at the same time, fix the bent X-shaped water stop strip on the pre-cast trench 101 for connecting one end of the post-cast trench 102, so that the width direction of the middle rib 301 is parallel to the lateral direction of the tunnel trench 1, and one side of the X-shaped water stop strip is located in the area to be cast in the pre-cast trench 101; In order to achieve reliable fixation of the X-shaped water stop during real-time setting, it is preferred to set the X-shaped water stop to be pre-buried on one side of the first pouring groove 101 for subsequent connection to the end template 4 of the post-pouring groove 102, such as Figure 4When installing the end formwork 4, it is preferred that a plurality of fixing members 5 are provided on the middle rib 301, and each fixing member 5 can be connected to the molded end surface of the end formwork 4 with its end after passing through the middle rib 301; at the same time, based on the deformation capacity of the X-shaped water stop, the two wing bands 302 provided in the post-casting groove 102 are bent and attached to the inner end surface of the end formwork 4 respectively. The above process can be achieved by pressing the middle rib 301 tightly against the inner end surface of the end formwork 4, so that the side of the X-shaped water stop that is attached to the end formwork 4 is in a flattened state, as shown in FIG. Figure 4 as shown in .

[0064] Of course, in actual settings, a special end template can also be set to complete the fixation of the X-shaped waterstop strip at the end of the pre-cast groove 101, so that the two wing strips 302 on one side of the thickness direction extend into the area to be poured of the pre-cast groove 101, while the two wing strips 302 on the other side of the thickness direction extend out of the end template and protrude from the end face of the pre-cast groove 101 after the end template is demolded.

[0065] S3, pouring concrete at the construction position of the first-cast groove 101 to complete the casting and forming of the first-cast groove 101; After being formed in this way, the X-shaped water stop is integrally buried in one end of the concrete structure of the first cast groove 101. Figure 4 as shown in .

[0066] After that, the precast groove 101 is demoulded, the end template 4 is removed from the X-shaped water stop, and the two wing strips 302 whose end faces are flush with the end faces of the precast groove 101 are dug out from the end faces of the precast groove 101; under the restoring force of the rubber of the X-shaped water stop or with the help of manual labor, the two flattened wing strips 302 return to their initial state and protrude from the end faces of the precast groove 101; S4: tying the structural steel bars of the post-cast groove 102 and setting the casting template at one longitudinal end of the pre-cast groove 101, so that the two wing strips 302 at the end of the pre-cast groove 101 extend into the casting and forming area of ​​the post-cast groove 102; If the post-cast groove 102 is not the last section of the tunnel groove 1, the X-shaped waterstop strip at the end of the post-cast groove 102 is fixed according to the method in step S2 on the end formwork 4 at the end of the post-cast groove 102 away from the first cast groove 101; if the post-cast groove 102 is the last section of the tunnel groove 1, only the end formwork 4 is set at the end of the post-cast groove 102 away from the first cast groove 101.

[0067] Of course, in actual settings, even the last post-cast groove 102 can be provided with an X-shaped waterstop at its end away from the first-cast groove 101. At this time, in each pair of wing bands 302 in the X-shaped waterstop, one wing band 302 is fixedly embedded in the end of the post-cast groove 102, and the other wing band 302 is embedded in other structures connected to the end of the tunnel groove 1.

[0068] In addition, during the actual concrete pouring construction, it is preferred to avoid directly pouring concrete onto the wing bands 302 of the X-shaped water stop to prevent a significant change in the angle between the brackets of the two wing bands 302 due to the impact during concrete pouring.

[0069] S5: After completing the construction of all sections of the tunnel trench 1 and removing the formwork, apply several layers of cement-based penetrating crystalline waterproof coating on the water-facing surface 107 of the construction joint 103 between two adjacent sections of the trench unit (i.e., the inner peripheral wall surface of the ditch 104 corresponding to the construction joint 103), and form a waterproof coating layer of a certain thickness and a certain width on one side of the water-facing surface 107 of each construction joint 103, forming a primary waterproof structure 2 between the water-facing surface 107 and the water-repellent surface 108 at the construction joint 103.

[0070] At the same time, by using the setting of X-shaped waterstop strips between each group of pre-cast grooves 101 and post-cast grooves 102, a secondary waterproof structure 3 is formed between the water-facing surface 107 and the water-retaining surface 108 at the construction joint 103.

[0071] Preferably, when the waterproof coating layer is actually applied, the interval between two adjacent layers is preferably 2 to 3 hours. Before the first application, the concrete surface of the structural construction joint 103 on the water-facing side 107 is preferably cleaned of impurities and roughened to improve the quality of the waterproof coating layer.

[0072] More preferably, the coating width of each layer of waterproof coating (the dimension of the waterproof coating layer in the longitudinal direction of the tunnel trench 1) is preferably not less than 20 cm.

[0073] The waterproof structure suitable for tunnel trench construction joints of the present invention has a simple structure and is convenient to construct. It can realize the setting of waterproof structures at the construction joints of two adjacent trenches while meeting the requirements of segmented construction of the tunnel trench, thereby ensuring the stability and reliability of waterproofing at the construction joints of the trenches at both ends, and fully preventing water on the water-facing side from leaking through the construction joints to the water-receiving side, thereby ensuring the reliability of operation after tunnel trench construction and reducing the operation and maintenance costs of the tunnel.

[0074] It will be easily understood by those skilled in the art that the above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions and improvements made within the spirit and principles of the present invention should be included in the protection scope of the present invention.

Claims

1. A waterproof structure suitable for tunnel trench construction joints, used for waterproofing between the front and back surfaces of the construction joints of the first-cast trench and the second-cast trench during segmented tunnel trench construction, characterized in that: include: A primary waterproof structure, which is a waterproof coating layer applied on the water-facing surface of the construction joint; A secondary waterproof structure is provided in the concrete structure between the water-facing surface and the water-retaining surface, and is formed by an X-shaped waterstop extending into the first-cast groove on one side and into the second-cast groove on the other side; and The X-shaped waterstop is arranged along the annular direction to surround the construction joint on the water-facing surface, and includes a strip-shaped middle rib, and a pair of wing bands are respectively arranged on both sides of the width direction of the middle rib; the wing band extends within the full length of the middle rib, and one side of the wing band is fixedly connected to one side of the width direction of the middle rib; the two wing bands in each pair of wing bands are arranged at a certain angle to each other, and one of the wing bands is buried in the end concrete of the pre-cast groove during the construction of the pre-cast groove, and the other wing band is buried in the end concrete of the post-cast groove during the construction of the post-cast groove.

2. The waterproof structure suitable for tunnel trench construction joints according to claim 1, characterized in that: The waterproof coating layer completely covers the construction joints on the water-facing surface and is obtained by brushing with cement-based penetrating crystallization waterproof coating; The cement-based penetrating crystallization waterproof coating is prepared by mixing an inorganic base material, an active compound, and a functional additive in a mass ratio of (70-105):(0.1-1):(0.5-2), and the cement-based penetrating crystallization waterproof coating is mixed with water in a ratio of 0.25:1-0.35:1 when in use.

3. The waterproof structure suitable for tunnel trench construction joints according to claim 2, characterized in that: The width of the waterproof coating layer is not less than 20 cm; and / or the thickness of the waterproof coating layer is between 1 and 2 mm; and / or The angle between the two wing straps in each pair of wing straps is 90°~150°; correspondingly, the angle between the surface of each wing strap and the end surface of the middle rib is 105°~135°.

4. The waterproof structure suitable for tunnel trench construction joint according to any one of claims 1 to 3, characterized in that: A convex strip is protrudingly arranged on at least one end surface of the wing band, and the convex strip is continuously extended in the length direction of the wing band and extends from one end of the wing band to the other end.

5. The waterproof structure suitable for tunnel trench construction joints according to claim 4, characterized in that: The convex strip is arranged on a side end surface of the corresponding wing band away from the middle rib, and the number of the convex strips arranged on the side end surface is multiple.

6. The waterproof structure suitable for tunnel trench construction joint according to any one of claims 1 to 3 and 5, characterized in that: A water filter belt is arranged along the length direction between the two wing belts on the side close to the water-facing surface; The water filter belt extends along the length direction of the wing belt, and its two sides in the width direction are respectively connected to the end faces of the two wing belts away from the middle rib, and a gap is formed between the end face of the water filter belt and one side of the width direction of the middle rib, so that water leaked through the construction joint on the water-facing side can be collected in the gap after passing through the filter water belt; accordingly, a water absorption strip is arranged in the gap, and the end of the water absorption strip extends from the end of the X-shaped waterstop belt, which is used to absorb the water in the gap.

7. The waterproof structure suitable for tunnel trench construction joint according to any one of claims 1 to 3 and 5, characterized in that: The X-shaped waterstop is arranged in the middle part of the tunnel groove concrete, one end of which extends to the bottom of the cable groove on one lateral side of the tunnel groove, and the other end of which goes around the bottom of the water ditch in the middle of the tunnel groove and extends to the bottom of the cable groove on the other lateral side.

8. The waterproof structure suitable for tunnel trench construction joints according to claim 7, characterized in that: A waterproof coating layer is applied on the inner peripheral wall surface of the cable trough at the construction joints corresponding to the first-cast groove and the post-cast groove.

9. A construction method for a waterproof structure suitable for a tunnel trench construction joint as described in any one of claims 1 to 8, characterized in that: The process includes the following: S1. Design the X-shaped waterstop according to the design size of the tunnel trench, determine its use length, setting position and turning position, and bend the X-shaped waterstop at the turning position for standby use; S2: Tie the steel mesh of the first-cast groove and set the casting template, and set the bent X-shaped water stop strip in the first-cast groove for connecting one end of the post-cast groove, so that the two wing strips on one side of the thickness direction of the X-shaped water stop strip are located in the area to be cast in the first-cast groove; S3, pouring the pre-cast groove to complete the shaping of the pre-cast groove, so that the two wing strips on one side of the X-shaped water stop are buried inside the end of the pre-cast groove, and the two wing strips on the other side of the X-shaped water stop protrude from the pre-cast groove to connect to the end surface of the post-cast groove; S4: tying the steel mesh of the post-cast groove at one longitudinal end of the formed pre-cast groove and setting a casting template so that the two wing strips protruding from the end surface of the pre-cast groove extend into the area to be cast of the post-cast groove; If the post-cast groove is not the last section of the tunnel groove, an X-shaped water stop is provided at the end of the post-cast groove away from the pre-cast groove according to the method in step S2; thereafter, the post-cast groove is cast and formed; S5: According to the method in step S4, the construction and forming of all sections of the tunnel groove are completed in sequence, and a waterproof coating layer of a certain width and thickness is applied on the water-facing surface of the construction joint between each first-cast groove and the later-cast groove to form a primary waterproof structure between the water-facing surface and the water-receiving surface at the construction joint; accordingly, the X-shaped waterstop strip arranged between the first-cast groove and the later-cast groove forms a secondary waterproof structure between the water-facing surface and the water-receiving surface at the construction joint.

10. The construction method of the waterproof structure applicable to the tunnel trench construction joint according to claim 9, characterized in that: When setting the X-shaped water stop in step S2, the two wing strips extending into the post-cast groove are flattened to be flush with the end surface of the middle rib, and the X-shaped water stop is tightly fixed to the end formwork of the pre-cast groove by using a plurality of fixing parts; Correspondingly, after the first-cast groove is formed in step S3, the end template is removed, and the two wing strips for embedding the end of the post-cast groove are cut out from the end surface of the first-cast groove so that the two wing strips protrude from the end surface of the first-cast groove.